CN109740944A
CN109740944A CN201910011568.6A CN201910011568A CN109740944A CN 109740944 A CN109740944 A CN 109740944A CN 201910011568 A CN201910011568 A CN 201910011568A CN 109740944 A CN109740944 A CN 109740944A
Authority
CN
China
Prior art keywords
coal
bucket wheel
wheel machine
data
location data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910011568.6A
Other languages
Chinese (zh)
Inventor
陈磊
许崇翔
刘强
张志�
张月宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuyang China Resources Power Co Ltd
Original Assignee
Fuyang China Resources Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuyang China Resources Power Co Ltd filed Critical Fuyang China Resources Power Co Ltd
Priority to CN201910011568.6A priority Critical patent/CN109740944A/en
Publication of CN109740944A publication Critical patent/CN109740944A/en
Pending legal-status Critical Current

Links

Abstract

Data managing method and data administrator provided in an embodiment of the present invention, are related to technical field of data administration.The data managing method is applied to electronic equipment, electronic equipment communication connection has track scale, overturning robot scaler and bucket wheel machine, this method comprises: type, weight and the quality of the coal by track scale acquisition current transportation to coal yard, and the license number for transporting the train of the coal is obtained by the overturning robot scaler, and establish the corresponding relationship of the type of the license number and the coal, weight and quality;The location data of the bucket wheel machine of coal piling operation is carried out by being set to the bucket wheel machine and with the positioning device acquisition of electronic equipment communication connection;Coal yard, which is generated, according to the location data of the corresponding relationship and the bucket wheel machine for carrying out coal piling operation stacks data.By the above method, the accuracy of coal data management can be improved.

Description

Data managing method and data administrator
Technical field
The present invention relates to technical field of data administration, fill in particular to a kind of data managing method and data management It sets.
Background technique
The raw materials for production of large-size thermal power plant are coal, it is however generally that, thermal power plant is to meet daily production needs, in factory Large-scale coal bedding plant (hereinafter referred to as coal yard) can be established inside area, in general coal yard can store meets power plant and send out at full capacity 15 days coal dosages of electricity.The stacking for depositing coal for coal yard is managed by special personnel.The coal piling operation of coal yard is adopted at present With large-scale hanging arm type bucket wheel stacker-reclaimer, assignment instructions are issued by operator of the program-controlled room of defeated coal to bucket-wheel stacker reclaimer, Material extracting operation is carried out to the coal of specific region or the coal that comes of coal yard buying is carried out that region heap is specified to unload.But through inventing People is the study found that in the prior art, this series of operation process, predominantly artificial enrollment mode, by operating personnel according to What the stored counts of weighing belt, program-controlled room personnel specified in the job area of stacker-reclaimer, operation process carrys out the statistics such as coal kind Relevant information, to there is a problem that the accuracy of coal data management is not high.
Summary of the invention
In view of this, the purpose of the present invention is to provide a kind of data managing method and data administrator, it is existing to improve There is the problem of technology.
To achieve the above object, the embodiment of the present invention adopts the following technical scheme that
A kind of data managing method is applied to electronic equipment, and electronic equipment communication connection has track scale, overturn automatic meter Counting apparatus and bucket wheel machine, this method comprises:
It is turned over by type, weight and the quality of the coal of track scale acquisition current transportation to coal yard, and by described Vehicle robot scaler obtains the license number for transporting the train of the coal, and establishes the type of the license number and the coal, weight And the corresponding relationship of quality;
Coal piling behaviour is carried out by being set to the bucket wheel machine and obtaining with the positioning device of electronic equipment communication connection The location data of the bucket wheel machine of work;
Coal yard, which is generated, according to the location data of the corresponding relationship and the bucket wheel machine for carrying out coal piling operation stacks data.
It is described by being set to the bucket wheel machine and leading to the electronic equipment in the embodiment of the present invention preferably selects Believe that the step of positioning device of connection obtains the location data for carrying out the bucket wheel machine of coal piling operation includes:
The operating state data of all bucket wheel machines is obtained, to obtain carrying out the number of the bucket wheel machine of coal piling operation;
Obtain the corresponding bucket wheel machine location data of number for carrying out coal piling operation bucket wheel machine.
In the embodiment of the present invention preferably selects, the method also includes:
By being set to the bucket wheel machine and with the positioning device acquisition of electronic equipment communication connection carrying out that coal is taken to grasp The location data of the bucket wheel machine of work;
New coal yard is generated according to the location data of the corresponding relationship and the bucket wheel machine for carrying out that coal is taken to operate to stack Data.
It is described by being set to the bucket wheel machine and leading to the electronic equipment in the embodiment of the present invention preferably selects Believe that the step of positioning device of connection obtains the location data for the bucket wheel machine for take coal to operate includes:
The operating state data of all bucket wheel machines is obtained, to obtain the number for the bucket wheel machine for take coal to operate;
Obtain the corresponding bucket wheel machine location data of number for take coal operation bucket wheel machine.
In the embodiment of the present invention preferably selects, the step of the operating state data for obtaining all bucket wheel machines, tool Body are as follows:
Work by being set to the bucket wheel machine and with the detection device acquisition bucket wheel machine of electronic equipment communication connection Make status data, to judge whether the bucket wheel machine carries out that coal is taken to operate according to the operating state data.
The embodiment of the invention also provides a kind of data administrator, which includes:
Corresponding relation building module, for by track scale obtain current transportation to the type of coal of coal yard, weight and Quality, and the license number for transporting the train of the coal is obtained by overturning robot scaler, and establish the license number and the coal The corresponding relationship of the type of charcoal, weight and quality;
Coal piling location data obtains module, for by being set to bucket wheel machine and filling with the positioning of electronic equipment communication connection Set the location data for obtaining the bucket wheel machine for carrying out coal piling operation;
Coal yard stacks data generation module, for according to the corresponding relationship and the bucket wheel machine for carrying out coal piling operation Location data generates coal yard and stacks data.
In the embodiment of the present invention preferably selects, the coal piling location data obtains module and includes:
First operating state data acquisition submodule, for obtaining the operating state data of all bucket wheel machines, with obtain into The number of the bucket wheel machine of row coal piling operation;
Coal piling location data acquisition submodule, the corresponding bucket wheel machine of number for obtaining progress coal piling operation bucket wheel machine are fixed Position data.
In the embodiment of the present invention preferably selects, described device further include:
Coal location data is taken to obtain module, for by being set to the bucket wheel machine and communicating to connect with the electronic equipment Positioning device obtain the location data of the bucket wheel machine for take coal to operate;
Coal yard stacks data update module, for according to the corresponding relationship and the bucket wheel machine for take coal to operate Location data generates new coal yard and stacks data.
In the embodiment of the present invention preferably selects, it is described take coal location data obtain module include:
Second operating state data acquisition submodule, for obtaining the operating state data of all bucket wheel machines, with obtain into The number for the bucket wheel machine that row takes coal to operate;
Coal location data acquisition submodule is taken, take the corresponding bucket wheel machine of number of coal operation bucket wheel machine fixed for obtaining Position data.
In the embodiment of the present invention preferably selects, the second operating state data acquisition submodule is specifically used for:
Work by being set to the bucket wheel machine and with the detection device acquisition bucket wheel machine of electronic equipment communication connection Make status data, to judge whether the bucket wheel machine carries out that coal is taken to operate according to the operating state data.
Data managing method and data administrator provided in an embodiment of the present invention, can establish current transportation to coal yard Type, weight and the quality of coal and transport the coal train license number corresponding relationship, and according to the corresponding relationship and The location data for carrying out the bucket wheel machine of coal piling operation generates coal yard and stacks data, to improve the accuracy of coal data management.
To enable the above objects, features and advantages of the present invention to be clearer and more comprehensible, preferred embodiment is cited below particularly, and cooperate Appended attached drawing, is described in detail below.
Detailed description of the invention
Fig. 1 is the structural block diagram of electronic equipment provided in an embodiment of the present invention.
Fig. 2 is the flow diagram of data managing method provided in an embodiment of the present invention.
Fig. 3 is the flow diagram of the step S120 in Fig. 2.
Fig. 4 is another flow diagram of data managing method provided in an embodiment of the present invention.
Fig. 5 is the flow diagram of the step S140 in Fig. 5.
Fig. 6 is the structural block diagram of data administrator provided in an embodiment of the present invention.
Fig. 7 is the structural block diagram that coal piling location data provided in an embodiment of the present invention obtains module.
Fig. 8 is another structural block diagram of data administrator provided in an embodiment of the present invention.
Fig. 9 is the structural block diagram provided in an embodiment of the present invention for taking coal location data to obtain module.
Icon: 10- electronic equipment;12- memory;14- processor;100- data administrator;110- corresponding relationship is built Formwork erection block;120- coal piling location data obtains module;121- the first operating state data acquisition submodule;122- coal piling positions number According to acquisition submodule;130- coal yard stacks data generation module;140- takes coal location data to obtain module;The work shape of 141- second State data acquisition submodule;142- takes coal location data acquisition submodule;150- coal yard stacks data update module.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment only It is a part of the embodiments of the present invention, instead of all the embodiments.The present invention being usually described and illustrated herein in the accompanying drawings The component of embodiment can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiment of the present invention provided in the accompanying drawings is not intended to limit below claimed The scope of the present invention, but be merely representative of selected embodiment of the invention.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without creative efforts belongs to the model that the present invention protects It encloses.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need that it is further defined and explained in subsequent attached drawing.In description of the invention In, term " first ", " second " etc. are only used for distinguishing description, and should not be understood as only or imply relative importance.
In the description of the present invention unless specifically defined or limited otherwise, term " setting ", " connected ", " connection " are answered It is interpreted broadly, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can be mechanical connect It connects, is also possible to be electrically connected;It can be directly connected, can also can be in two elements indirectly connected through an intermediary The connection in portion.For the ordinary skill in the art, the tool of above-mentioned term in the present invention can be understood with concrete condition Body meaning.
As shown in Figure 1, the embodiment of the invention provides a kind of electronic equipment 10, including memory 12, processor 14 and number According to managing device 100, wherein the data administrator 100 includes that one or more is stored in the memory 12 and by institute State the software function module of the execution of processor 14.
Optionally, the concrete form of the electronic equipment 10 is unrestricted, can be configured according to practical application.At this In embodiment, a kind of feasible example is provided, the electronic equipment 10 can be computer.
Wherein, it is directly or indirectly electrically connected between the memory 12 and processor 14, to realize the transmission of data Or interaction.It is electrically connected for example, these elements can be realized between each other by one or more communication bus or signal wire.It is described Data administrator 100 includes that at least one can be stored in the memory 12 in the form of software or firmware (firmware) Software function module.The processor 14 is for executing the executable computer program stored in the memory 12, example Such as, software function module and computer program etc. included by the data administrator 100, to realize data managing method.
Wherein, the memory 12 may be, but not limited to, random access memory (Random Access Memory, RAM), read-only memory (Read Only Memory, ROM), programmable read only memory (Programmable Read-Only Memory, PROM), erasable read-only memory (Erasable Programmable Read-Only Memory, EPROM), Electricallyerasable ROM (EEROM) (Electric Erasable Programmable Read-Only Memory, EEPROM) etc.. Wherein, memory 12 is for storing program, and the processor 14 executes described program after receiving and executing instruction.
The processor 14 may be a kind of IC chip, the processing capacity with signal.Above-mentioned processor 14 It can be general processor, including central processing unit (Central Processing Unit, CPU), network processing unit (Network Processor, NP) etc.;It can also be digital signal processor (DSP), specific integrated circuit (ASIC), scene Programmable gate array (FPGA) either other programmable logic device, discrete gate or transistor logic, discrete hardware group Part.
It is appreciated that structure shown in FIG. 1 is only to illustrate, the electronic equipment 10 may also include more than shown in Fig. 1 Perhaps less component or with the configuration different from shown in Fig. 1.Each component shown in Fig. 1 can use hardware, software Or combinations thereof realize.
In conjunction with Fig. 2, the embodiment of the invention provides a kind of data managing methods that can be applied to electronic equipment 10.Wherein, Method and step defined in the related process of the method can be realized by the processor 14.It below will be to tool shown in Fig. 2 Body process is described in detail.
Step S110 by type, weight and the quality of the coal of track scale acquisition current transportation to coal yard, and leads to It crosses the overturning robot scaler and obtains the license number for transporting the train of the coal, and establish the kind of the license number Yu the coal The corresponding relationship of class, weight and quality.
In detail, the communication connection of electronic equipment 10 has track scale, overturning robot scaler and bucket wheel machine, to pass through The track scale obtains type, weight and the quality of coal of the current transportation to coal yard, and counts dress by the way that the overturning is automatic The license number for obtaining the train for transporting the coal is set, and it is corresponding with the type of the coal, weight and quality to establish the license number Relationship, to determine type, weight and the quality of the coal of each license number for the train for transporting the coal.
Step S120, by being set to the bucket wheel machine and being obtained with the positioning device of the electronic equipment 10 communication connection Carry out the location data of the bucket wheel machine of coal piling operation.
In detail, the positioning device can be a part of the bucket wheel machine, be also possible to be separately set in the bucket Turbine, as long as being communicated to connect with the electronic equipment 10 to send the location data of the bucket wheel machine.
Step S130 generates coal yard according to the location data of the corresponding relationship and the bucket wheel machine for carrying out coal piling operation Stack data.
In detail, the coal yard is stacked data and can be shown on the screen of the electronic equipment 10, so that operation Personnel can understand the more specific location information of the coal of bucket wheel machine progress coal piling operation and type, weight and the product of corresponding coal in real time Matter.
With the above arrangement, can establish current transportation to coal yard coal type, weight and quality and transport the coal The corresponding relationship of the license number of the train of charcoal, and it is raw according to the location data of the corresponding relationship and the bucket wheel machine for carrying out coal piling operation Data are stacked at coal yard, to improve the accuracy of coal data management.
In conjunction with Fig. 3, the step S120 can also include step S121 and step S122, carry out coal piling operation to obtain The location data of bucket wheel machine.
Step S121 obtains the operating state data of all bucket wheel machines, to obtain carrying out the volume of the bucket wheel machine of coal piling operation Number.
In detail, the working condition includes working and not working.
Optionally, the concrete mode for obtaining the operating state data of all bucket wheel machines is unrestricted, can be according to actually answering It is configured with demand.For example, in the present embodiment, the step of the operating state data for obtaining all bucket wheel machines, specifically Are as follows:
By being set to the bucket wheel machine and obtaining bucket wheel machine with the detection device of the electronic equipment 10 communication connection Operating state data, to judge whether the bucket wheel machine carries out that coal is taken to operate according to the operating state data.
In detail, the concrete form of the detection device is unrestricted, can be configured according to practical application request.Example Such as, one kind can in alternative embodiment, the detection device can be the sensor for being set to the bucket wheel machine engine, By detecting the operating status of the bucket wheel machine engine to obtain the operating state data of bucket wheel machine.
Step S122 obtains the corresponding bucket wheel machine location data of number for carrying out coal piling operation bucket wheel machine.
In detail, the number for obtaining carrying out the bucket wheel machine of coal piling operation by step S121, by being set to the progress The positioning device of the bucket wheel machine of coal piling operation obtains the location data for carrying out the bucket wheel machine of coal piling operation.
Further, in conjunction with Fig. 4, the data managing method can also include step S140 and step S150, to obtain The location data for the bucket wheel machine for taking coal to operate is carried out, and updates coal yard and stacks data.
Step S140, by being set to the bucket wheel machine and being obtained with the positioning device of the electronic equipment 10 communication connection Carry out the location data for the bucket wheel machine for taking coal to operate.
In detail, the positioning device can be a part of the bucket wheel machine, be also possible to be separately set in the bucket Turbine, as long as being communicated to connect with the electronic equipment 10 to send the location data of the bucket wheel machine.
In conjunction with Fig. 5, the step S140 may include step S141 and step S142, to obtain the bucket for take coal to operate The location data of turbine.
Step S141 obtains the operating state data of all bucket wheel machines, to obtain the volume for the bucket wheel machine for take coal to operate Number.
Optionally, the concrete mode for obtaining the operating state data of all bucket wheel machines is unrestricted, can be according to actually answering It is configured with demand.For example, in the present embodiment, the step of the operating state data for obtaining all bucket wheel machines, specifically Are as follows:
By being set to the bucket wheel machine and obtaining bucket wheel machine with the detection device of the electronic equipment 10 communication connection Operating state data, to judge whether the bucket wheel machine carries out that coal is taken to operate according to the operating state data.
In detail, the concrete form of the detection device is unrestricted, can be configured according to practical application request.Example Such as, one kind can in alternative embodiment, the detection device can be the sensor for being set to the bucket wheel machine engine, By detecting the operating status of the bucket wheel machine engine to obtain the operating state data of bucket wheel machine.
Step S142 obtains the corresponding bucket wheel machine location data of number for take coal operation bucket wheel machine.
In detail, the number for the bucket wheel machine for take coal to operate is obtained by step S141, by being set to the progress The positioning device for the bucket wheel machine for taking coal to operate obtains the location data for the bucket wheel machine for take coal to operate.
Step S150 is generated newly according to the location data of the corresponding relationship and the bucket wheel machine for carrying out that coal is taken to operate Coal yard stacks data.
Wherein, coal yard is generated according to the location data for the bucket wheel machine for carrying out coal piling operation by step S130 and stacks data, When bucket wheel machine carries out that coal is taken to operate, the coal amount on coal yard is constantly being reduced, can be according to the corresponding relationship and the progress The location data for the bucket wheel machine for taking coal to operate updates coal yard and stacks data.
In conjunction with Fig. 6, the embodiment of the invention also provides a kind of data administrators that can be applied to above-mentioned electronic equipment 10 100, it may include corresponding relation building module 110, coal piling location data obtains module 120 and coal yard stacks data generation module 130。
The corresponding relation building module 110, for by track scale obtain current transportation to coal yard coal type, Weight and quality, and by overturning robot scaler obtain transport the coal train license number, and establish the license number with The corresponding relationship of the type of the coal, weight and quality.In the present embodiment, the corresponding relation building module 110 can be with For executing step S110 described in Fig. 2, it is right above that the specific descriptions about the corresponding relation building module 110 are referred to The description of step S110.
The coal piling location data obtains module 120, for by be set to bucket wheel machine and with 10 communication link of electronic equipment The positioning device connect obtains the location data for carrying out the bucket wheel machine of coal piling operation.In the present embodiment, the coal piling location data Obtaining module 120 can be used for executing step S120 described in Fig. 2, and the tool of module 120 is obtained about the coal piling location data Body description is referred to the description to step S120 above.
The coal yard stacks data generation module 130, for according to the corresponding relationship and described carrying out coal piling operation The location data of bucket wheel machine generates coal yard and stacks data.In the present embodiment, the coal yard stack data generation module 130 can be with For executing step S130 described in Fig. 2, before the specific descriptions about coal yard stacking data generation module 130 are referred to Description of the text to step S130.
In conjunction with Fig. 7, it may include the first operating state data acquisition submodule that the coal piling location data, which obtains module 120, 121 and coal piling location data acquisition submodule 122.
The first operating state data acquisition submodule 121, for obtaining the operating state data of all bucket wheel machines, with Obtain carrying out the number of the bucket wheel machine of coal piling operation.In the present embodiment, the first operating state data acquisition submodule 121 It can be used for executing step S121 described in Fig. 3, the specific descriptions about the first operating state data acquisition submodule 121 It is referred to the description above to step S121.
Wherein, the first operating state data acquisition submodule 121 is specifically used for:
By being set to the bucket wheel machine and obtaining bucket wheel machine with the detection device of the electronic equipment 10 communication connection Operating state data, to judge whether the bucket wheel machine carries out that coal is taken to operate according to the operating state data.
The coal piling location data acquisition submodule 122, the number for obtaining progress coal piling operation bucket wheel machine are corresponding Bucket wheel machine location data.In the present embodiment, the coal piling location data acquisition submodule 122 can be used for executing described in Fig. 3 Step S122, the specific descriptions about the coal piling location data acquisition submodule 122 are referred to above to step S122 Description.
In conjunction with Fig. 8, the data administrator 100 can also include that coal location data is taken to obtain module 140 and coal yard heap Put data update module 150.
It is described take coal location data obtain module 140, for by be set to the bucket wheel machine and with the electronic equipment The positioning device of 10 communication connections obtains the location data for the bucket wheel machine for take coal to operate.In the present embodiment, described to take coal Location data, which obtains module 140, can be used for executing step S140 described in Fig. 4, take coal location data to obtain module about described 140 specific descriptions are referred to the description to step S140 above.
In conjunction with Fig. 9, it is described take coal location data obtain module 140 may include the second operating state data acquisition submodule 141 and take coal location data acquisition submodule 142.
The second operating state data acquisition submodule 141, for obtaining the operating state data of all bucket wheel machines, with Obtain the number for the bucket wheel machine for take coal to operate.In the present embodiment, the second operating state data acquisition submodule 141 It can be used for executing step S141 described in Fig. 5, the specific descriptions about the second operating state data acquisition submodule 141 It is referred to the description above to step S141.
Wherein, the second operating state data acquisition submodule 141 is specifically used for:
By being set to the bucket wheel machine and obtaining bucket wheel machine with the monitoring device of the electronic equipment 10 communication connection Operating state data, to judge whether the bucket wheel machine carries out that coal is taken to operate according to the operating state data.
It is described to take coal location data acquisition submodule 142, take the number of coal operation bucket wheel machine corresponding for obtaining Bucket wheel machine location data.In the present embodiment, described that coal location data acquisition submodule 142 is taken to can be used for executing described in Fig. 5 Step S142, be referred to above about the specific descriptions for taking coal location data acquisition submodule 142 to step S142 Description.
The coal yard stacks data update module 150, for according to the corresponding relationship and described carrying out coal is taken to operate The location data of bucket wheel machine generates new coal yard and stacks data.In the present embodiment, the coal yard stacks data update module 150 It can be used for executing step S150 described in Fig. 4, the specific descriptions for stacking data update module 150 about the coal yard can join According to the description above to step S150.
In conclusion data managing method provided in an embodiment of the present invention and data administrator 100, can establish current The corresponding relationship of the license number to type, weight and the quality of the coal of coal yard and the train for transporting the coal is transported, and according to institute The location data stated corresponding relationship and carry out the bucket wheel machine of coal piling operation generates coal yard stacking data, to improve coal data management Accuracy.
In several embodiments provided by the embodiment of the present invention, it should be understood that disclosed device and method, it can also To realize by another way.Device and method embodiment described above is only schematical, for example, in attached drawing Flow chart and block diagram show that the devices of multiple embodiments according to the present invention, method and computer program product are able to achieve Architecture, function and operation.In this regard, each box in flowchart or block diagram can represent module, a program A part of section or code, a part of the module, section or code include that one or more is patrolled for realizing defined Collect the executable instruction of function.It should also be noted that in some implementations as replacement, function marked in the box It can occur in a different order than that indicated in the drawings.For example, two continuous boxes can actually be held substantially in parallel Row, they can also be executed in the opposite order sometimes, and this depends on the function involved.It is also noted that block diagram and/or The combination of each box in flow chart and the box in block diagram and or flow chart, can the function as defined in executing or dynamic The dedicated hardware based system made is realized, or can be realized using a combination of dedicated hardware and computer instructions.
In addition, each functional module in each embodiment of the present invention can integrate one independent portion of formation together Point, it is also possible to modules individualism, an independent part can also be integrated to form with two or more modules.
It, can be with if the function is realized and when sold or used as an independent product in the form of software function module It is stored in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially in other words The part of the part that contributes to existing technology or the technical solution can be embodied in the form of software products, the meter Calculation machine software product is stored in a storage medium, including some instructions are used so that a computer equipment (can be a People's computer, electronic equipment or network equipment etc.) execute all or part of step of each embodiment the method for the present invention Suddenly.And storage medium above-mentioned includes: USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), deposits at random The various media that can store program code such as access to memory (RAM, Random Access Memory), magnetic or disk. It should be noted that, in this document, the terms "include", "comprise" or its any other variant are intended to the packet of nonexcludability Contain, so that the process, method, article or equipment for including a series of elements not only includes those elements, but also including Other elements that are not explicitly listed, or further include for elements inherent to such a process, method, article, or device. In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including the element Process, method, article or equipment in there is also other identical elements.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of data managing method, which is characterized in that be applied to electronic equipment, the electronic equipment communication connection have track scale, Overturning robot scaler and bucket wheel machine, this method comprises:
It overturns certainly by type, weight and the quality of the coal of track scale acquisition current transportation to coal yard, and by described Dynamic counting device obtains the license number for transporting the train of the coal, and establishes the type, weight and product of the license number and the coal The corresponding relationship of matter;
Coal piling operation is carried out by being set to the bucket wheel machine and obtaining with the positioning device of electronic equipment communication connection The location data of bucket wheel machine;
Coal yard, which is generated, according to the location data of the corresponding relationship and the bucket wheel machine for carrying out coal piling operation stacks data.
2. data managing method according to claim 1, which is characterized in that it is described by be set to the bucket wheel machine and with The positioning device of electronic equipment communication connection obtains the step of location data for carrying out the bucket wheel machine of coal piling operation and includes:
The operating state data of all bucket wheel machines is obtained, to obtain carrying out the number of the bucket wheel machine of coal piling operation;
Obtain the corresponding bucket wheel machine location data of number for carrying out coal piling operation bucket wheel machine.
3. data managing method according to claim 1, which is characterized in that the method also includes:
Take coal operation by being set to the bucket wheel machine and obtaining with the positioning device of electronic equipment communication connection The location data of bucket wheel machine;
New coal yard, which is generated, according to the location data of the corresponding relationship and the bucket wheel machine for carrying out that coal is taken to operate stacks data.
4. data managing method according to claim 3, which is characterized in that it is described by be set to the bucket wheel machine and with The step of positioning device of electronic equipment communication connection obtains the location data for the bucket wheel machine for take coal to operate include:
The operating state data of all bucket wheel machines is obtained, to obtain the number for the bucket wheel machine for take coal to operate;
Obtain the corresponding bucket wheel machine location data of number for take coal operation bucket wheel machine.
5. data managing method according to claim 4, which is characterized in that the working condition for obtaining all bucket wheel machines The step of data, specifically:
Work shape by being set to the bucket wheel machine and with the detection device acquisition bucket wheel machine of electronic equipment communication connection State data, to judge whether the bucket wheel machine carries out that coal is taken to operate according to the operating state data.
6. a kind of data administrator, which is characterized in that the device includes:
Corresponding relation building module, for by track scale obtain current transportation to coal yard coal type, weight and quality, And the license number for transporting the train of the coal is obtained by overturning robot scaler, and establish the kind of the license number Yu the coal The corresponding relationship of class, weight and quality;
Coal piling location data obtains module, for by being set to bucket wheel machine and obtaining with the positioning device of electronic equipment communication connection Take the location data for carrying out the bucket wheel machine of coal piling operation;
Coal yard stacks data generation module, for the positioning according to the corresponding relationship and the bucket wheel machine for carrying out coal piling operation Data generate coal yard and stack data.
7. data administrator according to claim 6, which is characterized in that the coal piling location data obtains module packet It includes:
First operating state data acquisition submodule, for obtaining the operating state data of all bucket wheel machines, to obtain carrying out heap The number of the bucket wheel machine of coal operation;
Coal piling location data acquisition submodule, for obtaining the corresponding bucket wheel machine positioning number of number for carrying out coal piling operation bucket wheel machine According to.
8. data administrator according to claim 6, which is characterized in that described device further include:
Coal location data is taken to obtain module, for by being set to the bucket wheel machine and determining with what the electronic equipment communicated to connect Position device obtains the location data for the bucket wheel machine for take coal to operate;
Coal yard stacks data update module, for the positioning according to the corresponding relationship and the bucket wheel machine for carrying out that coal is taken to operate Data generate new coal yard and stack data.
9. data administrator according to claim 8, which is characterized in that described that coal location data is taken to obtain module packet It includes:
Second operating state data acquisition submodule, for obtaining the operating state data of all bucket wheel machines, to obtain being taken The number of the bucket wheel machine of coal operation;
Coal location data acquisition submodule is taken, for obtaining the location data for the bucket wheel machine for take coal to operate.
10. data administrator according to claim 9, which is characterized in that the second operating state data acquisition submodule It is specifically used for:
Work shape by being set to the bucket wheel machine and with the detection device acquisition bucket wheel machine of electronic equipment communication connection State data, to judge whether the bucket wheel machine carries out that coal is taken to operate according to the operating state data.
CN201910011568.6A 2019-01-07 2019-01-07 Data managing method and data administrator Pending CN109740944A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910011568.6A CN109740944A (en) 2019-01-07 2019-01-07 Data managing method and data administrator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910011568.6A CN109740944A (en) 2019-01-07 2019-01-07 Data managing method and data administrator

Publications (1)

Publication Number Publication Date
CN109740944A true CN109740944A (en) 2019-05-10

Family

ID=66363549

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910011568.6A Pending CN109740944A (en) 2019-01-07 2019-01-07 Data managing method and data administrator

Country Status (1)

Country Link
CN (1) CN109740944A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112907069A (en) * 2021-02-19 2021-06-04 山东矩阵软件工程股份有限公司 Coal mine transport vehicle distribution method and device, electronic equipment and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5144317A (en) * 1990-04-07 1992-09-01 Rheinbraun Aktiengesellschaft Method of determining mining progress in open cast mining by means of satellite geodesy
CN104483952A (en) * 2014-12-31 2015-04-01 华电郑州机械设计研究院有限公司 Novel intelligent coal conveying control system based on FCS on-site bus technology
CN206075478U (en) * 2016-10-12 2017-04-05 中国石化集团胜利石油管理局胜利发电厂 A kind of intelligent digitalized coal yard generalized information management device
CN109132592A (en) * 2018-06-22 2019-01-04 中国电建集团长春发电设备有限公司 The unattended control method of bucket wheel machine based on the storage of plc data subregion

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5144317A (en) * 1990-04-07 1992-09-01 Rheinbraun Aktiengesellschaft Method of determining mining progress in open cast mining by means of satellite geodesy
CN104483952A (en) * 2014-12-31 2015-04-01 华电郑州机械设计研究院有限公司 Novel intelligent coal conveying control system based on FCS on-site bus technology
CN206075478U (en) * 2016-10-12 2017-04-05 中国石化集团胜利石油管理局胜利发电厂 A kind of intelligent digitalized coal yard generalized information management device
CN109132592A (en) * 2018-06-22 2019-01-04 中国电建集团长春发电设备有限公司 The unattended control method of bucket wheel machine based on the storage of plc data subregion

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112907069A (en) * 2021-02-19 2021-06-04 山东矩阵软件工程股份有限公司 Coal mine transport vehicle distribution method and device, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
CN103632026B (en) Goods sorting method and system
CN105446281B (en) Processing chamber sends pallet piling up method and system
CN110136264B (en) Three-dimensional laser scanning-based stock ground material modeling method and system
CN107450501A (en) A kind of manufacturing execution system for being applied to automate filling workshop
CN109740944A (en) Data managing method and data administrator
CN109767133A (en) The electric quantity compensating method and apparatus of data are recorded based on load
CN107832386A (en) A kind of error correction method and apparatus of electronic map
CN108469796A (en) The autonomous detection method of plant maintenance based on product qualification rate
CN107524188A (en) Excavator bucket counting number method and system
CN104101837B (en) A kind of on-line calculation method of the current total capacity of battery
CN202295445U (en) Production line packaging device
CN103116315A (en) Control method for achieving cutting tool radius compensation overall interference in numerical control system
CN117213502B (en) Positioning method of port hoisting equipment in digital twin scene
CN106645868A (en) Short-circuit current scanning method and device
CN104683130B (en) A kind of method and apparatus of configuring stacking port
CN109003686A (en) Localization method, device, computer equipment and the storage medium of nuclear power station loosening part
CN110987103B (en) Liquid level measuring method and device and engineering machinery
CN108255950A (en) Date storage method and terminal device
CN107800816A (en) A kind of IP address database method for building up and terminal device
CN201955668U (en) System for monitoring and managing dry-mixed mortar
CN109455527A (en) A kind of cargo de-stacking method and device
CN106585576B (en) Bus based on motion controller moves battery methods certainly
CN113281695B (en) Automatic sampling system of automatic verification assembly line of electric energy meter
CN108266364A (en) Electric pump load too low method for diagnosing faults and device
CN108223401A (en) Electric pump load too high method for diagnosing faults and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190510