CN110130660A - A kind of assembled architecture execution management method therefor and system based on hologram - Google Patents
A kind of assembled architecture execution management method therefor and system based on hologram Download PDFInfo
- Publication number
- CN110130660A CN110130660A CN201910313659.5A CN201910313659A CN110130660A CN 110130660 A CN110130660 A CN 110130660A CN 201910313659 A CN201910313659 A CN 201910313659A CN 110130660 A CN110130660 A CN 110130660A
- Authority
- CN
- China
- Prior art keywords
- assembled architecture
- hologram
- target
- prefabricated components
- mathematical model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/18—Adjusting tools; Templates
- E04G21/1841—Means for positioning building parts or elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of assembled architecture execution management method therefor and system based on hologram, this method comprises: establishing the mathematical model of target assembled architecture;The mathematical model of target assembled architecture is converted to the hologram signal of target assembled architecture;The hologram of target assembled architecture is projected in the construction site of assembled architecture according to the hologram signal of target assembled architecture, auxiliary construction worker carries out prefabricated components assembly, so, by the hologram for projecting target assembled architecture in the construction site of assembled architecture, it is referred to construction worker one, auxiliary construction worker carries out prefabricated components positioning in the assembling process of assembled architecture, it installs, setting-out, reduce rigging error, to avoid the later period to the correction work amount of prefabricated components, with the working time of less construction worker and labor intensity, improve the benefit of assembled architecture enterprise.
Description
Technical field
The present invention relates to line holographic projections technical fields more particularly to a kind of assembled architecture based on hologram to construct and manage
Manage method and system.
Background technique
Line holographic projections technology belongs to one kind of 3D technology, refers to that simultaneously reconstructed object is true using interference and diffraction principle record
The technology of 3-D image, hologram technology are to show the technology of 3-D image using interference and diffraction principle, reproduction it is complete
Retire into private life as being further processed, removes digital interference, obtain clearly image.
On the other hand, assembled architecture refers to based on the prefabricated components of use the factorial production, by site-assembled
The structure class building construction of mode design-build is assembled up prefabricated components using various reliable connection types.However, dress
With formula building during prefabricated components, prefabricated components assembly majority of case is that manual operation is assembled after worker sees drawing, is held
Easily there is rigging error, and then increases working time and the labor intensity of construction worker.
Summary of the invention
Technical problems based on background technology, the invention proposes a kind of assembled architectures based on hologram to apply
Work management method and system;
A kind of assembled architecture execution management method therefor based on hologram proposed by the present invention, comprising:
Establish the mathematical model of target assembled architecture;
The mathematical model of target assembled architecture is converted to the hologram signal of target assembled architecture;
Target assembled is projected in the construction site of assembled architecture according to the hologram signal of target assembled architecture
The hologram of building, auxiliary construction worker carry out prefabricated components assembly.
Preferably, the auxiliary construction worker carries out prefabricated components assembly, specifically includes: auxiliary construction worker carries out prefabricated
Component positions, installs, setting-out.
A kind of assembled architecture construction management system based on hologram, comprising:
Mathematical model constructs module, for establishing the mathematical model of target assembled architecture;
Signal conversion module, for the mathematical model of target assembled architecture to be converted to the holography of target assembled architecture
Video signal;
Projection module, for being thrown according to the hologram signal of target assembled architecture in the construction site of assembled architecture
The hologram of target assembled architecture is penetrated, auxiliary construction worker carries out prefabricated components assembly.
Preferably, the projection module, is specifically used for: auxiliary construction worker carries out prefabricated components positioning, installs, setting-out.
The present invention initially sets up the mathematical model of target assembled architecture, and the mathematical model of target assembled architecture is turned
It is changed to the hologram signal of target assembled architecture, then according to the hologram signal of target assembled architecture in assembled
The hologram of the construction site projection target assembled architecture of building, auxiliary construction worker carry out prefabricated components assembly, in this way,
It is auxiliary to construction worker one reference by projecting the hologram of target assembled architecture in the construction site of assembled architecture
It helps construction worker to carry out prefabricated components positioning in the assembling process of assembled architecture, install, setting-out, reduces rigging error, from
And the later period is avoided to the correction work amount of prefabricated components, with the working time of less construction worker and labor intensity, improve assembly
The benefit of formula building enterprise.
Detailed description of the invention
Fig. 1 is a kind of process signal of assembled architecture execution management method therefor based on hologram proposed by the present invention
Figure;
Fig. 2 is a kind of module signal of assembled architecture construction management system based on hologram proposed by the present invention
Figure.
Specific embodiment
Referring to Fig.1, a kind of assembled architecture execution management method therefor based on hologram proposed by the present invention, comprising:
Establish the mathematical model of target assembled architecture.
The mathematical model of target assembled architecture is converted to the hologram signal of target assembled architecture.
Target assembled is projected in the construction site of assembled architecture according to the hologram signal of target assembled architecture
The hologram of building, auxiliary construction worker carry out prefabricated components assembly.
In this step, auxiliary construction worker carries out prefabricated components assembly, specifically includes: auxiliary construction worker carries out prefabricated structure
Part positions, installs, setting-out.
In concrete scheme, the mathematical model for needing the building assembled is constructed first, then translates into hologram
Signal, and hologram is projected on the construction site for needing the building assembled, hologram is in the construction process as fixed
Position installs, the foundation of setting-out, and auxiliary construction worker assembles, and can simultaneously serve as the foundation of prefabricated components production, and auxiliary is applied
The production of work worker progress prefabricated components.
Referring to Fig. 2, a kind of assembled architecture construction management system based on hologram proposed by the present invention, comprising:
Mathematical model constructs module, for establishing the mathematical model of target assembled architecture;
Signal conversion module, for the mathematical model of target assembled architecture to be converted to the holography of target assembled architecture
Video signal;
Projection module, for being thrown according to the hologram signal of target assembled architecture in the construction site of assembled architecture
The hologram of target assembled architecture is penetrated, auxiliary construction worker carries out prefabricated components assembly.
Projection module is specifically used for: auxiliary construction worker carries out prefabricated components positioning, installs, setting-out.
In concrete scheme, the mathematical model for needing the building assembled is constructed first, then translates into hologram
Signal, and hologram is projected on the construction site for needing the building assembled, hologram is in the construction process as fixed
Position installs, the foundation of setting-out, and auxiliary construction worker assembles, and can simultaneously serve as the foundation of prefabricated components production, and auxiliary is applied
The production of work worker progress prefabricated components.
Present embodiment initially sets up the mathematical model of target assembled architecture, and by the digital mould of target assembled architecture
Type is converted to the hologram signal of target assembled architecture, is then being filled according to the hologram signal of target assembled architecture
The hologram of construction site projection target assembled architecture with formula building, auxiliary construction worker carry out prefabricated components assembly,
In this way, by the hologram for projecting target assembled architecture in the construction site of assembled architecture, to construction worker one ginseng
It examines, auxiliary construction worker carries out prefabricated components positioning in the assembling process of assembled architecture, installs, setting-out, reduces assembly and misses
Difference, so that the later period be avoided to improve the correction work amount of prefabricated components with the working time of less construction worker and labor intensity
The benefit of assembled architecture enterprise.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto,
Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its
Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.
Claims (4)
1. a kind of assembled architecture execution management method therefor based on hologram characterized by comprising
Establish the mathematical model of target assembled architecture;
The mathematical model of target assembled architecture is converted to the hologram signal of target assembled architecture;
Target assembled architecture is projected in the construction site of assembled architecture according to the hologram signal of target assembled architecture
Hologram, auxiliary construction worker carry out prefabricated components assembly.
2. the assembled architecture execution management method therefor according to claim 1 based on hologram, which is characterized in that described
Auxiliary construction worker carries out prefabricated components assembly, specifically includes: auxiliary construction worker carries out prefabricated components positioning, installs, setting-out.
3. a kind of assembled architecture construction management system based on hologram characterized by comprising
Mathematical model constructs module, for establishing the mathematical model of target assembled architecture;
Signal conversion module, for the mathematical model of target assembled architecture to be converted to the hologram of target assembled architecture
Signal;
Projection module, for projecting mesh in the construction site of assembled architecture according to the hologram signal of target assembled architecture
The hologram of assembled architecture is marked, auxiliary construction worker carries out prefabricated components assembly.
4. the assembled architecture construction management system according to claim 3 based on hologram, which is characterized in that described
Projection module is specifically used for: auxiliary construction worker carries out prefabricated components positioning, installs, setting-out.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910313659.5A CN110130660A (en) | 2019-04-18 | 2019-04-18 | A kind of assembled architecture execution management method therefor and system based on hologram |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910313659.5A CN110130660A (en) | 2019-04-18 | 2019-04-18 | A kind of assembled architecture execution management method therefor and system based on hologram |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110130660A true CN110130660A (en) | 2019-08-16 |
Family
ID=67570198
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910313659.5A Pending CN110130660A (en) | 2019-04-18 | 2019-04-18 | A kind of assembled architecture execution management method therefor and system based on hologram |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110130660A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111428082A (en) * | 2020-03-10 | 2020-07-17 | 广东技术师范大学天河学院 | Building construction video guidance method and system based on holographic image technology |
CN111951398A (en) * | 2020-07-27 | 2020-11-17 | 中建三局第二建设工程有限责任公司 | Intelligent lofting construction method based on unmanned aerial vehicle oblique image technology |
CN112097070A (en) * | 2020-07-22 | 2020-12-18 | 南京工业大学 | Auxiliary device and method for producing prefabricated parts of assembly type building with movable portal frame |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102013007070A1 (en) * | 2013-04-23 | 2014-10-23 | Gerhard Führer | Holographically assisted creation of objects |
CN105446069A (en) * | 2016-01-07 | 2016-03-30 | 江苏建筑职业技术学院 | BIM-based holographic imaging full-decoration simulation display method and display system |
CN107863049A (en) * | 2017-11-14 | 2018-03-30 | 湖北聚注通用技术研究有限公司 | A kind of finishing outpost display system based on line holographic projections technology |
CN108683848A (en) * | 2018-05-15 | 2018-10-19 | 中国十七冶集团有限公司 | A kind of 720 ° of panorama construction methods based on BIM+MR |
EP3457253A1 (en) * | 2017-09-15 | 2019-03-20 | Trimble Inc. | Collaboration methods to improve use of 3d models in mixed reality environments |
-
2019
- 2019-04-18 CN CN201910313659.5A patent/CN110130660A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102013007070A1 (en) * | 2013-04-23 | 2014-10-23 | Gerhard Führer | Holographically assisted creation of objects |
CN105446069A (en) * | 2016-01-07 | 2016-03-30 | 江苏建筑职业技术学院 | BIM-based holographic imaging full-decoration simulation display method and display system |
EP3457253A1 (en) * | 2017-09-15 | 2019-03-20 | Trimble Inc. | Collaboration methods to improve use of 3d models in mixed reality environments |
CN107863049A (en) * | 2017-11-14 | 2018-03-30 | 湖北聚注通用技术研究有限公司 | A kind of finishing outpost display system based on line holographic projections technology |
CN108683848A (en) * | 2018-05-15 | 2018-10-19 | 中国十七冶集团有限公司 | A kind of 720 ° of panorama construction methods based on BIM+MR |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111428082A (en) * | 2020-03-10 | 2020-07-17 | 广东技术师范大学天河学院 | Building construction video guidance method and system based on holographic image technology |
CN112097070A (en) * | 2020-07-22 | 2020-12-18 | 南京工业大学 | Auxiliary device and method for producing prefabricated parts of assembly type building with movable portal frame |
CN111951398A (en) * | 2020-07-27 | 2020-11-17 | 中建三局第二建设工程有限责任公司 | Intelligent lofting construction method based on unmanned aerial vehicle oblique image technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110130660A (en) | A kind of assembled architecture execution management method therefor and system based on hologram | |
CN104102765A (en) | BIM (Building Information Modeling)-based curtain wall parametrization design method | |
CN111119480A (en) | Assembly type building panoramic construction management method based on BIM + MR technology | |
CN101799754A (en) | Method and system for developing web application | |
CN114417466A (en) | BIM-based electromechanical system assembling and managing method, system, storage medium and equipment | |
WO2022222432A1 (en) | Bim-based dynamic and intelligent building lifecycle management system and method | |
US20080082214A1 (en) | Method for animating a robot | |
CN104281753A (en) | Two-dimension and three-dimension integration based transmission line corridor parameterized building method and system | |
CN111625971A (en) | Assembling method for prefabricated components of assembled concrete bridge | |
CN107092764A (en) | A kind of concrete assembled construction method based on BIM | |
EP1530128A3 (en) | Method and system for installing software in a network | |
CN103745067A (en) | Power generator stator end parameterization automatic modeling system and method | |
CN116341069A (en) | BIM-based construction method for optimizing efficient collection, water storage and water storage of rainwater in artificial lake | |
CN106874014B (en) | Three-layer code generation method based on model and framework | |
CN116186821A (en) | AI (automatic construction) automatic construction method based on BIM (building information modeling) technology | |
Piaia et al. | Plug-and-Play and innovative process technologies (Mapping/Modelling/Making/Monitoring) in deep renovation interventions | |
CN109284935A (en) | A kind of task processing system based on micro- assistance the superior and the subordinate office group | |
CN115526988A (en) | Special-shaped pipeline template manufacturing and installing method based on BIM model | |
Xu et al. | Study on construction planning for bridge structure based on BIM technology | |
CN113742824A (en) | Lightweight steel structure smart collaborative design cloud platform and operation method thereof | |
CN111460671A (en) | Construction management and control method combining BIM simulation and environmental conditions | |
Bocciarelli et al. | A Methodological Template for Model Driven Systems Engineering. | |
CN117034409A (en) | Ancient tower construction method based on BIM+three-dimensional laser scanning technology | |
CN204754442U (en) | Precast prestressed enclosure subassembly | |
CN115081086A (en) | Optimization method of independent support system of casting belt based on BIM technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190816 |
|
RJ01 | Rejection of invention patent application after publication |