CN110286285A - A kind of test equipment and test method for testing AISG electricity tune equipment - Google Patents

A kind of test equipment and test method for testing AISG electricity tune equipment Download PDF

Info

Publication number
CN110286285A
CN110286285A CN201910621809.9A CN201910621809A CN110286285A CN 110286285 A CN110286285 A CN 110286285A CN 201910621809 A CN201910621809 A CN 201910621809A CN 110286285 A CN110286285 A CN 110286285A
Authority
CN
China
Prior art keywords
connector
equipment
test
aisg
signal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910621809.9A
Other languages
Chinese (zh)
Other versions
CN110286285B (en
Inventor
陈美多
张立红
吴四维
张明珠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Guoren Wireless Communication Co Ltd
Original Assignee
Shenzhen Compatriots Ltd Co That Communicates By Letter
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Compatriots Ltd Co That Communicates By Letter filed Critical Shenzhen Compatriots Ltd Co That Communicates By Letter
Priority to CN201910621809.9A priority Critical patent/CN110286285B/en
Publication of CN110286285A publication Critical patent/CN110286285A/en
Application granted granted Critical
Publication of CN110286285B publication Critical patent/CN110286285B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The present invention relates to a kind of test equipments and test method for testing AISG electricity tune equipment, the AISG electricity tune equipment includes the first connector and the second connector, the corresponding terminal of first connector is in parallel with the corresponding terminal of second connector, the test equipment includes third connector, the 4th connector, signal source and signal supervisory instrument, wherein: the signal source is connect with the third connector, for providing test signal to the third connector;The third connector can be connect with first connector;4th connector can be connect with second connector;The signal supervisory instrument is connect with the 4th connector, and can the signal supervisory instrument detect whether the AISG electricity tune equipment breaks down for receive the test signal passed over via first connector and the second connector according to the 4th connector.Detection efficiency of the present invention is high, time saving and energy saving.

Description

A kind of test equipment and test method for testing AISG electricity tune equipment
[technical field]
The present invention relates to test equipments and survey that a kind of test AISG (abbreviation of Antenna Interface Standards Group) electricity adjusts equipment Method for testing.
[background technique]
AISG electricity tune equipment generally includes a public connector and a female connectors, the corresponding terminal of public connector and mother The corresponding terminal of connector is in parallel.When carrying out fault detection to AISG electricity tune equipment, current test equipment can only be passed through Can detection public connector and female connectors transmit the test signal of test equipment offer respectively is to detect AISG electricity tune equipment No failure, since the corresponding terminal of public connector and the corresponding terminal of female connectors are in parallel, if one of connection Device breaks down, and while detecting uses another connector, and the AISG electricity tune equipment detected at this time can show as work Normally, fault detection can not be come out, to affect use.
[summary of the invention]
It is an object of the invention to overcome the shortcomings of above-mentioned technology, a kind of test equipment for testing AISG electricity tune equipment is provided And test method, the test equipment can be detected simultaneously by two connectors to AISG electricity tune equipment to realize that AISG electricity tune is set Standby fault detection, detection efficiency are high.
The first aspect of the present invention provides a kind of test equipment for testing AISG electricity tune equipment, the AISG electricity tune equipment packet Include the first connector and the second connector, the corresponding terminal of the corresponding terminal of first connector and second connector is simultaneously Connection, the test equipment includes third connector, the 4th connector, signal source and signal supervisory instrument, in which:
The signal source is connect with the third connector, for providing test signal to the third connector;
The third connector can be connect with first connector;
4th connector can be connect with second connector;
The signal supervisory instrument is connect with the 4th connector, and the signal supervisory instrument is used for according to the 4th connection It is described to detect that can device receive the test signal passed over via first connector and the second connector Whether AISG electricity tune equipment breaks down.
Further, the signal source includes voltage source, and the test signal includes voltage signal;The signal detection dress Set including reduction voltage circuit and voltage indicator lamp, the reduction voltage circuit is connect with the corresponding terminal of the 4th connector, for pair The voltage signal decompression passed over via first connector and the second connector, and by the voltage after decompression to institute State voltage indicator lamp power supply.
Further, the voltage signal is at least supplied to two independent terminals of first connector, and this two Independent terminals have voltage difference;Second connector, third connector and the 4th connector all have and the first connector pair At least two independent terminals answered.
Further, the signal source includes data signal source, and the test signal includes data-signal;The signal inspection Surveying device includes data processing module and communicate indicator light, the corresponding terminal of the data processing module and the 4th connector Connection, for handling the data-signal passed over via first connector and the second connector, and will Treated, and data-signal is transmitted through the communication indicator light.
Further, the data-signal is at least supplied to two independent terminals of first connector;Described second Connector, third connector and the 4th connector all have at least two independent terminals corresponding with the first connector.
The second aspect of the present invention provides a kind of test method of AISG electricity tune equipment, and the AISG electricity tune equipment includes the A connector and the second connector, the corresponding terminal of first connector is in parallel with the corresponding terminal of second connector, The test method includes the steps that carrying out fault detection, the test equipment to the AISG electricity tune equipment by test equipment Including third connector, the 4th connector, signal source and signal supervisory instrument;
Include: to the step of AISG electricity tune equipment progress fault detection by test equipment
Establish the connection between first connector and third connector;
Establish the connection between second connector and the 4th connector;
Test signal is provided to the third connector by the signal source;
The 4th connector, which can be detected, by signal supervisory instrument receive via first connector and the second connection The test signal that device passes over, the AISG electricity tune equipment fault as described in judgement if not receiving.
Further, the signal source includes voltage source, and the test signal is voltage signal;The signal supervisory instrument Including reduction voltage circuit and voltage indicator lamp, the reduction voltage circuit is connect with the corresponding terminal of the 4th connector, for warp The voltage signal decompression passed over by first connector and the second connector, and by the voltage after decompression to described Voltage indicator lamp power supply;If voltage indicator lamp does not work, then the AISG electricity tune equipment fault is determined.
Further, the signal source includes data signal source, and the test signal is data-signal;The signal detection Device includes that data processing module connects with indicator light, the corresponding terminal of the data processing module and the 4th connector is communicated It connects, for handling the data-signal passed over via first connector and the second connector, and will place Data-signal after reason is transmitted through the communication indicator light;It such as communicates indicator light not flash, then determines the AISG electricity tune equipment event Barrier.
Further, the test method further includes being surveyed by performance of the test equipment to the AISG electricity tune equipment The step of examination, the step include:
S1, test parameter is preset by test equipment, and load match corresponding with each sequence number of AISG electricity tune equipment Set file;The test parameter includes the motor angle value of software version number, hardware version numbers, 0.1 degree of umber of pulse and setting At least one;
S2, all sequences number that AISG electricity tune equipment is obtained by test equipment, and all sequences number that will acquire are sent To AISG electricity tune equipment to carry out sequence numbers match, if successful match, AISG electricity tune equipment is to test equipment feedback sequence number Successful match order;
S3, test command is sent to AISG electricity tune equipment by test equipment, test equipment is enable to set from AISG electricity tune Standby place obtains the property parameters of AISG electricity tune equipment, the property parameters include software version number, hardware version numbers, umber of pulse, At least one of align mode and the motor angle value of setting;
S4, the property parameters that will acquire by test equipment and default test parameter are matched, if successful match, are mentioned Show that test passes through, test terminates.
Further, in the step S3, the test command includes sequence number scanning, the address distribution of sequence number, sequence The link of row number, software version inquiry, hardware version inquiry, configuration file load, is calibrated, the angle of setting motor at information inquiry The motor angle value of degree, inquiry umber of pulse and setting;
Step S3 is specifically included:
S31, by test equipment to AISG electricity tune equipment successively transmit Sequence Number scanning, sequence number address distribution, sequence The test command of link, the information inquiry, software version inquiry, hardware version inquiry, configuration file load of row number;
AISG electricity tune equipment receive sequence number scanning, the address distribution of sequence number, the link of sequence number, information are looked into It askes, software version is inquired, hardware version is inquired, returns to this equipment to test equipment respectively after the test command of configuration file load All sequences number, all sequences number of this equipment are successively carried out address distribution and to test equipment return sequence number address It is allocated successfully order, all sequences number of this equipment are successively established with communication linkage and is returned to test equipment the link of sequence number Be successfully established order, information that this equipment is returned to test equipment, the software version number for returning to test equipment this equipment, to survey Examination equipment returns to the hardware version numbers of this equipment, all sequences number of this equipment is successively carried out with loading configuration file and to test Equipment returns to configuration file and loads success command;
S32, the test command for sending calibration to AISG electricity tune equipment by test equipment, AISG electricity tune equipment are receiving Calibration operation is carried out after the test command of calibration and returns to calibration success command to test equipment;
S33, the test command that the angle of motor is set, AISG electricity tune are sent to AISG electricity tune equipment by test equipment Equipment is configured the angle of motor after receiving the test command of angle of setting motor and originally sets to test equipment return At least one of the angle value of standby setting motor;
S34, the test for inquiring the motor angle value of umber of pulse and setting is sent to AISG electricity tune equipment by test equipment Order, AISG electricity tune equipment are returned in the test command back testing equipment for the motor angle value for receiving inquiry umber of pulse and setting Return at least one of the umber of pulse and the motor angle value of setting of this equipment.
Test equipment of the invention can be detected simultaneously by two connectors to AISG electricity tune equipment to realize AISG electricity The fault detection of equipment is adjusted, detection efficiency is high, time saving and energy saving.
[Detailed description of the invention]
Fig. 1 is a kind of circuit structure signal of the test equipment for test AISG electricity tune equipment that one embodiment of the invention provides Figure;
Fig. 2 is the electrical block diagram of AISG electricity tune equipment provided by the invention;
Fig. 3 is in a kind of test method for AISG electricity tune equipment that one embodiment of the invention provides by test equipment pair AISG electricity tune equipment carries out the block diagram representation of the step of fault detection;
Fig. 4 is electric to AISG by test equipment in a kind of test method of AISG electricity tune equipment provided by the invention The block diagram representation for the step of adjusting the performance of equipment to be tested;
Fig. 5 is the block diagram representation of step S3 shown in Fig. 4.
[specific embodiment]
The invention will be further described with reference to the accompanying drawings and examples.
With reference to Fig. 1 and Fig. 2, a kind of test equipment for testing AISG electricity tune equipment provided by the invention, the test equipment packet Include third connector 10 (public connector), the 4th connector 20 (female connectors), signal source 30 and signal supervisory instrument 40. AISG electricity tune equipment includes the first connector 61 (female connectors) and the second connector 62 (public connector), the first connector 61 Corresponding terminal is in parallel with the corresponding terminal of the second connector 62, and in the present embodiment, the first connector 61 and the second connector 62 divide It Ju You not terminal 1, terminal 2, terminal 3, terminal 4, terminal 5, terminal 6, terminal 7, terminal 8, terminal 9 totally 9 independent terminals.Letter Number source 30 is connect with third connector 10, for providing test signal to third connector 10.Third connector 10 can be with first Connector 61 connects, so that test signal can be passed to the first connector 61 by third connector 10, the first connector 61 can be incited somebody to action Test signal is supplied to the second connector 62.4th connector 20 can be connect with the second connector 62, thus the second connector 62 Test signal can be passed to the 4th connector 20.Signal supervisory instrument 40 is connect with the 4th connector 20, signal supervisory instrument Can 40 for receive the test passed over via the first connector 61 and the second connector 62 according to the 4th connector 20 Signal detects whether AISG electricity tune equipment breaks down.By this kind of structure, test equipment be can be used to AISG electricity tune equipment The first connector 61, the second connector 62 detection simultaneously mode detect whether AISG electricity tune equipment breaks down, detect It is high-efficient, it is time saving and energy saving.When actually carrying out fault detection to AISG electricity tune equipment by test equipment, by third connector 10 It is connect with the first connector 61, the 4th connector 20 connect and can be detected with the second connector 62.
Specifically, signal source 30 includes voltage source, test signal includes voltage signal.Signal supervisory instrument 40 includes drop Volt circuit 41 and voltage indicator lamp 42.Third connector 10 and the 4th connector 20 are respectively provided with terminal 1, terminal 2, terminal 3, end Son 4, terminal 5, terminal 6, terminal 7, the totally 8 independent terminals of terminal 8, when actually carrying out AISG electricity tune equipment fault detection, The 8 butt correspondence of third connector 10 is connect with preceding 8 butt of the first connector 61,8 butts of the 4th connector 20 Correspondence is connect with preceding 8 butt of the second connector 62.Voltage source can pass through GND (electric wire ground terminal) 1 line and VCC IN (electricity Source input) line provides voltage signal to three independent terminals such as terminal 7, terminal 1 and terminal 6 of third connector 10.Voltage letter Number can terminal 7, terminal 1 and terminal 6 through third connector 10 pass to three independent terminals of the first connector 61 as held Son 7, terminal 1 and terminal 6, can have voltage difference between terminal 7 and terminal 1, terminal 6.Three of first connector 61 are independent Voltage signal can be supplied to three independent terminal such as terminals of the second connector 62 by terminal such as terminal 7, terminal 1 and terminal 6 7, terminal 1 and terminal 6.Three independent terminals of the second connector 62 such as terminal 7, terminal 1 and terminal 6 can be by voltage signals Pass to three independent terminals such as terminal 7, terminal 1 and the terminal 6 of the 4th connector 20.Reduction voltage circuit 41 and the 4th connector 20 corresponding terminal such as terminal 1 and terminal 6 connect, and the terminal 7 of the 4th connector 20 is grounded, and two of the 4th connector 20 are solely Voltage signal can be passed to reduction voltage circuit 41 and carry out decompression processing by vertical terminal such as terminal 1 and terminal 6, and reduction voltage circuit 41 can incite somebody to action Voltage after decompression is powered to voltage indicator lamp 42, when actually detected, if voltage indicator lamp 42 does not work, can determine the 4th company It connects device 20 to fail to receive the voltage signal passed over via the first connector 61 and the second connector 62, so can determine that AISG electricity tune equipment power circuit failure, i.e. AISG electricity tune equipment fault can determine the 4th company if voltage indicator lamp 42 is bright The voltage signal passed over via the first connector 61 and the second connector 62 can be received by connecing device 20, so can determine that AISG Electricity adjusts equipment power circuit normal.
The reduction voltage circuit 41 of the present embodiment mainly includes TPSS430 main control chip, capacitor C1, capacitor C2, capacitor C3, inductance The electronic components such as coil L1, zener diode D1, resistance R1, resistance R2 and capacitor E1.Voltage indicator lamp 42 is one luminous two Pole pipe.
In other embodiments, voltage source is also possible to provide voltage to two independent terminals of third connector 10 Signal, correspondingly, the first connector 61, the second connector 62, the 4th connector 20 all have corresponding two piece-root grafting and receive voltage letter Number terminal.
Signal source 30 includes data signal source, and test signal includes data-signal.Signal supervisory instrument 40 includes at data Reason module 43 with communicate indicator light 44.Data signal source can be by 485A line and 485B line to two independences of third connector 10 Terminal such as terminal 3, terminal 5 provide data-signal.Data-signal can terminal 3, terminal 5 through third connector 10 pass to first Two independent terminals of connector 61 such as terminal 3, terminal 5.Two independent terminals such as terminal 3 of first connector 61, end Data-signal can be supplied to two independent terminals such as terminal 3, terminal 5 of the second connector 62 by son 5.Second connector 62 Voltage signal can be passed to two independent terminals of the 4th connector 20 as held by two independent terminals such as terminal 3, terminal 5 Sub 3, terminal 5.Data processing module 43 is connect with the corresponding terminal of the 4th connector 20 such as terminal 3 and terminal 5, the 4th connection Data-signal can be passed to data processing module 43 and handled by two independent terminals such as terminal 3 and terminal 5 of device 20, example Data-signal is such as converted into analog signal, data processing module 43 can data-signal be transmitted through communication indicator light by treated 44, when actually detected, if communication indicator light 44 does not work, it can determine that the 4th connector 20 fails to receive via the first connection The data-signal that device 61 and the second connector 62 pass over so can determine that AISG electricity tune device signal line fault, i.e., AISG electricity tune equipment fault can determine that the 4th connector 20 can be received via the first connection if communication indicator light 44 flashes The data-signal that device 61 and the second connector 62 pass over so can determine that AISG electricity tune device signal route is normal.
The data processing module 43 of the present embodiment mainly uses MAX485ESA chip.Communicating indicator light 44 is one luminous two Pole pipe.
In other embodiments, data signal source is also possible to two or more such as three of third connector 10 solely Vertical terminal provides data-signal, and correspondingly, the first connector 61, the second connector 62, the 4th connector 20 all have correspondence Two or more such as three piece-root graftings receive data-signal terminal.
The signal source 30 of the present embodiment includes voltage source and data signal source simultaneously, and signal supervisory instrument 40 includes drop simultaneously Volt circuit 41 and voltage indicator lamp 42, data processing module 43 and indicator light 44 is communicated, thus by test equipment to AISG electricity It when equipment being adjusted to carry out fault detection, can be detected simultaneously in terms of voltage and signal two, if voltage indicator lamp 42 is bright, communication refers to Show that lamp 44 flashes, then can determine that AISG electricity tune equipment is normal, if voltage indicator lamp 42 is bright, communication indicator light 44 does not flash, or Voltage indicator lamp 42 do not work, communicate the flashing of indicator light 44 or voltage indicator lamp 42 does not work, communicates indicator light 44 and do not flash, this It can determine that AISG electricity tune equipment fault in the case of three kinds.
In other embodiments, signal source 30 can only include voltage source or data signal source, and signal supervisory instrument 40 can Only include reduction voltage circuit 41 and voltage indicator lamp 42 or data processing module 43 with communicate indicator light 44, thus set by test When the standby progress fault detection to AISG electricity tune equipment, can unilaterally it be detected by voltage or signal;Passing through voltage detecting When, it if voltage indicator lamp 42 is bright, can determine that AISG electricity tune equipment is normal, if voltage indicator lamp 42 is bright, can determine that AISG electricity Adjust equipment fault;When passing through signal detection, if communication indicator light 44 flashes, it can determine that AISG electricity tune equipment is normal, if logical Letter indicator light 44 does not flash, then can determine that AISG electricity tune equipment fault.
With reference to Fig. 3, the present invention is based on the AISG electricity tune equipment of the test equipment of Fig. 1 and Fig. 2 to additionally provide a kind of AISG electricity The test method of equipment is adjusted, test method includes the steps that carrying out fault detection to AISG electricity tune equipment by test equipment, should Step includes:
S10, connection between the first connector 61 and third connector 10 is established, i.e. first 8 of the first connector 61 are solely Vertical terminal correspondence is connect with 8 independent terminals of third connector 10.
S11, connection between the second connector 62 and the 4th connector 20 is established, i.e. first 8 of the second connector 62 are solely Vertical terminal correspondence is connect with 8 independent terminals of the 4th connector 20.
S12, test signal is provided to third connector 10 by signal source 30.
S13, it the 4th connector 20 is detected by signal supervisory instrument 40 can receive via the first connector 61 and the The test signal that two connectors 62 pass over determines AISG electricity tune equipment fault if do not received.
In the present embodiment, signal source 30 includes voltage source, and test signal includes voltage signal.Signal supervisory instrument 40 includes Reduction voltage circuit 41 and voltage indicator lamp 42.Voltage source is by GND (electric wire ground terminal) 1 line and VCC IN (power input) line to the Three independent terminals of three connectors 10 such as terminal 7, terminal 1 and terminal 6 provide voltage signal.Voltage signal is connected through third Terminal 7, terminal 1 and the terminal 6 of device 10 pass to three independent terminals such as terminal 7, terminal 1 and the end of the first connector 61 Son 6, can have voltage difference between terminal 7 and terminal 1, terminal 6.Three independent terminals such as terminal 7 of first connector 61, end Voltage signal is supplied to three independent terminals such as terminal 7, terminal 1 and the terminal 6 of the second connector 62 by son 1 and terminal 6.The Voltage signal is passed to the 4th connector 20 by three independent terminals of two connectors 62 such as terminal 7, terminal 1 and terminal 6 Three independent terminals such as terminal 7, terminal 1 and terminal 6.The corresponding terminal of reduction voltage circuit 41 and the 4th connector 20 such as terminal 1 It is connected with terminal 6, the terminal 7 of the 4th connector 20 is grounded, two independent terminals such as terminal 1 of the 4th connector 20 and end Voltage signal is passed to reduction voltage circuit 41 and carries out decompression processing by son 6, and reduction voltage circuit 41 indicates the voltage after decompression to voltage Lamp 42 is powered, if voltage indicator lamp 42 does not work, can determine that the 4th connector 20 fails to receive via 61 He of the first connector The voltage signal that second connector 62 passes over so can determine that AISG electricity tune equipment power circuit failure, i.e. AISG electricity tune Equipment fault can determine that the 4th connector 20 can be received via the first connector 61 and second if voltage indicator lamp 42 is bright The voltage signal that connector 62 passes over so can determine that AISG power circuit is normal.
Signal source 30 includes data signal source, and test signal includes data-signal.Signal supervisory instrument 40 includes at data Reason module 43 with communicate indicator light 44.Data signal source passes through 485A line and 485B line to two separate ends of third connector 10 Son such as terminal 3, terminal 5 provide data-signal.Terminal 3, terminal 5 of the data-signal through third connector 10 pass to the first connection Two independent terminals of device 61 such as terminal 3, terminal 5.Two independent terminals of the first connector 61 such as terminal 3, terminal 5 will Data-signal is supplied to two independent terminals such as terminal 3, terminal 5 of the second connector 62.Two of second connector 62 are solely Voltage signal is passed to two independent terminals such as terminal 3, terminal of the 4th connector 20 by vertical terminal such as terminal 3, terminal 5 5.Data processing module 43 is connect with the corresponding terminal of the 4th connector 20 such as terminal 3 and terminal 5, and two of the 4th connector 20 Data-signal is passed to data processing module 43 and handled by independent terminal such as terminal 3 and terminal 5, data processing module 43 By treated, data-signal is transmitted through communication indicator light 44, if communication indicator light 44 does not work, can determine the 4th connector 20 not The data-signal passed over via the first connector 61 and the second connector 62 can be received, so can determine that AISG electricity tune is set Standby signal line failure, i.e. AISG electricity tune equipment fault can determine that the 4th connector 20 can connect if communication indicator light 44 flashes The data-signal passed over via the first connector 61 and the second connector 62 is received, so can determine that AISG electricity tune equipment is believed Number route is normal.
The signal source 30 of the present embodiment includes voltage source and data signal source simultaneously, and signal supervisory instrument 40 includes drop simultaneously Volt circuit 41 and voltage indicator lamp 42, data processing module 43 and indicator light 44 is communicated, thus by test equipment to AISG electricity It in the step of adjusting equipment to carry out fault detection, including by voltage and two aspect of signal while being detected, if voltage indicator lamp 42 is bright, communication indicator light 44 flashes, then can determine that AISG electricity tune equipment is normal, if voltage indicator lamp 42 is bright, communication indicator light 44 Do not flash perhaps voltage indicator lamp 42 do not work, communicate indicator light 44 flashing or voltage indicator lamp 42 do not work, communicate indicator light 44 do not flash, and can determine that AISG electricity tune equipment fault in the case of these three.
In other embodiments, signal source 30 can only include voltage source or data signal source, and signal supervisory instrument 40 can Only include reduction voltage circuit 41 and voltage indicator lamp 42 or data processing module 43 with communicate indicator light 44, thus set by test When the standby progress fault detection to AISG electricity tune equipment, can unilaterally it be detected by voltage or signal;Passing through voltage detecting When, it if voltage indicator lamp 42 is bright, can determine that AISG electricity tune equipment is normal, if voltage indicator lamp 42 is bright, can determine that AISG electricity Adjust equipment fault;When passing through signal detection, if communication indicator light 44 flashes, it can determine that AISG electricity tune equipment is normal, if logical Letter indicator light 44 does not flash, then can determine that AISG electricity tune equipment fault.
With reference to Fig. 4, a kind of test method of AISG electricity tune equipment provided by the invention, which further includes passing through survey The step of examination equipment tests the performance of AISG electricity tune equipment, the step are to determine the normal Shi Caijin of AISG electricity tune equipment Capable step.The step includes:
S1, test parameter is preset by test equipment, and load match corresponding with each sequence number of AISG electricity tune equipment Set file;Test parameter include software version number, hardware version numbers, 0.1 degree of umber of pulse and the motor angle value of setting at least One of.The Serial No. of AISG electricity tune equipment is more than two.The motor angle value of setting may be one, it is also possible to multiple.
S2, all sequences number that AISG electricity tune equipment is obtained by test equipment, and all sequences number that will acquire are sent To AISG electricity tune equipment to carry out sequence numbers match, if successful match, AISG electricity tune equipment is to test equipment feedback sequence number Successful match order;If matching is unsuccessful, interruption is tested, test does not pass through.AISG electricity tune equipment is obtained by test equipment All sequences number, it is pasting with each sequence number pair on the general shell by scanner manual scanning AISG electricity tune equipment The bar code answered is obtained, inside the sequence number pasted on the shell to guarantee AISG electricity tune equipment and AISG electricity tune equipment On the sequence number of program record is corresponding.
S3, test command is sent to AISG electricity tune equipment by test equipment, test equipment is enable to set from AISG electricity tune Standby place obtains the property parameters of AISG electricity tune equipment, and property parameters include software version number, hardware version numbers, umber of pulse, calibration At least one of state and the motor angle value of setting;
S4, the property parameters that will acquire by test equipment and default test parameter are matched, if successful match, are mentioned Show that test passes through, test terminates.If matching is unsuccessful, test is prompted not pass through, test terminates.
In the step S4, the test report of AISG electricity tune equipment is also automatically generated after prompt test passes through.
With reference to Fig. 5, in the step S3, test command includes sequence number scanning, (address is for the address distribution of sequence number Program address, according to AISG agreement, each sequence number distributes a program address, such as generally addresses since 1), sequence number Link, information inquiry (information is, for example, the information such as the model of AISG electricity tune equipment), software version inquiry, hardware version looks into It askes, configuration file load (binary file that configuration file is a bin format), calibration, the angle of setting motor, inquiry The motor angle value of umber of pulse and setting;
Step S3 is specifically included:
S31, by test equipment to AISG electricity tune equipment successively transmit Sequence Number scanning, sequence number address distribution, sequence The test command of link, the information inquiry, software version inquiry, hardware version inquiry, configuration file load of row number.
AISG electricity tune equipment receive sequence number scanning, the address distribution of sequence number, the link of sequence number, information are looked into It askes, software version is inquired, hardware version is inquired, returns to this equipment to test equipment respectively after the test command of configuration file load All sequences number, all sequences number of this equipment are successively carried out address distribution and to test equipment return sequence number address It is allocated successfully order, all sequences number of this equipment are successively established with communication linkage and is returned to test equipment the link of sequence number Be successfully established order, information that this equipment is returned to test equipment, the software version number for returning to test equipment this equipment, to survey Examination equipment returns to the hardware version numbers of this equipment, all sequences number of this equipment is successively carried out with loading configuration file and to test Equipment returns to configuration file and loads success command.
S32, the test command for sending calibration to AISG electricity tune equipment by test equipment, AISG electricity tune equipment are receiving Calibration operation is carried out after the test command of calibration and returns to calibration success command to test equipment.Calibration operation is primarily to look for The zero point rotated to motor, the mode that motor rotation is usually taken get the zero point of motor rotation.
S33, the test command that the angle of motor is set, AISG electricity tune are sent to AISG electricity tune equipment by test equipment Equipment is configured the angle of motor after receiving the test command of angle of setting motor and originally sets to test equipment return At least one of the angle value of standby setting motor.
S34, the test for inquiring the motor angle value of umber of pulse and setting is sent to AISG electricity tune equipment by test equipment Order, AISG electricity tune equipment are returned in the test command back testing equipment for the motor angle value for receiving inquiry umber of pulse and setting Return at least one of the umber of pulse and the motor angle value of setting of this equipment.
A kind of test method of AISG electricity tune equipment provided by the invention carries out AISG electricity tune equipment by test equipment The step of fault detection, detects AISG using passing through by way of two connectors to AISG electricity tune equipment detect simultaneously Electricity adjusts whether equipment breaks down, and detection efficiency is high;The step tested by performance of the test equipment to AISG electricity tune equipment Suddenly, the automatic progress address distribution of all sequences number, link, information inquiry, software version inquiry, hardware version can be looked into simultaneously The operations such as inquiry, configuration file load, it is relatively existing that address distribution, link, information are carried out manually one by one to all sequence numbers The mode of the operations such as inquiry, software version inquiry, hardware version inquiry, configuration file load, can save the testing time, time saving province Power.
Above embodiments only express the preferred embodiment of the present invention, and the description thereof is more specific and detailed, but can not Therefore limitations on the scope of the patent of the present invention are interpreted as.It should be pointed out that for those of ordinary skill in the art, Without departing from the inventive concept of the premise, various modifications and improvements can be made, such as special to the difference in each embodiment Sign is combined, and these are all within the scope of protection of the present invention.

Claims (10)

1. a kind of test equipment for testing AISG electricity tune equipment, the AISG electricity tune equipment includes the first connector and the second connection Device, the corresponding terminal of first connector are in parallel with the corresponding terminal of second connector, which is characterized in that the test Equipment includes third connector, the 4th connector, signal source and signal supervisory instrument, in which:
The signal source is connect with the third connector, for providing test signal to the third connector;
The third connector can be connect with first connector;
4th connector can be connect with second connector;
The signal supervisory instrument is connect with the 4th connector, and the signal supervisory instrument is used for according to the 4th connector energy It is no to receive the test signal that passes over via first connector and the second connector to detect the AISG electricity Adjust whether equipment breaks down.
2. test equipment according to claim 1, which is characterized in that the signal source includes voltage source, the test letter Number include voltage signal;The signal supervisory instrument includes reduction voltage circuit and voltage indicator lamp, the reduction voltage circuit and described the The corresponding terminal of four connectors connects, for the voltage passed over via first connector and the second connector Signal decompression, and the voltage after decompression is powered to the voltage indicator lamp.
3. test equipment according to claim 2, which is characterized in that the voltage signal is at least supplied to described first and connects Two independent terminals of device are connect, and two independent terminals have voltage difference;Second connector, third connector and the 4th Connector all has at least two independent terminals corresponding with the first connector.
4. test equipment according to claim 1, which is characterized in that the signal source includes data signal source, the survey Trial signal includes data-signal;The signal supervisory instrument includes data processing module and communicate indicator light, the data processing Module is connect with the corresponding terminal of the 4th connector, for transmitting to via first connector and the second connector The data-signal come is handled, and data-signal is transmitted through the communication indicator light by treated.
5. test equipment according to claim 4, which is characterized in that the data-signal is at least supplied to described first and connects Connect two independent terminals of device;Second connector, third connector and the 4th connector all have and the first connector pair At least two independent terminals answered.
6. a kind of test method of AISG electricity tune equipment, the AISG electricity tune equipment includes the first connector and the second connector, The corresponding terminal of first connector is in parallel with the corresponding terminal of second connector, which is characterized in that the test side Method includes the steps that through test equipment, to AISG electricity tune equipment progress fault detection, the test equipment includes that third connects Connect device, the 4th connector, signal source and signal supervisory instrument;
Include: to the step of AISG electricity tune equipment progress fault detection by test equipment
Establish the connection between first connector and third connector;
Establish the connection between second connector and the 4th connector;
Test signal is provided to the third connector by the signal source;
The 4th connector, which can be detected, by signal supervisory instrument receive via first connector and the second connector biography The test signal passed, the AISG electricity tune equipment fault as described in judgement if not receiving.
7. test method according to claim 6, which is characterized in that the signal source includes voltage source, the test letter Number be voltage signal;The signal supervisory instrument includes reduction voltage circuit and voltage indicator lamp, the reduction voltage circuit and the described 4th The corresponding terminal of connector connects, for believing the voltage passed over via first connector and the second connector Number decompression, and by the voltage after decompression to the voltage indicator lamp power supply;If voltage indicator lamp does not work, then the AISG electricity is determined Adjust equipment fault.
8. test method according to claim 6, which is characterized in that the signal source includes data signal source, the survey Trial signal is data-signal;The signal supervisory instrument includes data processing module and communicate indicator light, the data processing mould Block is connect with the corresponding terminal of the 4th connector, for passing over to via first connector and the second connector The data-signal handled, and will treated that data-signal is transmitted through the communication indicator light;Such as communicate indicator light not Flashing, then determine the AISG electricity tune equipment fault.
9. test method according to claim 6, which is characterized in that the test method further includes by test equipment pair The step of performance of the AISG electricity tune equipment is tested, which includes:
S1, test parameter is preset by test equipment, and load configuration text corresponding with each sequence number of AISG electricity tune equipment Part;The test parameter include software version number, hardware version numbers, 0.1 degree of umber of pulse and the motor angle value of setting at least One of;
S2, all sequences number that AISG electricity tune equipment is obtained by test equipment, and all sequences number that will acquire are sent to AISG electricity tune equipment is to carry out sequence numbers match, if successful match, AISG electricity tune equipment is to test equipment feedback sequence number With success command;
S3, test command is sent to AISG electricity tune equipment by test equipment, enables test equipment from AISG electricity tune equipment The property parameters of AISG electricity tune equipment are obtained, the property parameters include software version number, hardware version numbers, umber of pulse, calibration At least one of state and the motor angle value of setting;
S4, the property parameters that will acquire by test equipment and default test parameter are matched, if successful match, prompt to survey It pinged, test terminates.
10. test method according to claim 9, which is characterized in that in the step S3, the test command includes sequence Row number scanning, the link of sequence number, information inquiry, software version inquiry, hardware version inquiry, is matched at the address distribution of sequence number Set file load, calibration, the angle of setting motor, the motor angle value of inquiry umber of pulse and setting;
Step S3 is specifically included:
S31, by test equipment to AISG electricity tune equipment successively transmit Sequence Number scanning, sequence number address distribution, sequence number Link, information inquiry, software version inquiry, hardware version inquiry, configuration file load test command;
AISG electricity tune equipment receive sequence number scanning, the address distribution of sequence number, the link of sequence number, information inquiry, it is soft Return to the institute of this equipment after the test command that part version querying, hardware version inquiry, configuration file load to test equipment respectively There is sequence number, all sequences number of this equipment are successively carried out with address distribution and is distributed to the address that test equipment returns to sequence number Success command is successively established communication linkage to all sequences number of this equipment and is established to the link that test equipment returns to sequence number Success command, the software version number for returning to test equipment this equipment, is set to test the information that this equipment is returned to test equipment The standby hardware version numbers for returning to this equipment successively carry out loading configuration file to all sequences number of this equipment and to test equipment It returns to configuration file and loads success command;
S32, the test command for sending calibration to AISG electricity tune equipment by test equipment, AISG electricity tune equipment are receiving calibration Test command after carry out calibration operation and to test equipment return calibration success command;
S33, the test command that the angle of motor is set is sent to AISG electricity tune equipment by test equipment, AISG electricity tune equipment exists The angle of motor is configured after receiving the test command of the angle of setting motor and returns to the setting of this equipment to test equipment At least one of angle value of motor;
S34, the test command for inquiring the motor angle value of umber of pulse and setting is sent to AISG electricity tune equipment by test equipment, AISG electricity tune equipment returns to this in the test command back testing equipment for receiving the motor angle value of inquiry umber of pulse and setting At least one of umber of pulse and the motor angle value of setting of equipment.
CN201910621809.9A 2019-07-10 2019-07-10 Test equipment and test method for testing AISG (automatic identification System) electric tilt equipment Active CN110286285B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910621809.9A CN110286285B (en) 2019-07-10 2019-07-10 Test equipment and test method for testing AISG (automatic identification System) electric tilt equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910621809.9A CN110286285B (en) 2019-07-10 2019-07-10 Test equipment and test method for testing AISG (automatic identification System) electric tilt equipment

Publications (2)

Publication Number Publication Date
CN110286285A true CN110286285A (en) 2019-09-27
CN110286285B CN110286285B (en) 2022-02-01

Family

ID=68021300

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910621809.9A Active CN110286285B (en) 2019-07-10 2019-07-10 Test equipment and test method for testing AISG (automatic identification System) electric tilt equipment

Country Status (1)

Country Link
CN (1) CN110286285B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111856160A (en) * 2020-07-30 2020-10-30 苏州韦博通信技术有限公司 Test system of electric tilt antenna equipment

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837840A (en) * 2006-03-06 2006-09-27 中控科技集团有限公司 Cable tester
CN101674591A (en) * 2009-09-29 2010-03-17 中兴通讯股份有限公司 Electrical tilt antenna system and scanning method of electrical tilt antenna
CN101937037A (en) * 2009-07-01 2011-01-05 哈尔滨建成集团有限公司 Device for automatically testing performance of cable bunch
CN102143516A (en) * 2011-03-31 2011-08-03 华为技术有限公司 Detection method, device and system
CN202795335U (en) * 2011-11-18 2013-03-13 华为技术有限公司 Antenna line device, controller and systems
US20140265592A1 (en) * 2013-03-13 2014-09-18 Schumacher Electric Corporation Interconnect device for detecting whether a vehicle on-board diagnostics (obd) data port includes circuitry which prevents back feeding of power through the obd data port
CN104330685A (en) * 2014-11-06 2015-02-04 湖南南车时代电动汽车股份有限公司 Connection check-up method and connection check-up device
US9069026B1 (en) * 2009-11-12 2015-06-30 Eric G. Rutkowsky Diagnostic tool for trailer lights
CN104767631A (en) * 2014-01-07 2015-07-08 中兴通讯股份有限公司 Method and device for automatically carrying out batch tune measurement on AISG (Antenna Interface Standards Group) tunable antennas
CN204731364U (en) * 2015-06-24 2015-10-28 株洲南车时代电气股份有限公司 A kind of portable polycore cable distribution tester
CN204903696U (en) * 2015-07-27 2015-12-23 南车株洲电力机车研究所有限公司 Wind generating set cable detection device
CN205882245U (en) * 2016-06-16 2017-01-11 深圳市西多利精密实业有限公司 Cable subassembly of control line is transferred to electricity
CN205958687U (en) * 2016-03-07 2017-02-15 通号工程局集团有限公司北京分公司 Conduction testing device of circular connector and cable
CN108650033A (en) * 2018-04-19 2018-10-12 摩比天线技术(深圳)有限公司 Test method, test terminal, test system and the storage medium of radio-frequency devices
CN109640352A (en) * 2019-01-16 2019-04-16 深圳国人通信股份有限公司 A kind of device for the wireless commissioning of electrical tilt antenna, system and method

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837840A (en) * 2006-03-06 2006-09-27 中控科技集团有限公司 Cable tester
CN101937037A (en) * 2009-07-01 2011-01-05 哈尔滨建成集团有限公司 Device for automatically testing performance of cable bunch
CN101674591A (en) * 2009-09-29 2010-03-17 中兴通讯股份有限公司 Electrical tilt antenna system and scanning method of electrical tilt antenna
US9069026B1 (en) * 2009-11-12 2015-06-30 Eric G. Rutkowsky Diagnostic tool for trailer lights
CN102143516A (en) * 2011-03-31 2011-08-03 华为技术有限公司 Detection method, device and system
CN202795335U (en) * 2011-11-18 2013-03-13 华为技术有限公司 Antenna line device, controller and systems
US20140265592A1 (en) * 2013-03-13 2014-09-18 Schumacher Electric Corporation Interconnect device for detecting whether a vehicle on-board diagnostics (obd) data port includes circuitry which prevents back feeding of power through the obd data port
CN104767631A (en) * 2014-01-07 2015-07-08 中兴通讯股份有限公司 Method and device for automatically carrying out batch tune measurement on AISG (Antenna Interface Standards Group) tunable antennas
CN104330685A (en) * 2014-11-06 2015-02-04 湖南南车时代电动汽车股份有限公司 Connection check-up method and connection check-up device
CN204731364U (en) * 2015-06-24 2015-10-28 株洲南车时代电气股份有限公司 A kind of portable polycore cable distribution tester
CN204903696U (en) * 2015-07-27 2015-12-23 南车株洲电力机车研究所有限公司 Wind generating set cable detection device
CN205958687U (en) * 2016-03-07 2017-02-15 通号工程局集团有限公司北京分公司 Conduction testing device of circular connector and cable
CN205882245U (en) * 2016-06-16 2017-01-11 深圳市西多利精密实业有限公司 Cable subassembly of control line is transferred to electricity
CN108650033A (en) * 2018-04-19 2018-10-12 摩比天线技术(深圳)有限公司 Test method, test terminal, test system and the storage medium of radio-frequency devices
CN109640352A (en) * 2019-01-16 2019-04-16 深圳国人通信股份有限公司 A kind of device for the wireless commissioning of electrical tilt antenna, system and method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
许其峰: "新型AISG连接器的设计", 《机电元件》 *
韦炳佐: "分布式多芯电缆测试仪研制", 《中国优秀硕士学位论文全文数据库信息科技辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111856160A (en) * 2020-07-30 2020-10-30 苏州韦博通信技术有限公司 Test system of electric tilt antenna equipment
CN111856160B (en) * 2020-07-30 2022-11-22 苏州韦博通信技术有限公司 Test system of electric tilt antenna equipment

Also Published As

Publication number Publication date
CN110286285B (en) 2022-02-01

Similar Documents

Publication Publication Date Title
CN100369410C (en) Method and apparatus for supplying power to external device via Ethernet
CN2938129Y (en) Tin interconnection detection circuit, open-circuit detection circuit and welding quiality detection circuit
CN101769976A (en) Connector detection system
EP1402684A2 (en) Network documentation system with electronic modules
US6671222B2 (en) Apparatus and method for distributed control of seismic data acquisition
CN104113422A (en) Communication apparatus
CN103399251A (en) USB (Universal Serial Bus) communication line detection device
CN110286285A (en) A kind of test equipment and test method for testing AISG electricity tune equipment
CN102751602A (en) E1 cable connector, cable type detection circuit board and method
US6466885B2 (en) Line tester
CN111965563A (en) Flat cable detection device
CN109510662B (en) Receiving test system and method of optical module, upper computer and light source board
CN101502087A (en) Office ID remote with oscillating circuit
CN102141592B (en) Cable detection method and system
CN113514757A (en) Test equipment
CN116559629A (en) Chip testing method, device, system and readable storage medium
KR20040016236A (en) System for testing multi-lan cable and method for testing multi-lan cable using the same
WO2006015350A2 (en) Cable adapter port module
CN100512062C (en) Method for detecting chain circuit cross misconnection
CN213715749U (en) Integrated analyzer for transformer area
CN215447762U (en) Detection circuit for improving identification of installation position of feeder and chip mounter of detection circuit
CN201397370Y (en) A/V detecting wire
US11586570B2 (en) Dual mode carriage system translation
GB2226477A (en) Data transmission with erroneous data distribution detection
CN220611404U (en) Chip test system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230814

Address after: 518057 room 1403, building a, Guoren building, No.5, kejizhong Third Road, Gaoxin garden, Maling community, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: Shenzhen Guoren Wireless Communication Co.,Ltd.

Address before: 518000 15F, building a, Guoren building, kejizhong Third Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: SHENZHEN GRENTECH Corp.,Ltd.

TR01 Transfer of patent right