CN112766919A - Project management method for deep editing based on Gantt chart - Google Patents

Project management method for deep editing based on Gantt chart Download PDF

Info

Publication number
CN112766919A
CN112766919A CN202110109034.4A CN202110109034A CN112766919A CN 112766919 A CN112766919 A CN 112766919A CN 202110109034 A CN202110109034 A CN 202110109034A CN 112766919 A CN112766919 A CN 112766919A
Authority
CN
China
Prior art keywords
task
gantt chart
bar
draggable
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110109034.4A
Other languages
Chinese (zh)
Inventor
杨磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Urban And Rural Planning And Design Research Institute Co ltd
Original Assignee
Yiqian Architectural Technology Shanghai Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yiqian Architectural Technology Shanghai Co ltd filed Critical Yiqian Architectural Technology Shanghai Co ltd
Priority to CN202110109034.4A priority Critical patent/CN112766919A/en
Publication of CN112766919A publication Critical patent/CN112766919A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • G06F3/048Interaction techniques based on graphical user interfaces [GUI]
    • G06F3/0484Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range
    • G06F3/04845Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range for image manipulation, e.g. dragging, rotation, expansion or change of colour
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • G06F3/048Interaction techniques based on graphical user interfaces [GUI]
    • G06F3/0487Interaction techniques based on graphical user interfaces [GUI] using specific features provided by the input device, e.g. functions controlled by the rotation of a mouse with dual sensing arrangements, or of the nature of the input device, e.g. tap gestures based on pressure sensed by a digitiser
    • G06F3/0488Interaction techniques based on graphical user interfaces [GUI] using specific features provided by the input device, e.g. functions controlled by the rotation of a mouse with dual sensing arrangements, or of the nature of the input device, e.g. tap gestures based on pressure sensed by a digitiser using a touch-screen or digitiser, e.g. input of commands through traced gestures
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • General Engineering & Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Human Computer Interaction (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a project management method used for deep editing based on Gantt chart, wherein project tasks are displayed as a plurality of task bars in the Gantt chart, and the project management method comprises the following steps: setting a plurality of draggable tool units which are in one-to-one correspondence with a plurality of operation instructions, wherein the draggable tool units and the Gantt chart are displayed in the same page; when the draggable unit is dragged to the task bar or the time bar of the Gantt chart, calling the corresponding operation instruction to act on the task bar or the time bar so as to modify the Gantt chart.

Description

Project management method for deep editing based on Gantt chart
Technical Field
The invention belongs to the field of project management, and particularly relates to a project management method for deep editing based on Gantt charts.
Background
A project management system is software used by a project manager to manage projects. The project management system enables project managers to control various resources related to projects through links such as organization, planning, execution and monitoring, and finally achieves project objectives. With the development of internet technology, project management software is becoming an indispensable management tool for project managers.
Gantt charts, also known as cross-bar charts, are a very central tool in project management. The whole project flow can be finely managed by showing the time, personnel and resources of the project. With the development of internet technology, the gantt chart is transferred from off-line to on-line, and people can more conveniently use the gantt chart on-line to arrange personnel, time and work. In project management software, gantt charts are a frequently and widely used tool.
However, the use of gantt charts by current project management software only remains at the level of basic task time adjustment, staff assignment. The possibility of using Gantt charts is not deeply mined, so that project managers need to complete the whole project management by means of a plurality of other tools, such as an instant messaging tool, a calendar tool, a file transfer tool and the like. The operation cost of project managers is increased, and the efficiency of the whole project management is influenced.
Therefore, it is an urgent problem to solve how to reduce the communication cost and operation cost of people in project management by deeply mining the use possibility of the gantt chart, increase the management efficiency, and continuously improve the project management ability of people by tools.
Disclosure of Invention
In order to solve the problems in the prior art, the invention provides a project management method for deep editing and use based on a Gantt chart, and partial embodiments of the project management method can transplant originally dispersed functions to the Gantt chart, so that a user can directly use the Gantt chart to finish important operations of project management.
In order to achieve the purpose, the invention adopts the following technical scheme:
a project management method for use in a gantt chart-based deep editing, a project task being displayed as a plurality of task bars in the gantt chart, the project management method comprising: setting a plurality of draggable tool units which are in one-to-one correspondence with a plurality of operation instructions, wherein the draggable tool units and the Gantt chart are displayed in the same page; when the draggable unit is dragged to the task bar or the time bar of the Gantt chart, calling the corresponding operation instruction to act on the task bar or the time bar so as to modify the Gantt chart.
Preferably, the calling the corresponding operation instruction to act on the task bar or the time bar includes: and generating an input box in the page, wherein the input box is used for inputting parameters required by the operation instruction.
The parameters required by the operation instruction herein mean that the operations that the user can do in the input bullet box include, but are not limited to: enter text, paste links, adjust panel parameters (time, permission buttons … …), upload pictures, upload documents, share, etc. The generated input box may contain default parameters, or the user may directly use the default parameters without inputting.
Preferably, the operation instruction corresponding to the draggable unit is used for adding a task bar in a meeting. Further, the task bars of the meeting can be arranged in a vertical column and used for meeting with other task bars in the transverse direction. In parallel, the task bar of the meeting is arranged in the transverse direction, and other task bars and time bars are arranged in the longitudinal direction. In parallel, the angle between the task bar in the meeting and the other task bars is not equal to 90 °.
Preferably, the project management method includes: judging whether the task bar added with the conference has time overlap with other task bars; and screening out task executing personnel corresponding to the task bars overlapped in time according to a set rule, and using the task executing personnel as a personnel list for participating in the conference.
Preferably, the gantt chart can be presented to task performers according to predetermined rules, including: only the task bars associated with the task performers are shown on the gantt chart.
Preferably, the operation instruction corresponding to the draggable unit is used for extending the task bar.
Preferably, the project management method includes: for task executors who only have the permission of postponing application for tasks, after the task bar is executed to prolong the operation instruction of the task bar, the task bar enters a display state to be confirmed; and when a task executive person with the task postponing confirmation authority carries out a confirmation operation instruction on the task bar entering the display state to be confirmed, the task bar exits the display state to be confirmed.
A project management method for deep editing use based on Gantt charts, the project management system comprises: a Gantt chart displaying project tasks as a plurality of task bars in the Gantt chart; the draggable tool units are in one-to-one correspondence with the operating instructions, the draggable tool units and the Gantt chart are displayed in the same page, and when the draggable unit is dragged to the task bar or the time bar of the Gantt chart, the corresponding operating instructions are called to act on the task bar or the time bar so as to modify the Gantt chart; the storage device is used for storing Gantt chart information and operation instructions; and the computing device is used for visualizing the Gantt chart information into the Gantt chart and executing the operation instruction to modify the Gantt chart information.
Preferably, the storage device stores account information.
Compared with the prior art, the invention has the beneficial effects that: by deep use of each element on the Gantt chart, project management personnel can finish a series of important work of project management such as task editing, task scoring, reminding item issuing, team meeting organizing and the like without using other tools.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a flow chart illustrating a project management method according to the present invention.
Fig. 2 is a diagram of operations used to set a meeting for a time bar.
FIG. 3 is a diagram of operations for a task bar to defer tasks.
Fig. 4 is a schematic illustration of gantt chart.
1-a draggable unit; 2-task bar; 3-time bar.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without inventive effort based on the embodiments of the present invention, are within the scope of the present invention.
In the description of the present invention, it is to be understood that the terms "longitudinal", "lateral", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on those shown in the drawings, and are used merely for convenience of description and for simplicity of description, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed in a particular orientation, and be operated, and thus, are not to be construed as limiting the present invention. The tool elements of the gantt diagram are shown as rectangles, but other representations (circles, shapes, etc.) can be used without affecting the function they perform. The task bar is the same as the time bar.
Firstly, a project comprises a plurality of specific tasks, and each task comprises information such as task name, task time, task priority, task completion state, task performer and the like. The existing project management software can edit various information of the task only by clicking the task to enter a detail interface, or edit the task information by means of a table and then reflect the task information on a Gantt chart. However, the invention provides a function of directly editing tasks on the Gantt chart, so that a user can edit the detailed task information without switching pages.
Further, in addition to the editing function for the task itself, the user can edit and add information of the entire project through the provided draggable unit. Each draggable unit contains instruction information, a user drags the draggable unit to be placed on a target unit, the target unit can be a time point or a task, and the target unit receives the information contained in the draggable unit, can make corresponding feedback and is displayed on a Gantt chart. Through such dragging operations, a user can directly set a team meeting, generate reminders, mark project nodes, score project completion quality, and the like on the Gantt chart.
Through the simple and direct editing and operating modes, the user can quickly manage the project on the Gantt chart, the operating cost of the user is reduced, and a series of important project management functions such as editing, informing and reminding are quickly completed.
Dragging the draggable unit to the placeable unit through a certain medium (a mouse and a touch screen sliding mode), and after the draggable unit is detected and identified by the placeable unit, a user can specifically edit an instruction in the information input unit; and the information transmission unit sends data to the information processing unit, the information processing unit stores the related instruction data and sends the processing result to the feedback unit, and the feedback unit displays the related instruction information on the Gantt chart.
An embodiment of the present invention provides a system including:
the client, the client taking the browser as a carrier comprises: the Gantt chart module can drag a tool unit, can be placed in the tool unit and is an information input unit;
a server: an information transmission unit and an information processing unit;
background database: an information storage unit.
The Gantt chart is displayed on a Web page of a browser, elements of the Gantt chart page are rendered for display by using languages such as HTML, CSS and JavaScript, and the displayed content comprises a draggable tool unit, a placeable unit, an information input unit and the like.
The specific implementation method comprises the following steps:
step 1: and clicking a draggable tool unit on a browser Web page in a mouse or touch screen mode, and dragging the draggable tool unit to a placeable unit.
The technology comprises the following steps: and identifying mouse dragging action of a user on the browser and positioning of a placed unit by using browser technology and JavaScript.
Step 2: the placeable unit detects and identifies the operation instruction contained in the draggable tool unit.
The technology comprises the following steps: each draggable tool unit comprises an operation instruction, and the browser identifies the dragging operation instruction through JavaScript.
And step 3: the browser Web page generates an input box which can input or edit the relevant parameters of the operation instruction.
The technology comprises the following steps: the JavaScript identifies the dragging operation instruction, the browser performs feedback to generate default parameters after processing according to a set program, and optionally, an input box is provided for adjusting the default parameters.
(optional/optional step 3)
And 4, step 4: and sending the information data related to the operation instruction to the server.
The technology comprises the following steps: the JavaScript sends the parameter information data to the server through the network, and the server receives the operation instruction and the related parameter information and carries out processing calculation.
And 5: the background database stores information data processed by the server, the server sends the processing result to the client, and the information is displayed on the client Gantt chart.
The technology comprises the following steps: the server transmits the processed result data through the network
To the client browser. And rendering the information on the client Gantt chart in a visual mode through technologies such as JavaScript of a browser.
Although the present invention has been described in detail with respect to the above embodiments, it will be understood by those skilled in the art that modifications or improvements based on the disclosure of the present invention may be made without departing from the spirit and scope of the invention, and these modifications and improvements are within the spirit and scope of the invention.

Claims (9)

1. A project management method used by deep editing based on Gantt chart, wherein project tasks are displayed as a plurality of task bars in the Gantt chart, and the project management method comprises the following steps:
setting a plurality of draggable tool units which are in one-to-one correspondence with a plurality of operation instructions, wherein the draggable tool units and the Gantt chart are displayed in the same page;
when the draggable unit is dragged to the task bar or the time bar of the Gantt chart, calling the corresponding operation instruction to act on the task bar or the time bar so as to modify the Gantt chart.
2. The project management method for Gantt-graph-based deep editing use according to claim 1, wherein invoking the corresponding operation instruction to act on the task bar or the time bar comprises:
and generating an input box in the page, wherein the input box is used for inputting parameters required by the operation instruction.
3. The project management method for Gantt chart-based deep editing use according to claim 2, wherein the operation instruction corresponding to the draggable unit is used for adding a task bar for a meeting.
4. The method for managing a project used for gantt chart-based deep editing as claimed in claim 3, wherein the method for managing a project comprises:
judging whether the task bar added with the conference has time overlap with other task bars;
and screening out task executing personnel corresponding to the task bars overlapped in time according to a set rule, and using the task executing personnel as a personnel list for participating in the conference.
5. The method for project management based on Gantt chart deep editing use according to claim 4, wherein the Gantt chart can be displayed to task performers according to a predetermined rule, and the predetermined rule comprises: only the task bars associated with the task performers are shown on the gantt chart.
6. The project management method for Gantt chart-based deep editing use according to claim 2, wherein the operation instruction corresponding to the draggable unit is used for extending the task bar.
7. The method for managing a project used for gantt chart-based deep editing as claimed in claim 6, wherein the method for managing a project comprises:
for task executors who only have the permission of postponing application for tasks, after the task bar is executed to prolong the operation instruction of the task bar, the task bar enters a display state to be confirmed;
and when a task executive person with the task postponing confirmation authority carries out a confirmation operation instruction on the task bar entering the display state to be confirmed, the task bar exits the display state to be confirmed.
8. A project management system for use in deep editing based on gantt chart, the project management system comprising:
a Gantt chart displaying project tasks as a plurality of task bars in the Gantt chart;
the draggable tool units are in one-to-one correspondence with the operating instructions, the draggable tool units and the Gantt chart are displayed in the same page, and when the draggable unit is dragged to the task bar or the time bar of the Gantt chart, the corresponding operating instructions are called to act on the task bar or the time bar so as to modify the Gantt chart;
the storage device is used for storing Gantt chart information and operation instructions; and
a computing device to visualize the Gantt chart information as the Gantt chart, execute the operational instructions to modify the Gantt chart information.
9. The project management system for Gantt-chart-based deep editing use according to claim 8, wherein the storage device stores account information.
CN202110109034.4A 2021-01-27 2021-01-27 Project management method for deep editing based on Gantt chart Pending CN112766919A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110109034.4A CN112766919A (en) 2021-01-27 2021-01-27 Project management method for deep editing based on Gantt chart

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110109034.4A CN112766919A (en) 2021-01-27 2021-01-27 Project management method for deep editing based on Gantt chart

Publications (1)

Publication Number Publication Date
CN112766919A true CN112766919A (en) 2021-05-07

Family

ID=75706003

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110109034.4A Pending CN112766919A (en) 2021-01-27 2021-01-27 Project management method for deep editing based on Gantt chart

Country Status (1)

Country Link
CN (1) CN112766919A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114219372A (en) * 2021-11-01 2022-03-22 佛山技研智联科技有限公司 Gantt chart processing method and device, computer equipment and storage medium

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0830686A (en) * 1994-07-14 1996-02-02 Yokogawa Electric Corp Scheduling system
KR20010001198A (en) * 1999-06-02 2001-01-05 구자홍 Video browsing system based on event
US20020120489A1 (en) * 2001-02-28 2002-08-29 Kazuyuki Matsuda Method and apparatus for managing information
US20040119713A1 (en) * 2002-12-20 2004-06-24 Michael Meyringer Interactive and web-based Gantt Chart
JP2004310273A (en) * 2003-04-03 2004-11-04 Sony Corp Device, method and program for supporting group work and storage medium
JP2011013958A (en) * 2009-07-02 2011-01-20 Tsuneo Ogawa Method for providing cost management of communication between tasks having dependent relation in project
US8863021B1 (en) * 2012-07-26 2014-10-14 Google Inc. Scheduling calendar events for tasks
US20170061360A1 (en) * 2015-09-01 2017-03-02 SmartSheet.com, Inc. Interactive charts with dynamic progress monitoring, notification, and resource allocation
JP2017107355A (en) * 2015-12-09 2017-06-15 株式会社神戸製鋼所 Schedule creation support device and method
JP2018196979A (en) * 2017-05-22 2018-12-13 株式会社アートプリントジャパン schedule book
CN109918157A (en) * 2019-01-08 2019-06-21 北京航天飞行控制中心 Operation processing method and device
CN110751456A (en) * 2019-09-20 2020-02-04 北京恒亿慧通科技有限公司 Project management system

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0830686A (en) * 1994-07-14 1996-02-02 Yokogawa Electric Corp Scheduling system
KR20010001198A (en) * 1999-06-02 2001-01-05 구자홍 Video browsing system based on event
US20020120489A1 (en) * 2001-02-28 2002-08-29 Kazuyuki Matsuda Method and apparatus for managing information
US20040119713A1 (en) * 2002-12-20 2004-06-24 Michael Meyringer Interactive and web-based Gantt Chart
JP2004310273A (en) * 2003-04-03 2004-11-04 Sony Corp Device, method and program for supporting group work and storage medium
JP2011013958A (en) * 2009-07-02 2011-01-20 Tsuneo Ogawa Method for providing cost management of communication between tasks having dependent relation in project
US8863021B1 (en) * 2012-07-26 2014-10-14 Google Inc. Scheduling calendar events for tasks
US20170061360A1 (en) * 2015-09-01 2017-03-02 SmartSheet.com, Inc. Interactive charts with dynamic progress monitoring, notification, and resource allocation
JP2017107355A (en) * 2015-12-09 2017-06-15 株式会社神戸製鋼所 Schedule creation support device and method
JP2018196979A (en) * 2017-05-22 2018-12-13 株式会社アートプリントジャパン schedule book
CN109918157A (en) * 2019-01-08 2019-06-21 北京航天飞行控制中心 Operation processing method and device
CN110751456A (en) * 2019-09-20 2020-02-04 北京恒亿慧通科技有限公司 Project management system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《自动自发的工作》: "《自动自发的工作》", 31 December 2008, 《自动自发的工作》, pages: 134 *
卡尔·T.犹里齐等: "《产品设计与开发》", 31 May 2009, 卡尔·T.犹里齐等 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114219372A (en) * 2021-11-01 2022-03-22 佛山技研智联科技有限公司 Gantt chart processing method and device, computer equipment and storage medium

Similar Documents

Publication Publication Date Title
US7168045B2 (en) Modeling business objects
US20170083290A1 (en) Integrated System for Software Application Development
US7519539B1 (en) Assisted profiling of skills in an enterprise management system
US20040002887A1 (en) Presenting skills distribution data for a business enterprise
US6754674B2 (en) Method and apparatus for creation and maintenance of incident crisis response plans
US9052812B1 (en) System for exportable graphical designs with interactive linked comments between design and playback environments
US8924842B2 (en) Method and system to build interactive documents
US20090048981A1 (en) SiteWare a 3D (x,y,z dimensions) 4D (time;past(s), present future(s)) & 5D (Business Rules) infrastructure business intelligence and configuration management solution managing all enterprise physical and logical assets characteristics and relationships
US20070288865A1 (en) Information processing apparatus for project management and its computer software
WO2008100948A1 (en) Interactive graphics-based planning systems
US20120191507A1 (en) System for unifying and collaborating new product development activities across a disparate set of users
CN112070450A (en) TCM system
CN112766920A (en) Method for bidirectional influence of list and Gantt chart
EP4092514A1 (en) Systems and methods for asynchronous sub-window interaction in application views
CN112766919A (en) Project management method for deep editing based on Gantt chart
US20120310711A1 (en) System using feedback comments linked to performance document content
Terenghi et al. Virtual Obeya: A new collaborative web application for running lean management workshops
JP7328195B2 (en) Construction work plan support system
JP2017182405A (en) Business management device, information processing method, and business management program
US20160314103A1 (en) Computer System for Generation of Electronic Checklists
CN115564397A (en) Automatic model management method suitable for three-dimensional collaborative design platform
US9002958B2 (en) Performance management system using unsolicited feedback
US20020194044A1 (en) Computerized systems and methods for performing new product introductions
Matsumoto et al. Use of process maps to develop a management briefing sheet for a design consultancy
US10200496B2 (en) User interface configuration tool

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20221221

Address after: No. 298, Wenhua North Road, Huiji District, Zhengzhou, Henan 450040

Applicant after: Henan urban and rural planning and Design Research Institute Co.,Ltd.

Address before: Room 1044, Building 9, No. 891 Lingshi Road, Jing'an District, Shanghai 200040

Applicant before: YIQIAN ARCHITECTURAL TECHNOLOGY (SHANGHAI) Co.,Ltd.