CN109547745A - A kind of monitoring system and method based on video technique - Google Patents

A kind of monitoring system and method based on video technique Download PDF

Info

Publication number
CN109547745A
CN109547745A CN201811363584.3A CN201811363584A CN109547745A CN 109547745 A CN109547745 A CN 109547745A CN 201811363584 A CN201811363584 A CN 201811363584A CN 109547745 A CN109547745 A CN 109547745A
Authority
CN
China
Prior art keywords
temperature
object surface
cement
unit
controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811363584.3A
Other languages
Chinese (zh)
Other versions
CN109547745B (en
Inventor
徐艺玮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Gaozhi Project Management Co., Ltd.
Original Assignee
Jiangsu Gaozhi Project Management Co Ltd
Zhejiang A&F University ZAFU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Gaozhi Project Management Co Ltd, Zhejiang A&F University ZAFU filed Critical Jiangsu Gaozhi Project Management Co Ltd
Priority to CN201811363584.3A priority Critical patent/CN109547745B/en
Publication of CN109547745A publication Critical patent/CN109547745A/en
Application granted granted Critical
Publication of CN109547745B publication Critical patent/CN109547745B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
    • H04N7/181Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast for receiving images from a plurality of remote sources
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01DMEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE; ARRANGEMENTS FOR MEASURING TWO OR MORE VARIABLES NOT COVERED IN A SINGLE OTHER SUBCLASS; TARIFF METERING APPARATUS; MEASURING OR TESTING NOT OTHERWISE PROVIDED FOR
    • G01D21/00Measuring or testing not otherwise provided for
    • G01D21/02Measuring two or more variables by means not covered by a single other subclass
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06VIMAGE OR VIDEO RECOGNITION OR UNDERSTANDING
    • G06V20/00Scenes; Scene-specific elements
    • G06V20/50Context or environment of the image
    • G06V20/52Surveillance or monitoring of activities, e.g. for recognising suspicious objects
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06VIMAGE OR VIDEO RECOGNITION OR UNDERSTANDING
    • G06V40/00Recognition of biometric, human-related or animal-related patterns in image or video data
    • G06V40/10Human or animal bodies, e.g. vehicle occupants or pedestrians; Body parts, e.g. hands
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B19/00Alarms responsive to two or more different undesired or abnormal conditions, e.g. burglary and fire, abnormal temperature and abnormal rate of flow

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Multimedia (AREA)
  • Theoretical Computer Science (AREA)
  • Human Computer Interaction (AREA)
  • Signal Processing (AREA)
  • Investigating Or Analyzing Materials Using Thermal Means (AREA)
  • Alarm Systems (AREA)

Abstract

The monitoring system and method based on video technique that the invention discloses a kind of, the former includes the controller and acquisition component being electrically connected to each other, controller and remote control center are wirelessly connected, acquisition component includes being installed on the first camera of construction site and being installed on the second camera that cement pours object surface, first camera is used to acquire the first image information in the construction site preset range in real time, second camera is thermal imaging system, the second image information that second camera pours object surface for acquiring cement in real time, first image information and the second image information pass through the controller respectively and are transmitted to the remote control center;Controller enters the identity information of the personnel in the preset range of construction site by the verifying of the first image information, judges that cement pours the temperature on object surface by the second image information, to control the starting of temperature control device.It can be realized by above system and effective monitoring carried out to the temperature that thes cement solidifies, while guaranteeing to monitor in construction field.

Description

A kind of monitoring system and method based on video technique
Technical field
The present invention relates to the monitoring technical field of construction more particularly to a kind of monitoring system based on video technique and Method.
Background technique
With the development of social economy and the raising of living standards of the people, construction Supervision has penetrated into the side of engineering practice Aspect face.In existing construction process, cement, which pours rear multi-pass, which crosses natural air drying, makes its solidification, and cement is in solidification When, it is to want exothermic, will affect the construction quality after theing cement solidifies if heat can not be successfully release;Meanwhile if cement Environment temperature is too low in process of setting, will affect setting rate and Solidification Quality.Therefore, how to be monitored during theing cement solidifies With its temperature of adjustment, to guarantee the cement solidifies quality and setting rate, with regard to becoming, those skilled in the art are urgently to be resolved to be asked Topic.
Summary of the invention
The purpose of the present invention is to solve at least one above-mentioned problem, which is by the following technical programs It realizes.
The present invention provides a kind of monitoring systems in video technique, including the controller being electrically connected to each other and acquisition group Part, the controller and remote control center are wirelessly connected, and the acquisition component includes that first be installed in construction site is taken the photograph As head and it is installed on the second camera that cement pours object surface;
First camera is used to acquire the first image information in the construction site preset range in real time, and described first takes the photograph As collected the first image information is transmitted to the remote control center by the controller;
The second camera is thermal imaging system, the second figure that the second camera pours object surface for acquiring cement in real time As information, collected second image information of second camera is transmitted to the long-range control by the controller Center;
The controller enters the identity of the personnel in the preset range of construction site by the first image Information Authentication, so as to Control the starting of alarm and temperature control device;The controller judges that cement pours object surface by second image information Temperature, to control the starting of temperature control device.
Further, the controller includes main control unit, comparing unit and storage unit, the main control unit respectively with The comparing unit and storage unit electrical connection;
The comparing unit by the first image information compared with default personal information, it is default into construction site to judge The identity of personnel in range, the comparing unit by the second image information compared with preset temperature image, to judge cement Pour the temperature on object surface;
The main control unit is used to receive the judging result of the comparing unit, and controls the temperature control according to the judging result The start and stop of device;
The storage unit is for storing the default personal information and the preset temperature image.
Further, the controller further includes that the communication unit being electrically connected respectively with the main control unit and positioning are single Member, the communication unit are wirelessly connected by 4G network and the remote control center, and the positioning unit for acquiring in real time Carry the location information of the personnel of default personal information.
Further, the controller further includes that the display unit being electrically connected respectively with the main control unit and alarm are single Member, the display unit is for showing the judging result, and the alarm unit is for issuing alarm signal.
Further, the acquisition component further includes the temperature sensor being electrically connected with the controller, and the temperature passes Sensor is set to the cement and pours object surface, and the temperature on object surface is poured for acquiring the cement.
Further, the temperature control device includes cooling unit, is preset when the temperature that the cement pours object surface is higher than Temperature and when the identity of personnel entered in the preset range of construction site meets default identity, controls the cooling unit starting.
Further, the temperature control device further includes heat-insulation unit, when the cement pours the temperature on object surface lower than pre- If temperature and when the identity of personnel entered in the preset range of construction site meets default identity, controls the heat-insulation unit and open It is dynamic.
Further, the acquisition component further includes the humidity sensor being electrically connected with the controller, and the humidity passes Sensor is set to the cement and pours object surface, and the humidity on object surface is poured for acquiring the cement.
Further, the controller Electricity Federation is connected to humidity conditioner, and the controller pours object according to the cement The humidity on surface judges whether to start the humidity conditioner.
The present invention also provides a kind of monitoring methods based on video technique, by as described above based on video technique Monitoring system is implemented, method includes the following steps:
S1: the personal information that acquisition is currently entering in the preset range of construction site;
S2: whether the personal information that judgement is currently entering in the preset range of construction site meets with preset personal information, if so, It is then transferred to S3, if it is not, feeding back judging result to remote control center, and issues alarm signal;
S3: acquisition cement pours the temperature and humidity on object surface;
S4: judge that cement pours the temperature on object surface and whether is in preset temperature section, judging result is shown and fed back To remote control center, when the temperature that cement pours object surface is not in preset temperature section or enters construction site preset range When interior personal information and preset personal information are not met, alarm signal is issued;
When the temperature that cement pours object surface is not in preset temperature section and enters personnel's letter in the preset range of construction site When breath meets with preset personal information, start temperature control device;
When the temperature that cement pours object surface is in preset temperature section and enters the personal information in the preset range of construction site When meeting with preset personal information, it is transferred to S5;
S5: judge that cement pours the humidity on object surface and whether is in default humidity section, judging result is shown and fed back It issues alarm signal when the humidity that cement pours object surface is not in default humidity section to remote control center and starts Humidity conditioner returns to S1 when the humidity that cement pours object surface is in default humidity section.
Monitoring system and method provided by the invention based on video technique, having the beneficial effect that compared with prior art
1, it can be realized by the first camera and the identity of the personnel entered in the preset range of construction site verified, avoid Irrelevant personnel enters the generation of the case where building site, meanwhile, it is capable to which the work whole process to staff is monitored, guarantee was constructed The effective monitoring of journey.
2, the heating power image for acquiring formation in real time by second camera is compared with preset heating power image, effectively supervises Survey cement pours object and situation uneven in temperature occurs, so as to guarantee the quality that thes cement solidifies.
3, when the temperature during theing cement solidifies occurs abnormal, effectively staff can be reminded to adopt by warning function Take requisite measure.
4, it can effectively realize that the humidity for pouring object to cement carries out effective monitoring by the way that humidity sensor is arranged, and pass through Humidity conditioner carries out Effective Regulation, is theed cement solidifies and humidity condition with monitoring at any time.
Detailed description of the invention
By reading the following detailed description of the preferred embodiment, various other advantages and benefits are common for this field Technical staff will become clear.The drawings are only for the purpose of illustrating a preferred embodiment, and is not considered as to the present invention Limitation.And throughout the drawings, the same reference numbers will be used to refer to the same parts.In the accompanying drawings:
Fig. 1 is a kind of structural block diagram of specific embodiment of the monitoring system provided by the present invention based on video technique;
Fig. 2 is a kind of flow chart of specific embodiment of the monitoring method provided by the present invention based on video technique.
Appended drawing reference
1 is controller, and 11 be main control unit, and 12 comparing units, 13 be storage unit, and 14 be display unit, and 15 be communication unit, 16 be alarm unit;
2 be remote control center;
3 be the first camera;
4 be second camera;
5 be temperature sensor;
6 be humidity sensor.
Specific embodiment
The illustrative embodiments of the disclosure are more fully described below with reference to accompanying drawings.Although showing this public affairs in attached drawing The illustrative embodiments opened, it being understood, however, that may be realized in various forms the disclosure without the reality that should be illustrated here The mode of applying is limited.It is to be able to thoroughly understand the disclosure on the contrary, providing these embodiments, and can be by this public affairs The range opened is fully disclosed to those skilled in the art.
Referring to FIG. 1, Fig. 1 is monitoring system a kind of specific embodiment provided by the present invention based on video technique Structural block diagram.
In a specific embodiment, Fig. 1 provided by the present invention is provided by the present invention based on video technique A kind of structural block diagram of specific embodiment of monitoring system, including the controller 1 being electrically connected to each other and acquisition component, the control Device 1 and remote control center 2 are wirelessly connected, and the acquisition component includes the first camera 3 being installed in construction site and peace The second camera 4 on object surface is poured loaded on cement, first camera 3 for acquiring in the preset range of construction site in real time The first image information, the second camera 4 be thermal imaging system, the second camera 4 in real time acquire compartment in Second image information, the first image information and second image information pass through respectively the controller 1 be transmitted to it is described Remote control center 2;The controller 1 enters the personnel in the preset range of construction site by the first image Information Authentication Identity judge that cement pours object surface by second image information to control the starting of alarm and temperature control device Temperature, to control the starting of temperature control device.
In above system, the first camera 3 is installed on a certain fixed position in building site, when sensing that someone enters building site model When enclosing interior, controller 1 is carried out wireless communication with remote control center 2, and default personal information is transmitted to control by remote control center 2 In device 1 processed, the first camera 3 acquires the first image information, which is the facial information into site staff, control Facial information is compared device 1 processed with the facial information of the default personnel received, should when the result of comparison is not meet Personnel start temperature control device without response, while controller 1 issues alarm sound, and comparison result is fed back to long-range control by controller 1 Center 2 processed, remote control center 2 issue situation feedback result to spot dispatch personnel immediately, remind spot dispatch personnel in time The replacement and examination of carry out personnel;When the result of comparison meets, second camera 4 pours the case where progress of object surface to cement Video acquisition forms the second image information, and since second camera 4 is thermal imaging system, the second image information is the thermal map in compartment Picture, controller 1 is by the way that the second image information to be compared with preset temperature image, when the two comparison structure is inconsistent, temperature The adjustment that object surface temperature is poured to cement is realized in control device starting, or can start temperature control device above by the personnel of verifying, Until the result that the two compares is consistent.
It is to be appreciated that above-mentioned default personal information be for each job location be configured at least one it is corresponding The information (identity information and facial information) of the staff is acquired in advance and prestores by staff, when needing to carry out work When making, personnel's permission at the construction is only prior matched personnel, is entered so as to effectively avoid the occurrence of irrelevant personnel The case where construction site or malicious operation, occurs.
It should be pointed out that above-mentioned second camera 4 is thermal imaging system, the second image information collected is thermal image, Preset temperature image is similarly thermal image, and the thermal image and temperature value form data and curves, passes through different colors on thermal image Different temperatures is represented, when being compared, the thermal image of acquisition is compared with preset thermal image, it is cold and hot when occurring When uneven, which there is deviation, in two thermal images to be matched, to judge that cement pours the temperature anomaly on object surface, to open Dynamic temperature control device is intervened, and reminds staff.Meanwhile above-mentioned pre-set image be not it is fixed, according to theing cement solidifies Requirement and Location set, so as to effectively meet the versatility for the condition monitoring that thes cement solidifies.
It is further understood that, the controller 1 includes main control unit 11, comparing unit 12 and storage unit 13, described Main control unit 11 is electrically connected with the comparing unit 12 and the storage unit 13 respectively;The comparing unit 12 is by described first Image information is compared with default personal information, to judge the identity of personnel, the comparing unit 12 by the second image information with Preset temperature image compares, to judge that cement pours the temperature on object surface;The main control unit 11 is for receiving the comparison The judging result of unit 12, and control according to the judging result start and stop of the temperature control device;The storage unit 13 is used for Store the default personal information and the preset temperature image.Above-mentioned main control unit 11 is communicated with remote control center 2, Main control unit 11 is in real time by the first image information, the second image information, for the judging result and needle of the formation of the first image information Remote control center 2 is uploaded to the judging result that the second image information is formed, while main control unit 11 receives long-range control list The default personal information and preset temperature information that member is sent, and the storage that default personal information and preset temperature information are prestored is single In member 13.
When needing the identity to the personnel entered in the preset range of construction site to verify, the acquisition of the first camera 3 First image information (personnel's present image information), comparing unit 12 calls default personal information, and the two is compared, When the first image information is consistent with default personal information, the authentication of personnel passes through, and can carry out related start and stop temperature control The operation of device, when the first image information and default personal information are inconsistent, the authentication of personnel does not pass through, main control unit Judging result is fed back to remote controllers 1 by 11, and remote controllers 1 feed back the situation to spot dispatch personnel, supervises live tune Degree personnel carry out field verification processing.
After the personal identity authentication entered in the preset range of construction site passes through, second camera 4 is to the feelings in compartment Condition carries out video acquisition and forms the second image information, and since second camera 4 is thermal imaging system, the second image information is poured for cement Build the thermal image on object surface, comparing unit calls preset temperature image, by by the second image information and preset temperature image into Row compares, and when the two comparison result is inconsistent, the adjustment that object surface temperature is poured to cement is realized in temperature control device starting, until The result that the two compares is consistent.
Further, the controller 1 further includes the communication unit 15 being electrically connected respectively with the main control unit 11 and determines Bit location, the communication unit 15 are wirelessly connected by 4G network and the remote control center 2, and the positioning unit is for real When collector location information (specifically, which is the personnel after being verified, in practice can be by being related Personnel provide locator or the mode of alignment code is realized).First image information and the second figure can be realized by using 4G network As the high efficiency of transmission of information, to guarantee the real-time of monitoring, it can be realized by positioning unit and personnel positioned in real time, To guarantee the effective monitoring to location of personnel.
It should be pointed out that above-mentioned positioning unit is GPS module, the module locating effect is good, can be improved the essence of monitoring True degree.
Further, the controller 1 further includes the display unit 14 being electrically connected respectively with the main control unit 11 and report Alert unit 16, the display unit 14 is for showing the judging result, and the alarm unit 16 is for issuing alarm signal.When When judgement is compared in first image information, the result of judgement is sent to display unit 14 and is shown in real time by main control unit 11 Show, so that personnel go and find out what's going in time, if judging result is abnormal, alarm unit 16 issues alarm signal;When When judgement is compared in second image information, the result of judgement is sent to display unit 14 and is shown in real time by main control unit 11 Show, if judging result is abnormal, alarm unit 16 issues alarm signal, and staff's cement is reminded to pour the temperature on object surface There are exceptions, to adopt an effective measure in time.
It should be pointed out that above-mentioned display unit 14 is display screen, which can show multipacket message simultaneously, wherein wrapping Temperature information, information of personnel etc. are included, above-mentioned alarm unit 16 is alarm, and when occurring abnormal, which issues buzzing Sound is to effectively remind staff unusual condition occur.
The temperature control device includes cooling unit, when the cement pour object surface temperature be higher than preset temperature and into When entering the identity of the personnel in the preset range of construction site and meeting default identity, the cooling unit starting is controlled;The temperature control Device further includes heat-insulation unit, is preset when the temperature that the cement pours object surface is lower than preset temperature and enters construction site When the identity of personnel in range meets default identity, the heat-insulation unit starting is controlled.The acquisition component further includes and institute The humidity sensor of controller electrical connection is stated, the humidity sensor is set to the cement and pours object surface, for acquiring State the humidity that cement pours object surface.So as to which according to the collected data, whether control cooling system starts, or control adds Warm device is kept the temperature.
Specifically understand, the acquisition component further include the temperature sensor 5 being electrically connected respectively with the controller 1, Humidity sensor 6, the temperature sensor 5 are set to the cement and pour object surface, pour object table for acquiring the cement The temperature in face, the humidity sensor 6 are set to the cement and pour object surface, pour object surface for acquiring the cement Humidity.The setting of temperature sensor 5 pours object surface in cement, and real-time monitoring cement pours the temperature on object surface, and by monitoring As a result controller 1 is fed back to, and is shown by display unit 14, humidity sensor 6, which is arranged, pours object surface in cement, real When monitoring cement pour the humidity on object surface, and the result of monitoring is fed back into controller 1, and shown by display unit 14 Show that the temperature of feedback, the humidity of feedback are sent to remote control center 2 respectively by controller 1, enables remote control center 2 The information that cement pours object surface is further obtained, so that the precision of monitoring is further promoted.
It is shown it is to be appreciated that the numerical value monitored is directly carried out feedback by temperature sensor 5, realization pours cement The temperature on object surface is further monitored, and second camera 4 is avoided error occur when being judged, to improve monitoring Precision;It can be realized the humidity for pouring object surface to cement by setting humidity sensor 6 effectively to be monitored, exist to meet Humidity requirement during theing cement solidifies.
Specifically, 1 Electricity Federation of controller is connected to humidity conditioner, and the controller 1 pours object surface according to cement Humidity judge whether to start the humidity conditioner.When the cement that humidity sensor 6 is monitored pours the humidity on object surface When content is higher than the requirement of humidity, controller 1 starts humidity conditioner and realizes the dehumidification operation for pouring object surface to cement, from And reduce cement and pour object surface moisture, to improve the effect that thes cement solidifies.
Please refer to Fig. 1 and Fig. 2, wherein Fig. 2 is that the monitoring method provided by the present invention based on video technique is a kind of specific The flow chart of embodiment.
The present invention also provides a kind of monitoring methods based on video technique, pass through the above-mentioned monitoring based on video technique System is implemented, method includes the following steps:
S1: the personal information that acquisition is currently entering in the preset range of construction site;
S2: whether the personal information that judgement is currently entering in the preset range of construction site meets with preset personal information, if so, It is then transferred to S3, if it is not, feeding back judging result to remote control center, and issues alarm signal;
S3: acquisition cement pours the temperature and humidity on object surface;
S4: judge that cement pours the temperature on object surface and whether is in preset temperature section, judging result is shown and fed back To remote control center, when the temperature that cement pours object surface is not in preset temperature section or enters construction site preset range When interior personal information and preset personal information are not met, alarm signal is issued;
When the temperature that cement pours object surface is not in preset temperature section and enters personnel's letter in the preset range of construction site When breath meets with preset personal information, start temperature control device;
When the temperature that cement pours object surface is in preset temperature section and enters the personal information in the preset range of construction site When meeting with preset personal information, it is transferred to S5;
S5: judge that cement pours the humidity on object surface and whether is in default humidity section, judging result is shown and fed back It issues alarm signal when the humidity that cement pours object surface is not in default humidity section to remote control center and starts Humidity conditioner returns to S1 when the humidity that cement pours object surface is in default humidity section.
Monitoring system and method provided by the invention based on video technique, having the beneficial effect that compared with prior art
1, it can be realized by the first camera and the identity of the personnel entered in the preset range of construction site verified, avoid Irrelevant personnel enters the generation of the case where building site, meanwhile, it is capable to which the work whole process to staff is monitored, guarantee was constructed The effective monitoring of journey.
2, the heating power image for acquiring formation in real time by second camera is compared with preset heating power image, effectively supervises Survey cement pours object and situation uneven in temperature occurs, so as to guarantee the quality that thes cement solidifies.
3, when the temperature during theing cement solidifies occurs abnormal, effectively staff can be reminded to adopt by warning function Take requisite measure.
4, it can effectively realize that the humidity for pouring object to cement carries out effective monitoring by the way that humidity sensor is arranged, and pass through Humidity conditioner carries out Effective Regulation, is theed cement solidifies and humidity condition with monitoring at any time.
It should be understood that although multiple element, portion can be described using term first, second, third, etc. in the text Part, region, layer and/or section still these component, assembly units, region, layer and/or are limited by these terms than Duan Buying. These terms can only be used to distinguish a component, assembly unit, region, layer or section with another region, layer or section.Unless Context is it is manifestly intended that when otherwise the term and other numerical terms of such as " first ", " second " etc use in the text Sequence or order is not implied that.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, In the technical scope disclosed by the present invention, any changes or substitutions that can be easily thought of by anyone skilled in the art, It should be covered by the protection scope of the present invention.Therefore, protection scope of the present invention answers the protection model with claim Subject to enclosing.

Claims (10)

1. a kind of monitoring system based on video technique, including the controller and acquisition component being electrically connected to each other, which is characterized in that The controller and remote control center are wirelessly connected, and the acquisition component includes the first camera being installed in construction site With the second camera for being installed on cement and pouring object surface;
First camera is used to acquire the first image information in the construction site preset range in real time, and described first takes the photograph As collected the first image information is transmitted to the remote control center by the controller;
The second camera is thermal imaging system, the second figure that the second camera pours object surface for acquiring cement in real time As information, collected second image information of second camera is transmitted to the long-range control by the controller Center;
The controller enters the identity of the personnel in the preset range of construction site by the first image Information Authentication, so as to Control the starting of alarm and temperature control device;The controller judges that cement pours object surface by second image information Temperature, to control the starting of temperature control device.
2. the monitoring system according to claim 1 based on video technique, which is characterized in that the controller includes master control Unit, comparing unit and storage unit, the main control unit are electrically connected with the comparing unit and the storage unit respectively;
The comparing unit by the first image information compared with default personal information, it is default into construction site to judge The identity of personnel in range, the comparing unit by the second image information compared with preset temperature image, to judge cement Pour the temperature on object surface;
The main control unit is used to receive the judging result of the comparing unit, and controls the temperature control according to the judging result The start and stop of device;
The storage unit is for storing the default personal information and the preset temperature image.
3. the monitoring system according to claim 2 based on video technique, which is characterized in that the controller further includes point The communication unit and positioning unit not being electrically connected with the main control unit, the communication unit pass through 4G network and the long-range control Center processed is wirelessly connected, and the positioning unit carries the location information of the personnel of default personal information for acquiring in real time.
4. the monitoring system according to claim 3 based on video technique, which is characterized in that the controller further includes point The display unit and alarm unit not being electrically connected with the main control unit, the display unit for showing the judging result, The alarm unit is for issuing alarm signal.
5. the monitoring system according to claim 1 based on video technique, which is characterized in that the acquisition component further includes The temperature sensor being electrically connected with the controller, the temperature sensor is set to the cement and pours object surface, for adopting Collect the temperature that the cement pours object surface.
6. the monitoring system according to claim 5 based on video technique, which is characterized in that the temperature control device includes cold But unit, when the temperature that the cement pours object surface is higher than preset temperature and enters the personnel in the preset range of construction site Identity when meeting default identity, control the cooling unit starting.
7. the monitoring system according to claim 6 based on video technique, which is characterized in that the temperature control device further includes Heat-insulation unit, when the cement pours the temperature on object surface lower than preset temperature and enters the people in the preset range of construction site When the identity of member meets default identity, the heat-insulation unit starting is controlled.
8. the monitoring system according to claim 7 based on video technique, which is characterized in that the acquisition component further includes The humidity sensor being electrically connected with the controller, the humidity sensor is set to the cement and pours object surface, for adopting Collect the humidity that the cement pours object surface.
9. the monitoring system according to claim 7 based on video technique, which is characterized in that the controller Electricity Federation is connected to Humidity conditioner, the controller judge whether to start the humid control dress according to the humidity that the cement pours object surface It sets.
It is described in any item based on video technique by claim 1-9 10. a kind of monitoring method based on video technique Monitoring system is implemented, which is characterized in that method includes the following steps:
S1: the personal information that acquisition is currently entering in the preset range of construction site;
S2: whether the personal information that judgement is currently entering in the preset range of construction site meets with preset personal information, if so, It is then transferred to S3, if it is not, feeding back judging result to remote control center, and issues alarm signal;
S3: acquisition cement pours the temperature and humidity on object surface;
S4: judge that cement pours the temperature on object surface and whether is in preset temperature section, judging result is shown and fed back To remote control center, when the temperature that cement pours object surface is not in preset temperature section or enters construction site preset range When interior personal information and preset personal information are not met, alarm signal is issued;
When the temperature that cement pours object surface is not in preset temperature section and enters personnel's letter in the preset range of construction site When breath meets with preset personal information, start temperature control device;
When the temperature that cement pours object surface is in preset temperature section and enters the personal information in the preset range of construction site When meeting with preset personal information, it is transferred to S5;
S5: judge that cement pours the humidity on object surface and whether is in default humidity section, judging result is shown and fed back It issues alarm signal when the humidity that cement pours object surface is not in default humidity section to remote control center and starts Humidity conditioner returns to S1 when the humidity that cement pours object surface is in default humidity section.
CN201811363584.3A 2018-11-16 2018-11-16 Monitoring system and method based on video technology Active CN109547745B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811363584.3A CN109547745B (en) 2018-11-16 2018-11-16 Monitoring system and method based on video technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811363584.3A CN109547745B (en) 2018-11-16 2018-11-16 Monitoring system and method based on video technology

Publications (2)

Publication Number Publication Date
CN109547745A true CN109547745A (en) 2019-03-29
CN109547745B CN109547745B (en) 2021-01-19

Family

ID=65847591

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811363584.3A Active CN109547745B (en) 2018-11-16 2018-11-16 Monitoring system and method based on video technology

Country Status (1)

Country Link
CN (1) CN109547745B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111582188A (en) * 2020-05-11 2020-08-25 广东创成建设监理咨询有限公司 Concrete pouring side station supervision method based on artificial intelligence
CN112754096A (en) * 2020-12-28 2021-05-07 北京田一科技有限公司 Intelligent safety helmet
CN114613090A (en) * 2022-01-06 2022-06-10 湖南省正邦建设工程有限公司 Informationized monitoring method and construction method for asphalt concrete pavement

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101382457A (en) * 2008-10-14 2009-03-11 上海建工股份有限公司 Mass concrete temperature monitoring system and method based on GPRS
CN102681567A (en) * 2012-05-04 2012-09-19 天津大学 Concrete temperature remote monitoring system for concrete dam
CN203174477U (en) * 2012-12-27 2013-09-04 上海热像机电科技有限公司 Real-time temperature segregation detection system for asphalt concrete pavement course
CN103676997A (en) * 2013-10-16 2014-03-26 中国水利水电科学研究院 Large-volume concrete temperature monitoring method based on real-time monitoring data
CN105045307A (en) * 2015-08-20 2015-11-11 中国水利水电科学研究院 Full-process intelligent temperature control system and method for large-volume concrete
US20150379362A1 (en) * 2013-02-21 2015-12-31 Iee International Electronics & Engineering S.A. Imaging device based occupant monitoring system supporting multiple functions
CN105807339A (en) * 2016-04-29 2016-07-27 华能澜沧江水电股份有限公司 Alarming device and method for microclimate environment of roller-compacted concrete lift surface
CN107067696A (en) * 2017-05-22 2017-08-18 中国铁建大桥工程局集团有限公司 The temperature wireless monitoring system and method for a kind of winter construction concrete structure
CN107730428A (en) * 2017-10-17 2018-02-23 贾俊力 Job site intelligent monitoring administration system and its control method
CN107989634A (en) * 2017-12-29 2018-05-04 中国铁道科学研究院铁道建筑研究所 A kind of information-based monitoring system of tunnel lining trolley concrete cast
CN207420020U (en) * 2017-11-07 2018-05-29 沭阳县新生代木制品厂 A kind of building template that concrete is kept to be in air-setting

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101382457A (en) * 2008-10-14 2009-03-11 上海建工股份有限公司 Mass concrete temperature monitoring system and method based on GPRS
CN102681567A (en) * 2012-05-04 2012-09-19 天津大学 Concrete temperature remote monitoring system for concrete dam
CN203174477U (en) * 2012-12-27 2013-09-04 上海热像机电科技有限公司 Real-time temperature segregation detection system for asphalt concrete pavement course
US20150379362A1 (en) * 2013-02-21 2015-12-31 Iee International Electronics & Engineering S.A. Imaging device based occupant monitoring system supporting multiple functions
CN103676997A (en) * 2013-10-16 2014-03-26 中国水利水电科学研究院 Large-volume concrete temperature monitoring method based on real-time monitoring data
CN105045307A (en) * 2015-08-20 2015-11-11 中国水利水电科学研究院 Full-process intelligent temperature control system and method for large-volume concrete
CN105807339A (en) * 2016-04-29 2016-07-27 华能澜沧江水电股份有限公司 Alarming device and method for microclimate environment of roller-compacted concrete lift surface
CN107067696A (en) * 2017-05-22 2017-08-18 中国铁建大桥工程局集团有限公司 The temperature wireless monitoring system and method for a kind of winter construction concrete structure
CN107730428A (en) * 2017-10-17 2018-02-23 贾俊力 Job site intelligent monitoring administration system and its control method
CN207420020U (en) * 2017-11-07 2018-05-29 沭阳县新生代木制品厂 A kind of building template that concrete is kept to be in air-setting
CN107989634A (en) * 2017-12-29 2018-05-04 中国铁道科学研究院铁道建筑研究所 A kind of information-based monitoring system of tunnel lining trolley concrete cast

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111582188A (en) * 2020-05-11 2020-08-25 广东创成建设监理咨询有限公司 Concrete pouring side station supervision method based on artificial intelligence
CN111582188B (en) * 2020-05-11 2022-04-26 广东创成建设监理咨询有限公司 Concrete pouring side station supervision method based on artificial intelligence
CN112754096A (en) * 2020-12-28 2021-05-07 北京田一科技有限公司 Intelligent safety helmet
CN112754096B (en) * 2020-12-28 2024-04-09 北京田一科技有限公司 Intelligent safety helmet
CN114613090A (en) * 2022-01-06 2022-06-10 湖南省正邦建设工程有限公司 Informationized monitoring method and construction method for asphalt concrete pavement

Also Published As

Publication number Publication date
CN109547745B (en) 2021-01-19

Similar Documents

Publication Publication Date Title
CN109547745A (en) A kind of monitoring system and method based on video technique
US10861317B2 (en) Wearable smart gateway
WO2017017984A1 (en) Moving body identification system and identification method
US10237518B2 (en) Mobile body system, control apparatus and method for controlling a mobile body
JP2002366223A (en) System and method for remote management of equipment operating parameter
CN109278681A (en) A kind of Research on Vehicle Remote Monitoring System Based on GPRS
CN109189132A (en) A kind of machine room monitoring system and method
CN101707528A (en) Method for transmitting alarm data of centralized monitoring system
CN106657881A (en) Multi-dimensional video monitoring system
WO2022166775A1 (en) Elevator accessory authentication method and system, and server and storage medium
KR20140125934A (en) System and method for management for livestock delivery room
CN205211126U (en) Vibrations warning system
CN107293946B (en) Terminal box of transformer substation monitors system
JP2014040221A (en) Video monitoring system
CN108415387A (en) A kind of safety control system and method for controlling security
TW202105206A (en) Verification system and verification method
JP2013192202A (en) Work image monitoring system
JP5925141B2 (en) Engineering tool monitoring system
JP5743648B2 (en) Management device and equipment management system
CN108256502A (en) Security system based on image procossing
CN109413386B (en) Temperature monitoring method and system
CN113203488A (en) Temperature and humidity monitoring alarm processing method and device in different application environments
TWM500955U (en) Intelligent disaster monitoring strained joint defense system
JP2015032995A (en) Video monitoring system
CN109815443A (en) A kind of statistical estimation system of work safety accident

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200303

Address after: 212000 Derun Building, No. 20 Huangshan South Road, Zhenjiang City, Jiangsu Province, 9th Floor

Applicant after: Jiangsu Gaozhi Project Management Co., Ltd.

Address before: 212000 Derun Building, No. 20 Huangshan South Road, Zhenjiang City, Jiangsu Province, 9th Floor

Applicant before: Jiangsu Gaozhi Project Management Co., Ltd.

Applicant before: ZHEJIANG A & F University

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant