CN112884290A - BIM-based field construction management method - Google Patents

BIM-based field construction management method Download PDF

Info

Publication number
CN112884290A
CN112884290A CN202110106470.6A CN202110106470A CN112884290A CN 112884290 A CN112884290 A CN 112884290A CN 202110106470 A CN202110106470 A CN 202110106470A CN 112884290 A CN112884290 A CN 112884290A
Authority
CN
China
Prior art keywords
construction
bim
management
model
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110106470.6A
Other languages
Chinese (zh)
Inventor
陆跃东
张涌
孙玮玮
张璐瑶
王鲁敏
吴耀伟
窦静静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Guoxin Haitian Center Construction Co ltd
Original Assignee
Qingdao Guoxin Haitian Center Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Guoxin Haitian Center Construction Co ltd filed Critical Qingdao Guoxin Haitian Center Construction Co ltd
Priority to CN202110106470.6A priority Critical patent/CN112884290A/en
Publication of CN112884290A publication Critical patent/CN112884290A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Geometry (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Computer Hardware Design (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Structural Engineering (AREA)
  • Computer Graphics (AREA)
  • Architecture (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Software Systems (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a field construction management method based on BIM, and relates to the technical field of field construction management methods. The invention comprises the following steps: s1 deepening design: combining construction operation specifications and construction processes based on a BIM model; carrying out refined modeling on the project steel structure; generating a secondary structure reserved hole map by using BIM after the comprehensive arrangement of pipelines is finished; s2 field cloth management; s3 group management: simulating, analyzing and optimizing a project construction scheme by adopting a BIM technology; and S4 progress management: adding information into the three-dimensional model by combining the construction progress plan, and performing 4D construction simulation; s5 materials, equipment management: providing basis for material requirement plans of different stages of a project; s6, quality and safety management: simulating engineering quality and safety key control points based on a BIM model; and S7 completion management: forming a complete BIM model. The high-efficiency transmission and real-time sharing of construction site information are realized, and the construction management level is improved.

Description

BIM-based field construction management method
Technical Field
The invention relates to the technical field of field construction management methods, in particular to a field construction management method based on BIM.
Background
With the development of urbanization, the requirements of society on building quality are continuously improved. In the building engineering management process, a project planning decision-making stage, a building design stage, a construction and construction stage and a completion input operation management stage are involved. The existing design drawing is a two-dimensional drawing, and is difficult to communicate with non-professionals, and the communication of the professionals depends on imagination, so that the situation that deviation is difficult to find easily occurs; in the construction process, multiple specialties are needed to work cooperatively, and a large amount of time and energy are consumed by the cooperative work.
Therefore, a field construction management method based on BIM is urgently needed, which realizes the efficient transmission and real-time sharing of construction field information, improves the construction management level, and performs multi-professional coordination, field arrangement optimization, construction progress, quality management, safety management and resource and cost management in the construction process, thereby greatly reducing rework and saving construction cost.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides a BIM-based field construction management method, which realizes the high-efficiency transmission and real-time sharing of construction field information, improves the construction management level, and performs multi-professional coordination, field arrangement optimization, construction progress, quality management, safety management, resource and cost management in the construction process, thereby greatly reducing rework and saving construction cost.
The invention specifically adopts the following technical scheme:
the BIM-based field construction management method comprises the following steps:
s1 deepening design: carrying out comprehensive collision inspection on buildings, structures and electromechanical equipment based on a BIM model in combination with construction operation specifications and a construction process; carrying out refined modeling on the project steel structure, and marking the specification, material, weight, axis and elevation information of the component; generating a secondary structure reserved hole map by using BIM after the comprehensive arrangement of pipelines is finished;
and S2 field layout management: planning, arranging, analyzing and optimizing site terrain, existing facilities, surrounding environment, construction area, temporary road and facilities, processing area, material yard, construction machinery and safe and civilized construction facilities in each construction stage based on the BIM model;
s3 group management: simulating, analyzing and optimizing a project construction scheme by adopting a BIM technology;
and S4 progress management: adding information into the three-dimensional model by combining the construction progress plan, performing 4D construction simulation through dynamic linkage of the plan progress model and the actual progress model, integrating the construction model with on-site facility, machinery, equipment and pipeline information, and checking the space and the space, wherein the space and time matching degree is obtained;
s5 materials, equipment management: on the basis of a BIM model, the BIM software is used for exporting various professional material and equipment lists, and bases are provided for material demand plans of different stages of a project;
s6, quality and safety management: performing analog simulation and scheme optimization on engineering quality and safety key control points based on a BIM model;
and S7 completion management: and adding completion acceptance information to the model based on the construction BIM model, and correcting according to completion requirements to further form a completion BIM model.
The present invention is further preferred: the refined modeling of the project steel structure in S1 is based on TEKLA software.
The present invention is further preferred: and after the project steel structure is refined and modeled in S1, counting the specifications and the quantity of materials required by a local area or a construction section, providing a basis for material planning, and providing a relevant basis for field level arrangement, tower crane model selection and climbing.
The present invention is further preferred: and S1, deeply arranging all water pipe wells and electric wells of the project, reasonably setting the positions of the supports and the pipelines in the well, and finally generating a two-dimensional drawing.
The present invention is further preferred: and S1, comprehensively arranging all machine rooms based on the BIM technology, and transmitting the machine rooms to field operators in a drawing mode.
The present invention is further preferred: and S3, the construction process is displayed in an animation demonstration mode before formal construction, so that the problem of edge folding and closing caused by quality reworking easily in the construction process is solved.
The present invention is further preferred: the construction progress plan in S4 is compiled by project, and the information is added to the three-dimensional model by means of Navisvorks software.
The present invention is further preferred: and the EBIM platform mobile equipment is used for checking and accepting the quality and the safety of the field engineering, and the dynamic tracking and recording of quality and safety management are realized.
The present invention is further preferred: and the EBIM platform uploads the BIM model to a server after the BIM model is lightened, and the PC end and the mobile end are mutually associated through the cloud platform.
The invention has the beneficial effects that:
the invention coordinates multiple specialties, optimizes site layout, manages construction progress, quality, safety and resources and cost during construction, greatly reduces rework and saves construction cost. Through the deepening design, the comprehensive collision inspection of the majors such as buildings, structures, electromechanical equipment and the like is carried out, the collision problem of each major is solved, the construction optimization design is completed, the construction model is perfected, and the reasonability, the accuracy and the checking performance of each major are improved. Through the refined modeling, a basis is provided for a material plan, and a related basis can also be provided for field level arrangement, tower crane model selection, climbing and the like. Through field distribution management, the field arrangement is scientific and reasonable. Through group management, zero collision, zero conflict and zero rework are realized as much as possible, so that the rework cost is greatly reduced, the resource waste, conflict and safety problems are reduced, and real construction is guided. The problems which can occur in the construction can be found before the construction is started through schedule management so as to be dealt with in advance; the method can also be used as a feasibility guidance of construction, and helps to determine a reasonable construction scheme, a personnel and equipment configuration scheme and the like. Through material and equipment management, on the premise of ensuring the requirement of site construction progress, the material and capital cost are saved to the greatest extent. Through completion management, completion acceptance information is added to the model and is corrected according to completion requirements, so that a completion BIM model is formed and serves as an important reference basis for completion data.
Detailed Description
Hereinafter, embodiments of the present invention will be described in detail. The following examples are only for illustrating the technical solutions of the present invention more clearly, and therefore are only examples, and the protection scope of the present invention is not limited thereby.
It is to be noted that, unless otherwise specified, technical or scientific terms used herein shall have the ordinary meaning as understood by those skilled in the art to which the invention pertains.
What is called BIM, the national standard for BIM in the united states is explained as follows: "digital representation of physical and functional characteristics of a construction project; an information sharing platform; an information process for realizing the whole life cycle management of the construction engineering; a collaborative work platform for realizing the insertion, extraction, update and modification of information of different stages of a building project.
The BIM-based field construction management method comprises the following steps:
s1 deepening design: carrying out comprehensive collision inspection on buildings, structures and electromechanical equipment based on a BIM model in combination with construction operation specifications and a construction process; the problem of collision of each specialty is solved, the construction optimization design is completed, the construction model is perfected, and the reasonability, the accuracy and the checking performance of each specialty of construction are improved. Carrying out refined modeling on the project steel structure, and marking the specification, material, weight, axis and elevation information of the component; after the comprehensive arrangement of pipelines is completed in the electromechanical industry, a hole pattern reserved for a secondary structure is generated by using BIM (building information modeling) to realize one-layer-one-row-one-wall-one-figure, and after the drawings are confirmed by each party, a labor team is issued to construct according to the drawings, so that the construction quality is greatly improved, and convenience is provided for later-stage pipeline installation.
And S2 field layout management: and planning, arranging, analyzing and optimizing site terrain, existing facilities, surrounding environment, construction area, temporary road and facilities, processing area, material yard, construction machinery and safety civilized construction facilities in each construction stage based on the BIM model.
S3 group management: simulating, analyzing and optimizing a project construction scheme by adopting a BIM technology; therefore, problems possibly occurring in construction are found, preventive measures are taken before construction until an optimal construction scheme is obtained, and zero collision, zero conflict and zero rework are realized as far as possible, so that the rework cost is greatly reduced, the resource waste, conflict and safety problems are reduced, and real construction is guided.
And S4 progress management: adding information into the three-dimensional model by combining the construction progress plan, performing 4D construction simulation through dynamic linkage of the plan progress model and the actual progress model, integrating the construction model with on-site facility, machinery, equipment and pipeline information, and checking whether space conflicts with space and time so as to find possible problems in construction before construction is started and process in advance; the method can also be used as a feasibility guidance of construction, and helps to determine a reasonable construction scheme, a personnel and equipment configuration scheme and the like.
S5 materials, equipment management: on the basis of the BIM model, the BIM software is used for exporting the detailed lists of all professional materials and equipment, so that a basis is provided for material demand plans of different stages of a project, and the materials and the capital cost are saved to the greatest extent on the premise of ensuring the requirements of site construction progress.
S6, quality and safety management: and performing analog simulation and scheme optimization on the engineering quality and the safety key control points based on the BIM model.
And S7 completion management: and adding completion acceptance information to the model based on the construction BIM model, and correcting according to completion requirements to further form a completion BIM model as an important reference basis for completion data.
The present invention is further preferred: the refined modeling of the project steel structure in S1 is based on TEKLA software.
The present invention is further preferred: and after the project steel structure is refined and modeled in S1, counting the specifications and the quantity of materials required by a local area or a construction section, providing a basis for material planning, and providing a relevant basis for field level arrangement, tower crane model selection and climbing.
The present invention is further preferred: and S1, aiming at the characteristics of narrow pipe wells and dense pipelines of the project, deeply arranging all the pipe wells and the electric wells of the project, reasonably setting the positions of the supports and the pipelines in the well, finally generating a two-dimensional drawing, issuing labor service, and guiding site construction and prefabrication and processing of the supports.
The present invention is further preferred: the machine room construction drawing provided by a design institute is not detailed for the spatial position of a pipeline, generally focuses on a certain specialty, cannot completely consider the comprehensive arrangement of the pipeline of multiple specialties, the selection of equipment is often selected according to experience when the construction drawing is drawn, and has larger deviation with equipment provided by a manufacturer in the later period, so that the construction drawing in the earlier period has larger difference with the actual installation on the site in the later period, and all machine rooms are comprehensively arranged by means of a BIM technology at present and are transmitted to site operators in a CAD drawing mode. The method has the advantages that the influence of human factors on the construction process and the difficulty of specific operation are reduced, the construction efficiency is improved, the cost is reduced, and the engineering quality is improved. And S1, comprehensively arranging all machine rooms based on the BIM technology, and transmitting the machine rooms to field operators in a drawing mode.
The present invention is further preferred: and S3, the construction process is displayed in an animation demonstration mode before formal construction, so that the problem of edge folding and closing of quality reworking easily occurs in the construction process, the reworking rate is reduced, repeated construction is avoided, and the purpose of 'one-time survival' is achieved. Meanwhile, the overall display effect can be predicted, and the construction scheme can be guided.
The present invention is further preferred: the construction progress plan in S4 is compiled by project, and the information is added to the three-dimensional model by means of Navisvorks software.
The present invention is further preferred: and the EBIM platform mobile equipment is used for checking and accepting the quality and the safety of the field engineering, and the dynamic tracking and recording of quality and safety management are realized.
The present invention is further preferred: the EBIM platform uploads the BIM to the server after being lightened, and the PC end and the mobile end are mutually associated through the cloud platform, so that the work communication of each construction unit in safety, quality and other construction contents is realized, and the personnel operation management and quality management are greatly enhanced.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; such modifications and substitutions do not depart from the spirit and scope of the present invention, and they should be construed as being included in the following claims and description.

Claims (9)

1. A field construction management method based on BIM is characterized in that: the method comprises the following steps:
s1 deepening design: carrying out comprehensive collision inspection on buildings, structures and electromechanical equipment based on a BIM model in combination with construction operation specifications and a construction process; carrying out refined modeling on the project steel structure, and marking the specification, material, weight, axis and elevation information of the component; generating a secondary structure reserved hole map by using BIM after the comprehensive arrangement of pipelines is finished;
and S2 field layout management: planning, arranging, analyzing and optimizing site terrain, existing facilities, surrounding environment, construction area, temporary road and facilities, processing area, material yard, construction machinery and safe and civilized construction facilities in each construction stage based on the BIM model;
s3 group management: simulating, analyzing and optimizing a project construction scheme by adopting a BIM technology;
and S4 progress management: adding information into the three-dimensional model by combining the construction progress plan, performing 4D construction simulation through dynamic linkage of the plan progress model and the actual progress model, integrating the construction model with on-site facility, machinery, equipment and pipeline information, and checking the space and the space, wherein the space and time matching degree is obtained;
s5 materials, equipment management: on the basis of a BIM model, the BIM software is used for exporting various professional material and equipment lists, and bases are provided for material demand plans of different stages of a project;
s6, quality and safety management: performing analog simulation and scheme optimization on engineering quality and safety key control points based on a BIM model;
and S7 completion management: and adding completion acceptance information to the model based on the construction BIM model, and correcting according to completion requirements to further form a completion BIM model.
2. The BIM-based construction site management method according to claim 1, wherein: the refined modeling of the project steel structure in S1 is based on TEKLA software.
3. The BIM-based construction site management method according to claim 1, wherein: and after the project steel structure is refined and modeled in S1, counting the specifications and the quantity of materials required by a local area or a construction section, providing a basis for material planning, and providing a relevant basis for field level arrangement, tower crane model selection and climbing.
4. The BIM-based construction site management method according to claim 1, wherein: and S1, deeply arranging all water pipe wells and electric wells of the project, reasonably setting the positions of the supports and the pipelines in the well, and finally generating a two-dimensional drawing.
5. The BIM-based construction site management method according to claim 1, wherein: and S1, comprehensively arranging all machine rooms based on the BIM technology, and transmitting the machine rooms to field operators in a drawing mode.
6. The BIM-based construction site management method according to claim 1, wherein: and S3, the construction process is displayed in an animation demonstration mode before formal construction, so that the problem of edge folding and closing caused by quality reworking easily in the construction process is solved.
7. The BIM-based construction site management method according to claim 1, wherein: the construction progress plan in S4 is compiled by project, and the information is added to the three-dimensional model by means of Navisvorks software.
8. The BIM-based construction site management method according to claim 1, wherein: and the EBIM platform mobile equipment is used for checking and accepting the quality and the safety of the field engineering, and the dynamic tracking and recording of quality and safety management are realized.
9. The BIM-based construction site management method according to claim 8, wherein: and the EBIM platform uploads the BIM model to a server after the BIM model is lightened, and the PC end and the mobile end are mutually associated through the cloud platform.
CN202110106470.6A 2021-01-26 2021-01-26 BIM-based field construction management method Pending CN112884290A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110106470.6A CN112884290A (en) 2021-01-26 2021-01-26 BIM-based field construction management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110106470.6A CN112884290A (en) 2021-01-26 2021-01-26 BIM-based field construction management method

Publications (1)

Publication Number Publication Date
CN112884290A true CN112884290A (en) 2021-06-01

Family

ID=76052466

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110106470.6A Pending CN112884290A (en) 2021-01-26 2021-01-26 BIM-based field construction management method

Country Status (1)

Country Link
CN (1) CN112884290A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113434931A (en) * 2021-06-23 2021-09-24 安徽省交通控股集团有限公司 BIM technology-based highway construction safety management method
CN113536423A (en) * 2021-07-06 2021-10-22 国网江苏省电力有限公司建设分公司 Safety monitoring system and method based on three-dimensional steel structure ultrahigh tower construction
CN114580752A (en) * 2022-03-08 2022-06-03 武汉大博智能科技有限公司 Intelligent engineering construction progress management system based on BIM technology
CN116739309A (en) * 2023-08-09 2023-09-12 山东萌山钢构工程有限公司 Engineering construction cloud management system based on BIM three-dimensional modeling

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130335413A1 (en) * 2012-06-13 2013-12-19 National Chiao Tung University System and method for estimating construction duration
CN109165394A (en) * 2018-06-25 2019-01-08 中国人民解放军陆军工程大学 A kind of standardization BIM model lightweight implementation method
CN109543233A (en) * 2018-10-26 2019-03-29 中交第航务工程局有限公司 A kind of electromechanical pipeline assembly construction method based on BIM technology
CN110276555A (en) * 2019-06-26 2019-09-24 武昌工学院 Residential housing entity Life cycle analysis method based on internet and BIM
CN111461672A (en) * 2020-04-16 2020-07-28 山东交通职业学院 BIM technology-based tunnel equipment management method
CN111861358A (en) * 2019-12-11 2020-10-30 安徽建筑大学 Building information integration platform based on BIM technology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130335413A1 (en) * 2012-06-13 2013-12-19 National Chiao Tung University System and method for estimating construction duration
CN109165394A (en) * 2018-06-25 2019-01-08 中国人民解放军陆军工程大学 A kind of standardization BIM model lightweight implementation method
CN109543233A (en) * 2018-10-26 2019-03-29 中交第航务工程局有限公司 A kind of electromechanical pipeline assembly construction method based on BIM technology
CN110276555A (en) * 2019-06-26 2019-09-24 武昌工学院 Residential housing entity Life cycle analysis method based on internet and BIM
CN111861358A (en) * 2019-12-11 2020-10-30 安徽建筑大学 Building information integration platform based on BIM technology
CN111461672A (en) * 2020-04-16 2020-07-28 山东交通职业学院 BIM technology-based tunnel equipment management method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
冯善中 等: ""BIM 技术在工程管理中的综合应用研究"", 《安徽建筑》 *
罗鹏程 等: ""EPC模式下BIM 技术在房建项目中的应用"", 《四川建筑》 *
芦琴 等: ""谈BIM技术在土木工程的应用"", 《经济•管理•综述》 *
马勇军 等: ""基于BIM 技术的地铁机电施工中云平台应用"", 《四川建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113434931A (en) * 2021-06-23 2021-09-24 安徽省交通控股集团有限公司 BIM technology-based highway construction safety management method
CN113536423A (en) * 2021-07-06 2021-10-22 国网江苏省电力有限公司建设分公司 Safety monitoring system and method based on three-dimensional steel structure ultrahigh tower construction
CN114580752A (en) * 2022-03-08 2022-06-03 武汉大博智能科技有限公司 Intelligent engineering construction progress management system based on BIM technology
CN116739309A (en) * 2023-08-09 2023-09-12 山东萌山钢构工程有限公司 Engineering construction cloud management system based on BIM three-dimensional modeling

Similar Documents

Publication Publication Date Title
CN112884290A (en) BIM-based field construction management method
Wong et al. Toward low-carbon construction processes: the visualisation of predicted emission via virtual prototyping technology
Liu et al. Retracted: Using BIM to improve the design and construction of bridge projects: A case study of a long-span steel-box arch bridge project
CN109801038B (en) General engineering construction method based on BIM technology application
Kaner et al. Case studies of BIM adoption for precast concrete design by mid-sized structural engineering firms
Neelamkavil Automation in the prefab and modular construction industry
CN107958101A (en) A kind of assembled architecture Information Management System and method based on BIM
CN109544051A (en) A kind of construction management application platform based on BIM technology application
Pan et al. Stakeholder perceptions of the future application of construction robots for buildings in a dialectical system framework
CN111125814A (en) BIM-based project supervision and supervision method and system
KR20130016620A (en) 3d process management method for bim(building information modeling)
CN104978696A (en) Electronic acceptance and handover method based on BIM technology
CN110717685A (en) Building material management system and method
CN112465390A (en) BIM-based subway station construction progress management method
CN114036622A (en) BIM-based fabricated concrete building design and construction method
Begić et al. Digitalization and automation in construction project's life-cycle: a review.
Cai et al. Construction automation and robotics: From one-offs to follow-ups based on practices of Chinese construction companies
CN209486723U (en) A kind of construction management application platform based on BIM technology application
Laurini et al. Technology 4.0 for buildings management: from building site to the interactive building book
CN210072621U (en) BIM management-based deepened transformation system for vehicle section with ultra-large cover body
CN116562802A (en) Intelligent construction application platform of track traffic based on BIM
CN103628483B (en) The concrete dam pouring mechanically combining that puts in storage builds simulation and optimum method
CN115329416A (en) Building construction method based on BIM
CN114169044A (en) BIM + GIS-based construction site layout optimization method and system
CN112948913A (en) Electromechanical pipeline assembly type construction method based on BIM technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210601

RJ01 Rejection of invention patent application after publication