EP3198118A1 - Rock bolt to be embedded in a fixing material, in a bore hole - Google Patents

Rock bolt to be embedded in a fixing material, in a bore hole

Info

Publication number
EP3198118A1
EP3198118A1 EP15848259.6A EP15848259A EP3198118A1 EP 3198118 A1 EP3198118 A1 EP 3198118A1 EP 15848259 A EP15848259 A EP 15848259A EP 3198118 A1 EP3198118 A1 EP 3198118A1
Authority
EP
European Patent Office
Prior art keywords
energy
rock bolt
absorbing part
tubular part
absorbing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP15848259.6A
Other languages
German (de)
French (fr)
Other versions
EP3198118A4 (en
Inventor
Håkan KREKULA
Leif Eriksson
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northern Mining Products AB
Original Assignee
Northern Mining Products AB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northern Mining Products AB filed Critical Northern Mining Products AB
Publication of EP3198118A1 publication Critical patent/EP3198118A1/en
Publication of EP3198118A4 publication Critical patent/EP3198118A4/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/02Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection having means for indicating tension
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • E21D21/0033Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts having a jacket or outer tube
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • E21D21/004Bolts held in the borehole by friction all along their length, without additional fixing means
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/008Anchoring or tensioning means

Definitions

  • the present invention concerns a rock bolt for the absorption of forces during the reinforcement of rock chambers in mines and during similar work with rock.
  • a second method is to deform or strain the bolt. If the degree of strain is large, the absorption of energy is also large. The larger the degree of strain, the larger the absorption of energy.
  • the disengaged length which is the length between attachment of the bolt inside the borehole and the free end of the bolt, should be as long possible.
  • An embedded dynamic rock bolt normally consists of an extent with a thread with a screw joint, and one or several attachment regions along the bolt.
  • attachment region is here used to denote one or several regions along the extent of the bolt that has been embedded in the borehole.
  • the energy-absorbing regions along the bolt, at which the bolt can be strained, are constituted by stretches between the embedded parts that have a low friction between the grout and the bolt. A bolt with several anchors reduces the energy-absorbing ability of the bolt, since the stretch over which the bolt can be strained is reduced.
  • the purpose of the present invention is to remove the problems described above by offering an embedded dynamic rock bolt of which the energy-absorbing ability is larger since the extent that can be strained being longer than it is in conventional embedded dynamic rock bolts.
  • This purpose is achieved through an embedded dynamic rock bolt with an energy-absorbing part that is located in a protected environment without being able to come into contact with the grout, at the same time as the energy-absorbing part is as long as possible.
  • Figure 1 shows a side view of a rock bolt according to the invention with an anchor with a wedge
  • Figure 1A shows an alternative embodiment of a rock bolt according to the invention
  • Figure 2 shows the rock bolt from Figure 1 in cut-through view
  • Figure 2A shows the rock bolt from Figure 1A in cut-through view
  • Figure 3 shows an end view of a screw joint
  • Figure 4 shows an end view of an anchor
  • Figure 5 shows the bolt from Figure 1, where the anchor has been exchanged for a stirring arrangement
  • Figure 6a shows an external tubular part provided with lugs
  • Figure 6b shows an external tubular part with perforations
  • Figure 6c shows an external tubular part with a pattern
  • Figure 7a shows an energy-absorbing part in the form of a reinforcement member
  • Figure 7b shows an energy-absorbing part in the form of a wire
  • Figure 7c shows an energy-absorbing part in the form of a steel rod
  • Figure 7d shows an energy-absorbing part in the form of a composite material
  • Figure 8 shows rock with a borehole for the introduction of a rock bolt.
  • Figure 1 shows a rock bolt 1 according to the invention intended to be embedded in a borehole 2 in rock.
  • the rock bolt 1 comprises an extended external tubular part 3 and an internal extended energy-absorbing part 4.
  • the external part 3 has been given a length that is somewhat less than the length of the energy-absorbing part 4.
  • the external tubular part 3 has a first end 5 and a second end 6, and a magnitude that allows the energy-absorbing part 4 to be surrounded by the external part 3. It is an advantage if the external part 3 has circular cross-section in the form of a circularly symmetrical metal tube, but it should be realised that also other forms and materials are possible. Square, elliptical or rectangular tubes, of metal, plastic or composite material can, for example, be used. Also other forms of the external tubular part 3 can be used.
  • the jacket 7 of the external tubular part 3 is, as is shown in Figures 6a-6c, arranged with a friction-increasing structure, for example in the form of a pattern 8.
  • the jacket 7 may be arranged with lugs 9, in the same manner as the lugs on a commonly occurring reinforcement member.
  • the jacket 7 also may be arranged with perforations 10, or with various combinations of pattern, lugs and perforations.
  • the purpose of the friction-increasing structure is to give a better attachment surface in the concrete into which the bolt 1 has been embedded. If the jacket 7 is provided with perforations 10, the concrete is given the possibility to grip onto the tubular part 3 without the concrete running into the tubular part and making contact with the energy-absorbing part 4.
  • the internal energy-absorbing part 4 demonstrates a length that exceeds the length of the external tubular part 3.
  • the energy-absorbing part 4 comprises a reinforcement member 4a, but it can in other embodiments comprise a wire 4b, a rod 4c or an extended member of a composite material 4d, as shown in Figures 7a-7d.
  • the slot 13 is placed in the end 11 of the energy-absorbing part 4 in such a manner that the end has a division to a certain extent.
  • a wedge 14 is located in the slot 13.
  • the bolt 1 When the bolt 1 is introduced into the borehole 2 and reaches the bottom of the borehole, the bolt 1 is pressed or beaten against the bottom of the borehole such that the wedge 14 is pressed into the slot 13. When the wedge 14 is pressed into the slot 13, the parts on the two sides of the slot are pressed outwards against the walls of the borehole and attach in this manner the end 11 of the rock bolt in the borehole 2.
  • the second end 15 of the energy-absorbing part 4 is provided with a threaded section 16 that extends a certain distance into the energy-absorbing part 4.
  • the threaded section 16 is intended to be located outside of the borehole when the bolt 1 has been introduced into the hole 2, and has a diameter that is equal to or greater than the external dimension of the outer part, as shown in Figures 1 and 2. The purpose of this is to avoid any weakening of the internal energy-absorbing part caused by the thread.
  • a screw joint 17 in the form of a nut 18, a washer 19 and a force distributor in the form of a half sphere 20 is mounted at the threaded section 16. When the rock bolt 1 is mounted and embedded in the borehole 2, it is prestressed by the screw joint 17.
  • the task of the half sphere 20 is to direct the force from the rock against the washer 19 and the nut 18. It should be realised that, when the internal energy-absorbing part 4 comprises a wire 4b or a composite material 4d, the threaded section 16 and the anchor 12 are attached to the energy-absorbing part 4c or 4d through welding, gluing or in another manner permanent attached.
  • the internal energy-absorbing part 4 is introduced into, placed inside, the external tubular part 3.
  • One end 5 of the external tubular part 3 is attached at the internal energy-absorbing part 4 in association with the anchor 12.
  • the second end 6 of the tubular part 3 is attached in close association with the screw joint 17, in direct association with the end of the threaded section 16.
  • the ends 5, 6 of the external tubular part 3 are attached by means of welding with fully welded joins S.
  • another type of fastening can be used, such as gluing or other permanent fastening. Gluing is particularly appropriate when other material than steel is used for the energy- absorbing part 4 and/or the external tubular part 3.
  • the tubular part 3 is adapted such that its second end 6 comes into contact with the washer 19 and makes contact with it when the rock bolt is prestressed.
  • the preferred rock bolt is mounted in the following manner as shown in Figure 8: a fixing material such as concrete is introduced into the borehole 2 when it has been drilled in the rock. The rock bolt 1 is subsequently introduced into the hole with the anchor 12 entering the borehole first. When the rock bolt 1 reaches the bottom, the bolt is pressed or beaten against the bottom of the borehole such that the anchor becomes attached and the bolt is fixed. When the concrete has hardened, the screw joint 17 is mounted on the part of the threaded part 16 that protrudes from the borehole 2, and is tightened such that the energy-absorbing part 4 is prestressed.
  • the bolt 2 is provided with an anchor in the form of a stirring arrangement 21 formed by a blade or disk having the form of a paddle, instead of the wedge.
  • the resin is introduced into the borehole, after which the bolt is introduced into the borehole and rotated such that the resin is mixed by the stirring arrangement 21.
  • the resin hardens rapidly, which is why the screw joint 17 can be mounted and prestressed in direct association with the insertion of the bolt 1 into the hole 2.
  • rock bolt 1 is given a maximum extent over which the bolt can be bent, since the energy-absorbing part 4 does not come into contact with the embedding material. This gives the advantage that the rock bolt can be bent more extensively and in this way can absorb larger forces than those absorbed by other types of embedded rock bolt.
  • the rock bolt is manufactured in the following manner:
  • an extended energy-absorbing part 4 is arranged, - an extended tubular part 3 is arranged,
  • the energy-absorbing part 4 is adapted inside of the tubular part 3,
  • a final step in the manufacture comprises
  • the final step in the manufacture comprises
  • the dimensions may be so adapted that the energy-absorbing part 4 must be pressed into the external tubular part 3, but it should be realised that it is an advantage if the external tubular part 3 has an internal dimension that is large enough to allow the internal energy-absorbing part 4 to move or be displaced freely relative to the tubular part 3 before the fastening, by, for example, welding or gluing. If the internal dimension of the external tubular part 3 is sufficiently large relative to the dimension of the internal energy-absorbing part 4, the advantage is achieved that the risk that grout comes into contact with the energy-absorbing part is minimised.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Dowels (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

The present invention concerns a rock bolt (1) to be embedded in a borehole (2), comprising an extended energy-absorbing part (4), the first end (11) of the energy-absorbing part (4) comprising an anchor (12) and the second end (15) of the energy-absorbing part (4) comprising a screw joint (16) for prestressing of the rock bolt (1). The rock bolt (1) comprises an extended tubular part (3) with a jacket (7) and a first end section (5) and a second end section (6), with an internal dimension that is larger than the external dimension of the energy-absorbing part (4) and arranged in such a manner that it surrounds the energy- absorbing part (4). The invention concerns also a method for the manufacture of such a rock bolt.

Description

ROCK BOLT TO BE EMBEDDED IN A FIXING MATERIAL, IN A BORE HOLE
The present invention concerns a rock bolt for the absorption of forces during the reinforcement of rock chambers in mines and during similar work with rock.
BACKGROUND Mines in the world are being constructed ever deeper in order to reach minerals. This leads to increased rock tension and an increased risk of seismic activity. As the depth increases and in regions with large deformations, reinforcement with the ability to absorb energy, known as "dynamic reinforcement", is used.
There are principally two different types of energy-absorbing bolt. In one variant, the absorption of energy takes place through friction between the bolt and the grout or between the bolt and the borehole. The bolt glides and absorbs energy.
A second method is to deform or strain the bolt. If the degree of strain is large, the absorption of energy is also large. The larger the degree of strain, the larger the absorption of energy.
In order to achieve as large a degree of strain as possible, the disengaged length, which is the length between attachment of the bolt inside the borehole and the free end of the bolt, should be as long possible.
An embedded dynamic rock bolt normally consists of an extent with a thread with a screw joint, and one or several attachment regions along the bolt. The term "attachment region" is here used to denote one or several regions along the extent of the bolt that has been embedded in the borehole. The energy-absorbing regions along the bolt, at which the bolt can be strained, are constituted by stretches between the embedded parts that have a low friction between the grout and the bolt. A bolt with several anchors reduces the energy-absorbing ability of the bolt, since the stretch over which the bolt can be strained is reduced.
One disadvantage of dynamic embedded bolts arises if damage in the rock chamber reaches the region between the anchors, since in this case no counteracting forces are present to hold the rock in place.
SUMMARY OF THE INVENTION
The purpose of the present invention is to remove the problems described above by offering an embedded dynamic rock bolt of which the energy-absorbing ability is larger since the extent that can be strained being longer than it is in conventional embedded dynamic rock bolts. This purpose is achieved through an embedded dynamic rock bolt with an energy-absorbing part that is located in a protected environment without being able to come into contact with the grout, at the same time as the energy-absorbing part is as long as possible.
DESCRIPTION OF DRAWINGS
The invention will be described below with reference to the attached drawings of which:
Figure 1 shows a side view of a rock bolt according to the invention with an anchor with a wedge,
Figure 1A shows an alternative embodiment of a rock bolt according to the invention, Figure 2 shows the rock bolt from Figure 1 in cut-through view, Figure 2A shows the rock bolt from Figure 1A in cut-through view, Figure 3 shows an end view of a screw joint, Figure 4 shows an end view of an anchor,
Figure 5 shows the bolt from Figure 1, where the anchor has been exchanged for a stirring arrangement,
Figure 6a shows an external tubular part provided with lugs,
Figure 6b shows an external tubular part with perforations,
Figure 6c shows an external tubular part with a pattern,
Figure 7a shows an energy-absorbing part in the form of a reinforcement member, Figure 7b shows an energy-absorbing part in the form of a wire,
Figure 7c shows an energy-absorbing part in the form of a steel rod,
Figure 7d shows an energy-absorbing part in the form of a composite material, and
Figure 8 shows rock with a borehole for the introduction of a rock bolt. DESCRIPTION OF EMBODIMENTS
Figure 1 shows a rock bolt 1 according to the invention intended to be embedded in a borehole 2 in rock. The rock bolt 1 comprises an extended external tubular part 3 and an internal extended energy-absorbing part 4. In one preferred embodiment, the external part 3 has been given a length that is somewhat less than the length of the energy-absorbing part 4. The external tubular part 3 has a first end 5 and a second end 6, and a magnitude that allows the energy-absorbing part 4 to be surrounded by the external part 3. It is an advantage if the external part 3 has circular cross-section in the form of a circularly symmetrical metal tube, but it should be realised that also other forms and materials are possible. Square, elliptical or rectangular tubes, of metal, plastic or composite material can, for example, be used. Also other forms of the external tubular part 3 can be used.
The jacket 7 of the external tubular part 3 is, as is shown in Figures 6a-6c, arranged with a friction-increasing structure, for example in the form of a pattern 8. The jacket 7 may be arranged with lugs 9, in the same manner as the lugs on a commonly occurring reinforcement member. The jacket 7 also may be arranged with perforations 10, or with various combinations of pattern, lugs and perforations. The purpose of the friction-increasing structure is to give a better attachment surface in the concrete into which the bolt 1 has been embedded. If the jacket 7 is provided with perforations 10, the concrete is given the possibility to grip onto the tubular part 3 without the concrete running into the tubular part and making contact with the energy-absorbing part 4.
The internal energy-absorbing part 4 demonstrates a length that exceeds the length of the external tubular part 3. In one preferred embodiment, the energy-absorbing part 4 comprises a reinforcement member 4a, but it can in other embodiments comprise a wire 4b, a rod 4c or an extended member of a composite material 4d, as shown in Figures 7a-7d. One end 11 of the internal energy-absorbing part 4, the end that is intended to be located at the bottom of the borehole 2 when the rock bolt 1 has been mounted, is arranged with an anchor 12 in the form of a slot 13 with a wedge 14. The slot 13 is placed in the end 11 of the energy-absorbing part 4 in such a manner that the end has a division to a certain extent. A wedge 14 is located in the slot 13. When the bolt 1 is introduced into the borehole 2 and reaches the bottom of the borehole, the bolt 1 is pressed or beaten against the bottom of the borehole such that the wedge 14 is pressed into the slot 13. When the wedge 14 is pressed into the slot 13, the parts on the two sides of the slot are pressed outwards against the walls of the borehole and attach in this manner the end 11 of the rock bolt in the borehole 2.
The second end 15 of the energy-absorbing part 4 is provided with a threaded section 16 that extends a certain distance into the energy-absorbing part 4. The threaded section 16 is intended to be located outside of the borehole when the bolt 1 has been introduced into the hole 2, and has a diameter that is equal to or greater than the external dimension of the outer part, as shown in Figures 1 and 2. The purpose of this is to avoid any weakening of the internal energy-absorbing part caused by the thread. A screw joint 17 in the form of a nut 18, a washer 19 and a force distributor in the form of a half sphere 20 is mounted at the threaded section 16. When the rock bolt 1 is mounted and embedded in the borehole 2, it is prestressed by the screw joint 17. The task of the half sphere 20 is to direct the force from the rock against the washer 19 and the nut 18. It should be realised that, when the internal energy-absorbing part 4 comprises a wire 4b or a composite material 4d, the threaded section 16 and the anchor 12 are attached to the energy-absorbing part 4c or 4d through welding, gluing or in another manner permanent attached.
The internal energy-absorbing part 4 is introduced into, placed inside, the external tubular part 3. One end 5 of the external tubular part 3 is attached at the internal energy-absorbing part 4 in association with the anchor 12. The second end 6 of the tubular part 3 is attached in close association with the screw joint 17, in direct association with the end of the threaded section 16. According to one preferred embodiment, the ends 5, 6 of the external tubular part 3 are attached by means of welding with fully welded joins S. It should, however, be realised that another type of fastening can be used, such as gluing or other permanent fastening. Gluing is particularly appropriate when other material than steel is used for the energy- absorbing part 4 and/or the external tubular part 3.
In another embodiment, only the end 5 of the tubular part is attached through welding with fully welded joins to the internal energy-absorbing part in association with the anchor 12. The length of the tubular part 3 is adapted such that its second end 6 comes into contact with the washer 19 and makes contact with it when the rock bolt is prestressed. The preferred rock bolt is mounted in the following manner as shown in Figure 8: a fixing material such as concrete is introduced into the borehole 2 when it has been drilled in the rock. The rock bolt 1 is subsequently introduced into the hole with the anchor 12 entering the borehole first. When the rock bolt 1 reaches the bottom, the bolt is pressed or beaten against the bottom of the borehole such that the anchor becomes attached and the bolt is fixed. When the concrete has hardened, the screw joint 17 is mounted on the part of the threaded part 16 that protrudes from the borehole 2, and is tightened such that the energy-absorbing part 4 is prestressed.
If resin is used instead of concrete, the bolt 2 is provided with an anchor in the form of a stirring arrangement 21 formed by a blade or disk having the form of a paddle, instead of the wedge. When the bolt is to be mounted, the resin is introduced into the borehole, after which the bolt is introduced into the borehole and rotated such that the resin is mixed by the stirring arrangement 21. The resin hardens rapidly, which is why the screw joint 17 can be mounted and prestressed in direct association with the insertion of the bolt 1 into the hole 2. Due to the fact that the external tubular part 3 surrounds and encloses the energy-absorbing part 4, the energy-absorbing part 4 is not subject to corrosion or other influences that can weaken the bolt 1. This gives a lifetime that is longer than that of other types of embedded rock bolt. In addition, the rock bolt 1 is given a maximum extent over which the bolt can be bent, since the energy-absorbing part 4 does not come into contact with the embedding material. This gives the advantage that the rock bolt can be bent more extensively and in this way can absorb larger forces than those absorbed by other types of embedded rock bolt.
The rock bolt is manufactured in the following manner:
- a length and a diameter of the hole 2 in the rock are determined,
- an extended energy-absorbing part 4 is arranged, - an extended tubular part 3 is arranged,
- the energy-absorbing part 4 is adapted inside of the tubular part 3,
- one end 5 of the tubular part 3 is permanently attached in association with a first end section 11 of the energy-absorbing part 4. A final step in the manufacture comprises
- the second end 6 of the tubular part 3 being permanently attached in association with a second end section 15 of the energy-absorbing part 4.
According to a second embodiment described above, the final step in the manufacture comprises
- a screw joint 17 with a washer 19 being arranged at a second end section 16 of the energy- absorbing part, and the second end 6 of the tubular part 3 coming into contact with the washer.
The internal dimension of the external tubular part 3, i.e. its internal diameter in the case in which it comprises a circular pipe, exceeds the external dimension or the diameter of the energy-absorbing part 4. The dimensions may be so adapted that the energy-absorbing part 4 must be pressed into the external tubular part 3, but it should be realised that it is an advantage if the external tubular part 3 has an internal dimension that is large enough to allow the internal energy-absorbing part 4 to move or be displaced freely relative to the tubular part 3 before the fastening, by, for example, welding or gluing. If the internal dimension of the external tubular part 3 is sufficiently large relative to the dimension of the internal energy-absorbing part 4, the advantage is achieved that the risk that grout comes into contact with the energy-absorbing part is minimised.
The present invention is not limited to what has been described above and shown in the drawings: it can be changed and modified in several different ways within the scope of the innovative concept defined by the attached patent claims.

Claims

Claims
1. A rock bolt (1) to be embedded in a borehole (2), comprising an extended energy- absorbing part (4), the first end (11) of the energy-absorbing part (4) comprising an anchor (12) and the second end (15) of the energy-absorbing part (4) comprising a screw joint (16) for prestressing of the rock bolt (1), characterised in that the rock bolt (1) comprises an extended tubular part (3) with a jacket (7) and a first (5) and a second (6) end section, and an internal dimension of the tubular part (3) that is larger than the external dimension of the energy-absorbing part (4) and arranged in such a manner that it surrounds the energy-absorbing part (4).
2. The rock bolt according to claim 1, whereby the tubular part (3) extends between the anchor (12) and the screw joint (16) and in this way prevents the energy-absorbing part (4) coming into contact with the grout.
3. The rock bolt according to any one of the preceding claims, whereby the end sections (5, 6) of the tubular part (3) are united with the energy-absorbing part (4) in association with the anchor (12) and the screw joint (16).
4. The rock bolt according to claim 3, whereby the tubular part (3) is attached by means of welding.
5. The rock bolt according to claims 1, 2 and 4, whereby the first end section (5) of the tubular part (3) is connected with the energy-absorbing part (4) in association with the anchor (12) and the second end section (6) is arranged to make contact with a washer (19) that is a component of the screw joint (16) and to make contact with the washer (19) when the rock bolt is prestressed.
6. The rock bolt according to any one of claims 1-5, whereby the jacket (7) of the tubular part (3) is provided with a structure (8) to increase friction.
7. The rock bolt according to any one of claims 1-5, whereby the jacket (7) of the tubular part (3) is perforated.
8. The rock bolt according to any one of claims 1-5, whereby the jacket (7) of the tubular part (3) is provided with lugs (9).
9. The rock bolt according to claims 1-8, whereby the energy-absorbing part (4) comprises a reinforcement member (4a).
10. The rock bolt according to claims 1-8, whereby the energy-absorbing part (4) comprises a wire (4b).
11. The rock bolt according to claims 1-8, whereby the energy-absorbing part (4) comprises a steel rod (4c).
12. The rock bolt according to claim 1, whereby the energy-absorbing part (4) comprises an extended body of a composite material (44).
13. The rock bolt according to claims 3 and 12, whereby the tubular part (3) is attached by means of welding.
14. The rock bolt according to claim 1, whereby the anchor (12) comprises a wedge (14) introduced into a slot (13) in the end (11) of the energy-absorbing part (4).
15. The rock bolt according to claim 1, whereby the anchor (12) comprises a stirring arrangement (18) arranged at the end (11) of the energy-absorbing part (4).
16. A method for the manufacture of a rock bolt (1), characterised in that it comprises the following operational steps: that a length and a diameter of the hole (2) in the rock are determined, that an extended energy-absorbing part (4) is arranged, that an extended tubular part (3) is arranged, - that the energy-absorbing part (4) is adapted inside of the tubular part (3), that one end (5) of the tubular part (3) is permanently attached in association with a first end section (11) of the energy-absorbing part (4), that the second end (6) of the tubular part (3) is permanently attached in association with a second end section (15) of the energy-absorbing part (4), and that the first end (11) and the second end (15) of the energy-absorbing part (4) are arranged with a screw joint (16) and an anchor (12), respectively.
17. A method for the manufacture of a rock bolt, characterised in that it comprises the following operational steps: - that a length and a diameter of the hole (2) in the rock are determined, that an extended energy-absorbing part (4) is arranged, that an extended tubular part (3) is arranged, that the energy-absorbing part (4) is adapted inside of the tubular part (3), that one end (5) of the tubular part (3) is permanently attached in association with a first end section (11) of the energy-absorbing part (4), that the first end (11) and the second end (15) of the energy-absorbing part (4) are arranged with a screw joint (16) and an anchor (12), respectively, and that a washer (19) that is a component of the screw joint (16) is arranged in such a manner that it makes contact with the second end (6) of the tubular part (3).
EP15848259.6A 2014-09-25 2015-09-22 Rock bolt to be embedded in a fixing material, in a bore hole Withdrawn EP3198118A4 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
SE1451130A SE538335C2 (en) 2014-09-25 2014-09-25 Energy absorbing rock bolt for casting as well as the method of manufacture of such rock bolt
PCT/SE2015/050985 WO2016056973A1 (en) 2014-09-25 2015-09-22 Rock bolt to be embedded in a fixing material, in a bore hole

Publications (2)

Publication Number Publication Date
EP3198118A1 true EP3198118A1 (en) 2017-08-02
EP3198118A4 EP3198118A4 (en) 2018-05-16

Family

ID=55653444

Family Applications (1)

Application Number Title Priority Date Filing Date
EP15848259.6A Withdrawn EP3198118A4 (en) 2014-09-25 2015-09-22 Rock bolt to be embedded in a fixing material, in a bore hole

Country Status (15)

Country Link
US (1) US20170298732A1 (en)
EP (1) EP3198118A4 (en)
CN (1) CN106715831A (en)
AP (1) AP2017009847A0 (en)
AU (1) AU2015328736A1 (en)
BR (1) BR112017005961A2 (en)
CA (1) CA2960672A1 (en)
CL (1) CL2017000688A1 (en)
CO (1) CO2017003951A2 (en)
EA (1) EA201790702A1 (en)
MX (1) MX2017003885A (en)
PE (1) PE20170618A1 (en)
SE (1) SE538335C2 (en)
WO (1) WO2016056973A1 (en)
ZA (1) ZA201702339B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6661449B2 (en) * 2016-04-06 2020-03-11 株式会社ケー・エフ・シー Rock bolt
PE20220103A1 (en) * 2019-01-29 2022-01-26 Support Tech Innovations Pty Ltd A ROCK BOLT

Family Cites Families (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2697914A (en) * 1949-10-11 1954-12-28 Joy Mfg Co Releasable wedge type roof bolt
US4056036A (en) * 1976-03-17 1977-11-01 Bergwerksverband Gmbh Borehole anchor
US4100748A (en) * 1977-01-07 1978-07-18 Stratabolt Corporation Mine roof or rock bolt expansion anchor of the bail type
US4411643A (en) * 1981-02-10 1983-10-25 Berlin & Jones Company, Inc. Double envelope and method of making same
US4516883A (en) * 1983-04-01 1985-05-14 Die-Matic Corporation Mine roof bolt mounting assembly
DE3417252C1 (en) * 1984-05-10 1986-04-17 Bergwerksverband Gmbh, 4300 Essen Combined rigid profile and expansion anchor
US5073064A (en) * 1990-04-27 1991-12-17 Birmingham Bolt Company Method and apparatus for retorquing an installed mine roof bolt
DE4411643A1 (en) * 1994-04-02 1995-10-05 Dyckerhoff & Widmann Ag Method of dismantling free part of tensioned member of prestressed anchor on bore-hole end of loaded anchoring body
AUPS310802A0 (en) * 2002-06-21 2002-07-11 Industrial Rollformers Pty Limited Yielding cable bolt
AU2003262348A1 (en) * 2002-11-18 2004-06-03 Industrial Roll Formers Pty Ltd Yielding Rock Bolt
RU2343287C2 (en) * 2003-06-03 2009-01-10 Дьюнфаер Пти Лтд Anchor bolt
WO2006106883A1 (en) * 2005-03-31 2006-10-12 Dowa Electronics Materials Co., Ltd. Fluorescent substance, fluorescent substance sheet and process for producing the same, and luminescent device using said fluorescent substance
DE102006053141B3 (en) * 2006-11-10 2008-06-19 Atlas Copco Mai Gmbh Improved slip anchor
CA2638725C (en) * 2007-08-17 2017-03-28 Jennmar Corporation Self drilling rock bolt
US8255726B2 (en) * 2008-07-18 2012-08-28 International Business Machines Corporation Zero indication forwarding for floating point unit power reduction
US8485758B2 (en) * 2009-01-07 2013-07-16 Ming Cai Yieldable cone bolt and method of manufacturing same
SE535627C2 (en) * 2010-05-26 2012-10-23 Luossavaara Kiirunavaara Ab rock bolt
US20130185920A1 (en) * 2010-08-25 2013-07-25 Amir Peled Anchor device and method of use
FI124908B (en) * 2011-02-24 2015-03-13 Suomen Metallityö Oy rock bolt
US20130018592A1 (en) * 2011-07-15 2013-01-17 Pulsar Informatics, Inc. Systems and Methods for Inter-Population Neurobehavioral Status Assessment Using Profiles Adjustable to Testing Conditions

Also Published As

Publication number Publication date
EA201790702A1 (en) 2017-07-31
CO2017003951A2 (en) 2017-07-11
CA2960672A1 (en) 2016-04-14
BR112017005961A2 (en) 2017-12-19
US20170298732A1 (en) 2017-10-19
CN106715831A (en) 2017-05-24
SE538335C2 (en) 2016-05-24
MX2017003885A (en) 2017-12-15
WO2016056973A1 (en) 2016-04-14
AU2015328736A1 (en) 2017-04-27
ZA201702339B (en) 2022-05-25
PE20170618A1 (en) 2017-05-17
AP2017009847A0 (en) 2017-03-31
SE1451130A1 (en) 2016-03-26
EP3198118A4 (en) 2018-05-16
CL2017000688A1 (en) 2017-10-30

Similar Documents

Publication Publication Date Title
JP5135034B2 (en) Exposed type column base structure
JP5778791B2 (en) Anchoring element
AU2014101640A4 (en) Multiple-point anchored rock bolt
WO2011149420A1 (en) Rock bolt embedded in grout
JP2006312822A (en) Anchoring structure of tendon
JP2005351412A (en) Connection method for steel pipes
US20170298732A1 (en) Rock bolt
KR101987381B1 (en) Anti-loosing apparatus for nut
JP7028817B2 (en) Slope collapse prevention reinforcement body and slope collapse prevention reinforcement method using this
JP6532906B2 (en) Installation structure of precast wall column
CA2714264A1 (en) Fastening element and method for producing a fastening element
JP3960559B1 (en) Reinforcement pipe with pressure plate, ground fall prevention method, and slope reinforcement method
KR102110806B1 (en) Construction method for reinforced helical pile
KR102108429B1 (en) Anti-loosing nut equipped with locking pin and production method therof
FI20185933A1 (en) Reinforcement means for insertion and fixation in a borehole
JP7261658B2 (en) Method for joining precast concrete members
JP6418824B2 (en) Junction structure
JP4097643B2 (en) Strengthening method of landslide prevention pile
JP5385842B2 (en) Gibber device for joining concrete members to steel members
KR101213588B1 (en) Tie Cable for Ground Embankment
JP4711463B2 (en) Pile head joint structure
JP7289245B2 (en) Anchor installation structure
JP6448644B2 (en) Mounting system on submerged anchor and reinforcing assembly using such mounting system
JP6878124B2 (en) Anchor and support structure
KR101368055B1 (en) Anchor head device

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20170421

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
A4 Supplementary search report drawn up and despatched

Effective date: 20180418

RIC1 Information provided on ipc code assigned before grant

Ipc: E21D 21/00 20060101AFI20180412BHEP

19U Interruption of proceedings before grant

Effective date: 20190129

19W Proceedings resumed before grant after interruption of proceedings

Effective date: 20230502

RIN1 Information on inventor provided before grant (corrected)

Inventor name: ERIKSSON, LEIF

Inventor name: KREKULA, HAKAN

PUAJ Public notification under rule 129 epc

Free format text: ORIGINAL CODE: 0009425

32PN Public notification

Free format text: COMMUNICATION PURSUANT TO RULE 142 EPC (RESUMPTION OF PROCEEDINGS UNDER RULE 142(2) EPC DATED 10.11.2022)

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20231103