CN109683921A - A kind of whole process system deployment method based on Automation of Electric Systems operation platform - Google Patents

A kind of whole process system deployment method based on Automation of Electric Systems operation platform Download PDF

Info

Publication number
CN109683921A
CN109683921A CN201811624918.8A CN201811624918A CN109683921A CN 109683921 A CN109683921 A CN 109683921A CN 201811624918 A CN201811624918 A CN 201811624918A CN 109683921 A CN109683921 A CN 109683921A
Authority
CN
China
Prior art keywords
host
deployment
operation platform
creation
automation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811624918.8A
Other languages
Chinese (zh)
Other versions
CN109683921B (en
Inventor
冒佳明
李叶飞
王松云
陈国琳
厉文婕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Information And Communication Branch Of Jiangsu Electric Power Co Ltd
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Jiangsu Fangtian Power Technology Co Ltd
Original Assignee
Information And Communication Branch Of Jiangsu Electric Power Co Ltd
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Jiangsu Fangtian Power Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Information And Communication Branch Of Jiangsu Electric Power Co Ltd, State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Jiangsu Fangtian Power Technology Co Ltd filed Critical Information And Communication Branch Of Jiangsu Electric Power Co Ltd
Priority to CN201811624918.8A priority Critical patent/CN109683921B/en
Publication of CN109683921A publication Critical patent/CN109683921A/en
Application granted granted Critical
Publication of CN109683921B publication Critical patent/CN109683921B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F8/00Arrangements for software engineering
    • G06F8/60Software deployment
    • G06F8/61Installation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F9/00Arrangements for program control, e.g. control units
    • G06F9/06Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
    • G06F9/44Arrangements for executing specific programs
    • G06F9/4401Bootstrapping
    • G06F9/4403Processor initialisation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Software Systems (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Computer Security & Cryptography (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Stored Programmes (AREA)

Abstract

The whole process system deployment method based on Automation of Electric Systems operation platform that the invention discloses a kind of, step include inputting host application information, the judgement for carrying out host application information and verifying, the automatic installation and deployment examining step by step, create host, carrying out agent client for carrying out examination & approval end, carrying out system environment initialization configuration, carry out the customized deployment of operation system basic environment, be transferred to operation system data configuration and carry out operation system deployment;Solve the problems, such as each link manual creation and deployment when new business system deployment, improving O&M efficiency reduces O&M cost, has a good application prospect.

Description

A kind of whole process system deployment method based on Automation of Electric Systems operation platform
Technical field
The invention belongs to Automation of Electric Systems O&M construction technique fields, more particularly to a kind of automatic based on electric system Change the whole process system deployment method of operation platform.
Background technique
Currently, with informationization technology and the high speed development of technology of Internet of things, privately owned cloud is gradually mature, in life It produces and is used widely in environment, the privately owned cloud platform that building is applied to production environment becomes the important interior of electric system IT construction Hold.As electric power information infrastructure is improved day by day, information system application deepens continuously in all respects, power information Chemical industry work has obvious development.At the same time, along with the continuous expansion of network size, system complexity is continuously increased, full On the basis of sufficient service operation demand, the difficulty of system administration and maintenance is continuously increased, to meet increasingly huge O&M scale, The automation operation platform built up realizes that O&M automation reduces O&M cost and improves O&M efficiency and quality.The electric power built up System cloud computing platform, provides integrated operation for service application, integrated and information shows environment, realizes that information resources are intensive Management and dynamic adaptation reduce operating cost, improve resource utilization;Realize that data center resource is intensive using cloud computing technology Change management, uniformly use and dynamic adaptation, reduces operating cost, greatly improve resource utilization.
On the other hand, it takes root with virtualization technology in electric power enterprise, because data center is transformed, large quantities of physical systems Legacy system need to carry out cloud migration, the pure maintenance work amoun of deployment by hand is huge.The online deployment of a large amount of new systems is manually tieed up Protect inefficiency.How effectively to solve the above problems, reduce cost, also becomes electric power enterprise facing challenges.
Summary of the invention
To solve above-mentioned the technical problems existing in the prior art, the present invention provides one kind to be based on Automation of Electric Systems The whole process system deployment method of operation platform realizes new business system full-range automatically dispose from scratch, by right It connects privately owned cloud platform and realizes empty machine creation or physical machine system deployment, and be torqued into automation operation platform and realize the initial ring of system The whole process solution of system middleware and automatic service deployment is realized in border automatic deployment and configuration.Solves new business system When system deployment the problem of each link manual creation and deployment, improving O&M efficiency reduces O&M cost, before having good application Scape.
The present invention solves its technical problem and is achieved through the following technical solutions:
A kind of whole process system deployment method based on Automation of Electric Systems operation platform, comprising the following steps:
Step S1, Yu Zidong operation platform fills in host application information, and the host application information includes host information system System title, responsible person's name, host model and operating system version, after the completion of filling in, put down from automatic operation platform to private clound Platform initiates host application process;
Step S2, the privately owned cloud platform in the described step S1 carries out host letter of application after receiving host application information The judgement and verifying of breath;
Step S3, examine whether the host application information of the step S2 matches privately owned cloud platform, after the assay was approved, then will The examination & approval end that host application information pushes to each relevant person in charge is examined step by step, and responsible person, which audits host application information, is No to meet application condition, if responsible person's examination & approval do not pass through, programmed decision is to reject, and corresponding host application information is returned After automatic operation platform modification, application is re-started;If responsible person's examination & approval pass through, corresponding host application information is made to enter master Machine visioning procedure;
Step S4, when the host application information of the step S3 enters host visioning procedure, according to host application information In creation type, judge that the host of creation is empty machine or physical machine, if empty machine, then pass through according to host application information OpenStack and VMWare interface creates OpenStack void machine or VMWare void machine, if physical machine, then according to host application Information carries out automation operating system installation and deployment to physical machine;
If the result that the host of step S5, the described step S4 creates is failure, repeatedly step S4 carries out host again Creation terminates host visioning procedure and simultaneously informs automation operation platform, if the result that create of the host of the step S4 at Function then informs that automation operation platform host has created success;
Step S6, it in the step S5, after host known to automation operation platform has created successfully, creates successfully main Machine is reversed to automatic operation platform, and the automatic installation and deployment of agent client, the proxy client are carried out by automatic operation platform End is installed on the successful host of creation, creates successful host in the registration of automatic operation platform and managed to realize;
Step S7, after the completion of the step S6, then the system environment initialization configuration for creating successful host, institute are carried out Stating system environment initialization and preparing includes online preceding compliance configuration and security hardening configuration;
Step S8, the successful host system initial environment of creation is matched in completing the step S7 and is postponed by automatic O&M The customized deployment of platform further progress operation system basic environment, the customized deployment of operation system basic environment includes industry The business customized creation of user, the customized installation of the variant version of JDK, middleware weblogic and tomcat make Yian city by oneself Dress;
Step S9, in completing the step S8 to the successful customized deployment of host service system-based environment of creation Afterwards, operation system data configuration is transferred to by automatic operation platform, the operation system data configuration includes operation system title, needs The numeric field data to be created, the configuration using data for needing the service data created and needs to issue;
Step S10, in completing the step S9 to the successful host service system data of creation with postponing, by Account Dept It affixes one's name to control centre and carries out operation system deployment, if Weblogic middleware, then content is configured according to business datum and carried out automatically Change domain creation, server creation, cluster creation and application publication, if Tomcat middleware, then configured according to business datum in Hold and carries out using publication.
As further improved technical solution, in the step S4, if virtual machine, then dock OpenStack and VMWare calls different virtual platform interfaces to carry out empty machine creation, if physical machine, then the physical machine operation by realizing The automatic installation function of system carries out physical machine creation.
As further improved technical solution, the step of installation of the agent client in the step S6 successively includes Client downloads, the configuration of the source Yum, Yum is installed automatically, Key is automatically configured and Key authentication checks.
As further improved technical solution, the step of compliance configures in the step S7 successively includes service-user Customized creation, category group authority configuration and baseline directory configuration, the system environment initialization in the step S8, which is prepared, to be completed The customized installation of safe JDK of variant version is then carried out afterwards.
As further improved technical solution, the step of Weblogic middleware in the step S10 is disposed is successively Including creation domain, creation Server, starting AdminServer, creation cluster, creation data source and application publication.
As further improved technical solution, the step of Tomcat middleware in the step S10 is disposed successively is wrapped Include configuration system information, deployment way selection, collocating traffic parameter, starting Tomcat and application publication.
Compared with prior art, the invention has the benefit that
The present invention is based on the whole process system deployment method of Automation of Electric Systems operation platform, realize new business system from Low efficiency, approval process complexity etc. are reversed without each O&M teams and groups system application linking to there is full-range automatically dispose, is solved Problem solves the problems, such as host manual creation and operation system manually dispose, and improving O&M efficiency reduces O&M cost, has good Good application prospect.
Detailed description of the invention
Fig. 1 is flow chart of the invention.
Specific embodiment
Below by specific embodiment, the invention will be further described, and it is not limit that following embodiment, which is descriptive, Qualitatively, this does not limit the scope of protection of the present invention.
Embodiment
A kind of whole process system deployment method based on Automation of Electric Systems operation platform realizes new business system from nothing To there is full-range automatically dispose, each O&M teams and groups system application linking torsion low efficiency is solved, approval process complexity etc. is asked Topic solves the problems, such as host manual creation and operation system manually dispose, and improving O&M efficiency reduces O&M cost, such as Fig. 1 institute Show, comprising the following specific steps
Step S1, Yu Zidong operation platform fills in host application information, and host application information includes host information system name The basic informations such as title, responsible person's name, host model and operating system version, after the completion of filling in, from automatic operation platform to private There is cloud platform to initiate host application process;
Step S2, automatic operation platform and the docking of private clound platform interface in step S1, is receiving in privately owned cloud platform After host application information, the judgement and verifying of host application information are carried out;
Step S3, examine whether the host application information of the step S2 matches privately owned cloud platform, after the assay was approved, then will The examination & approval end that host application information pushes to each relevant person in charge is examined step by step, and responsible person, which audits host application information, is No to meet application condition, if responsible person's examination & approval do not pass through, programmed decision is to reject, and corresponding host application information is returned After automatic operation platform modification, application is re-started;If responsible person's examination & approval pass through, corresponding host application information is made to enter master Machine visioning procedure;
Step S4, when the host application information of step S3 enters host visioning procedure, according in host application information Type is created, judges that the host of creation is empty machine or physical machine, if empty machine, then pass through according to host application information OpenStack and VMWare interface creates OpenStack void machine or VMWare void machine, if physical machine, then according to host application Information carries out automation operating system installation and deployment to physical machine;
If step S5, the result of the host creation of step S4 is failure, repeatedly step S4 carries out re-creating for host Or terminate host visioning procedure and inform automation operation platform, if the result that the host of step S4 creates is successfully, to inform Automation operation platform host has created success, can carry out next step service level deployment;
Step S6, it after in step s 5, host known to automation operation platform has created successfully, creates successful host and turns round Automatic operation platform is gone to, the automatic installation and deployment of agent client are carried out by automatic operation platform, agent client is installed on It creates on successful host, creates successful host in the registration of automatic operation platform and managed to realize, wherein proxy client The step of installation at end successively includes client downloads, the configuration of the source Yum, Yum is installed automatically, Key is automatically configured to authenticate with Key and be examined It surveys.
Step S7, after the completion of step S6, then the system environment initialization configuration for creating successful host, system ring are carried out The step of border initialization is prepared to be operated including online preceding compliance configuration and security hardening configuration etc., compliance configuration is successively wrapped Include customized creation, category group authority configuration and the baseline directory configuration of service-user;
Step S8, in completing step S7 to the successful host system initial environment of creation with postponing, according to project teams Concrete condition, by the customized deployment of automatic operation platform further progress operation system basic environment, operation system basic environment It is customized deployment include the customized creation of service-user, the customized installation of the variant version of JDK, middleware weblogic and The customized installation of tomcat, wherein system environment initialization then carries out variant version safe JDK after the completion of preparing makes by oneself Yian city dress;
Step S9, in completing step S8 to the successful customized deployment of host service system-based environment is created after, by Automatic operation platform is transferred to operation system data configuration, and operation system data configuration includes operation system title, needs to create The configuration using data that the service data and needs that numeric field data, needs create are issued;
Step S10, in completing step S9 to the successful host service system data of creation with postponing, by system deployment control Center processed carries out operation system deployment, if Weblogic middleware, the service deployment of Weblogic middleware is relative complex, therefore Content, which is configured, according to business datum successively carries out creation domain, creation Server, starting AdminServer, creation cluster, creation number According to source and application publication, if Tomcat middleware, then content is configured according to business datum and successively carry out configuration system information, portion The selection of management side formula, collocating traffic parameter, starting Tomcat and application publication.Entire operation system is realized since then from scratch, The publication of application system uses.
In conclusion the whole process system deployment method of the invention based on Automation of Electric Systems operation platform, is realized New business system full-range automatically dispose from scratch solves each O&M teams and groups system application linking torsion low efficiency, examines The problems such as batch list is complicated solves the problems, such as host manual creation and operation system manually dispose, and improving O&M efficiency reduces fortune Cost is tieed up, is had a good application prospect.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (6)

1. a kind of whole process system deployment method based on Automation of Electric Systems operation platform, which is characterized in that including following Step:
Step S1, Yu Zidong operation platform fills in host application information, and the host application information includes host information system name Title, responsible person's name, host model and operating system version, after the completion of filling in, are sent out from automatic operation platform to privately owned cloud platform Play host application process;
Step S2, the privately owned cloud platform in the described step S1 carries out host application information after receiving host application information Judgement and verifying;
Step S3, examine whether the host application information of the step S2 matches privately owned cloud platform, after the assay was approved, then by host The examination & approval end that application information pushes to each relevant person in charge is examined step by step, and responsible person audits whether host application information accords with Application condition is closed, if responsible person's examination & approval do not pass through, programmed decision is rejection, and the return of corresponding host application information is automatic After operation platform modification, application is re-started;If responsible person's examination & approval pass through, corresponding host application information is made to enter host wound Build process;
Step S4, when the host application information of the step S3 enters host visioning procedure, according in host application information Type is created, judges that the host of creation is empty machine or physical machine, if empty machine, then pass through according to host application information OpenStack and VMWare interface creates OpenStack void machine or VMWare void machine, if physical machine, then according to host application Information carries out automation operating system installation and deployment to physical machine;
If the result that the host of step S5, the described step S4 creates is failure, repeatedly step S4 carries out re-creating for host Or terminate host visioning procedure and inform automation operation platform, if the result that the host of the step S4 creates be successfully, Inform that automation operation platform host has created success;
Step S6, it in the step S5, after host known to automation operation platform has created successfully, creates successful host and turns round Automatic operation platform is gone to, the automatic installation and deployment of agent client, the agent client peace are carried out by automatic operation platform Loaded on creating on successful host, successful host is created in the registration of automatic operation platform and managed to realize;
Step S7, after the completion of the step S6, then the system environment initialization configuration for creating successful host, the system are carried out It includes online preceding compliance configuration and security hardening configuration that context initialization of uniting, which is prepared,;
Step S8, the successful host system initial environment of creation is matched in completing the step S7 and is postponed by automatic operation platform The customized deployment of further progress operation system basic environment, the customized deployment of operation system basic environment includes that business is used The customized creation at family, the customized installation of the variant version of JDK, the customized installation of middleware weblogic and tomcat;
Step S9, in completing the step S8 to the successful customized deployment of host service system-based environment is created after, by Automatic operation platform is transferred to operation system data configuration, and the operation system data configuration includes operation system title, needs to create The numeric field data built, the configuration using data for needing the service data created and needs to issue;
Step S10, in completing the step S9 to the successful host service system data of creation with postponing, by system deployment control Center processed carries out operation system deployment, if Weblogic middleware, then configures content according to business datum and carries out automation domain Creation, server creation, cluster creation and application publication, if Tomcat middleware, then according to business datum configure content into Row application publication.
2. a kind of whole process system deployment method based on Automation of Electric Systems operation platform according to claim 1, It is characterized in that, if virtual machine, then docking OpenStack and VMWare in the step S4 and calling different virtualizations flat Platform interface carries out empty machine creation, if physical machine, then carries out physics by the automatic installation function of the physical machine operating system realized Machine creation.
3. a kind of whole process system deployment method based on Automation of Electric Systems operation platform according to claim 1, It is characterized in that, the step of installation of agent client in the step S6 successively include client downloads, the configuration of the source Yum, Yum is installed automatically, Key is automatically configured and Key authentication checks.
4. a kind of whole process system deployment method based on Automation of Electric Systems operation platform according to claim 1, It is characterized in that, the step of compliance configures in the step S7 successively includes customized creation, the category group permission of service-user Configuration and baseline directory configure, and the system environment initialization in the step S8 then carries out the peace of variant version after the completion of preparing The customized installation of full JDK.
5. a kind of whole process system deployment method based on Automation of Electric Systems operation platform according to claim 1, It is characterized in that, in the step S10 Weblogic middleware deployment the step of successively include creation domain, creation Server, Start AdminServer, creation cluster, creation data source and application publication.
6. a kind of whole process system deployment method based on Automation of Electric Systems operation platform according to claim 1, It is characterized in that, the Tomcat middleware in the step S10 successively includes configuration system information, deployment way the step of deployment Selection, collocating traffic parameter, starting Tomcat and application publication.
CN201811624918.8A 2018-12-28 2018-12-28 Full-process system deployment method based on power system automation operation and maintenance platform Active CN109683921B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811624918.8A CN109683921B (en) 2018-12-28 2018-12-28 Full-process system deployment method based on power system automation operation and maintenance platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811624918.8A CN109683921B (en) 2018-12-28 2018-12-28 Full-process system deployment method based on power system automation operation and maintenance platform

Publications (2)

Publication Number Publication Date
CN109683921A true CN109683921A (en) 2019-04-26
CN109683921B CN109683921B (en) 2022-04-15

Family

ID=66190887

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811624918.8A Active CN109683921B (en) 2018-12-28 2018-12-28 Full-process system deployment method based on power system automation operation and maintenance platform

Country Status (1)

Country Link
CN (1) CN109683921B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110795108A (en) * 2019-09-18 2020-02-14 国网江苏省电力有限公司 Method for deploying Weblogic application based on Ansible layout
CN113438104A (en) * 2021-06-10 2021-09-24 上海甄汇信息科技有限公司 System non-inductive automatic iteration method
CN113778461A (en) * 2021-09-09 2021-12-10 北京炎黄新星网络科技有限公司 Method and system for realizing automatic application deployment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110209140A1 (en) * 2010-02-25 2011-08-25 Microsoft Corporation Automated deployment and servicing of distributed applications
CN106325954A (en) * 2016-08-30 2017-01-11 广西电网有限责任公司 Oracle and Weblogic combined one-key automatic deployment method
CN106325951A (en) * 2016-08-30 2017-01-11 广西电网有限责任公司 Automatic deployment method for application system supporting multiple databases and multiple middleware types
CN106603267A (en) * 2016-08-30 2017-04-26 广西电网有限责任公司 Automatic one-key deployment method of MySQL and Weblogic combination

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110209140A1 (en) * 2010-02-25 2011-08-25 Microsoft Corporation Automated deployment and servicing of distributed applications
CN106325954A (en) * 2016-08-30 2017-01-11 广西电网有限责任公司 Oracle and Weblogic combined one-key automatic deployment method
CN106325951A (en) * 2016-08-30 2017-01-11 广西电网有限责任公司 Automatic deployment method for application system supporting multiple databases and multiple middleware types
CN106603267A (en) * 2016-08-30 2017-04-26 广西电网有限责任公司 Automatic one-key deployment method of MySQL and Weblogic combination

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110795108A (en) * 2019-09-18 2020-02-14 国网江苏省电力有限公司 Method for deploying Weblogic application based on Ansible layout
CN110795108B (en) * 2019-09-18 2022-08-16 国网江苏省电力有限公司 Method for deploying Weblogic application based on Ansible layout
CN113438104A (en) * 2021-06-10 2021-09-24 上海甄汇信息科技有限公司 System non-inductive automatic iteration method
CN113778461A (en) * 2021-09-09 2021-12-10 北京炎黄新星网络科技有限公司 Method and system for realizing automatic application deployment

Also Published As

Publication number Publication date
CN109683921B (en) 2022-04-15

Similar Documents

Publication Publication Date Title
CN110192380B (en) System and method for managing blockchain cloud services
US20220222593A1 (en) Portable network interfaces for authentication and license enforcement
CN109683921A (en) A kind of whole process system deployment method based on Automation of Electric Systems operation platform
US10554646B2 (en) Providing domain-joined remote applications in a cloud environment
CN108462746B (en) Container deployment method and framework based on openstack
CN112514319A (en) System and method for supporting SQL-based rich queries in a hyper-ledger architecture blockchain
CN105024865B (en) Cloud joint services
CN109800056A (en) A kind of block chain dispositions method based on container
CN111190730B (en) Heterogeneous cloud management platform
CN108549580A (en) Methods and terminal device of the automatic deployment Kubernetes from node
EP2899947A1 (en) Component oriented hybrid cloud operating system architecture and communication method thereof
US20150271148A1 (en) System and method for transporting a document between a first service provider and a second service provider
US8646062B2 (en) Remote authentication based on challenge-response using digital certificates
EP2811397B1 (en) Method for managing virtual machine and device therefor
CN103514038B (en) A kind of smooth method for closing and system of virtual system
CN109889480A (en) Based on container and the totally-domestic of cloud platform fusion cloud platform management method and system
CN108021608A (en) A kind of lightweight website dispositions method based on Docker
CN105577442B (en) Storage virtual machine based on cloud platform receives pipe method
CN108037978A (en) A kind of managing computing resources method based on virtualization technology
CN103207965A (en) Method and device for License authentication in virtual environment
WO2018063663A1 (en) Cloud container resource binding and tasking using keys
CN114666333A (en) Control method for cloud computing resource scheduling problem based on multi-tenant theory
CN103490983B (en) Corporate mail system and its method carrying out mail migration
CN107741853A (en) A kind of method, system and the information management platform of deployment services device
CN112181745B (en) Cloud service platform system and method for FPGA prototype verification

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant