Prior art keywords
temperature controller
gateway
air conditioner
central air
communication
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910595360.3A
Other languages
Chinese (zh)
Other versions
CN110440422B (en
Inventor
梁永波
张忠
曾水根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Urban Investment Comprehensive Energy Investment Management Co ltd
Original Assignee
Guangzhou University Town Investment Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou University Town Investment Management Co Ltd filed Critical Guangzhou University Town Investment Management Co Ltd
Priority to CN201910595360.3A priority Critical patent/CN110440422B/en
Publication of CN110440422A publication Critical patent/CN110440422A/en
Application granted granted Critical
Publication of CN110440422B publication Critical patent/CN110440422B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/50Control or safety arrangements characterised by user interfaces or communication
    • F24F11/56Remote control
    • F24F11/58Remote control using Internet communication
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/89Arrangement or mounting of control or safety devices
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q20/00Payment architectures, schemes or protocols
    • G06Q20/08Payment architectures
    • G06Q20/14Payment architectures specially adapted for billing systems
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q20/00Payment architectures, schemes or protocols
    • G06Q20/22Payment schemes or models
    • G06Q20/28Pre-payment schemes, e.g. "pay before"
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07FCOIN-FREED OR LIKE APPARATUS
    • G07F17/00Coin-freed apparatus for hiring articles; Coin-freed facilities or services
    • G07F17/0014Coin-freed apparatus for hiring articles; Coin-freed facilities or services for vending, access and use of specific services not covered anywhere else in G07F17/00
    • G07F17/0021Access to services on a time-basis

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Accounting & Taxation (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Chemical & Material Sciences (AREA)
  • Finance (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Human Computer Interaction (AREA)
  • Development Economics (AREA)
  • Economics (AREA)
  • Air Conditioning Control Device (AREA)

Abstract

The present invention is the central air conditioner temperature controller Payment control method based on LORA communication, and temperature controller has communication module, comprising the following steps: temperature controller establishes communication connection with the gateway with communication module;Gateway and Cloud Server establish communication connection, and having can call the host computer of Third-party payment interface to be connected to Cloud Server;The value data of payment is sent in temperature controller by host computer by Cloud Server and gateway: temperature controller uses the time by record air-conditioning draught fan or the accumulative of two-port valve, amount is deducted until when remaining sum reaches setting value by accumulative correspond to using the time, stops using temperature controller.The present invention also provides the central air conditioner temperature controller Cost Control Systems based on communication.Temperature controller of the invention can be avoided wiring, avoid the cumbersome scheme that legacy user is supplemented with money by IC card, by calling the convenient and fast paying of Third-party payment platform interface, and is written to record recharge amount in temperature controller and central air-conditioning is operated normally.

Description

Central air conditioner temperature controller Payment control method and its system based on LORA communication
Technical field
The present invention relates to central air conditioning system field, especially a kind of central air conditioner temperature controller based on LORA communication Payment control method and its system.
Background technique
Central Air Conditioning Billing System mainly has two kinds of charging modes of energy type and time type, and energy type charging passes through each Air conditioning terminal installation ultrasonic wave or electromagnetism cold meter measure, but are much taken with ultrasonic calorimeter in Practical Project negative Method replaces cold meter, and calorimetry is usually the big temperature difference of small flow, and cooling capacity measurement is usually the small temperature difference of big flow, to temperature The requirement for spending measurement is high, and the ultrasonic calorimeter that tradition is used in heating measurement is unsuitable to apply to the cooling capacity measurement of air-conditioning, and dedicated Air-conditioning cold meter it is at high cost, installation is complicated, and maintenance is inconvenient, it is also necessary to periodic verification, and cooling capacity meter only measures cooling capacity, and There is no the component of control valve, electric two-way valve cannot be controlled, is difficult to large area in view of various reasons energy type charging It promotes.
It can replace energy type charging well in a manner of equivalent time charging at this stage.Time type charging is with " GBT 29580-2013 Time Method central air conditioning individual household metering device " it is standard, by the heat exchange, that is, two-way for acquiring high, normal, basic three gear The threshold switch time obtains equivalent time multiplied by corresponding power coefficient, is a kind of relatively accurate metering method, and which has Following advantages: one, seemingly metering user uses the equivalent time of air-conditioning to time measurement, and substantially, metering also It is effective refrigerating capacity used by a user.Metering based on time is the effective cooling time for measuring each end, user effective Refrigerating capacity in cooling time is indirectly showed with time mode.Since effective cooling time and refrigerating capacity are one linear Relationship, so in essence, the target of metering based on time and metering in energy is consistent.Two, metering based on time system It is not related with water system.Since for all-electronic system, all connections are electrical connection, therefore air-conditioner water system of getting along well Connection, installation, debugging and maintenance are quite convenient to, and a usual common electrical has the ability to carry out not shutdown maintenance and replacement, The operation of air-conditioner set and the normal use of other users are not interfered with.Three, time type temperature controller can with collection site temperature, And more functions can be able to achieve with equipment networking by controlling two-port valve.
Traditional time type Central Air Conditioning Billing System is C/S structure, and user needs with IC card to administrator charging center Computer, which supplement with money, could use air-conditioning, and now with the universal of network payment, the present invention uses cloud platform B/S framework, user It can realize that network supplements payment, small routine with money and remotely controls the behaviour such as air-conditioning use, inquiry into expenses, refund by mobile phone barcode scanning Make, administrator can be managed by mobile phone small routine or the computer surfed the Internet with any by log-on webpage whenever and wherever possible Charge system.
Summary of the invention
Present invention aims at above-mentioned technical problem is solved, a kind of central air conditioner temperature controller expense based on LORA communication is provided With control method and its system.Through the invention based on LORA communication central air conditioner temperature controller Payment control method and its be System, so that temperature controller can be avoided wiring, avoids the cumbersome scheme that legacy user is supplemented with money by IC card, directly passes through calling the The convenient and fast paying of tripartite's payment platform interface, and be written in temperature controller record recharge amount enable central air-conditioning just Often operation.
In order to achieve the above object, technical solution of the present invention has:
Based on the central air conditioner temperature controller Payment control method of LORA communication, temperature controller has LORA communication module, including Following steps:
The temperature controller establishes communication connection with the gateway with LORA communication module;
The gateway and Cloud Server establish communication connection, and having can call the host computer of Third-party payment interface to connect To the Cloud Server;
The value data of payment is sent in the temperature controller by the host computer by the Cloud Server and gateway:
The temperature controller uses the time by record air-conditioning draught fan or the accumulative of two-port valve, by accumulative corresponding using the time Amount is deducted until stopping using temperature controller when remaining sum reaches setting value.
It is logical using wireless LORA according to the central air conditioner temperature controller Payment control method based on LORA communication of the application Believe that module carries out the communication between temperature controller and gateway, realize the wireless connection between temperature controller and gateway, it is logical to no longer need to setting Route is interrogated, saves installation cost and the set-up time of product, and Cloud Server and host computer, host computer are connected by gateway The interface that third hair payment platform can easily be called, realizes the online payment operation on host computer, avoids traditional Many and diverse step that IC card is supplemented with money directly can be completed the payment to temperature controller by newest on-line payment technology, enable users to It is enough more easily to use central air-conditioning, and the value data supplemented with money is sent directly to store in temperature controller, so i.e. Make gateway suspension, still is able in temperature controller voluntarily carry out accumulative operation of deducting fees, is further convenient for the user to use, avoids Gateway suspension is made troubles to user;And LORA communicates the communication distance that can be realized five kilometers of ranks, so a building Or arrange that a gateway can cover whole area in several neighbouring buildings.
Further, the step further include:
Value data conversion is used the time by the temperature controller, and corresponding deduct adds up using the time until using the time When reaching setting value, temperature controller is stopped using.By the time can more intuitive prompt user recognize remaining use when Between, convenient for supplementing purchase with money in time using duration, central air-conditioning is avoided to stop using because of arrearage.
Further, the step further include:
The gateway and multiple temperature controllers establish communication connection, and a temperature controller has unique communication Data Identification.
Further, the step further include:
The gateway establishes communication connection using mobile wireless network or internet and Cloud Server.Mobile wireless network packet Include the mobile invalid network such as GPRS, 2G, 3G, 4G and 5G and internet be commonly used between host computer and host computer with The means communicated between Cloud Server, so the gateway also uses aforesaid way and cloud service to establish communication connection, to build Communication connection between view and host computer.
It further, further include the cooling capacity meter with LORA communication module and the voltameter with LORA communication module, The step further include:
The cooling capacity meter and voltameter and the gateway establish communication connection.Between plate changes and refrigerating plant room is generally positioned at ground Under, the signals such as general signal such as zigbee are difficult to be completely covered, but LORA has telecommunication and strong anti-interference ability, peace Mounted in plate change between or refrigerating plant room in cold meter and voltameter can be by LORA communication module by the cold energy consumption analysis of central air-conditioning Data transmission is sent to Cloud Server storage to gateway, and by gateway, convenient for the operational data collection of central air-conditioning, and deposits A large amount of central air-conditioning operation datas of storage have the statistical significance of height, and the operation for studying central air-conditioning has height Value.
Further, the step further include:
The host computer is mobile phone, plate or PC, which is transmitted by Cloud Server and gateway to the temperature controller Control signal.Charge system is logged in by small routine on mobile phone, plate and PC, application program or webpage, it can be by the Tripartite's payment platform carries out the operation such as recharge amount, no longer needs to supplement with money using traditional IC card, and host computer can also pass through Charge system controls temperature controller, transmits control instruction to temperature controller by Cloud Server and gateway.
Further, the temperature controller includes main control board, Fare determined by travel time module, air conditioner power source and output driving mould Block, the step further include:
The air conditioner power source and output driving module are for driving air-conditioning draught fan and two-port valve to run, the Fare determined by travel time mould Block records air-conditioning draught fan starting or the two-port valve starting time carries out Fare determined by travel time, and forms described accumulative using the time or described make Use the amount of money.Fare determined by travel time module is arranged in temperature controller, enables the offline timing of temperature controller, so that temperature controller is in suspension Bales catch still is able to go using time or remaining sum.
Based on LORA communication central air conditioner temperature controller Cost Control System, including temperature controller, gateway, Cloud Server and Host computer, the gateway are equipped with first communication module and second communication module, and the first communication module is LORA communication module, The temperature controller has LORA communication module, which establishes communication connection, the net by first communication module and gateway It closing and communication connection is established by second communication module and Cloud Server, the host computer and Cloud Server establish communication connection, and Data are transmitted to temperature controller by Cloud Server and gateway.
Further, the second communication module is the communication module using mobile wireless network or internet communication.
Further, the host computer is mobile phone, plate or PC.
Detailed description of the invention
Fig. 1 is the connection schematic diagram for the central air conditioner temperature controller Cost Control System that LORA of the invention is communicated;
Fig. 2 is the recharge interface schematic diagram for the central air conditioner temperature controller Cost Control System that LORA of the invention is communicated;
Fig. 3 is that the display interface of the temperature controller for the central air conditioner temperature controller Cost Control System that LORA of the invention is communicated shows It is intended to.
Specific embodiment
Be described with reference to the drawings a kind of central air conditioner temperature controller Payment control method based on LORA communication of the invention and its System.
The central air conditioner temperature controller Cost Control System based on LORA communication as shown in Figure 1, including temperature controller, gateway, Cloud Server and host computer, the temperature controller are equipped with multiple, and each temperature controller has unique communication identifier, leads to It crosses the communication identifier to be bound with host computer, avoids mixing up between temperature controller and cause unnecessary confusion, the host computer is Mobile phone, plate or PC, can be established and cloud by tools such as small routine, application program and webpages on mobile phone, plate or PC Then the communication connection of server is called and is carried out with the interface of the Third-party payment platform on mobile phone, plate or PC in line charge Value.
The gateway is equipped with first communication module and second communication module, and the first communication module is that LORA communicates mould Block, the temperature controller have LORA communication module, which establishes communication connection by first communication module and gateway, described Gateway establishes communication connection by second communication module and Cloud Server, and the host computer and Cloud Server establish communication connection, And data are transmitted to temperature controller by Cloud Server and gateway.The data supplemented with money supplement temperature controller with money by Cloud Server and gateway It is interior.
The second communication module is the communication module using mobile wireless network or internet communication.
As shown in Fig. 2, Fig. 2 is a kind of interface schematic diagram of wechat mobile phone small routine of the invention, contains in schematic diagram and fill It is worth touch area, is that temperature controller is supplemented with money by touching the region to call wechat payment interface, in addition, being additionally provided with control temperature control The control area and display area of device such as show the Current Temperatures and set temperature of temperature controller, can press button adjusting by "+" "-" Set temperature touch area is saved, wind speed selects touch area, is capable of the wind speed of multi-gear adjustment central air-conditioning, model selection Touch Zone Domain selects suitable refrigeration or heating mode etc., locks touch area, can lock the control panel of temperature controller, switchs touch-control Region can remotely realize the switch of central air-conditioning, and historical data shows touch area, for showing that using for temperature controller can data And history curve.
As shown in figure 3, the operation picture of temperature controller, operation picture is provided with multiple buttons, can show room temperature, setting temperature Degree, on-off state, mode state, gustiness and timing etc..The temperature controller includes main control board, Fare determined by travel time mould Block, air conditioner power source and output driving module, the air conditioner power source and output driving module are for driving air-conditioning draught fan and two-port valve It runs, the Fare determined by travel time module record air-conditioning draught fan starting or two-port valve starting time carry out Fare determined by travel time, and described in formation It is accumulative to use time or the amount.Fare determined by travel time module is arranged in temperature controller, temperature controller is counted offline When, so that temperature controller still is able to bales catch in suspension and goes using time or remaining sum.
Based on the central air conditioner temperature controller Payment control method of LORA communication, temperature controller has LORA communication module, including Following steps:
The temperature controller establishes communication connection with the gateway with LORA communication module;
The gateway and Cloud Server establish communication connection, and having can call the host computer of Third-party payment interface to connect To the Cloud Server;
The value data of payment is sent in the temperature controller by the host computer by the Cloud Server and gateway:
The temperature controller uses the time by record air-conditioning draught fan or the accumulative of two-port valve, by accumulative corresponding using the time Amount is deducted until stopping using temperature controller when remaining sum reaches setting value.Two-port valve timing mode uses equivalent time meter Take.Blower timing mode uses fan operation time-based charging, accumulative in temperature controller using the time and it is remaining using the time by height In the low three temperature coefficient conversions kept out the wind at a temperature of fast acquisition time, wind speed coefficient and different set obtain, converting standard energy conservation Operating condition recommends 26 degrees Celsius of set temperature and low-grade wind speed.Taken according to the central air conditioner temperature controller based on LORA communication of the application With control method, the communication between temperature controller and gateway is carried out using wireless LORA communication module, realizes temperature controller and gateway Between wireless connection, no longer need to setting communication line, save installation cost and the set-up time of product, and pass through gateway Cloud Server and host computer are connected, host computer can easily call the interface of third hair payment platform, realize on host computer Online payment operation, avoid many and diverse step that traditional IC card is supplemented with money, directly pass through newest on-line payment technology The payment to temperature controller is completed, allows users to more easily use central air-conditioning, and the value data supplemented with money is straight Sending and receiving are sent in temperature controller and store, accordingly even when gateway suspension, still is able in temperature controller voluntarily carry out accumulative operation of deducting fees, It is further convenient for the user to use, avoid gateway suspension makes troubles to user;And LORA communication can be realized five public affairs In rank communication distance, so in a building or neighbouring several buildings arrange a gateway can cover whole area.
The step further include:
Value data conversion is used the time by the temperature controller, and corresponding deduct adds up using the time until using the time When reaching setting value, temperature controller is stopped using.By the time can more intuitive prompt user recognize remaining use when Between, convenient for supplementing purchase with money in time using duration, central air-conditioning is avoided to stop using because of arrearage.
The step further include:
The gateway and multiple temperature controllers establish communication connection, and a temperature controller has unique communication Data Identification.
The step further include:
The gateway establishes communication connection using mobile wireless network or internet and Cloud Server.Mobile wireless network packet Include the mobile invalid network such as GPRS, 2G, 3G, 4G and 5G and internet be commonly used between host computer and host computer with The means communicated between Cloud Server, so the gateway also uses aforesaid way and cloud service to establish communication connection, to build Communication connection between view and host computer.
It further include the cooling capacity meter with LORA communication module and the voltameter with LORA communication module, the step is also wrapped It includes:
The cooling capacity meter and voltameter and the gateway establish communication connection.Between plate changes and refrigerating plant room is generally positioned at ground Under, the signals such as general signal such as zigbee are difficult to be completely covered, but LORA has telecommunication and strong anti-interference ability, peace Mounted in plate change between or refrigerating plant room in cold meter and voltameter can be by LORA communication module by the cold energy consumption analysis of central air-conditioning Data transmission is sent to Cloud Server storage to gateway, and by gateway, convenient for the operational data collection of central air-conditioning, and deposits A large amount of central air-conditioning operation datas of storage have the statistical significance of height, and the operation for studying central air-conditioning has height Value.
The step further include:
The host computer is mobile phone, plate or PC, which is transmitted by Cloud Server and gateway to the temperature controller Control signal.Charge system is logged in by small routine on mobile phone, plate and PC, application program or webpage, it can be by the Tripartite's payment platform carries out the operation such as recharge amount, no longer needs to supplement with money using traditional IC card, and host computer can also pass through Charge system controls temperature controller, transmits control instruction to temperature controller by Cloud Server and gateway.
The temperature controller includes main control board, Fare determined by travel time module, air conditioner power source and output driving module, the step Further include:
The air conditioner power source and output driving module are for driving air-conditioning draught fan and two-port valve to run, the Fare determined by travel time mould Block records air-conditioning draught fan starting or the two-port valve starting time carries out Fare determined by travel time, and forms described accumulative using the time or described make Use the amount of money.Fare determined by travel time module is arranged in temperature controller, enables the offline timing of temperature controller, so that temperature controller is in suspension Bales catch still is able to go using time or remaining sum.
According to the disclosure and teachings of the above specification, those skilled in the art in the invention can also be to above-mentioned embodiment party Formula is changed and is modified.Therefore, the invention is not limited to the specific embodiments disclosed and described above, to of the invention Some modifications and changes should also be as falling into the scope of the claims of the present invention.In addition, although being used in this specification Some specific terms, these terms are merely for convenience of description, does not limit the present invention in any way.

Claims (10)

1. the central air conditioner temperature controller Payment control method based on LORA communication, which is characterized in that temperature controller is communicated with LORA Module, comprising the following steps:
The temperature controller establishes communication connection with the gateway with LORA communication module;
The gateway and Cloud Server establish communication connection, and having can call the host computer of Third-party payment interface to be connected to institute State Cloud Server;
The value data of payment is sent in the temperature controller by the host computer by the Cloud Server and gateway:
The temperature controller uses the time by recording air-conditioning draught fan or the accumulative of two-port valve, uses time corresponding deduction by accumulative Amount stops using temperature controller until when remaining sum reaches setting value.
2. the central air conditioner temperature controller Payment control method according to claim 1 based on LORA communication, which is characterized in that The step further include:
Value data conversion is used the time by the temperature controller, and corresponding deduct is added up using the time until being reached using the time When setting value, temperature controller is stopped using.
3. the central air conditioner temperature controller Payment control method according to claim 1 based on LORA communication, which is characterized in that The step further include:
The gateway and multiple temperature controllers establish communication connection, and a temperature controller has unique communication Data Identification.
4. the central air conditioner temperature controller Payment control method according to claim 1 based on LORA communication, which is characterized in that The step further include:
The gateway establishes communication connection using mobile wireless network or internet and Cloud Server.
5. the central air conditioner temperature controller Payment control method according to claim 1 based on LORA communication, which is characterized in that It further include the cooling capacity meter with LORA communication module and the voltameter with LORA communication module, the step further include:
The cooling capacity meter and voltameter and the gateway establish communication connection.
6. the central air conditioner temperature controller Payment control method according to claim 1 based on LORA communication, which is characterized in that The step further include:
The host computer is mobile phone, plate or PC, which is transmitted to the temperature controller by Cloud Server and gateway and controlled Signal.
7. the central air conditioner temperature controller Payment control method according to claim 2 based on LORA communication, which is characterized in that The temperature controller includes main control board, Fare determined by travel time module, air conditioner power source and output driving module, the step further include:
The air conditioner power source and output driving module are for driving air-conditioning draught fan and two-port valve to run, the Fare determined by travel time module note It records air-conditioning draught fan starting or the two-port valve starting time carries out Fare determined by travel time, and formed described accumulative using the time or described using gold Volume.
8. the central air conditioner temperature controller Cost Control System based on LORA communication, which is characterized in that including temperature controller, gateway, cloud Server and host computer, the gateway are equipped with first communication module and second communication module, and the first communication module is LORA communication module, the temperature controller have LORA communication module, which is established logical by first communication module and gateway News connection, the gateway establish communication connection by second communication module and Cloud Server, and the host computer is built with Cloud Server Vertical communication connection, and data are transmitted to temperature controller by Cloud Server and gateway.
9. the central air conditioner temperature controller Cost Control System according to claim 8 based on LORA communication, which is characterized in that The second communication module is the communication module using mobile wireless network or internet communication.
10. the central air conditioner temperature controller Cost Control System according to claim 8 based on LORA communication, feature exist In the host computer is mobile phone, plate or PC.
CN201910595360.3A 2019-07-03 2019-07-03 LORA communication-based central air-conditioning temperature controller cost control method and system Active CN110440422B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910595360.3A CN110440422B (en) 2019-07-03 2019-07-03 LORA communication-based central air-conditioning temperature controller cost control method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910595360.3A CN110440422B (en) 2019-07-03 2019-07-03 LORA communication-based central air-conditioning temperature controller cost control method and system

Publications (2)

Publication Number Publication Date
CN110440422A true CN110440422A (en) 2019-11-12
CN110440422B CN110440422B (en) 2020-06-30

Family

ID=68429423

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910595360.3A Active CN110440422B (en) 2019-07-03 2019-07-03 LORA communication-based central air-conditioning temperature controller cost control method and system

Country Status (1)

Country Link
CN (1) CN110440422B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112413830A (en) * 2020-11-02 2021-02-26 青岛海尔空调器有限总公司 Information processing method and information processing equipment for shared air conditioning system
CN113883693A (en) * 2021-10-28 2022-01-04 湖北合合能源科技发展有限公司 Metering method of centralized central air-conditioning system
CN113917211A (en) * 2021-11-05 2022-01-11 万合智联(浙江)科技有限公司 Central air-conditioning charging and distributing system
CN114046597A (en) * 2021-11-15 2022-02-15 万合智联(浙江)科技有限公司 Central air conditioning's interior machine data collection station

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140324244A1 (en) * 2013-04-29 2014-10-30 Eaton Corporation Centralized controller for intelligent control of thermostatically controlled devices
CN104359193A (en) * 2014-12-29 2015-02-18 江苏联宏自动化系统工程有限公司 Fan coil temperature controller adopting multiple energy saving models
CN107576007A (en) * 2017-10-12 2018-01-12 深圳市信锐网科技术有限公司 A kind of method and system of tail end of central air conditioner control, management platform, thermostat
CN107726546A (en) * 2017-10-11 2018-02-23 武汉鸿图节能技术有限公司 The central air-conditioning intelligence system and its control method of unmanned operation
CN208027194U (en) * 2018-04-19 2018-10-30 广州大学城能源发展有限公司 A kind of intelligent temperature controller
CN208312633U (en) * 2018-05-30 2019-01-01 杭州九米建筑设计有限公司 Central air-conditioning Real-time Billing System based on energy scale and pulse ammeter
CN109474660A (en) * 2018-09-21 2019-03-15 广州柏诚智能科技有限公司 A kind of cloud energy management system based on NB-IoT technology

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140324244A1 (en) * 2013-04-29 2014-10-30 Eaton Corporation Centralized controller for intelligent control of thermostatically controlled devices
CN104359193A (en) * 2014-12-29 2015-02-18 江苏联宏自动化系统工程有限公司 Fan coil temperature controller adopting multiple energy saving models
CN107726546A (en) * 2017-10-11 2018-02-23 武汉鸿图节能技术有限公司 The central air-conditioning intelligence system and its control method of unmanned operation
CN107576007A (en) * 2017-10-12 2018-01-12 深圳市信锐网科技术有限公司 A kind of method and system of tail end of central air conditioner control, management platform, thermostat
CN208027194U (en) * 2018-04-19 2018-10-30 广州大学城能源发展有限公司 A kind of intelligent temperature controller
CN208312633U (en) * 2018-05-30 2019-01-01 杭州九米建筑设计有限公司 Central air-conditioning Real-time Billing System based on energy scale and pulse ammeter
CN109474660A (en) * 2018-09-21 2019-03-15 广州柏诚智能科技有限公司 A kind of cloud energy management system based on NB-IoT technology

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112413830A (en) * 2020-11-02 2021-02-26 青岛海尔空调器有限总公司 Information processing method and information processing equipment for shared air conditioning system
WO2022088895A1 (en) * 2020-11-02 2022-05-05 重庆海尔空调器有限公司 Information processing method and information processing device for shared air-conditioning system
CN113883693A (en) * 2021-10-28 2022-01-04 湖北合合能源科技发展有限公司 Metering method of centralized central air-conditioning system
CN113917211A (en) * 2021-11-05 2022-01-11 万合智联(浙江)科技有限公司 Central air-conditioning charging and distributing system
CN114046597A (en) * 2021-11-15 2022-02-15 万合智联(浙江)科技有限公司 Central air conditioning's interior machine data collection station

Also Published As

Publication number Publication date
CN110440422B (en) 2020-06-30

Similar Documents

Publication Publication Date Title
CN110440422A (en) Central air conditioner temperature controller Payment control method and its system based on LORA communication
CN201858710U (en) Remote control device of heating system
CN201210322Y (en) Pre-payment electrical energy meter
CN201748553U (en) Intelligent temperature control type pre-payment heat meter
CN203870789U (en) Bluetooth remote-transmission metering and meter reading system
CN104991540A (en) Telemetering communication system of temperature control and heat metering, and method thereof
CN104180825A (en) Charge system of central air conditioner of hotel
CN112330885A (en) Central air conditioner charging method, system, charging management equipment and storage medium
CN108280637B (en) Artificial intelligence internet of things charging valve and method
CN1959263B (en) Air conditioning system and operation method
CN203190519U (en) Concentrator circuit for heating system
CN101839521B (en) Real-time heat sharing device
CN202813650U (en) Monitoring device for central air-conditioner fan coil energy conservation
CN2482656Y (en) Central heating system temperature controller for charge
CN202694121U (en) Data acquisition system for energy storage air conditioner
CN2913914Y (en) Intelligent control device for household heating
CN203397431U (en) System for wirelessly reading gas meter employing integrated circuit (IC) card prepaid multi-rate
CN205951734U (en) Batteries of electric vehicle fills and trades integrated frame
CN202660681U (en) Control system of energy-storage air conditioning local work station
CN110440423B (en) Novel charging central air-conditioning temperature controller and display method thereof
CN206771516U (en) A kind of heating temperature control module and automatic temperature-adjusting control system
CN208954224U (en) A kind of toilet intelligence lavatory paper box
CN208188706U (en) A kind of heat meter based on NFC technique
KR20120094625A (en) Energy management system and air-conditioning system including the same
CN201654503U (en) Energy-saving network universal controller

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 510006 Floor 9, information hub building, No. 1, Chengzhong 6th Road, Guangzhou University, Xiaoguwei, Panyu District, Guangzhou City, Guangdong Province (office use only)

Patentee after: Guangzhou Urban Investment Comprehensive Energy Investment Management Co.,Ltd.

Address before: 9th Floor, Information Hub Building, Zhongliu Road, Xiaoguwei Street, Panyu District, Guangzhou City, Guangdong Province, 510000

Patentee before: Guangzhou University Town Investment Management Co.,Ltd.

CP03 Change of name, title or address