CN110335018A - Low-voltage network project feasibility study review system and method - Google Patents

Low-voltage network project feasibility study review system and method Download PDF

Info

Publication number
CN110335018A
CN110335018A CN201910531923.2A CN201910531923A CN110335018A CN 110335018 A CN110335018 A CN 110335018A CN 201910531923 A CN201910531923 A CN 201910531923A CN 110335018 A CN110335018 A CN 110335018A
Authority
CN
China
Prior art keywords
feasibility study
data
low
voltage network
network project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910531923.2A
Other languages
Chinese (zh)
Inventor
孔海波
王延梅
张慧
谢继信
李慧
周中华
李秀霞
刘君
刘延静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201910531923.2A priority Critical patent/CN110335018A/en
Publication of CN110335018A publication Critical patent/CN110335018A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Game Theory and Decision Science (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of low-voltage network project feasibility study review system and methods, the system includes: position resolver determining module, for obtaining the site inspection data in unreasonable area of layouting, capacity per family is calculated after radius of electricity supply and transformation, determines number transformer and position;Training program release module is depicted as training program table, and distribute data to corresponding junior's department user for obtaining pioneering program high voltage distribution network project data;Department, junior receiving module, for receiving training program table, and pops up training notice;Department, junior uploads feasibility study material module, the feasibility study data of each low-voltage network project for collecting and saving the upload of department, junior;The secondary interior careful module of feasibility study data, for obtaining the feasibility study data of each low-voltage network project, and by it compared with mesolow distribution project feasibility study review comment template, obtain low-voltage network project feasibility study data and lack data, and modifies adjustment to the feasibility study data of low-voltage network project.

Description

Low-voltage network project feasibility study review system and method
Technical field
This disclosure relates to a kind of low-voltage network project feasibility study review system and method.
Background technique
Existing low-voltage network project sufficiently week thickly incorporates related participating department opinion, to give project operation It ensures, carries out monomer project and overall network Synergy is analyzed, and carry out monomer project and the relevant item feasibility study goodness of fit Analysis.The existing low-voltage network number of entry is more, and material needed for each low-voltage network project is relatively more, need to divide every year Batch is designed evaluation in administrative service area, causes communication not smooth, evaluation period is longer.
Current evaluation mode is that higher level department passes through Email for the power distribution network low pressure feasibility study project's earlier stage in the current year Plan is sent to department, junior, it is also necessary to make a report on unit by Advise By Wire or notice of meeting junior and make a report on.Subordinate unit receives Collect the relevant data of all power distribution network low pressure projects in pioneering program, then is sent to by way of Email or paper document Higher level department.
Inventor has found that above scheme there is problems in R&D process:
The assessment material as required for each power distribution network low pressure project is more, reports in batches sometimes, and evaluates not Qualified material will be also retired to be made a report on again, this will occur assessment material report not in time, a kind of assessment material repeatedly sends out The case where sending, leads to that evaluation period is long, repeated workload is more, working efficiency is low, so that heavy-overload route, platform area problem are still Cannot solve, user's low-voltage, card neck subproblem there are still.
Summary of the invention
In order to overcome the above-mentioned deficiencies of the prior art, present disclose provides a kind of low-voltage network project feasibility study review systems And method, it realizes to low-voltage network project feasibility study management of appraising, improves evaluation quality and efficiency.
Technical solution used by the disclosure is:
A kind of low-voltage network project feasibility study review system, the system include:
Position resolver determining module obtains the scene in unreasonable area of layouting for filtering out unreasonable area of layouting It reconnoitres data, calculates after radius of electricity supply and transformation capacity per family, determine number transformer and position;
Training program release module is depicted as training program table for obtaining pioneering program high voltage distribution network project data, And distribute data to corresponding junior's department user;
Department, junior receiving module, for receiving training program table, and pops up training notice;
Department, junior uploads feasibility study material module, for collecting and saving each low-voltage network item of department, junior upload Purpose feasibility study data;
The secondary interior careful module of feasibility study data, for obtaining the feasibility study data of each low-voltage network project, and by it in Low-voltage distribution network project feasibility study review comment template is compared, and data, file etc. that low-voltage network project feasibility study data lacks are obtained Information, and modify adjustment to the feasibility study data of low-voltage network project.
It further, further include feasibility study ability evaluation module, the feasibility study ability evaluation module, for obtaining department, junior User's feasibility study professional technique aptitude tests data, give a mark.
It further, further include that feasibility study appraisal standards formulate module, the feasibility study appraisal standards formulate module, for formulating The check-up system of feasibility study Compilation Quality.
It further, further include feasibility study data Compilation Quality evaluation module, the feasibility study data Compilation Quality evaluation module, For obtaining the feasibility study data of each low-voltage network project, and by it compared with the check-up system of feasibility study Compilation Quality, statistics The feasibility study data Compilation Quality of low-voltage network project.
A kind of low-voltage network project feasibility study reviewing method evaluates system using low-voltage network project feasibility study as described above What system was realized, method includes the following steps:
It filters out unreasonable area of layouting, obtains the site inspection data in unreasonable area of layouting, using " low capacity, close Layout, short radius " principle, capacity per family after radius of electricity supply and transformation is calculated, determines number transformer and position;
Pioneering program high voltage distribution network project data is obtained, training program table is depicted as, and distributes data under corresponding Grade department user;
Training program table is received, and pops up training notice;
Collect and save the feasibility study data of each low-voltage network project of department, junior upload;
Obtain the feasibility study data of each low-voltage network project, and by itself and mesolow distribution project feasibility study review comment mould Plate is compared, and the information such as data, the file that low-voltage network project feasibility study data lacks are obtained, and to low-voltage network project can The data of grinding is modified adjustment;
It further, further include obtaining junior's department user feasibility study professional technique aptitude tests data, the step given a mark Suddenly.
It further, further include the check-up system for formulating feasibility study Compilation Quality;Obtain each low-voltage network project can Data is ground, and by it compared with the check-up system of feasibility study Compilation Quality, the feasibility study data of statistics low-voltage network project works out matter Amount.
Through the above technical solutions, the beneficial effect of the disclosure is:
(1) disclosure improves feasibility study evaluation percent of pass, promotes low pressure feasibility study quality, greatly reduces corrupt data rate It substantially reduces, provides reliable guarantee for the next step construction of Medial & Low Voltage Power Network;
(2) disclosure saves job costs, improves work efficiency, and shortens work in preliminary project stage and carries out the time, has Effect improves the power supply reliability and power supply capacity of power distribution network.
Detailed description of the invention
The Figure of description for constituting a part of this disclosure is used to provide further understanding of the disclosure, and the disclosure is shown Meaning property embodiment and its explanation do not constitute the improper restriction to the disclosure for explaining the application.
Fig. 1 is the structure chart of one low-voltage network project feasibility study review system of embodiment;
Fig. 2 is the flow chart of two low-voltage network project feasibility study reviewing method of embodiment.
Specific embodiment
The disclosure is described further with embodiment with reference to the accompanying drawing.
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the disclosure.Unless another It indicates, all technical and scientific terms that the disclosure uses have logical with disclosure person of an ordinary skill in the technical field The identical meanings understood.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
Embodiment one
Attached drawing 1 is please referred to, the present embodiment provides a kind of low-voltage network project feasibility study review system, which includes:
Position resolver determining module obtains the scene in unreasonable area of layouting for filtering out unreasonable area of layouting Data are reconnoitred, using " low capacity, gather point, short radius " principle, capacity per family is calculated after radius of electricity supply and transformation, determines transformation Device quantity and position;
Training program release module is depicted as training program table for obtaining pioneering program high voltage distribution network project data, And distribute data to corresponding junior's department user;
Department, junior receiving module, for receiving training program table, and pops up training notice;
Feasibility study ability evaluation module is beaten for obtaining junior's department user feasibility study professional technique aptitude tests data Point;
Department, junior uploads feasibility study material module, for collecting and saving each low-voltage network item of department, junior upload Purpose feasibility study data;
The secondary interior careful module of feasibility study data, for obtaining the feasibility study data of each low-voltage network project, and by it in Low-voltage distribution network project feasibility study review comment template is compared, and data, file etc. that low-voltage network project feasibility study data lacks are obtained Information, and modify adjustment to the feasibility study data of low-voltage network project;
Feasibility study appraisal standards formulate module, for formulating the check-up system of feasibility study Compilation Quality;
Feasibility study data Compilation Quality evaluation module, for obtaining the feasibility study data of each low-voltage network project, and by its Compared with the check-up system of feasibility study Compilation Quality, the feasibility study data Compilation Quality of low-voltage network project is counted.
In the present embodiment, the site inspection data include the power distribution locations for filtering out unreasonable regional transformer of layouting And capacity per family after transformation.
The present embodiment realizes rationally layouting for transformer by position resolver determining module, and capacity per family It is promoted, radius of electricity supply meets corresponding power supply area requirement after transformation, and capacity reaches the family 2.0kVA/ per family, is higher than standard requirements.This Embodiment reasonably optimizing transformer is layouted, and exploitativeness is strong, and timeliness is short, spends few.
The low-voltage network project feasibility study review system that the present embodiment proposes improves feasibility study evaluation percent of pass, is promoted low Feasibility study quality is pressed, corrupt data rate is greatly reduced and substantially reduces, work in preliminary project stage is shortened and carries out the time, effectively improve The power supply reliability and power supply capacity of power distribution network.
Embodiment two
Attached drawing 2 is please referred to, the present embodiment provides a kind of low-voltage network project feasibility study reviewing methods, and this method includes following Step:
It filters out unreasonable area of layouting, obtains the site inspection data in unreasonable area of layouting, using " low capacity, close Layout, short radius " principle, capacity per family after radius of electricity supply and transformation is calculated, determines number transformer and position;
Pioneering program high voltage distribution network project data is obtained, training program table is depicted as, and distributes data under corresponding Grade department user;
Training program table is received, and pops up training notice;
Junior's department user feasibility study professional technique aptitude tests data are obtained, are given a mark;
Collect and save the feasibility study data of each low-voltage network project of department, junior upload;
Obtain the feasibility study data of each low-voltage network project, and by itself and mesolow distribution project feasibility study review comment mould Plate is compared, and the information such as data, the file that low-voltage network project feasibility study data lacks are obtained, and to low-voltage network project can The data of grinding is modified adjustment;
Formulate the check-up system of feasibility study Compilation Quality;
The feasibility study data of each low-voltage network project is obtained, and by it compared with the check-up system of feasibility study Compilation Quality, Count the feasibility study data Compilation Quality of low-voltage network project.
The low-voltage network project feasibility study reviewing method that the present embodiment proposes improves feasibility study evaluation percent of pass, is promoted low Feasibility study quality is pressed, corrupt data rate is greatly reduced and substantially reduces, work in preliminary project stage is shortened and carries out the time, effectively improve The power supply reliability and power supply capacity of power distribution network.
Although above-mentioned be described in conjunction with specific embodiment of the attached drawing to the disclosure, model not is protected to the disclosure The limitation enclosed, those skilled in the art should understand that, on the basis of the technical solution of the disclosure, those skilled in the art are not Need to make the creative labor the various modifications or changes that can be made still within the protection scope of the disclosure.

Claims (7)

1. a kind of low-voltage network project feasibility study review system, characterized in that the system includes:
Position resolver determining module obtains the site inspection in unreasonable area of layouting for filtering out unreasonable area of layouting Data calculate capacity per family after radius of electricity supply and transformation, determine number transformer and position;
Training program release module is depicted as training program table, and divide for obtaining pioneering program high voltage distribution network project data Data are sent out to corresponding junior's department user;
Department, junior receiving module, for receiving training program table, and pops up training notice;
Department, junior uploads feasibility study material module, for collecting and saving each low-voltage network project of department, junior upload Feasibility study data;
The secondary interior careful module of feasibility study data, for obtaining the feasibility study data of each low-voltage network project, and by itself and mesolow Distribution project feasibility study review comment template is compared, and data, the file information that low-voltage network project feasibility study data lacks are obtained, and It modifies adjustment to the feasibility study data of low-voltage network project.
2. low-voltage network project feasibility study review system according to claim 1, characterized in that further include that feasibility study ability is examined Core module, the feasibility study ability evaluation module are carried out for obtaining junior's department user feasibility study professional technique aptitude tests data Marking.
3. low-voltage network project feasibility study review system according to claim 1, characterized in that further include feasibility study examination mark Standard formulates module, and the feasibility study appraisal standards formulate module, for formulating the check-up system of feasibility study Compilation Quality.
4. low-voltage network project feasibility study review system according to claim 3, characterized in that further include that feasibility study data is compiled Quality examination module processed, the feasibility study data Compilation Quality evaluation module, for obtaining the feasibility study of each low-voltage network project Data, and by it compared with the check-up system of feasibility study Compilation Quality, count the feasibility study data Compilation Quality of low-voltage network project.
5. a kind of low-voltage network project feasibility study reviewing method, using low-voltage distribution according to any one of claims 1 to 4 What net project feasibility study review system was realized, characterized in that method includes the following steps:
Filter out unreasonable area of layouting, obtain the site inspection data in unreasonable area of layouting, using " low capacity, densely covered point, Short radius " principle calculates capacity per family after radius of electricity supply and transformation, determines number transformer and position;
Pioneering program high voltage distribution network project data is obtained, training program table is depicted as, and distributes data to corresponding portion, junior Door user;
Training program table is received, and pops up training notice;
Collect and save the feasibility study data of each low-voltage network project of department, junior upload;
Obtain the feasibility study data of each low-voltage network project, and by itself and mesolow distribution project feasibility study review comment template phase Than obtaining data, the file information that low-voltage network project feasibility study data lacks, and to the feasibility study data of low-voltage network project It modifies adjustment.
6. low-voltage network project feasibility study reviewing method according to claim 5, characterized in that further include obtaining portion, junior Door user's feasibility study professional technique aptitude tests data, the step of marking.
7. low-voltage network project feasibility study reviewing method according to claim 5, characterized in that further include formulating to compile carefully The check-up system of quality processed;Obtain the feasibility study data of each low-voltage network project, and by the examination of itself and feasibility study Compilation Quality System is compared, and the feasibility study data Compilation Quality of low-voltage network project is counted.
CN201910531923.2A 2019-06-19 2019-06-19 Low-voltage network project feasibility study review system and method Pending CN110335018A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910531923.2A CN110335018A (en) 2019-06-19 2019-06-19 Low-voltage network project feasibility study review system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910531923.2A CN110335018A (en) 2019-06-19 2019-06-19 Low-voltage network project feasibility study review system and method

Publications (1)

Publication Number Publication Date
CN110335018A true CN110335018A (en) 2019-10-15

Family

ID=68142190

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910531923.2A Pending CN110335018A (en) 2019-06-19 2019-06-19 Low-voltage network project feasibility study review system and method

Country Status (1)

Country Link
CN (1) CN110335018A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105373885A (en) * 2015-11-10 2016-03-02 国网福建省电力有限公司 Electric power engineering design review and technical economic evaluation information system
CN107292578A (en) * 2016-04-10 2017-10-24 国网山东省电力公司经济技术研究院 The online estimating and examining system of high voltage distribution network project feasibility study and method
US20180143237A1 (en) * 2016-11-21 2018-05-24 Grid2020, Inc. Transformer monitoring and data analysis systems and methods
CN109449932A (en) * 2018-12-07 2019-03-08 国网辽宁省电力有限公司鞍山供电公司 It is a kind of based on voltage synchronous test low-voltage reforming mode determine method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105373885A (en) * 2015-11-10 2016-03-02 国网福建省电力有限公司 Electric power engineering design review and technical economic evaluation information system
CN107292578A (en) * 2016-04-10 2017-10-24 国网山东省电力公司经济技术研究院 The online estimating and examining system of high voltage distribution network project feasibility study and method
US20180143237A1 (en) * 2016-11-21 2018-05-24 Grid2020, Inc. Transformer monitoring and data analysis systems and methods
CN109449932A (en) * 2018-12-07 2019-03-08 国网辽宁省电力有限公司鞍山供电公司 It is a kind of based on voltage synchronous test low-voltage reforming mode determine method

Similar Documents

Publication Publication Date Title
CN109800250B (en) System architecture for no longer configuring enterprise central server
CN109858746A (en) A kind of fault ticket distributing method and fault ticket management system
CN104123134B (en) Intelligent electricity use data management method and system based on AMI and J2EE
CN105354268B (en) A kind of meter reading data management system
CN106600114A (en) Multi-dimensional quality evaluation method of collection operation and maintenance system
CN109934459B (en) Visual grid-based abnormal dispatching method for operation errors of low-voltage station electric energy meter
CN108921391A (en) A kind of method for distributing business and device
CN108171362A (en) Power supply facilities breakdown repair method, system and terminal device
CN112698123A (en) Low-voltage distribution area user topological relation identification method based on decision tree
CN104992279A (en) Performance assessment method and device
CN109038816A (en) A kind of polling transmission line management system
CN107292578A (en) The online estimating and examining system of high voltage distribution network project feasibility study and method
CN101931986A (en) Indication method of network energy efficiency, indicator and system
CN110335018A (en) Low-voltage network project feasibility study review system and method
CN109284330A (en) A kind of Internet of Things big data management system for garden
CN109190947A (en) A kind of traffic control evaluation system
CN109035062A (en) A kind of client's electricity charge anomaly analysis and tactful application system
CN111082418B (en) System and method for analyzing topological relation of power distribution network equipment
CN108596782A (en) A kind of quick interoperability methods of large-area power-cuts data
CN109829637A (en) A kind of medical services performance assessment system
CN109449930B (en) Power distribution network reliability assessment and repair time parameter modeling method, equipment and medium
CN112785276B (en) Engineering consultation management system and method
CN114880534A (en) Load aggregation information display method and device, electronic equipment and storage medium
CN111049157B (en) Distribution network transformer reactive compensation condition analysis method
CN109960231A (en) A kind of production management system and its method based on Internet of Things

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191015

RJ01 Rejection of invention patent application after publication