FR2524145A1 - METHOD AND APPARATUS FOR CONTROLLING THE INJECTION AREA OF A SOIL CEMENTING AGENT DURING A SOIL STABILIZATION PROCESS - Google Patents

METHOD AND APPARATUS FOR CONTROLLING THE INJECTION AREA OF A SOIL CEMENTING AGENT DURING A SOIL STABILIZATION PROCESS Download PDF

Info

Publication number
FR2524145A1
FR2524145A1 FR8304655A FR8304655A FR2524145A1 FR 2524145 A1 FR2524145 A1 FR 2524145A1 FR 8304655 A FR8304655 A FR 8304655A FR 8304655 A FR8304655 A FR 8304655A FR 2524145 A1 FR2524145 A1 FR 2524145A1
Authority
FR
France
Prior art keywords
soil
electrodes
tube
cementing agent
injection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
FR8304655A
Other languages
French (fr)
Inventor
Takeo Suzuki
Akira Nakai
Shigetaka Suzuki
Kiyoshi Inoue
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TEIESU GIJUTSU KK
Original Assignee
TEIESU GIJUTSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from JP4566582A external-priority patent/JPS58164817A/en
Priority claimed from JP12517682A external-priority patent/JPS5918812A/en
Priority claimed from JP23307082A external-priority patent/JPS59122618A/en
Application filed by TEIESU GIJUTSU KK filed Critical TEIESU GIJUTSU KK
Publication of FR2524145A1 publication Critical patent/FR2524145A1/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N27/00Investigating or analysing materials by the use of electric, electrochemical, or magnetic means
    • G01N27/02Investigating or analysing materials by the use of electric, electrochemical, or magnetic means by investigating impedance
    • G01N27/04Investigating or analysing materials by the use of electric, electrochemical, or magnetic means by investigating impedance by investigating resistance
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • E02D3/126Consolidating by placing solidifying or pore-filling substances in the soil and mixing by rotating blades
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N33/00Investigating or analysing materials by specific methods not covered by groups G01N1/00 - G01N31/00
    • G01N33/24Earth materials

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Electrochemistry (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Soil Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

L'INVENTION CONCERNE UN PROCEDE ET UN APPAREIL POUR CONTROLER LA ZONE D'INJECTION D'UN AGENT DE CIMENTATION DANS UN SOL. CE PROCEDE DE CONTROLE D'UNE ZONE 21 D'UN SOL DANS LAQUELLE ON INJECTE UN AGENT DE CIMENTATION CONSISTE A DISPOSER DES ELECTRODES 27, 28, 29; 27, 28, 29 DANS LADITE ZONE, A ENVOYER UN COURANT AUX ELECTRODES A PARTIR D'UNE SOURCE D'ALIMENTATION EN ENERGIE 31 ET A MESURER EN 32 LA VARIATION DE LA RESISTANCE ELECTRIQUE ENTRE LES ELECTRODES, L'AGENT DE CIMENTATION ETANT INTRODUIT PAR DES TIGES CREUSES 24, 24 PORTANT LES ELECTRODES. APPLICATION NOTAMMENT AU CONTROLE DE LA RESISTANCE D'UN SOL LORS DE SA STABILISATION.The invention relates to a method and an apparatus for controlling the area of injection of a cementing agent into a soil. THIS PROCESS FOR MONITORING A ZONE 21 OF A SOIL INTO WHICH A CEMENT AGENT IS INJECTED CONSISTS OF PROVIDING THE ELECTRODES 27, 28, 29; 27, 28, 29 IN THE SAID ZONE, TO SEND A CURRENT TO THE ELECTRODES FROM AN ENERGY SUPPLY SOURCE 31 AND TO MEASURE IN 32 THE VARIATION OF THE ELECTRICAL RESISTANCE BETWEEN THE ELECTRODES, THE CEMENT AGENT BEING INTRODUCED BY HOLLOW RODS 24, 24 CARRYING THE ELECTRODES. APPLICATION IN PARTICULAR TO THE CONTROL OF THE RESISTANCE OF A SOIL DURING ITS STABILIZATION.

Description

La présente invention concerne un procédé et un appareil pour contr 8 lerThe present invention relates to a method and apparatus for controlling

une zone ou région d'un sol,an area or region of a soil,

dans laquelle un agent de cimentation, par exemple un pro-  in which a cementing agent, for example a

duit chimique (désigné ci-après simplement sous le terme de produit chimique) est injecté au cours d'un processus  chemical product (hereinafter simply referred to as a chemical) is injected during a process

de stabilisation du sol.soil stabilization.

Récemment, un certain type de procédé de sta-  Recently, a certain type of statistical procedure

bilisation des sols a connu un grand développement dans le domaine des travaux de génie civil Ce procédé est tel qu'un produit chimique se solidifiant est injecté dans la partie désirée d'un sol en vue de's'y solidifier et de solidifier et de stabiliser de ce fait le sol ou  The process is such that a solidifying chemical is injected into the desired part of a soil in order to solidify and solidify and stabilize the soil. this makes the soil or

de le rendre imperméable à l'eau.to make it waterproof.

Les types de sols requérant une stabilisation incluent les couches de terrain ordinaire, les fissures dans les rochers, des zones rompues et disloquéesou des combinaisons quelconques de ces dernières, et l'action  Soil types requiring stabilization include ordinary soil layers, cracks in rocks, broken and dislocated areas or any combinations of these, and

de la cimentation dépend, dans de nombreux cas, des pro-  cementing depends, in many cases, on

priétés des couches ou des strates du sol.  properties of the layers or strata of the soil.

En d'autres termes, lorsque le produit chimi-  In other words, when the chemical product

que de stabilisation injecté quitte le tube de cimenta-  injected stabilization leaves the cement tube

tion, il pénètre dans les couches ou strates en fonc-  tion, it enters the layers or strata

tion de la pression appliquée et tend à pénétrer en di-  applied pressure and tends to penetrate di-

rection ou à l'intérieur de la zone des strates présen-  or within the area of the strata presented

tant la résistance minimum à la cimentation, par exemple  both the minimum resistance to cementation, for example

au niveau des limites des couches du sol ou de la cou-  at the level of the boundaries of the soil layers or the cou-

che de gravier ou de la couche d'argile tendre possédant  gravel or soft clay

un coefficient élevé de perméabilité.  a high coefficient of permeability.

C'est pourquoi il existe le risque d'appari-  This is why there is the risk of

tion d'un phénomène selon lequel l'ensemble du produit chimique injecté n'est pas nécessairement solidifié à l'intérieur de la zone prévue du sol considéré, même  phenomenon that the entire injected chemical is not necessarily solidified within the intended area of the soil

si la durée de gélification du produit chimique est ré-  if the gelling time of the chemical is

glée.Glee.

Lors de la mise en oeuvre de ce type d'opéra-  When implementing this type of operation,

t.Lon d'amenée du produit chimique, il est nécessaire  t.Lon of bringing the chemical, it is necessary

d'observer l'existence d'une fuite du produit chimi-  to observe the existence of a leak of the chemical product

que de manière à empêcher ce dernier de s'échapper à  in order to prevent the latter from escaping

l'extérieur d'une zone prédéterminée d'amenée du pro-  the outside of a predetermined zone for bringing the

duit chimique autour du trou de cimentation servant à l'injection dudit produit chimique et de pénétrer dans les puits, un bassin ou analogue au voisinage du site des travaux, ce qui entraînerait une pollution de la nappe phréatique ou de l'eau située dans le bassin De façon plus spécifique, cette observation est réalisée au moyen du forage et de la mise en place de puits  a chemical sink around the cementing hole for the injection of the chemical and entering wells, a pond or the like in the vicinity of the work site, which would result in pollution of the water table or water located in the basin More specifically, this observation is carried out by drilling and placing wells

d'observation sur le côté extérieur d'une zone d'ame-  on the outer side of a breathing zone.

née du produit chimique possédant un raycnd'environ m à partir du centre du trou de cimentation servant à l'injection du produit chimique, en effectuant le  from the chemical having a radius of about 1 m from the center of the cementing hole for the injection of the chemical,

contrôle de la qualité de l'eau dans les puits d'obser-  control of water quality in the observation wells

vation à trois moments différents, c'est-à-dire avant, pendant et après l'injection du produit chimique dans le trou de cimentation, en comparant les données du contrôle obtenues et en confirmant la fuite du produit  at three different times, ie before, during and after injection of the chemical into the cementing hole, comparing the control data obtained and confirming the leakage of the product

chimique vers l'extérieur de la zone prédéterminée d'ame-  outside the predetermined area of ame-

née ou d'injection dudit produit chimique.  or injection of the said chemical product.

Cependant, lors de la mise en oeuvre d'une telle méthode d'observation, s'il apparaft un cas o la valeur du p H de l'eau dans le puits d'observation  However, when implementing such an observation method, if there is a case where the value of the p H of the water in the observation well

dépasse une valeur de référence prédéterminée, par sui-  exceeds a predetermined reference value, by following

te de l'échappement effectif du produit chimique vers l'extérieur de la zone d'amenée du produit chimique, sur la base du test effectué au moment de l'injection,  the effective escape of the chemical to the outside of the chemical feed zone, based on the test performed at the time of injection,

qui fait partie des trois étapes du test de contrô-  which is one of the three steps of the test of

le de la qualité de l'eau, il est nécessaire d'arrêter immédiatement l'opération d'amenée du produit chimique au niveau de l'emplacement o le trou de cimentation  the quality of the water, it is necessary to immediately stop the operation of bringing the chemical at the location where the cementing hole

servant à l'injection du produit chimique est situé.  used for the injection of the chemical is located.

En réalité le contrôle de la qualité de l'eau dans le  In reality the control of the quality of water in the

puits d'observation pendant l'injection du produit chimi-  observation well during injection of the chemical product

que requiert un intervalle de temps considérable jusqu'à ce que le produit chimique s'étant échappé à l'extérieur de la zone d'amenée soit infiltré dans l'eau situé à l'intérieur du puits d'observation, en raison de la dis-  a significant time interval until the chemical escaping outside the delivery zone is infiltrated into the water inside the observation well, due to the dis-

tance d'environ 10 m existant entre le trou de cimenta-  about 10 m between the cement hole

tion et le puits d'observation Il en résulte que,étant  tion and the observation well. As a result, since

donné que l'opération d'amenée du produit chimique pro-  given that the operation of bringing the chemical product

gresse de façon considérable avant que l'on découvre que la valeur du p H de l'eau au niveau de l'emplacement du puits d'observation dépasse la valeur de référence, l'opération d'amenée doit être arrêtée à ce moment là et il faut à nouveau percer un trou de cimentation en un emplacement différent, et l'opération doit être à nouveau déclenchée à partir de la phase initiale, ce qui entraine une perte considérable du point de vue  gresse considerably before it is discovered that the value of the p H of the water at the location of the observation well exceeds the reference value, the supply operation must be stopped at that moment and it is necessary to drill a cementing hole again at a different location, and the operation must be re-triggered from the initial phase, resulting in a considerable loss of the point of view.

temps, appareillage et main d'oeuvre.  time, equipment and manpower.

En vue de résoudre ces inconvénients, il a été récemment proposé des procédés selon lesquels, à  In order to overcome these disadvantages, methods have recently been proposed whereby

titre d'exemple, on introduit en premier lieu un pro-  As an example, we first introduce a

duit chimique à solidification instantanée afin de ga-  instant chemical solidification in order to guarantee

rantir l'obtention d'une zone stabilisée du sol, puis  to obtain a stabilized area of the soil, then

on met en oeuvre l'opération usuelle d'amenée du pro-  the usual operation of bringing the

duit chimique, et en général, il est difficile d'ob-  chemical product, and in general it is difficult to

tenir, au moyen d'une telle méthode, une confirmation  to hold, by means of such a method, a confirmation

quantitative de la zone cimentée.quantitative of the cemented zone.

Pour déterminer la zone solidifiée, il a été  To determine the solidified zone, it was

proposé différentes méthodes incluant dans letrprinci-  proposed different methods including in the main

pe la création d'une excavation dans le sol ainsi que  eg the creation of an excavation in the ground as well as

la mise en oeuvre de mesures du coefficient de perméa-  the implementation of permeation coefficient measurements.

bilité,d'un test de pénétration,de la mesure au moyen d'un radio-isotope, de la mesure de la résistance spécifique du sol, de la méthode sismique, etc. Bien que la réalisation d'une excavation dans le sol, l'utilisation d'un radio-isotope ou la méthode sismique aient été des procédés utilisés dans le cas de  a penetration test, measurement using a radioisotope, measuring the specific resistance of the ground, the seismic method, etc. Although performing an excavation in the ground, the use of a radioisotope or the seismic method were methods used in the case of

travaux de stabilisation du sol à grande échelle, l'em-  large-scale soil stabilization work, the use of

ploi de ces méthodes n'est pas universel En outre étant  The use of these methods is not universal.

donné que les résultats des mesures n'ont pas été justi-  given that the results of the measurements were not justified

fiés d'une manière satisfaisante, le procédé de mesure utilisant la résistance spécifique du sol, n'a pas été employé fréquemment et a plutôt été utilisé pour la  In a satisfactory manner, the measurement method using the specific soil resistance has not been used frequently and has instead been used for

prospection de veines d'eau dans le sol et analogue.  prospecting for water veins in the soil and the like.

Dans ces conditions, bien que le procédé de détermi-  In these circumstances, although the process of determining

nation de l'effet d'écran ou de blocage basé sur la  nation the screen effect or blocking based on the

mesure du coefficient de perméabilité ait été extrê-  the coefficient of permeability has been extremely

mement utilisé, ce procédé n'a pas été toujours uni-  used, this process has not always been uniform

versel et n'a pas été développé à un état le rendant  versel and was not developed to a state making it

approprié pour son utilisation.suitable for its use.

Compte-tenu de ces conditions, il était en-  In view of these conditions, he was

core d'une pratique usuelle, dans le cadre des procé-  common practice, in the context of

dés de l'art antérieur de stabilisation des sols uti-  of the prior art of soil stabilization used

lisation d'injection de produits chimiques, d'effec-  injection of chemicals,

tuer le travail lors de l'injection d'une quantité  kill the job when injecting a quantity

prédéterminée d'un produit chimique sans ou sans pos-  of a chemical without or without

sibilité de confirmer l'état réel atteint une fois  sibility to confirm the actual condition reached once

achevé le travail de stabilisation.  completed the stabilization work.

La présente invention a pour but de résou-  The present invention aims to solve

dre les inconvénients précédents de l'art antérieur et est baséesur la découverte du fait que, en tant que résultat de diverses recherches effectuées sur les mesures de la résistance électrique, qui n'ont pas  the above drawbacks of the prior art and is based on the discovery that, as a result of various researches on electrical resistance measurements, which have not

été beaucoup utiliséoe en considération des circonstan-  been used extensively in view of the circumstances

ces mentionnées précédemment, on a trouvé que les va-  previously mentioned, it has been found that

leurs mesurées présentent un comportement quantitatif et accusé en rapport avec la résistance électrique,  their measurements show a quantitative behavior and accused in relation to the electrical resistance,

dans le cas de la présence d'un gel dans le sol.  in the case of the presence of a gel in the soil.

C'est pourquoi le but principal de la pré-  This is why the main purpose of the pre-

sente invention est de fournir un procédé de contrô-  It is an object of the present invention to provide a method of controlling

le de la zone d'injection d'un agent de cimentation dans le sol servant à contrôler une zone d'injection d'un produit chimique de cimentation au cours d'un processus de stabilisation d'un sol, et qui consiste à disposer des électrodes dans une zone devant être contrôlée, à enregistrer un courant produit par une  the injection zone of a cementing agent into the soil for controlling an injection zone of a cementing chemical during a soil stabilization process, which consists of disposing of electrodes in an area to be monitored, to record a current produced by a

source d'énergie et à mesurer la variation d'une ré-  source of energy and to measure the variation of a

sistance électrique entre les électrodes, et de four-  electrical resistance between the electrodes, and

nir un procédé de contrôle du travail effectué et un appareil de mesure mettant en oeuvre ledit procédé de  a process for controlling the work performed and a measuring apparatus implementing said method of

contrôle.control.

D'autres caractéristiques et avantages de  Other features and benefits of

la présente invention ressortiront de la description  the present invention will emerge from the description

donnée ci-après, prise en référence aux dessins anne-  given below, taken with reference to the

xés, sur lesquels: la figure 1 est une vue en coupe d'un support  in which: FIG. 1 is a sectional view of a support

ou pivot à trois tubes de cinentation servant à l'injec-  or pivot to three tubes of cinentation for the injection

tion d'un produit chimique;a chemical product;

la figure 2 est un diagramme schématique ser-  FIG. 2 is a schematic diagram

vant à expliciter l'état dans lequel un produit chimi-  to clarify the state in which a chemical product

que est injecté dans un trou percé au moyen de forets; la figure 3 montre l'état dans lequel un gel  that is injected into a hole drilled by means of drills; Figure 3 shows the state in which a gel

d'essai est enterré dansdu sable, la figure 3 (a) mon-  test is buried in sand, Figure 3 (a) shows

trant une vue en plan et la figure 3 (b) une vue en cou-  with a plan view and Figure 3 (b) a cross-section view.

pe transversale axiale; les figures 4 à 6 représentent des graphiques  axial transverse pe; Figures 4 to 6 show graphs

montrant des courbes de variation de la résistance élec-  showing curves of variation of electrical resistance

trique entre électrodes en fonction de leur distance dans le sol;  between electrodes as a function of their distance in the ground;

la figure 7 est un diagramme schématique mon-  FIG. 7 is a schematic diagram of

trant les positions d'un tube de la cimentation servant à  the positions of a cementation tube used to

l'injection d'un produit chimique et de tubes d'obersa-  the injection of a chemical product and obersa-

tion:tion:

la figure 8 est un diagramme schématique mon-  FIG. 8 is a schematic diagram of

trant la manière dont un produit chimique est injecté selon un procédé d'injection à haute pression;  the way in which a chemical is injected according to a high-pressure injection process;

la figure 9 est un diagramme schématique mon-  FIG. 9 is a schematic diagram of

trant l'état dans lequel un produit chimique est injec-  the state in which a chemical is injected

té au moyen d'un tube de perçage de la cirwntation ser-  by means of a drilling tube of the cir-

vant à l'injection d'un produit chimique; et la figure 10 est un graphique illustrant 1 '  before injecting a chemical product; and FIG. 10 is a graph illustrating the

opération de cimentation effectuée.  cementing operation performed.

Conformément à la présente invention, le ter-  In accordance with the present invention, the

me "produit chimique" désigne l'un quelconque des pro-  my "chemical" means any of the

duits chimiques qui sont habituellement utilisés dans la stabilisation des sols, incluant par exemple des produits chimiques organiques,tels que la lignine et des produits chimiques à base d'urée, d'acide acrylique et d'acrylamide ainsi que le verre soluble, le lait de ciment, etc. Le terme "zone devant être mesurée" designe une zone recouvrant de façon idéale une région ou un  chemicals that are commonly used in soil stabilization, including for example organic chemicals, such as lignin and urea, acrylic acid and acrylamide chemicals, and water glass, milk cement, etc. The term "area to be measured" refers to an area ideally covering a region or

espace de rayon uniforme à partir d'un tube de cimen-  uniform radius space from a cement tube

tation introduit à l'intérieur du sol et dans laquelle le produit chimique injecté dans le tube est tenu de pénétrer, ou bien une zone incluant des coefficients de  introduced into the soil and into which the chemical injected into the pipe is required to penetrate, or an area

perméabilité non uniformes dans le sol, si de tels coef-  non-uniform permeability in the soil, if such

ficients ont déjà été déterminés par des perçages d'es-  ficients have already been determined by drill holes

sai Le terme "électrode" désigne-une électrode qui produit et reçoit un courant de mesure et qui, si elle est placée dans un tube de cimentation servant à  The term "electrode" refers to an electrode which produces and receives a measurement current and which, if placed in a cementation tube for

l'injection d'un produit chimique, devrait être de pré-  the injection of a chemical product, should be

férence séparéadu tube de cimentation par un isolant, tel qu'une matière plastique, et être protégée par un boltier possédant une résistance fiable En ce qui concerne la disposition des électrodes dans le tube  separating the cementing tube with an insulator, such as a plastic, and being protected by a boltier having a reliable resistance With regard to the arrangement of the electrodes in the tube

de cimentation servant à l'injection du produit chi-  cementing agent for the injection of the chi-

mique, si l'on utilise une seule électrode, cette der-  If a single electrode is used, this last

nière est enterrée au voisinage de l'extrémité du tube de cimentation, par exemple au niveau d'une partie du  is buried near the end of the cementation tube, for example at a part of the

foret Si l'on installe plusieurs électrodes, on les lo-  When installing multiple electrodes, they are

ge dans la paroi du tube de cimentation à des intervalles  in the wall of the cementation tube at intervals

appropriés et on les utilise telles quelles.  appropriate and used as is.

Lorsque de telles électrodes sont disposées sur un tube d'observation, il serait préférable de pré- voir un nombre aussi important que possible d'électrodes de manière à réaliser une observation multiple avec un  When such electrodes are arranged on an observation tube, it would be preferable to provide as many electrodes as possible so as to make a multiple observation with a

degré élevé de précision.high degree of accuracy.

Chacune des électrodes disposées sur le tube  Each of the electrodes arranged on the tube

de cimentation servant à l'introduction du-produit chi-  cementing agent for the introduction of the

mique et sur les tubes d'observation est reliée aux fils  and on the observation tubes is connected to the wires

conducteurs situés à l'intérieur du tube et est raccor-  conductors inside the tube and is connected to

dée alors à un émetteur et à un récepteur placéssur le sol. Un exemple spécifique d'un appareil servant à mettre en oeuvre le procédé de contrôle d'une région d'injection d'un produit chimique servant à réaliser une cimentation, comporte un support ou pivot possédant un  then to a transmitter and receiver placed on the ground. A specific example of an apparatus for carrying out the method of controlling a region of injection of a chemical used for cementing comprises a support or pivot having a

circuit électrique fermé entre au moins une porte dis-  closed electrical circuit between at least one door

posée sur la tête du pivot et un connecteur à câble  placed on the head of the pivot and a cable connector

disposé dans la partie centrale de l'extrémité infé-  disposed in the central part of the lower end

rieure du pivot, par l'intermédiaire d'un balai coulis-  the pivot, through a sliding brush

sant, et un câble, une tige du tube de cimentation in-  and a cable, a rod of the cementing tube

cluant un conduit pour câble possédant un connecteur pour câble à chaque extrémité et disposé au centre d'un tube à plusieurs éléments tubulaires concentriques, et une tige du tube de cimentation équipée d'une électrode et contenant un conduit pour câble muni d'un connecteur pour câble à chaque extrémité et disposé au centre d'un tube à élémentstubulaires multiples concentriques, et une électrode disposée sur la paroi extérieuredu tube et raccordée à un fil conducteur s'étendant à partir  a cable conduit having a cable connector at each end and disposed at the center of a tube having a plurality of concentric tubular elements, and a cementation tube rod equipped with an electrode and containing a conduit for a cable having a connector for a cable at each end and disposed at the center of a tube with concentric multiple tubular elements, and an electrode disposed on the outer wall of the tube and connected to a conductive wire extending from

du conduit pour câble, le pivot et les tiges étant con-  cable duct, with the pivot and the rods being

nectés entre eux de façon appropriée.  nected between them appropriately.

On va maintenantdécrire de façon plus détail-  We will now write in more detail

lée, en référence aux dessins annexés, la construction  With reference to the accompanying drawings, the construction

de l'appareil à tube de cimentation servant à l'injec-  of the apparatus with a cementation tube for injecting

tion d'un produit chimique.of a chemical product.

A titre d'exemple, la figure 1 représente un pivot ou support à trois tubes, qui comporte plusieurs bornes 1 disposées sur la tête du pivot et qui sont chacune isolée par rapport à l'environnement au moyen  By way of example, FIG. 1 represents a pivot or support with three tubes, which comprises several terminals 1 arranged on the head of the pivot and which are each isolated from the environment by means of

d'un isolant 18 Chaque borne l est raccordée par l'in-  an insulator 18 Each terminal l is connected by the in-

termédiaire d'un balai coulissant 4 à une borne rotati-  of a sliding broom 4 to a rotating terminal

ve 3 montée sur le cÈtéextérieur d'une broche d'élec-  ve 3 mounted on the outer side of an electric spindle

trode 2, qui est maintenue de façon étanche à l'inté-  trode 2, which is sealed to the

rieur de la partie du tube du pivot de manière à tourner autour de son axe et, de même, des fils conducteurs sont également ressortis hors de l'intérieur des bornes  of the tube portion of the pivot so as to rotate about its axis and, likewise, conductors son are also out of the interior of the terminals

rotatives 3 et sont raccordés à une borne de raccorde-  3 and are connected to a connection terminal

ment appropriée, par exemple un connecteur pour câble  appropriate, for example a cable connector

6 monté sur l'extrémité inférieure du pivot, par l'in-  6 mounted on the lower end of the pivot, by the

termédiaire d'un conduit pour câble 5 disposé au cen-  a cable duct 5 disposed at the center of

tre du corps du pivot.be the body of the pivot.

Il est prévu un élément tubulaire médian 7 servant à former finalement un premier passage 9 pour le fluide entre lui-même et une gaine tubulaire 8 du pivot, et sa partie supérieure forme un passage fermé  There is provided a medial tubular element 7 serving to finally form a first passage 9 for the fluid between itself and a tubular sheath 8 of the pivot, and its upper part forms a closed passage

au-dessus d'une admission 10 pour un fluide.  above an inlet 10 for a fluid.

Un élément tubulaire intérieur coaxial il  A coaxial inner tubular element

est disposé à l'intérieur de l'élément tubulaire mé-  is disposed within the tubular element

dian 7 de manière à former un second passage 12 pour le fluide entre luimême et l'élément tubulaire médian  dian 7 so as to form a second passage 12 for the fluid between itself and the median tubular element

7, et sa partie supérieure forme un passage fermé au-  7, and its upper part forms a closed passage

dessus d'une seconde admission 13 pour un fluide.  above a second inlet 13 for a fluid.

L'élément tubulaire médian 7 et l'élément tu-  The medial tubular element 7 and the tuft element

bulaire intérieur 11 sont portés avec possibilité de  Inner bungee 11 are worn with possibility of

rotation, d'une manière étanche, par des joints tori-  rotation, in a sealed manner, by tori joints

ques 14, des paliers à billes 15, des coupelles en U  14, ball bearings 15, U-shaped cups

16 et un joint d'étanchéité à l'huile 17.  16 and an oil seal 17.

L'extrémité de la gaine tubulaire 9 du pivot,  The end of the tubular sheath 9 of the pivot,

de l'élément tubulaire médian 7 et de l'élément tubu-  of the medial tubular element 7 and the tubular element

laire intérieur 11 est réalisée respectivement sous la  interior 11 is carried out respectively under the

forme d'un bouchon ou d'une douille pour le raccorde-  plug or socket for the connection

ment à une tige de tube de cimentation (un tube triple  to a cement tube stem (a triple tube

dans la présente forme de réalisation).  in the present embodiment).

Le partie de raccordement d'extrémité du câ-  The end connection part of the cable

ble, incluant le connecteur pour câble 6, etc, peut présenter une certaine tolérance sur la longueur de  ble, including the cable connector 6, etc., may have some tolerance over the length of

manière à faciliter l'opération d'accouplement du con-  to facilitate the coupling operation of the con-

necteur pour câble pendant l'opération de raccordement  cable connector during the connection operation

de la tige du tube de cimentation.of the stem of the cementation tube.

Naturellement la tige du tube de cimentation comporte un câble muni d'un connecteur pour câble à chaque extrémité et possède une constitution à trois tubes qui fournit un premier et un second passages  Naturally, the stem of the cementation tube has a cable with a cable connector at each end and has a three-tube constitution that provides first and second passages

pour le fluide en correspondance avec le pivot.  for the fluid in correspondence with the pivot.

Si l'on utilise le pivot et la tige du tube de cimentation décrits cidessus, il est possible par  If the pivot and stem of the cementation tube described above is used, it is possible

exemple de raccorder une source extérieure d'alimen-  example of connecting an external power source

tation en énergie aux bornes 1 ménagées sur la tête  energy consumption at terminals 1 arranged on the head

du pivot de sorte que l'application d'une tension ap-  of the pivot so that the application of a voltage

propriée (par exemple environ 6 à 12 V) provoque le  property (for example, about 6 to 12 V) causes the

passage d'un courant dans le sol à partir de l'élec-  passage of a current in the ground from the elec-

trode du tube de cimentation, le long des conduits à câble Il en résulte que, si l'on dispose séparément  trode the cementation tube, along the cable ducts It follows that, if available separately

les électrodes de manière à capter le courant en dif-  the electrodes so as to capture the current in different

férents emplacements, il est possible de déterminer aisément la condition d'amenée du produit chimique  In many places, it is possible to easily determine the supply condition of the chemical.

conformément à la vitesse de diminution de la résis-  according to the rate of decrease of the resistance

tance électrique variant en fonction de l'étendue (ou de l'épaisseur de couche) de la zone d'injection  electrical power varies according to the extent (or the layer thickness) of the injection zone

du produit chimique.chemical.

On va maintenir décrire une autre forme de  We will continue to describe another form of

réalisation de l'appareil, sous la forme d'un appa-  realization of the apparatus, in the form of a

reil de formation de piles de ciment de solidification du sol, représenté sur la figure 2 Des forets 23 et 23 ' du type double sont insérés dans un sol déterminé 21 de manière à permettre l'injection d'un lait de ciment 26 à partir des pointesou des ailettes 25 et 25 ' des tiges 24 et 24 ' des forets, tout en pulvérisant les particu- les du sol, et le lait de ciment 26 et les particules  soil forming cement piles of solidification, shown in Figure 2 Drills 23 and 23 'of the double type are inserted in a determined soil 21 so as to allow the injection of a cement milk 26 from the ends or fins 25 and 25 'of the drill rods 24 and 24' while spraying the soil particles, and the cement milk 26 and the particles

22 du sol sont agitées et mélangées ensemble Les ti-  22 of the soil are agitated and mixed together.

ges 24 et 24 ' des forets sont respectivement équipées  24 and 24 'of the drills are respectively equipped

d'électrodes 27,28,29 et 27 ', 28 ', 29 ', qui sont dis-  electrodes 27, 28, 29 and 27 ', 28', 29 ', which are

posées à des intervalles identiques et sont isolées vis-à-vis des tiges associées elle-mêmes,et un fil conducteur 30 ou 30 ' s'étenrdepuis chaque électrode à l'intérieur de la tige 24 ou 24 ', jusqu'à l'intérieur  placed at identical intervals and are insulated from the associated rods themselves, and a conductive wire 30 or 30 'extends from each electrode inside the rod 24 or 24', up to the inside

du sol Les filsconducteurs 30 et 30 ' partant des élec-  The conductor wires 30 and 30 'from the electrodes

trodes sont raccordés de telle manière qu'une source  trodes are connected in such a way that a source

d'alimentation en énergie 31 et une jauge à résistan-  energy supply 31 and a strain gauge

ce 32 sont disposées entre les électrodes 27 et 27 ', 28 et 28 ' et 29 et 29 ', qui sont installées dans les mêmes positions verticales sur les tiges 24 et 24 ' des  32 are arranged between the electrodes 27 and 27 ', 28 and 28' and 29 and 29 ', which are installed in the same vertical positions on the rods 24 and 24' of the

forets.drills.

Avant de mettre en place un béton fraîche-  Before setting up a fresh concrete

ment mélangé A à proximité des particules du sol dé-  mixed A in the vicinity of the soil particles de-

gagées par les forets 23 et 23 ', et le lait de ciment  provided by drills 23 and 23 ', and cement milk

26 envoyé par l'intermédiaire desdits forets, on pré-  24 sent through these forests, we would like to

pare de façon préliminaire sur le sol un échantillon  Preliminarily pare on the ground a sample

dans les mêmesconditions ou dans des conditions simi-  under the same conditions or under similar conditions

laires à celles du béton fraichement mélangé A, et à  to those of freshly mixed A concrete, and to

l'aide de cet échantillon, on obtient les données né-  using this sample, we obtain the necessary data.

cessairesconcernant les valeurs de la résistance électrique dans le béton fraîchement mélangé  on the values of electrical resistance in freshly mixed concrete

que l'on désire obtenir Ces données d'échan-  that one wishes to obtain This data of exchange

tillonnage sont obtenues par exemple en ajoutant et en mélangeant un mélange de quantités prédéterminées de ciment et d'eau aux particules du sol pulvérisé  for example by adding and mixing a mixture of predetermined amounts of cement and water to the particles of the sprayed soil

22 et en mesurant les valeurs de la résistance élzec-  22 and measuring the values of the electrical resistance

trique dans le béton fraîchement mélangé entre les  in freshly mixed concrete between

électrodes disposées à la même distance W que la dis-  electrodes arranged at the same distance W as the dis-

tance réciproque des tiges 24 et 24 ' des forets.  reciprocation of the rods 24 and 24 'of the drills.

De même, pour obtenir un béton présentant les mêmes conditions ou les conditions similaires à celles de l'échantillon, on détermine préalablement par le calcul les proportions de matièrespremières pour le ciment de stabilisation du sol devant être utilisées lors de la formation réelle d'une pile, c'est-à-dire que l'on calcule la quantité de lait de ciment devant être délivrée en dernier lieu sur la base des quantités ce ciment etd'eau en conformité  Similarly, to obtain a concrete having the same conditions or conditions similar to those of the sample, the proportions of raw materials for the soil stabilization cement to be used during the actual formation of a soil are determined beforehand by calculation. stack, that is to say that we calculate the quantity of cement milk to be delivered last on the basis of the quantities of cement and water in conformity

avec par exemple la quantité de sol pulvérisé calcu-  with, for example, the amount of pulverized soil

lée sur la base du diamètre des forets 23 et 23 'et  on the basis of the diameter of the drills 23 and 23 'and

de la profondeur.depth.

Une fois que l'on placé une quantité dési-  Once a quantity has been placed

rée de ciment de consolidation du sol et qu'on l'a mélangé soigneusement dans le sol 21 représenté sur la figure 2, on envoie un courant aux électrodes 27, 28, 29 et 27 ', 28 ', 29 ' montées sur les tiges 24 et 24 '  In the soil shown in FIG. 2, a stream of soil consolidation cement is mixed with the electrodes 27, 28, 29 and 27 ', 28', 29 'mounted on the stems. 24 and 24 '

des forets et l'on mesure les valeurs de la résistan-  forests, and the values of the resistance

ce électrique du ciment frais consolidant le sol,en-  this electric fresh cement consolidating the soil,

tre les électrodes 27 et 27 ', 28 et 28 ' et 29 et 29 ' dans des positions verticales identiques, au moyen  the electrodes 27 and 27 ', 28 and 28' and 29 and 29 'in identical vertical positions, by means of

des jauges à résistances 32, qui sont disposées au-  resistance gauges 32, which are arranged

dessus desdites électrodes.above said electrodes.

Des expérimentations ont montré que la va-  Experiments have shown that the

leur de la résistance électrique d'un mélange compre-  of the electrical resistance of a mixture

nant 2000 g de sable et 400 g d'eauétait égaleà 770 ?, lorsqu 'on la mesure avec deux électrodes éloignées réciproquement d'une distance de 10 cm, tandis que la valeur mesurée était de 260 '2 lorsque l'on ajoutait g de ciment au même mélange et qu'on effectuait  2000 g of sand and 400 g of water were equal to 770 °, when measured with two electrodes 10 cm apart, while the measured value was 260 '2 when g was added. cement to the same mixture and that was carried out

un mélange pendant une minute, et que la valeur me-  a mixture for one minute, and that the value

surée était de 200 a lorsque ce dernier mélange était soumis à une action de mélange pendant une durée de cinq minutes. Il s'est également avéré que l'adjonction de g de sable, de 400 g d'eau et de 200 g de ciment et leur mélange pendant 1 minute fournissait une valeur de résistance électrique de 150 q entre les électrodes, alors que le mélange de l'ensemble pendant une durée de 5 minutes fournissait une valeur de 130 Q On peut voir que l'adjonction de ciment à un mélange de sable et d'eau réduit la valeur de la résistance électrique entre les électrodes et qu'un mélange plus intime du  when the latter mixture was subjected to a mixing action for a period of five minutes. It was also found that the addition of g of sand, 400 g of water and 200 g of cement and mixing them for 1 minute provided an electrical resistance value of 150 q between the electrodes, while the mixture of the whole for a period of 5 minutes provided a value of 130 Q It can be seen that the addition of cement to a mixture of sand and water reduces the value of the electrical resistance between the electrodes and that a mixture more intimate

* mortier de ciment homogénéise les ingrédients et provo-* cement mortar homogenizes the ingredients and provokes

que une diminution supplémentaire de la valeur de la ré-  that a further decrease in the value of the

sistance électrique.electrical resistance.

Dans la mesure o le concept de la présente invention est bien compris, on peut voir que les forets ne sont pas censés être limités à des forets de type double.  Inasmuch as the concept of the present invention is well understood, it can be seen that the drills are not meant to be limited to dual type drills.

La mise en oeuvre de l'appareil décrit ci-  The implementation of the apparatus described above

dessus conformément à la présente invention présente  according to the present invention

l'avantage non seulement de déterminer de façon effi-  the advantage not only of determining effectively

cace si le travail en cours d'exécution progresse de façon satisfaisante, mais aussi,lo=,d'une confirmation d'un travail effectué incomplètement,de pouvoir injecter un supplément de produit chimique et de vérifier la direction d'échappement du produit chimique, ce :ui empêche par exemple la pollution de l'eau potable,  if the work in progress progresses satisfactorily, but also, lo =, a confirmation of work done incompletely, to be able to inject a chemical supplement and to check the direction of escape of the chemical. for example, it prevents the pollution of drinking water,

d'une rivière ou analogue.of a river or the like.

Les exempes spécifiques suivants décrivent le façon plus détaillée la construction et les effets  The following specific exemptions describe the more detailed construction and effects

obtenus conformément à l'invention.  obtained according to the invention.

Exemple lExample l

Comme représenté sur la figure 3 (a) et 3 (b)  As shown in Figure 3 (a) and 3 (b)

on a placé du sable 42 possédant une teneur en humidi-  sand 42 having a moisture content of

té de 10,5 % dans une boite plastique 41 et un gel pour sable 43, d'un diamètre de 10 cm et d'une longueur  10.5% tee in a plastic box 41 and a sand gel 43, with a diameter of 10 cm and a length

de 1 cm fut enterré dans le sable 42 Les électrodes fu-  1 cm was buried in the sand.

rent disposées à des intervalles identiques suivant la  arranged at identical intervals following the

direction diamétrale du corps du gel 43 et chaque élec-  diametral direction of the body of the gel 43 and each

trode fut raccordée à une jauge à résistance du type à  The trode was connected to a resistance

pont de Kohlrausch (du type BF-62 A fabriqué par la so-  Kohlrausch Bridge (type BF-62 A manufactured by the

ciété dite Shimazu Manufactory) Le comportement résul-  Shimazu Manufactory) The resulting behavior

tant des valeurs de résistance fut mesuré comme repré-  both resistance values were measured as

senté sur la figure 4 Sur cette figure, la courbe A représente le comportement à la résistance obtenoe dans  4 In this figure, the curve A represents the resistance behavior obtained in

le cas o l'électrode était disposée dans la partie cen-  the case where the electrode was arranged in the central part

trale du gel et o l'autre électrode était déplacéesui-  gel and the other electrode was displaced

vant les directions de dilatation du diamètre (comme  the directions of expansion of the diameter (as

représenté par les flèche BA), en mesurant alors les va-  represented by the arrow BA), then measuring the values

leurs de la résistance, tandis que la courbe B repré-  their resistance, whereas curve B represents

sente le cas o l'électrode fut fixéedans une position  the case where the electrode was fixed in a position

B de la figure 3 (a) et o l'autre électrode fut dépla-  B in Figure 3 (a) and where the other electrode was moved

cée suivant la direction de la flèche situnedans la par-  in the direction of the arrow located in the

tie centrale du gel de manière à être écartkedu point B.  of the gel so as to be separated from point B.

Comme cela est visible clairement sur la fi-  As is clearly visible on the

gure 4, le gel possède une valeur de résistance très faible et on obtient un comportement et une variation marqués de la valeur de la résistance électrique au  4, the gel has a very low resistance value and a marked behavior and variation in the value of the electrical resistance at

niveau des limites entre le corps du gel et le sable.  level of the boundaries between the body of the gel and the sand.

Il a été confirmé que ce phénomène se produit de façon similaire même si le sable est remplacé par une argile ou par une terre granitique pulvérisée On a également découvert que la profondeur n'avait pratiquement aucun effet dans aucun des cas, lorsqu'un courant de mesure  It has been confirmed that this phenomenon occurs in a similar way even if the sand is replaced by clay or granitic ground spray. It has also been discovered that the depth has practically no effect in any case, when a current of measured

traverse le corps du gel.crosses the body of the gel.

Exemple 2Example 2

On a réalisé un gel d'essai à base de verre  A glass-based test gel was made

soluble et de sable selon une structure en trois cou-  soluble and sand in a three-layer structure.

ches, sous une forme cylindrique d'un diamètre de 15 cm et d'une longueur d'environ 30 cm, et pour lequel les concentrations du verre soluble dans la partie centrale (jusqu'à la distance correspondant à un rayon d'environ 2,5 cm), dans la partie centrale (jusqu'à la distance correspondant à un rayon d'environ 5 cm) et dans la partie périphérique extérieure étaient respectivement égales à 38,6 %, 23,9 % et 11,2 % Ce gel d'essai fut  in a cylindrical shape with a diameter of 15 cm and a length of about 30 cm, and for which the concentrations of the water glass in the central part (up to the distance corresponding to a radius of about 2 , 5 cm), in the central part (up to the distance corresponding to a radius of about 5 cm) and in the outer peripheral part were respectively equal to 38.6%, 23.9% and 11.2% Ce test gel was

introduit dans du sable possédant une teneur en humidi-  introduced into sand with a moisture content

té de 10,3 %, et les variations de la valeur de la ré-  10.3%, and changes in the value of the

sistance correspondant aux différentes distances suivant  sistance corresponding to the following distances

les directions diamétrales à partir de la partie centra-  the diametrical directions from the central part

le du corps du gel furent mesurées et sont représentées  the body of the gel were measured and are represented

dans le tableau indiqué ci-après Le comportement ré-  in the table below.

sultant est illustré par la courbe en trait plein sur  sultant is illustrated by the solid line curve on

la figure 5.Figure 5.

Il ne s'est produit pratiquement aucune modifi-  There has been virtually no change

cation de la résistance électrique entre les différentes  cation of the electrical resistance between the different

couches du corps en-verre soluble à trois couches.  three-layer soluble-glass body layers.

Exemple 3Example 3

La même procédure que celle utilisée dans le cas de l'exemple 2 fut à nouveau mise en oeuvre, hormis  The same procedure as that used in the case of Example 2 was again implemented, except

que le corps similaire du gel, tel qu'utilisé dans l'exem-  that the similar body of the gel, as used in the example

ple, fut enterré dans un sol granitique pulvérisé possé-  ple, was buried in pulverized granitic soil

dant une teneur en humidité de 17, 3 % et les résultats ob-  with a moisture content of 17.3% and the results obtained

tenus sont représentés dans le tableau indiqué ci-après.  are shown in the table below.

Le comportement résultant de la valeur de la résistance est illustré par la ligne formée de traits interrompus Distance Côté gauche Côté droit l (cm) I x( 102 n) (X 102 È)  The resulting behavior of the resistance value is illustrated by the line of broken lines Distance Left side Right side l (cm) I x (102 n) (X 102 È)

2,5 1 0,13 0,132.5 1 0.13 0.13

3,5 1 0,20 0,213.5 1 0.20 0.21

1 0,23 0,261 0.23 0.26

6 1 0,35 0,366 1 0.35 0.36

7,5 0,45 0,477.5 0.45 0.47

8,5 13,2 1 12,88.5 13.2 1 12.8

,5 19,8 21, 5 19.8 21

30 j 32 sur la figure 5 Distance Côté gauche Côté droit (cm (X 102 s) (x 102 Q)  30 d 32 in Figure 5 Distance Left side Right side (cm (X 102 s) (x 102 Q)

2,5 0,17 0,172.5 0.17 0.17

3,5 0,35 0,293.5 0.35 0.29

, 0,48 0,40.48 0.4

6,0 0,77 0,626.0 0.77 0.62

7,5 1 0,757.5 1 0.75

8,5 16,9 17,28.5 16.9 17.2

, 24 19,8, 19.8

, 31 34, 31 34

On peut voir, d'après ces résultats, qu'en mesu-  From these results it can be seen that in

rant les valeurs de la résistance électrique sur le site  the values of the electrical resistance on the site

de travail, il est possible d'obtenir pratiquement un com-  of work, it is possible to obtain practically

portement tel que représenté sur la figure 6 et de ce fait  bearing as shown in Figure 6 and thereby

de déterminer de façon nette l'étendue du corps du gel.  to clearly determine the extent of the body of the gel.

Sur la figure, on peut voir qu'une courbe A représente un sol qui n'est soumis à aucun traitement, et qu'une courbe B illustre la présence d'un corps d'un  In the figure, it can be seen that a curve A represents a soil which is not subjected to any treatment, and that a curve B illustrates the presence of a body of a

gel en un certain point, au moyen du comportement repé-  at a certain point, by means of the repetitive behavior

ré par la ligne formée de traits interrompus La courbe  d by the line formed of broken lines The curve

C représente lep valeurs de résistance mesurées en par-  C represents the resistance values measured in

tant de la partie centrale du corps du gel, cette cour-  both of the central part of the body of the gel, this

be permettant de confirmer l'étendue limitée.  be used to confirm the limited extent.

Exemple 4Example 4

Comme représenté sur la figure 7, on a inséré des dispositifs de contrôleQ et R en des emplacements  As shown in FIG. 7, control devices Q and R are inserted at locations

qui sont séparés d'une ouverture P de cimentation ser-  which are separated from an opening P of cementation

vant à l'introduction d'un produit chimique, à des distan-  the introduction of a chemical product at a distance of

ces différentes,-et l'on a appliqué une tension entre P et Q et P et R, en mesurant de ce fait les résistances électriques au niveau des bornes de mesure, comme cela  these different, and a voltage was applied between P and Q and P and R, thereby measuring the electrical resistances at the measuring terminals, as this

est représenté dans le tableau donné ci-après On note-  is shown in the table given below.

ra que la distance P-Q était égale à 1 m et que la dis_ tance P-R était égale à 75 cm La profondeur maximale des tiges à partir du niveau du sol était de 4,5 m et  ra that the distance P-Q was equal to 1 m and that the distance P-R was equal to 75 cm The maximum depth of the stems from the ground level was 4.5 m and

les points de mesure 1, 2, 3, 4 et 5, 6, 7, 8 des dis-  measuring points 1, 2, 3, 4 and 5, 6, 7, 8 of the dis-

positifs de contrôle Q et R respectivement étaient si-  positive control Q and R respectively were

tués à des intervalles identiques de 50 cm à partir des points les plus profonds Le sol visé était constitué par le remblais ou le banc s'étendant à partir de la surface du sol jusqu'à une profondeur de 85 cm, une boue argileuse jusqu'à une profondeur de 310 cm et du sable de grosseur moyenne jusqu'à une profondeur de  killed at identical intervals of 50 cm from the deepest points The target soil consisted of the embankment or bench extending from the soil surface to a depth of 85 cm, clay mud up to at a depth of 310 cm and sand of medium size to a depth of

450 cm.450 cm.

Comme cela ressort nettement du tableau in-  As is clear from the table

diqué ci-après, les limites de la zone d'injection du  indicated below, the limits of the injection zone of the

produit chimique peuvent être déterminées d'une maniè-  chemical product can be determined in a way that

re extrêmement nette.is extremely clear.

Quantité Résistance électrique (ohms) injectée _ Secti p-1 p-2 p-3 P-4 P5 P-6 P-7 P-8 1-5 2-6 3-7 4-8 mesuree  Quantity Resistance (ohms) injected _ Secti p-1 p-2 p-3 P-4 P5 P-6 P-7 P-8 1-5 2-6 3-7 4-8 measure

0 225 250 270 250 230 245 260 370 76 124 174 270  0 225 250 270 250 230 245 260 370 76 124 174 270

49 72 90 77 54 76 89 143 86 141 173 200  49 72 90 77 54 76 89 143 86 141 173 200

48 71 97 75 50 74 89 120 86 142 174 158  48 71 97 75 50 74 89 120 86 142 174 158

45 69 98 74 49 68 88 90 84 160 138 116  45 69 98 74 49 68 88 90 84 160 138 116

44 69 103 76 45 70 85 85 83 132 188 156  44 69 103 76 45 70 85 85 83 132 188 156

43 70 103 78 38 8,6 63 83 77 71 164 156  43 70 103 78 38 8.6 63 83 77 71 164 156

240 43 68 112 80 37 7,5 65 72 74 73 172 148  240 43 68 112 80 37 7.5 65 72 74 73 172 148

260 43 68 94 14,6 40 8,2 72 6879 73 151 81  260 43 68 94 14.6 40 8.2 72 6879 73 151 81

280 43 9,7 20,513,8 39 8,3 6770 78 14 73 79  280 43 9.7 20.513.8 39 8.3 6770 78 14 73 79

300 42 9,9 8,9 11,8 37 8,267 6877 13,6 69 76  300 42 9.9 8.9 11.8 37 8.267 6877 13.6 69 76

320 43 8,6 8,3 9,6 37 7,7 60 6145 12,1 6777  320 43 8.6 8.3 9.6 37 7.7 60 6145 12.1 6777

340 9,8 7,5 7; 6 9,738 7,968 70 43 112 69 70  340 9.8 7.5 7; 6 9,738 7,968 70 43,112 69 70

La figure 8 trant une autre formeFigure 8 trant another form

est un diagramme schématique mon-is a schematic diagram

de réalisation de la présente in-of the present invention

vention mise en oeuvre selon le procédé décrit ci-dessus à titre déré au  invention implemented according to the process described above for

d'exemple On aménage un trou dans le sol consi-  example A hole in the soil is

moyen d'un tube de cimentation servant à réaliser ce perçage et possédant un foret et utilisant un jet  means of a cementation tube used to perform this drilling and having a drill and using a jet

d'air ou de l'eau sous haute pression, et l'on arre-  air or water under high pressure, and

te l'opération de perçage lorsque la profondeur dési-  the drilling operation when the desired depth

rée est atteinte Ensuiteun produit chimique est déli-  If a chemical is found to be

vré sous une pression élevée d'environ 5 à 150 106 Pa à partir d'une buse latérale du tube de cimentation et de perçage, et les particules de terre se trouvant dans la direction de déplacement du fluide sous pression  at a high pressure of about 5 to 150 106 Pa from a side nozzle of the grouting and piercing tube, and the soil particles in the direction of displacement of the pressurized fluid.

élevée sontagitées alors que le produit chimique pénè-  are high while the chemical is entering

tre entre les particules et se solidifie On relève ou on abaisse le tube de perçage et de cimentation tout en le faisant tourner ou sans le faire tourner, et une zone stabilisée d'une étendue dépendant de la pression d'injection et/ou du coefficient de perméabilité des particules du sol est formée Dans ce cas, moyennant l'insertion d'électrodes de mesure E dans des positions  between the particles and solidifies The piercing and cementing tube is raised or lowered while rotating or rotating, and a stabilized zone of a range depending on the injection pressure and / or the coefficient In this case, the permeability of the soil particles is formed by inserting measuring electrodes E into

prédéterminées en vue de réaliser la mesure des résis-  predetermined measures to measure the resistance

tances électriques pendant l'exécution du travail, il  during the execution of the work, he

est possible de réaliser un travail parfait.  is possible to do a perfect job.

Exemple 5Example 5

Après la mise en place des tubes de détect-  After the introduction of the detection tubes

tion, on a percé dans la position correcte un trou de  tion, a hole has been drilled in the correct position

cimentation servant à l'injection d'un produit chimique.  cementation for the injection of a chemical.

Dans ce cas, bien qu'il fut d'une pratique usuelle d'uti-  In this case, although it was a standard practice to use

liser un tube de perçage servant à effectuer le cioentation avec injection d'un produit chimique, le tube utilisé  a piercing tube used to carry out the injection with a chemical, the tube used

comportait en outre une borne d'émission de signal élec-  additionally included an electronic signal

trique ou un capteur situé en un emplacement approprié sur son extrémité avant, et l'on a mesuré la valeur de  a sensor located in a suitable location on its front end, and the value of

la résistance R O du sol de façon continue ou intermit-  the soil resistance R O continuously or intermittently

tente, alors que la profondeur du trou percé augmentait, en mémorisant de ce fait les valeurs mesurées dans un ordinateur Une fois achevée l'opération de perçage,on  tent, while the depth of the drilled hole increased, thus memorizing the values measured in a computer. Once the drilling operation is completed, one

a utilisé de façon correcte un produit chimique à soli-  correctly used a solid chemical

dification instantanée ou à solidification lente, en  instantaneous or slow-solidification

fonction de la structure du sol et le tube de cimenta-  function of the soil structure and cement tube

tion avec injection du produit chimique fut soulevé de façon continue ou par intermittence pendant l'injec  chemical injection was lifted continuously or intermittently during the injection.

tion du produit chimique Dans ce cas les signaux élec-  In this case, the electrical signals

triques étaient produits on permanence par les bornes mé- nagées sur l'extrémité du tube de cimentation servant à l'injection du produit chimique, si bien que la valeur R du signal variant de temps en temps fut enregistrée  were permanently produced by the terminals on the end of the cementation tube for the injection of the chemical, so that the R value of the signal varying from time to time was recorded

par les capteurs situés sur les tubes de détection ins-  sensors located on the detection tubes

tallés dans la zone alentour et fut envoyée en permanen-  in the surrounding area and was sent permanently

ce à l'ordinateur.this to the computer.

De façon plus spécifique, comme représenté sur la figure 9, sur laquelle on voit que des tubes de  More specifically, as shown in FIG. 9, on which we see that

détection II et III sont situés dans des positions sy-  Detection II and III are located in

métriques par rapport à un tube de cimentation I, en se trouvant à une distance de 50 cm de ce dernier, le tube de cimentation I fut soulevé par paliers de 50 cm de telle sorte que la quantité dl injection initiale de O O 1160 2 fut envoyée alors que la sortie du tube de cimentation se trouvait dans la position i, les 160 pi 320,suivant furent envoyés alors que ladite sortie se trouvait dans la position ii, tandis que la quantité suivante 320 xv  metrically with respect to a cementing tube I, being at a distance of 50 cm from the latter, the cementing tube I was raised in increments of 50 cm so that the amount of the initial injection of OO 1160 2 was sent while the outlet of the cementation tube was in position i, the following 160 ft 320 were sent while said outlet was in position ii, while the following quantity 320 xv

460 ú fut envoyée dans la position iii, que la quanti-  460 ú was sent to heading iii, that the quantity

té suivante 480 -1 640 9 fut envoyée das la position iv, et ainsi de suite (la position de capteur sur le tube de  following tense 480 -1 640 9 was sent to position iv, and so on (the sensor position on the

cimentation 1 fut naturellement relevée de a à d par pa-  cementation 1 was naturally relieved from a to d by

liers) et l'on a obtenu les variations de la quantité  liers) and the variations in the quantity

d'injecticnde produit chimique et de la résistance élec-  injecting chemicals and electrical resistance

trique. La variation de la valeur de la résistance fut introduitesuccessivement dans l'ordinateur, qui a calculé et affiché les valeurs de la résistance R introduites en permanence sur la base d'une valeur de résistance R 10 correspondant à la formation d'un corps de gel à 100 % dans le sol En représentant les  cudgel. The variation of the value of the resistance was introduced successively into the computer, which calculated and displayed the values of the resistance R introduced permanently on the basis of a resistance value R 10 corresponding to the formation of a gel body at 100% in the soil By representing the

valeurs sur un dispositif d'affichage, un papier d'enre-  values on a display device, a paper

gistrement ou analogue sous la forme d'une vue en coupe  recording or the like in the form of a sectional view

longitudinale des deux côtés du tube de cimentation ser-  lengthwise on both sides of the cementing tube

vant à introduire le produit chimique, il est possible de représenter de façon claire la pénétration du produit chimique, comme représenté sur la figure 10 Ainsi on note un effet pratique remarquable dans le fait que,  In order to introduce the chemical, it is possible to clearly represent the penetration of the chemical, as shown in FIG. 10. Thus, a remarkable practical effect is noted in the fact that

lorsque l'on modifie la position des tubes de détec-  when the position of the detector tubes is changed

tion, il est possible de déterminer ou de confirmer la condition d'injection du produit chimique, couche après couche, et que de ce fait il est possible de  In this way, it is possible to determine or confirm the injection condition of the chemical, layer by layer, and that it is therefore possible to

prendre en charge la responsabilité du résultat du tra-  take responsibility for the result of the work

vail effectué.done.

Sur la figure 10, la surface hachurée repé-  In FIG. 10, the hatched surface

rée en G représente une zone d'injection idéale et la surface entourée par un trait formé de tirets est une  in G represents an ideal injection zone and the surface surrounded by a dashed line is a

représentation graphique de la zone d'injection obte-  graphical representation of the injection zone obtained

nue par suite de la cimentation effective De même la ligne formée d'un trait mixte représente les sections des parties gélifiées dans la même direction et qui ont  as a result of effective cementation Similarly the line formed of a mixed line represents the sections of the gelled parts in the same direction and which have

été obtenues à la suite de l'opération effective d'exca-  obtained as a result of the actual operation of exca-

vation.vation.

Claims (4)

REVENDICATIONS 1 Procédé de contrôle d'une zone d'injec-  1 Method for controlling an injection zone tion d'un agent de cimentation dans le sol, pour assu-  a cementing agent in the soil, to ensure rer le contrôle d'une zone ( 21) d'injection d'un agent de cimentation au cours d'un processus de stabilisation d'un sol,caractérisé en ce qu'il comprend les phases  controlling a zone (21) for injecting a cementing agent during a soil stabilization process, characterized in that it comprises the phases opératoires consistant à disposer au moins deux élec-  which consists of having at least two electri- trodes ( 27,28,29; 27 ',28 ',29 ') dans une zone devant être contrôlée; à envoyer un courant auxdites électrodes à partir d'une source d'alimentation en énergie ( 31); et  trodes (27,28,29; 27 ', 28', 29 ') in an area to be controlled; sending a current to said electrodes from a power supply source (31); and à mesurer ( 32) la variation d'une résistance électri-  to measure (32) the variation of an electrical resistance que entre lesditesélectrodes ( 27,28,29; 27 ',28 ',29 ').  between said electrodes (27,28,29; 27 ', 28', 29 '). 2 Procédé selon la revendication 1, carac-  The process according to claim 1, wherein térisé en ce qu'on forme au moins un trou de contrôle dans le volume extérieur d'une zone prédéterminée ( 21)  characterized by forming at least one control hole in the outer volume of a predetermined zone (21) d'injection d'un agent de cimentation au centre de la-  injection of a cementing agent in the center of the quelle est situé un trou d'injection dudit agent de ci-  which is located an injection hole of said agent of ci- mentation, et qu'au moins une électrode ( 27,28,29; 27 ',28 ', 291) est disposée dans ledit trou d'injection de l'agent de cimentation et ledit trou de contrôle, ce qui a pour effet que l'opération de cimentation dans ladite zone  ment, and that at least one electrode (27,28,29; 27 ', 28', 291) is disposed in said injection hole of the cementing agent and said control hole, which has the effect that the cementing operation in said area ( 21) prédéterminée d'injection est contrôlée conformé-  (21) predetermined injection is controlled according to ment à la variation de la valeur de la résistance élec-  change in the value of the electrical resistance trique entre lesdites électrodes.between said electrodes. 3, Procédé selon l'une quelconque des revendi-  3. Process according to any one of the claims cations 1 ou 2, caractérisé en ce qu'on mesure la varia-  1 or 2, characterized by measuring the variation tion d'une valeur de la résistance électrique entre les  of a value of the electrical resistance between électrodes correspondantes ( 27,27 ',28,28 ',29,29 ') fai-  corresponding electrodes (27,27 ', 28,28', 29,29 ') made sant partie des électrodes ( 27,28,29; 27 ',28 ',29 ') dispo-  part of the electrodes (27,28,29; 27 ', 28', 29 ') sées dans plusieurs trous de contrôle.  in several control holes. 4 Procédé selon la revendication 1, caracté-  4. Process according to claim 1, characterized risé en ce qu'on mesure la valeur de la résistance élec-  rised by measuring the value of the electrical resistance trique d'un corps souterrain électriquement conducteur ( 43) situé entre plusieurs électrodes disposées dans  of an electrically conductive subterranean body (43) located between a plurality of electrodes arranged in un trou de contrôle.a control hole. Procédé de contrôle d'une zone d'injec- tion d'un agent de cimentation de sol, caractérisé en ce qu'il inclut une mesure de la résistance du sol au  A method of controlling an injection zone of a soil cementing agent, characterized in that it includes a measure of soil resistance at moyen de la mise en oeuvre des phases opératoires con-  means of implementing the operating phases sistant à disposer au moins un couple d'électrodes ( 27, 28,29; 27 ',28 ', 29 ') dans des positions des deux côtés d'une zone ( 43) d'injection de l'agent de cimentation  at least having a pair of electrodes (27, 28, 29; 27 ', 28', 29 ') in positions on both sides of an injection zone (43) of the cementing agent lors d'un processus de stabilisation d'un sol, pour me-  during a soil stabilization process, to surer la valeur de la résistance électrique d'un agent non solidifié de cimentation entre lesdites électrodes,  to measure the value of the electrical resistance of an unsolidified cementing agent between said electrodes, et à comparer ladite valeur mesureeà une valeur préala-  and comparing said measured value with a previously blement mesurée de la résistance électrique d'un échan-  properly measured electrical resistance of an tillon réalisé dans les conditions similaires à celles  made in conditions similar to those dudit agent de cimentation, de manière à prévoir d'avan-  said cementing agent, so as to provide advance ce, alors que ledit agent de cimentation est à l'état  this, while said cementing agent is in the state non solidifié, sa résistance après solidification.  not solidified, its resistance after solidification. 6 Appareil à tube de cimentation servant à injecter un produit chimique et destiné à être utilisé dans l'amélioration des sols, caractérisé en ce qu'il comporte: (a) un pivot comportant un circuit électrique fermé entre au moins une borne ( 1) disposée dans une  6 Apparatus with a cementation tube for injecting a chemical product and intended for use in soil improvement, characterized in that it comprises: (a) a pivot comprising a closed electrical circuit between at least one terminal (1) arranged in a tête dudit pivot et un connecteur pour câble ( 3) dispo-  head of said pivot and a cable connector (3) sé dans une partie centrale de l'extrémité inférieure dudit pivot, à travers un balai coulissant ( 4), et un câble; (b) une tige ( 11) du tube de cimentation incluant un conduit pour câble ( 5) comportant un autre connecteur pour câble ( 6) à chacune de ses extrémités  in a central portion of the lower end of said pivot, through a sliding broom (4), and a cable; (b) a rod (11) of the cementation tube including a cable conduit (5) having another cable connector (6) at each end thereof et situé en position centrée dans un tube à élémentsmul-  and located in a centered position in a multi-element tube tiples concentriques; (c) une tige du tube de cimentation équipée d'une électrode ( 30,30 ') comportant un autre conduit pour câble possédant également un autre connecteur pour câble à chacune de ses extrémités et situé en position  concentric tiples; (c) a stem of the cementation tube equipped with an electrode (30, 30 ') having another cable duct also having another cable connector at each of its ends and located in position centrée dans un autre tube à éléments multiples concen-  centered in another multi-element tube triques, et une électrode disposée sur une paroi exté-  and an electrode placed on an outer wall. rieure dudit tube et raccordéeà un fil conducteur s'éten-  said tube and connected to a lead wire extends dant à partir d'un autre connecteur pour câble; ledit pivot, ladite tige du tube de cimenta- tion et ladite tige du tube de cimentation équipé d'une  from another cable connector; said pivot, said rod of the cementation tube and said rod of the cementation tube equipped with a électrode étant de façon appropriée raccordés réciproque-  electrode being suitably connected reciprocally ment.is lying.
FR8304655A 1982-03-24 1983-03-22 METHOD AND APPARATUS FOR CONTROLLING THE INJECTION AREA OF A SOIL CEMENTING AGENT DURING A SOIL STABILIZATION PROCESS Pending FR2524145A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP4566582A JPS58164817A (en) 1982-03-24 1982-03-24 Measurement of grout injection range in ground stabilization work
JP12517682A JPS5918812A (en) 1982-07-20 1982-07-20 Grout injection tube device
JP23307082A JPS59122618A (en) 1982-12-28 1982-12-28 Confirmation of improvement of ground

Publications (1)

Publication Number Publication Date
FR2524145A1 true FR2524145A1 (en) 1983-09-30

Family

ID=27292331

Family Applications (1)

Application Number Title Priority Date Filing Date
FR8304655A Pending FR2524145A1 (en) 1982-03-24 1983-03-22 METHOD AND APPARATUS FOR CONTROLLING THE INJECTION AREA OF A SOIL CEMENTING AGENT DURING A SOIL STABILIZATION PROCESS

Country Status (2)

Country Link
FR (1) FR2524145A1 (en)
GB (1) GB2119100A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2746187A1 (en) * 1996-03-15 1997-09-19 Electricite De France Soil injection monitoring process
LU92313B1 (en) * 2013-11-25 2015-05-26 Arman Innovations Sa Method of consolidating a soil by acquiring a curve revealing the permeability of the soil

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AUPP395798A0 (en) * 1998-06-05 1998-07-02 HarbourDom Pty Limited Detection of potential acid sulphate soils
AU766011B2 (en) * 1998-06-05 2003-10-09 Vozoff And Associates Pty Limited Detection of potential acid sulphate soils
EP1914350B2 (en) 2006-10-13 2019-06-05 Geosec S.r.l. A method for homogenizing and stabilising a soil by way of injections
CN102621190B (en) * 2012-03-23 2014-10-15 山东大学 Soil body sample compressing consolidation and resistivity real-time imaging monitoring device and soil sampler thereof
CN114034839A (en) * 2021-11-03 2022-02-11 广东中煤江南工程勘测设计有限公司 Soil bonding curing agent and soil detection method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB645975A (en) * 1948-07-28 1950-11-15 Square Grip Reinforcement Comp Method of and means for determining the degree of compacting of concrete masses in the fluid state
USB79099I5 (en) * 1970-10-08 1976-01-13
US4120166A (en) * 1977-03-25 1978-10-17 Exxon Production Research Company Cement monitoring method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB335051A (en) * 1929-02-21 1930-09-18 Mines Domaniales De Potasse Process and means for geological examinations for studying and exploring the subsoil
GB690892A (en) * 1951-02-12 1953-04-29 Kenneth Spink Apparatus for measuring ground resistivity
GB1102740A (en) * 1965-08-09 1968-02-07 Stichting Waterbouwkundig Lab Improvements relating to soil measurements

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB645975A (en) * 1948-07-28 1950-11-15 Square Grip Reinforcement Comp Method of and means for determining the degree of compacting of concrete masses in the fluid state
USB79099I5 (en) * 1970-10-08 1976-01-13
US4120166A (en) * 1977-03-25 1978-10-17 Exxon Production Research Company Cement monitoring method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2746187A1 (en) * 1996-03-15 1997-09-19 Electricite De France Soil injection monitoring process
LU92313B1 (en) * 2013-11-25 2015-05-26 Arman Innovations Sa Method of consolidating a soil by acquiring a curve revealing the permeability of the soil
WO2015075234A1 (en) * 2013-11-25 2015-05-28 Arman Innovations S.A. Method for consolidating soil by acquiring a curve that reveals the permeability of the soil

Also Published As

Publication number Publication date
GB8308107D0 (en) 1983-05-05
GB2119100A (en) 1983-11-09

Similar Documents

Publication Publication Date Title
FR2681461A1 (en) METHOD AND ARRANGEMENT FOR THE TRANSMISSION OF INFORMATION, PARAMETERS AND DATA TO AN ELECTRO-MAGNETIC RECEIVING OR CONTROL MEMBER ASSOCIATED WITH A LONG LENGTH SUBTERRANEAN PIPING.
EP0330558B1 (en) Method and device for transmitting information by cable and by mud waves
CA1265122A (en) Assembly enabling oriented drilling
EP0216706B1 (en) Apparatus and process to measure the bubble point of petroleum from an underground formation
EP0995877B1 (en) Apparatus and method for information transmission by electromagnetic waves
FR2524145A1 (en) METHOD AND APPARATUS FOR CONTROLLING THE INJECTION AREA OF A SOIL CEMENTING AGENT DURING A SOIL STABILIZATION PROCESS
WO1991012987A1 (en) Self propelled probe, particularly for penetrating a powdered material
FR2529612A1 (en) DRILLING AND INJECTION DEVICE, SOIL IMPROVEMENT METHOD USING THE SAME, AND SOIL CONDITION SURVEY METHOD USING SAID DEVICE
EP1306517A1 (en) Method and system for drilling when forming concrete piles
EP1108854B1 (en) Diameter monitoring method for columns produced by an injection method
FR2680380A1 (en) METHOD FOR PRODUCING A UNIVERSAL FOUNDATION BODY AND DEVICE FOR IMPLEMENTING SAID METHOD
EP0290338B1 (en) Connecting device for the mechanical and electrical coupling of a multiwire cable to a boring drilling pipe
EP0786673A2 (en) Method and apparatus for probing and inspecting an underground volume
FR2569850A1 (en) CONTAINER FOR RHEOLOGICALLY DEVELOPABLE MATERIAL FOR USE IN A RHEOLOGICAL DEVELOPMENT ANALYSIS CONSISTOMETER
EP0370873A1 (en) Method and apparatus for the analysis of a polyphasic fluid flowing through a conduit
WO2007101931A1 (en) Method for laying and protecting an underground pipe
EP0475986B1 (en) Method and device for in-situ measurement of ground heave characteristics
FR3035222B1 (en) SYSTEM FOR MEASURING INTERSTITIAL PRESSURE IN THE MARINE SEDIMENT
FR2521210A1 (en) INSTRUMENT CAPABLE OF NEGOTIATING ELBOWS IN A SURFACE FOR TRANSPORTING USEFUL LOAD AT THE BOTTOM OF HOLE AND METHODS OF MAKING AND USING THE INSTRUMENT
FR2569765A1 (en) Ground anchor to fasten rock
FR2694333A1 (en) Resistivity exploration and concrete injection control processes
WO2006008361A1 (en) Train of rods for the high-speed transmission of information in a wellbore
FR2839531A1 (en) METHOD AND DEVICE FOR DETERMINING THE NATURE OF A HEAD FORMATION OF A DRILLING TOOL
EP2902547B1 (en) Floor densification method
Derlich Study methods for the drillings around the underground nuclear explosions in the Sahara. Part 1. study of rock samples

Legal Events

Date Code Title Description
ER Errata listed in the french official journal (bopi)

Free format text: 39/83