Control device for controlling an energy allocation and device for providing electrical energy to a building-associated consumer group Download PDFInfo
- Publication number
- DE202010015254U1 DE202010015254U1 DE202010015254U DE202010015254U DE202010015254U1 DE 202010015254 U1 DE202010015254 U1 DE 202010015254U1 DE 202010015254 U DE202010015254 U DE 202010015254U DE 202010015254 U DE202010015254 U DE 202010015254U DE 202010015254 U1 DE202010015254 U1 DE 202010015254U1
- Authority
- DE
- Germany
- Prior art keywords
- energy
- consumer
- control device
- plant
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/12—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
- H02J3/14—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J13/00—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
- H02J13/00004—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the power network being locally controlled
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J13/00—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
- H02J13/00006—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2300/00—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
- H02J2300/20—The dispersed energy generation being of renewable origin
- H02J2300/22—The renewable source being solar energy
- H02J2300/24—The renewable source being solar energy of photovoltaic origin
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2300/00—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
- H02J2300/20—The dispersed energy generation being of renewable origin
- H02J2300/28—The renewable source being wind energy
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2310/00—The network for supplying or distributing electric power characterised by its spatial reach or by the load
- H02J2310/10—The network having a local or delimited stationary reach
- H02J2310/12—The local stationary network supplying a household or a building
- H02J2310/14—The load or loads being home appliances
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
- H02J3/381—Dispersed generators
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y02B70/3225—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B90/00—Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
- Y02B90/20—Smart grids as enabling technology in buildings sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
- Y02E10/56—Power conversion systems, e.g. maximum power point trackers
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/222—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/242—Home appliances
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S40/00—Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
- Y04S40/12—Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
Steuereinrichtung (15) zum Steuern einer Zuteilung von elektrischer Energie an einen gebäudezugeordneten Verbraucherverbund (2) mit zumindest einem elektrischen Verbraucher (3 bis 7), wobei der Verbraucherverbund (2) durch eine elektrische Energie aus regenerativer Energie erzeugenden Anlage (12) und/oder aus einem öffentlichen Energieversorgungsnetz (11) mit elektrischer Energie versorgbar ist,
– mit einer ersten Verarbeitungseinheit (15a), welche zur Verarbeitung von Signalen enthaltend Informationen über eine momentan bereitstellbare Anlagen-Energiemenge der Anlage (12) ausgebildet ist, und
– mit einer zweiten Verarbeitungseinheit (15b), welche zur Verarbeitung von Signalen enthaltend eine Informationen über die Anforderung eines eine Verbraucher-Energiemenge verbrauchenden Betriebs zumindest eines elektrischen Verbrauchers (3 bis 7) des Verbraucherverbunds (2) ausgebildet ist, und
– mit einer Verzögerungseinheit (15d) welche dazu ausgebildet ist, dass bei einem Vorliegen einer Anforderung eines eine Verbraucher-Energiemenge verbrauchenden Betriebs eines gebäudezugeordneten Verbrauchers (3 bis 7) des Verbraucherverbunds (2) der Betrieb des Verbrauchers (3 bis 7) automatisch gesteuert zumindest so lange...Control device (15) for controlling an allocation of electrical energy to a building-associated consumer network (2) with at least one electrical load (3 to 7), wherein the consumer network (2) by an electrical energy regenerative energy generating plant (12) and / or from a public power supply network (11) can be supplied with electrical energy,
- With a first processing unit (15 a), which is designed for processing signals containing information about a currently available plant energy amount of the system (12), and
- With a second processing unit (15b), which is designed for processing signals containing information about the requirement of consuming a consumer energy amount operating at least one electrical load (3 to 7) of the consumer group (2), and
- With a delay unit (15d) which is designed so that in the presence of a request for consuming a consumer energy consumption of a building consumers (3 to 7) of the consumer group (2) the operation of the consumer (3 to 7) automatically controlled at least so long...
Description
Die Erfindung betrifft eine Steuereinrichtung zum Steuern einer Zuteilung von elektrischer Energie an einen gebäudezugeordneten Verbraucherverbund mit zumindest einem elektrischen Verbraucher, bei welchem elektrische Energie durch eine gebäudezugeordnete Anlage aus regenerativer Energie erzeugt wird. Die erzeugte elektrische Energie kann zumindest anteilig in ein öffentliches und somit nicht gebäudezugeordnetes Energieversorgungsnetz eingespeist werden. Ein elektrischer Verbraucher des Verbraucherverbunds kann durch die Anlage und/oder das Energieversorgungsnetz mit elektrischer Energie versorgt werden. Des Weiteren betrifft die Erfindung eine Vorrichtung zum Bereitstellen von elektrischer Energie an einen gebäudezugeordneten Verbraucherverbund mit einer entsprechenden Steuereinrichtung.The invention relates to a control device for controlling an allocation of electrical energy to a building-associated consumer network with at least one electrical load, in which electrical energy is generated by a building-associated system of regenerative energy. The generated electrical energy can be at least partially fed into a public and thus not building-related energy supply network. An electrical consumer of the consumer group can be supplied by the plant and / or the power grid with electrical energy. Furthermore, the invention relates to a device for providing electrical energy to a building-associated consumer network with a corresponding control device.
In der modernen Gebäudetechnik werden Photovoltaik-Anlagen eingesetzt, die aus Sonnenlicht elektrische Energie erzeugen. Der dabei erzeugte Strom wird üblicherweise zu einem großen Teil in das öffentliche Energieversorgungsnetz eingespeist. Dazu gibt es gegenwärtig Vereinbarungen, bei denen die Betreiber der gebäudezugeordneten Anlagen und somit beispielsweise private Betreiber eine so genannte Einspeisevergütung erhalten.In modern building technology, photovoltaic systems are used that generate electrical energy from sunlight. The electricity generated is usually fed to a large extent in the public power grid. For this purpose, there are currently agreements in which the operators of the building-related installations and thus for example private operators receive a so-called feed-in tariff.
Darüber hinaus sind modernere Anlagen bekannt, bei denen ein Anteil des von der Photovoltaik-Anlage erzeugten Stroms von gebäudezugeordneten Verbrauchern selbst verbraucht wird. Eine derartige Verbrauchsgröße wird als Eigenverbrauch bezeichnet. Der Eigenverbrauch bezeichnet dabei die Quote, die anteilsmäßig von der gesamten erzeugten elektrischen Energiemenge der Photovoltaik-Anlage von einem gebäudezugeordneten elektrischen Verbraucherverbund selbst verbraucht wird. Aufgrund der gegenwärtigen Ausgestaltung und Betriebsweise der Anlagen ist diese Quote jedoch gering und beträgt gegenwärtig um die maximal 30%.In addition, more modern plants are known in which a portion of the electricity generated by the photovoltaic system is consumed by building consumers themselves. Such consumption is referred to as self-consumption. The self-consumption refers to the rate that is proportionately consumed by the total amount of electrical energy generated by the photovoltaic system of a building-associated electrical consumer network itself. However, due to the current design and operation of the facilities, this rate is low and currently at most 30%.
Da zukünftig einerseits die Einspeisevergütung reduziert wird und das Energiemanagement von gebäudezugeordneten Verbrauchern effektiver erfolgen soll, ist die gegenwärtige Situation unbefriedigend.Since, on the one hand, the feed-in tariff will be reduced in future and the energy management of building-related consumers should be more effective, the current situation is unsatisfactory.
Es ist Aufgabe der vorliegenden Erfindung, eine Steuereinrichtung zum Steuern einer Zuteilung von elektrischer Energie an einen gebäudezugeordneten Verbraucherverbund, als auch eine Vorrichtung zum Steuern einer derartigen Zuteilung zu schaffen, mit welcher die Eigenverbrauchsquote einer zur Umwandlung von regenerativer Energie in elektrische Energie ausgebildeten Anlagen erhöht wird und somit die Erhöhung der Quote der von der Anlage erzeugten und von dem gebäudezugeordneten Verbraucherverbund selbst verbrauchten elektrische Energie erreicht wird.It is an object of the present invention to provide a control device for controlling an allocation of electrical energy to a building-associated consumer group, as well as a device for controlling such an allocation, with which the self-consumption of a trained for the conversion of renewable energy into electrical energy systems is increased and thus the increase in the rate of electricity generated by the system and consumed by the building-related consumer group itself is achieved.
Die Aufgabe wird durch die Merkmale der unabhängigen Ansprüche gelöst.The object is solved by the features of the independent claims.
Eine erfindungsgemäße Steuereinrichtung ist zum Steuern einer Zuteilung von elektrischer Energie an einen gebäudezugeordneten Verbraucherverbund mit zumindest einem elektrischen Verbraucher ausgebildet, wobei der Verbraucherverbund durch eine elektrische Energie aus regenerativer Energie erzeugenden Anlage und/oder aus einem öffentlichen Energieversorgungsnetz mit elektrischer Energie versorgbar ist. Die Steuereinrichtung umfasst zumindest eine erste Verarbeitungseinheit, welche zur Verarbeitung von Signalen enthaltend Informationen über eine momentan bereitstellbare Anlagen-Energiemenge der Anlage ausgebildet ist. Die Steuereinrichtung umfasst darüber hinaus eine zweite Verarbeitungseinheit, welche zur Verarbeitung von Signalen enthaltend Informationen über die Anforderung eines eine Verbraucher-Energiemenge verbrauchenden Betriebs zumindest eines elektrischen Verbrauchers des Verbraucherverbunds ausgebildet ist. Die Steuereinrichtung umfasst darüber hinaus eine Verzögerungseinheit, welche dazu ausgebildet ist, dass bei einem Vorliegen einer Anforderung für einen eine Verbraucher-Energiemenge verbrauchenden Betriebs eines gebäudezugeordneten Verbrauchers des Verbraucherverbunds der Betrieb des Verbrauchers automatisch gesteuert zumindest solange verzögerbar ist, bis die insbesondere momentan bereitstellbare Anlagen-Energiemenge einen vorgebbaren Energiemengen-Schwellwert übersteigt.A control device according to the invention is designed to control an allocation of electrical energy to a building-associated consumer group with at least one electrical load, wherein the consumer group is supplied by an electrical energy from regenerative energy generating system and / or from a public power grid with electrical energy. The control device comprises at least one first processing unit which is designed to process signals containing information about a currently available plant energy quantity of the system. The control device further comprises a second processing unit, which is designed to process signals containing information about the requirement of consuming a consumer energy amount operating at least one electrical consumer of the consumer group. The control device further comprises a delay unit, which is designed so that, in the presence of a request for consuming a consumer energy consumption of a building-associated consumer of the consumer group, the operation of the consumer is automatically controlled at least as long delayed until the currently available in particular equipment Energy amount exceeds a predetermined amount of energy threshold.
Es kann vorgesehen sein, dass die Verbrauchereinheiten in einer gemeinsamen Einheit angeordnet sind. Insbesondere kann auch vorgesehen sein, dass die beiden Verbrauchereinheiten und die Verzögerungseinheit durch eine gemeinsame Einheit gebildet sind.It can be provided that the consumer units are arranged in a common unit. In particular, it can also be provided that the two consumer units and the delay unit are formed by a common unit.
In besonders vorteilhafter Weise ist vorgesehen, dass die Steuereinheit Mittel bzw. Einheiten aufweist, die zur Durchführung von spezifischen Abläufen zur Steuerung der Verzögerung, insbesondere im Hinblick auf deren Verlängerung oder deren Abbruch etc. ausgebildet sind. So sind in diesem Zusammenhang insbesondere die Steuerabläufe zur Durchführung der Verzögerung, zur Verzögerungsverlängerung, zur Laufzeitbestimmung und zum Abbruch der Verzögerung vorgesehen. Insbesondere werden auch die elektrischen Verbraucher im Hinblick auf ihre Reihenfolge des Betriebs sowie im Hinblick auf die Zuteilung von Energie zu deren Betrieb einerseits aus der Anlage und/oder dem öffentlichen Energieversorgungsnetz und/oder einem gebäudezugeordneten Energiespeicher gesteuert.In a particularly advantageous manner, it is provided that the control unit has means or units which are designed to carry out specific sequences for controlling the deceleration, in particular with regard to their extension or their demolition. In this context, in particular, the control processes for carrying out the delay, extending the delay, determining the transit time and terminating the delay are provided. In particular, the electrical consumers are also controlled with regard to their sequence of operation and with regard to the allocation of energy for their operation on the one hand from the plant and / or the public energy supply network and / or a building-assigned energy storage.
Insbesondere weist die Steuereinrichtung Mittel auf, mit denen die nachfolgend in der Beschreibung erläuterten Abläufe steuerbar sind. In particular, the control device has means with which the processes explained below in the description can be controlled.
Die Steuereinrichtung kann dazu neben der Verarbeitungseinheiten und der Verzögerungseinheit vorteilhafterweise zumindest eine Auswerteeinheit und/oder eine Entscheidereinheit und/oder eine Erwartungswertbestimmungseinheit und/oder eine Speichereinheit aufweisen. Weitere Einheiten können vorgesehen sein.In addition to the processing units and the delay unit, the control device may advantageously have at least one evaluation unit and / or a decision unit and / or an expected value determination unit and / or a memory unit. Further units can be provided.
Bezüglich der optionalen Angabe, dass eine Verzögerung eines angeforderten grundsätzlichen Betriebstarts zumindest eines Verbrauchers oder die Fortführung eines unterbrochenen Betriebs eines Verbrauchers erfolgen kann ist dies dahingehen zu verstehen, dass die Verzögerungsfunktion grundsätzlich vorhanden und möglich wird bzw. ist. In einer primären Ausführung kann dabei vorgesehen sein, dass das Verzögern des Betriebs, wie es im Kontext der Erfindung zu verstehen ist, nur abhängig von der Vorgabe ist, ob die Anlagen-Energiemenge zum Zeitpunkt der Betriebsanforderung kleiner dem Energiemengen-Schwellwert ist und wenn dem so ist der Betrieb verzögert wird, insbesondere so lange, bis die Anlagen-Energiemenge den Energiemengen-Schwellwert wieder übersteigt. Es kann jedoch auch vorgesehen sein, dass aufgrund von Nutzervorgaben und/oder zumindest einem weiteren Entscheidungskriterium keine Verzögerung zum Zeitpunkt der Betriebsanforderung stattfindet, und zwar auch dann nicht, wenn zum Zeitpunkt der Betriebsanforderung eines Verbrauchers die Anlagen-Energiemenge kleiner oder gleich dem Energiemengen-Schwellwert ist.With regard to the optional indication that a delay of a requested basic operation start of at least one consumer or the continuation of an interrupted operation of a consumer can take place, it is to be understood that the delay function is basically present and possible or is. In a primary embodiment, it may be provided that the deceleration of the operation, as it is to be understood in the context of the invention, is only dependent on the specification of whether the plant energy quantity at the time of the operating request is smaller than the energy amount threshold value and if Thus, the operation is delayed, in particular until the system energy amount exceeds the energy level threshold again. However, it can also be provided that, on the basis of user specifications and / or at least one further decision criterion, no delay takes place at the time of the operating request, even if the system energy quantity is less than or equal to the energy quantity threshold value at the time of a consumer's operating request is.
Die Betriebsanforderung eines Verbrauchers ist dabei insbesondere in einer Phase erfolgt, in der die Anlagen-Energiemenge bereits kleiner als der Energiemengen-Schwellwert war.The operating requirement of a consumer has occurred in particular in a phase in which the system energy amount was already smaller than the energy quantity threshold value.
Unter einer Gebäudezuordnung wird im Kontext der Erfindung eine definierte Zuordnung der Verbraucher zu einer gegenüber anderen Wohneinheiten abgegrenzten Wohneinheit verstanden. Eine Wohneinheit kann beispielsweise eine Privatwohnung, ein Privatwohnhaus oder können aber auch gewerblich genutzte Wohnräume sein. Wird beispielsweise eine derartige Anlage auf einem Dach eines spezifizierten Gebäudes, wie beispielsweise einem Wohnhaus, einem Bürohaus oder landwirtschaftlichen Stallungen, oder aber auch auf einem zumindest anteilig privat genutzten Garten oder landwirtschaftlichen Feld installiert, so ist diese Gebäudezuordnung im Verständnis der vorliegenden Erfindung unter anderem gegeben.In the context of the invention, a building association is defined as a defined assignment of the consumers to a residential unit delimited from other residential units. A residential unit may be, for example, a private apartment, a private residence or may also be commercially used living spaces. For example, if such a system installed on a roof of a specified building, such as a residential building, an office building or agricultural stables, or even on a proportionately privately used garden or agricultural field, this building allocation is given in the understanding of the present invention, inter alia ,
Unter gebäudezugeordneten Verbrauchern werden somit insbesondere diejenigen verstanden, die nur in oder zu diesem Gebäude genutzt oder angeordnet sind. Beispielsweise kann hier vorgesehen sein, dass Haushaltsgeräte eines Gebäudes als derartige gebäudezugeordnete Verbraucher angesehen werden.Under building associated consumers are thus understood in particular those who are used or arranged only in or to this building. For example, it may be provided here that household appliances of a building are regarded as such building-associated consumers.
Im Hinblick auf die momentan bereitstellbare elektrische Anlagen-Energiemenge der Anlage betrifft dies insbesondere diejenige Energiemenge, die gerade direkt von der Anlage erzeugt wird. Zusätzlich oder anstatt dazu kann die momentan bereitstellbare elektrische Anlagen-Energiemenge auch diejenige Energiemenge umfassen, die in einem gebäudezugeordneten Energiespeicher, in den zumindest anteilig bereits vorher von der Anlage erzeugte elektrische Energie zwischengespeichert wurde.With regard to the current amount of electrical system energy that can be supplied to the system, this relates in particular to the amount of energy that is currently being generated directly by the system. In addition to or instead of this, the currently available electrical system energy quantity can also include the amount of energy that has been stored temporarily in an energy store associated with the building, in which at least a proportion of the electrical energy previously generated by the system has been stored.
Im Hinblick auf die erforderliche elektrische Verbraucher-Energiemenge betrifft dies insbesondere die momentan erforderliche elektrische Verbraucher-Energiemenge des gebäudezugeordneten Verbraucherverbunds.With regard to the required amount of electrical consumer energy, this relates in particular to the currently required amount of electrical consumer energy of the building-associated consumer group.
Im Hinblick auf die Begrifflichkeit eines Verzögerns eines energieverbrauchenden Betriebs des Verbrauchers wird dabei sowohl das Verzögern eines grundsätzlichen Startens des angeforderten Betriebs von Anfang verstanden.With regard to the concept of delaying an energy-consuming operation of the consumer, both the delaying of a fundamental starting of the requested operation is understood from the beginning.
Ebenso wird darunter jedoch auch verstanden, dass ein bereits energieverbrauchender Betrieb des Verbrauchers gestartet wurde und dann unterbrochen wurde. Die Verzögerung liegt dann in der Verlängerung der Unterbrechung. Die Unterbrechung kann aufgrund unterschiedlicher Faktoren erfolgt sein. Es kann vorgesehen sein, dass das Unterbrechen auch abhängig von der Anlagen-Energiemenge erfolgt. Dazu kann ein spezifischer Unterschreitungswert der Anlagen-Energiemenge vorgegeben werden. Beispielsweise kann dann die Unterbrechung so lange dauern, bis die Anlagen-Energiemenge einen vorgebbaren Wert wieder überschreitet, insbesondere beispielsweise den Energiemengen-Schwellwert wieder überschreitet. Auch dies ist unter einer Verzögerung im Kontext der vorliegenden Erfindung zu verstehen. Ganz allgemein ist auch hier zu erwähnen, dass situationsspezifisch ein Verbraucher entweder vollständig mit Energie aus dem Energieversorgungsnetz oder vollständig mit elektrischer Energie von der Anlage betrieben werden kann. Ebenso ist es möglich, dass der Energieverbrauch des betriebenen Verbrauchers zumindest anteilig durch Energie aus dem Energieversorgungsnetz und anteilig durch Energie von der Anlage gedeckt wird. Bezüglich des Verzögerns betrifft dies hier Abläufe, bei denen in der Verzögerungsphase der im Betrieb verzögerte Verbraucher insbesondere keine Energie verbraucht.However, this also means that an already energy-consuming operation of the consumer was started and then interrupted. The delay is then in the extension of the interruption. The interruption may have been due to various factors. It can be provided that the interruption also takes place as a function of the system energy quantity. For this purpose, a specific underflow value of the plant energy quantity can be specified. For example, then the interruption can take so long until the system energy amount exceeds a predetermined value again, in particular, for example, exceeds the energy level threshold again. Again, this is a delay in the context of the present invention. Quite generally, it should also be mentioned here that, depending on the situation, a consumer can either be operated entirely with energy from the energy supply network or completely with electrical energy from the installation. It is also possible that the energy consumption of the operated consumer is at least partially covered by energy from the power grid and proportionately by energy from the plant. With regard to deceleration, this concerns processes in which, in the deceleration phase, the consumer delayed in operation, in particular, consumes no energy.
Durch das erfindungsgemäße Verfahren kann die Eigenverbrauchsquote gegenüber herkömmlichen bekannten Betriebsweisen und Vorrichtungen erhöht werden und kann sogar auf Werte über 60%, insbesondere deutlich über 60%, gesteigert werden. Dies bezieht sich auf Vorrichtungen, die beispielsweise im Hinblick auf Leistung der Anlage, Anzahl und Art der Verbraucher etc. vergleichbar sind.By the method according to the invention, the self-consumption rate can be compared conventional known operations and devices can be increased and can even be increased to values above 60%, in particular well above 60%. This refers to devices that are comparable, for example, in terms of performance of the system, number and type of consumers, etc.
Besonders vorteilhaft ist es, dass die elektrische Energie aus Sonnenlicht durch eine als Photovoltaik-Anlage ausgebildete gebäudezugeordnete Anlage erzeugt wird. Gerade bei dieser Art von regenerativer Energie ist es aufgrund der nicht beeinflussbaren Gegebenheiten des Tagesablaufs sowie meteorologischen Einflüssen nicht möglich, dass stets und dauerhaft fortwährend elektrische Energie durch die Anlage erzeugt wird. Da sich gerade bei derartig spezifizierten Anlagen somit die Zeiten, in denen elektrische Energie von Photovoltaik-Anlage geliefert wird, und die Zeiten, in denen elektrische Verbraucher des Verbraucherverbunds betrieben werden, nicht immer decken, kann durch den erfindungsgemäßen Verzögerungsbetrieb dies aneinander angepasst werden und somit die Eigenverbrauchsquote erhöht werden.It is particularly advantageous that the electrical energy from sunlight is generated by a building-associated system designed as a photovoltaic system. Especially with this type of regenerative energy, it is not possible due to the uncontrollable conditions of the daily routine and meteorological influences that always and permanently continuously electrical energy is generated by the system. Since the times in which electrical energy is supplied by the photovoltaic system and the times in which electrical consumers of the consumer network are operated, do not always cover precisely in such specified systems, this can be adapted to each other by the deceleration operation according to the invention and thus the self-consumption rate will be increased.
Grundsätzlich ist das erfindungsgemäße Verfahren jedoch auch auf andere Anlagen, die elektrische Energie aus regenerativer Energie erzeugen, anwendbar. Insbesondere betrifft dies derartige regenerative Energie, die naturgegeben und aufgrund meteorologischer Einflüsse nicht dauerhaft und vor allen Dingen auch nicht exakt vorhersehbar elektrische Energie liefern bzw. deren regenerativer Energie nicht durch den Menschen steuerbar bereitstellbar ist. Beispielsweise betrifft dies auch Windkraftanlagen.In principle, however, the method according to the invention can also be applied to other systems which generate electrical energy from regenerative energy. In particular, this relates to such regenerative energy that naturally and due to meteorological influences not permanently and above all, not exactly predictable electrical energy supply or their regenerative energy is not controllable by humans available. For example, this also applies to wind turbines.
Vorzugsweise ist vorgesehen, dass nach dem Überschreiten des Energiemengen-Schwellwerts die Betriebszeitverzögerung des Verbrauchers beendet wird und die Anlagen-Energiemenge zumindest anteilig dem zumindest einen elektrischen Verbraucher zu dessen Betrieb zugeteilt wird.Preferably, it is provided that after exceeding the amount of energy threshold, the operating time delay of the consumer is terminated and the system energy amount is at least partially allocated to the at least one electrical load for its operation.
Insbesondere kann somit vorgesehen sein, dass unmittelbar ohne weitere Verzögerung nach dem Überschreiten des Energiemengen-Schwellwerts der andere geforderte Betrieb des Verbrauchers sofort gestartet wird, oder der vorab unterbrochene Betrieb weitergeführt wird. Im Hinblick auf die Weiterführung eines unterbrochenen Betriebs kann die vorab erfolgte Unterbrechung aufgrund unterschiedlicher Faktoren erfolgt sein. Beispielsweise kann dies dahingehend erfolgt sein, dass der Wert der Anlagen-Energiemenge unter dem Energiemengen-Schwellwert abgesunken war. Zusätzlich oder anstatt dazu können jedoch auch eine Vielzahl von weiteren Faktoren, die darüber hinaus auch sogar unabhängig von dem Anlagen-Energiemengenwert sind, erfolgen.In particular, it can thus be provided that the other required operation of the consumer is started immediately without further delay after the energy quantity threshold value has been exceeded, or the previously interrupted operation is continued. With regard to the continuation of an interrupted operation, the previous interruption may have been due to various factors. For example, this may have been to the effect that the value of the plant energy amount has fallen below the energy quantity threshold value. In addition to or instead of this, however, a multiplicity of further factors which, in addition, may even be independent of the plant energy quantity value, can take place.
Im Hinblick auf das nach dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge erfolgten Energie verbrauchenden Betriebs eines elektrischen Verbrauchers kann dies dann bis zum Ende der erforderlichen Betriebszeit durchgeführt werden. So kann somit beispielsweise vorgesehen sein, dass der dann durchgeführte Betrieb des Verbrauchers ohne weitere Unterbrechung bis zu dessen Ende vollständig durchgeführt wird. Dies kann dann beispielsweise auch unabhängig davon erfolgen, ob die Anlagen-Energiemenge im Betriebsverlauf des Verbrauchers dann nochmals zumindest einmal unter den Energiemengen-Schwellwert fällt. So kann in diesem Zusammenhang vorgesehen sein, dass dann automatisch und kontinuierlich der Betrieb des Verbrauchers fortgesetzt wird.In view of the energy-consuming operation of an electrical consumer after the energy quantity threshold value has been exceeded by the amount of plant energy, this can then be carried out until the end of the required operating time. Thus, it can thus be provided, for example, that the then performed operation of the consumer is carried out completely without further interruption until its end. This can then, for example, also be carried out independently of whether the system energy amount falls again at least once in the course of operation of the consumer below the energy level threshold. Thus, it may be provided in this context that then automatically and continuously the operation of the consumer is continued.
Wird es nicht ermöglicht, dass der Gesamtenergiemengenbedarf des Verbrauchers durch die Anlage gedeckt werden kann, so wird der erforderliche Restenergiemengenwert aus dem öffentlichen Energieversorgungsnetz bezogen.If it is not possible for the total amount of energy consumed by the consumer to be covered by the installation, the required remainder energy will be obtained from the public energy network.
Es kann jedoch auch vorgesehen sein, dass der gestartete oder weitergeführte Energie verbrauchende Betrieb des Verbrauchers dann unterbrochen bzw. nochmals unterbrochen wird, wobei dies abhängig von ein oder mehreren Entscheidungsfaktoren der Fall sein kann.However, it can also be provided that the started or continued energy-consuming operation of the consumer is then interrupted or interrupted again, depending on one or more decision factors may be the case.
In einer weiteren alternativen Ausführung kann vorgesehen sein, dass nach dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge der Betrieb des Verbrauchers abhängig von zumindest einem Verzögerungsverlängerungs-Entscheidungskriterium weiterhin verzögert wird. Bei einer derartigen Ausführung wird dann sogar vorgesehen, dass selbst wenn der Energiemengen-Schwellwert überschritten wird, das Starten des angeforderten Betriebs oder das Weiterführen eines unterbrochenen Betriebs nicht durchgeführt wird und diesbezüglich nochmals eine weitere Verzögerung auftritt. Dies kann neben sicherheitskritischen Aspekten weitere Bedingungen umfassen, die ebenfalls im Nachfolgenden noch angegeben werden.In a further alternative embodiment, it may be provided that, after the energy quantity threshold value has been exceeded by the system energy quantity, the operation of the consumer is further delayed as a function of at least one delay extension decision criterion. In such an embodiment, it is then even provided that even if the amount of energy threshold is exceeded, the starting of the requested operation or the continuation of an interrupted operation is not performed and in this regard, a further delay occurs. In addition to safety-critical aspects, this can include further conditions, which are also specified below.
Einige beispielhafte Entscheidungskriterien können sein, dass zunächst noch abgewartet wird, wie sich der Verlauf der Anlagen-Energiemenge innerhalb eines vorgebbaren Zeitintervalls nach dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge entwickelt. Als Zeitintervall können hier Werte kleiner eine Stunde, insbesondere beispielsweise kleiner 20 Minuten betrachtet werden. Dies kann insbesondere einerseits abhängig vom Energiemengen-Schwellwert selbst aber auch von der Differenz, um die die Anlagen-Energiemenge den Energiemengen-Schwellwert übersteigt, sein. Insbesondere dann, wenn der Betrieb von mehreren Energien verbrauchenden Verbrauchern ansteht, kann diese Berücksichtigung der Kriterien interessant sein. Gerade dann, wenn diese Verbraucher im Hinblick auf weitere Kriterien, wie beispielsweise eine Prioritätenliste oder dergleichen betrieben werden sollen und/oder im Hinblick auf ihre Betriebsdauern über einen Großteil ihrer Betriebszeit überlappen und/oder die Betriebszeiten relativ ähnlich sind und somit der gesamte Energiebedarf der Verbraucher sehr hoch ist, betrieben werden, kann dies für eine Energiezuteilung bezüglich der Steigung der Eigenverbrauchsquote entscheidend sein.Some exemplary decision criteria may be that initially it is still to be seen how the course of the system energy quantity develops within a predefinable time interval after the energy quantity threshold value has been exceeded by the system energy quantity. Values of less than one hour, in particular, for example, less than 20 minutes, can be considered here as the time interval. This can in particular on the one hand depending on the amount of energy threshold itself but also on the difference to the System power amount exceeds the power level threshold. In particular, when the operation of several energy-consuming consumers is pending, this consideration of the criteria may be interesting. Especially when these consumers are to be operated with regard to further criteria, such as a priority list or the like and / or overlap in terms of their operating lives over much of their operating time and / or operating times are relatively similar and thus the total energy needs of consumers is very high, this can be crucial for an energy allocation with respect to the slope of the self-consumption quota.
Gerade dann, wenn nach dem Überschreiten des Energiemengen-Schwellwerts durch den Anlagen-Energiemengenwert eine weitere Verzögerung zumindest eines Betriebs eines angeforderten elektrischen Verbrauchers vollzogen wird, kann insbesondere vorgesehen sein, dass die erzeugte Anlage-Energiemenge zumindest anteilig in einen gebäudezugeordneten Energiespeicher zumindest zeitweise eingespeist wird. Dies ist insbesondere dahingehend vorteilhaft, dass dann, wenn auch nach weiterer Verzögerung der Betrieb eines oder mehrerer angeforderter elektrischer Verbraucher dann gestartet oder weitergeführt wird, nicht nur ab dem Zeitpunkt die erzeugte Anlagen-Energiemenge zur Verfügung gestellt werden kann, sondern auch die zwischenzeitlich in den Energiespeicher eingespeicherte Anlagen-Energiemenge zur Verfügung gestellt werden kann. Auch dies trägt äußerst positiv zur Erhöhung der Eigenverbrauchsquote bei.Just when, after exceeding the energy level threshold by the plant energy level value, a further delay at least one operation of a requested electrical consumer is completed, can be provided in particular that the generated amount of energy plant is at least partially fed into a building energy storage at least temporarily , This is particularly advantageous in that then, although after a further delay, the operation of one or more requested electrical loads then started or continued, not only from the time the generated power plant amount can be made available, but also in the meantime in the Energy storage stored system energy can be provided. This also contributes extremely positively to increasing the self-consumption rate.
Weitere spezifische Entscheidungskriterien, warum eine weitere Verzögerung auch nach dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge durchgeführt werden kann, werden im Späteren noch angegeben.Further specific decision criteria as to why a further delay can be carried out even after the energy quantity threshold value has been exceeded by the plant energy quantity will be specified later.
In einer weiteren vorteilhaften Ausführung wird vorgesehen, dass die Verzögerung des Betriebs des zumindest einen Verbrauchers vor dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge abgebrochen und der Betrieb des Verbrauchers durchgeführt wird, wenn während des Verzögerns zumindest ein Abbruch-Entscheidungskriterium erfüllt wird. So kann insbesondere bei zu berücksichtigenden Sicherheitsanforderungen oder entstehenden sicherheitskritischen Phasen ein derartiger Abbruch der Verzögerung erfolgen. Bei derartigen Szenarien kann dann entweder die Sicherheit im Vordergrund vor der Erhöhung der Eigenverbrauchsquote oder vor Nutzerinteressen Vorrang haben. Darüber hinaus kann beispielsweise auch vorgesehen sein, dass dann, wenn die Verzögerung eine vorgebbare Zeitdauer überschreitet und somit der Verzögerungsbetrieb zu lange wäre, auch in diesem Zusammenhang ein Abbruch erfolgen kann. Dies ist beispielsweise dann von Interesse, wenn der Betrieb der Verzögerung jahreszeitabhängig und/oder tageszeitabhängig in einer Phase angefordert wird, in der im Nachgang mit hoher Wahrscheinlichkeit für eine relativ lange Zeit der Energiemengen-Schwellwert von der Anlagen-Energiemenge nicht überschritten werden kann und weitere Kriterien erfüllt sind.In a further advantageous embodiment, it is provided that the delay of the operation of the at least one consumer is aborted before the energy quantity threshold value is exceeded by the amount of plant energy and the operation of the consumer is carried out if at least one abort decision criterion is fulfilled during the deceleration. Thus, in particular for safety requirements to be taken into account or safety-critical phases that arise, such an interruption of the delay can take place. In such scenarios, then either the safety in the foreground before increasing the self-consumption rate or user interests can take precedence. In addition, it can also be provided, for example, that when the delay exceeds a predefinable time duration and thus the delay operation would be too long, an abort can also take place in this context. This is of interest, for example, if the operation of the delay is requested in a season-dependent and / or time-of-day-dependent manner in which the energy quantity threshold value can not be exceeded by the plant's energy quantity for a relatively long time, and more Criteria are met.
Ein derartiges Abbruch-Zeitintervall kann mehrere Minuten bis hin zu mehreren Stunden betragen.Such an abort time interval can be several minutes to several hours.
Des Weiteren kann vorgesehen sein, dass dann, wenn der Energie verbrauchende Betrieb des zumindest einen Verbrauchers durchgeführt wird, die Zeitdauer, wie lange der Betrieb durchgeführt wird, abhängig von zumindest einem Laufzeit-Entscheidungskriterium festgelegt wird. Es wird also dann, wenn der Wert der Anlagen-Energiemenge den Energiemengen-Schwellwert übersteigt, der Betrieb sofort durchgeführt oder gegebenenfalls durch eine weitere Zeitverzögerung verzögert irgendwann gestartet oder die erfolgte Unterbrechung aufgehoben, wobei dann im weiteren Betriebsverlauf fortwährend oder in diskreten Zeitabständen geprüft wird, ob Laufzeit-Entscheidungskriterium erfüllt sind und dann wiederum ein Unterbrechen des Betriebs stattfindet. Alternativ dazu kann vorgesehen sein, dass dann, wenn festgelegt wird, dass der Betrieb gestartet oder die Unterbrechung aufgehoben wird, mit dem Starten oder dem Aufheben des Betriebs oder gegebenenfalls auch bereits zeitlich vorher festgelegt wird, wie lange der Energie verbrauchende Betrieb durchgeführt wird. Insbesondere wird diesbezüglich der Energie verbrauchende Betrieb für eine Zeitdauer festgelegt, die kürzer ist als die bis zur Beendigung des Betriebs erforderliche Zeitdauer. Auch dies kann aufgrund unterschiedlicher Kriterien erfolgen, die im Nachgang noch näher erläutert werden. Insbesondere kann dies auch wiederum von Sicherheitsanforderungen oder von insbesondere weiteren zu betreibenden Verbrauchern des Verbraucherverbunds erfolgen, wobei insbesondere dann dies beispielsweise aufgrund von einer Prioritätenliste dieser zu betreibenden Verbraucher erfolgen kann.Furthermore, it can be provided that, when the energy-consuming operation of the at least one consumer is performed, the time period for how long the operation is carried out is determined depending on at least one transit time decision criterion. Thus, when the value of the plant energy quantity exceeds the energy quantity threshold value, the operation is carried out immediately or, if appropriate delayed by a further time delay, started at some point or the interruption is canceled, in which case further testing is carried out continuously or at discrete time intervals, whether runtime decision criteria are met and then in turn an interruption of the operation takes place. Alternatively, it can be provided that, when it is determined that the operation is started or the interruption is canceled, is set with the start or cancellation of the operation or possibly even in advance, how long the energy-consuming operation is performed. In particular, in this regard, the power consuming operation is set for a period of time shorter than the time required to complete the operation. This can also be done on the basis of different criteria, which will be explained in more detail later. In particular, this can in turn also be carried out by security requirements or, in particular, by other consumers of the consumer group to be operated, in which case this can take place, for example, on the basis of a priority list of these consumers to be operated.
In weiterer vorteilhafter Vorgehensweise kann vorgesehen sein, dass bei einer Anlagen-Energiemenge größer einer erforderlichen Gesamtenergiemenge des einen Verbrauchers oder der mehreren zu betreibenden Verbraucher, deren Betriebswunsch, der bereits angefordert oder der bereits laufende Betrieb unterbrochen wurde, abhängig von zumindest einem Abgabe-Entscheidungskriterium bestimmt wird, welcher Anteil der Anlagen-Energiemenge in einen gebäudezugeordneten Energiespeicher gespeichert wird und/oder welcher Anteil in das öffentliche Energieversorgungsnetz eingespeist wird. Auch dadurch können sich vielfältige und unterschiedlichste Szenarien ergeben, die es ermöglichen, die angeforderten Betriebe der Verbraucher derart intelligent zeitlich zu steuern, dass die Eigenverbrauchsquote deutlich erhöht wird.In a further advantageous procedure, it can be provided that for a system energy amount greater than a required total amount of energy of the consumer or the plurality of consumers to be operated whose operation request has already been requested or already running operation was interrupted, determined depending on at least one delivery decision criterion is, which proportion of the system energy amount is stored in a building energy storage associated and / or what proportion is fed into the public power grid. This can also be varied and result in a wide variety of scenarios that enable consumers to control the required businesses in such an intelligent way that the self-consumption rate is significantly increased.
Vorzugsweise wird als Entscheidungskriterium die Anzahl der Verbraucher eines gebäudezugeordneten Verbraucherverbunds berücksichtigt. Dies kann als Verzögerungsverlängerungs-Entscheidungskriterium und/oder als Abbruch-Entscheidungskriterium und/oder als Laufzeit-Entscheidungskriterium und/oder als Abgabe-Entscheidungskriterium berücksichtigt werden. Ist die Anzahl der Verbraucher hoch, so steigt die Wahrscheinlichkeit, dass deren Betrieb gewünscht oder erforderlich wird und es steigt dann dadurch auch die erforderliche Energiemenge. Die Anzahl der Verbraucher gibt somit einen individuellen Parameter an, mit denen eine Verzögerungsverlängerung und/oder ein Abbruch der Verzögerung und/oder die Abgabe von erzeugter Energie in einen gebäudezugeordneten Energiespeicher und/oder in das öffentliche Energieversorgungsnetz zeitlich und/oder mengenmäßig individuell vorgegeben werden kann.Preferably, the number of consumers of a building-associated consumer group is taken into account as a decision criterion. This can be taken into account as a delay extension decision criterion and / or as a termination decision criterion and / or as a transit time decision criterion and / or as a delivery decision criterion. If the number of consumers is high, the likelihood that their operation is desired or required increases and the amount of energy required thereby increases as well. The number of consumers thus indicates an individual parameter with which a delay extension and / or a termination of the delay and / or the delivery of generated energy in a building-assigned energy storage and / or in the public power grid can be individually set in terms of time and / or quantity ,
Ein zusätzlicher oder individueller anderer Parameter bzw. ein anderes Entscheidungskriterium ist der Gesamtenergiebedarf eines oder mehrerer gebäudezugeordneter Verbraucher. Sind sehr energieintensive Verbraucher vorhanden, so kann beispielsweise vorgesehen sein, dass deren angeforderter Betrieb oder gegebenenfalls auch deren zu erwartender Betrieb gerade dann, wenn insbesondere auch mehrere derartige energieintensive Verbraucher zumindest zeitweise gleichzeitig betrieben werden sollten, zu einer Verzögerungsverlängerung führt. Grundsätzlich kann jedoch dann auch vorgesehen sein, dass die Anlagen-Energiemenge zu einem größtmöglichen Anteil in den Energiespeicher eingespeichert wird, so dass ein größtmöglicher Anteil für diese energieintensiven und/oder mit einer großen Anzahl dann zu betreibenden Verbraucher zur Verfügung steht. Ebenso ist dieses Entscheidungskriterium auch für die gegebenenfalls durchzuführende Laufzeitvorgabe für einen Verbraucher, der nachfolgend gestartet oder dessen unterbrochener Betrieb fortgeführt werden soll, berücksichtigbar und der Verbraucher ist in dieser vorgegebenen Laufzeit dann stets zumindest anteilig mit einer Anlagen-Energiemenge versorgt wird.An additional or individual other parameter or decision criterion is the total energy demand of one or more building-associated consumers. If very energy-intensive consumers are present, it may be provided, for example, that their requested operation, or possibly their expected operation, leads to a delay extension even if, in particular, several such energy-intensive consumers should be operated at least temporarily. In principle, however, it can then also be provided that the plant energy quantity is stored to the greatest possible extent in the energy storage, so that the largest possible proportion is available for this energy-intensive and / or with a large number then to be operated consumers. Likewise, this decision criterion is also for the possibly to be carried out run time specification for a consumer who started subsequently or whose interrupted operation is to be continued, considered and the consumer is then always at least partially supplied in this predetermined period with a system energy.
Des Weiteren kann als Entscheidungskriterium zusätzlich oder anstatt zu den genannten Kriterien eine Betriebsprioritätenliste der gebäudezugeordneten Verbraucher angegeben und berücksichtigt werden. Beispielsweise können als Parameter für eine derartige Priorisierung ein Nutzerprofil, das individuell von einem Nutzer vorgegeben wird und auf sein Anforderungsprofil festgelegt wird, berücksichtigt werden. Darüber hinaus kann zusätzlich oder anstatt dazu die Prioritätenliste auch anhand der Energieverbräuche der einzelnen Verbraucher aufgestellt werden, wobei beispielsweise der energieintensivste die größte Priorität hat. Ebenso kann jedoch auch vorgesehen sein, dass der mit der geringsten Energieverbrauchsmenge die größte Priorität aufweist. Die Prioritätenliste kann sich auch daran orientieren, welche Sicherheitsanforderungen für den Betrieb der einzelnen Verbraucher erforderlich sind. Beispielsweise kann hier dasjenige Gerät die größte Priorität aufweisen, welches dann, wenn es einmal gestartet ist, ohne Unterbrechung seinen Betrieb bis zum Betriebsende durchführen muss. Als weiterer Parameter für die Prioritätenliste kann beispielsweise auch die Reihenfolge, nach denen die Anforderungen der gewünschten Betriebe von mehreren Verbrauchern zeitlich erfolgt sind, berücksichtigt werden. So kann beispielsweise vorgesehen sein, dass der zeitlich als erster angeforderte Betrieb eines Verbrauchers dann auch in der Prioritätenliste ganz oben steht und dann auch als erster betrieben wird und mit zumindest anteiliger Energie aus der Anlagen-Energiemenge versorgt wird. Diese hier genannten möglichen Parameter zur Erstellung einer Prioritätenliste der gebäudezugeordneten Verbraucher sind nicht abschließend zu verstehen und es können selbstverständlich auch weitere Kriterien und Parameter berücksichtigt werden, um eine derartige Prioritätenliste aufzustellen.Furthermore, as a decision criterion, in addition to or instead of the criteria mentioned above, an operating priority list of the building-related consumers can be specified and taken into account. For example, as a parameter for such a prioritization, a user profile which is specified individually by a user and is set to his requirement profile can be taken into account. In addition, in addition to or instead of the priority list can also be based on the energy consumption of individual consumers, for example, the most energy-intensive has the highest priority. However, it can also be provided that the one with the lowest amount of energy consumption has the highest priority. The priority list may also be based on what security requirements are required for the operation of each consumer. For example, here the device that has the highest priority, which, once it has been started, must carry out its operation without interruption until the end of operation. As a further parameter for the priority list, for example, the order in which the requirements of the desired operations of several consumers have occurred in time, are taken into account. Thus, for example, it may be provided that the operation of a consumer which is first requested in terms of time is then also at the top of the list of priorities and then also operated first and supplied with at least partial energy from the plant's energy quantity. These possible parameters mentioned here for establishing a priority list of the building-associated consumers are not conclusive and, of course, further criteria and parameters can be taken into account in order to establish such a priority list.
Als weiteres Entscheidungskriterium kann ein im insbesondere zukünftigen Betrieb zu erwartender Energieverbrauch eines Verbrauchers und/oder ein im insbesondere zukünftigen Betrieb zu erwartender Energieverbrauch des gesamten Verbraucherverbunds berücksichtigt werden. Ist aufgrund des Anforderungsprofils bekannt, welche Verbraucher zukünftig betrieben werden sollen, und gegebenenfalls deren Betriebe aufgrund des nicht Übersteigens des Energiemenge-Schwellwerts durch die Anlagen-Energiemenge gegebenenfalls noch verzögert sind, so kann eine Verzögerungsverlängerungszeitdauer und/oder ein Abbruch der Verzögerung und/oder eine Laufzeitvorgabe und/oder eine Abgabe der Anlagen-Energiemenge in den Energiespeicher und/oder das öffentliche Energieversorgungsnetz abhängig von diesen Erwartungswerten erfolgen. Die durchzuführenden Betriebe sind anhand des von einem Nutzer direkt angeforderten Betriebs eines oder mehrerer Verbraucher und/oder auch von automatisch vorgegebenen, beispielsweise durch eine permanente Programmierung in einem Gebäudesystem, erforderlichen Betrieben von Verbrauchern mit dem jeweils zu erwartenden Energieverbrauch mit einem gewissen Wahrscheinlichkeitswert vorhersagbar. Im Hinblick auf die Bestimmung eines zu erwartenden Energieverbrauchs kann dies beispielsweise anhand einer Mittelwertbildung von mehreren vorhergehenden Betrieben eines spezifischen Verbrauchers und/oder des gesamten Verbraucherbunds erfolgen. Zusätzlich oder anstatt dazu kann dies beispielsweise jedoch auch nur anhand des letzten gespeicherten detektierten Betriebs eines Verbrauchers und/oder des Verbraucherverbunds erfolgen.As a further decision criterion, it is possible to take into account a consumer's energy consumption, which is to be expected in particular in future operation, and / or an energy consumption of the entire consumer group to be expected in particular in future operation. If, due to the requirement profile, it is known which consumers are to be operated in the future, and their operations may possibly still be delayed due to the energy quantity threshold being exceeded by the plant energy quantity, then a delay extension period and / or an interruption of the delay and / or a delay Runtime specification and / or a delivery of the system energy amount in the energy storage and / or the public power grid made depending on these expected values. The establishments to be carried out are predictable with a certain probability value on the basis of the operation of one or more consumers which is directly requested by a user and / or of automatically prescribed premises, for example by permanent programming in a building system, of consumers. With regard to the determination of an expected energy consumption, this can be done, for example, by averaging of several preceding operations of a specific consumer and / or of the entire consumer group. In addition or instead of this, for example However, only on the basis of the last stored detected operation of a consumer and / or the consumer group done.
Als weiteres separates Entscheidungskriterium kann auch die Anzahl der betriebenen Verbraucher und/oder der Energieverbrauch von Verbrauchern in einem vorgebbaren Zeitintervall vor dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge berücksichtigt werden. So kann dies durch eine Steuereinheit detektiert werden und beispielsweise innerhalb von einem Zeitintervall von Minuten oder aber auch bis hin zu einem Zeitintervall größer einer Stunde erkannt und abgeschätzt werden. Ist die Anzahl der betriebenen Verbraucher in diesem vorhergehenden Zeitintervall groß, so ist die zu erwartende Energiemenge nach dem Überschreiten des Energiemenge-Schwellwerts ebenfalls als relativ hoch einzuschätzen. Gegebenenfalls ist es dann sinnvoll eine weitere Verzögerung zumindest für einen der angeforderten Betriebe eine Verbrauchers durchzuführen. Hier kann dann natürlich selbstverständlich ebenfalls individuell abgewägt und entschieden werden, ob alle der angeforderten Betriebe der Verbraucher nochmals verzögert werden, oder ob dies für zumindest einen, aber nicht alle erfolgt. Auch hier können somit vielfältigste individuelle Szenarien über die Betriebsweise der angeforderten Betriebe von Verbrauchern erstellt und individuell optimal angepasst werden. Auch dadurch kann in äußerst flexibler variabler Weise die Erhöhung der Eigenverbrauchsquote beeinflusst werden.As a further separate decision criterion, the number of consumers operated and / or the energy consumption of consumers in a predeterminable time interval before the energy quantity threshold value is exceeded by the system energy quantity can also be taken into account. Thus, this can be detected by a control unit and detected and estimated, for example, within a time interval of minutes or even up to a time interval greater than one hour. If the number of operated consumers in this preceding time interval is large, then the expected amount of energy after exceeding the energy quantity threshold value is likewise to be estimated as relatively high. If appropriate, it then makes sense to carry out a further delay at least for one of the requested operations of a consumer. Of course, then, of course, can be individually weighed and decided here, whether all of the requested businesses, consumers are delayed again, or whether this is done for at least one, but not all. Here too, the most varied individual scenarios concerning the mode of operation of the requested businesses can thus be created by consumers and individually optimally adapted. This can also be used to influence the increase in the self-consumption rate in a highly flexible and variable manner.
Des Weiteren kann vorgesehen sein, dass ein Entscheidungskriterium eine zu erwartende Betriebsreihenfolge von Verbrauchern des Verbraucherverbunds berücksichtigt. Ist beispielsweise ein Anforderungsprofil für einen Betrieb einer Waschmaschine bekannt, so kann mit hoher Wahrscheinlichkeit davon ausgegangen werden, dass nach dem Betrieb der Waschmaschine gegebenenfalls auch ein Wäschetrockner betrieben wird. Diese Betriebswahrscheinlichkeit kann dann auch noch abhängig von weiteren Parametern gewichtet werden. So kann beispielsweise ein höheres Gewicht dieser möglichen Betriebsreihenfolge dann erfolgen, wenn es Abend ist und/oder die Jahreszeit Herbst, Winter oder Frühling ist. Dann wird die gewaschene Wäsche mit hoher Wahrscheinlichkeit nicht im Freien zum Trocknen gehängt, da sie dann nicht trocknet. Vielmehr wird dann die Wahrscheinlichkeit sehr hoch sein, dass dann zu diesen Tageszeiten und/oder Jahreszeiten die Wäsche nach dem Waschen in einen Wäschetrockner gegeben wird.Furthermore, it can be provided that a decision criterion takes into account the expected operating order of consumers of the consumer group. If, for example, a requirement profile for the operation of a washing machine is known, it can be assumed with a high degree of probability that, if appropriate, a tumble dryer will also be operated after the operation of the washing machine. This operating probability can then also be weighted depending on further parameters. For example, when it is evening and / or the season is autumn, winter or spring, a higher weight of this possible operating sequence can take place. Then, the washed laundry is most likely not hung outside to dry because it will not dry. Rather, then the probability will be very high that then at these times of the day and / or seasons, the laundry is given after washing in a tumble dryer.
Als weiteres Entscheidungskriterium kann vorgesehen sein, dass das Verhältnis von bereitstellbarer Anlagen-Energiemenge zu Bezugs-Energiemenge aus dem öffentlichen Energieversorgungsnetz zur Deckung des gesamten Energiemengenbedarfs eines zu betreibenden Verbrauchers berücksichtigt wird. Ist es nicht erforderlich, dass ein unverzüglicher Betrieb eines oder mehrerer Verbraucher unmittelbar nach dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge erfolgt, so kann dieser angeforderte Betrieb oder der unterbrochene Betrieb weiterhin verzögert werden, solange bis die Anlagen-Energiemenge größer ist und somit das Verhältnis größer ist. Auch dadurch kann dann die Eigenverbrauchsquote insbesondere dann gesteigert werden, wenn ein möglichst hoher Anteil der Anlagen-Energiemenge selbst verbraucht wird und nicht in das öffentliche Energieversorgungsnetz eingespeist wird.As a further decision criterion, provision may be made for the ratio of the amount of available plant energy to the amount of reference energy from the public energy supply network to be taken into account in order to cover the entire amount of energy required by a consumer to be operated. If it is not necessary for an immediate operation of one or more loads to occur immediately after exceeding the energy level threshold by the amount of plant energy, then such requested operation or interrupted operation may continue to be delayed until the amount of plant energy is greater and thus the ratio is greater. In this way too, the self-consumption quota can then be increased, in particular, if the highest possible proportion of the plant energy quantity itself is consumed and is not fed into the public energy supply grid.
Weitere spezifische Entscheidungskriterien können die Jahreszeit und/oder die Tageszeit sein. So kann üblicherweise davon ausgegangen werden, dass in Abend- und Nachzeiten der Energiebedarf des Verbraucherverbunds zurückgeht, da nicht mehr so viele Verbraucher betrieben werden oder betrieben werden müssen. Darüber hinaus kann durch die intelligente Steuerung erkannt werden, dass gerade bei Photovoltaik-Anlagen bei am späten Nachmittag oder in den Abendstunden angeforderten Betrieben von Verbrauchern diese Anlagen alsbald keine Anlagen-Energiemenge liefern werden, da dann, wenn die Sonne nicht scheint auch die Photovoltaik-Anlage sich selbst automatisch abschaltet. So kann hier im Zusammenhang vorgesehen sein, dass eine relativ lange Verzögerung des angeforderten Betriebs erfolgt, wenn es abends ist und/oder Herbst, Winter oder Frühling ist, und somit zu erwarten ist, dass die Anlagen-Energiemenge im weiteren Tagesverlauf sinken oder wenn bereits gegenwärtig keine Anlagen-Energiemenge mehr geliefert wird, auch dies auf absehbare Zeit nicht erfolgen wird.Other specific decision criteria may be the season and / or the time of day. Thus, it can usually be assumed that the energy requirements of the consumer network decline in the evenings and after-hours, since there are no longer so many consumers to operate or operate. In addition, it can be recognized by the intelligent control system that, especially in the case of photovoltaic systems, in the late afternoon or in the evening, consumer plants will soon supply no plant energy, since if the sun does not shine, then the photovoltaic Plant automatically shuts itself off. Thus, it may be provided in connection herewith that a relatively long delay of the requested operation takes place when it is evening and / or is autumn, winter or spring, and thus it is to be expected that the plant energy quantity will decrease later in the day or if already currently no more plant energy is delivered, even this will not happen for the foreseeable future.
Als weiteres Entscheidungskriterium kann auch der Ladezustand eines gebäudezugeordneten Energiespeichers, in den Anlagen-Energiemenge eingespeichert werden kann, berücksichtigt werden. Ist dieser relativ niedrig, so kann wiederum abhängig von einem oder mehreren der bereits oben genannten Entscheidungskriterien das Einspeichern einer Anlagen-Energiemenge in diesen Energiespeicher zumindest anteilig und/oder zeitabhängig erfolgen.As a further decision criterion, it is also possible to take into account the state of charge of a building-related energy store in which the system energy quantity can be stored. If this is relatively low, then in turn, depending on one or more of the decision criteria already mentioned above, the storage of an amount of plant energy into this energy store can take place at least proportionally and / or time-dependent.
Als weiteres Entscheidungskriterium können Leistungsdaten der Anlage berücksichtigt werden. Ist diese sehr großdimensioniert und kann somit innerhalb kurzer Zeit relativ viel Anlagen-Energiemenge produzieren und bereitstellen, so kann auch hier die Verzögerungsverlängerungszeit und/oder die Abbruchzeit und/oder die Laufzeit und/oder die Abgabe in den Speicher und/oder ein öffentliches Energieversorgungsnetz sehr bedarfsgerecht erfolgen.As a further decision criterion performance data of the plant can be considered. If this is very large and can thus produce and provide a relatively large amount of plant energy within a short time, then the delay extension time and / or the break time and / or the runtime and / or the discharge into the storage and / or a public power supply network can be very high be made according to demand.
Nicht zuletzt können auch weitere Daten zur Berücksichtigung als Entscheidungskriterien verwendet werden. Besonders interessant sind in diesem Zusammenhang meteorologische Daten für den geografischen Standort der Anlage, und dies insbesondere innerhalb eines vorgebbaren zukünftigen Zeitintervalls. Es ist gerade beispielsweise bei Photovoltaik-Anlagen sehr interessant, da dadurch ein möglicher Erwartungswert im Hinblick auf zukünftig zu erwartende Anlage-Energiemenge innerhalb eines Tages und/oder einer Woche vorhergesagt werden kann und auf Basis dieser Informationen dann ein intelligentes Betriebsszenario von angeforderten Betrieben eines oder mehrerer Verbraucher des Verbraucherverbunds gestaltet werden kann. Last but not least, other data can also be used for consideration as decision criteria. Particularly interesting in this context are meteorological data for the geographical location of the plant, and this in particular within a predeterminable future time interval. It is particularly interesting, for example, in photovoltaic systems, as a possible expectation can be predicted in terms of future expected amount of energy within a day and / or a week and based on this information then an intelligent operating scenario of requested operations of one or several consumers of the consumer group can be designed.
Des Weiteren kann als Entscheidungskriterium der Verlauf der Anlagen-Energiemenge in einem vorgebbaren Zeitintervall vor dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge berücksichtigt werden. Ist die aufgrund der Tageszeit und/oder der Jahreszeit und/oder einer gegebenen Wettersituation relativ flach ansteigend, so kann dies auch gegebenenfalls mit einer bestimmten Wahrscheinlichkeit für den Zeitverlauf nach dem Überschreiten des Energiemengen-Schwellwerts zugrundegelegt werden. Abhängig davon kann dann gegebenenfalls eine Verzögerungsverlängerung von einem oder mehreren der angeforderten Betriebe der Verbraucher sinnvoll sein. Andererseits kann dann, wenn ein relativ steiler Anstieg dieser Anlagen-Energiemenge vorliegt und darüber hinaus gegebenenfalls der Energiemengenspeicher relativ stark bereits aufgeladen ist, auch ein Abbruch der Verzögerung ohne die Verzögerungsverlängerung erfolgen. Auch die Laufzeiten können dadurch gegebenenfalls nach dem Starten und/oder nach dem Beenden der Unterbrechung verlängert werden.Furthermore, as a decision criterion, the course of the system energy quantity in a predefinable time interval before the energy quantity threshold value is exceeded by the system energy quantity can be taken into account. If, due to the time of day and / or the season and / or a given weather situation, it is relatively flat, this may also be based, if appropriate, on a certain probability over time after the energy quantity threshold has been exceeded. Depending on this, a delay extension of one or more of the requested consumer businesses may be useful. On the other hand, if there is a relatively steep increase in this amount of system energy and, moreover, if necessary, the energy quantity memory is already relatively heavily charged, also a termination of the delay without the delay extension. The transit times can also be extended if necessary after starting and / or after the termination of the interruption.
Insbesondere können des Weiteren als Entscheidungskriterien der Verlauf der Anlagen-Energiemenge in einem vorgebbaren Zeitintervall nach dem Überschreiten des Energiemengen-Schwellwerts und/oder Sicherheitsanforderungen an betriebene Verbraucher berücksichtigt werden.In particular, furthermore, the course of the system energy quantity in a predefinable time interval after exceeding the energy quantity threshold value and / or safety requirements for operated consumers can be taken into account as decision criteria.
Es ist explizit zu erwähnen, dass die beispielhaft genannten Entscheidungskriterien nicht abschließend zu verstehen sind und darüber hinaus auch weitere Entscheidungskriterien berücksichtigt werden können. Ein wesentlicher Aspekt ist auch darin zu sehen, dass für die Beurteilung eines Entscheidungskriteriums ein oder weitere mehrere der genannten Entscheidungskriterien berücksichtigt werden können, um das eben zu beurteilende Entscheidungskriterium bestärken oder abzuschwächen oder zu konkretisieren oder mit einem gewissen Wahrscheinlichkeitswert zu präzisieren. Insbesondere ist auch zu betonen, dass jedes genannte Entscheidungskriterium abhängig von weiteren genannten Entscheidungskriterien auch noch individuell gewichtet werden kann.It is to be explicitly mentioned that the exemplarily mentioned decision criteria are not to be understood conclusively and beyond that also further decision criteria can be considered. An essential aspect is also to be seen in the fact that for the assessment of a decision criterion one or more of the mentioned decision criteria can be taken into account in order to strengthen or mitigate the decision criterion to be judged, or to substantiate it or to specify it with a certain probability value. In particular, it should also be emphasized that each named decision criterion can also be weighted individually depending on further mentioned decision criteria.
Insbesondere ist auch zu erwähnen, dass der Energiemengen-Schwellwert variabel vorgegeben werden kann. Die Variabilität kann sich diskret oder auch kontinuierlich ergeben und es kann insbesondere auch automatisch gesteuert eine derartige Veränderung des Energiemengen-Schwellwerts erfolgen. Insbesondere erfolgt die variable Einstellung anhand zumindest einem der oben genannten Entscheidungskriterien.In particular, it should also be mentioned that the energy quantity threshold value can be set variably. The variability may arise discretely or continuously and, in particular, such a change in the energy quantity threshold value may also be automatically controlled. In particular, the variable setting is based on at least one of the above decision criteria.
Insbesondere dann, wenn vor dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge zumindest zwei Betriebe von Verbrauchern angefordert werden oder bereits gestartete Betriebe unterbrochen wurden, eines oder mehrere der genannten Entscheidungskriterien herangezogen wird, um die dann im Weiteren zu erfolgenden Betriebe in ihrer Reihenfolge und/oder in ihrer Energiemengenaufteilung und/oder im Hinblick auf ihre Laufzeiten entsprechend durchzuführen.In particular, if, before the energy quantity threshold value is exceeded, at least two plants are requested by consumers or already started plants have been interrupted, one or more of the mentioned decision criteria is used to order the plants to be subsequently performed in their order and / or in their energy distribution and / or in terms of their maturity.
Insbesondere wird vorgesehen, dass auch nach dem Starten und/oder dem Fortführen eines angeforderten Betriebs eines Verbrauchers nach dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge verschiedene Szenarien erfolgen können, wenn dann zeitlich nachfolgend die Anlagen-Energiemenge wieder unter den Energiemengen-Schwellwert fällt. So kann diesbezüglich einerseits vorgesehen sein, dass ein oder alle dann im Betrieb befindlichen Verbraucher ohne weitere Einschränkung fortgeführt werden und falls erforderlich, die jeweiligen Restenergiemengen, die zur Deckung der jeweiligen Gesamtmengenenergiebedarfe über das öffentliche Energieversorgungsnetz und/oder den Energiespeicher gedeckt werden.In particular, it is provided that even after the start and / or continuation of a requested operation of a consumer after exceeding the amount of energy threshold through the system energy amount different scenarios can be done, if then in time the system energy amount below the energy level threshold falls. Thus, on the one hand, provision can be made in this regard for one or all of the consumers then in operation to be continued without further restriction and, if necessary, for the respective residual energy quantities which are covered by the public energy supply network and / or the energy store in order to cover the respective total quantity energy requirements.
Es kann jedoch auch vorgesehen sein, dass dann, wenn ein oder mehrere der angeforderten Betriebe oder der unterbrochenen Betriebe nach dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge nur solange durchgeführt werden, bis die Anlagen-Energiemenge einen weiteren vorgebbaren Energiemengen-Schwellwert unterschreitet. Dieser zweite Energiemengen-Schwellwert wird insbesondere unterschiedlich zum ersten Energiemengen-Schwellwert festgelegt, insbesondere kleiner als dieser festgelegt. Er kann ebenso variabel geändert werden, wobei dies ebenfalls abhängig von einem oder mehreren Entscheidungskriterien, insbesondere der oben genannten Entscheidungskriterien, erfolgen kann.However, it can also be provided that, if one or more of the requested operations or the interrupted operations are exceeded only after the energy quantity threshold value is exceeded, then the system energy quantity falls below a further predefinable energy quantity threshold value , This second energy-quantity threshold value is determined in particular differently from the first energy-quantity threshold value, in particular set smaller than this. It can also be varied variably, and this can also be done depending on one or more decision criteria, in particular the above-mentioned decision criteria.
In einer besonders vorteilhaften und hervorzuhebenden Ausführung wird vorgesehen, dass das automatisch gesteuerte Verzögern zumindest eines angeforderten Betriebs des Verbrauchers nutzerspezifisch verhindert oder beendet werden kann. Ist in dem Zusammenhang beispielsweise vorgesehen, dass ein Nutzer den Betrieb zumindest eines spezifischen Verbrauchers anfordert oder wünscht, ist zum gegenwärtigen Zeitpunkt jedoch die Anlagen-Energiemenge, die geliefert werden kann, kleiner als der vorgebbare Energiemengen-Schwellwert, so würde zunächst dieser angeforderte Betrieb verzögert werden. Ist dies dem Nutzer in dieser Situation nicht Recht und möchte er dennoch ein unverzügliches Starten oder Beenden eines unterbrochenen Betriebs des zumindest einen Verbrauchers, so kann er dies anfordern. Insbesondere kann er dabei durch entsprechende Eingabe in einer Steuereinrichtung diese Verzögerung verhindern oder beenden und es erfolgt dann ein unverzügliches Starten oder Beenden der Unterbrechung des Betriebs des gewünschten Verbrauchers. Dies erfolgt selbst dann auch, wenn die erforderliche Energiemenge für den Betrieb des Verbrauchers vollständig aus dem öffentlichen Energieversorgungsnetz bezogen werden muss.In a particularly advantageous and emphasized embodiment, it is provided that the automatically controlled delay at least one requested operation of the consumer user-specific prevented or terminated. For example, in the context where, for example, a user requests or wishes to operate at least one specific consumer, but at the present time the amount of plant energy that can be delivered is less than the predetermined amount of energy threshold, then this requested operation would initially be delayed become. If this is not the user's right in this situation and he still wants an immediate start or stop of an interrupted operation of the at least one consumer, he may request this. In particular, he can prevent or terminate this delay by appropriate input in a control device and then there is an immediate start or stop the interruption of the operation of the desired consumer. This is done even if the required amount of energy for the operation of the consumer must be obtained completely from the public power grid.
Vorzugsweise wird das nutzerspezifische Verhindern oder Unterbrechen momentan situationsspezifisch durch den Nutzer durchgeführt. Alternativ kann jedoch auch vorgesehen sein, dass der Nutzer für eine bestimmte Tageszeit und/oder einen bestimmten Verbraucher und/oder eine bestimmte Zeitdauer die Verhinderung vorgibt und dies solange automatisch gesteuert beibehalten wird, bis der Nutzer diese programmierte Vorgabe ändert. Möchte beispielsweise ein Nutzer, dass zwischen 17 und 19 Uhr eines jeden Tages der Betrieb eines spezifischen Verbrauchers, beispielsweise einer Waschmaschine, unverzögert durchgeführt wird, so kann er dies entsprechend programmieren. Jeden Tag wird dann automatisch geprüft, ob während dieser Zeitdauer die Waschmaschine betrieben und von einem Nutzer eingeschaltet wird. Ist dies der Fall und kann dann beispielsweise zumindest anteilig der Energiebedarf durch die Anlagen-Energiemenge gedeckt werden, so wird dies durchgeführt. Dies auch dann, wenn die Anlagen-Energiemenge kleiner als der Energiemengen-Schwellwert ist. Wird in dieser Zeitdauer die Waschmaschine von einem Benutzer eingeschaltet und liefert die Anlage überhaupt keine Anlagen-Energiemengen, so wird dann auch unverzüglich der Verbraucher gestartet und über das Energieversorgungsnetz mit Energie versorgt.Preferably, the user-specific prevention or interruption is currently performed situation-specific by the user. Alternatively, however, it can also be provided that the user prescribes the prevention for a certain time of day and / or a specific consumer and / or a certain period of time and this is maintained automatically controlled until the user changes this programmed specification. For example, if a user wishes to have instantaneous operation of a specific consumer, such as a washing machine, between 17:00 and 19:00 each day, he may program this accordingly. Every day it is then automatically checked whether during this period the washing machine is operated and turned on by a user. If this is the case and can then be covered, for example, at least proportionally, the energy requirement by the plant's energy amount, this is done. This also applies if the system energy quantity is smaller than the energy quantity threshold value. If the washing machine is turned on by a user during this period and the system does not deliver any system energy amounts at all, then the consumer is also started immediately and supplied with energy via the energy supply network.
In besonders vorteilhafter Weise ist vorgesehen, dass der Energiemengen-Schwellwert auf den Wert Null festgelegt wird. Immer dann, wenn die Photovoltaik-Anlage sich aufgrund des nicht vorhandenen Sonnenlichts selbst automatisch abschaltet und somit keine elektrische Energie erzeugt, ist das oben genannte von besonderer Vorteilhaftigkeit. Denn dann kann nicht einmal ein geringer Anteil durch die Anlage selbst erzeugt werden und es muss quasi alles aus dem öffentlichen Energieversorgungsnetz geholt werden. Dies insbesondere dann, wenn auch ein möglicherweise vorhandener gebäudezugeordneter Energiespeicher leer ist oder nur einen geringen Energiemengenanteil liefern kann.In a particularly advantageous manner, it is provided that the energy quantity threshold value is set to the value zero. Whenever the photovoltaic system shuts itself off automatically due to the absence of sunlight and thus does not generate electrical energy, the above-mentioned is of particular advantage. Because then not even a small amount can be generated by the system itself and it must be brought almost everything from the public power grid. This is especially true if a possibly existing building-assigned energy storage is empty or can deliver only a small amount of energy.
Besonders vorteilhaft ist es, wenn der Verbraucherverbund einen Heizstab zum Erwärmen von Wasser in einem Warmwasser-Pufferspeicher und/oder zumindest ein Haushaltsgerät zur Pflege von Wäschestücken und/oder zumindest einen Geschirrspüler aufweist. Hausgeräte zur Pflege von Wäschestücken sind insbesondere ein Wäschetrockner und eine Waschmaschine. Ihre genannten spezifischen elektrischen Verbraucher sind im Hinblick auf den Energiebedarf und den Betriebsweisen sehr spezifische Verbraucher. Sie können gerade im Hinblick auf variable Betriebsweise mit gegebenenfalls vorhandenen Möglichkeiten einer zeitverschobenen Betriebsweise die Erfindung sehr positiv im Hinblick auf die Erhöhung der Eigenverbrauchsquote beeinflussen.It is particularly advantageous if the consumer group has a heating rod for heating water in a hot water storage tank and / or at least one domestic appliance for the care of laundry items and / or at least one dishwasher. Domestic appliances for the care of laundry items are in particular a clothes dryer and a washing machine. Their specified specific electrical loads are very specific consumers in terms of energy requirements and operating modes. With regard to the variable mode of operation with possibly existing possibilities of a time-shifted mode of operation, they can influence the invention very positively with regard to increasing the self-consumption rate.
Prinzipiell können jedoch alle beispielsweise gebäudezugeordneten elektrischen Verbraucher, die quasi als private Verbraucher vorgesehen sind, und auch nicht anderen externen Kreisen zur Verfügung gestellt werden sollen, berücksichtigt werden. Insbesondere können an dieser Stelle weitere Haushaltsgeräte einer Wohneinheit oder Gewerbeeinheit berücksichtigt werden. Beispielsweise kann dies auch eine Beleuchtungsanlage für eine Außenbeleuchtung oder dergleichen, die zeitgesteuert betrieben werden kann, umfassen.In principle, however, all, for example, building-related electrical consumers, which are intended to be provided as private consumers, and should not be made available to other external circles, are taken into account. In particular, other household appliances of a residential unit or commercial unit can be considered at this point. For example, this may also include a lighting system for outdoor lighting or the like, which can be operated in a time-controlled manner.
Des Weiteren betrifft die Erfindung eine Vorrichtung zum Bereitstellen von elektrischer Energie an einen gebäudezugeordneten Verbraucherverbund mit zumindest einem elektrischen Verbraucher. Die Vorrichtung umfasst den Verbraucherverbund und umfasst darüber hinaus eine gebäudezugeordnete Anlage, welche zur Erzeugung von elektrischer Energie aus regenerativer Energie ausgebildet ist. Die erzeugte elektrische Energie ist zumindest anteilig in ein öffentliches und nicht gebäudezugeordnetes Energieversorgungsnetz einspeisbar. Ein elektrischer Verbraucher ist durch die Anlage und/oder das Energieversorgungsnetz mit elektrischer Energie versorgbar. Die Vorrichtung umfasst eine erfindungsgemäße Steuereinrichtung oder eine vorteilhafte Ausgestaltung davon. Insbesondere ist die Vorrichtung auch zur Durchführung eines erfindungsgemäßen Verfahrens oder einer vorteilhaften Ausgestaltung davon ausgebildet. So kann vorgesehen sein, dass die Vorrichtung eine Messeinheit umfasst, mit der die momentan bereitstellbare elektrische Anlagen-Energiemenge der Anlage erfassbar bzw. messbar ist. Darüber hinaus kann die Vorrichtung eine weitere Messeinheit aufweisen, mit der die momentan erforderliche elektrische Verbraucher-Energiemenge des gebäudezugeordneten Verbraucherverbunds erfassbar ist. Vorzugsweise können diese Messeinheiten mit der Steuereinrichtung elektrisch verbunden sein, so dass sie zur Signalübertragung kommunizieren können. Die von den Messeinheiten erhaltenen Signale können dann durch die Steuereinrichtung ausgewertet und verarbeitet werden.Furthermore, the invention relates to a device for providing electrical energy to a building-associated consumer network with at least one electrical consumer. The device comprises the consumer network and moreover comprises a building-associated system, which is designed to generate electrical energy from regenerative energy. The electrical energy generated is at least partially fed into a public and not building-related energy supply network. An electrical load is supplied by the system and / or the power grid with electrical energy. The device comprises a control device according to the invention or an advantageous embodiment thereof. In particular, the device is also designed for carrying out a method according to the invention or an advantageous embodiment thereof. Thus, it can be provided that the device comprises a measuring unit, with which the currently available electrical system energy amount of the system can be detected or measured. In addition, the device may have a further measuring unit, with which the currently required amount of electrical consumer energy of building associated consumer group is detectable. Preferably, these measuring units can be electrically connected to the control device, so that they can communicate for signal transmission. The signals received by the measuring units can then be evaluated and processed by the control device.
Vorzugsweise ist die Anlage eine Photovoltaik-Anlage. Sie kann beispielsweise auf einem Dach eines Wohngebäudes oder an einer Außenwand des Wohngebäudes oder auch auf Freiflächen, wie beispielsweise in einem Garten oder in einer externen Wiese angeordnet sein. Die Gebäudezuordnung bedeutet in diesem Zusammenhang, dass die von der Anlage erzeugte elektrische Energie nur Verbrauchern dieses gebäudezugeordneten Verbraucherverbunds bereitstellt oder die erzeugte elektrische Energie in einem gebäudezugeordneten Energiespeicher zwischenspeichert oder in ein öffentliches Energieversorgungsnetz einspeist.Preferably, the plant is a photovoltaic system. It may for example be arranged on a roof of a residential building or on an outer wall of the residential building or on open spaces, such as in a garden or in an external meadow. In this context, the building allocation means that the electrical energy generated by the plant only provides consumers of this building-related consumer group or temporarily stores the generated electrical energy in a building-assigned energy store or feeds it into a public energy supply grid.
Die Vorrichtung umfasst vorzugsweise eine Mehrzahl von Photovoltaik-Modulen. Die genannten Messeinheiten sind insbesondere Stromwandlereinheiten. Vorzugsweise werden diese Stromwandler direkt nach einem Wechselrichter der Vorrichtung angeordnet und eingebaut. Vorzugsweise werden diese Stromwandler vor einem Eigenverbrauchszähler, der somit den Anteil des Eigenverbrauchs der von der Anlage erzeugten elektrischen Energie durch gebäudezugeordnete Verbraucher erfasst, angeordnet. Vorzugsweise sind weitere Stromwandler zur Verbrauchserfassung und somit zur Erfassung des momentanen Verbraucher-Energiebedarfs durch den Verbraucherverbund angeordnet. Diese werden vorzugsweise nach dem Strombezugszähler montiert.The device preferably comprises a plurality of photovoltaic modules. The measuring units mentioned are in particular current transformer units. Preferably, these current transformers are arranged and installed directly after an inverter of the device. These current transformers are preferably arranged in front of a self-consumption counter, which thus detects the proportion of self-consumption of the electrical energy generated by the system by building-associated consumers. Preferably, further current transformer for consumption detection and thus for detecting the current consumer energy demand by the consumer network are arranged. These are preferably mounted after the power reference meter.
Die Steuereinrichtung kann darüber hinaus insbesondere auch eine Vergleichereinheit aufweisen, mittels der die momentane elektrische Anlagen-Energiemenge der Anlage und die momentan erforderliche elektrische Verbraucher-Energiemenge des gebäudezugeordneten Verbraucherverbunds verglichen werden. Insbesondere dann, wenn in diesem Zusammenhang ein Überschuss an Energie vorhanden ist und somit die Anlagen-Energiemenge größer als die erforderliche elektrische Verbraucher-Energiemenge ist, wird vorzugsweise der gesamte Bedarf der Verbraucher-Energiemenge durch die Anlagen-Energiemenge gedeckt.In addition, the control device can in particular also have a comparator unit, by means of which the instantaneous electrical system energy quantity of the system and the currently required electrical consumer energy quantity of the building-associated consumer network are compared. In particular, if in this context an excess of energy is present and thus the system energy amount is greater than the required amount of electrical consumer energy, preferably the entire demand of the consumer energy amount is covered by the system energy.
Besonders vorteilhaft ist es, dass die Erfassung der elektrischen Anlagen-Energiemenge und/oder die Erfassung der momentan erforderlichen elektrischen Verbraucher-Energiemenge nach bestimmten Zeitintervallen durchgeführt wird und somit in diskreten Zeitabständen erfolgt. Diese können kleiner zehn Sekunden sein, insbesondere in Abständen von fünf Sekunden erfolgen.It is particularly advantageous that the detection of the electrical system energy quantity and / or the detection of the currently required amount of electrical consumer energy is carried out after certain time intervals and thus takes place at discrete time intervals. These can be less than ten seconds, especially at intervals of five seconds.
Bei symmetrisch aufgebauten Anlagen wird auf jeder Phasenleitung der gleiche Strom erzeugt. Dadurch können Stromwandler eingespart werden. Dafür muss in der Steuereinrichtung auf einem spezifischen Modul A1. M2 eine Brücke von der Klemme
Vorzugsweise ist vorgesehen, dass zur Erhöhung der Stabilität des Systems ein ausschaltverzögerndes Zeitrelais vorgesehen ist, bei dem die Zeitverzögerung insbesondere im Minutenbereich, vorzugsweise fünf Minuten beträgt. Dies verhindert gerade bei Wettersituationen, bei denen am Himmel Wolken vorbeiziehen, ein häufiges Schalten der elektrischen Verbraucher.It is preferably provided that to increase the stability of the system, a time delay relay is provided, in which the time delay, in particular in the minute range, preferably five minutes. This prevents frequent switching of electrical consumers, especially in weather situations where clouds pass by in the sky.
Vorzugsweise umfasst die Steuereinrichtung eine Anzeigeeinheit, auf der eine Vielzahl von Informationen für einen Nutzer darstellbar sind. In diesem Zusammenhang sind die Informationen bezüglich der momentanen Anlage-Energiemenge und/oder der momentanen Verbraucher-Energiemenge und/oder der gegenwärtig vorliegenden Anforderungen von Betrieben von elektrischen Verbrauchern des Verbraucherverbunds und/oder momentan tatsächlich durchgeführte und ablaufende Energie verbrauchende Betriebe der Verbraucher und/oder Informationen über eine zu erwartende Verzögerungszeit und/oder der prozentuale Anteil der Anlagen-Energiemenge an der Gesamtenergiemenge eines momentan ablaufenden Betriebs eines Verbrauchers anzeigbar.Preferably, the control device comprises a display unit on which a plurality of information can be displayed for a user. In this context, the information relating to the current amount of installation energy and / or the current amount of consumer energy and / or the currently available requirements of operations of consumers of electrical consumers of the consumer group and / or currently actually performed and running energy consuming operations of consumers and / or Information about an expected delay time and / or the percentage of the system energy amount of the total amount of energy of a current running operation of a consumer displayable.
Vorzugsweise ist vorgesehen, dass der Heizstab für die Aufheizung des Wassers in dem Warmwasser-Pufferspeicher in vertikaler Richtung betrachtet in etwa auf halber Höhe des Gesamtvolumens angeordnet ist. Vorzugsweise kann damit erreicht werden, dass in etwa die Hälfte des in dem Pufferspeicher enthaltenen Wassers allein durch den Heizstab aufheizbar ist.Preferably, it is provided that the heating element for heating the water in the hot water storage tank in the vertical direction is arranged approximately at half the height of the total volume. Preferably, it can thus be achieved that approximately half of the water contained in the buffer memory can be heated by the heating element alone.
In besonders vorteilhafter Weise wird dabei der Betrieb des Heizstabs durch die Steuereinrichtung derart gesteuert, dass wenn immer möglich der Heizstab geheizt wird und somit immer wieder ein zusätzliches Zwischenheizen des Warmwassers erfolgt. Damit kann in ganz besonders effizienter Weise ein sehr energiesparendes Aufheizen einerseits erreicht werden. Denn immer dann, wenn Anlage-Energiemenge zur Verfügung steht, wird zumindest für kurze Zeit der Heizstab betrieben, und somit wieder eine entsprechende, wenn auch nur geringfügige Erwärmung des Wassers in dem Pufferspeicher erzielt. Dies trägt in besonders vorteilhafter Weise dazu bei, dass kein unerwünschtes zu starkes Absinken der Temperatur des Wassers in dem Pufferspeicher auftritt und nicht nachfolgend, gerade bei sehr großen Pufferspeichern, ein sehr energieineffizientes und lang andauerndes Erwärmen des Wasserspeichers auf einen gewünschten Temperaturwert mittels einer zusätzlichen Kesselanlage, beispielsweise einer Pellet-Heizung oder einer Gas-Heizung oder einer Öl-Brennwert-Heizung oder sonstigen Heizungen, erfolgen muss. Ein sehr großer Energiebedarf über das öffentliche Energieversorgungsnetz ist dadurch vermeidbar.In a particularly advantageous manner, the operation of the heating element is controlled by the control device such that whenever possible, the heating element is heated and thus takes place again and again an additional intermediate heating of the hot water. This can be achieved in a particularly efficient way, a very energy-efficient heating on the one hand. For whenever the amount of plant energy is available, the heating element is operated at least for a short time, and thus again a corresponding, albeit only slight, heating of the water in the buffer memory is achieved. This contributes in a particularly advantageous manner to the fact that no unwanted too strong drop in the temperature of the water in the Buffer occurs and not below, especially in very large buffers, a very energy-inefficient and long-lasting heating of the water storage to a desired temperature value by means of an additional boiler system, such as a pellet heater or a gas heater or an oil condensing heating or other heaters , must be done. A very large energy requirement via the public power grid can be avoided.
In besonders vorteilhafter Weise kann vorgesehen sein, dass abhängig von der Temperatur des Wassers in dem Pufferspeicher der Betrieb des Heizstabs mit größerer Priorität versehen wird und dadurch die Position des Heizstabs in einer gegebenenfalls vorhandenen Prioritätenliste der elektrischen Verbraucher ansteigt. Es kann darüber hinaus auch vorgesehen sein, dass dann, wenn die Temperatur im Warmwasserspeicher unter einen vorgebbaren Schwellwert sinkt und bis dahin keine Anlage-Energiemenge dem Heizstab zur Verfügung gestellt werden kann, dieser dann auch zumindest zeitweise mit Energie aus dem Energiespeicher und/oder dem öffentlichen Energieversorgungsnetz betrieben wird.In a particularly advantageous manner, it may be provided that, depending on the temperature of the water in the buffer memory, the operation of the heating element is provided with greater priority, thereby increasing the position of the heating element in an optional priority list of electrical consumers. In addition, it can also be provided that when the temperature in the hot water tank drops below a predefinable threshold value and until then no amount of system energy can be made available to the heating element, this then at least temporarily with energy from the energy storage and / or public power grid is operated.
Insbesondere dann, wenn die Anlagen-Energiemenge größer als die momentan erforderliche elektrische Verbraucher-Energiemenge ist, wird der Heizstab automatisch eingeschaltet. Dies erfolgt insbesondere aber jedoch nur dann, wenn die Temperatur im Warmwasserspeicher einen vorgebbaren oberen Temperaturschwellwert noch nicht überschritten hat.In particular, when the system energy amount is greater than the currently required amount of electrical consumer energy, the heating element is automatically turned on. However, this is done in particular but only if the temperature in the hot water tank has not exceeded a predetermined upper temperature threshold.
Vorzugsweise erfolgt die Abschaltung des Heizstabs zeitverzögert, beispielsweise mit einer Zeitverzögerung im Minutenbereich, insbesondere etwa mit einer Minute. Dadurch wird erreicht, dass bei kurzzeitigen Stromspitzen in dem Verbraucherverbund der Heizstab auch laufend ein- und wieder ausgeschaltet werden kann.Preferably, the shutdown of the heating element takes place with a time delay, for example with a time delay in the minute range, in particular approximately one minute. This ensures that at short-term peak currents in the consumer group, the heating element can also be switched on and off again.
Gerade bei den oben genannten beispielhaften Haushaltsgeräten des Geschirrspülers und der Waschmaschine wird die Steuerung so vorgenommen, dass die Geräte, wenn sie in Betrieb genommen wurden, nicht mehr unterbrochen werden, sondern bis zum Ende fortgeführt werden. Dies erfolgt dann unabhängig, ob nach dem Betriebsbeginn der elektrische Energiebedarf ausschließlich durch die Anlagen-Energiemenge abgedeckt wird oder zumindest anteilig durch Energie aus dem öffentlichen Energieversorgungsnetz gedeckt wird. Dies ist dahingehend vorteilhaft, da gerade bei diesen Geräten eine Unterbrechung des bereits gestarteten Betriebs wenig energieeffizient wäre, da bei einer Unterbrechung das bereits aufgeheizte Wasser sich wieder abkühlen würde und bei dann Fortfahren des Betriebs nach der Unterbrechung dieses Wasser erst einmal wieder aufgeheizt werden müsste.Especially in the above exemplary household appliances of the dishwasher and the washing machine, the control is made so that the devices, when they were put into operation, are no longer interrupted, but continued to the end. This then takes place independently, whether after the start of operation of the electrical energy demand is covered exclusively by the system energy amount or at least partially covered by energy from the public power grid. This is advantageous in that just with these devices interruption of the already started operation would be less energy efficient, since in an interruption, the already heated water would cool down again and then continue to be heated again after the operation of the interruption of this water.
Vorzugsweise ist vorgesehen, dass bei einem benutzerdefinierten Beenden oder Unterbrechen einer Verzögerung des Betriebs eines Verbrauchers diese Deaktivierung der Verzögerung um eine vorgebbare Zeitdauer erfolgt. Diese kann benutzerindividuell vorgegeben werden. Vorzugsweise beträgt dies dann mehrere Stunden, beispielsweise drei Stunden. Vorzugsweise ist vorgesehen, dass diese Deaktivierung der Verzögerungsfunktion für zumindest eines der nachfolgend zu betreibenden Geräte bzw. Verbraucher durch eine Zählereinheit gezählt wird. Diese Information kann dann ebenfalls im Weiteren zur Steuerung der elektrischen Verbraucher berücksichtigt werden.It is preferably provided that in the case of a user-defined termination or interruption of a delay in the operation of a consumer, this deactivation of the delay takes place by a predefinable time duration. This can be specified user-individually. This is preferably several hours, for example three hours. It is preferably provided that this deactivation of the delay function for at least one of the devices or consumers to be subsequently operated is counted by a counter unit. This information can then also be taken into account for controlling the electrical consumers.
Des Weiteren ist vorzugsweise vorgesehen, dass in der Vorrichtung ein Zwei-Tarif-Zähler für Tag- und Nachtstrom eingesetzt ist. Vorzugsweise wird dann ein potenzialfreier Kontakt für die Nachtstromzeit auf die Steuerung aufgeschaltet. In diesem Zeitraum werden dann die Steckdosen für spezifische elektrische Verbraucher, insbesondere Waschmaschine, Geschirrspüler und Wäschetrockner freigegeben. Dadurch werden die Geräte mit dem vergünstigten Nachtstrom betrieben, wenn dies gewünscht ist. Ist ein derartiger Betrieb in den Nachtzeiten nicht zwingend erforderlich, so kann auch nach Betriebsanforderung eine entsprechende Verzögerung bis zum nächsten Tag erfolgen, indem dann gegebenenfalls wiederum durch die Anlage elektrische Energie erzeugt wird und dann die Anlagen-Energiemenge zum Betrieb der genannten Geräte bereitgestellt wird.Furthermore, it is preferably provided that in the device, a two-tariff counter for day and night power is used. Preferably, then a potential-free contact for the night time is switched to the control. During this period, the sockets are then released for specific electrical consumers, in particular washing machine, dishwasher and tumble dryer. As a result, the devices are operated with the discounted night current, if desired. If such operation is not absolutely necessary during the night, a corresponding delay can also be made according to the operation request until the next day, in which case electrical energy is again generated, if appropriate, by the installation and then the system energy amount is provided for the operation of the devices mentioned.
Die Steuereinrichtung weist Mittel, insbesondere Einheiten auf, mit den alleine oder in Zusammenwirken von mehreren Einheiten die oben genannten Abläufe steuerbar sind.The control device has means, in particular units, with which alone or in cooperation of a plurality of units, the above-mentioned sequences are controllable.
Weitere Merkmale der Erfindung ergeben sich aus den Ansprüchen, den Figuren und der Figurenbeschreibung. Die vorstehend in der Beschreibung genannten Merkmale und Merkmalskombinationen, also auch die in den Figuren alleine gezeigten Merkmale und Merkmalskombinationen und/oder die nur in der Figurenbeschreibung genannten Merkmale und Merkmalskombinationen, sind nicht nur in der jeweils angegebenen Kombination, sondern auch in anderen Kombinationen oder in Alleinstellung verwendbar, ohne den Rahmen der Erfindung zu verlassen.Further features of the invention will become apparent from the claims, the figures and the description of the figures. The features and feature combinations mentioned above in the description, and thus also the features and feature combinations shown in the figures alone and / or the features and feature combinations mentioned only in the figure description, are not only in the respectively specified combination, but also in other combinations or in Used alone, without departing from the scope of the invention.
Insbesondere die sehr große Variabilität und Flexibilität der Kombinationsmöglichkeiten der genannten Entscheidungskriterien weist für sich alleine betrachtet also auch für die Berücksichtigung von einem Entscheidungskriterium oder mehreren Entscheidungskriterien zur Beurteilung eines oder mehrerer anderer Entscheidungskriterien und somit final für die Entscheidung, wann ein angeforderter Betrieb oder mehrere angeforderte Betriebe eines oder mehrerer Verbraucher vollständig durchgeführt wird, insbesondere unter Berücksichtigung der Anlagen-Energiemenge, eine große Szenarienoptionalität auf, wodurch eine sehr detaillierte und präzisierte Steuerung zur Steigerung der Eigenverbrauchsquote ermöglicht ist.In particular, the very large variability and flexibility of the combination possibilities of the mentioned decision criteria, taken on its own, thus also means that one or more decision criteria are taken into account for the evaluation of one or more decision criteria a plurality of other decision criteria, and thus final for deciding when a requested operation or multiple requested operations of one or more consumers will be fully implemented, particularly taking into account the amount of plant power, a large scenario option, thus providing very detailed and precise control to increase the self-consumption rate is possible.
Es kann vorgesehen sein, dass die Anzahl und/oder welche der Entscheidungskriterien und/oder in welcher Reihenfolge Entscheidungskriterien für die Beurteilung eines anderen Entscheidungskriteriums berücksichtigt werden, variabel ist. Insbesondere kann dies vom zu beurteilenden Entscheidungskriterium selbst und/oder von der, insbesondere momentanen, Anlagen-Energiemenge und/oder der, insbesondere momentanen, Verbraucher-Energiemenge und/oder vom, insbesondere momentanen, Energiemengen-Schwellwert und/oder von einem oder mehreren der vorhergehenden Werte oder Aussagen dieses zu beurteilenden Entscheidungskriteriums abhängig sein. Die Beurteilung erfolgt dabei im Hinblick auf eine Verzögerungsverlängerung und/oder eine Laufzeitbestimmung und/oder einen Verzögerungsabbruch und/oder eine Energieabgabe in den Speicher und/oder das öffentliche Netz. Es kann vorgesehen sein, dass abhängig von einem oder mehreren berücksichtigten anderen Entscheidungskriterien die Beurteilung eines Entscheidungskriteriums in eine spezifischen Szenario dazu führt, dass die Verzögerung verlängert wird und in einem anderen unterschiedlichen Szenario die Verzögerung nicht verlängert wird. Entsprechendes kann für die Abbruchentscheidung und/oder die Laufzeitentscheidung und/oder die Abgabeentscheidung möglich sein.It can be provided that the number and / or which of the decision criteria and / or in which order decision criteria are taken into account for the evaluation of another decision criterion is variable. In particular, this can be determined by the decision criterion to be assessed itself and / or by the, in particular momentary, amount of plant energy and / or the, in particular instantaneous, amount of consumer energy and / or by, in particular momentary, energy quantity threshold value and / or one or more of previous values or statements of this decision criterion to be assessed. The assessment is carried out with regard to a delay extension and / or a runtime determination and / or a delay termination and / or an energy release in the memory and / or the public network. It may be provided that, depending on one or more other decision criteria considered, the evaluation of one decision criterion in a specific scenario results in the delay being extended and in another different scenario the delay is not prolonged. The same can be possible for the termination decision and / or the runtime decision and / or the delivery decision.
Ausführungsbeispiele der Erfindung werden nachfolgend anhand schematischer Zeichnungen näher erläutert. Es zeigen:Embodiments of the invention are explained in more detail below with reference to schematic drawings. Show it:
In den Figuren werden gleiche oder funktionsgleiche Elemente mit den gleichen Bezugszeichen versehen.In the figures, identical or functionally identical elements are provided with the same reference numerals.
