CN206084390U - Formula pipe prefabrication production line between locomotive - Google Patents

Formula pipe prefabrication production line between locomotive Download PDF

Info

Publication number
CN206084390U
CN206084390U CN201620654169.3U CN201620654169U CN206084390U CN 206084390 U CN206084390 U CN 206084390U CN 201620654169 U CN201620654169 U CN 201620654169U CN 206084390 U CN206084390 U CN 206084390U
Authority
CN
China
Prior art keywords
production line
formula pipe
pipe prefabrication
centring system
prefabrication production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620654169.3U
Other languages
Chinese (zh)
Inventor
戚觊
钟皆彩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Qianshan Piping Technology Co Ltd
Original Assignee
Jiangsu Qianshan Piping Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Qianshan Piping Technology Co Ltd filed Critical Jiangsu Qianshan Piping Technology Co Ltd
Priority to CN201620654169.3U priority Critical patent/CN206084390U/en
Application granted granted Critical
Publication of CN206084390U publication Critical patent/CN206084390U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Butt Welding And Welding Of Specific Article (AREA)
  • Arc Welding In General (AREA)

Abstract

The utility model provides a formula pipe prefabrication production line between locomotive which the dual -purpose cutting of diaxon numerical control flame, plasma / groove system, automatic bottoming welding centering system, the mechanized automatic center align system, nozzle stub flange welding centering system of organizing link to each other consecutively with ground commodity circulation conveying system respectively, each system modularization sets up, steel structure skeleton is put up to each system below, satisfies liftoff requirement. The utility model provides a formula pipe prefabrication production line between locomotive, it builds steel structure skeleton on prefabricated cement pier, and the skeleton adopts quick assembly disassembly formula structure, but reuse builds fast, adopt the ground commodity circulation, need not the fixed required line of workshop formula pipe prefabrication solution and hang and basic construction, we are furnished with the exhaust fan in every system, the fluorescent lamp, and necessary facility such as fire extinguisher and instrument can guarantee that the operator has an operational environment comfortable relatively, also accords with on -the -spot requirement to the safety work simultaneously, but fast assembly utilizes fork truck wholly to move fast.

Description

A kind of mobile workshop formula pipe prefabrication production line
Technical field
The utility model is related to a kind of pipe prefabrication production line, and in particular to a kind of mobile workshop formula pipe prefabrication production Line.
Background technology
Pipe prefabrication production line, generally fixed, its production and construction cycle is long, and place is fixed, the scope of its application It is limited, it is obviously improper for foreign project.Present invention mainly solves the fixed pipeline prefabricated solution construction period is long, ground The fixed deficiency of point, meets the demand of the prefabricated work of field pipes, and improve production efficiency deepens prefabricated depth.
Utility model content
The utility model aims to provide a kind of mobile workshop formula pipe prefabrication production line, which solves fixed pipeline prefabricated The solution construction period is long, the deficiency that place is fixed, and meets the demand of the prefabricated work of field pipes, improve production efficiency, plus Deep prefabricated depth.
In order to solve the above problems, the mobile workshop formula pipe prefabrication production line that the utility model is provided employs following Technical scheme:
A kind of mobile workshop formula pipe prefabrication production line, it is characterised in that:Including two-axis numerical control flame, plasma is dual-purpose cuts Cut/groove system, automatic bottoming welding centring system, automatic group of mechanization to centring system, short tube flange welding centring system, Ground logistics conveyer system, described two-axis numerical control flame, the dual-purpose cutting of plasma/groove system and automatic bottoming welding center System is connected, and described automatic bottoming welding centring system outlet is connected for automatic group with mechanization to centring system, described machine Automatic group of toolization is connected to centring system outlet with short tube flange welding centring system, each system respectively with ground handling and conveying System is connected, and each system modular is arranged, and steel structure skeleton is built in each system lower section, meets liftoff requirement.
Preferably, described two-axis numerical control flame, the dual-purpose cutting of plasma/groove system conversion are band sawing machine/beveling machine Cut-out groove system.
Preferably, described short tube flange welding centring system is replaced by middle long tube welding centring system.
Preferably, described short tube flange welding centring system is replaced by mesohigh pipeline automation welding centring system.
Preferably, each system is furnished with ventilating fan, fluorescent lamp, fire extinguisher.
The beneficial effects of the utility model are:A kind of mobile workshop formula pipe prefabrication production line is provided, it is in prefabricated water Steel structure skeleton is built on mud pier, skeleton adopts quickly dismantled structure, repeats and utilizes, built quick;Frame structure work station Length specification is 6M;Using ground logistics, hang without the need for the row needed for fixed workshop formula pipe prefabrication solution and basic build If;We are furnished with the necessary facility such as ventilating fan, fluorescent lamp, fire extinguisher and instrument in each system, it is ensured that operator has The working environment of one relative comfort, while also complying with requirement of the scene to trouble free service;All weather operations, 2 days can be quick Assembling, can overall quick resettlement using fork truck.
Description of the drawings
The structural representation of the preferred embodiment that Fig. 1 is provided for the utility model.
Wherein:1. two-axis numerical control flame, plasma dual-purpose cutting/groove system;2. band sawing machine/beveling machine cuts off groove system System;3. centring system is welded in automatic bottoming;4. automatic group of mechanization is to centring system;5. short tube flange welding centring system;51. Middle long tube welds centring system;52. mesohigh pipeline automations weld centring system;6. ground logistics conveyer system;7. steel structure Skeleton.
Specific embodiment
In order that those skilled in the art more fully understand the technical scheme in the application, below in conjunction with the application reality The accompanying drawing in example is applied, the technical scheme in the embodiment of the present application is clearly and completely described, it is clear that described enforcement Example is only some embodiments of the present application, rather than the embodiment of whole.Based on the embodiment in the application, this area is common The every other embodiment that technical staff is obtained under the premise of creative work is not made, should all belong to the application protection Scope.
As shown in figure 1, the mobile workshop formula pipe prefabrication production line that the utility model is provided, it includes two-axis numerical control fire Flame, plasma dual-purpose cutting/groove system 1, automatic bottoming automatic group of centring system 3, mechanization of welding are to centring system 4, short Pipe flange welding centring system 5, ground logistics conveyer system 6, described two-axis numerical control flame, the dual-purpose cutting/groove of plasma System 1 is connected with automatic bottoming welding centring system 3, and the described automatic bottoming welding outlet of centring system 3 is automatic with mechanization Group is connected to centring system 4, and automatic group of described mechanization is exported and the phase of short tube flange welding centring system 5 to centring system 4 Even, each system is connected respectively with ground logistics conveyer system 6, and each system modular is arranged, and steel is built in each system lower section Structure skeleton 7, meets liftoff requirement.
In a preferred embodiment of the present utility model, described two-axis numerical control flame, the dual-purpose cutting/slope of plasma Port system 1 is replaced by band sawing machine/beveling machine cut-out groove system 2.
In a preferred embodiment of the present utility model, during described short tube flange welding centring system 5 is replaced by Long tube welds centring system 51.
In a preferred embodiment of the present utility model, during described short tube flange welding centring system 5 is replaced by Pressure piping automatic welding centring system 52.
In a preferred embodiment of the present utility model, each system is furnished with ventilating fan, fluorescent lamp, fire extinguisher.
The beneficial effects of the utility model are:The beneficial effects of the utility model are:A kind of mobile workshop formula is provided Pipe prefabrication production line, it builds steel structure skeleton on pre-cast concrete pier, and skeleton adopts quickly dismantled structure, repeats profit With building quick;Frame structure work station length specification is 6M;Using ground logistics, without the need for fixed workshop formula pipe prefabrication solution Certainly the row needed for scheme hangs and fundamental construction;It is necessary that we are furnished with ventilating fan, fluorescent lamp, fire extinguisher etc. in each system Facility and instrument, it is ensured that operator has the working environment of a relative comfort, while also comply with scene wanting to trouble free service Ask;All weather operations, can quickly assemble for 2 days, can overall quick resettlement using fork truck.
Above-described embodiment only to illustrate technology design of the present utility model and feature, its object is to allow and be familiar with technique Personage will appreciate that content of the present utility model and implement according to this, protection domain of the present utility model can not be limited with this. All equivalence changes done according to the utility model or modification, all should cover within protection domain of the present utility model.

Claims (5)

1. a kind of mobile workshop formula pipe prefabrication production line, it is characterised in that:Including two-axis numerical control flame, plasma is dual-purpose cuts Cut/groove system, band sawing machine/beveling machine cut-out groove system, automatic bottoming welding centring system, the automatic Zu Dui centers of mechanization System, short tube flange welding centring system, ground logistics conveyer system, described two-axis numerical control flame, the dual-purpose cutting of plasma/ Groove system and band sawing machine/beveling machine cut-out groove system is connected, described band sawing machine/beveling machine cut-out groove system outlet and Automatically bottoming welding centring system is connected, and described automatic bottoming welding centring system outlet is organized centering and felt concerned about automatically with mechanization System is connected, and automatic group of described mechanization is connected to centring system outlet with short tube flange welding centring system, described short tube Flange welding centring system is connected with ground logistics conveyer system, and each system modular is arranged, and steel is built in each system lower section Structure skeleton, meets liftoff requirement.
2. a kind of mobile workshop formula pipe prefabrication production line according to claim 1, it is characterised in that:The two described number of axle Control flame, the dual-purpose cutting of plasma/groove system conversion are band sawing machine/beveling machine cut-out groove system.
3. a kind of mobile workshop formula pipe prefabrication production line according to claim 1, it is characterised in that:Described short pipe method Orchid welding centring system is replaced by middle long tube welding centring system.
4. a kind of mobile workshop formula pipe prefabrication production line according to claim 1, it is characterised in that:Described short pipe method Orchid welding centring system is replaced by mesohigh pipeline automation welding centring system.
5. a kind of mobile workshop formula pipe prefabrication production line according to claim 1, it is characterised in that:Each system is furnished with Ventilating fan, fluorescent lamp, fire extinguisher.
CN201620654169.3U 2016-06-28 2016-06-28 Formula pipe prefabrication production line between locomotive Active CN206084390U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620654169.3U CN206084390U (en) 2016-06-28 2016-06-28 Formula pipe prefabrication production line between locomotive

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620654169.3U CN206084390U (en) 2016-06-28 2016-06-28 Formula pipe prefabrication production line between locomotive

Publications (1)

Publication Number Publication Date
CN206084390U true CN206084390U (en) 2017-04-12

Family

ID=59975026

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620654169.3U Active CN206084390U (en) 2016-06-28 2016-06-28 Formula pipe prefabrication production line between locomotive

Country Status (1)

Country Link
CN (1) CN206084390U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110949983A (en) * 2019-12-25 2020-04-03 杜泽臣 Dynamic production device and working method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110949983A (en) * 2019-12-25 2020-04-03 杜泽臣 Dynamic production device and working method thereof
CN110949983B (en) * 2019-12-25 2021-05-28 杜泽臣 Dynamic production device and working method thereof

Similar Documents

Publication Publication Date Title
CN202015947U (en) Multifunctional modular container-type pipeline prefabricating work station
CN206084390U (en) Formula pipe prefabrication production line between locomotive
CN104265306A (en) Municipal shield tunnel
CN203782750U (en) Combined type inspection well
CN102426620A (en) High-pressure and ultrahigh-pressure hydraulic pipeline 3D (Three-Dimensional) preassembly and plant prefabrication construction method
CN107297579B (en) One tower desulfurization regeneration tower construction method
CN204456772U (en) The spliced glass fiber reinforced plastic smoke exhaust barrel of arc sheet
CN204326607U (en) A kind of assembled steel reinforced machining shed
CN109967975B (en) Method for building large floating access door
CN206231959U (en) Lift pipe level conveying arrangement in situ in a kind of pipe gallery
CN107489165B (en) Modular protection method suitable for buried pipeline
CN204575567U (en) High-altitude single pipeline flaw detection auxiliary trammer
CN203404551U (en) Petroleum pipeline fixing band with adjustable transverse length
CN204113300U (en) Municipal tunnel
CN212712355U (en) Platform for assembling and hoisting air pipe on construction site
CN203454182U (en) Central gas supply system of boiler
CN205917847U (en) Steel structural system
CN207750586U (en) Gas pipeline cross a river mounting structure
CN204284734U (en) A kind of structure for the conversion of pumping hole footpath
CN203834687U (en) Drum joint steel structure framework
CN203835365U (en) Skid-mounted gas-injection brine-discharge device for salt-cavern gas storage
CN207176524U (en) A kind of packaged type staircase structure of bridge maintenance
CN204370691U (en) A kind of Combination Welding annular compound stirrup
CN116956419B (en) Method for designing and building fabricated high-rise pipeline module
CN203922591U (en) Vertical large diameter pipeline is installed Synchronous lifting platform

Legal Events

Date Code Title Description
GR01 Patent grant