- Prior art keywords
- surveying
- grid
- subregion
- survey
- case
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063118—Staff planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q40/00—Finance; Insurance; Tax strategies; Processing of corporate or income taxes
- G06Q40/08—Insurance
Abstract
The present invention is suitable for Internet technical field, provide a kind of method, apparatus and terminal device based on the task distribution for surveying grid, the described method includes: obtaining the current case information of current event, the current case information is included at least currently to be in danger and place and currently be reported a case to the security authorities the time;It is currently reported a case to the security authorities the time according to described, acquisition is corresponding with the time of currently reporting a case to the security authorities to survey grid;According to the place of being currently in danger determine described in survey the target in grid and survey subregion;The corresponding task of surveying of the current event is dispatched to the person of surveying that the target surveys subregion.The present invention surveys grid by the way that acquisition is corresponding with the time of currently reporting a case to the security authorities, and then according to the assignment that grid survey task is surveyed, improves the reasonability for surveying task assignment.
Description
Technical field
The invention belongs to Internet technical field more particularly to a kind of methods distributed based on the surveying grid of the task, dress
It sets and terminal device.
Background technique
Vehicle insurance industry forms in such a way that municipal administration region divides and surveys grid at present, then using survey grid into
Row surveys the assignment of task.
But usually grid is surveyed using same from beginning to end, can not dynamic adjustment effectively be carried out to surveying grid.
It is thus in the prior art to assign not reasonable using surveying grid and survey task, it needs to improve.
Summary of the invention
In view of this, the embodiment of the invention provides a kind of method, apparatus based on the task distribution for surveying grid and ends
End equipment assigns not reasonable technical problem to solve the prior art task of surveying.
The first aspect of the embodiment of the present invention provides a kind of method distributed based on the surveying grid of the task, comprising:
Obtain the current case information of current event, the current case information includes at least the place and current of being currently in danger
It reports a case to the security authorities the time;
It is currently reported a case to the security authorities the time according to described, acquisition is corresponding with the time of currently reporting a case to the security authorities to survey grid;
According to the place of being currently in danger determine described in survey the target in grid and survey subregion;
The corresponding task of surveying of the current event is dispatched to the person of surveying that the target surveys subregion.
The second aspect of the embodiment of the present invention provides a kind of based on the task assigned unit for surveying grid, comprising:
First obtains module, and for obtaining the current case information of current event, the current case information is included at least
It is currently in danger and place and currently reports a case to the security authorities the time;
Second obtains module, for currently reporting a case to the security authorities the time according to described, obtains look into corresponding with the time of currently reporting a case to the security authorities
Survey grid;
Determining module, for according to the place of being currently in danger determine described in survey the target in grid and survey subregion;
Dispatch module surveys looking into for subregion for the corresponding task of surveying of the current event to be dispatched to the target
The person of surveying.
The third aspect of the embodiment of the present invention provides a kind of terminal device, including memory and processor, described to deposit
The computer program that can be run on the processor is stored in reservoir, when the processor executes the computer program,
Realize following steps:
Obtain the current case information of current event, the current case information includes at least the place and current of being currently in danger
It reports a case to the security authorities the time;
It is currently reported a case to the security authorities the time according to described, acquisition is corresponding with the time of currently reporting a case to the security authorities to survey grid;
According to the place of being currently in danger determine described in survey the target in grid and survey subregion;
The corresponding task of surveying of the current event is dispatched to the person of surveying that the target surveys subregion.
The fourth aspect of the embodiment of the present invention provides a kind of computer readable storage medium, the computer-readable storage
Media storage has computer program, and the computer program realizes following steps when being executed by processor:
Obtain the current case information of current event, the current case information includes at least the place and current of being currently in danger
It reports a case to the security authorities the time;
It is currently reported a case to the security authorities the time according to described, acquisition is corresponding with the time of currently reporting a case to the security authorities to survey grid;
According to the place of being currently in danger determine described in survey the target in grid and survey subregion;
The corresponding task of surveying of the current event is dispatched to the person of surveying that the target surveys subregion.
In the embodiment of the present invention, by obtaining the current case information of current event, then obtains and currently report a case to the security authorities the time
It is corresponding to survey grid, it is last according to the assignment that grid survey task is surveyed, improve the reasonability for surveying task assignment.
Detailed description of the invention
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to embodiment or description of the prior art
Needed in attached drawing be briefly described, it should be apparent that, the accompanying drawings in the following description is only of the invention some
Embodiment for those of ordinary skill in the art without any creative labor, can also be according to these
Attached drawing obtains other attached drawings.
Fig. 1 is a kind of implementation flow chart of method distributed based on the surveying grid of the task provided in an embodiment of the present invention;
Fig. 2 is the implementation process of another method distributed based on the surveying grid of the task provided in an embodiment of the present invention
Figure;
Fig. 3 is the implementation process of another method distributed based on the surveying grid of the task provided in an embodiment of the present invention
Figure;
Fig. 4 is a kind of structural block diagram based on the task assigned unit for surveying grid provided in an embodiment of the present invention;
Fig. 5 is the schematic diagram of terminal device provided in an embodiment of the present invention.
Specific embodiment
In being described below, for illustration and not for limitation, the tool of such as particular system structure, technology etc is proposed
Body details, to understand thoroughly the embodiment of the present invention.However, it will be clear to one skilled in the art that there is no these specific
The present invention also may be implemented in the other embodiments of details.In other situations, it omits to well-known system, device, electricity
The detailed description of road and method, in case unnecessary details interferes description of the invention.
In order to illustrate technical solutions according to the invention, the following is a description of specific embodiments.
Fig. 1 shows the implementation process of the method provided in an embodiment of the present invention distributed based on the surveying grid of the task, should
Method flow includes step S101 to S104.This method is applicable to survey the situation of task assignment.This method is by base
It is executed in the task assigned unit for surveying grid, it is described terminal is configured at based on the task assigned unit for surveying grid to set
It is standby, it can be implemented by software and/or hardware.Terminal device includes but is not limited to server.The specific implementation principle of each step is as follows.
S101, obtains the current case information of current event, and the current case information includes at least place of being currently in danger
With currently report a case to the security authorities the time.
In the embodiment of the present invention, current event can be the vehicle insurance case currently got, for vehicle insurance case to be assigned.
In addition, current event can also include other cases, such as produce dangerous case, people's guarantor's case, even criminal case etc..With it is subsequent
The historical events that refers to is different, and historical events can be the vehicle insurance case assigned, including survey setting loss or
And complete to survey the vehicle insurance case of setting loss.In addition, historical events can also include other cases, such as produce dangerous case, people guarantor
Case, even criminal case etc..
Current case information is the case information of corresponding current event, when including at least place of being currently in danger with currently reporting a case to the security authorities
Between.The current place where the accident occurred that place is current event of being in danger;The current time of reporting a case to the security authorities is insurer's reporting a case to the security authorities for current event
Time.
It is self-service when insurer is by dialing phone number or logging in the default application program of its all intelligent terminal
When reporting a case to the security authorities event, by case information reporting to server and in database purchase, server gets current thing at this time
The current case information of part.It then further include that server passes through language if user reports a case to the security authorities to event by dialing phone number
The step of sound identification technology converts speech information into text information.
Illustratively, for example, when insurer Zhang San meets with vehicle insurance case, by the default application for logging in its terminal device
Program carries out reporting a case to the security authorities for vehicle insurance case, and case information relevant to vehicle insurance case is committed to server, at this point, server obtains
It is subsequent that the corresponding assignment for surveying task of vehicle insurance case is carried out according to the case information to case information.
For another example, when insurer Li Si meets with vehicle insurance case, reporting a case to the security authorities for vehicle insurance case is carried out by dialing phone number, it will
By voice transfer to phone customer service, the voice messaging that phone customer service will acquire is converted into case information relevant to vehicle insurance case
Text is committed to server, at this point, server gets case information, it is subsequent corresponding according to case information progress vehicle insurance case
The assignment for surveying task.
S102 currently reports a case to the security authorities the time according to described, and determination is corresponding with the time of currently reporting a case to the security authorities to survey grid.
In the embodiment of the present invention, the grid of surveying is that event affiliated area surveys grid.For example, Enterprises of Futian District
Survey grid or In Luohu District of Shenzhen Municipal survey grid or Shenzhen survey grid etc..Each affiliated area surveys net
Lattice be it is multiple, each survey grid include it is multiple survey subregion, each survey subregion and be both provided with the corresponding person of surveying.
Server be previously stored with each region correspondence it is in different time periods it is multiple survey grid, for the same area
Difference surveys grid, divide to survey subregion not identical.According to currently reporting a case to the security authorities the time, acquisition is described currently to report a case to the security authorities the time pair
That answers surveys grid, surveys network distribution so as to basis and surveys task.
Illustratively, 5 periods: 00:00-07:00,07:00-09:00,09:00-16:00,16 are divided within one day:
00-20:00 and 20:00-24:00.It is respectively arranged with for 5 periods and corresponding surveys grid A, B, C, D and E.If current
The time report a case to the security authorities as 09:50, then acquisition is corresponding with the time of reporting a case to the security authorities surveys grid C.
As an embodiment of the present invention, as shown in Fig. 2, step 102, currently reports a case to the security authorities the time according to described, obtain with it is described
Currently report a case to the security authorities the time it is corresponding survey grid, including step 201 is to 202.
S201 determines the target time section that the time falls into of currently reporting a case to the security authorities.
S202, obtains that the target time section is corresponding to survey grid as the time of currently reporting a case to the security authorities and corresponding survey net
Lattice.
Illustratively, if event affiliated area is divided into 5 in one day for In Luohu District of Shenzhen Municipal for In Luohu District of Shenzhen Municipal
Period: 00:00-07:00,07:00-09:00,09:00-16:00,16:00-20:00 and 20:00-24:00;When for 5
Between section be respectively arranged with and corresponding survey grid A, B, C, D and E.If the time of currently reporting a case to the security authorities is 09:50, the target time section fallen into
For 09:00-16:00, target time section correspondence surveys grid C, then will survey grid C and corresponding survey as the time of currently reporting a case to the security authorities
Grid.
S103, according to the place of being currently in danger determine described in survey the target in grid and survey subregion.
In the embodiment of the present invention, be currently in danger place based on described, and according to it is described survey that grid includes multiple survey
Subregion determines that the target belonging to place of being currently in danger surveys subregion.
Illustratively, if survey that grid C includes it is multiple survey subregion be respectively C1, C2, C3 ... and C10, when
Before place of being in danger belong to and survey subregion C6, it is determined that surveying subregion C6 is that target surveys subregion.
The corresponding task of surveying of the current event is dispatched to the person of surveying that the target surveys subregion by S104.
In the embodiment of the present invention, since each subregion of surveying is provided with the corresponding person of surveying, thus, by the task of surveying point
Task the person of surveying that the target surveys subregion.
Server surveys end for what the current case information of current event pushed to that target surveys the corresponding person of surveying of subregion
End after the person of surveying knows current event by surveying terminal, carries out subsequent surveying setting loss.Surveying terminal can be mobile phone or plate
The Intelligent mobile equipments such as computer.
Optionally, if step 104 include: the target survey subregion the person of surveying be one, by the current thing
The corresponding task of surveying of part is dispatched to the person of surveying;If the person of surveying that the target surveys subregion is multidigit, according to pre-
If scheduling rule the corresponding task of surveying of the current event is dispatched to the person of surveying.
The task of surveying of event is distributed to the person of surveying by server, and each person of surveying is corresponding with one and surveys task queue, will
Being distributed for the task of surveying is added to this and surveys in task queue.The task of surveying can be vehicle insurance and survey task, it is of course also possible to
It is that others need the Claims Resolution for carrying out dam site investigation to survey task.Each person of surveying holds one for surveying with what server communicated
Terminal is surveyed terminal with positioning function, after the person of surveying terminates to survey every time, can be sent out by surveying terminal to server
It send END instruction, such as is operated in surveying in operation interface of surveying that terminal shows, completed pair by clicking task of surveying
The control answered is to send END instruction to server.Survey in task queue corresponding for each person of surveying surveys task,
If be over it is a certain survey task, this is surveyed in task queue and deletes the corresponding task of surveying in the server
It removes, so as to the subsequent assignment for survey to the person of surveying task.
Optionally, server survey according to preset scheduling rule the assignment of task, comprising: obtain affair character and
The person's of surveying feature matches the affair character and the person's of surveying feature, selects the person of surveying for meeting preset schedule condition
Survey the assignment of task.
Wherein, affair character includes but is not limited to: the affiliated insurance company of current event, place of being in danger, accident pattern etc.;It looks into
The person's of surveying feature includes but is not limited to: the person's of surveying credit grade surveys task amount, current location etc..
For example, surveying for the current event is appointed if place of being in danger described in the current location distance for the person of surveying is nearest
Business pushes to that described the person of surveying is corresponding surveys terminal.
For another example, if the task amount of surveying for the person of surveying is less than preset task amount threshold value (such as 3), and the present bit for the person of surveying
It is nearest to set place of being in danger described in distance, then the task of surveying of the current event pushes to described the person of surveying is corresponding surveys end
End.
For another example, it if the affiliated insurance company for the person of surveying is identical as the affiliated insurance company of event, and surveys task amount and is less than
Preset task amount threshold value, such as 3, and the current location for the person of surveying is nearest apart from the place of being currently in danger, then works as by described in
The task of surveying of preceding event pushes to that described the person of surveying is corresponding surveys terminal.
In the embodiment of the present invention, by obtaining the current case information of current event, then obtains and currently report a case to the security authorities the time
It is corresponding to survey grid, it is last according to the assignment that grid survey task is surveyed, improve the reasonability for surveying task assignment.
On the basis of the above embodiments, the present invention also provides it is a kind of based on survey grid task distribute method,
Existing single grid of surveying is adjusted, multiple and different is looked into so that the correspondence for generating the embodiment of the present invention is in different time periods
Grid is surveyed, to realize the rationalization to task assignment is surveyed.As shown in figure 3, based on the method that the surveying grid of the task is distributed,
It further include step 301 to 304 before step S101.
S301, obtains the history case information of historical events, and the history case information includes at least history and is in danger place
It reports a case to the security authorities the time with history.
As previously mentioned, the historical events is different from current event, it is allocated event.
Illustratively, in available preset time period, for example, one week in or one month in, historical events history case
Part information.
S302 determines hot spot in several preset time periods for including from one day according to the history case information
Period and non-hot period, and will in time continuous hot spot period and non-hot period splice respectively,
Generate several target time sections.
Wherein, it is reported a case to the security authorities the time according to the history, the history for calculating several preset time periods for including in one day is reported a case to the security authorities
Quantity, such as with 1 hour duration for a preset time period, include 24 preset time periods within 1 day, 00:00-01:00,01:
00-02:00 ... and 23:00-24:00.If the history is reported a case to the security authorities, quantity is greater than or equal to preset quantity threshold value, it is determined that
The preset time period is the hot spot period;If the history is reported a case to the security authorities, quantity is less than preset quantity threshold value, it is determined that described default
Period is the non-hot period.It should be noted that preset quantity threshold value is empirical value, it can according to need and select setting
It sets.
Then will in time continuous hot spot period and non-hot period splice respectively, generate several mesh
Mark the period.For example, if the hot spot period is 07:00-08:00,08:00-09:00,16:00-17:00,17:00- in one day
18:00,18:00-19:00,19:00-20:00 and 23:00-24:00, remaining is the non-hot period, then will continuous heat
Point period and non-hot period are spliced respectively, generate six target time sections, respectively 00:00-07:00 is (non-thermal
Point the period), 07:00-09:00 (hot spot period), 09:00-16:00 (non-hot period), 16:00-20:00 (hot spot
Period), 20:00-23:00 (non-hot period) and 23:00-24:00 (hot spot period).
S303 is obtained and is initially surveyed grid, and from it is described initially survey that grid includes multiple initially survey in subregion
Determine to correspond to the hot spot subregion of each target time section.
Wherein, the grid of initially surveying be that grid is surveyed in some region of correspondence, and initially to survey grid include several
Subregion initially is surveyed, subregion is each initially surveyed and is correspondingly arranged on the person of surveying.
The grid of initially surveying can survey grid for some region used under the prior art, can also be other
Grid is surveyed in any way initialization.Surveying several initial subregions of surveying that grid includes can be to draw some region
It is divided into the molecular domains such as several or irregular subregion.The present invention not limits the division for the subregion for initially surveying grid
System.
It is in danger place according to the history of each target time section, described is gone through in described initially survey in grid to each
History place of being in danger is labeled;According to the obtained mark point quantity and area for initially surveying subregion, calculating is each initially looked into
Subregion is surveyed in the density of being in danger of each target time section.If the density of being in danger is greater than or equal to default density threshold of being in danger,
Then determine that the subregion of initially surveying is hot spot subregion;If the density of being in danger is less than default density threshold of being in danger, really
The fixed subregion of initially surveying is non-hot subregion.It, can be with it should be noted that default density threshold of being in danger is empirical value
Selection setting is carried out as needed.
Optionally, the density of being in dangerWherein, NumaccidentIt indicates initially to survey subregion packet
The mark point quantity included, AreadisctrictIndicate the area for initially surveying subregion.Illustratively, described initially to survey subregion
Area be with the area on the map of the scale of 1:400 ten thousand, unit cm2。
In other embodiments, if each initially surveying subregion and being correspondingly arranged on the multidigit person of surveying, it is described be in danger it is close
DegreeWherein, N indicates initially to survey the corresponding person's of the surveying quantity of subregion, NumaccidentIt indicates just
Beginning surveys the mark point quantity that subregion includes, AreadisctrictIndicate the area for initially surveying subregion, it is illustratively, described
The area for initially surveying subregion is with the area on the map of the scale of 1:400 ten thousand, unit cm2。
S304, corresponding each target time section are initially surveyed according to the hot spot subregion determined described
Grid is adjusted generation and surveys grid.
Wherein, to it is described initially survey grid and be adjusted generation survey grid, comprising: reduce and described initially survey grid
Described in the area of hot spot subregion correspondingly increase the area of the non-hot subregion adjacent with the hot spot subregion.
The area for initially surveying hot spot subregion described in grid is reduced, correspondingly, is increased and the hot spot sub-district
The area of the adjacent non-hot subregion in domain, including, reduce the area for initially surveying hot spot subregion described in grid, phase
Ying Di, increases the area of the non-hot subregion adjacent with the hot spot subregion, initially looks into until having adjusted the several of area
That surveys subregion is in danger density within a preset range.
By this set, so that the several density of being in danger for initially surveying subregion for having adjusted area are similar.For example,
The absolute value of several density differences that are in danger for initially surveying subregion for having adjusted area is less than preset value.It should be noted that
Preset value is empirical value, can according to need and carries out selection equipment.
Previous embodiment is connected, if corresponding generate six target time sections, corresponds to six target time sections generated, really
The corresponding hot spot subregion of each target time section is made, different adjustment is carried out to initial mesh, to generate six corresponding
Six of target time section survey grid.Available grid of surveying is with regard to there are six in such one day, thus surveys grid at one day
In can carry out dynamic adjustment, improve the reasonability for surveying assignment.
On the basis of above-mentioned embodiment illustrated in fig. 3, further include, by each target time section and the object time
The corresponding network of surveying of section is associated storage.
By by target time section and surveying network and being associated storage, use is transferred for subsequent.
It should be understood that the size of the serial number of each step is not meant that the order of the execution order in above-described embodiment, each process
Execution sequence should be determined by its function and internal logic, the implementation process without coping with the embodiment of the present invention constitutes any limit
It is fixed.
Corresponding to the method distributed described in foregoing embodiments based on the surveying grid of the task, Fig. 4 shows of the invention real
The structural block diagram based on the task assigned unit for surveying grid for applying example offer illustrates only and this hair for ease of description
The relevant part of bright embodiment.
Referring to Fig. 4, should include: based on the task assigned unit for surveying grid
First obtains module 41, and for obtaining the current case information of current event, the current case information is at least wrapped
It includes currently to be in danger and place and currently report a case to the security authorities the time;
Second obtains module 42, for currently being reported a case to the security authorities the time according to described, obtains corresponding with the time of currently reporting a case to the security authorities
Survey grid;
Determining module 43, for according to the place of being currently in danger determine described in survey the target in grid and survey sub-district
Domain;
Dispatch module 44 surveys subregion for the corresponding task of surveying of the current event to be dispatched to the target
The person of surveying.
Fig. 5 is the schematic diagram for the terminal device that one embodiment of the invention provides.As shown in figure 5, the terminal of the embodiment is set
Standby 5 include: processor 50, memory 51 and are stored in the meter that can be run in the memory 51 and on the processor 50
Calculation machine program 52, such as survey the program of task assignment.The processor 50 is realized above-mentioned when executing the computer program 52
The step in embodiment of the method distributed based on the surveying grid of the task, such as step S101 to S104 shown in FIG. 1.Alternatively,
The processor 50 realizes the function of each module/unit in above-mentioned each Installation practice, example when executing the computer program 52
The function of module 41 to 44 as shown in Figure 4.
Illustratively, the computer program 52 can be divided into one or more module/units, it is one or
Multiple module/units are stored in the memory 51, and are executed by the processor 50, to complete the present invention.Described one
A or multiple module/units can be the series of computation machine program instruction section that can complete specific function, which is used for
Implementation procedure of the computer program 52 in the terminal device 5 is described.
The terminal device 5 can be server etc..The terminal device 5 may include, but be not limited only to, processor 50,
Memory 51.It will be understood by those skilled in the art that Fig. 5 is only the example of terminal device 5, do not constitute to terminal device 5
Restriction, may include perhaps combining certain components or different components, such as institute than illustrating more or fewer components
Stating terminal device can also include input-output equipment, network access equipment, bus etc..
Alleged processor 50 can be central processing unit (Central Processing Unit, CPU), can also be
Other general processors, digital signal processor (Digital Signal Processor, DSP), specific integrated circuit
(Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field-
Programmable Gate Array, FPGA) either other programmable logic device, discrete gate or transistor logic,
Discrete hardware components etc..General processor can be microprocessor or the processor is also possible to any conventional processor
Deng.
The memory 51 can be the internal storage unit of the terminal device 5, such as the hard disk or interior of terminal device 5
It deposits.The memory 51 is also possible to the External memory equipment of the terminal device 5, such as be equipped on the terminal device 5
Plug-in type hard disk, intelligent memory card (Smart Media Card, SMC), secure digital (Secure Digital, SD) card dodge
Deposit card (Flash Card) etc..Further, the memory 51 can also both include the storage inside list of the terminal device 5
Member also includes External memory equipment.The memory 51 is for storing needed for the computer program and the terminal device
Other programs and data.The memory 51 can be also used for temporarily storing the data that has exported or will export.
It is apparent to those skilled in the art that for convenience of description and succinctly, only with above-mentioned each function
Can unit, module division progress for example, in practical application, can according to need and by above-mentioned function distribution by different
Functional unit, module are completed, i.e., the internal structure of described device is divided into different functional unit or module, more than completing
The all or part of function of description.Each functional unit in embodiment, module can integrate in one processing unit, can also
To be that each unit physically exists alone, can also be integrated in one unit with two or more units, it is above-mentioned integrated
Unit both can take the form of hardware realization, can also realize in the form of software functional units.In addition, each function list
Member, the specific name of module are also only for convenience of distinguishing each other, the protection scope being not intended to limit this application.Above system
The specific work process of middle unit, module, can refer to corresponding processes in the foregoing method embodiment, and details are not described herein.
In the above-described embodiments, it all emphasizes particularly on different fields to the description of each embodiment, is not described in detail or remembers in some embodiment
The part of load may refer to the associated description of other embodiments.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit
The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple
In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme
's.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit
It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list
Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated module/unit be realized in the form of SFU software functional unit and as independent product sale or
In use, can store in a computer readable storage medium.Based on this understanding, the present invention realizes above-mentioned implementation
All or part of the process in example method, can also instruct relevant hardware to complete, the meter by computer program
Calculation machine program can be stored in a computer readable storage medium, the computer program when being executed by processor, it can be achieved that on
The step of stating each embodiment of the method.
Embodiment described above is merely illustrative of the technical solution of the present invention, rather than its limitations;Although referring to aforementioned reality
Applying example, invention is explained in detail, those skilled in the art should understand that: it still can be to aforementioned each
Technical solution documented by embodiment is modified or equivalent replacement of some of the technical features;And these are modified
Or replacement, the spirit and scope for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution should all
It is included within protection scope of the present invention.
Claims (10)
1. a kind of method distributed based on the surveying grid of the task characterized by comprising
The current case information of current event is obtained, the current case information is included at least currently to be in danger and place and currently be reported a case to the security authorities
Time;
It is currently reported a case to the security authorities the time according to described, acquisition is corresponding with the time of currently reporting a case to the security authorities to survey grid;
According to the place of being currently in danger determine described in survey the target in grid and survey subregion;
The corresponding task of surveying of the current event is dispatched to the person of surveying that the target surveys subregion.
2. the method as described in claim 1, which is characterized in that described currently to be reported a case to the security authorities the time according to described, acquisition is worked as with described
Before time of reporting a case to the security authorities corresponding survey grid, comprising:
Determine the target time section that the time falls into of currently reporting a case to the security authorities;
Obtain that the target time section is corresponding to survey grid as the time of currently reporting a case to the security authorities and corresponding survey grid.
3. method according to claim 2, which is characterized in that described to be dispatched to the corresponding task of surveying of the current event
The target surveys the person of surveying of subregion, comprising:
If the person of surveying that the target surveys subregion is one, the corresponding task of surveying of the current event is dispatched to institute
State the person of surveying;If the person of surveying that the target surveys subregion is multidigit, according to preset scheduling rule by the current thing
The corresponding task of surveying of part is dispatched to the person of surveying.
4. the method as described in claim 1, which is characterized in that further include:
Obtain the history case information of historical events, the history case information includes at least that history is in danger place and history is reported a case to the security authorities
Time;
According to the history case information, hot spot period and non-is determined in several preset time periods for including from one day
The hot spot period, and will in time continuous hot spot period and non-hot period splice respectively, generate several
Target time section;
It obtains and initially surveys grid, and initially survey multiple initially survey that grid includes from described and determine to correspond in subregion
The hot spot subregion of each target time section;
Corresponding each target time section carries out the grid of initially surveying according to the hot spot subregion determined
Adjustment generates and surveys grid.
5. method as claimed in claim 4, which is characterized in that it is described to it is described initially survey grid and be adjusted generation survey
Grid, comprising:
The area for initially surveying hot spot subregion described in grid is reduced, correspondingly, is increased and the hot spot subregion phase
Grid is surveyed in the area of adjacent non-hot subregion, generation.
6. method as described in claim 4 or 5, which is characterized in that it is described from it is described initially survey that grid includes it is multiple just
Beginning surveys in subregion the hot spot subregion for determining to correspond to each target time section, comprising:
It is in danger place according to the history of each target time section, initially surveys in grid to go out each history described
Strategical vantage point point is labeled;
According to the obtained mark point quantity and area for initially surveying subregion, calculating each initially surveys subregion in each mesh
Mark the density of being in danger of period;
If the density of being in danger is greater than or equal to default density threshold of being in danger, it is determined that the subregion of initially surveying is hot spot
Region;
If the density of being in danger is less than default density threshold of being in danger, it is determined that the subregion of initially surveying is non-hot sub-district
Domain.
7. method as claimed in claim 3, which is characterized in that it is described according to preset scheduling rule by the current event pair
Answering for the task of surveying is dispatched to the person of surveying, comprising:
Affair character and the person's of surveying feature are obtained, affair character and the person's of surveying feature are matched, selects and meets default adjust
The person of surveying of degree condition survey the assignment of task.
8. a kind of based on the task assigned unit for surveying grid characterized by comprising
First obtains module, and for obtaining the current case information of current event, the current case information includes at least current
It is in danger and place and currently reports a case to the security authorities the time;
Second obtains module, and for currently being reported a case to the security authorities the time according to described, acquisition is corresponding with the time of currently reporting a case to the security authorities to survey net
Lattice;
Determining module, for according to the place of being currently in danger determine described in survey the target in grid and survey subregion;
Dispatch module surveys surveying for subregion for the corresponding task of surveying of the current event to be dispatched to the target
Member.
9. a kind of terminal device, including memory and processor, it is stored with and can transports on the processor in the memory
Capable computer program, which is characterized in that when the processor executes the computer program, realize following steps:
The current case information of current event is obtained, the current case information is included at least currently to be in danger and place and currently be reported a case to the security authorities
Time;
It is currently reported a case to the security authorities the time according to described, acquisition is corresponding with the time of currently reporting a case to the security authorities to survey grid;
According to the place of being currently in danger determine described in survey the target in grid and survey subregion;
The corresponding task of surveying of the current event is dispatched to the person of surveying that the target surveys subregion.
10. a kind of computer readable storage medium, the computer-readable recording medium storage has computer program, and feature exists
In when the computer program is executed by processor the step of any one of such as claim 1 to 7 of realization the method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811222337.1A CN109543947A (en) | 2018-10-19 | 2018-10-19 | Method, apparatus and terminal device based on the task distribution for surveying grid |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811222337.1A CN109543947A (en) | 2018-10-19 | 2018-10-19 | Method, apparatus and terminal device based on the task distribution for surveying grid |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109543947A true CN109543947A (en) | 2019-03-29 |
Family
ID=65844061
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811222337.1A Pending CN109543947A (en) | 2018-10-19 | 2018-10-19 | Method, apparatus and terminal device based on the task distribution for surveying grid |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109543947A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110443440A (en) * | 2019-06-19 | 2019-11-12 | 中国平安财产保险股份有限公司 | Work dispatching method, device, computer equipment and storage medium based on GPS positioning |
CN110766288A (en) * | 2019-09-25 | 2020-02-07 | 支付宝(杭州)信息技术有限公司 | Method and device for distributing claim settlement investigators and electronic equipment |
CN111476464A (en) * | 2020-03-20 | 2020-07-31 | 中保车服科技服务股份有限公司 | Method, device and equipment for scheduling survey resources based on grids and readable medium |
CN112084281A (en) * | 2020-09-04 | 2020-12-15 | 中国平安财产保险股份有限公司 | Method and device for drawing survey grid, computer equipment and storage medium |
CN113240554A (en) * | 2021-01-26 | 2021-08-10 | 张作中 | Intellectual property project service personnel management system and method |
CN113643048A (en) * | 2021-08-30 | 2021-11-12 | 平安国际融资租赁有限公司 | Survey task processing method, device, equipment and medium based on trusted terminal |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106408147A (en) * | 2016-01-25 | 2017-02-15 | 平安科技(深圳)有限公司 | Automobile insurance survey task distribution method and system |
CN107844851A (en) * | 2017-09-30 | 2018-03-27 | 平安科技(深圳)有限公司 | Survey grid optimization method, electronic equipment and computer-readable recording medium |
-
2018
- 2018-10-19 CN CN201811222337.1A patent/CN109543947A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106408147A (en) * | 2016-01-25 | 2017-02-15 | 平安科技(深圳)有限公司 | Automobile insurance survey task distribution method and system |
CN107844851A (en) * | 2017-09-30 | 2018-03-27 | 平安科技(深圳)有限公司 | Survey grid optimization method, electronic equipment and computer-readable recording medium |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110443440A (en) * | 2019-06-19 | 2019-11-12 | 中国平安财产保险股份有限公司 | Work dispatching method, device, computer equipment and storage medium based on GPS positioning |
CN110443440B (en) * | 2019-06-19 | 2023-06-20 | 中国平安财产保险股份有限公司 | Dispatching method and device based on GPS positioning, computer equipment and storage medium |
CN110766288A (en) * | 2019-09-25 | 2020-02-07 | 支付宝(杭州)信息技术有限公司 | Method and device for distributing claim settlement investigators and electronic equipment |
CN111476464A (en) * | 2020-03-20 | 2020-07-31 | 中保车服科技服务股份有限公司 | Method, device and equipment for scheduling survey resources based on grids and readable medium |
CN112084281A (en) * | 2020-09-04 | 2020-12-15 | 中国平安财产保险股份有限公司 | Method and device for drawing survey grid, computer equipment and storage medium |
CN112084281B (en) * | 2020-09-04 | 2023-11-03 | 中国平安财产保险股份有限公司 | Method, device, computer equipment and storage medium for drawing survey grid |
CN113240554A (en) * | 2021-01-26 | 2021-08-10 | 张作中 | Intellectual property project service personnel management system and method |
CN113643048A (en) * | 2021-08-30 | 2021-11-12 | 平安国际融资租赁有限公司 | Survey task processing method, device, equipment and medium based on trusted terminal |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109543947A (en) | Method, apparatus and terminal device based on the task distribution for surveying grid | |
CN110163474A (en) | A kind of method and apparatus of task distribution | |
Ignall et al. | Using simulation to develop and validate analytic models: some case studies | |
CN111931949A (en) | Communication in a federated learning environment | |
CN107832139A (en) | For the method, apparatus and system for the computing resource for managing block chain link point | |
CN107480845A (en) | Order allocator and device | |
CN106453146B (en) | Method, system, device and readable storage medium for allocating private cloud computing resources | |
Berg et al. | Comparison of static ambulance location models | |
Zhang et al. | A novel probabilistic formulation for locating and sizing emergency medical service stations | |
CN109274717A (en) | Shared storage method, device, medium and electronic equipment based on block chain | |
CN109615370A (en) | Object select method and device, electronic equipment | |
CN108596627B (en) | Big data calculation method and system based on block chain and fog calculation | |
CN105488578A (en) | Stadium reservation management method | |
CN109117608A (en) | A kind of data processing method, device and relevant device | |
Lei et al. | A stochastic emergency vehicle redeployment model for an effective response to traffic incidents | |
CN110322578A (en) | A kind of Work attendance method and device | |
CN110163634A (en) | Withdrawing method and device, electronic equipment based on block chain | |
CN110175869A (en) | Vehicle allocation method and device, electronic equipment and computer readable storage medium | |
CN109583799A (en) | The method and device of region division, electronic equipment | |
CN109242161A (en) | The generation method and terminal device of distribution route based on big data | |
CN104715313A (en) | Dispatching management system and method | |
CN108920111A (en) | Data sharing method and Distributed data share system | |
US10242349B1 (en) | Efficient scheduling of maintenance for power distribution systems | |
CN109271438A (en) | A kind of data bank access method and its system | |
Sun et al. | Development of a fuzzy-queue-based interval linear programming model for municipal solid waste management |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |