CN113489939A - Intelligent monitoring method and system for power transmission line construction site - Google Patents

Intelligent monitoring method and system for power transmission line construction site Download PDF

Info

Publication number
CN113489939A
CN113489939A CN202010608330.4A CN202010608330A CN113489939A CN 113489939 A CN113489939 A CN 113489939A CN 202010608330 A CN202010608330 A CN 202010608330A CN 113489939 A CN113489939 A CN 113489939A
Authority
CN
China
Prior art keywords
violation
site
construction site
mobile terminal
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010608330.4A
Other languages
Chinese (zh)
Inventor
易建山
袁小超
薛小刚
翟国光
于壮状
李攀
薛赛
孙洋
尉涛
司海青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing North Star Technology Development Co ltd
State Grid Tibet Electric Power Co ltd
Original Assignee
Beijing North Star Technology Development Co ltd
State Grid Tibet Electric Power Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing North Star Technology Development Co ltd, State Grid Tibet Electric Power Co ltd filed Critical Beijing North Star Technology Development Co ltd
Priority to CN202010608330.4A priority Critical patent/CN113489939A/en
Publication of CN113489939A publication Critical patent/CN113489939A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B13/00Burglar, theft or intruder alarms
    • G08B13/18Actuation by interference with heat, light, or radiation of shorter wavelength; Actuation by intruding sources of heat, light, or radiation of shorter wavelength
    • G08B13/189Actuation by interference with heat, light, or radiation of shorter wavelength; Actuation by intruding sources of heat, light, or radiation of shorter wavelength using passive radiation detection systems
    • G08B13/194Actuation by interference with heat, light, or radiation of shorter wavelength; Actuation by intruding sources of heat, light, or radiation of shorter wavelength using passive radiation detection systems using image scanning and comparing systems
    • G08B13/196Actuation by interference with heat, light, or radiation of shorter wavelength; Actuation by intruding sources of heat, light, or radiation of shorter wavelength using passive radiation detection systems using image scanning and comparing systems using television cameras
    • G08B13/19602Image analysis to detect motion of the intruder, e.g. by frame subtraction

Landscapes

  • Engineering & Computer Science (AREA)
  • Multimedia (AREA)
  • Signal Processing (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Telephonic Communication Services (AREA)

Abstract

The application discloses an intelligent monitoring method and system for a power transmission line construction site. The method comprises the steps that a mobile terminal of a construction site manager logs in a site management and control APP, a mobile phone camera is called to collect site video data, and the video data are transmitted to a system server through a mobile network; the system server automatically analyzes and identifies the video data, stores a site violation certificate when violation behaviors exist in the identified video data, and transmits the violation data to a construction site manager mobile terminal and a management layer command center through a mobile network; and the construction field manager mobile terminal and the management layer command center obtain the field violation behaviors, and start a bidirectional interactive voice conversation in a voice mode to confirm the field violation conditions and coordinate subsequent violation processing. By adopting the scheme of the application, special mobile monitoring equipment does not need to be purchased on site, the cost is lower, the operation is simple, the application is convenient and fast, and the mobile monitoring equipment is suitable for being used on site.

Description

Intelligent monitoring method and system for power transmission line construction site
Technical Field
The application relates to the technical field of video analysis, in particular to an intelligent monitoring method and system for a power transmission line construction site.
Background
The intelligent video analysis technology is characterized in that image processing, mode recognition and computer vision technologies are utilized, intelligent video analysis is added in a video monitoring system, useless or interference information of video pictures is filtered out by means of data processing capacity of a computer, different objects are automatically recognized, key useful information in a video source is analyzed and extracted, an abnormal site is rapidly and accurately positioned, abnormal conditions in the monitored pictures are judged, and alarms are sent or other actions are triggered in a fastest and optimal mode.
The mobile video monitoring is that the front-end acquisition mode of a mobile video image is a dynamic mode; the rear end is professional level control product that traditional security protection trade closely combines, and the portable mode is received, for example: the function of monitoring remote real-time dynamic pictures can be realized through a mobile phone or a computer, and a simpler, more convenient and more timely monitoring solution is provided for enterprises and families.
The construction site of the power transmission line engineering is developed outdoors, the distribution points are many, and the violation behaviors of personnel in the construction process need to be monitored in real time. However, no household power supply is basically available on the construction site of the power transmission line, and a fixed camera cannot be installed to carry out real-time monitoring. Meanwhile, the video is checked manually to identify the violation behaviors on site, so that time and labor are wasted, and omission is easy to generate.
At present, for the characteristics of more distribution of the power transmission line construction site, mobile operation and lack of power supply on site, site video monitoring is carried out by adopting a mobile distribution control 4G ball machine to carry out video monitoring, and the method mainly comprises the steps of erecting the mobile distribution control 4G ball machine on the construction site, transmitting video signals to a video server through a mobile network, and then carrying out video browsing and viewing in a monitoring center. Furthermore, intelligent video analysis technology can be combined, and based on some identification algorithms of typical violations such as no safety helmet wearing, smoking and the like, the on-site video is monitored in real time, and the typical violations on the site are automatically discovered.
Disclosure of Invention
The application provides an intelligent monitoring method for a power transmission line construction site, which comprises the following steps:
a mobile terminal of a construction site manager logs in a site management and control APP, calls a mobile phone camera to collect site video data, and transmits the video data to a system server through a mobile network;
the system server receives video data sent by a construction site manager mobile terminal, automatically analyzes and identifies the video data, stores a site violation certificate when violation behaviors exist in the identified video data, and transmits the violation data to the construction site manager mobile terminal and a management layer command center through a mobile network;
after the violation data are analyzed by the construction site manager mobile terminal and the management layer command center to obtain the site violation behaviors, the bidirectional interactive voice conversation between the construction site manager mobile terminal and the management layer command center is started in a voice mode, the site violation conditions are confirmed, and subsequent violation processing is coordinated.
According to the intelligent monitoring method for the power transmission line construction site, the site control APP is installed in the construction site manager mobile terminal in advance, the construction site manager logs in by using the account number of the construction site manager, the preset operation point number information in the APP is selected after the login is successful, the number information is associated with the position, operation content, personnel investment and working time of an operation point, and therefore the association relationship between the video information and the site violation person account number is established, the situation where the violation information occurs and the site responsible personnel are judged when the violation information is found, and therefore violation reminding information can be pushed to the relevant personnel quickly and accurately.
According to the intelligent monitoring method for the power transmission line construction site, the intelligent video analysis system capable of identifying abnormal violation behaviors is deployed in the system server, and the video data uploaded by the mobile end of the construction site manager can be automatically analyzed, detected and identified through the video monitoring service and the image identification service in the intelligent video analysis system, so that the violation behaviors in the video can be found in time, and abnormal alarm reminding is carried out.
According to the intelligent monitoring method for the power transmission line construction site, after the system server identifies that the video data has the violation behaviors, the violation data is stored in the database, the construction site manager mobile terminal account information, the engineering basic information and the video equipment configuration information of the uploaded video data are stored in the database, the one-to-one correspondence relationship between the information and the violation data is established, and the preservation of the site violation certificates is realized.
The intelligent monitoring method for the power transmission line construction site further comprises the step that after receiving the violation data, the mobile end of a construction site manager transmits and checks data such as files, photos or characters with a command center of a management layer.
The intelligent monitoring method for the power transmission line construction site further comprises the step that a construction site manager moving end checks information such as the current position, the distribution situation of peripheral personnel and emergency medical resources through a map module, and assists in developing site emergency rescue.
According to the intelligent monitoring method for the power transmission line construction site, after the violation data are analyzed by the mobile terminal of the construction site manager and the management layer command center to obtain the site violation behaviors, the management layer command center checks the key word introduction and the video screenshot of the site violation information, starts the two-way interaction with the management special responsibility personnel of the construction site, confirms the specific information of the site violation conditions, and can communicate with the management personnel through voice, words, files and the like to explain the site conditions.
The application also provides a transmission line job site intelligent monitoring system, includes: the system comprises a construction site manager mobile terminal, a system server and a management layer command center;
the construction site management personnel mobile terminal is used for logging in a site management and control APP, calling a mobile phone camera to collect site video data, and transmitting the video data to the system server through a mobile network; after receiving the violation data of the system server, starting a bidirectional interactive voice conversation between a construction site manager mobile terminal and a management layer command center in a voice mode, confirming the site violation condition, and coordinating subsequent violation processing;
the system server is used for receiving video data sent by the construction site manager mobile terminal, automatically analyzing and identifying the video data, storing a site violation certificate when violation behaviors exist in the identified video data, and transmitting the violation data to the construction site manager mobile terminal and the management layer command center through a mobile network;
and the management layer command center is used for receiving the violation data sent by the system server, starting a bidirectional interactive voice conversation between the construction site manager mobile terminal and the management layer command center in a voice mode after receiving the violation data, confirming the site violation condition and coordinating subsequent violation processing.
The intelligent monitoring system for the power transmission line construction site comprises a file information management module, and the file information management module and a management layer command center are used for transmitting and checking data such as files, photos or characters.
According to the intelligent monitoring system for the power transmission line construction site, the construction site manager moving end comprises a map module, and information such as the current position, the distribution situation of surrounding personnel and emergency medical resources is checked through the map module to assist in developing site emergency rescue.
The beneficial effect that this application realized is as follows: by adopting the intelligent monitoring method and system for the power transmission line construction site, through installing special site management and control app software in a mobile phone of site management personnel, the collection and transmission of site videos, the distribution and viewing of violation information, the bidirectional interaction and the like are carried out, no special mobile monitoring equipment needs to be purchased on site, the violation behaviors on site can be rapidly monitored by transmitting the violation information to a system server through a wireless network, the problems of high cost, inconvenience in carrying and limitation of bidirectional interaction operation in the conventional mobile monitoring scheme are solved, the cost is lower, the operation is simple, the application is convenient and fast, and the intelligent monitoring method and system are suitable for being used on site.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments described in the present invention, and other drawings can be obtained by those skilled in the art according to the drawings.
Fig. 1 and fig. 2 are schematic diagrams of an intelligent monitoring system for a power transmission line construction site according to an embodiment of the present application;
fig. 3 is a flowchart of an intelligent monitoring method for a power transmission line construction site according to a second embodiment of the present application.
Detailed Description
In the following, the technical solutions in the embodiments of the present invention are clearly and completely described with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, not all, embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example one
An embodiment of the present application provides an intelligent monitoring system for a power transmission line construction site, as shown in fig. 1 and fig. 2, the intelligent monitoring system includes a construction site manager mobile terminal 11, a system server 12 and a management layer command center 13;
a construction site manager moving end 11:
the construction site manager mobile terminal 11 may be an android or apple mobile phone of a construction site manager, for a plurality of construction sites where projects exist simultaneously, a management dedicated person corresponding to each construction site installs a site control APP on the mobile phone in advance, the construction site manager uses an account to log in the site control APP and then calls a mobile phone camera, collects site video data (for example, collects behavior videos such as a helmet, a smoke, a crossing railing and the like), and transmits the video data to the system server 12 through a mobile network;
specifically, when using a field control APP, a construction field manager firstly logs in by using an own account number, selects preset operating point number information in the APP after the login is successful, and the number information is associated with the position, the operating content, the personnel investment, the working time and the like of an operating point, so that the association relationship between the video information and the account number of the field violation personnel is established, the situation where the violation information occurs and the responsibility personnel of the field are judged when the violation information is found, and the violation reminding message is rapidly and accurately pushed to the relevant personnel;
in addition, the construction site manager mobile terminal 11 is further configured to receive the prompt and the instruction sent by the system server 12, analyze the prompt and the instruction of the system server to obtain detailed contents, and perform a voice conversation with the management layer command center 13 through a mobile phone voice; a file information management module is arranged in a construction site manager mobile terminal 11, and data such as files, photos or characters are transmitted and checked through the file information management module and a management layer command center 13; in addition, the construction site manager moving terminal 11 further includes a map module, and the map module is used for checking information such as the current position, the distribution condition of surrounding personnel, emergency medical resources and the like, so as to assist in developing site emergency rescue.
The system server 12:
the system server 12 is used for receiving the video data sent by the construction site manager mobile terminal 11, and performing operations such as forwarding, storing and analyzing on the video data; deploying an intelligent video analysis system of the violation behaviors in the system server 12, integrating video monitoring service and image recognition algorithm service in the intelligent video analysis system, managing, analyzing and diagnosing the video data uploaded by the construction site manager mobile terminal 11 in real time through the video monitoring service and the image recognition algorithm service, automatically detecting the violation behaviors such as no safety helmet, smoking, crossing an enclosure and the like, finding the violation behaviors in real time, and storing corresponding abnormal information when the intelligent video analysis system detects the abnormal behaviors for retaining the on-site violation evidence;
the system server 12 is further provided with a database for storing service management data, and the management data stored in the database includes, but is not limited to, personnel account numbers, engineering basic information, video equipment configuration information, found field violation problem information and the like, so that the data is stored and managed;
in addition, after the intelligent video analysis system finds the violation condition, a violation abnormal mechanism is triggered, an abnormal alarm prompt is sent to the system server 12, the system server 12 obtains the violation information from the intelligent video analysis system through a data interface after receiving the abnormal alarm prompt, and the violation information not only contains the violation information, but also contains the site control app account information corresponding to the site where the violation is located;
after the system server 12 identifies account information in the violation behavior information, the violation data is pushed to a construction site manager mobile terminal 11 where the violation behavior occurs, voice warning is started, alarm prompting is carried out on site related conditions, the alarm prompting is distributed to mobile phones of managers at all levels in a short message mode, prompt is carried out in time, and rapid monitoring and warning of the site violation behavior are achieved; meanwhile, the system server side pushes the data to a management layer command center 13 corresponding to the current place of the violation behaviors, so that the management layer is reminded in time.
Management layer command center 13:
the management layer command center 13 can be arranged at a mobile terminal or a webpage terminal, and is operated by a manager after logging in an account, so as to realize configuration of system basic data, viewing statistics of information, viewing of site video, interactive operation with a construction site and the like;
specifically, the management layer command center 13 is used for checking key word introduction and video screenshot of the site violation information, starting bidirectional interaction with a construction site management special person, confirming the specific information of the site violation condition, and performing voice, word, file and other communication with the management person to explain the site condition.
Example two
An embodiment of the present application provides an intelligent monitoring method for a power transmission line construction site, as shown in fig. 3, including:
step 310, a mobile terminal of a construction site manager logs in a site management and control APP, calls a mobile phone camera to collect site video data, and transmits the video data to a system server through a mobile network;
in the embodiment of the application, the field control APP is installed in the mobile terminal of the construction field management personnel in advance, the construction field management personnel log in by using the own account number, the preset operating point number information in the APP is selected after the login is successful, the number information is associated with the position, the operating content, the personnel investment, the working time and the like of an operating point, the association relationship between the video information and the account number of the field violation personnel is established, the situation where the violation information occurs and the responsibility personnel on the field are judged when the violation information on the field is found, and therefore violation reminding information can be pushed to the relevant personnel quickly and accurately.
Step 320, the system server receives video data sent by the construction site manager mobile terminal, automatically analyzes and identifies the video data, stores a site violation certificate when violation behaviors exist in the identified video data, and transmits the violation data to the construction site manager mobile terminal and the management layer command center through a mobile network;
an intelligent video analysis system capable of identifying abnormal violation behaviors is deployed in the system server, and video data uploaded by a mobile terminal of a construction site manager can be automatically analyzed, detected and identified through video monitoring service and image identification service in the intelligent video analysis system, so that the violation behaviors in the video can be found in time, and abnormal alarm reminding is carried out;
after identifying that the video data has the violation behaviors, the system server stores the violation data in the database, stores the account information of the mobile terminal of the construction site manager, the engineering basic information, the video equipment configuration information and the like which upload the video data in the database, establishes the one-to-one corresponding relation between the information and the violation data, and realizes the preservation of the on-site violation certificates.
Step 330, after the construction site manager mobile terminal and the management layer command center analyze the violation data to obtain the site violation behaviors, starting a two-way interactive voice conversation between the construction site manager mobile terminal and the management layer command center in a voice mode, confirming the site violation conditions and coordinating subsequent violation processing;
in the embodiment of the application, a file information management module is arranged in a construction site manager mobile terminal, and the file information management module and a management layer command center are used for transmitting and checking data such as files, photos or characters; in addition, the construction site management personnel moving end also comprises a map module, and the map module is used for checking information such as the current position, the distribution condition of peripheral personnel, emergency medical resources and the like to assist in developing site emergency rescue;
specifically, after a mobile end of a construction site manager and a management layer command center analyze violation data to obtain site violation behaviors, the management layer command center checks key character introduction and video screenshot of the site violation information, starts bidirectional interaction with a construction site management special responsible person, confirms specific information of the site violation conditions, and can communicate with the manager through voice, characters, files and the like to explain the site conditions.
According to the application, the mobile app is designed and developed on the site, the mobile 4G ball machine is distributed and controlled by the mobile phone, hardware purchasing cost is saved, the problem that people are inconvenient to carry is reduced, the site video monitoring function can be rapidly started by site management personnel anytime and anywhere, the condition of violation of regulations on the site is found by combining automatic monitoring of an intelligent analysis technology, rapid distribution and bidirectional interaction of information can be carried out by fully utilizing the advantages of the intelligent mobile phone, and the timeliness of finding, confirming and processing of the problem of violation of the site is improved.
The above-mentioned embodiments are only specific embodiments of the present application, and are used for illustrating the technical solutions of the present application, but not limiting the same, and the scope of the present application is not limited thereto, and although the present application is described in detail with reference to the foregoing embodiments, those skilled in the art should understand that: any person skilled in the art can modify or easily conceive the technical solutions described in the foregoing embodiments or equivalent substitutes for some technical features within the technical scope disclosed in the present application; such modifications, changes or substitutions do not depart from the spirit and scope of the present disclosure, which should be construed in light of the above teachings. Are intended to be covered by the scope of the present application. Therefore, the protection scope of the present application shall be subject to the protection scope of the claims.

Claims (10)

1. An intelligent monitoring method for a power transmission line construction site is characterized by comprising the following steps:
a mobile terminal of a construction site manager logs in a site management and control APP, calls a mobile phone camera to collect site video data, and transmits the video data to a system server through a mobile network;
the system server receives video data sent by a construction site manager mobile terminal, automatically analyzes and identifies the video data, stores a site violation certificate when violation behaviors exist in the identified video data, and transmits the violation data to the construction site manager mobile terminal and a management layer command center through a mobile network;
after the violation data are analyzed by the construction site manager mobile terminal and the management layer command center to obtain the site violation behaviors, the bidirectional interactive voice conversation between the construction site manager mobile terminal and the management layer command center is started in a voice mode, the site violation conditions are confirmed, and subsequent violation processing is coordinated.
2. The intelligent monitoring method for the power transmission line construction site according to claim 1, characterized in that a site control APP is installed in a construction site manager mobile terminal in advance, a construction site manager logs in by using an account of the construction site manager, after the login is successful, preset operation point number information in the APP is selected, the number information is associated with the position, operation content, personnel investment and working time of an operation point, and therefore an association relationship between video information and the account of the site violation personnel is established, the situation where the violation information occurs and the responsible personnel on the site are judged when the violation information on the site is found, and therefore violation reminding information can be pushed to relevant personnel quickly and accurately.
3. The intelligent monitoring method for the power transmission line construction site as claimed in claim 1, wherein an intelligent video analysis system capable of identifying abnormal violation behaviors is deployed in the system server, and video data uploaded by a mobile terminal of a construction site manager can be automatically analyzed, detected and identified through video monitoring services and image identification services in the intelligent video analysis system, so that the violation behaviors in the video can be found in time, and abnormal alarm reminding is performed.
4. The intelligent monitoring method for the power transmission line construction site as claimed in claim 1, wherein the system server stores the violation data in the database after recognizing that the video data has violation behaviors, stores the account information of the construction site manager mobile terminal, the engineering basic information and the video equipment configuration information which upload the video data in the database, establishes the one-to-one correspondence relationship between the information and the violation data, and realizes the retention of the on-site violation certificates.
5. The intelligent monitoring method for the power transmission line construction site as claimed in claim 1, wherein the method further comprises the step that the mobile end of the construction site manager transmits and checks data such as files, photos or characters with the command center of the management layer after receiving the violation data.
6. The intelligent monitoring method for the power transmission line construction site according to claim 1, further comprising the step that a construction site manager moving end checks information such as the current position, the distribution situation of surrounding personnel and emergency medical resources through a map module to assist in carrying out site emergency rescue.
7. The intelligent monitoring method for the power transmission line construction site as claimed in claim 1, wherein after the mobile terminal of the construction site manager and the management layer command center analyze the violation data to obtain the site violation behaviors, the management layer command center checks the key word introduction and the video screenshot of the site violation information, starts the two-way interaction with the management special responsibility personnel of the construction site to confirm the specific information of the site violation conditions, and the management special responsibility can communicate with the management personnel through voice, words, files and the like to explain the site conditions.
8. The utility model provides a transmission line job site intelligent monitoring system which characterized in that includes: the system comprises a construction site manager mobile terminal, a system server and a management layer command center;
the construction site management personnel mobile terminal is used for logging in a site management and control APP, calling a mobile phone camera to collect site video data, and transmitting the video data to the system server through a mobile network; after receiving the violation data of the system server, starting a bidirectional interactive voice conversation between a construction site manager mobile terminal and a management layer command center in a voice mode, confirming the site violation condition, and coordinating subsequent violation processing;
the system server is used for receiving video data sent by the construction site manager mobile terminal, automatically analyzing and identifying the video data, storing a site violation certificate when violation behaviors exist in the identified video data, and transmitting the violation data to the construction site manager mobile terminal and the management layer command center through a mobile network;
and the management layer command center is used for receiving the violation data sent by the system server, starting a bidirectional interactive voice conversation between the construction site manager mobile terminal and the management layer command center in a voice mode after receiving the violation data, confirming the site violation condition and coordinating subsequent violation processing.
9. The intelligent monitoring system for the power transmission line construction site as claimed in claim 8, wherein the construction site manager moving end comprises a file information management module, and the file information management module and the management layer command center are used for transmitting and viewing data such as files, photos or characters.
10. The intelligent monitoring system for the power transmission line construction site as claimed in claim 8, wherein the construction site manager moving end comprises a map module, and information such as the current position, the distribution situation of surrounding personnel, emergency medical resources and the like is checked through the map module to assist in developing site emergency rescue.
CN202010608330.4A 2020-06-29 2020-06-29 Intelligent monitoring method and system for power transmission line construction site Pending CN113489939A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010608330.4A CN113489939A (en) 2020-06-29 2020-06-29 Intelligent monitoring method and system for power transmission line construction site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010608330.4A CN113489939A (en) 2020-06-29 2020-06-29 Intelligent monitoring method and system for power transmission line construction site

Publications (1)

Publication Number Publication Date
CN113489939A true CN113489939A (en) 2021-10-08

Family

ID=77932695

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010608330.4A Pending CN113489939A (en) 2020-06-29 2020-06-29 Intelligent monitoring method and system for power transmission line construction site

Country Status (1)

Country Link
CN (1) CN113489939A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115131172A (en) * 2022-08-29 2022-09-30 广东电网有限责任公司佛山供电局 Multi-source data fusion-based intelligent electric power operation violation identification method and system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201903942U (en) * 2010-10-22 2011-07-20 中国石油化工股份有限公司 Accident prewarning device of production field
CN105930866A (en) * 2016-04-19 2016-09-07 唐山新质点科技有限公司 Violation information processing method, device and system
CN106204784A (en) * 2016-06-30 2016-12-07 北京海顿中科技术有限公司 Safety guides intelligence and patrols point detection system
CN108319234A (en) * 2017-12-31 2018-07-24 分众安环(北京)科技有限公司 Safety management system, method, equipment, storage medium, information processing cloud platform
CN109670771A (en) * 2018-10-31 2019-04-23 中国大唐集团科学技术研究院有限公司 A kind of power engineering construction project management system
CN109889791A (en) * 2019-04-11 2019-06-14 吉林同益光电科技有限公司 A kind of electric power construction field managing and control system and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201903942U (en) * 2010-10-22 2011-07-20 中国石油化工股份有限公司 Accident prewarning device of production field
CN105930866A (en) * 2016-04-19 2016-09-07 唐山新质点科技有限公司 Violation information processing method, device and system
CN106204784A (en) * 2016-06-30 2016-12-07 北京海顿中科技术有限公司 Safety guides intelligence and patrols point detection system
CN108319234A (en) * 2017-12-31 2018-07-24 分众安环(北京)科技有限公司 Safety management system, method, equipment, storage medium, information processing cloud platform
CN109670771A (en) * 2018-10-31 2019-04-23 中国大唐集团科学技术研究院有限公司 A kind of power engineering construction project management system
CN109889791A (en) * 2019-04-11 2019-06-14 吉林同益光电科技有限公司 A kind of electric power construction field managing and control system and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115131172A (en) * 2022-08-29 2022-09-30 广东电网有限责任公司佛山供电局 Multi-source data fusion-based intelligent electric power operation violation identification method and system

Similar Documents

Publication Publication Date Title
CN109375594B (en) City safety wisdom management and control platform
CN105023403B (en) A kind of inter-linked controlling method based on industry security emergency command integrated system
KR101038370B1 (en) Monitoring system and methode using internet network and cellular network at a playground
CN102930702B (en) Zero false alarm networking video security method and system thereof
CN110807460B (en) Transformer substation intelligent patrol system based on image recognition and application method thereof
CN110535711B (en) Video monitoring fault diagnosis system and diagnosis method
CN111626636A (en) Industrial safety emergency management platform based on big data analysis technology
CN106097220A (en) A kind of prediction scheme sends method and device
CN114023031A (en) Intelligent fire-fighting management system and method for small and micro-place based on 5G technology
CN110544362A (en) Construction site anomaly identification method and device based on block chain
CN111371895A (en) Electromechanical equipment management system for expressway tunnel and method thereof
CN208732382U (en) Elevator signal acquisition device and system
CN111738115A (en) Mobile camera automatic identification method and system based on artificial intelligence
CN113489939A (en) Intelligent monitoring method and system for power transmission line construction site
CN110443562A (en) A kind of positioning attendance management method and system
KR20120057829A (en) Monitoring system and methode using internet network and cellular network at a parking place
CN112001810A (en) Intelligent forestry patrolling system and method based on machine vision
CN107483544A (en) A kind of intelligent movable monitoring system and monitoring method
CN104767969A (en) Intelligent operation safety monitoring system and method for railway crossing
CN116778370A (en) Event processing method, device, equipment, storage medium and program product
CN106533479A (en) Infrared imaging search method and interphone with infrared imaging search function
CN113487840A (en) Gas management and monitoring early warning system
CN109067566B (en) Method, terminal and monitoring equipment for screenshot in silent mode
CN112218040A (en) Background monitoring device and system for high-voltage cable accessory installation
CN111392540A (en) Non-contact feedback monitoring method and device for equipment running state

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211008

RJ01 Rejection of invention patent application after publication