CN209431971U - A kind of quick-fried system of hydroelectric project intelligence brill - Google Patents

A kind of quick-fried system of hydroelectric project intelligence brill Download PDF

Info

Publication number
CN209431971U
CN209431971U CN201822125440.6U CN201822125440U CN209431971U CN 209431971 U CN209431971 U CN 209431971U CN 201822125440 U CN201822125440 U CN 201822125440U CN 209431971 U CN209431971 U CN 209431971U
Authority
CN
China
Prior art keywords
processing unit
central processing
quick
outer container
explosion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822125440.6U
Other languages
Chinese (zh)
Inventor
樊启祥
洪文浩
王毅
高鹏
谭志国
周敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges Projects Development Co Ltd CTG
Original Assignee
China Three Gorges Projects Development Co Ltd CTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges Projects Development Co Ltd CTG filed Critical China Three Gorges Projects Development Co Ltd CTG
Priority to CN201822125440.6U priority Critical patent/CN209431971U/en
Application granted granted Critical
Publication of CN209431971U publication Critical patent/CN209431971U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Earth Drilling (AREA)

Abstract

The utility model discloses a kind of hydroelectric projects intelligently to bore quick-fried system; it includes protection outer container; the bottom of the protection outer container is equipped with detachable idler wheel, and the inside of the protection outer container is equipped with central processing unit, satellite positioning transmission and measuring device are connected on the central processing unit;Signal reception and sending device are connected on the central processing unit, antenna is connected on the signal reception and sending device, multiple data transmission interfaces are connected on the central processing unit, it is connected with laser scanning device on the central processing unit, scanning aperture is provided on the laser scanning device.It is systematic to carry out explosion intelligent design, process automation data collection and analysis from using big data, to explosion design optimization scheme is ultimately formed, realize the purpose of intelligent, automation, precision guiding construction.

Description

A kind of quick-fried system of hydroelectric project intelligence brill
Technical field
The utility model relates to water power drill bursting technology field, specifically a kind of hydroelectric project intelligently bores quick-fried system.
Background technique
Drilling and blasting method because its to the tunnel strong applicabilities of various sections, driving is fast, the features such as at low cost due to be widely used in tunnel In road construction, links are also all towards automation, the direction of mechanization is developed for current drilling, powder charge etc., but lack of wisdom, Systematization, is mainly reflected in that there is presently no a kind of systems by explosion design, construction of explosion, performance rating and explosion design optimization Etc. overall processes run through, and realize intelligent, automation in links.
Utility model content
Intelligently bore quick-fried system the purpose of this utility model is to provide a kind of hydroelectric project, the system be related to explosion design, The construction of explosion overall processes such as construction of explosion, Blast Vibration Monitoring, blasting quality evaluation and explosion design optimization, satellite positioning is surveyed Amount system, laser projection device and signal receiving and transmitting apparatus introduce, systematic to carry out explosion intelligent design, mistake from using big data Process automation data collection and analysis realize intelligent, automation, precision to explosion design optimization scheme is ultimately formed The purpose of guiding construction.
In order to realize above-mentioned technical characteristic, purpose of the utility model is realized as follows: a kind of hydroelectric project is intelligent Quick-fried system is bored, it includes protection outer container, and the bottom of the protection outer container is equipped with detachable idler wheel, the inside of the protection outer container Central processing unit is installed, satellite positioning transmission and measuring device are connected on the central processing unit;The central processing unit On be connected with signal and receive and sending device, the signal receive and sending device on be connected with antenna, the central processing unit On be connected with multiple data transmission interfaces, laser scanning device, the laser scanning device are connected on the central processing unit On be provided with scanning aperture.
The bottom of the protection outer container is fixedly installed with fixed device.
The controller phase that the signal receives and sending device passes through wireless or wired mode and construction of explosion equipment Even.
The construction of explosion equipment includes multi-arm trolley and hand air drill.
The signal receives and sending device is passed with for monitoring the detecting instrument for boring quick-fried process and sensing device by cloud Defeated realization data sharing.
The utility model has the advantages that:
1, intelligent.Central processing unit built in the system, has operation and analysis ability, realizes first with big data quick-fried Broken design, then the laser scanning data of explosion achievement is received after the completion of Blast Vibration Monitoring data collection and explosion during Collection is optimized and revised explosion design through network analysis, is instructed for construction in next step.
2, it automates.The links that automation works through the system, the determination including primary blasting design parameter are arrived The iteration optimization that explosion designs after completion blast working, realizes automatic processing.After primary blasting design parameter determines, one Aspect projects hole location information to face, and still further aspect will bore quick-fried information and be transmitted to relevant device, realizes that automatic guidance is applied The purpose of work.Meanwhile in the process, realize that automaticdata is shared between Blast Vibration Monitoring equipment, after the completion of blast working, Data collection is scanned to explosion achievement, analysis generates optimization achievement, is automated completion.
3, it refines.Precision is mainly reflected in three aspects, compares traditional dependence empirical method or analogy method first, this is System is the precision that explosion design parameter is realized by big data and integration project real data, and second is compared to traditional measurement After positioning center hole, borrow measuring instrument and manually indicate the mode of hole location, this system by introduce satellite positioning surveys system and Laser projection positions the precision of drilling hole location.Third is at evaluation and process vibrations monitoring data by blasting quality Reason, it is final to realize that explosion designs dynamic optimization, more accurate design parameter is provided for next step.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawings and examples.
Fig. 1 is the system construction drawing of the utility model.
Fig. 2 is the working principle diagram of the utility model.
In figure: 1 central processing unit;The transmission of 2 satellite positionings and measuring device;3 signals receive and sending device;4 antennas;5 Laser scanning device;6 scanning apertures;7 detachable idler wheels;8 fixed devices;9 data transmission interfaces;10 protection outer containers.
Specific embodiment
The embodiments of the present invention is described further with reference to the accompanying drawing.
Embodiment 1:
Referring to Fig. 1-2, a kind of quick-fried system of hydroelectric project intelligence brill, it includes protection outer container 10, the protection outer container 10 Bottom is equipped with detachable idler wheel 7, and the inside of the protection outer container 10 is equipped with central processing unit 1, on the central processing unit 1 It is connected with satellite positioning transmission and measuring device 2;Signal reception and sending device 3 are connected on the central processing unit 1, it is described It is connected with antenna 4 on signal reception and sending device 3, multiple data transmission interfaces 9, institute are connected on the central processing unit 1 It states and is connected with laser scanning device 5 on central processing unit 1, scanning aperture 6 is provided on the laser scanning device 5.By adopting Quick-fried system is bored with above-mentioned intelligence, can be used in during Hydroelectric Project Construction, cooperating other to bore, the brill of quick-fried equipment realization automation is quick-fried to be applied Work process, and then the automation process of construction of explosion is greatly improved, improve construction efficiency and quality.
It can carry out the position of construction by satellite positioning transmission and measuring device 2 accurate during the work time Positioning and measurement, and data analysis is able to carry out by central processing unit 1, and will locate by signal reception and sending device 3 Reason structure passes to construction of explosion equipment by way of wirelessly or non-wirelessly, to realize the brill of automation until construction of explosion equipment Quick-fried construction operation.It, can be to the section of tunnel by laser scanning device 5 after the construction of explosion of one of section is completed It is scanned, and scan data is retransmitted to central processing unit 1, then optimize to quick-fried data are bored, it is next to instruct The construction of section, and then ensure that the quality of construction of explosion.
Further, the bottom of the protection outer container 10 is fixedly installed with fixed device 8.Pass through above-mentioned fixation device 8 Whole device can be fixed.
Further, the signal receives and sending device 3 passes through wireless or wired mode and construction of explosion equipment Controller be connected.Quick-fried instruction can will be bored by above-mentioned communication modes to pass to specifically by wireless or wired mode Construction equipment, and then realize the effective integration of entire drilling and blasting device, improve automation construction of explosion efficiency.
Further, the construction of explosion equipment includes multi-arm trolley and hand air drill.Pass through above-mentioned construction of explosion equipment Greatly construction of explosion efficiency.
Further, the signal receives and sending device 3 is filled with for monitoring the detecting instrument for boring quick-fried process and induction It sets to transmit by cloud and realizes data sharing.Prison constantly can be carried out to the quick-fried process of brill by above-mentioned detecting instrument and sensing device Control.For the optimization of subsequent construction of explosion, data basis is provided.
The working process and principle of the utility model are as follows:
Step1: this system is positioned about with vehicle-mounted or dragging means of transportation, transport to excavation face;
Step2: optics or laser precise measurement mode are combined by satellite positioning transmission and measuring device 2 again, by satellite After the measuring basis of positioning introduces in hole, system anchor point and current excavated section be accurately positioned and actual size is swept It retouches;
Step3: specific blasting scheme design is carried out by system;
Step4: it is accurately incident upon in hole according to the explosion point that Step3 borehole blasting design obtains by laser projection mode Prepare explosion, excavation section on;The position of drilling, quantity, hole depth information and parameter are transferred to simultaneously and bore quick-fried equipment, to Construction of explosion is instructed, the quick-fried equipment of guidance brill is accurately drilled, powder charge is constructed;
Step5: in blasting process, the extraordinary detecting instrument and sensing device being arranged by excavated section, with blasting process It is transmitted between vibration monitoring equipment by cloud and realizes data sharing, explosion attenuation law is analyzed, demolition effect is carried out Real-time measurement, synchronous transfer are analyzed to system host;
Step6: after the completion of explosion, being scanned the face Quan Dong by laser scanning device 5, obtain flatness, residual porosity, Injury tolerance relevant information, and compared and analyzed with original design, by analysis system processes built in system, propose that demolition effect is commented Valence;
Step7: the effect assessment in more Step6 further corrects explosion data, and then to explosion design optimization, leads to Cross continuous iteration, optimization, it is ensured that explosion design increasingly optimizes, is accurate, achievees the purpose that accurate explosion.
Further, the specific method of the Step3 is, in system built-in system operation program, according to theoretical calculation public affairs The empirical data of formula, Other Engineering tunnel excavation magnanimity, in conjunction with the lithology at each position of tunnel excavation, buried depth, state properties, excavation Section configuration and area excavate Particle size requirements after drilling depth, explosion, then are calculated automatically, form tunnel three-dimensional global blowup and set Count and be accurate to the specific explosion design of current excavated section;The last accurate brill blast hole quantity for determining current section optimization, Delay time parameter between position, hole depth, explosive payload, blasting sequence and hole.
Above-described embodiment is used to illustrate the utility model, rather than limits the utility model, practical at this In novel spirit and scope of protection of the claims, to any modifications and changes that the utility model is made, this reality is both fallen within With novel protection scope.

Claims (5)

1. a kind of hydroelectric project intelligently bores quick-fried system, it is characterised in that: it includes protection outer container (10), the protection outer container (10) Bottom be equipped with detachable idler wheel (7), it is described protection outer container (10) inside central processing unit (1), the center are installed Satellite positioning transmission and measuring device (2) are connected on processor (1);Signal reception is connected on the central processing unit (1) And sending device (3), the signal receive and sending device (3) on be connected with antenna (4), connect on the central processing unit (1) It is connected to multiple data transmission interfaces (9), is connected with laser scanning device (5), the laser scanning on the central processing unit (1) Scanning aperture (6) is provided on device (5).
2. a kind of hydroelectric project intelligently bores quick-fried system according to claim 1, it is characterised in that: protection outer container (10) Bottom is fixedly installed with fixed device (8).
3. a kind of hydroelectric project intelligently bores quick-fried system according to claim 1, it is characterised in that: the signal is received and sent Device (3) is connected by wireless or wired mode with the controller of construction of explosion equipment.
4. a kind of hydroelectric project intelligently bores quick-fried system according to claim 3, it is characterised in that: the construction of explosion equipment packet Include multi-arm trolley and hand air drill.
5. a kind of hydroelectric project intelligently bores quick-fried system according to claim 1, it is characterised in that: the signal is received and sent Device (3) transmits realization data sharing by cloud with for monitoring the detecting instrument for boring quick-fried process and sensing device.
CN201822125440.6U 2018-12-18 2018-12-18 A kind of quick-fried system of hydroelectric project intelligence brill Active CN209431971U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822125440.6U CN209431971U (en) 2018-12-18 2018-12-18 A kind of quick-fried system of hydroelectric project intelligence brill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822125440.6U CN209431971U (en) 2018-12-18 2018-12-18 A kind of quick-fried system of hydroelectric project intelligence brill

Publications (1)

Publication Number Publication Date
CN209431971U true CN209431971U (en) 2019-09-24

Family

ID=67972219

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822125440.6U Active CN209431971U (en) 2018-12-18 2018-12-18 A kind of quick-fried system of hydroelectric project intelligence brill

Country Status (1)

Country Link
CN (1) CN209431971U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109405686A (en) * 2018-12-18 2019-03-01 中国三峡建设管理有限公司 A kind of quick-fried system and method for hydroelectric project intelligence brill

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109405686A (en) * 2018-12-18 2019-03-01 中国三峡建设管理有限公司 A kind of quick-fried system and method for hydroelectric project intelligence brill
CN109405686B (en) * 2018-12-18 2023-10-13 中国三峡建工(集团)有限公司 Drilling and blasting method adopting intelligent drilling and blasting system of hydro-electric engineering

Similar Documents

Publication Publication Date Title
CN108930539B (en) BIM-based tunnel overbreak and underexcavation control method
KR101917937B1 (en) Mine vehicle and method of initiating mine work task
CN103760517B (en) Underground scanning satellite high-precision method for tracking and positioning and device
JP2002311123A (en) Satellite position measuring system
CN111093150A (en) Well worker positioning and communication system
Bedford et al. Evaluation of ZigBee (IEEE 802.15. 4) time-of-flight-based distance measurement for application in emergency underground navigation
CN201031704Y (en) Tunnel wireless laser setting-out work device
CN102638763A (en) Underground electromagnetic-wave ultrasound united positioning system and method
CN102721944A (en) Distance-constraint-based electromagnetic and ultrasound wave combined positioning system and method for downholes
CN209431971U (en) A kind of quick-fried system of hydroelectric project intelligence brill
CN106760549A (en) A kind of real-time monitoring system and monitoring method of vibrate chassis positioning and insertion depth
CN112097630A (en) Tunnel deformation monitoring and early warning radar system
CN109405686A (en) A kind of quick-fried system and method for hydroelectric project intelligence brill
CN103558591B (en) Ground testing method under satellite-borne microwave radar non-darkroom condition
CN111479233A (en) Mine unmanned vehicle detection and position feedback system based on UWB technology
CN202583451U (en) Downhole electromagnetic wave ultrasound union positioning system
CN204851232U (en) Wireless drift indicator
CN202870292U (en) Distance-constraint-based electromagnetic and ultrasound wave combined positioning system for down holes
CN108344970B (en) Wireless positioning automatic calibration method using mobile robot
CN202471067U (en) Airport clearance monitor
CN113756711B (en) Underground coal mine drilling construction equipment system and construction parameter optimization method thereof
CN103534606A (en) Proximity sensor
CN106154256B (en) The automatic real-time positioning system of getting working face drilling depth based on radar detection
JP5361444B2 (en) Cycle time measurement method in tunnel construction
CN115184863A (en) Positioning method, positioning device, electronic equipment and storage medium