CN208538175U CN201820920088.2U CN201820920088U CN208538175U CN 208538175 U CN208538175 U CN 208538175U CN 201820920088 U CN201820920088 U CN 201820920088U CN 208538175 U CN208538175 U CN 208538175U
Authority
CN
China
Prior art keywords
circuit
equipment
information
field communication
terminal device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820920088.2U
Other languages
Chinese (zh)
Inventor
郭洪远
李瑞东
苏永健
李云峰
徐义巍
邓万平
杨致富
陈文�
李鹏竹
贺学军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningxia Jing Nengningdong Power Generation Corp Ltd
Original Assignee
Ningxia Jing Nengningdong Power Generation Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningxia Jing Nengningdong Power Generation Corp Ltd filed Critical Ningxia Jing Nengningdong Power Generation Corp Ltd
Priority to CN201820920088.2U priority Critical patent/CN208538175U/en
Application granted granted Critical
Publication of CN208538175U publication Critical patent/CN208538175U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model provides a kind of flow management and control system of work ticket, is related to power system security administrative skill field.Hand-held terminal device in system is acquired the radio frequency identification mark code of equipment on the spot, shoots the image information of relevant staff and one or more operations of the voice messaging by recording device acquisition relevant staff by near-field communication identification chip collection site earthing or grounding means information, by near-field communication identification chip collection site sign board information, by near-field communication identification chip collector's identity board information, by the photographic device under one or more working stage of electric industry trouble free service;The radio frequency identification mark code of collected equipment on the spot, live earthing or grounding means information, live sign board information, personnel identity Sign Board information, image information and the one or more of voice messaging are recorded, and the background server equipment is uploaded to by network.

Description

A kind of flow management and control system of work ticket
Technical field
The utility model relates to power system security administrative skill field more particularly to a kind of flow management and control systems of work ticket System.
Background technique
In power system security administrative skill field, work ticket permits working on electrical equipment and system software Writ, and execute the written foundation for guaranteeing technical safety measures.The flow management and control mode for being currently based on work ticket is general It also rests in the artificial and way to manage of papery, process is general are as follows:
Firstly, safety measure arranges that executor according to the requirement of work ticket safety measure, carries out safety and arranges after work approval Arrangement is applied, before service work starts, work permit people can arrive jointly scene control work ticket with work responsible person and check item by item, really Recognize listed safety measure to improve and correctly execute.Which equipment live work permit people is described in detail to work responsible person, has pressure Power, high temperature, explosion and Danger Electric shock risk etc., the cosignatory completion work ticket of both sides permit formality.Forbid to run after going into operation or examine It repairs personnel and unilaterally changes safety measure.Workplace faulted-stage section: when work interruption, shift member should withdraw from from scene, listed Safety measure remains stationary, and work ticket is still held by the responsible person that works and deposited.Before working on after interruption, work responsible person should recognize again The true requirement for checking safety measure and should meeting work ticket, can work.When leading without work responsible person, staff must not be into Enter job site.The equipment test run stage: the equipment after maintenance should carry out test run.Repair apparatus test run work should be by the responsible person that works File an application, work ticket agreed to and withdrawn through work permit people, job crew class member withdraws job site, by operations staff into The relevant work of row test run.Forbid not withdraw work ticket, contacts test run equipment by parole.It still to work after test run When, after work permit people should fulfil again work permit formality by " safety measure " execution column with work responsible person, it can restore Work.It such as needs to change former work ticket safety measure, work ticket should be signed and issued again.Work finishing steps: after work, work Responsible person should check comprehensively and cleaning housekeeping scene is organized to lead staff to withdraw scene after confirming no problem.Work Licensor and work responsible person arrive onsite acceptance jointly, check status of equipment, whether there is or not leave object, if then cleaning etc. exists It is filled on work ticket knocking-off time, both sides' signature, come to an end knot for work side.Work ticket completes the stage: operator is torn open Except temporary fence, nameplate is removed, restores safety measure, report value is long (squad leader, machine group leader).To unrecovered safety measure, Report value long (squad leader, machine group leader) simultaneously makes a record, and covers " execution " chapter in the work ticket upper right corner, come to an end knot for work ticket side.
As it can be seen that the flow management and control mode based on work ticket also rests on artificial and papery way to manage in the prior art On, it can not be to stages such as work ticket safety measure arrangement, safety measure recovery, work permit, work terminations whether according to " electric industry Safety work regulation " it is managed, it is difficult to whether the process in electric power monitoring system work performs effectively.
Utility model content
The embodiments of the present invention provide a kind of flow management and control system of work ticket, to solve to be based on work in the prior art The flow management and control mode for making ticket also rests in the artificial and way to manage of papery, can not arrange to work ticket safety measure, peace Whether the stages such as full measure recovery, work permit, work termination are managed according to " electric industry safety work regulation ", it is difficult to monitor The problem of whether process in work of electric power system performs effectively.
In order to achieve the above objectives, the utility model adopts the following technical solution:
A kind of flow management and control system of work ticket, comprising: background server equipment, is provided with radio frequency at hand-held terminal device The equipment on the spot of identification marking code, the live earthing or grounding means for being respectively arranged with near-field communication identification chip, live sign board and people Member's identity board;The hand-held terminal device is connect by network with the background server equipment;The handheld terminal is set It is standby to be provided with photographic device and recording device;
The hand-held terminal device is used under one or more working stage of electric industry trouble free service, is acquired and is set on the spot Standby radio frequency identification identifies code, passes through near-field communication identification chip collection site earthing or grounding means information, passes through near-field communication identification Chip collection site sign board information is taken the photograph by near-field communication identification chip collector's identity board information, by described The voice messaging of relevant staff is acquired as the image information of device shooting relevant staff and by the recording device One or more operations;By the radio frequency identification mark code of collected equipment on the spot, live earthing or grounding means information, scene mark Board information, personnel identity Sign Board information, image information and the one or more of voice messaging are recorded, and by network Reach the background server equipment.
Further, the hand-held terminal device is additionally provided with central processing element circuit, radio communication circuit, radio frequency and knows Other circuit and near-field communication identification circuit;The central processing element circuit and the radio communication circuit, rfid circuit It is separately connected with near-field communication identification circuit;
Circuit connection is to network by wireless communication for the hand-held terminal device, to connect with the background server equipment It connects;
The hand-held terminal device identifies code by the radio frequency identification of the rfid circuit acquisition equipment on the spot;
The hand-held terminal device senses each near-field communication identification chip by the near-field communication identification circuit, and acquisition is existing Field earthing or grounding means information, live sign board information and personnel identity Sign Board information.
Specifically, the photographic device and recording device and the central processing element circuit connection.
Specifically, the hand-held terminal device is additionally provided with liquid crystal touch display screen, speaker circuit and power circuit, institute State liquid crystal touch display screen, speaker circuit and power circuit respectively with the central processing element circuit connection.
Further, the flow management and control system of the work ticket further includes backstage display equipment, and the backstage shows equipment It is communicated to connect with the background server equipment, to show the data information of background server equipment.
A kind of flow management and control system of work ticket provided by the embodiment of the utility model, hand holds terminal device in the system The radio frequency identification mark code of equipment on the spot under one or more working stage of electric industry trouble free service, can be acquired, passed through Near-field communication identification chip collection site earthing or grounding means information, by near-field communication identification chip collection site sign board information, Shoot relevant staff's by near-field communication identification chip collector's identity board information, by the photographic device One or more operations of image information and the voice messaging by recording device acquisition relevant staff;So as to By the radio frequency identification mark code of collected equipment on the spot, live earthing or grounding means information, live sign board information, personnel identity mark Know board information, image information and the one or more of voice messaging to be recorded, and the background service is uploaded to by network Device equipment.In this way, under each working stage of electric industry trouble free service, may be implemented the acquisition of work ticket relevant information, record and Upload, can monitoring work personnel whether executed according to regulatory requirements, can be improved personnel safety consciousness.It solves in the prior art Flow management and control mode based on work ticket also rests in the artificial and way to manage of papery, can not be to work ticket safety measure cloth It sets and recovery situation etc. is managed, it is difficult to the problem of whether process in electric power monitoring system work performs effectively.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, before not making the creative labor property It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is a kind of structural schematic diagram one of the flow management and control system of work ticket provided by the embodiment of the utility model;
Fig. 2 is a kind of structural schematic diagram two of the flow management and control system of work ticket provided by the embodiment of the utility model.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
It should be noted that since the flow management and control mode in the prior art based on work ticket also rests on artificial and papery Way to manage on, therefore there are problems, such as:
1., can not to work ticket safety measure arrange and recovery situation manage.
Service work ticket safety measure is that service work goes on smoothly most important security perimeter, due to production scene people Member's professional standards are irregular, working attitude is full different, if safety measure arrangement is not in place, service personnel may be made injured Or equipment damage will affect unit safety production if safety measure cannot be restored comprehensively;It simultaneously also can not be to maintenance people " maintenance is taken care of oneself " safety measure executive condition of member is managed.
2., live nameplate can not be managed.
When unit maintenance, since overhauling project is more, numerous maintenance safety measures can be overlapped, thus will lead to one switch or Multiple nameplates are hung at person's valve, can not be managed when rearranging safety measure either with or without the new nameplate of suspension, When restoring safety measure, can not also be managed either with or without nameplate is extractd, more, miscellaneous so as to cause production scene nameplate, Disorderly, some nameplates even arbitrarily abandon, and keep Overhaul site nameplate chaotic.
3., " work permit ", the processes such as " work termination " whether executed according to " electrical safe working order ", Wu Faguan Control.
" electrical safe working order " requirement: before service work starts, work permit people can arrive jointly with work responsible person Scene control work ticket checks that the listed safety measure of confirmation is improved and correct execution item by item.Work permit people to work responsible person Which equipment live is described in detail, has pressure, high temperature, explosion and Danger Electric shock risk etc., the cosignatory completion work ticket license of both sides Formality.
" electrical safe working order " requirement: after work, work responsible person should check comprehensively and organize to clean and arrange Working site leads staff to withdraw scene after confirming no problem.Work permit people and work responsible person arrive scene jointly and test It receives, checks status of equipment, whether there is or not leave object, if then cleaning etc. is filled in knocking-off time on work ticket, both sides' label Name, come to an end knot for work side.
" work permit " " work termination " is all to carry out on computers at present, and whether work permit people/responsible person is according to " electricity Industry safety work order " it requires to execute, it can not manage.
4., work ticket " Analysis about Dangerous Point control single " executive condition can not be managed.
If crewmember is unclear to content listed by " Analysis about Dangerous Point controls single ", it may result in crewmember and go to the wrong way Maintenance interval cannot use qualified Work tool, not know about the problems such as service area danger source, cause personal injury or equipment Damage, and the responsible person that works before starting the work at present carries out " Analysis about Dangerous Point controls single " executive condition to crewmember and has no way of Verification, only personnel, which are signed, to be confirmed, and can random allograph.
5., whether service personnel carries out in real earnest according to content listed by " Analysis about Dangerous Point controls single " in maintenance process, can not Control.
For " Analysis about Dangerous Point control is single " executive condition during service work, no detection methods, for example overhaul In the process whether using qualified Work tool, the low use of the whether high extension of safety belt etc., it will lead to service personnel for a long time and loosen safe meaning Know, off one's guard, there are security risks.
6., cannot achieve to full factory ground line, grounding switch data control.
Earthing or grounding means registration at present is manually to register, but use demolition, installation feelings to site examining and repairing demand and earthing or grounding means Condition can not fully understand, be easy to appear artificial accidentally registration, while there is also the risk of accidentally division earthing or grounding means, it is hidden to there is safety Suffer from.
In order to overcome above-mentioned many defects, as shown in Figure 1, the utility model embodiment provides a kind of process pipe of work ticket Control system 10, comprising: background server equipment 11, hand-held terminal device 12 are provided with radio frequency identification (Radio Frequency Identification, abbreviation RFID) identification code 131 equipment on the spot 13, be respectively arranged with near-field communication (Near Field Communication, abbreviation NFC) identification chip live earthing or grounding means 14, live sign board 15 and personnel identity Sign Board 16;The hand-held terminal device 12 is connect by network with the background server equipment 11;The hand-held terminal device 12 is set It is equipped with photographic device 121 and recording device 122.It is portable that the hand-held terminal device 12 can be smart phone, tablet computer etc. Movable equipment, but be not only limited to this.More hand-held terminal devices 12 can be set in the utility model embodiment, respectively It is communicated to connect by network and background server equipment 11.
In addition, the scene sign board 15 is the various sign boards for operating position to be arranged in, number can be set thereon, And the information recorded in near-field communication identification chip is identical as information indicated by each sign board.For example, live sign board 15 can And have " No switching on, someone work, number: 348 ", " work herein, number: 159 ", " quiescing, someone work, number: 050 " etc., but it is not only limited to this.
Personnel's identity board 16 can be lanyard, and above-noted has employee's photo, name, department and post etc. Information, the information recorded in the near-field communication identification chip include at least the information that 16 surface of personnel identity Sign Board is recorded.
The hand-held terminal device 12 can under one or more working stage of electric industry trouble free service (such as peace arrange arrangement rank Section, the license stage that goes into operation, safety are told somebody what one's real intentions are stage, work finishing steps and work ticket completion stage etc.), it is acquired and sets on the spot Standby 13 radio frequency identification mark code 131, by 14 information of near-field communication identification chip collection site earthing or grounding means, pass through near field 15 information of communication identification chip collection site sign board is believed by near-field communication identification chip collector's identity board 16 It ceases, is related to being acquired by the recording device 122 by the image information of the photographic device 121 shooting relevant staff One or more operations of the voice messaging of staff;The radio frequency identification mark code of collected equipment on the spot, scene are connect Ground device information, live sign board information, personnel identity Sign Board information, image information and voice messaging it is one or more into Row record, and the background server equipment 11 is uploaded to by network.
Further, as shown in Fig. 2, the hand-held terminal device 12 is additionally provided with central processing element circuit 123, wireless Telecommunication circuit 124, rfid circuit 125 and near-field communication identification circuit 126;The central processing element circuit 123 and institute Radio communication circuit 124, rfid circuit 125 and near-field communication identification circuit 126 is stated to be separately connected.
Circuit 124 is connected to network to the hand-held terminal device 12 by wireless communication, with the background server equipment 11 connections.
The hand-held terminal device 12 acquires the radio frequency identification marking of the equipment 13 on the spot by the rfid circuit 125 Know code 131.
To sense each near-field communication identification chip (right by the near-field communication identification circuit 126 for the hand-held terminal device 12 It is respectively near-field communication identification chip 141,151 that live earthing or grounding means 14, live sign board 15 and personnel identity mark 16, which should be arrived, With 161), collection site earthing or grounding means information, live sign board information and personnel identity Sign Board information.
Specifically, as shown in Fig. 2, the photographic device 121 and recording device 122 and the central processing element circuit 123 connections.
Specifically, as shown in Fig. 2, the hand-held terminal device 12 is additionally provided with liquid crystal touch display screen 127, loudspeaker electricity Road 128 and power circuit 129, the liquid crystal touch display screen 127, speaker circuit 128 and power circuit 129 respectively with it is described Central processing element circuit connection.It can control and operate the hand-held terminal device 12 by liquid crystal touch display screen 127, it can also Show the data information in hand-held terminal device 12.It can be 12 sending sound of hand-held terminal device by speaker circuit 128 Sound.It can be powered by power circuit 129 for hand-held terminal device 12.
Further, as shown in Fig. 2, the flow management and control system 10 of the work ticket further includes backstage display equipment 17, institute It states backstage display equipment 17 and the background server equipment 11 communicates to connect, to show the data of background server equipment 11 Information.
A kind of flow management and control system of work ticket provided by the embodiment of the utility model, hand holds terminal device in the system The radio frequency identification mark code of equipment on the spot under one or more working stage of electric industry trouble free service, can be acquired, passed through Near-field communication identification chip collection site earthing or grounding means information, by near-field communication identification chip collection site sign board information, Shoot relevant staff's by near-field communication identification chip collector's identity board information, by the photographic device One or more operations of image information and the voice messaging by recording device acquisition relevant staff;So as to By the radio frequency identification mark code of collected equipment on the spot, live earthing or grounding means information, live sign board information, personnel identity mark Know board information, image information and the one or more of voice messaging to be recorded, and the background service is uploaded to by network Device equipment.In this way, under each working stage of electric industry trouble free service, may be implemented the acquisition of work ticket relevant information, record and Upload, can monitoring work personnel whether executed according to regulatory requirements, can be improved personnel safety consciousness.It solves in the prior art Flow management and control mode based on work ticket also rests in the artificial and way to manage of papery, can not be to work ticket safety measure cloth It sets and recovery situation etc. is managed, it is difficult to the problem of whether process in electric power monitoring system work performs effectively.
Specific embodiment is applied in the utility model to be expounded the principles of the present invention and embodiment, with The explanation of upper embodiment is merely used to help understand the method and its core concept of the utility model;Meanwhile for this field Those skilled in the art, based on the idea of the present invention, there will be changes in the specific implementation manner and application range, comprehensive Upper described, the content of the present specification should not be construed as a limitation of the present invention.

Claims (5)

1. a kind of flow management and control system of work ticket characterized by comprising background server equipment, is set hand-held terminal device The equipment on the spot for being equipped with radio frequency identification mark code, the live earthing or grounding means for being respectively arranged with near-field communication identification chip, scene mark Will board and personnel identity Sign Board;The hand-held terminal device is connect by network with the background server equipment;The hand It holds terminal device and is provided with photographic device and recording device;
The hand-held terminal device is used under one or more working stage of electric industry trouble free service, is acquired equipment on the spot Radio frequency identification identifies code, passes through near-field communication identification chip collection site earthing or grounding means information, passes through near-field communication identification chip Collection site sign board information is filled by near-field communication identification chip collector identity board information, by the camera shooting Set the one of the image information for shooting relevant staff and the voice messaging by recording device acquisition relevant staff Kind or a variety of operations;By the radio frequency identification mark code of collected equipment on the spot, live earthing or grounding means information, live sign board letter Breath, personnel identity Sign Board information, image information and the one or more of voice messaging are recorded, and are uploaded to by network The background server equipment.
2. the flow management and control system of work ticket according to claim 1, which is characterized in that the hand-held terminal device is also set It is equipped with central processing element circuit, radio communication circuit, rfid circuit and near-field communication identification circuit;The central processing Chip circuit is separately connected with the radio communication circuit, rfid circuit and near-field communication identification circuit;
Circuit connection is to network by wireless communication for the hand-held terminal device, to connect with the background server equipment;
The hand-held terminal device identifies code by the radio frequency identification of the rfid circuit acquisition equipment on the spot;
The hand-held terminal device senses each near-field communication identification chip by the near-field communication identification circuit, and collection site connects Ground device information, live sign board information and personnel identity Sign Board information.
3. the flow management and control system of work ticket according to claim 2, which is characterized in that the photographic device and recording dress It sets and the central processing element circuit connection.
4. the flow management and control system of work ticket according to claim 3, which is characterized in that the hand-held terminal device is also set It is equipped with liquid crystal touch display screen, speaker circuit and power circuit, the liquid crystal touch display screen, speaker circuit and power supply electricity Road respectively with the central processing element circuit connection.
5. the flow management and control system of work ticket according to claim 1, which is characterized in that the flow management and control of the work ticket System further includes backstage display equipment, and the backstage shows that equipment and the background server equipment communicate to connect, after display The data information of platform server apparatus.
CN201820920088.2U 2018-06-14 2018-06-14 A kind of flow management and control system of work ticket Active CN208538175U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820920088.2U CN208538175U (en) 2018-06-14 2018-06-14 A kind of flow management and control system of work ticket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820920088.2U CN208538175U (en) 2018-06-14 2018-06-14 A kind of flow management and control system of work ticket

Publications (1)

Publication Number Publication Date
CN208538175U true CN208538175U (en) 2019-02-22

Family

ID=65391403

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820920088.2U Active CN208538175U (en) 2018-06-14 2018-06-14 A kind of flow management and control system of work ticket

Country Status (1)

Country Link
CN (1) CN208538175U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108537471A (en) * 2018-06-14 2018-09-14 宁夏京能宁东发电有限责任公司 A kind of flow management and control system and its data processing method of work ticket
CN110808040A (en) * 2019-09-24 2020-02-18 国网河北省电力有限公司衡水市桃城区供电分公司 System and method for controlling flow of interlocking work tickets and operation tickets based on voice
CN113114747A (en) * 2021-03-31 2021-07-13 内蒙古科电数据服务有限公司 Intelligent auxiliary decision-making method for work ticket permission link

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108537471A (en) * 2018-06-14 2018-09-14 宁夏京能宁东发电有限责任公司 A kind of flow management and control system and its data processing method of work ticket
CN110808040A (en) * 2019-09-24 2020-02-18 国网河北省电力有限公司衡水市桃城区供电分公司 System and method for controlling flow of interlocking work tickets and operation tickets based on voice
CN110808040B (en) * 2019-09-24 2021-12-28 国网河北省电力有限公司衡水市桃城区供电分公司 System and method for controlling flow of interlocking work tickets and operation tickets based on voice
CN113114747A (en) * 2021-03-31 2021-07-13 内蒙古科电数据服务有限公司 Intelligent auxiliary decision-making method for work ticket permission link

Similar Documents

Publication Publication Date Title
CN108537471A (en) A kind of flow management and control system and its data processing method of work ticket
CN208538175U (en) A kind of flow management and control system of work ticket
CN107181319B (en) Intelligent inspection method for state of hard pressing plate of transformer substation
CN100485558C (en) Electrical power system safety operation intelligent monitoring device and monitoring method thereof
CN103544739A (en) B/S (Browser/Server) architecture-based polling method of visual subway equipment polling management system
CN110795989A (en) Intelligent safety monitoring system for electric power operation and monitoring method thereof
CN113191591B (en) On-site monitoring method for electric power operating personnel
CN110992509B (en) Equipment monitoring system and method for production workshop
CN103871119A (en) Electronic inspection system for troubleshooting safety production hidden danger
CN101458502A (en) Electrical power system standardized work intelligent control method and special equipment
CN113872332B (en) Intelligent operation and maintenance and error prevention management and control system and method for secondary pressure plates of transformer substation
CN107293024A (en) A kind of kindergarten based on recognition of face is far from garden management system and method
CN105160454A (en) Safety tool test management system based on two-dimensional code technology
JP2012088905A (en) Cable operation support/management system
CN104076767A (en) Railway signal equipment overhauling control system and method
CN104318300A (en) Three-card-in-one based transformer substation tool management system and method
CN107688125A (en) Aging testing system and method
CN104808516A (en) Electrical equipment operation control method and device
CN111063144A (en) Abnormal behavior monitoring method, device, equipment and computer readable storage medium
CN207799760U (en) Intelligent building management system
JP4170000B2 (en) Device connection management system
CN106059090B (en) A kind of working method based on dispatch automated system prompt system
CN108491710A (en) Laboratory equipment supervisory systems
CN109142951B (en) Safety detection method for ground wire hanging connection in electric power operation process