In
Im Ausführungsbeispiel umfasst der gebäudezugeordnete Verbraucherverbund
Der Heizstab
Die Vorrichtung
Die Steuereinrichtung
Die Steuereinheit
Die Steuereinrichtung
Die Steuereinrichtung
Die Vorrichtung
Vorzugsweise ist vorgesehen, dass die Messeinheiten
Die Vorrichtung
Im Hinblick auf das vereinfachte Blockbild in
Beispielhaft sind auf der Leitungsverbindung zur Waschmaschine
Im Ausführungsbeispiel gemäß der Darstellung in
Dies bedeutet, dass damit diejenige Quote des von der Photovoltaik-Anlage
Der Eigenverbrauchs-Zähler
Im Hinblick auf die Ausgestaltung der Steuereinrichtung
Des Weiteren weist die Steuereinrichtung
Beispielhafte Funktionsszenarien der Vorrichtung
Ausgehend von der beispielhaften Diagrammdarstellung wird zum Zeitpunkt t0 von einem Nutzer der Betrieb der Waschmaschine
Im Ausführungsbeispiel ist vorgesehen, dass der Energiemengen-Schwellwert gleich Null ist. Dies bedeutet, dass zum Zeitpunkt t0 der Anlagen-Energiemengenwert nicht größer ist als dieser Energiemengen-Schwellwert, so dass zunächst automatisch gesteuert über die Steuereinrichtung
Im Hinblick auf diese doch sehr lange Verzögerungszeitdauer, die sich von einem Abend bis zum nächsten Morgen des nachfolgenden Tages erstrecken kann, kann auch vorgesehen sein, dass die Verzögerung des angeforderten Betriebs der Waschmaschine
Darüber hinaus kann auch vorgesehen sein, dass über die Steuereinrichtung
Wird der Betrieb der Waschmaschine
Besonders vorteilhaft ist es in diesem Zusammenhang jedoch, wenn bis zum Zeitpunkt t1 mit dem Starten des Betriebs der Waschmaschine
Es kann jedoch auch vorgesehen sein, dass der Betrieb der Waschmaschine
Gemäß einem weiteren Szenario ist in der Darstellung gemäß
Zum Zeitpunkt t2 wird dann der Betrieb eines elektrischen Verbrauchers, beispielsweise der Waschmaschine
Alternativ kann jedoch auch vorgesehen werden, dass auch zum Zeitpunkt t2 der Betrieb der Waschmaschine
Zum Zeitpunkt t3 wird ein weiterer elektrischer Verbraucher, beispielsweise der Heizstab
Zum Zeitpunkt t4 wird zusätzlich zum ablaufenden Betrieb der Waschmaschine
Es kann jedoch auch vorgesehen sein, dass der Betrieb des Heizstabs
Alternativ könnte zum Zeitpunkt t4 vorgesehen sein, dass auch gleich der Betrieb des Geschirrspülers
Wie aus dem beispielhaften Szenario in
Es kann jedoch auch vorgesehen sein, dass zum Zeitpunkt t6 der Betrieb des Heizstabs
Zum Zeitpunkt t7 wird dann im Wesentlichen gleichzeitig der Geschirrspüler
Zum Zeitpunkt t11 geht der Wert der Anlagen-Energiemenge gegen den Wert Null und die Photovoltaik-Anlage
Es kann auch vorgesehen sein, dass in einem Zeitfenster irgendwo zwischen den Zeitpunkten t11 und t13 umfassend den Zeitpunkt t12 der Nutzer für jeden Tag in der Steuereinrichtung
Zurückkehrend zum Zeitpunkt t7 kann beispielsweise vorgegeben werden, für wie lange des gestarteten Betriebs des Wäschetrockners
Gemäß der vorliegenden Erläuterung, bei der der Wäschetrockner
Bedarfsgerecht und anteilig kann auch die Beleuchtungsvorrichtung
Besonders vorteilhaft ist das erfindungsgemäße Verfahren und eine vorteilhafte Ausgestaltung davon, wenn die Photovoltaik-Anlage
Im Hinblick auf die Entscheidungskriterien kann dabei die Anzahl der Verbraucher eines gebäudezugeordneten Verbraucherverbunds und/oder die Gesamtenergie eines oder mehrerer gebäudezugeordneter Verbraucher und/oder eine Betriebsprioritätenliste der gebäudezugeordneten Verbraucher und/oder ein im Betrieb zu erwartender Energieverbrauch des zumindest einen Verbrauchers und/oder ein im Betrieb zu erwartender Energieverbrauch des gesamten Verbraucherverbunds und/oder die Anzahl der betriebenen Verbraucher sowohl momentan oder innerhalb eines vorhergehenden Zeitintervalls, und/oder der Energieverbrauch von Verbrauchern in einem vorgebbaren Zeitintervall vor dem Überschreiten des Energiemengen-Schwellwerts durch die Anlagen-Energiemenge und/oder eine zu erwartende Betriebsreihenfolge der Verbraucher des Verbraucherverbunds. Diesbezüglich kann die zu erwartende Betriebsreihenfolge abhängig von dem bereits vorhandenem Betriebsanforderungsprofil und/oder abhängig von bereits angeforderten Betrieben von spezifischen Verbrauchern unter Berücksichtigung von momentan noch nicht angeforderten Betrieben von anderen Verbrauchern des Verbraucherverbunds und/oder von Restlaufzeiten bis zu den jeweiligen Betriebsenden von unterbrochenen Betrieben von Verbrauchern erfolgen. Zusätzliche oder weitere Entscheidungskriterien können noch das Verhältnis von bereitstellbarer Anlagen-Energiemenge zu Bezugs-Energiemenge aus dem öffentlichen Energieversorgungsnetz zur Deckung des gesamten Energiebedarfs des Verbraucherverbunds und/oder die momentane Jahreszeit und/oder die momentane Tageszeit und/oder der Ladezustand des gebäudezugeordneten Energiespeichers und/oder Leistungsdaten der Photovoltaik-Anlage
Ebenso kann vorgesehen sein, dass der Energiemengen-Schwellwert kontinuierlich oder diskret geändert wird, wobei dazu ebenfalls zumindest einer der oben genannten Entscheidungskriterien berücksichtigt werden kann. Der Energiemengen-Schwellwert ist daher auch dynamisch änderbar.It can also be provided that the energy quantity threshold value is changed continuously or discretely, for which purpose at least one of the above-mentioned decision criteria can likewise be taken into account. The energy quantity threshold value can therefore be changed dynamically.
Ebenso kann vorgesehen sein, dass mehrere Energiemengen-Schwellwerte vorgegeben werden können. Wird dann ein erster Energiemengen-Schwellwert überschritten kann vorgesehen sein, dass ein oder mehrere im Betrieb gestartete Verbraucher in ihrem Betrieb nicht unterbrochen werden, solange die Anlagen-Energiemenge, die momentan von der Photovoltaik-Anlage
Wird nach dem Abschalten des Heizstabs
Im Hinblick auf die Entscheidungskriterien betreffend die meteorologischen Daten kann hierbei eine lokale Wetterstation, die gebäudezugeordnet ausgebildet oder angeordnet ist und/oder Daten von externen Wetterstationen abgefragt und berücksichtigt werden. Beispielsweise kann hier auch eine Datenverwertung über das Internet vorgesehen sein. Im Hinblick auf sicherheitskritische Betriebsgeräte wie beispielsweise eine Beleuchtungsvorrichtung im und/oder außerhalb des Hauses, wie Sie durch die Vorrichtung
Insbesondere umfasst die Erfindung auch ein Verfahren sowie eine Vorrichtung, mit der abhängig von den spezifischen Verbrauchern eines Verbraucherverbunds
Claims (19)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE202010015254U DE202010015254U1 (en) | 2010-11-09 | 2010-11-09 | Control device for controlling an energy allocation and device for providing electrical energy to a building-associated consumer group |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE202010015254U DE202010015254U1 (en) | 2010-11-09 | 2010-11-09 | Control device for controlling an energy allocation and device for providing electrical energy to a building-associated consumer group |
Publications (1)
Publication Number | Publication Date |
---|---|
DE202010015254U1 true DE202010015254U1 (en) | 2011-01-27 |
Family
ID=43525495
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE202010015254U Expired - Lifetime DE202010015254U1 (en) | 2010-11-09 | 2010-11-09 | Control device for controlling an energy allocation and device for providing electrical energy to a building-associated consumer group |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE202010015254U1 (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202011005048U1 (en) | 2011-04-08 | 2011-10-11 | Rudolf Baier | Electrical power distribution device for a building |
DE102011082520A1 (en) * | 2011-09-12 | 2013-03-14 | KM Industrie-Elektronik GmbH | Device for supplying electric power of photovoltaic power source to e.g. washing machine, has control unit that controls switching state of switches, when actual power value exceeds or below target power value |
DE102011118900A1 (en) * | 2011-10-19 | 2013-04-25 | Institute For Information Industry | Energy management method and system and computer readable storage medium for storing the method |
EP2610999A2 (en) | 2011-12-29 | 2013-07-03 | Werner Schmid | Method and device for using the electrical energy of a device connected to a domestic power grid for generating renewable electrical energy |
DE202012101240U1 (en) * | 2012-04-05 | 2013-07-09 | Wi-Koon Energy Anstalt | Energy Management System |
DE102012213907A1 (en) * | 2012-08-06 | 2014-02-06 | Robert Bosch Gmbh | Photovoltaic storage system |
WO2014083083A1 (en) * | 2012-11-29 | 2014-06-05 | Kostal Industrie Elektrik Gmbh | Electrical arrangement and electrical installation comprising an electrical arrangement |
DE102013217765A1 (en) | 2013-09-05 | 2015-03-05 | Robert Bosch Gmbh | Controllable switch and method for controlling a power distribution in a household power network |
DE102013017900A1 (en) * | 2013-10-29 | 2015-04-30 | Stiebel Eltron Gmbh & Co. Kg | Power plant |
US9760956B2 (en) | 2011-04-08 | 2017-09-12 | Sma Solar Technology Ag | Optimized load management |
DE102016111343A1 (en) * | 2016-06-21 | 2017-12-21 | sonnen GmbH | Energy management system and energy management process |
DE202021002165U1 (en) | 2021-06-23 | 2021-08-10 | Alexander Mlynek | Washing machine with power adjustment to maximize self-consumption with local regenerative power generation |
DE202021002540U1 (en) | 2021-08-01 | 2021-08-25 | Alexander Mlynek | Dishwasher with power adjustment to maximize self-consumption with local regenerative power generation |
-
2010
- 2010-11-09 DE DE202010015254U patent/DE202010015254U1/en not_active Expired - Lifetime
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2012136346A1 (en) | 2011-04-08 | 2012-10-11 | Franz Muschaweck | Electric energy distribution system for a building |
DE202011005048U1 (en) | 2011-04-08 | 2011-10-11 | Rudolf Baier | Electrical power distribution device for a building |
DE102012103081B4 (en) | 2011-04-08 | 2021-12-30 | Sma Solar Technology Ag | Optimized load management |
US9760956B2 (en) | 2011-04-08 | 2017-09-12 | Sma Solar Technology Ag | Optimized load management |
DE102011082520A1 (en) * | 2011-09-12 | 2013-03-14 | KM Industrie-Elektronik GmbH | Device for supplying electric power of photovoltaic power source to e.g. washing machine, has control unit that controls switching state of switches, when actual power value exceeds or below target power value |
US9124137B2 (en) | 2011-10-19 | 2015-09-01 | Institute For Information Industry | Energy management method and system, and computer readable storage medium for storing the method |
DE102011118900A1 (en) * | 2011-10-19 | 2013-04-25 | Institute For Information Industry | Energy management method and system and computer readable storage medium for storing the method |
EP2610999A2 (en) | 2011-12-29 | 2013-07-03 | Werner Schmid | Method and device for using the electrical energy of a device connected to a domestic power grid for generating renewable electrical energy |
DE102011090141A1 (en) | 2011-12-29 | 2013-07-04 | Werner Schmid | Method and device for using electrical energy of a device connected to a household power network for generating renewable electrical energy |
DE202012101240U1 (en) * | 2012-04-05 | 2013-07-09 | Wi-Koon Energy Anstalt | Energy Management System |
DE102012213907A1 (en) * | 2012-08-06 | 2014-02-06 | Robert Bosch Gmbh | Photovoltaic storage system |
WO2014083083A1 (en) * | 2012-11-29 | 2014-06-05 | Kostal Industrie Elektrik Gmbh | Electrical arrangement and electrical installation comprising an electrical arrangement |
DE102013217765A1 (en) | 2013-09-05 | 2015-03-05 | Robert Bosch Gmbh | Controllable switch and method for controlling a power distribution in a household power network |
DE102013017900A1 (en) * | 2013-10-29 | 2015-04-30 | Stiebel Eltron Gmbh & Co. Kg | Power plant |
DE102016111343A1 (en) * | 2016-06-21 | 2017-12-21 | sonnen GmbH | Energy management system and energy management process |
DE202021002165U1 (en) | 2021-06-23 | 2021-08-10 | Alexander Mlynek | Washing machine with power adjustment to maximize self-consumption with local regenerative power generation |
DE202021002540U1 (en) | 2021-08-01 | 2021-08-25 | Alexander Mlynek | Dishwasher with power adjustment to maximize self-consumption with local regenerative power generation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE202010015254U1 (en) | Control device for controlling an energy allocation and device for providing electrical energy to a building-associated consumer group | |
DE102012103081B4 (en) | Optimized load management | |
EP2615385B1 (en) | System manager for energy converters with adjustable power | |
EP3590169B1 (en) | Energy management method for an energy system, and energy system | |
EP2610999A2 (en) | Method and device for using the electrical energy of a device connected to a domestic power grid for generating renewable electrical energy | |
DE112015006058T5 (en) | MANAGEMENT DEVICE FOR OPERATING A WATER HEATING DEVICE, MANAGEMENT SYSTEM FOR OPERATING A WATER HEATING DEVICE AND MANAGEMENT METHOD FOR OPERATING A WATER HEATING DEVICE | |
DE102016015503A1 (en) | Heating and / or cooling system with predictive energy management | |
DE102010043611A1 (en) | Method for controlling distribution of electrical power to consumer network in e.g. office building, involves controlling operation of consumers until amount of power-deployable photovoltaic plant exceeds amount of power threshold value | |
EP3561983B1 (en) | Method for operating an energy supply system | |
AT509882B1 (en) | Method for controlling a heat supply system | |
DE102011051074A1 (en) | Controlling the use of energy | |
WO2017211551A1 (en) | Method and device for controlling a discharge power for a storage unit | |
EP3167412A1 (en) | Method and apparatus for forecasting the temporal trend in a power requirement for a residential complex | |
DE102012011119A1 (en) | Local energy system | |
DE102015109113B4 (en) | Storage unit for a consumer, storage system and method for controlling a storage system | |
EP2875560A1 (en) | Method for controlling the ratio between supplied and drawn electric energy in an electric energy supply network | |
EP3688693A1 (en) | Energy flow control device for controlling a load transfer | |
EP2998802B1 (en) | Energy distribution system for an energy network | |
DE102014206892A1 (en) | Method and control device for operating an energy storage device for a photovoltaic system | |
DE202013105950U1 (en) | Arrangement for operating at least one consumer with the electrical power of a regenerative energy source | |
DE102012212321A1 (en) | Device for determining and / or controlling an operating time of a consumer coupled to a power plant, in particular a photovoltaic power plant, and an energy store, and method for operating an energy store coupled to a power plant | |
DE102010036087A1 (en) | Method for supplying electrical load i.e. lithium-ion battery, with electrical energy in electric car, involves partially transmitting electrical energy to electrical load that is supplied with energy without immediate loading of supply net | |
DE202021002540U1 (en) | Dishwasher with power adjustment to maximize self-consumption with local regenerative power generation | |
EP2667475B1 (en) | Device and method for changing a power consumption profile of at least one person in a house or in a dwelling unit with a distribution network | |
DE102020132200A1 (en) | Method for consumption control of an electrical heat generator coupled with a photovoltaic system and a thermal storage unit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R207 | Utility model specification |
Effective date: 20110303 |
|
R156 | Lapse of ip right after 3 years |