CN209070519U - Application software performance real time monitoring apparatus - Google Patents

Application software performance real time monitoring apparatus Download PDF

Info

Publication number
CN209070519U
CN209070519U CN201821799322.7U CN201821799322U CN209070519U CN 209070519 U CN209070519 U CN 209070519U CN 201821799322 U CN201821799322 U CN 201821799322U CN 209070519 U CN209070519 U CN 209070519U
Authority
CN
China
Prior art keywords
equipment
performance
achievement data
application
alarm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821799322.7U
Other languages
Chinese (zh)
Inventor
郭晨阳
牛路
李可佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Friends Education Also Education Technology Co Ltd
Original Assignee
Suzhou Friends Education Also Education Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Friends Education Also Education Technology Co Ltd filed Critical Suzhou Friends Education Also Education Technology Co Ltd
Priority to CN201821799322.7U priority Critical patent/CN209070519U/en
Application granted granted Critical
Publication of CN209070519U publication Critical patent/CN209070519U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Debugging And Monitoring (AREA)

Abstract

The utility model discloses a kind of application software performance real time monitoring apparatus, including application performance achievement data processing equipment;Application performance achievement data processing equipment front end obtains equipment with application performance achievement data and is electrically connected, application performance achievement data processing equipment rear end is electrically connected with storage equipment, display equipment, collection analysis equipment, alarm equipment respectively, and alarm equipment is electrically connected with alarm result monitoring processing equipment;Wherein, alarm result monitoring processing equipment includes: elastic telescopic alarm unit and business monitoring alarm unit.The utility model is convenient for intuitively showing;In application software abnormal performance, abnormality alarming can be provided at the first time, it can find to generate corresponding abnormal reason in time convenient for user, and it solves a problem promptly when determining that the multinomial application performance achievement data in preset time period is abnormal, abnormality alarming is carried out, the function of monitoring and early warning is reached.

Description

Application software performance real time monitoring apparatus
Technical field
The utility model relates to application software performance monitoring fields, real-time more particularly, to a kind of application software performance Monitoring device.
Background technique
Real time monitoring application system user (asu) experience index main target is the application system to solve enterprise's terminaloriented user The problem of system experience can not track helps company information department to understand application system towards different user response time, access frequency Rate etc., improves application system O&amp level, and help information department establishes good attitude.Company information department is ensureing base While plinth framework, application system stable operation, start more to assess information technology to service impact.Information technology management fortune The trend of dimension is, by the O&M and Continuous optimization of business guiding progress information technology, meanwhile, it is anti-by the operation management of information technology Service operation of feeding improves operation flow or even innovative service mode.
With Distributed Application, the development that deepens continuously of cloud computing, the logical construction of operation system is just becoming more and more multiple It is miscellaneous, it is operated in different platform using the form for having evolved into series of services.The complexity of application and added flexibility fortune The difficulty of dimension, how to ensure application can stablize, efficient operation the problem of increasingly by the attention of user.Application performance It is to reflect that application program curstomer-oriented provides the key index of service quality, the height of application performance will directly influence user's Usage experience.Also, the case that in recent years, the corporate client as caused by application performance problems is lost also gradually increases.
The prior art carries out the detection of application software performance, such as the APP performance number of IOS system by software testing technology It is obtained according to the xcode client by being installed in Mac equipment, but xcode client cannot obtain in real time in IOS system The performance data of APP and display, are not easy to the real time monitoring to APP performance;And the prior art is usually to the single of application Performance indicator is monitored, and is easy to appear invalid alarm in this way, and can not accurately reflect the overall performance of application software.
Therefore it provides one kind is convenient for intuitively showing, the overall performance of application software can accurately reflect, can carry out The application software performance real time monitoring apparatus of abnormality alarming is those skilled in the art's technical problem urgently to be resolved.
Utility model content
In view of this, the present invention provides a kind of application software performance real time monitoring apparatus, comprising: application performance refers to Mark data processing equipment;
Application performance achievement data processing equipment front end obtains equipment with application performance achievement data and is electrically connected, application performance Achievement data processing equipment rear end is electrically connected with storage equipment, display equipment, collection analysis equipment, alarm equipment respectively, is alerted Equipment is electrically connected with alarm result monitoring processing equipment;
Wherein, alarm result monitoring processing equipment includes: elastic telescopic alarm unit and business monitoring alarm unit.
It preferably, further include uploading device and starting device, uploading device and application performance achievement data processing equipment are electric Connection, starting device obtain equipment with application performance achievement data and are electrically connected.
Preferably, further include statistics equipment and output equipment, count equipment and output equipment and be electrically connected respectively with storage equipment It connects.
It is further preferred that statistics equipment includes execution unit.
It is further preferred that output equipment includes generation unit and output unit.
Compared with prior art, application software performance real time monitoring apparatus provided by the utility model, at least realize as Under the utility model has the advantages that
The utility model provides a kind of application software performance real time monitoring apparatus, and the application performance achievement data of the device obtains It takes equipment to obtain the multinomial application performance achievement data of target application software within a preset period of time in real time, and passes through application performance Application performance achievement data is carried out processing conversion and calculating by achievement data processing equipment, and is stored in by keyword of timestamp In the local data base of target application software;Meanwhile by Grafana tool by the application performance of the target application software of storage Achievement data is shown by dimension of the time, is convenient for intuitively showing;It is comprehensive when determining application software abnormal performance Every numerical value of multinomial application performance index is considered, collection analysis equipment makes system resource by acquisition monitoring log It is analyzed to obtain the service life of system resource with the period, in this way, the sensitivity of application performance abnormal monitoring can be improved, be accused Alert equipment and alarm result monitoring processing equipment can provide abnormality alarming at the first time, can find to generate in time convenient for user Corresponding abnormal reason, and solve a problem promptly and determining that the multinomial application performance achievement data in preset time period is abnormal When, abnormality alarming is carried out, the function of monitoring and early warning is reached.The monitoring device of the utility model is for client, developer, fortune Dimension personnel etc. use.
Certainly, any product for implementing the utility model specific needs while must not reach above all technical effects.
By the detailed description referring to the drawings to the exemplary embodiment of the utility model, the utility model it is other Feature and its advantage will become apparent.
Detailed description of the invention
It is combined in the description and the attached drawing for constituting part of specification shows the embodiments of the present invention, and And together with its explanation for explaining the principles of the present invention.
Fig. 1 is a kind of application software performance real time monitoring apparatus frame diagram provided by the embodiment of the utility model;
Fig. 2 is a kind of application software performance real time monitoring apparatus frame diagram provided by the embodiment of the utility model;
Fig. 3 is a kind of application software performance real time monitoring apparatus frame diagram provided by the embodiment of the utility model.
Specific embodiment
The various exemplary embodiments of the utility model are described in detail now with reference to attached drawing.It should also be noted that unless another It illustrates outside, the component and the positioned opposite of step, numerical expression and numerical value otherwise illustrated in these embodiments is unlimited The scope of the utility model processed.
Be to the description only actually of at least one exemplary embodiment below it is illustrative, never as to this is practical Novel and its application or any restrictions used.
Technology, method and apparatus known to person of ordinary skill in the relevant may be not discussed in detail, but suitable In the case of, the technology, method and apparatus should be considered as part of specification.
It is shown here and discuss all examples in, any occurrence should be construed as merely illustratively, without It is as limitation.Therefore, other examples of exemplary embodiment can have different values.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, then in subsequent attached drawing does not need that it is further discussed.
Embodiment one
Referring to FIG. 1, Fig. 1 is a kind of application software performance real time monitoring apparatus frame provided by the embodiment of the utility model Figure, the application software performance real time monitoring apparatus of the present embodiment, comprising:
Application performance achievement data processing equipment 12;
12 front end of application performance achievement data processing equipment obtains equipment 11 with application performance achievement data and is electrically connected, and applies 12 rear end of performance indicator data processing equipment respectively with storage equipment 13, display equipment 14, collection analysis equipment 16, alarm equipment 15 electrical connections, alarm equipment 15 are electrically connected with alarm result monitoring processing equipment 17;
Application performance achievement data obtains equipment 11, answers for obtaining target application software within a preset period of time multinomial With performance indicator data;
Application performance achievement data processing equipment 12, for the multinomial application performance within a preset period of time being collected into Achievement data carries out processing conversion, calculates maximum value, minimum value and the average value of each single item application performance achievement data;And with Timestamp is that keyword is stored in the local data base of target application software;
Equipment 13 is stored, for being keyword by the maximum value of each single item application performance achievement data, minimum using timestamp Value and average value are stored in the local data base of target application software;
Equipment 14 is shown, for passing through Grafana tool for the application performance achievement data of the target application software of storage It is shown by dimension of the time;
Collection analysis equipment 16 analyzes the service life of system resource for acquiring monitoring log;
Alarm equipment 15, for determining the multinomial application performance achievement data in preset time period and monitoring log When abnormal, abnormality alarming is carried out;
It includes: elastic telescopic alarm unit 171 and business monitoring alarm unit 172 that alarm result, which monitors processing equipment 17,; 171 pairs of elastic telescopic alarm unit are monitored alarm using performance indicator data, can be flat to CPU, memory usage, system Load, outer net and Intranet go out inbound traffics etc. and are monitored alarm, and automatic distribution increases or decreases the accounting of resource;Business monitoring Alarm unit 172 to service line propelling data centre data it is asynchronous or it is synchronous not in time when trigger, and it is dry to project It is that people provides mail or short message prompt.
Wherein, application performance achievement data obtains equipment 11 and specifically includes: being obtained using top order every the first preset duration Take the performance data of all application software in application system;The performance data of all application software is filtered, target is obtained The performance data of application software;The performance data of target application software is screened, the target application software of screening is intercepted Number in performance data.The performance data of target application software is screened, is specifically included: to the property of target application software Energy data are split with space;The performance data of the target application software after segmentation is sieved by the Variant Tool of gawk Choosing.Application performance achievement data includes: central processor CPU occupancy, CPU holding time, virtual memory VSS occupancy, object Manage memory RSS occupancy, network consumption, electric quantity consumption, database CPU, internal storage state, database connection number, table space.Alarm Equipment specifically includes: at least one numerical value in the maximum value, minimum value and average value of every application performance achievement data When more than preset threshold, carry out abnormal alarm, and warning message is shown and recorded, is stored in the sheet of target application software In ground database.
Exist specifically, the present embodiment passes through the application performance achievement data acquisition acquisition target application software of equipment 11 first Multinomial application performance achievement data in preset time period obtains target application software within a preset period of time multinomial in real time and answers With performance indicator data, then application performance achievement data processing equipment 12 answers within a preset period of time multinomial being collected into Processing conversion is carried out with performance indicator data, calculates the maximum value of each single item application performance achievement data, minimum value and average Application performance achievement data is carried out processing conversion and calculating, and is stored in target application software by keyword of timestamp by value Local data base in;Meanwhile by Grafana tool by the application performance achievement data of the target application software of storage with when Between shown for dimension, be convenient for intuitively showing;When determining application software abnormal performance, multinomial answer has been comprehensively considered It can be provided at the first time different with every numerical value of performance indicator in this way, the sensitivity of application performance abnormal monitoring can be improved Often alarm can find the reason for generating corresponding exception in time convenient for user, and solve a problem promptly and determine preset time period When interior multinomial application performance achievement data is abnormal, abnormality alarming is carried out.
It, being capable of institute in real-time display system it should be noted that top order is common performance analysis tool in Linux Before thering is application performance achievement data, top order to exit, refresh how many times, defaults refresh interval, even the first preset duration For 1s, code is top-l10000, and the first preset duration can be configured according to actual needs, and the present embodiment is not made to have herein Body limits.
Embodiment two
Referring to FIG. 2, Fig. 2 is another application software performance real time monitoring apparatus frame provided by the embodiment of the utility model Frame figure, the application software performance real time monitoring apparatus of the present embodiment, comprising:
Application performance achievement data processing equipment 22;
22 front end of application performance achievement data processing equipment obtains equipment 21 with application performance achievement data and is electrically connected, and applies 22 rear end of performance indicator data processing equipment respectively with storage equipment 23, display equipment 24, collection analysis equipment 26, alarm equipment 25 electrical connections, alarm equipment 25 are electrically connected with alarm result monitoring processing equipment 27;
It further include uploading device 28 and starting device 29,22 electricity of uploading device 28 and application performance achievement data processing equipment Connection, starting device 29 obtain equipment 21 with application performance achievement data and are electrically connected.
Application performance achievement data obtains equipment 21, answers for obtaining target application software within a preset period of time multinomial With performance indicator data;
Application performance achievement data processing equipment 22, for the multinomial application performance within a preset period of time being collected into Achievement data carries out processing conversion, calculates maximum value, minimum value and the average value of each single item application performance achievement data;And with Timestamp is that keyword is stored in the local data base of target application software;
Equipment 23 is stored, for being keyword by the maximum value of each single item application performance achievement data, minimum using timestamp Value and average value are stored in the local data base of target application software;
Equipment 24 is shown, for passing through Grafana tool for the application performance achievement data of the target application software of storage It is shown by dimension of the time;
Collection analysis equipment 26 analyzes the service life of system resource for acquiring monitoring log;
Alarm equipment 25, for determining the multinomial application performance achievement data in preset time period and monitoring log When abnormal, abnormality alarming is carried out;
It includes: elastic telescopic alarm unit 271 and business monitoring alarm unit 272 that alarm result, which monitors processing equipment 27,; 271 pairs of elastic telescopic alarm unit are monitored alarm using performance indicator data, can be flat to CPU, memory usage, system Load, outer net and Intranet go out inbound traffics etc. and are monitored alarm, and automatic distribution increases or decreases the accounting of resource;Business monitoring Alarm unit 272 to service line propelling data centre data it is asynchronous or it is synchronous not in time when trigger, and it is dry to project It is that people provides mail or short message prompt;
Uploading device 28, for application performance achievement data to be uploaded to server, so as to the supplier of the application software Improve the loading performance of the application software in time according to the application performance achievement data of upload;
Starting device 29, for starting entire real time monitoring apparatus, to collect the performance indicator data of the application software.
Embodiment three
Referring to FIG. 3, Fig. 3 is another application software performance real time monitoring apparatus frame provided by the embodiment of the utility model Frame figure, the application software performance real time monitoring apparatus of the present embodiment, comprising:
Application performance achievement data processing equipment 32;
32 front end of application performance achievement data processing equipment obtains equipment 31 with application performance achievement data and is electrically connected, and applies 32 rear end of performance indicator data processing equipment respectively with storage equipment 33, display equipment 34, collection analysis equipment 36, alarm equipment 35 electrical connections, alarm equipment 35 are electrically connected with alarm result monitoring processing equipment 37;
Further include uploading device 38, starting device 39, count equipment 310 and output equipment 311, uploading device 38 and application Performance indicator data processing equipment 32 is electrically connected, and starting device 39 obtains equipment 31 with application performance achievement data and is electrically connected, and is united Meter equipment 310 and output equipment 311 are electrically connected with storage equipment 33 respectively.Counting equipment 310 includes execution unit 3101, output Equipment 311 includes generation unit 3111 and output unit 3112.
Application performance achievement data obtains equipment 31, answers for obtaining target application software within a preset period of time multinomial With performance indicator data;Detailed process is as follows: obtaining all applications in application system every the first preset duration using top order The performance data of software is filtered the performance data of all application software, obtains the performance data of target application software, right The performance data of target application software is split with space;By the Variant Tool of gawk to the target application software after segmentation Performance data screened;
Application performance achievement data processing equipment 32, for the multinomial application performance within a preset period of time being collected into Achievement data carries out processing conversion, calculates maximum value, minimum value and the average value of each single item application performance achievement data;And with Timestamp is that keyword is stored in the local data base of target application software;
Equipment 33 is stored, for being keyword by the maximum value of each single item application performance achievement data, minimum using timestamp Value and average value are stored in the local data base of target application software;
Equipment 34 is shown, for passing through Grafana tool for the application performance achievement data of the target application software of storage It is shown by dimension of the time;
Collection analysis equipment 36 analyzes the service life of system resource for acquiring monitoring log;
Alarm equipment 35, for determining the multinomial application performance achievement data in preset time period and monitoring log When abnormal, abnormality alarming is carried out;At least one in the maximum value, minimum value and average value of every application performance achievement data When a numerical value is more than preset threshold, carry out abnormal alarm, and warning message is shown and recorded, it is soft to be stored in target application In the local data base of part;
It includes: elastic telescopic alarm unit 371 and business monitoring alarm unit 372 that alarm result, which monitors processing equipment 37,; 371 pairs of elastic telescopic alarm unit are monitored alarm using performance indicator data, can be flat to CPU, memory usage, system Load, outer net and Intranet go out inbound traffics etc. and are monitored alarm, and automatic distribution increases or decreases the accounting of resource;Business monitoring Alarm unit 372 to service line propelling data centre data it is asynchronous or it is synchronous not in time when trigger, and it is dry to project It is that people provides mail or short message prompt;
Uploading device 38, for application performance achievement data to be uploaded to server, so as to the supplier of the application software Improve the loading performance of the application software in time according to the application performance achievement data of upload;
Starting device 39, for starting entire real time monitoring apparatus, to collect the performance indicator data of the application software.
Equipment 310 is counted, for counting performance index information when application software operation;Statistics equipment 310 includes holding Row unit 3101, for executing statistics script, statistics script follows according to the preset time interval when running for the application software Ring statistics performance index information;
Output equipment 311, for exporting performance index information when application software operation;Output equipment 311 includes life At unit 3111, for generating the corresponding chart of performance index information when application software operation;Output unit 3112, is used for Export the corresponding chart of performance index information when application software operation.
It should be noted that gawk is to the performance data default of the target application software as unit of line of text with space point It cuts, such as 5th column of the CPU usage in the performance data of target application software in the performance data of target APP, target are answered With 12nd column of the CPU holding time in the performance data of software in the performance data of target application software, then pass through gawk Variant Tool $ 5, the available target application software of $ 12 performance data in CPU usage and CPU holding time.
Through the foregoing embodiment it is found that application software performance real time monitoring apparatus provided by the utility model, is at least realized It is following the utility model has the advantages that
The utility model provides a kind of application software performance real time monitoring apparatus, and the application performance achievement data of the device obtains It takes equipment to obtain the multinomial application performance achievement data of target application software within a preset period of time in real time, and passes through application performance Application performance achievement data is carried out processing conversion and calculating by achievement data processing equipment, and is stored in by keyword of timestamp In the local data base of target application software;Meanwhile by Grafana tool by the application performance of the target application software of storage Achievement data is shown by dimension of the time, is convenient for intuitively showing;It is comprehensive when determining application software abnormal performance Every numerical value of multinomial application performance index is considered, collection analysis equipment makes system resource by acquisition monitoring log It is analyzed to obtain the service life of system resource with the period, in this way, the sensitivity of application performance abnormal monitoring can be improved, be accused Alert equipment and alarm result monitoring processing equipment can provide abnormality alarming at the first time, can find to generate in time convenient for user Corresponding abnormal reason, and solve a problem promptly and determining that the multinomial application performance achievement data in preset time period is abnormal When, abnormality alarming is carried out, the function of monitoring and early warning is reached.The monitoring device of the utility model is for client, developer, fortune Dimension personnel etc. use.
Although being described in detail by some specific embodiments of the example to the utility model, this field It is to be understood by the skilled artisans that example above merely to be illustrated, rather than in order to limit the scope of the utility model.This Field it is to be understood by the skilled artisans that can not depart from the scope of the utility model and spirit in the case where, to above embodiments It modifies.The scope of the utility model is defined by the following claims.

Claims (3)

1. a kind of application software performance real time monitoring apparatus characterized by comprising application performance achievement data processing equipment; It further include uploading device and starting device, the uploading device is electrically connected with the application performance achievement data processing equipment, institute Starting device is stated to be electrically connected with application performance achievement data acquisition equipment;It further include counting equipment and output equipment, it is described Statistics equipment and the output equipment are electrically connected with the storage equipment respectively;
The application performance achievement data processing equipment front end obtains equipment with application performance achievement data and is electrically connected, the application Performance indicator data processing equipment rear end is electrically connected with storage equipment, display equipment, collection analysis equipment, alarm equipment respectively, The alarm equipment is electrically connected with alarm result monitoring processing equipment;
Wherein, the alarm result monitoring processing equipment includes: elastic telescopic alarm unit and business monitoring alarm unit.
2. application software performance real time monitoring apparatus according to claim 1, which is characterized in that
The statistics equipment includes execution unit.
3. application software performance real time monitoring apparatus according to claim 1, which is characterized in that
The output equipment includes generation unit and output unit.
CN201821799322.7U 2018-11-02 2018-11-02 Application software performance real time monitoring apparatus Active CN209070519U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821799322.7U CN209070519U (en) 2018-11-02 2018-11-02 Application software performance real time monitoring apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821799322.7U CN209070519U (en) 2018-11-02 2018-11-02 Application software performance real time monitoring apparatus

Publications (1)

Publication Number Publication Date
CN209070519U true CN209070519U (en) 2019-07-05

Family

ID=67097416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821799322.7U Active CN209070519U (en) 2018-11-02 2018-11-02 Application software performance real time monitoring apparatus

Country Status (1)

Country Link
CN (1) CN209070519U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112235167A (en) * 2020-12-21 2021-01-15 北京每日优鲜电子商务有限公司 Flow alarm method, device, electronic equipment and computer readable medium

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112235167A (en) * 2020-12-21 2021-01-15 北京每日优鲜电子商务有限公司 Flow alarm method, device, electronic equipment and computer readable medium

Similar Documents

Publication Publication Date Title
CN107015892B (en) Pressure testing method, device and system
CN109032915A (en) Application software performance method for real-time monitoring and system
CN106874187B (en) Code coverage rate collection method and device
CN106093838B (en) Gate energy meter remote online method of calibration and system
CN102143507A (en) Method and system for monitoring service quality, and analytical method and system therefor
CN104572401A (en) Alarming method and alarming system
CN107819641B (en) Abnormity analysis method and device of information protection system
CN111866031B (en) Equipment monitoring and analyzing method and device, server and storage medium
CN111835582A (en) Configuration method and device of Internet of things inspection equipment and computer equipment
CN109240126A (en) A kind of distributed application services monitoring system and method with simulated operation function
CN110163458A (en) Data assets management and monitoring method based on artificial intelligence technology
CN110765189A (en) Exception management method and system for Internet products
CN109347665A (en) A kind of Website Usability alarm method and its system based on web log
CN109066996A (en) A kind of data monitoring method and its system for household power system
CN108663084A (en) Bridge structure safe intelligent monitor system based on big data processing
CN113271224A (en) Node positioning method and device, storage medium and electronic device
CN209070519U (en) Application software performance real time monitoring apparatus
CN106951360B (en) Data statistical integrity calculation method and system
CN107742162B (en) Multidimensional feature association analysis method based on allocation monitoring information
CN110262955B (en) Application performance monitoring tool based on pinpoint
CN110430085B (en) Intelligent detection device for centralized meter reading communication faults
CN110995525A (en) Router detection method based on maintenance matrix
CN114513334B (en) Risk management method and risk management device
CN109687999A (en) A kind of association analysis method of alarm failure, device and equipment
CN109450103A (en) Condition detection method, device and the intelligent terminal of pressing plate

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant