CN110446227A CN201910947746.6A CN201910947746A CN110446227A CN 110446227 A CN110446227 A CN 110446227A CN 201910947746 A CN201910947746 A CN 201910947746A CN 110446227 A CN110446227 A CN 110446227A
Authority
CN
China
Prior art keywords
gateway
time delay
terminal
server
message
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910947746.6A
Other languages
Chinese (zh)
Other versions
CN110446227B (en
Inventor
严泽宇
杨广学
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN HUILIAN UNLIMITED TECHNOLOGY Co Ltd
Original Assignee
WUHAN HUILIAN UNLIMITED TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN HUILIAN UNLIMITED TECHNOLOGY Co Ltd filed Critical WUHAN HUILIAN UNLIMITED TECHNOLOGY Co Ltd
Priority to CN201910947746.6A priority Critical patent/CN110446227B/en
Publication of CN110446227A publication Critical patent/CN110446227A/en
Application granted granted Critical
Publication of CN110446227B publication Critical patent/CN110446227B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W28/00Network traffic management; Network resource management
    • H04W28/02Traffic management, e.g. flow control or congestion control
    • H04W28/0231Traffic management, e.g. flow control or congestion control based on communication conditions
    • H04W28/0236Traffic management, e.g. flow control or congestion control based on communication conditions radio quality, e.g. interference, losses or delay
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W76/00Connection management
    • H04W76/10Connection setup
    • H04W76/11Allocation or use of connection identifiers

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Data Exchanges In Wide-Area Networks (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

The embodiment of the present application discloses control method and device, the equipment, medium on a kind of user equipment downlink window unlatching opportunity, and the control method that user equipment downlink window opens opportunity comprises determining that the mark of the forward gateway to E-Packet between the terminal and server;According to the mark of the forward gateway, the gateway time delay of the forward gateway is determined;Wherein, the gateway time delay is for characterizing the speed speed that the server responds the forward gateway;According to the gateway time delay, the setting time delay of the terminal is set;Wherein, the time delay that sets terminates as terminal transmission uplink message to the time difference for opening downlink window.

Description

Control method and device, the equipment, medium on user equipment downlink window unlatching opportunity
Technical field
The invention relates to wireless communication fields, relate to, but are not limited to the controlling party that user equipment downlink window opens opportunity Method and device, equipment, medium.
Background technique
LPWAN(Low Power Wide Area Network, low-power Wide Area Network) be it is a kind of towards low-power consumption, it is wide Cover the Internet of Things interconnection technique of application scenarios.LoRaWAN(Long Range Wide Area Network, remote wide area Network) be the LPWAN communication technology one kind, have low-power consumption, remote, highly-safe characteristic, at home and abroad made extensively With.
In LoRaWAN communication technology standard, the communication pattern of terminal is divided into Class A, Class B and Class C tri- Class.When under Class mode A, terminal in the most of the time all in dormant state, only in active on server After sending out data, of short duration unlatching downlink window is understood just to receive the data that server issues.The data that server issues reach eventually When end, if the downlink window of terminal is not in open state, issuing data will be unable to be properly received by terminal, cause to issue Loss of data.Therefore, it is necessary to a kind of control methods, are controlled by the unlatching opportunity of the downlink window to terminal, so that eventually Server can be properly received on end after hair data issues data, avoids issuing loss of data.
Summary of the invention
In view of this, the embodiment of the present application be solve the problems, such as it is existing in the prior art at least one and a kind of terminal is provided Control method and device, the equipment, medium on downlink window unlatching opportunity.
The technical solution of the embodiment of the present application is achieved in that
In a first aspect, the embodiment of the present application provides a kind of control method on user equipment downlink window unlatching opportunity, which comprises
Determine the mark of the forward gateway to E-Packet between the terminal and server;
According to the mark of the forward gateway, the gateway time delay of the forward gateway is determined;Wherein, the gateway time delay is used for table Levy the speed speed that the server responds the forward gateway;
According to the gateway time delay, the setting time delay of the terminal is set;Wherein, the time delay that sets is sent as the terminal For row the message ends to the time difference for opening downlink window, the downlink window receives what the server issued for the terminal Downlink message.
Second aspect, the embodiment of the present application provide a kind of control device on user equipment downlink window unlatching opportunity, described device Include:
Gateway determining module, for determining the mark of the forward gateway to E-Packet between the terminal and server;
Gateway time delay determining module determines the gateway time delay of the forward gateway for the mark according to the forward gateway;Its In, the gateway time delay is for characterizing the speed speed that the server responds the forward gateway;
Time delay setup module is set, for the setting time delay of the terminal to be arranged according to the gateway time delay;Wherein, described to set Fixed response time is that terminal transmission uplink message terminated to the time difference for opening downlink window, and the downlink window is for the end End receives the downlink message that the server issues.
The third aspect, the embodiment of the present application provide a kind of control equipment on user equipment downlink window unlatching opportunity, the equipment It include: memory, processor, the memory is stored with the computer program that can be run on a processor, and the processor is held Realize that above-mentioned user equipment downlink window opens the control method on opportunity when the row computer program.
Fourth aspect, the embodiment of the present application provide a kind of computer readable storage medium, the computer-readable storage medium Computer executable instructions are stored in matter, when which is configured to execute the unlatching of above-mentioned user equipment downlink window The control method of machine.
In the embodiment of the present application, the setting time delay of terminal is set according to the network delay of forward gateway, to control end The unlatching opportunity of downlink window is held, can be fluctuated to avoid network environment or server load variation causes terminal to receive response report The success rate decline of text, leads to the wasting of resources.
Detailed description of the invention
Figure 1A is the framework and network element composition schematic diagram of LoRaWAN communication network in the embodiment of the present application;
Figure 1B is the downlink window opening process schematic diagram of terminal in the embodiment of the present application;
Fig. 2 is the implementation process schematic diagram for the control method that user equipment downlink window opens opportunity in the embodiment of the present application;
Fig. 3 is the implementation process schematic diagram for the control method that another user equipment downlink window opens opportunity in the embodiment of the present application;
Fig. 4 is the composed structure schematic diagram that the user equipment downlink window of the embodiment of the present application opens the control device on opportunity;
Fig. 5 is a kind of hardware entities schematic diagram for the control equipment that user equipment downlink window opens opportunity in the embodiment of the present application.
Specific embodiment
The technical solution of the application is further elaborated on reference to the accompanying drawings and examples.
Figure 1A is the framework and network element composition of illustrative LoRaWAN communication network, includes in the LoRaWAN communication network Terminal 141, terminal 142, terminal 143, gateway 151, gateway 152 and server 160.
It is integrated with LoRaWAN network protocol service and LoRaWAN network management services in server 160, has LoRaWAN LoRaWAN Message processing function and terminal, the gateway management function of consensus standard defined.
Communication mode between server 160 and gateway 151, gateway 152 is IP(Internet Protocol, internet association View) broadband connections, such as Ethernet, 4G(the 4th Generation mobile communication technology, Fourth generation mobile communication technology), WIFI(Wireless Fidelity, the WLAN skill based on IEEE 802.11b standard Art), VSAT(Very Small Aperture Terminal, miniature earth station) satellite etc..
Communication mode between gateway 151, gateway 152 and corresponding terminal is LoRaWAN wireless communication.Gateway 151, gateway 152 has LoRaWAN message transmission function, and corresponding terminal is to have the sensor end of LoRaWAN communication function End.In Figure 1A, when terminal 141, terminal 142 and terminal 143 are communicated with gateway 151 or gateway 152, assisted using LoRaWAN View.
The downlink window opening process of LoRaWAN terminal is introduced by taking terminal 141 as an example below.As shown in Figure 1B, work as terminal 141 under Class mode A, if necessary to send uplink message to server 160, can open a uplink window 110.On After row message is sent, terminal 141 will close uplink window 110, and in waiting setting after the closing of uplink window 110 The first downlink window 120 is opened after prolonging.Then, terminal 141 will make the first downlink window 120 maintain open state, at one section The first downlink window 120 is closed after time.
Those skilled in the art will be seen that, terminal 141 can choose through the perhaps gateway 152 or simultaneously of gateway 151 Uplink message is sent to server 160 by gateway 151 and gateway 152.After server 160 receives uplink message, to upper Row message is handled, and response message is generated.Terminal 141 is sent by gateway 151 or gateway 152 by response message.
When response message reaches terminal 141, if the first downlink window 120 is in the open state, terminal 141 is connect The response message is received, the second downlink window 130 will not be then turned on.If terminal 141 do not open also the first downlink window 120 or The second downlink of person window 130 has been switched off, and terminal 141 will be unable to receive the response message.The needs of server 160 re-issue Response message, terminal 141 can open the first downlink window 120 or the at the time of setting time delay or window opens interval arrival Two downlink windows 130.During a successful message issues, terminal 141 needs under the first downlink window 120 or the second The open stage of row window 130 receives the response message that server 160 issues.
In LoRaWAN communication protocol, allow terminal network the stage and network after stage of communication to setting time delay into Row modification.Under normal conditions, the setting time delay of terminal and window, which open interval, can use agreement default parameters or one It is different from the fixed value of default parameters.That is, it is generally the case that the setting time delay and window of terminal, which open interval, is Fixed, it will not change, for example, setting time delay as 1 second, it is 1 second that window, which opens interval also,.
But as shown in Figure 1A, after uplink message is sent server 160 by terminal 141, server 160 is received The time of response message is not sustained.The time wherein spent may be by gateway 151 or gateway 152 and server The influence of communication condition between 160, it is also possible to the processing speed of message be influenced by server 160, lead to terminal 141 A kind of irregular dispersity is presented in the response time of the uplink message of sending.If the setting time delay of terminal 141 maintains not Become, in the response message of a certain number of uplink messages, the event of data loss of significant proportion necessarily occurs.
After terminal 141 has sent uplink message to server 160, if response message cannot be properly received, it will bring Following problems:
1) terminal 141 judges that itself is in off-network state, frequently attempts suspension reconnection, influences regular traffic;
2) terminal 141 reduces the transmission rate of data automatically, and equipment power dissipation is caused to increase, and the occupancy of radio frequency resource is promoted, whole Network transmission environmental degradation;
3) server 160 retransmits response message several times, and the equipment power dissipation of terminal 141 is caused to increase, server 160 Data processing load increases.
In order to avoid wasting of resources situation more than appearance, when the embodiment of the present application provides a kind of unlatching of user equipment downlink window The control method of machine.
Embodiment one
The embodiment of the present application provides a kind of control method on user equipment downlink window unlatching opportunity, as shown in Fig. 2, the user equipment downlink window Mouthful open opportunity control method include:
S110 determines the mark of the forward gateway to E-Packet between the terminal and server.
As shown in FIG. 1A and 1B, the control method in the embodiment of the present application is applied to server 160, and server 160 exists The setting time delay of setting terminal 141 into the downward message of terminal 141, and then the first downlink window 120 of controlling terminal 141 Unlatching opportunity.
Server 160 can be communicated with terminal 141 by the realization of at least one gateway, as shown in Figure 1A, at least one net Close includes gateway 151 and gateway 152.Those skilled in the art will be seen that, at least one net communicated to connect with server 160 The Central Shanxi Plain, each gateway length at a distance from server 160 is different, and the communication condition between each gateway and server 160 is not yet Together.When being E-Packeted between terminal 141 and server 160 using different forward gateways, the uplink message of the sending of terminal 141 Response time is not also identical.In order to match from different response times, the downlink window of characterization terminal 141 opens setting for opportunity Fixed response time is also required to difference.
Therefore, server 160 needs to determine the mark of forward gateway first, determine which gateway be server 160 with The setting time delay of terminal 141 is arranged further according to the gateway time delay of the forward gateway for forward gateway between terminal 141.This Shen It please be illustrated so that gateway 151 is forward gateway as an example in embodiment.
S120 determines the gateway time delay of the forward gateway according to the mark of the forward gateway;Wherein, the gateway Time delay is for characterizing the speed speed that the server responds the forward gateway.
Here, in order to terminal 141 downlink window open opportunity accurately control, it is thus necessary to determine that forward gateway namely The gateway time delay of gateway 151.
As shown in Figure 1A, terminal 141 issues uplink message, between the response message incoming terminal 141 of server 160 Time difference, including uplink message from terminal 141 to gateway 151 and from gateway 151 to the transmission duration of server 160, server Time that the processing of 160 pairs of uplink messages generates response message and response message are from server 160 to gateway 151 and from gateway 151 To the transmission duration of terminal 141.In the embodiment of the present application, this time difference is referred to gateway time delay, for characterizing server The speed speed of 160 response gateways 151.
The setting time delay of the terminal is arranged according to the gateway time delay in S130;Wherein, the time delay that sets is described Terminal, which sends uplink message, to be terminated to the time difference for opening downlink window, and the downlink window is for the terminal reception clothes The downlink message that business device issues.
Here, after terminal 141 issues uplink message, interval how long can just receive the response report of server 160 Text is determined by gateway time delay.In order to guarantee that terminal 141 can be successfully received response message, response message loss is avoided to make It at the wasting of resources, needs to be arranged according to gateway time delay the setting time delay of terminal 141, improves terminal 141 and receive response message Success rate.
As shown in Figure 1B, setting time delay terminates as the transmission uplink message of terminal 141 between the first downlink window 120 of unlatching Time difference.In general, setting the unit of time delay as the second.
In the embodiment of the present application, the setting time delay of terminal is set according to the network delay of forward gateway, to control end The unlatching opportunity of downlink window is held, can be fluctuated to avoid network environment or server load variation causes terminal to receive response report The success rate decline of text, leads to the wasting of resources.
Embodiment two
The embodiment of the present application provides a kind of control method on user equipment downlink window unlatching opportunity, which opens opportunity Control method include:
S210 determines the mark of the forward gateway to E-Packet between the terminal and server.
S220 obtains the propagation delay time between the forward gateway and the server.
In the embodiment of the present application, the propagation delay time between forward gateway and server is for characterizing the forward gateway and institute State the speed speed of transmitting message between server.As shown in Figure 1A, propagation delay time is from forward gateway i.e. gateway 151 to service Transmission duration the sum of of the transmission duration and response message of device 160 from server 160 to gateway 151.
In order to obtain propagation delay time, in some embodiments, S220 the following steps are included:
S221, the transmission duration of at least one message reported according to forward gateway described in the period 1 with second round, really The propagation delay time of the fixed forward gateway;Wherein, the second round is less than the period 1.
Here, every second round, gateway 151 reports the transmission duration an of message to server 160.Second round is small In the period 1.For example, the period 1 can be the integral multiple of second round, for example, 10 times.So, server 160 is by basis Report recently the 10 transmission durations of gateway 151 determine the propagation delay time of gateway 151.By increasing the number of transmission duration, Random error can be reduced, the accuracy in computation of propagation delay time is improved.
The value of second round can be determining, and it is according to the fluctuation of communication condition determining to be also possible to server 160.Such as Fruit communication condition maintains to stablize, and the propagation delay time of gateway 151 will remain unchanged as whithin a period of time, and server 160 can increase The value of second round reduces calculation amount.If communication condition fluctuation is very big, random errors affect result is accurate in order to prevent Property, server 160 can reduce the value of second round, increase the sample frequency of transmission duration, to exclude the influence of random error, Improve the accuracy of result.
The transmission duration for the message that gateway 151 is reported to server 160 can be uplink message from forward gateway i.e. gateway 151 arrive the transmission duration of server 160, are also possible to transmission duration of the response message from server 160 to gateway 151, can also To be the sum of both of the aforesaid transmission duration.
If the transmission duration that gateway 151 reports is transmission duration of the uplink message from gateway 151 to server 160, can To determine the transmission duration of message by sending common uplink message to server 160.As shown in Figure 1A, gateway 151 to Server 160 sends uplink message.After server 160 receives uplink message, at the time of record receives the uplink message, And the time of reception is written in the response message then issued.Gateway 151 receives after response message, so that it may according to this The transmission duration of message is determined at the time of receiving the moment and send uplink message.
If the transmission duration that gateway 151 reports is transmission duration of the response message from server 160 to gateway 151, net The transmission duration of message can be determined by receiving the generic downlink message that server 160 is sent by closing 151.As shown in Figure 1A, Server 160 sends downlink message to gateway 151, and the sending instant of the downlink message is written in downlink message.Gateway 151 After receiving downlink message, so that it may determine message with the sending instant according at the time of itself receiving the downlink message Transmit duration.
If the transmission duration that gateway 151 reports is uplink message from forward gateway i.e. biography of the gateway 151 to server 160 The sum of the transmission duration of defeated duration and response message from server 160 to gateway 151, gateway 151 can be by sending out to server Dedicated message is sent to determine the transmission duration of message.As shown in Figure 1A, forward gateway namely gateway 151 are sent to server 160 Dedicated message.After server 160 receives dedicated message, dedicated message can be handed down to gateway 151.In this way, eliminating clothes Be engaged in influence of the device 160 to the processing delay of dedicated message, gateway 151 can directly according to after issuing dedicated message, to receiving The time difference of the dedicated message determines the transmission duration of message.
If what gateway 151 reported is the transmission duration of one way, server 160 need to report gateway 151 at least one Transmission duration of the transmission duration of a message multiplied by 2, as message in a complete message response period;If on gateway 151 Report is that message one carrys out past the sum of a transmission duration between gateway 151 and server 160, then the report that gateway 151 reports Text transmission duration is the transmission duration of message in a complete message response period.
Transmission duration based at least one message, server 160 can be by averaging to obtain the transmission of gateway 151 Time delay can also intend the regularity of distribution for transmitting duration and existing probability-distribution function (such as normal distyribution function) It closes, obtains the desired value of propagation delay time.Here, transmission duration is the transmission duration of message in a complete message response period.
In order to determine propagation delay time based on the transmission duration of at least one message, in some embodiments, S221 includes Following steps:
S221a, according to the transmission duration distribution arrangement serial number that sequence from small to large is at least one message.
S221b sorts according to transmission duration of the arrangement serial number at least one message, when obtaining message transmissions Long sequence.
The total number of the arrangement serial number is rounded multiplied by setting ratio, and by product, obtains selected serial number by S221c.
S221d, by the corresponding propagation delay time transmitted duration and be determined as the forward gateway of the selected serial number.
Here, according to the transmission duration distribution arrangement serial number that sequence from small to large is at least one message.If transmission The number of duration is 15, then the corresponding arrangement serial number 1 of the smallest transmission duration of numerical value, the maximum transmission duration of numerical value is corresponding Arrangement serial number 15.When transmitting duration according to the sequence arrangement of serial number from small to large is arranged to get message transmissions are arrived for 15 Long sequence.
Typically, caused by the maximum value in message transmissions duration sequence is likely due to enchancement factor, reference price It is worth lower.Therefore, in the embodiment of the present application, it is provided with a setting ratio, this setting ratio is less than 1, to exclude maximum It is worth the influence of the enchancement factor represented.
In some embodiments, this setting ratio is also greater than 0.5, to adapt to propagation delay time caused by communication condition deterioration Increase.For example, setting ratio can be 0.8.In this way, the total number 15 for arranging serial number is obtained multiplied by setting ratio 0.8 Product is 12, and selected serial number is 12.The corresponding transmission duration of serial number 12 is determined as propagation delay time.
In other embodiments, setting ratio can also be 0.7.In this way, the total number 15 of serial number will be arranged multiplied by setting Ratio 0.7, obtained product are 10.5, need to be rounded product.In the embodiment of the present application, it can round up, obtain to product To 11;Product can also be rounded downwards, obtain 10.
S230 obtains the server to the processing delay of uplink message.
Server is used to characterize the speed speed of the server process uplink message to the processing delay of uplink message.Such as Shown in Figure 1A, server 160 needs to handle the uplink message from multiple terminals, and is managed to multiple terminals and gateway. In this way, server 160 possibly can not receive after the uplink message of terminal 141 at the first time just to the uplink message at Reason.On the other hand, server 160 needs while handling a large amount of uplink messages, under the operational capability that may cause server 160 Drop, to influence the processing speed to the uplink message of terminal 141.Therefore, in the embodiment of the present application, by server 160 to upper The processing delay of row message is also used as the reference factor of gateway time delay.
In some embodiments, S230 the following steps are included:
S231 determines the Message processing time of the server received each uplink message within the period 3.
The average value of the Message processing time of the uplink message is determined as the processing delay by S232.
In the embodiment of the present application, in order to exclude the influence of enchancement factor, by the period 3, server 160 is to uplink report The average handling time of text is as processing delay.
In some embodiments, server 160 can adjust the numerical value of period 3 according to the upper hair frequency of uplink message, To guarantee that the number of uplink message in the period 3 is enough to exclude the influence of random error.
S240 determines the gateway time delay of the forward gateway according to the propagation delay time and the processing delay;Wherein, institute Gateway time delay is stated for characterizing the speed speed that the server responds the forward gateway.
As shown in Figure 1A, after terminal 141 issues uplink message, uplink message needs to spend one from terminal 141 to gateway 151 It fixes time;After gateway 151 issues response message, response message is also required to take a certain time from gateway 151 to terminal 141.
In the embodiment of the present application, the gateway time delay of forward gateway is determined according to propagation delay time and processing delay.Such as Figure 1A institute Show, the determination method of this gateway time delay considers transmission duration of the message between gateway 151 and server 160, and clothes Business device 160 handles the time spent when uplink message.
It in other embodiments, can transmission duration and response message by uplink message from terminal 141 to gateway 151 The reference factor of gateway time delay is also used as from gateway 151 to the transmission duration of terminal 141.
In some embodiments, S240 the following steps are included:
S241 determines practical time delay according to the propagation delay time and the processing delay.
The practical time delay is determined as gateway time delay if the practical time delay is less than or equal to default time delay by S242.
The default time delay is determined as gateway time delay if the practical time delay is greater than default time delay by S243.
In the embodiment of the present application, practical time delay is the sum of propagation delay time and processing delay.If practical time delay is greater than default Default time delay is determined as gateway time delay by time delay;If practical time delay is less than or equal to default time delay, practical time delay is determined as Gateway time delay.
LoRaWAN communication protocol allows the setting time delay to terminal to modify, and range is 1-15 seconds.In some embodiments In, default time delay can be set as 15 seconds, to prevent the downlink window of terminal 141 from opening opportunity beyond protocol requirement.At it In his embodiment, default time delay can also be set as 15 seconds numerical value below, to prevent terminal 141 from opening setting for downlink window Fixed response time is too long to cause equipment power dissipation to increase.
In some embodiments, in order to reduce calculation amount, rounding processing can be done to it after acquiring practical time delay, Integer value is obtained, guarantees that gateway time delay is integer in seconds.
The setting time delay of the terminal is arranged according to the gateway time delay in S250;Wherein, the time delay that sets is described Terminal, which sends uplink message, to be terminated to the time difference for opening downlink window, and the downlink window is for the terminal reception clothes The downlink message that business device issues.
In communication process, terminal 141 is likely to be at the networking stage, it is also possible to the stage of communication after networking, in order to Promote the efficiency that downlink window opens opportunity adjustment, the different phase according to locating for terminal 141 in the embodiment of the present application, to setting Time delay uses different setting methods.
If terminal be in networking stage, in some embodiments, S210 the following steps are included:
211a, if the terminal is in the networking stage, receive the terminal networking request when, from the terminal with it is described Optimal gateway is selected at least one gateway between server.
The mark of the optimal gateway is determined as the mark of the forward gateway by 212a.
Here, if terminal 141 is in, the networking stage, there are no determine through which gateway come forwarding terminal 141 and clothes Be engaged in device 160 between message when, terminal 141 can first to server 160 send network request.Server 160 receives networking After request, optimal gateway is selected from least one gateway connected to it, in the embodiment of the present application, which is gateway 151.The mark of gateway 151 is the mark of forward gateway.
Those skilled in the art will be seen that, when server 160 determines optimal gateway, need to consider whether terminal 141 is located In in the coverage area of the gateway and between the gateway and terminal and server data transmission bauds and transmission quality whether It meets the requirements.
Accordingly, S250 the following steps are included:
The gateway time delay is determined as the setting time delay by S251a.
The setting time delay is arranged in the response message for networking request in S252a.
Here, when terminal 141 is in the networking stage, there are no carried out report by any one gateway and server 160 Text interaction, the downlink window of terminal 141 open opportunity not yet according to the progress toning of the gateway time delay of any one gateway It is whole.In this way, server 160 can initialize on the downlink window unlatching opportunity to terminal 141.It is, server 160 can Gateway time delay to be determined as to set time delay, and the setting setting time delay in the response message for the request that networks.Terminal 141 receives After the response message of networking request, so that it may adjust the unlatching opportunity of downlink window according to setting time delay.
Terminal be in network after stage of communication when, in some embodiments, S210 the following steps are included:
S211b will forward the gateway of the uplink message of the terminal if the terminal is in the stage of communication after networking Mark is determined as the mark of forward gateway.
Here, terminal 141 be in network after stage of communication, this means that terminal 141 by with server 160 Uplink message was sent out on some gateway of communication connection.Therefore, server 160 can will forward the gateway of uplink message to determine For forward gateway, the mark of the gateway is determined as to the mark of forward gateway.
Accordingly, S250 the following steps are included:
S251b obtains the current setting time delay of the terminal, obtains both fixed response times.
Both the fixed response time is subtracted a setting numerical value if the gateway time delay is less than both fixed response times by S252b, Obtain setting time delay.
S253, if the gateway time delay is greater than or equal to both fixed response times, when the gateway time delay is determined as setting Prolong.
The setting time delay is arranged in S254 in the transmitting order to lower levels for being sent to the terminal.
Here, terminal 141 is anticipated by sending out uplink message on some gateway for communicating to connect with server 160 Taste terminal 141 downlink window open opportunity adjustment was carried out according to the gateway time delay of the gateway.
In order to enable the downlink window of terminal 141, which opens opportunity, can adapt to the fluctuation and server load of communication condition Variation, server 160 need to judge the current downlink window of terminal 141 opens opportunity whether can be with the current net of forward gateway Time delay is closed to be adapted.
Based on this, server 160 obtains the current setting time delay of terminal 141, obtains both fixed response times, that is, terminal 141 Current downlink window opens opportunity.Then, server 160 compares the big of both fixed response times and the gateway time delay that determines in S240 It is small.
If gateway time delay is less than both fixed response times, numerical value subtracts when indicating the gateway time delay of forward gateway compared to last determine It is small.It may be because communication condition improves, or becomes smaller because of the processing delay of server 160.At this point, in order to protect The success rate that terminal 141 receives response message is demonstrate,proved, server 160 both will subtract a setting numerical value by fixed response time, when obtaining setting Prolong, reduces the windowing time delay of terminal 141.
Here, server 160 can determine setting numerical value according to the size of gateway time delay in proportion.For example, setting number Value can be the 10% of gateway time delay.When gateway time delay is 10s, setting numerical value is 1s.
If gateway time delay is more than or equal to both fixed response times, indicate that the gateway time delay of forward gateway is determined compared to last When numerical value become larger.It may be because communication condition is degrading, or is become larger because of the processing delay of server 160.This When, in order to guarantee that terminal 141 receives the success rate of response message, gateway time delay is determined as setting time delay by server 160.
Embodiment three
The embodiment of the present application provides a kind of control method on user equipment downlink window unlatching opportunity, and this method is logical applied to LoRaWAN Server in communication network.It as shown in Figure 1A, include terminal 141, terminal 142, terminal 143, gateway in LoRaWAN communication network 151, gateway 152 and server 160.In the embodiment of the present application, when being opened with the downlink window of 160 controlling terminal 141 of server It is illustrated for machine.
As shown in figure 3, the control method that user equipment downlink window opens opportunity includes:
S310, server 160 calculate the propagation delay time t between gateway 151 and server 160 with cycle T 11
Here, it is forwarded between terminal 141 and server 160 using the message that gateway 151 is realized.In order to give server 160 Calculate propagation delay time t1Data are provided, gateway 151 is using T2 as the period, when taken at regular intervals itself arrives the message transmissions of server 160 It is long, and it is reported to server 160.
Wherein, cycle T 2 is less than cycle T 1.For example, period 1 T1It can be second round T2Integral multiple, for example, 10 Times.So, server 160 transmits duration for report recently according to gateway 151 10 to determine the propagation delay time of gateway 151 t1.By the number for increasing transmission duration, it is possible to reduce random error improves propagation delay time t1Accuracy in computation.
It, can also be in addition, message transmissions duration can be transmission duration of the uplink message from gateway 151 to server 160 It is transmission duration of the response message from server 160 to gateway 151, is also possible to the sum of both of the aforesaid transmission duration.
If what gateway 151 reported is the transmission duration of one way, server 160 needs the message for reporting gateway 151 to pass Transmission duration of the defeated duration multiplied by 2, as message in a complete message response period;If what gateway 151 reported is message One carrys out past the sum of a transmission duration between gateway 151 and server 160, then the message transmissions duration that gateway 151 reports The transmission duration of message in an as complete message response period.
Server 160 determines propagation delay time t1 according to the transmission duration of at least one message.It is a length of when transmission here The transmission duration of message in one complete message response period.
Server 160 is according to the transmission duration distribution arrangement serial number that sequence from small to large is at least one message.If The number for transmitting duration is 15, then the corresponding arrangement serial number 1 of the smallest transmission duration of numerical value, the maximum transmission duration of numerical value Corresponding arrangement serial number 15.Duration is transmitted by 15 to pass according to the sequence arrangement of arrangement serial number from small to large to get to message Defeated duration sequence.
The total number for arranging serial number multiplied by ratio P, is obtained selected serial number by server 160 after which is rounded, and Using the corresponding message transmissions duration of selected serial number as the propagation delay time t of gateway 1511.Here, P is less than 1, to exclude maximum It is worth the influence of the enchancement factor represented.Moreover, P is greater than 0.5, to cope with forward gateway propagation delay time caused by communication environment deterioration t1Increase.For example, setting ratio can be 0.8.In this way, the total number 15 for arranging serial number is obtained multiplied by setting ratio 0.8 Product be 12, selected serial number is 12.The corresponding transmission duration of serial number 12 is determined as the propagation delay time t of gateway 1511
S320, server 160 determine 3 server 160 of cycle T to the processing delay t of uplink message2
In the embodiment of the present application, the Message processing time of each uplink message in 160 collection period T3 of server.At this The reason time is that server 160 receives uplink message that the terminal 141 of the upload of gateway 151 is sent to server 160 for response report Text is sent to the time difference of gateway 151.
Then, server 160 averages to the Message processing time of the uplink message in cycle T 3, obtains processing delay t2.Here, the number for the Message processing time that server 160 can be acquired according to the needs of setting adjusts the number of cycle T 3 Value, so that the number of uplink message is enough to exclude the influence of random error in cycle T 3.
S330, server 160 determine the gateway time delay GwDelay of gateway 151.
In the embodiment of the present application, server 160 determines gateway time delay GwDelay according to formula (1):
Here,For the function that rounds up, for example, propagation delay time t1With processing delay t2Summation obtain 13.1, by 13.1 to Upper rounding then obtains 14.Server 160 is first to propagation delay time t1With processing delay t2Summation, then round up, obtain gateway time delay The integer value of GwDelay.Then gateway time delay GwDelay and 15 are compared, if it is greater than or be equal to 15, then by 15 be used as net Close time delay GwDelay;If it is less than 15, then the integer value obtained the rounding is as gateway time delay GwDelay.For example, transmission Time delay t1With processing delay t2And be 11.3,12 will be obtained by rounding up, since 12 less than 15, it is thus determined that gateway time delay GwDelay is 12.
The setting time delay of terminal 141 is arranged according to gateway time delay GwDelay, carrys out controlling terminal 141 for S340, server 160 The unlatching opportunity of downlink window.
In the embodiment of the present application, according to different phase locating for terminal 141, the unlatching opportunity of downlink window is carried out respectively Control.
When terminal 141 is in the networking stage, terminal 141 can send the request that networks to server 160 first.Server After 160 receive networking request, an optimal gateway will be selected to realize that the message between server 160 and terminal 141 forwards. In the embodiment of the present application, it is illustrated so that gateway 151 realizes message forwarding as an example.That is, server 160 confirmed net Closing 151 is optimal gateway.
Then, server 160 obtains the gateway time delay GwDelay of gateway 151.The gateway time delay GwDelay of gateway 151 by The several steps of S310, S320 and S330 obtain.It will be understood by those skilled in the art that although terminal 141 passes through gateway not yet 151 send uplink message to server 160, but there is also other terminals in the communication network.Other terminals are before this Gateway 151 is passed through and has been transmitted across uplink message to server 160, therefore in S310, can have been passed according to the message of these terminals The defeated time determines the propagation delay time t of gateway 1511
When terminal 141 is in the networking stage, there are no carried out message by any one gateway and server 160 to hand over Mutually, the downlink window unlatching opportunity of terminal 141 carried out adjustment according to the gateway time delay of any one gateway not yet.This Sample, server 160 can initialize on the downlink window unlatching opportunity to terminal 141.It is, server 160 can incite somebody to action The gateway time delay GwDelay of gateway 151 is determined as setting time delay, and the setting setting time delay in the response message for the request that networks. Terminal 141 receives after the response message for the request that networks, so that it may when according to setting unlatching of the time delay to adjust downlink window Machine.
When terminal 141 is in the stage of communication after networking, it is meant that terminal 141 has passed through gateway 151 to service Device 160 is transmitted across uplink message.Therefore, server 160 can directly acquire the gateway time delay GwDelay of gateway 151.
Those skilled in the art will be seen that that server 160 obtains is the newest gateway time delay GwDelay of gateway 151. Before this setting time delay may be arranged according to the gateway time delay GwDelay before gateway 151 in terminal 141, that is, Adjustment was carried out to the unlatching opportunity of downlink window.But in order to enable terminal 141 downlink window open opportunity can adapt to The variation of fluctuation and the server load of communication condition, server 160 need to judge the current setting time delay of terminal 141 SnDelay(old)Whether can be adapted with the newest gateway time delay GwDelay of gateway 151.In the embodiment of the present application, server The 160 setting time delay SnDelay according to formula (2) come setting terminal 141 hereafter(new):
(2)
Here, if it is less than or be equal to, server 160 will be set as the setting time delay SnDelay of terminal 141 hereafter(new); If it does, server 160 will be set as, terminal 141 is set according to the variation of the gateway time delay of gateway 151 to update Fixed response time, dynamic adjust the unlatching opportunity of downlink window.
Example IV
Based on embodiment above-mentioned, the embodiment of the present application provides a kind of control device on user equipment downlink window unlatching opportunity, the dress Included each module is set, can be realized by the processor in computer equipment;Certainly it can also pass through specific logic electricity It realizes on road;In the process of implementation, processor can be central processing unit (CPU), microprocessor (MPU), Digital Signal Processing Device (DSP) or field programmable gate array (FPGA) etc..
Fig. 4 is the composed structure schematic diagram for the control device that the embodiment of the present application user equipment downlink window opens opportunity, terminal When the control device 400 that downlink window opens opportunity includes gateway determining module 401, gateway time delay determining module 402 and sets Prolong setup module 403, in which:
Gateway determining module 401, for determining the mark of the forward gateway to E-Packet between the terminal and server;
Gateway time delay determining module 402 determines the gateway time delay of the forward gateway for the mark according to the forward gateway; Wherein, the gateway time delay is for characterizing the speed speed that the server responds the forward gateway;
Time delay setup module 403 is set, for the setting time delay of the terminal to be arranged according to the gateway time delay;Wherein, described Setting time delay terminates as terminal transmission uplink message to the time difference for opening downlink window, and the downlink window is for described Terminal receives the downlink message that the server issues.
In some embodiments, the gateway time delay determining module, comprising:
Propagation delay time acquiring unit, for obtaining the propagation delay time between the forward gateway and the server;
Processing delay acquiring unit, for obtaining the server to the processing delay of uplink message;
Gateway time delay determination unit, when determining the gateway of the forward gateway according to the propagation delay time and the processing delay Prolong.
In some embodiments, the propagation delay time acquiring unit, is specifically used for:
The transmission duration of at least one message reported according to forward gateway described in the period 1 with second round, determine described in The propagation delay time of forward gateway;Wherein, the second round is less than the period 1.
In some embodiments, the propagation delay time acquiring unit, comprising:
It arranges serial number and distributes subelement, for being distributed according to the transmission duration that sequence from small to large is at least one message Arrange serial number;
Sorting subunit obtains message for sorting according to transmission duration of the arrangement serial number at least one message Transmit duration sequence;
Serial number selectes subelement, for the total number of the arrangement serial number to be rounded multiplied by setting ratio, and by product, is selected Sequencing number;
Propagation delay time determines subelement, for the corresponding transmission duration of the selected serial number to be determined as to the biography of the forward gateway Defeated time delay.
In some embodiments, the processing delay acquiring unit, comprising:
Time acquisition subelement is handled, for determining the message of the server received each uplink message within the period 3 Handle the time;
Processing delay determines subelement, for the average value of the Message processing time of the uplink message to be determined as the processing Time delay.
In some embodiments, the gateway time delay determination unit, is specifically used for:
Practical time delay is determined according to the propagation delay time and the processing delay;
If the practical time delay is less than or equal to default time delay, the practical time delay is determined as gateway time delay;
If the practical time delay is greater than default time delay, the default time delay is determined as gateway time delay.
In some embodiments, the gateway determining module, comprising:
Optimal gateway selecting unit, if being in the networking stage for the terminal, when receiving the networking request of the terminal, Optimal gateway is selected at least one gateway between the terminal and the server;
Gateway determination unit is determined as the mark of the forward gateway for the mark by the optimal gateway.
Accordingly, the setting time delay setup module, comprising:
Time delay determination unit is set, for the gateway time delay to be determined as the setting time delay;
Time delay setting unit is set, for the setting time delay to be arranged in the response message for networking request.
In some embodiments, the gateway determining module, comprising:
Gateway determination unit will forward the uplink of the terminal if being in the stage of communication after networking for the terminal The mark of the gateway of message is determined as the mark of forward gateway.
Accordingly, the setting time delay setup module, comprising:
It sets time delay determination unit and obtains both fixed response times for obtaining the current setting time delay of the terminal;
If the gateway time delay is less than both fixed response times, both fixed response times are subtracted into a setting numerical value, when obtaining setting Prolong;
If the gateway time delay is greater than or equal to both fixed response times, the gateway time delay is determined as to set time delay;
Time delay setting unit is set, for the setting time delay to be arranged in the transmitting order to lower levels for being sent to the terminal.
The description of apparatus above embodiment, be with the description of above method embodiment it is similar, have same embodiment of the method Similar beneficial effect.For undisclosed technical detail in the application Installation practice, the application embodiment of the method is please referred to Description and understand.
It should be noted that in the embodiment of the present application, if realized in the form of software function module under above-mentioned terminal Row window opens the control method on opportunity, and when sold or used as an independent product, also can store in a computer In read/write memory medium.Based on this understanding, the technical solution of the embodiment of the present application is substantially in other words to the prior art The part to contribute can be embodied in the form of software products, which is stored in a storage medium In, including some instructions use is so that a computer equipment (can be personal computer, server or network equipment etc.) Execute all or part of each embodiment the method for the application.And storage medium above-mentioned include: USB flash disk, mobile hard disk, only Read the various media that can store program code such as memory (Read Only Memory, ROM), magnetic or disk.In this way, The embodiment of the present application is not limited to any specific hardware and software and combines.
Accordingly, the embodiment of the present application provides a kind of control equipment that user equipment downlink window opens opportunity (such as computer Equipment), including memory and processor, the memory be stored with the computer program that can be run on a processor, the place Reason device realizes that the user equipment downlink window provided in above-described embodiment opens the step in the control method on opportunity when executing described program Suddenly.
Accordingly, the embodiment of the present application provides a kind of computer readable storage medium, which is characterized in that the computer can It reads to be stored with computer executable instructions in storage medium, which is configured to execute and mention in above-described embodiment The user equipment downlink window of confession opens the step in the control method on opportunity.
It need to be noted that: the description of medium stored above and apparatus embodiments, with retouching for above method embodiment It is similar for stating, and has with embodiment of the method similar beneficial effect.For in the application storage medium and apparatus embodiments not The technical detail of disclosure please refers to the description of the application embodiment of the method and understands.
Fig. 5 is a kind of hardware entities signal for the control equipment that user equipment downlink window opens opportunity in the embodiment of the present application Figure, as shown in figure 5, the hardware entities that the user equipment downlink window opens the control equipment 500 on opportunity include: processor 501, communication Interface 502 and memory 503, wherein
The usual controlling terminal downlink window of processor 501 opens the overall operation of the control equipment 500 on opportunity.
The control equipment 500 that communication interface 502 can make user equipment downlink window open opportunity passes through network and other equipment Communication.
Memory 503 is configured to store the instruction and application that can be performed by processor 501, can also cache device to be processed 501 and user equipment downlink window open that each module in the control equipment 500 on opportunity is to be processed or processed data, Ke Yitong It crosses flash memory (FLASH) or random access storage device (Random Access Memory, RAM) is realized.
It should be understood that " one embodiment " or " embodiment " that specification is mentioned in the whole text mean it is related with embodiment A particular feature, structure, or characteristic includes at least one embodiment of the application.Therefore, occur everywhere in the whole instruction " in one embodiment " or " in one embodiment " not necessarily refer to identical embodiment.In addition, these specific features, knot Structure or characteristic can combine in any suitable manner in one or more embodiments.It should be understood that in the various implementations of the application In example, magnitude of the sequence numbers of the above procedures are not meant that the order of the execution order, the execution sequence Ying Yiqi function of each process It can be determined with internal logic, the implementation process without coping with the embodiment of the present application constitutes any restriction.Above-mentioned the embodiment of the present application Serial number is for illustration only, does not represent the advantages or disadvantages of the embodiments.
It should be noted that, in this document, the terms "include", "comprise" or its any other variant are intended to non-row His property includes, so that the process, method, article or the device that include a series of elements not only include those elements, and And further include other elements that are not explicitly listed, or further include for this process, method, article or device institute it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including being somebody's turn to do There is also other identical elements in the process, method of element, article or device.
In several embodiments provided herein, it should be understood that disclosed device and method can pass through it Its mode is realized.Apparatus embodiments described above are merely indicative, for example, the division of the unit, only A kind of logical function partition, there may be another division manner in actual implementation, such as: multiple units or components can combine, or It is desirably integrated into another system, or some features can be ignored or not executed.In addition, shown or discussed each composition portion Mutual coupling or direct-coupling or communication connection is divided to can be through some interfaces, the INDIRECT COUPLING of equipment or unit Or communication connection, it can be electrical, mechanical or other forms.
Above-mentioned unit as illustrated by the separation member, which can be or may not be, to be physically separated, aobvious as unit The component shown can be or may not be physical unit;Both it can be located in one place, and may be distributed over multiple network lists In member;Some or all of units can be selected to achieve the purpose of the solution of this embodiment according to the actual needs.
In addition, each functional unit in each embodiment of the application can be fully integrated in one processing unit, it can also To be each unit individually as a unit, can also be integrated in one unit with two or more units;It is above-mentioned Integrated unit both can take the form of hardware realization, can also realize in the form of hardware adds SFU software functional unit.
Those of ordinary skill in the art will appreciate that: realize that all or part of the steps of above method embodiment can pass through The relevant hardware of program instruction is completed, and program above-mentioned can store in computer-readable storage medium, which exists When execution, step including the steps of the foregoing method embodiments is executed;And storage medium above-mentioned includes: movable storage device, read-only deposits The various media that can store program code such as reservoir (Read Only Memory, ROM), magnetic or disk.
If alternatively, the above-mentioned integrated unit of the application is realized in the form of software function module and as independent product When selling or using, it also can store in a computer readable storage medium.Based on this understanding, the application is implemented Substantially the part that contributes to existing technology can be embodied in the form of software products the technical solution of example in other words, The computer software product is stored in a storage medium, including some instructions are used so that a measuring instrument controls equipment (can be personal computer, server or network equipment etc.) execute each embodiment the method for the application whole or Part.And storage medium above-mentioned includes: that movable storage device, ROM, magnetic or disk etc. are various can store program code Medium.
The above, only presently filed embodiment, but the protection scope of the application is not limited thereto, it is any to be familiar with Those skilled in the art within the technical scope of the present application, can easily think of the change or the replacement, and should all cover Within the protection scope of the application.Therefore, the protection scope of the application should be based on the protection scope of the described claims.

Claims (11)

1. the control method that a kind of user equipment downlink window opens opportunity characterized by comprising
Determine the mark of the forward gateway to E-Packet between the terminal and server;
According to the mark of the forward gateway, the gateway time delay of the forward gateway is determined;Wherein, the gateway time delay is used for table Levy the speed speed that the server responds the forward gateway;
According to the gateway time delay, the setting time delay of the terminal is set;Wherein, the time delay that sets is sent as the terminal For row the message ends to the time difference for opening downlink window, the downlink window receives what the server issued for the terminal Downlink message.
2. the method according to claim 1, wherein the gateway time delay of the determination forward gateway, comprising:
Obtain the propagation delay time between the forward gateway and the server;
The server is obtained to the processing delay of uplink message;
The gateway time delay of the forward gateway is determined according to the propagation delay time and the processing delay.
3. according to the method described in claim 2, it is characterized in that, between the acquisition forward gateway and the server Propagation delay time, comprising:
The transmission duration of at least one message reported according to forward gateway described in the period 1 with second round, determine described in The propagation delay time of forward gateway;Wherein, the second round is less than the period 1.
4. according to the method described in claim 3, it is characterized in that, described report according to forward gateway described in the period 1 The transmission duration of at least one message, determines the propagation delay time of the forward gateway, comprising:
According to the transmission duration distribution arrangement serial number that sequence from small to large is at least one message;
It is sorted according to transmission duration of the arrangement serial number at least one message, obtains message transmissions duration sequence;
The total number of the arrangement serial number is rounded multiplied by setting ratio, and by product, obtains selected serial number;
By the corresponding propagation delay time transmitted duration and be determined as the forward gateway of the selected serial number.
5. according to the method described in claim 2, it is characterized in that, when the processing for obtaining the server to uplink message Prolong, comprising:
Determine the Message processing time of the server received each uplink message within the period 3;
The average value of the Message processing time of the uplink message is determined as the processing delay.
6. according to the method described in claim 2, it is characterized in that, described true according to the propagation delay time and the processing delay The gateway time delay of the fixed forward gateway, comprising:
Practical time delay is determined according to the propagation delay time and the processing delay;
If the practical time delay is less than or equal to default time delay, the practical time delay is determined as gateway time delay;
If the practical time delay is greater than default time delay, the default time delay is determined as gateway time delay.
7. method according to any one of claims 1 to 6, which is characterized in that the determination is in the terminal and server Between the mark of forward gateway that E-Packets, comprising:
If the terminal is in the networking stage, when receiving the networking request of the terminal, from the terminal and the service Optimal gateway is selected at least one gateway between device;
The mark of the optimal gateway is determined as to the mark of the forward gateway;
Accordingly, described according to the gateway time delay, the setting time delay of the terminal is set, comprising:
The gateway time delay is determined as the setting time delay;
The setting time delay is set in the response message for networking request.
8. method according to any one of claims 1 to 6, which is characterized in that the determination is in the terminal and server Between the mark of forward gateway that E-Packets, comprising:
If the terminal is in the stage of communication after networking, the mark of the gateway of the uplink message of the terminal will be forwarded true It is set to the mark of forward gateway;
Accordingly, described according to the gateway time delay, the setting time delay of the terminal is set, comprising:
The current setting time delay of the terminal is obtained, both fixed response times are obtained;
If the gateway time delay is less than both fixed response times, both fixed response times are subtracted into a setting numerical value, when obtaining setting Prolong;
If the gateway time delay is greater than or equal to both fixed response times, the gateway time delay is determined as to set time delay;
The setting time delay is set in the transmitting order to lower levels for being sent to the terminal.
9. the control device that a kind of user equipment downlink window opens opportunity characterized by comprising
Gateway determining module, for determining the mark of the forward gateway to E-Packet between the terminal and server;
Gateway time delay determining module determines the gateway time delay of the forward gateway for the mark according to the forward gateway;Its In, the gateway time delay is for characterizing the speed speed that the server responds the forward gateway;
Time delay setup module is set, for the setting time delay of the terminal to be arranged according to the gateway time delay;Wherein, described to set Fixed response time is that terminal transmission uplink message terminated to the time difference for opening downlink window, and the downlink window is for the end End receives the downlink message that the server issues.
10. the control equipment that a kind of user equipment downlink window opens opportunity, which is characterized in that the equipment includes: memory, processing Device, the memory are stored with the computer program that can be run on a processor, and the processor executes the computer program The user equipment downlink window that any one of Shi Shixian the claims 1 to 8 provide opens the control method on opportunity.
11. a kind of computer readable storage medium, which is characterized in that be stored with computer in the computer readable storage medium Executable instruction, the computer executable instructions are configured to execute the user equipment downlink that any one of the claims 1 to 8 provide The control method on window unlatching opportunity.
CN201910947746.6A 2019-10-08 2019-10-08 Method, device, equipment and medium for controlling opening time of downlink window of terminal Active CN110446227B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910947746.6A CN110446227B (en) 2019-10-08 2019-10-08 Method, device, equipment and medium for controlling opening time of downlink window of terminal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910947746.6A CN110446227B (en) 2019-10-08 2019-10-08 Method, device, equipment and medium for controlling opening time of downlink window of terminal

Publications (2)

Publication Number Publication Date
CN110446227A true CN110446227A (en) 2019-11-12
CN110446227B CN110446227B (en) 2020-01-07

Family

ID=68440620

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910947746.6A Active CN110446227B (en) 2019-10-08 2019-10-08 Method, device, equipment and medium for controlling opening time of downlink window of terminal

Country Status (1)

Country Link
CN (1) CN110446227B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110690953A (en) * 2019-12-06 2020-01-14 武汉慧联无限科技有限公司 Downlink gateway selection method, device and computer storage medium
CN110708763A (en) * 2019-12-02 2020-01-17 武汉慧联无限科技有限公司 Scheduling method, device and computer storage medium
CN111414255A (en) * 2020-03-24 2020-07-14 武汉慧联无限科技有限公司 Data issuing control method, device and equipment and computer storage medium
CN112165353A (en) * 2020-09-24 2021-01-01 天宸星通(深圳)科技有限公司 Satellite Internet of things terminal network access authentication method
WO2021098807A1 (en) * 2019-11-21 2021-05-27 华为技术有限公司 Method and device for updating mapping

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107071836A (en) * 2017-03-03 2017-08-18 国动物联网技术(上海)有限公司 A kind of compatible CLASSA and CLASSB data downstream method
CN107343032A (en) * 2017-06-21 2017-11-10 武汉慧联无限科技有限公司 The offline detection method and device of terminal node in remote low power consumption network
CN107612668A (en) * 2017-09-06 2018-01-19 深圳天珑无线科技有限公司 Communication means, device, terminal, server and storage medium based on LoRa
CN108235404A (en) * 2016-12-22 2018-06-29 上海未来宽带技术股份有限公司 A kind of realization method and system of wireless network relaying
CN108471642A (en) * 2018-03-26 2018-08-31 厦门四信通信科技有限公司 A kind of infusion pump network of LoRa transmission
US10178617B2 (en) * 2017-05-01 2019-01-08 Mueller International, Llc Hail and acceptance for battery-powered devices
CN109511154A (en) * 2018-12-28 2019-03-22 东信和平科技股份有限公司 A kind of terminal access method, device and medium
CN110278617A (en) * 2019-06-21 2019-09-24 浙江理工大学 A kind of LoRaWAN channel confliction bypassing method based on time division multiple acess

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108235404A (en) * 2016-12-22 2018-06-29 上海未来宽带技术股份有限公司 A kind of realization method and system of wireless network relaying
CN107071836A (en) * 2017-03-03 2017-08-18 国动物联网技术(上海)有限公司 A kind of compatible CLASSA and CLASSB data downstream method
US10178617B2 (en) * 2017-05-01 2019-01-08 Mueller International, Llc Hail and acceptance for battery-powered devices
CN107343032A (en) * 2017-06-21 2017-11-10 武汉慧联无限科技有限公司 The offline detection method and device of terminal node in remote low power consumption network
CN107612668A (en) * 2017-09-06 2018-01-19 深圳天珑无线科技有限公司 Communication means, device, terminal, server and storage medium based on LoRa
CN108471642A (en) * 2018-03-26 2018-08-31 厦门四信通信科技有限公司 A kind of infusion pump network of LoRa transmission
CN109511154A (en) * 2018-12-28 2019-03-22 东信和平科技股份有限公司 A kind of terminal access method, device and medium
CN110278617A (en) * 2019-06-21 2019-09-24 浙江理工大学 A kind of LoRaWAN channel confliction bypassing method based on time division multiple acess

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021098807A1 (en) * 2019-11-21 2021-05-27 华为技术有限公司 Method and device for updating mapping
CN110708763A (en) * 2019-12-02 2020-01-17 武汉慧联无限科技有限公司 Scheduling method, device and computer storage medium
CN110690953A (en) * 2019-12-06 2020-01-14 武汉慧联无限科技有限公司 Downlink gateway selection method, device and computer storage medium
CN110690953B (en) * 2019-12-06 2020-04-24 武汉慧联无限科技有限公司 Downlink gateway selection method, device and computer storage medium
CN111414255A (en) * 2020-03-24 2020-07-14 武汉慧联无限科技有限公司 Data issuing control method, device and equipment and computer storage medium
CN111414255B (en) * 2020-03-24 2023-05-23 武汉慧联无限科技有限公司 Data issuing control method, device, equipment and computer storage medium
CN112165353A (en) * 2020-09-24 2021-01-01 天宸星通(深圳)科技有限公司 Satellite Internet of things terminal network access authentication method

Also Published As

Publication number Publication date
CN110446227B (en) 2020-01-07

Similar Documents

Publication Publication Date Title
CN110446227A (en) Control method and device, the equipment, medium on user equipment downlink window unlatching opportunity
CN108337698B (en) Multilink-based data stream adjusting method, device, equipment and medium
Lai et al. Performance modeling and analysis of TCP and UDP flows over software defined networks
KR101153970B1 (en) Routing method for wireless mesh networks and wireless mesh network system using the same
CN106507696A (en) It is used to determine whether to initiate the first network node of the second multi-path transmission control protocol connection and method therein
WO2019157855A1 (en) Quality of service (qos) parameter processing method, network element, system, and storage medium
CN104040917A (en) System and Method for Quality of Service Control
US20190364440A1 (en) Role selection method in wireless communication networks
Chaporkar et al. An adaptive strategy for maximizing throughput in mac layer wireless multicast
Zhao et al. Exploiting link correlation for core-based dissemination in wireless sensor networks
Liu et al. Delay-aware multipath source routing protocol to providing QoS support for wireless ad hoc networks
Hou et al. A delay‐based transport layer mechanism for fair TCP throughput over 802.11 multihop wireless mesh networks
WO2021082732A1 (en) Communication method and communication apparatus
Lee et al. Opportunistic downlink data delivery for mobile collaborative communities
US20220124539A1 (en) Information configuration method, network apparatus, and terminal
Jamshaid et al. Mechanisms for centralized flow rate control in 802.11-based wireless mesh networks
CN113170352B (en) Multi-band communication in wireless mesh networks
CN110519778B (en) Downlink message sending method and device, equipment and medium
Makarevitch Jamming resistant architecture for WiMAX mesh network
US11785497B2 (en) First node, second node, third node, and methods performed thereby, for handling data traffic
Kipnis et al. The angel IEEE 802.15. 4 enhancement layer: Coupling priority queueing and service differentiation
Nguyen et al. Packet size variability affects collisions and energy efficiency in WLANs
Chowdhury et al. XCHARM: A routing protocol for multi-channel wireless mesh networks
Cui et al. Buffer-aware opportunistic routing for wireless sensor networks
Zhong et al. Adaptive load balancing algorithm for multi-homing mobile nodes in local domain

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Control method, device, equipment and medium of opening time of terminal downlink window

Effective date of registration: 20220324

Granted publication date: 20200107

Pledgee: China Construction Bank Corporation Wuhan Guanggu Free Trade Zone Branch

Pledgor: WUHAN EASYLINKIN TECHNOLOGY CO.,LTD

Registration number: Y2022420000077