CN112418650A - Method and device for determining petroleum drilling construction progress - Google Patents

Method and device for determining petroleum drilling construction progress Download PDF

Info

Publication number
CN112418650A
CN112418650A CN202011300237.3A CN202011300237A CN112418650A CN 112418650 A CN112418650 A CN 112418650A CN 202011300237 A CN202011300237 A CN 202011300237A CN 112418650 A CN112418650 A CN 112418650A
Authority
CN
China
Prior art keywords
drilling
actual
designed
days
design
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011300237.3A
Other languages
Chinese (zh)
Inventor
赵彤
张彦龙
葛云华
于洋
彭文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Engineering Technology R&D Co Ltd
Original Assignee
China National Petroleum Corp
CNPC Engineering Technology R&D Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Petroleum Corp, CNPC Engineering Technology R&D Co Ltd filed Critical China National Petroleum Corp
Priority to CN202011300237.3A priority Critical patent/CN112418650A/en
Publication of CN112418650A publication Critical patent/CN112418650A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Forestry; Mining

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Primary Health Care (AREA)
  • Animal Husbandry (AREA)
  • General Health & Medical Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Marine Sciences & Fisheries (AREA)
  • Agronomy & Crop Science (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method and a device for determining the construction progress of petroleum drilling, wherein the method comprises the following steps: obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project; obtaining the actual drilling depth and the actual completion period of the petroleum drilling project; for the drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth with the designed drilling depth of the drilling stage, and comparing the actual completion period with the designed completion period; determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days; according to the actual construction days and the design construction days, the construction progress is determined to be advanced or delayed, the method can automatically determine the actual drilling depth and the design construction days corresponding to the actual completion period, the advance or delay automatic judgment of the construction progress is realized, and the calculation efficiency and the accuracy of the petroleum drilling construction progress are improved.

Description

Method and device for determining petroleum drilling construction progress
Technical Field
The invention relates to the technical field of construction progress tracking, in particular to a method and a device for determining the construction progress of petroleum drilling.
Background
The construction progress of petroleum drilling directly influences the increasing, storing, building and production progress of oil and gas field enterprises and the project investment cost, and is also closely related to the production and operation of petroleum drilling companies. At present, the tracking of drilling construction progress is mainly realized through two kinds of modes, a mode is to draw paper construction progress chart according to traditional coordinate graph form, the condition of delaying in advance of single well construction progress is known to drilling well site technical staff through the mode of counting the coordinate check, another kind of mode is to draw the electron construction progress coordinate graph on the drilling company line, the technical staff knows the condition of delaying in advance of single well construction progress through the mode of counting the coordinate check on the line, because oil drilling construction is often the construction of multiwell, prior art adopts the mode of counting the coordinate check artificially, make the efficiency of tracking of drilling construction progress lower, also there is the problem because the human error leads to the wrong calculation of drilling construction progress simultaneously.
In view of the above problems, no effective solution has been proposed.
Disclosure of Invention
The embodiment of the invention provides a method for determining the construction progress of an oil drilling, which is used for improving the calculation efficiency and accuracy of the construction progress of the oil drilling and comprises the following steps:
obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
obtaining the actual drilling depth and the actual completion period of the petroleum drilling project;
for the drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth with the designed drilling depth of the drilling stage, and comparing the actual completion period with the designed completion period;
determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days;
and determining that the construction progress is advanced or lagged according to the actual construction days and the design construction days.
The embodiment of the invention provides a device for determining the construction progress of oil drilling, which is used for improving the calculation efficiency and accuracy of the construction progress of the oil drilling, and comprises the following components:
the design parameter obtaining module is used for obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
the construction parameter obtaining module is used for obtaining the actual drilling depth and the actual completion period of the petroleum drilling project;
the comparison module is used for comparing the actual drilling depth with the designed drilling depth of the drilling stage and comparing the actual completion period with the designed completion period for the drilling stage to which the actual drilling depth belongs;
the design construction days determination module is used for determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days;
and the construction progress determining module is used for determining whether the construction progress is ahead or behind according to the actual construction days and the design construction days.
The embodiment of the invention also provides computer equipment which comprises a memory, a processor and a computer program which is stored on the memory and can run on the processor, wherein the processor realizes the method for determining the construction progress of the petroleum drilling when executing the computer program.
Embodiments of the present invention also provide a computer-readable storage medium storing a computer program for executing the method for determining an oil drilling construction progress.
The embodiment of the invention comprises the following steps: obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project; obtaining the actual drilling depth and the actual completion period of the petroleum drilling project; for the drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth with the designed drilling depth of the drilling stage, and comparing the actual completion period with the designed completion period; determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days; according to the method, the actual drilling depth is compared with the designed drilling depth, the actual completion period is compared with the designed completion period, the designed construction days corresponding to the actual drilling depth and the actual completion period can be automatically determined, the advance or delay automatic judgment of the construction progress is further realized, the manual workload is reduced, and the calculation efficiency and accuracy of the petroleum drilling construction progress are improved.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts. In the drawings:
FIG. 1 is a schematic diagram of a method for determining the progress of oil drilling in an embodiment of the invention;
FIG. 2 is a schematic view of construction progress coordinates corresponding to an actual drilling depth less than the designed drilling depth at the drilling stage and an actual completion period of zero;
FIG. 3 is a schematic diagram of construction progress coordinates corresponding to an actual drilling depth greater than the designed drilling depth at the drilling stage and an actual completion period of zero;
FIG. 4 is a schematic diagram of construction progress coordinates corresponding to an actual drilling depth less than the designed drilling depth at the drilling stage and an actual completion period not equal to zero;
FIG. 5 is a schematic diagram of construction progress coordinates corresponding to an actual drilling depth greater than the designed drilling depth at the drilling stage and an actual completion period not being zero;
fig. 6 is a schematic diagram of the structure of the device for determining the construction progress of oil drilling in the embodiment of the invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As will be appreciated by one skilled in the art, embodiments of the present invention may be embodied as a system, apparatus, method or computer program product. Accordingly, the present disclosure may be embodied in the form of: entirely hardware, entirely software (including firmware, resident software, micro-code, etc.), or a combination of hardware and software.
In order to solve the technical problem that the drilling construction progress is determined by adopting an artificial number coordinate grid mode in the prior art, so that the efficiency and the accuracy of tracking the drilling construction progress are low, an embodiment of the invention provides a method for determining the oil drilling construction progress, which is used for improving the calculation efficiency and the accuracy of the oil drilling construction progress, fig. 1 is a schematic diagram of a flow of the method for determining the oil drilling construction progress in the embodiment of the invention, and as shown in fig. 1, the method comprises the following steps:
step 101: obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
step 102: obtaining the actual drilling depth and the actual completion period of the petroleum drilling project;
step 103: for the drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth with the designed drilling depth of the drilling stage, and comparing the actual completion period with the designed completion period;
step 104: determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days;
step 105: and determining that the construction progress is advanced or lagged according to the actual construction days and the design construction days.
As shown in fig. 1, an embodiment of the present invention is implemented by: obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project; obtaining the actual drilling depth and the actual completion period of the petroleum drilling project; for the drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth with the designed drilling depth of the drilling stage, and comparing the actual completion period with the designed completion period; determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days; according to the method, the actual drilling depth is compared with the designed drilling depth, the actual completion period is compared with the designed completion period, the designed construction days corresponding to the actual drilling depth and the actual completion period can be automatically determined, the advance or delay automatic judgment of the construction progress is further realized, the manual workload is reduced, and the calculation efficiency and accuracy of the petroleum drilling construction progress are improved.
In one embodiment, the method further comprises:
drawing a design progress coordinate graph according to the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
and drawing an actual progress coordinate graph according to the actual drilling depth and the actual completion period.
In specific implementation, in step 101, the oil drilling engineering design progress data may be first stored in a structured database, where the design progress data may include: designing the drilling depth, designing the drilling days, and designing the completion period, then drawing a design progress coordinate graph according to the design progress data, fig. 2 is a construction progress coordinate schematic diagram corresponding to the actual drilling depth being less than the design drilling depth of the drilling stage and the actual completion period being zero, as shown in fig. 2, the ordinate is the well depth, the abscissa is the days, the line segment with lighter color is the design progress line segment, in the design progress line segment, the days and the well depth of each drilling stage are different, the well depth of the completion operation stage is unchanged, in step 102, the actual construction data of the oil drilling project can be obtained, and the actual construction data can include: and (3) actual drilling depth and actual completion period, and then drawing an actual progress coordinate graph, wherein if a line segment with a darker color in fig. 2 is an actual progress line segment, the actual construction progress and the design construction progress have certain deviation in the drilling depth and the actual completion period, so that the calculation modes of the design construction days under different working conditions are different, and further comparison is needed to determine the design construction days.
In one embodiment, for the drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth with the design drilling depth of the drilling stage, and comparing the actual completion period with the design completion period in step 103 may include:
comparing the actual drilling depth with the designed drilling depth of the drilling stage according to the designed progress coordinate graph and the actual progress coordinate graph, and comparing the actual completion period with the designed completion period.
In specific implementation, in step 103, based on the design progress coordinate graph and the actual progress coordinate graph, for the drilling stage to which the actual drilling depth belongs, the actual drilling depth may be compared with the design drilling depth of the drilling stage, the actual completion period may be compared with the design completion period, and then, according to the comparison result, calculation modes of the design construction days under four different working conditions are determined.
In one embodiment, the step 104 of determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days may include:
and for the drilling stage to which the actual drilling depth belongs, determining the design drilling days corresponding to the actual drilling depth as the design construction days when the actual drilling depth is less than the design drilling depth of the drilling stage and the actual completion period is zero.
In specific implementation, as shown in fig. 2, the actual drilling depth is less than the designed drilling depth of the drilling stage, and the actual completion period is zero, then the designed construction days PpThe number of days P2 for actual drilling depth corresponds to the design drilling days, i.e. Pp=P2。
In one embodiment, the step 104 of determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days may include:
and for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion cycle is zero, determining the difference between the designed drilling days corresponding to the actual drilling depth and the designed completion cycle as the designed construction days.
In specific implementation, fig. 3 is a schematic diagram of a construction progress coordinate corresponding to an actual drilling depth greater than a designed drilling depth of the drilling stage and an actual completion period of zero, as shown in fig. 3, the actual drilling depth is greater than the designed drilling depth of the drilling stage, the actual completion period of zero, a number of designed drilling days corresponding to the actual drilling depth is P2, the designed completion period is P4-P3, and a number of designed construction days is PpThe difference between the number of days of drilling and the completion period in the design, P, corresponding to the actual drilling depthp=P2-(P4-P3)。
In one embodiment, the step 104 of determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days may include:
for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is smaller than the designed drilling depth of the drilling stage, and the actual completion period is larger than zero and smaller than the designed completion period, determining the sum of the designed drilling days corresponding to the actual drilling depth and the actual completion period as the designed construction days;
and when the actual drilling depth is less than the designed drilling depth of the drilling stage and the actual completion period is greater than or equal to the designed completion period, determining the sum of the designed drilling days corresponding to the actual drilling depth and the designed completion period as the designed construction days.
In specific implementation, fig. 4 is a schematic diagram of a construction progress coordinate corresponding to an actual drilling depth being smaller than a designed drilling depth of the drilling stage and an actual completion period being not zero, as shown in fig. 4, the actual drilling depth being smaller than the designed drilling depth of the drilling stage and the actual completion period being not zero, the designed drilling days P3 corresponding to the actual drilling depth, the actual completion period being P2-P1 and the designed completion period being P5-P4, the actual completion period and the designed completion period need to be first compared, and when the actual completion period is larger than zero and smaller than the designed completion period, that is, 0<P2-P1<P5-P4, design construction days PpThe sum of the number of drilling days of the design corresponding to the actual drilling depth and the actual completion period, i.e. PpP3+ (P2-P1), when the actual period is more than or equal to the design period, namely P2-P1 is more than or equal to P5-P4, the design construction days PpThe sum of the number of drilling days of the design corresponding to the actual drilling depth and the completion period in the design, i.e. Pp=P3+(P5-P4)。
In one embodiment, the step 104 of determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days may include:
for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion period is greater than zero and less than the designed completion period, subtracting the designed completion period from the designed drilling days corresponding to the actual drilling depth, and adding the actual completion period to obtain the designed construction days;
and when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion period is greater than or equal to the designed completion period, determining the designed drilling days corresponding to the actual drilling depth as the designed construction days.
In specific implementation, fig. 5 is a schematic diagram of a construction progress coordinate corresponding to an actual drilling depth greater than a designed drilling depth of the drilling stage and an actual completion period not being zero, as shown in fig. 5, the actual drilling depth is greater than the designed drilling depth of the drilling stage, the actual completion period is not zero, the designed drilling days P5 corresponding to the actual drilling depth, the actual completion period is P3-P1, and the designed completion period is P4-P2, the actual completion period and the designed completion period need to be first compared, and when the actual completion period is greater than zero and less than the designed completion period, that is, 0<P3-P1<P4-P2, design construction days PpSubtracting the design completion period from the design drilling days corresponding to the actual drilling depth, and adding the actual completion period, namely PpP5- (P4-P2) + (P3-P1), when the actual finished cycle is more than or equal to the design finished cycle, namely P3-P1 is more than or equal to P4-P2, the design construction days PpThe number of days of drilling of the design corresponding to the actual drilling depth, i.e. Pp=P5。
In one embodiment, the step 105 of determining whether the construction progress is advanced or delayed according to the actual construction days and the design construction days may include:
determining that the construction progress is delayed when the actual construction days are more than the design construction days;
and when the actual construction days are less than the design construction days, determining that the construction progress is advanced.
In specific implementation, as shown in fig. 2 to 5, after the design construction days are determined based on the actual working conditions, the actual construction days P may be determineddAnd design construction days PpComparing, when the actual construction days are more than the design construction days, determining that the construction progress is delayed, when the actual construction days are less than the design construction days, determining that the construction progress is advanced, and according to PdAnd PpThe difference between the two values is used for calculating the advancing amount or the retarding amount, so that the automatic judgment of the advancing or retarding of the construction progress of a plurality of wells can be realized.
Based on the same inventive concept, the embodiment of the invention also provides a device for determining the construction progress of oil drilling, and the device is as follows. Because the principle of solving the problems of the device for determining the petroleum drilling construction progress is similar to the method for determining the petroleum drilling construction progress, the implementation of the device can refer to the implementation of the method, and repeated parts are not repeated. As used hereinafter, the term "unit" or "module" may be a combination of software and/or hardware that implements a predetermined function. Although the means described in the embodiments below are preferably implemented in software, an implementation in hardware, or a combination of software and hardware is also possible and contemplated.
An embodiment of the present invention provides an apparatus for determining an oil drilling construction progress, which is used to improve the calculation efficiency and accuracy of the oil drilling construction progress, fig. 6 is a schematic diagram of a structure of the apparatus for determining an oil drilling construction progress in an embodiment of the present invention, and as shown in fig. 6, the apparatus includes:
the design parameter obtaining module 01 is used for obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
a construction parameter obtaining module 02 for obtaining the actual drilling depth and the actual completion period of the petroleum drilling project;
the comparison module 03 is used for comparing the actual drilling depth with the designed drilling depth of the drilling stage and comparing the actual completion period with the designed completion period for the drilling stage to which the actual drilling depth belongs;
the design construction days determination module 04 is used for determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days;
and the construction progress determining module 05 is used for determining that the construction progress is advanced or lagged according to the actual construction days and the design construction days by the construction progress determining module.
In one embodiment, the design construction days determination module 04 is specifically configured to:
and for the drilling stage to which the actual drilling depth belongs, determining the design drilling days corresponding to the actual drilling depth as the design construction days when the actual drilling depth is less than the design drilling depth of the drilling stage and the actual completion period is zero.
In one embodiment, the design construction days determination module 04 is specifically configured to:
and for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion cycle is zero, determining the difference between the designed drilling days corresponding to the actual drilling depth and the designed completion cycle as the designed construction days.
In one embodiment, the design construction days determination module 04 is specifically configured to:
for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is smaller than the designed drilling depth of the drilling stage, and the actual completion period is larger than zero and smaller than the designed completion period, determining the sum of the designed drilling days corresponding to the actual drilling depth and the actual completion period as the designed construction days;
and when the actual drilling depth is less than the designed drilling depth of the drilling stage and the actual completion period is greater than or equal to the designed completion period, determining the sum of the designed drilling days corresponding to the actual drilling depth and the designed completion period as the designed construction days.
In one embodiment, the design construction days determination module 04 is specifically configured to:
for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion period is greater than zero and less than the designed completion period, subtracting the designed completion period from the designed drilling days corresponding to the actual drilling depth, and adding the actual completion period to obtain the designed construction days;
and when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion period is greater than or equal to the designed completion period, determining the designed drilling days corresponding to the actual drilling depth as the designed construction days.
In one embodiment, the construction progress determining module 05 is specifically configured to:
determining that the construction progress is delayed when the actual construction days are more than the design construction days;
and when the actual construction days are less than the design construction days, determining that the construction progress is advanced.
In one embodiment, further comprising: a coordinate drawing module 06 for
Drawing a design progress coordinate graph according to the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
drawing an actual progress coordinate graph according to the actual drilling depth and the actual completion period;
the comparing module 03 is specifically configured to:
comparing the actual drilling depth with the designed drilling depth of the drilling stage according to the designed progress coordinate graph and the actual progress coordinate graph, and comparing the actual completion period with the designed completion period.
The embodiment of the invention also provides computer equipment which comprises a memory, a processor and a computer program which is stored on the memory and can run on the processor, wherein the processor realizes the method for determining the construction progress of the petroleum drilling when executing the computer program.
Embodiments of the present invention also provide a computer-readable storage medium storing a computer program for executing the method for determining an oil drilling construction progress.
The method and the device for determining the petroleum drilling construction progress are suitable for various drilling machines of 20 DJ-90 DJ, are suitable for monitoring the drilling construction progress in a timing and real-time mode, are suitable for monitoring the drilling construction progress of single wells and multiple wells, and are suitable for being applied to occasions such as drilling well sites, remote operation centers, PCs (personal computer) and mobile phone APPs (application program). The construction dynamic of all operation wells governed by an operation company can be comprehensively tracked, wells with serious complex accidents can be timely positioned, service experts are organized to make consultation decision and remotely support to eliminate problems, excellent drilling process methods and matched tools are quickly identified, excellent experience is promoted, further, the petroleum drilling engineering is promoted to reduce the occurrence rate and the disposal cost of the complex accidents, the drilling speed is increased, and the purpose of increasing the speed and the efficiency is finally achieved.
After the method and the device for determining the construction progress of the petroleum drilling well, which are provided by the embodiment of the invention, are specifically applied, the full life cycle construction progress automatic tracking of thousands of wells is realized, and the construction abnormity of hundreds of wells is intelligently pushed out; the automatic tracking time interval of the drilling construction progress is changed from once a month to real-time tracking, for example: in the prior art, 20 workers are required to count for 1 day when tracking the construction progress of 500 wells, and the advance or the lag for calculating the construction progress of 500 wells is only 30 seconds, so that the calculation efficiency and the accuracy of the petroleum drilling construction progress are obviously improved.
In summary, the embodiment of the present invention provides: obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project; obtaining the actual drilling depth and the actual completion period of the petroleum drilling project; for the drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth with the designed drilling depth of the drilling stage, and comparing the actual completion period with the designed completion period; determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days; according to the method, the actual drilling depth is compared with the designed drilling depth, the actual completion period is compared with the designed completion period, the designed construction days corresponding to the actual drilling depth and the actual completion period can be automatically determined, the advance or delay automatic judgment of the construction progress is further realized, the manual workload is reduced, and the calculation efficiency and accuracy of the petroleum drilling construction progress are improved.
As will be appreciated by one skilled in the art, embodiments of the present invention may be provided as a method, system, or computer program product. Accordingly, the present invention may take the form of an entirely hardware embodiment, an entirely software embodiment or an embodiment combining software and hardware aspects. Furthermore, the present invention may take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, and the like) having computer-usable program code embodied therein.
The present invention is described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the invention. It will be understood that each flow and/or block of the flow diagrams and/or block diagrams, and combinations of flows and/or blocks in the flow diagrams and/or block diagrams, can be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general purpose computer, special purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, create means for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be stored in a computer-readable memory that can direct a computer or other programmable data processing apparatus to function in a particular manner, such that the instructions stored in the computer-readable memory produce an article of manufacture including instruction means which implement the function specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be loaded onto a computer or other programmable data processing apparatus to cause a series of operational steps to be performed on the computer or other programmable apparatus to produce a computer implemented process such that the instructions which execute on the computer or other programmable apparatus provide steps for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention, and various modifications and variations of the embodiment of the present invention may occur to those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (14)

1. A method of determining an oil drilling construction progress, comprising:
obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
obtaining the actual drilling depth and the actual completion period of the petroleum drilling project;
for the drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth with the designed drilling depth of the drilling stage, and comparing the actual completion period with the designed completion period;
determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days;
and determining that the construction progress is advanced or lagged according to the actual construction days and the design construction days.
2. The method of claim 1, wherein determining the design construction days corresponding to the actual drilling depth and the actual completion cycle based on the comparison and the design drilling days comprises:
and for the drilling stage to which the actual drilling depth belongs, determining the design drilling days corresponding to the actual drilling depth as the design construction days when the actual drilling depth is less than the design drilling depth of the drilling stage and the actual completion period is zero.
3. The method of claim 1, wherein determining the design construction days corresponding to the actual drilling depth and the actual completion cycle based on the comparison and the design drilling days comprises:
and for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion cycle is zero, determining the difference between the designed drilling days corresponding to the actual drilling depth and the designed completion cycle as the designed construction days.
4. The method of claim 1, wherein determining the design construction days corresponding to the actual drilling depth and the actual completion cycle based on the comparison and the design drilling days comprises:
for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is smaller than the designed drilling depth of the drilling stage, and the actual completion period is larger than zero and smaller than the designed completion period, determining the sum of the designed drilling days corresponding to the actual drilling depth and the actual completion period as the designed construction days;
and when the actual drilling depth is less than the designed drilling depth of the drilling stage and the actual completion period is greater than or equal to the designed completion period, determining the sum of the designed drilling days corresponding to the actual drilling depth and the designed completion period as the designed construction days.
5. The method of claim 1, wherein determining the design construction days corresponding to the actual drilling depth and the actual completion cycle based on the comparison and the design drilling days comprises:
for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion period is greater than zero and less than the designed completion period, subtracting the designed completion period from the designed drilling days corresponding to the actual drilling depth, and adding the actual completion period to obtain the designed construction days;
and when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion period is greater than or equal to the designed completion period, determining the designed drilling days corresponding to the actual drilling depth as the designed construction days.
6. The method of claim 1, wherein determining whether construction progress is early or late based on actual construction days and design construction days comprises:
determining that the construction progress is delayed when the actual construction days are more than the design construction days;
and when the actual construction days are less than the design construction days, determining that the construction progress is advanced.
7. The method of claim 1, further comprising:
drawing a design progress coordinate graph according to the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
drawing an actual progress coordinate graph according to the actual drilling depth and the actual completion period;
for a drilling stage to which the actual drilling depth belongs, comparing the actual drilling depth to a design drilling depth for the drilling stage, and comparing the actual completion period to the design completion period, comprising:
comparing the actual drilling depth with the designed drilling depth of the drilling stage according to the designed progress coordinate graph and the actual progress coordinate graph, and comparing the actual completion period with the designed completion period.
8. An apparatus for determining the progress of an oil drilling operation, comprising:
the design parameter obtaining module is used for obtaining the design drilling depth, the design drilling days and the design completion period of each drilling stage of the petroleum drilling project;
the construction parameter obtaining module is used for obtaining the actual drilling depth and the actual completion period of the petroleum drilling project;
the comparison module is used for comparing the actual drilling depth with the designed drilling depth of the drilling stage and comparing the actual completion period with the designed completion period for the drilling stage to which the actual drilling depth belongs;
the design construction days determination module is used for determining the actual drilling depth and the design construction days corresponding to the actual completion period according to the comparison result and the design drilling days;
and the construction progress determining module is used for determining whether the construction progress is ahead or behind according to the actual construction days and the design construction days.
9. The apparatus of claim 8, wherein the construction days determination module is designed to:
and for the drilling stage to which the actual drilling depth belongs, determining the design drilling days corresponding to the actual drilling depth as the design construction days when the actual drilling depth is less than the design drilling depth of the drilling stage and the actual completion period is zero.
10. The apparatus of claim 8, wherein the construction days determination module is designed to:
and for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion cycle is zero, determining the difference between the designed drilling days corresponding to the actual drilling depth and the designed completion cycle as the designed construction days.
11. The apparatus of claim 8, wherein the construction days determination module is designed to:
for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is smaller than the designed drilling depth of the drilling stage, and the actual completion period is larger than zero and smaller than the designed completion period, determining the sum of the designed drilling days corresponding to the actual drilling depth and the actual completion period as the designed construction days;
and when the actual drilling depth is less than the designed drilling depth of the drilling stage and the actual completion period is greater than or equal to the designed completion period, determining the sum of the designed drilling days corresponding to the actual drilling depth and the designed completion period as the designed construction days.
12. The apparatus of claim 8, wherein the construction days determination module is designed to:
for the drilling stage to which the actual drilling depth belongs, when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion period is greater than zero and less than the designed completion period, subtracting the designed completion period from the designed drilling days corresponding to the actual drilling depth, and adding the actual completion period to obtain the designed construction days;
and when the actual drilling depth is greater than the designed drilling depth of the drilling stage and the actual completion period is greater than or equal to the designed completion period, determining the designed drilling days corresponding to the actual drilling depth as the designed construction days.
13. A computer device comprising a memory, a processor and a computer program stored on the memory and executable on the processor, wherein the processor implements the method of any one of claims 1 to 7 when executing the computer program.
14. A computer-readable storage medium, characterized in that the computer-readable storage medium stores a computer program for executing the method of any one of claims 1 to 7.
CN202011300237.3A 2020-11-19 2020-11-19 Method and device for determining petroleum drilling construction progress Pending CN112418650A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011300237.3A CN112418650A (en) 2020-11-19 2020-11-19 Method and device for determining petroleum drilling construction progress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011300237.3A CN112418650A (en) 2020-11-19 2020-11-19 Method and device for determining petroleum drilling construction progress

Publications (1)

Publication Number Publication Date
CN112418650A true CN112418650A (en) 2021-02-26

Family

ID=74773556

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011300237.3A Pending CN112418650A (en) 2020-11-19 2020-11-19 Method and device for determining petroleum drilling construction progress

Country Status (1)

Country Link
CN (1) CN112418650A (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100968709B1 (en) * 2010-04-14 2010-07-06 지에스건설 주식회사 Method to obtain the required completion percentage of milestone in construction project, method to establish the milestone schedule and evaluation method for established milestone schedule
DE102009011600A1 (en) * 2009-03-03 2010-09-16 Convia Gmbh Method for determining thermal conductivity of soil layers along vertical borehole, involves carrying out determination of thermal conductivity of each soil layer at each remote drilling tool by measuring device in partial manner
US20140207512A1 (en) * 2013-01-24 2014-07-24 DPR Construction Timeline-Based Visual Dashboard For Construction
CN104481398A (en) * 2014-12-10 2015-04-01 中国石油化工股份有限公司 Three-dimensional (3D) horizontal well drilling construction method
CN106156389A (en) * 2015-04-17 2016-11-23 普拉德研究及开发股份有限公司 For the well planning automatically performed
CN106761602A (en) * 2016-12-28 2017-05-31 中国石油天然气股份有限公司 The method and apparatus for determining oil well production operating mode
CN107237601A (en) * 2016-03-28 2017-10-10 中国石油化工股份有限公司 A kind of shale gas batch production wellbore construction method
KR20180097181A (en) * 2017-02-22 2018-08-31 (주) 한국씨엠씨 A method for automatically expressing a construction schedule according to its category and system for the same
CN108537462A (en) * 2018-04-17 2018-09-14 万翼科技有限公司 Confirmation method, device, computer readable storage medium and the system of project process
CN108694258A (en) * 2017-04-10 2018-10-23 中国石油化工股份有限公司 Drilling well underground dummy emulation method and system for arrangement and method for construction preview optimization
CN109064077A (en) * 2018-10-12 2018-12-21 深圳市艾泰克工程咨询监理有限公司 Engineering Project Construction process monitoring and managing method and methods of risk assessment
CN109308570A (en) * 2018-08-21 2019-02-05 中国石油天然气集团有限公司 A kind of underground complex working condition recognition methods, apparatus and system
CN109493397A (en) * 2018-09-30 2019-03-19 中国石油天然气股份有限公司 A kind of well data processing method, apparatus and system
CN111794743A (en) * 2020-08-28 2020-10-20 四川长宁天然气开发有限责任公司 Shale gas well engineering tracking deduction method
CN111794742A (en) * 2020-08-28 2020-10-20 四川长宁天然气开发有限责任公司 Shale gas drilling engineering tracking deduction method

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102009011600A1 (en) * 2009-03-03 2010-09-16 Convia Gmbh Method for determining thermal conductivity of soil layers along vertical borehole, involves carrying out determination of thermal conductivity of each soil layer at each remote drilling tool by measuring device in partial manner
KR100968709B1 (en) * 2010-04-14 2010-07-06 지에스건설 주식회사 Method to obtain the required completion percentage of milestone in construction project, method to establish the milestone schedule and evaluation method for established milestone schedule
US20140207512A1 (en) * 2013-01-24 2014-07-24 DPR Construction Timeline-Based Visual Dashboard For Construction
CN104481398A (en) * 2014-12-10 2015-04-01 中国石油化工股份有限公司 Three-dimensional (3D) horizontal well drilling construction method
CN106156389A (en) * 2015-04-17 2016-11-23 普拉德研究及开发股份有限公司 For the well planning automatically performed
CN107237601A (en) * 2016-03-28 2017-10-10 中国石油化工股份有限公司 A kind of shale gas batch production wellbore construction method
CN106761602A (en) * 2016-12-28 2017-05-31 中国石油天然气股份有限公司 The method and apparatus for determining oil well production operating mode
KR20180097181A (en) * 2017-02-22 2018-08-31 (주) 한국씨엠씨 A method for automatically expressing a construction schedule according to its category and system for the same
CN108694258A (en) * 2017-04-10 2018-10-23 中国石油化工股份有限公司 Drilling well underground dummy emulation method and system for arrangement and method for construction preview optimization
CN108537462A (en) * 2018-04-17 2018-09-14 万翼科技有限公司 Confirmation method, device, computer readable storage medium and the system of project process
CN109308570A (en) * 2018-08-21 2019-02-05 中国石油天然气集团有限公司 A kind of underground complex working condition recognition methods, apparatus and system
CN109493397A (en) * 2018-09-30 2019-03-19 中国石油天然气股份有限公司 A kind of well data processing method, apparatus and system
CN109064077A (en) * 2018-10-12 2018-12-21 深圳市艾泰克工程咨询监理有限公司 Engineering Project Construction process monitoring and managing method and methods of risk assessment
CN111794743A (en) * 2020-08-28 2020-10-20 四川长宁天然气开发有限责任公司 Shale gas well engineering tracking deduction method
CN111794742A (en) * 2020-08-28 2020-10-20 四川长宁天然气开发有限责任公司 Shale gas drilling engineering tracking deduction method

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
刘朝全, 蔡竟伦, 翟尚江, 杨锡亮: "用修正学习曲线测算井段的钻井时间", 西安石油学院学报(自然科学版), no. 01, 26 January 1999 (1999-01-26), pages 25 - 27 *
张伟文;朱达江;张阳春;徐翔;蒋蓉;林元华;: "钻井周期预测新方法――以塔里木油田为例", 天然气工业, no. 03, 25 March 2013 (2013-03-25), pages 75 - 79 *
李云峰;徐吉;徐小峰;朱宽亮;吴艳;: "南堡2号构造深层潜山水平井钻井完井技术", 石油钻探技术, no. 02, 10 April 2018 (2018-04-10), pages 14 - 20 *
汪光太;关岳;高魁旭;吴虹;: "钻井历史数据分析利用的新视角与启示", 石油工业技术监督, no. 11, 20 November 2013 (2013-11-20), pages 25 - 29 *
赵庆;蒋宏伟;史肖燕;霍宗强;杨光;朱伟伦;: "钻井工程设计和工艺软件一体化数据库研究及应用", 长江大学学报(自科版), no. 35, 15 December 2016 (2016-12-15), pages 82 - 86 *

Similar Documents

Publication Publication Date Title
CN105069524B (en) Planned dispatching optimization method based on big data analysis
CN111241067B (en) Water affair big data mining modeling management method, device, equipment and medium
CN103955491A (en) Method for synchronizing timing data increment
CN109583852B (en) Material and progress informatization management system for bridge cantilever pouring construction
CN103233741A (en) Method for quantitatively evaluating surrounding rock stability of ultra-large underground cavern group in construction period
RU2014115455A (en) SYSTEM AND METHOD OF STARTING A VIRTUAL MACHINE
CN104778185A (en) Determination method for abnormal SQL (structured query language) statement and server
CN105404966A (en) Construction method of construction process quality color rendering module based on BIM
US20120265570A1 (en) Method for critical path scheduling of activity time segments
WO2023284443A1 (en) Method and apparatus for determining working condition of excavator
CN109252855B (en) Method and device for determining final cumulative yield of gas well
CN114580752A (en) Intelligent engineering construction progress management system based on BIM technology
CN114936511A (en) Tailing paste filling design method based on digital twinning
Marinina et al. Cost management of mining project life cicle
CN115187039A (en) Construction progress management method and system based on BIM
Tokarsky et al. The concept of quality control of the organization of construction processes during construction supervision through the use of information technology
CN110674989A (en) Prediction method, system and equipment for coal bed gas extraction amount and readable storage medium
CN111178700A (en) Energy efficiency evaluation and analysis method, device and system of energy interconnection system
CN112418650A (en) Method and device for determining petroleum drilling construction progress
CN110659342A (en) Rule base automatic drawing comprehensive processing method and system based on information extraction features
Zhang et al. Research on construction schedule control based on critical chain method and BIM
KR20150049077A (en) Digital Manufacturing Optimization System for Scenario Simulation and Discovering Bottleneck Processes Based
CN102693289A (en) Simulation method for high arch dam construction
CN112184180A (en) Building life cycle management equipment based on BIM
CN111852466B (en) Method for shale gas well scale production allocation and pipe network operation optimization

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination