CN109377066A - A kind of live Schedule monitoring system and method based on threedimensional model - Google Patents
A kind of live Schedule monitoring system and method based on threedimensional model Download PDFInfo
- Publication number
- CN109377066A CN109377066A CN201811291756.0A CN201811291756A CN109377066A CN 109377066 A CN109377066 A CN 109377066A CN 201811291756 A CN201811291756 A CN 201811291756A CN 109377066 A CN109377066 A CN 109377066A
- Authority
- CN
- China
- Prior art keywords
- progress
- construction
- bim model
- schedule
- project
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012544 monitoring process Methods 0.000 title claims abstract description 50
- 238000000034 method Methods 0.000 title claims description 30
- 238000010276 construction Methods 0.000 claims abstract description 94
- 238000004040 coloring Methods 0.000 claims abstract description 13
- 238000004088 simulation Methods 0.000 claims abstract description 10
- 230000008569 process Effects 0.000 claims description 14
- 238000012937 correction Methods 0.000 claims description 6
- 238000000354 decomposition reaction Methods 0.000 claims description 4
- 230000008447 perception Effects 0.000 claims description 4
- 230000000007 visual effect Effects 0.000 claims description 2
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 239000004575 stone Substances 0.000 claims 1
- 238000007726 management method Methods 0.000 description 18
- 230000008859 change Effects 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000004075 alteration Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000006870 function Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06312—Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Physics & Mathematics (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Game Theory and Decision Science (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention belongs to engineering project progress control technical fields.A kind of live Schedule monitoring system based on threedimensional model, including BIM model equipment, progress compiling module, construction speed analog module, monitoring management platform and external smart mobile device;BIM model equipment is for generating BIM model;Progress compiling module is used to obtain the related data of BIM model inner member, works out construction schedule;Construction speed analog module is for construction schedule and BIM model to be associated, construction simulation progress;External smart mobile device is used for the actual progress according to the contents of a project to monitoring management platform input site operation;For actual progress to be compared to obtain project progress information with construction schedule, project progress information is shown in BIM model with coloring mode monitoring management platform.The present invention is effectively combined BIM with construction schedule, is realized that the intercommunication of information is shared, is improved the efficiency and precision of project progress monitoring management.
Description
Technical field
The invention belongs to engineering project progress control technical fields, and in particular to a kind of live progress based on threedimensional model
Monitoring system and method.
Background technique
The Schedule monitoring of engineering project is controlled in the three controls-control of investment, progress monitoring and quality of project management
In, it plays a very important role.Often there is various factor for influencing construction speed, traditional construction in work progress
Live Schedule monitoring method often exist progress update not in time, the problems such as construction schedule adjustment capability is not good enough.It is constructing
In the process, often because of a variety of causes, the realization evolved to construction speed causes to impact, such as planning defect, construction ring
Border variation, field condition adjustment, resource provisioning influence etc., need to adjust construction plan in time, but since progress updates
Not in time, and based on the construction schedule that construction network figure is worked out, it cannot intuitively reflect and construction schedule is caused to deviate
Key factor, thus targeted construction program cannot be compiled in time.
Summary of the invention
For overcome the deficiencies in the prior art, the live Schedule monitoring system based on threedimensional model that the present invention provides a kind of
And method, it effectively by BIM in conjunction with construction schedule, can realize that the intercommunication of information is shared, to reach engineering construction
Real-time progress overall process, round-the-clock, total involvement target, while can be improved the efficiency and essence of project progress monitoring management
Degree.
In order to realize appeal purpose, the invention provides the following technical scheme:
A kind of live Schedule monitoring system based on threedimensional model, including BIM model equipment, progress compiling module, construction
Progress analog module, monitoring management platform and external smart mobile device;The BIM model equipment and the progress compiling module
Connection, the progress compiling module are connect with the monitoring management platform with external smart mobile device;
The BIM model equipment generates BIM model, and BIM model is stored in service for obtaining modelling data
In device;
The progress compiling module is used to obtain the related data of BIM model inner member, works out construction schedule;
The construction speed analog module is used for according to BIM model and construction schedule, by construction schedule and BIM
Model is associated, and each of work progress is worked and is shown with visualizing the building element virtual construction process of image
Show, additional time, dimension, passed through construction simulation analysis construction speed of the building element under scheduling;
External smart mobile device for automatic collection construction site Internet of Things perception data and according to the contents of a project to prison
The actual progress of keyholed back plate platform input site operation;
Monitoring management platform is for actual progress to be compared to obtain project progress information, engineering with construction schedule
Progress msg is shown in BIM model with coloring mode.
The live Schedule monitoring method based on threedimensional model that the present invention also provides a kind of, this method comprises the following steps:
S1. modelling data are obtained, establish BIM model, and BIM model is stored in server;
S2. according to the related data of BIM model inner member, construction schedule is worked out;
S3. according to BIM model and construction schedule, construction schedule and BIM model are associated, and will construction
The work of each of process shows that additional time, dimension, passed through to visualize the building element virtual construction process of image
Construction simulation analysis construction speed of the building element under scheduling;
S4. the actual progress of site operation is inputted to monitoring management platform by external smart mobile device;
S5. the BIM model for being associated with construction schedule is directed into monitoring management platform, carries out Schedule monitoring, it will
Actual progress is compared to obtain project progress information with construction schedule, and project progress information is in BIM model with coloring
Mode is shown.
Further, in the step S2, the concrete operations of construction schedule are worked out are as follows: use the decomposition mould of WBS first
Project decomposition at multiple enforceable components, is judged and is inputted the planned value of duration by formula;In conjunction with resource factors, space factor
With the influence of technological factor, milestone node being determined, then determining each component deadline, creation time list simultaneously presses outline
Form is organized, and forms construction schedule, and whether the arrangement of time for checking construction schedule is reasonable.
Further, in the step S3, by Visual Simulation or Time liner software by construction speed
Plan is associated with BIM model.The project plan can be shown in the work progress under scheduling by 3D component
Come, the inter-related task that thus mode generates automatically associates on BIM model equipment, when encounter design alteration or construction drawing modification
When, by adjusting construction speed figure, scheduling can also change automatically.
Further, in the step S5, project progress include the duration in advance, normally complete with the duration lag three parts,
For the ease of intuitive compartment analysis, color that project progress uses is different, project progress with coloring mode BIM model component
Middle display, wherein the duration shifts to an earlier date part to be indicated with green, and normally completing part indicates that the duration, lagging portion was with red with yellow
It is highlighted to indicate.
Further, the duration lags, then the project progress analysis software mounted by monitoring management platform is analyzed, raw
At progress hysteresis reason analytical statement and progress correction report, construction schedule adjusted is formed, and be updated to three-dimensional BIM
In model, while correction report being associated in BIM model, staff is facilitated to consult.
Compared with prior art, the invention has the following advantages:
1. the present invention is inputted by passing through the Internet of Things perception data of external smart mobile device automatic collection construction site
The actual progress of site operation carries out sorted generalization and arrangement to the data of acquisition, construction speed is combined with BIM model,
The work progress at scene is resolved into several progress component nodes in conjunction with WBS, is compiled into establishment project construction schedule, favorably
In discovery construction gap, takes timely measure, carry out correction adjustment;Design alteration, construction drawing change are being encountered, it also can be quick
Ground associated modification schedule.
2. work out project construction schedule, using WBS resolution model by Project decomposition at the component for being easier to management
Node.In work progress, metering, construction speed, data are mounted around WBS process, unified to carry out calling in for data;It constructs
The 4D construction simulation of progress, can recognize in advance in work progress there may be the problem of, ancillary staff compiles more
For the construction schedule of efficiently and accurately.
3. field personnel logs in monitoring management platform, typing scene work by external smart mobile device, such as mobile phone
Journey progress msg, while by the inclined of component coloring mode display engineering actual progress in three-dimensional BIM model and target advance
Difference facilitates staff that can get information about engineering overall progress in time, timely solution of finding the problem, convenient for project progress
Real time monitoring.Project progress is mounted by monitoring management platform and analyzes software, and when project progress deviates target advance, generation is entangled
Report partially, instructs staff to adjust in time.Reduce the time loss of pilot process bring, can effectively improve engineering construction into
Degree.
Detailed description of the invention
Fig. 1 is a kind of flow diagram of the live Schedule monitoring based on threedimensional model of the present invention.
Specific embodiment
The invention will be further described with embodiment with reference to the accompanying drawing.It should be noted that specific reality of the invention
It applies example and is intended merely to the clearer description technique scheme of energy, and cannot function as a kind of limitation of the scope of the present invention.
A kind of live Schedule monitoring system based on threedimensional model, including BIM model equipment, progress compiling module, construction
Progress analog module, monitoring management platform and external smart mobile device;The BIM model equipment and the progress compiling module
Connection, the progress compiling module are connect with the monitoring management platform with external smart mobile device;
The BIM model equipment generates BIM model, and BIM model is stored in service for obtaining modelling data
In device;
The progress compiling module is used to obtain the related data of BIM model inner member, works out construction schedule;
The construction speed analog module is used for according to BIM model and construction schedule, by construction schedule and BIM
Model is associated, and each of work progress is worked and is shown with visualizing the building element virtual construction process of image
Show, additional time, dimension, passed through construction simulation analysis construction speed of the building element under scheduling;
External smart mobile device for automatic collection construction site Internet of Things perception data and according to the contents of a project to prison
The actual progress of keyholed back plate platform input site operation;
Monitoring management platform is for actual progress to be compared to obtain project progress information, engineering with construction schedule
Progress msg is shown in BIM model with coloring mode.
The present invention is shared by the intercommunication that BIM in conjunction with construction schedule, can be realized to information, to reach engineering
Construct real-time progress overall process, round-the-clock, total involvement target, at the same can be improved project progress monitoring management efficiency and
Precision.
Referring to Fig. 1, the present invention also provides a kind of live Schedule monitoring method based on threedimensional model, this method includes such as
Lower step:
S1. modelling data are obtained, establish BIM model, and BIM model is stored in server;
S2. according to the related data of BIM model inner member, construction schedule is worked out;
S3. according to BIM model and construction schedule, construction schedule and BIM model are associated, and will construction
The work of each of process shows that additional time, dimension, passed through to visualize the building element virtual construction process of image
Construction simulation analysis construction speed of the building element under scheduling;
S4. the actual progress of site operation is inputted to monitoring management platform by external smart mobile device;
S5. the BIM model for being associated with construction schedule is directed into monitoring management platform, carries out Schedule monitoring, it will
Actual progress is compared to obtain project progress information with construction schedule, and project progress information is in BIM model with coloring
Mode is shown.
In the step S2, the concrete operations of construction schedule are worked out are as follows: first divided project with the resolution model of WBS
Solution judges and inputs the planned value of duration at multiple enforceable components;In conjunction with resource factors, space factor and technological factor
Influence, determine milestone node, then determine each component deadline, creation time list and by the form of outline by its group
It knits, forms construction schedule, and whether the arrangement of time for checking construction schedule is reasonable.
In the step S5, project progress include the duration in advance, normally complete with the duration lag three parts, for the ease of straight
Compartment analysis is seen, the color that project progress uses is different, and project progress is shown in the component of BIM model with coloring mode,
In, the duration shifts to an earlier date part to be indicated with green, and normally complete part is indicated with yellow, and duration lagging portion is indicated so that red is highlighted.
It should be noted that project progress coloring is for the ease of distinguishing different process schedules, coloring selection is not unique.
When there is the case where duration lag, then the project progress analysis software mounted by monitoring management platform is divided
Analysis generates progress hysteresis reason analytical statement and progress correction report, forms construction schedule adjusted, and be updated to three
It ties up in BIM model, while correction report being associated in BIM model, staff is facilitated to consult.
Above description is the detailed description for the present invention preferably possible embodiments, but embodiment is not limited to this hair
Bright patent claim, it is all the present invention suggested by technical spirit under completed same changes or modifications change, should all belong to
In the covered the scope of the patents of the present invention.
Claims (6)
1. a kind of live Schedule monitoring system based on threedimensional model, which is characterized in that worked out including BIM model equipment, progress
Module, construction speed analog module, monitoring management platform and external smart mobile device;The BIM model equipment and it is described into
Compiling module connection is spent, the progress compiling module is connect with the monitoring management platform with external smart mobile device;
The BIM model equipment generates BIM model, and BIM model is stored in server for obtaining modelling data
It is interior;
The progress compiling module is used to obtain the related data of BIM model inner member, works out construction schedule;
The construction speed analog module is used for according to BIM model and construction schedule, by construction schedule and BIM model
It is associated, and each of work progress is worked and is shown with visualizing the building element virtual construction process of image,
Additional time, dimension, passed through construction simulation analysis construction speed of the building element under scheduling;
External smart mobile device for automatic collection construction site Internet of Things perception data and according to the contents of a project to monitoring pipe
The actual progress of platform input site operation;
Monitoring management platform is for actual progress to be compared to obtain project progress information, project progress with construction schedule
Information is shown in BIM model with coloring mode.
2. a kind of live Schedule monitoring method based on threedimensional model as described in claim 1, which is characterized in that including as follows
Step:
S1. modelling data are obtained, establish BIM model, and BIM model is stored in server;
S2. according to the related data of BIM model inner member, construction schedule is worked out;
S3. according to BIM model and construction schedule, construction schedule and BIM model are associated, and by work progress
Each of work show that dimension, passes through building additional time with the building element virtual construction process for visualizing image
Construction simulation analysis construction speed of the component under scheduling;
S4. the actual progress of site operation is inputted to monitoring management platform by external smart mobile device;
S5. the BIM model for being associated with construction schedule is directed into monitoring management platform, carries out Schedule monitoring, it will be practical
Progress is compared to obtain project progress information with construction schedule, and project progress information is in BIM model with coloring mode
Display.
3. a kind of live Schedule monitoring method based on threedimensional model according to claim 2, which is characterized in that the step
In rapid S2, the concrete operations of construction schedule are worked out are as follows: use the resolution model of WBS by Project decomposition at multiple implementable first
Component, judge and input the planned value of duration;In conjunction with the influence of resource factors, space factor and technological factor, in determining
Then journey upright stone tablet node determines each component deadline, creation time list is simultaneously organized by the form of outline, and formation is applied
Work schedule, and whether the arrangement of time for checking construction schedule is reasonable.
4. a kind of live Schedule monitoring method based on threedimensional model according to claim 2, which is characterized in that the step
In rapid S3, construction schedule and BIM model are associated by Visual Simulation or Time liner software.
5. a kind of live Schedule monitoring method based on threedimensional model according to claim 2, which is characterized in that the step
In rapid S5, project progress include the duration in advance, normally complete and lag three parts with the duration, project progress is with coloring mode in BIM
It is shown in the component of model, wherein the duration shifts to an earlier date part to be indicated with green, and normally complete part is indicated with yellow, duration lag
Part is indicated so that red is highlighted.
6. a kind of live Schedule monitoring method based on threedimensional model according to claim 5, which is characterized in that the duration is stagnant
Afterwards, then the project progress analysis software mounted by monitoring management platform is analyzed, and progress hysteresis reason analytical statement is generated
It rectifies a deviation and reports with progress, form construction schedule adjusted, and be updated in three-dimensional BIM model, while correction being reported
It is associated in BIM model.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811291756.0A CN109377066A (en) | 2018-10-31 | 2018-10-31 | A kind of live Schedule monitoring system and method based on threedimensional model |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811291756.0A CN109377066A (en) | 2018-10-31 | 2018-10-31 | A kind of live Schedule monitoring system and method based on threedimensional model |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109377066A true CN109377066A (en) | 2019-02-22 |
Family
ID=65396777
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811291756.0A Pending CN109377066A (en) | 2018-10-31 | 2018-10-31 | A kind of live Schedule monitoring system and method based on threedimensional model |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109377066A (en) |
Cited By (51)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109784781A (en) * | 2019-03-04 | 2019-05-21 | 中铁隧道局集团有限公司 | A kind of project management system served as theme with project progress, method and storage medium |
CN109933863A (en) * | 2019-02-26 | 2019-06-25 | 杭州吉风建筑科技有限公司 | One kind being used for power plant's construct platform |
CN109978387A (en) * | 2019-03-28 | 2019-07-05 | 浙江鑫润工程管理有限公司 | A kind of BIM engineering information management method and system |
CN109993449A (en) * | 2019-04-08 | 2019-07-09 | 中交一公局海威工程建设有限公司 | Laboratory equipment management method, BIM Visualization Platform, equipment and medium |
CN110008588A (en) * | 2019-04-04 | 2019-07-12 | 南京林业大学 | Multidimensional integrated highway engineering construction progress msg management system and method |
CN110084526A (en) * | 2019-05-05 | 2019-08-02 | 广西路桥工程集团有限公司 | A kind of visualization project management monitoring system based on BIM+WBS |
CN110119774A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A kind of contrast difference's method based on Building Information Model 4D progress Yu outdoor scene progress |
CN110119565A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A method of quick association and displaying based on BIM model and project programme |
CN110378588A (en) * | 2019-07-10 | 2019-10-25 | 重庆大学 | A kind of contract spatialization system |
CN110428236A (en) * | 2019-08-15 | 2019-11-08 | 宁夏信友监理咨询管理股份有限公司 | A kind of communication engineering construction whole process engineering consulting management system |
CN110443485A (en) * | 2019-07-30 | 2019-11-12 | 上海建工集团股份有限公司 | Engineering construction various dimensions plan correlating method and system |
CN110505452A (en) * | 2019-08-26 | 2019-11-26 | 广东电网有限责任公司 | A kind of capital construction power transmission engineering Schedule monitoring method and monitoring system |
CN110599027A (en) * | 2019-09-09 | 2019-12-20 | 中铁建设集团有限公司 | Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system |
CN110634186A (en) * | 2019-08-13 | 2019-12-31 | 中铁上海工程局集团有限公司 | Arch cover method underground excavation construction method based on BIM |
CN110750827A (en) * | 2019-10-10 | 2020-02-04 | 贵州百胜工程建设咨询有限公司 | Progress management method based on BIM |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN111062090A (en) * | 2019-12-20 | 2020-04-24 | 长江勘测规划设计研究有限责任公司 | Progress management method and device based on BIM |
CN111145354A (en) * | 2019-12-31 | 2020-05-12 | 北京恒华伟业科技股份有限公司 | BIM data model identification method and device |
CN111311187A (en) * | 2020-02-20 | 2020-06-19 | 广州易达建信科技开发有限公司 | Revit-based project progress monitoring method, system and storage medium |
CN111311203A (en) * | 2020-04-01 | 2020-06-19 | 陕西工业职业技术学院 | BIM-based engineering progress control system |
CN111340458A (en) * | 2020-03-17 | 2020-06-26 | 中铁城建集团有限公司 | Construction progress informatization management method |
CN111369226A (en) * | 2020-03-27 | 2020-07-03 | 陕西工业职业技术学院 | BIM-based project progress supervision system |
CN111445218A (en) * | 2020-04-22 | 2020-07-24 | 中铁二十一局集团电务电化工程有限公司 | BIM-based project progress management method, device, equipment and storage medium |
CN111444565A (en) * | 2020-03-26 | 2020-07-24 | 北京中交京纬公路造价技术有限公司 | Project collaborative simulation system based on mobile internet |
CN111539690A (en) * | 2020-04-28 | 2020-08-14 | 悉地(苏州)勘察设计顾问有限公司 | Construction project collaborative management method and system based on BIM |
CN111695884A (en) * | 2020-08-17 | 2020-09-22 | 广东新视野信息科技股份有限公司 | Internet of things big data visualization method and system based on smart construction site |
CN111724016A (en) * | 2019-03-21 | 2020-09-29 | 上海易智链智能科技发展有限公司 | BIM-based material dynamic management method and system |
CN111783270A (en) * | 2020-03-17 | 2020-10-16 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN111967838A (en) * | 2020-07-16 | 2020-11-20 | 译筑信息科技(上海)有限公司 | Intelligent 4D plan management and control method based on BIM |
CN112070482A (en) * | 2020-09-10 | 2020-12-11 | 广州市第二装修有限公司 | Engineering project integrated management method and device, computer equipment and storage medium |
CN112365113A (en) * | 2020-08-20 | 2021-02-12 | 中国铁道科学研究院集团有限公司电子计算技术研究所 | BIM-based four-power-station-group design simulation and resource dynamic adjustment method and system |
CN112365111A (en) * | 2020-02-28 | 2021-02-12 | 中国二十二冶集团有限公司 | Project progress management method |
CN112488664A (en) * | 2020-12-14 | 2021-03-12 | 广西路桥工程集团有限公司 | Project metering system based on WBS |
CN112486613A (en) * | 2020-11-27 | 2021-03-12 | 东南大学 | Engineering project Web end construction progress management method and device and readable storage medium |
CN112507430A (en) * | 2020-12-02 | 2021-03-16 | 国网江西省电力有限公司建设分公司 | Visual fusion method of BIM (building information modeling) model and engineering project |
CN112650820A (en) * | 2020-12-31 | 2021-04-13 | 天津博迈科海洋工程有限公司 | Method for tracking production data of oil-gas module structural part |
CN113177768A (en) * | 2020-11-10 | 2021-07-27 | 国网青海省电力公司 | Intelligent engineering platform based on comprehensive digital management of capital construction whole process |
CN113222564A (en) * | 2021-06-09 | 2021-08-06 | 合肥优尔电子科技有限公司 | Progress management system and method based on BIM system |
CN113256131A (en) * | 2021-06-01 | 2021-08-13 | 安徽鑫洋信息工程有限公司 | Intelligent coordination construction system of prefabricated building |
CN113268797A (en) * | 2021-05-18 | 2021-08-17 | 广州市第三建筑装修有限公司 | BIM-based indoor decoration project intelligent management method and system |
CN113360583A (en) * | 2021-06-15 | 2021-09-07 | 东南大学 | Construction progress visualization method based on BIM model and monitoring image comparison |
CN113379324A (en) * | 2021-07-06 | 2021-09-10 | 山东电力工程咨询院有限公司 | Construction site whole-course monitoring method and system |
CN113450018A (en) * | 2021-07-16 | 2021-09-28 | 中国化学工程第十一建设有限公司 | Project progress processing method, device and equipment and storage medium |
CN113656864A (en) * | 2021-07-27 | 2021-11-16 | 天一建设发展有限公司 | Building construction method and system based on BIM, computer device and storage medium |
CN113673967A (en) * | 2021-09-09 | 2021-11-19 | 国网江苏省电力有限公司建设分公司 | BIM technology-based ultrahigh tower construction progress management system and method |
CN114117596A (en) * | 2021-11-15 | 2022-03-01 | 国能大渡河猴子岩发电有限公司 | Real-time monitoring and management method for water conservancy and hydropower engineering |
CN115794759A (en) * | 2023-02-08 | 2023-03-14 | 中建深圳装饰有限公司 | BIM-based multi-target construction data sharing transmission method |
CN115983429A (en) * | 2022-12-02 | 2023-04-18 | 广东中科云所信息科技有限公司 | BIM model-based construction strategy optimization method, system, terminal and medium |
CN116029682A (en) * | 2023-03-29 | 2023-04-28 | 北京中昌工程咨询有限公司 | Construction progress management method and system based on BIM technology |
CN117010841A (en) * | 2023-08-31 | 2023-11-07 | 广东中联建建筑工程有限公司 | Method for controlling key line by integrating construction progress plan and BIM model |
CN117408643A (en) * | 2023-12-12 | 2024-01-16 | 长春建业集团股份有限公司 | Progress monitoring management method and system applied to engineering number intelligent management platform |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105512822A (en) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | Construction progress management method based on visualization technology |
CN105550802A (en) * | 2015-12-09 | 2016-05-04 | 中铁隧道集团有限公司 | Method for checking construction progress in underground-excavated metro station inter-zone tunnel model |
CN106897817A (en) * | 2017-01-22 | 2017-06-27 | 朗坤智慧科技股份有限公司 | A kind of construction speed Visualized management system and method based on augmented reality |
DE102016004382A1 (en) * | 2016-04-08 | 2017-10-12 | Liebherr-Werk Biberach Gmbh | Method and device for planning and / or controlling and / or simulating the operation of a construction machine |
CN107273640A (en) * | 2017-07-11 | 2017-10-20 | 黄河勘测规划设计有限公司 | Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model |
CN107480370A (en) * | 2017-08-10 | 2017-12-15 | 嘉兴恒创电力设计研究院有限公司 | A kind of construction speed Forecasting Methodology and system based on BIM models |
CN108596423A (en) * | 2018-03-02 | 2018-09-28 | 重庆机电装备技术研究院有限公司 | A kind of trackways engineering construction progress msg management method based on BIM |
-
2018
- 2018-10-31 CN CN201811291756.0A patent/CN109377066A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105550802A (en) * | 2015-12-09 | 2016-05-04 | 中铁隧道集团有限公司 | Method for checking construction progress in underground-excavated metro station inter-zone tunnel model |
CN105512822A (en) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | Construction progress management method based on visualization technology |
DE102016004382A1 (en) * | 2016-04-08 | 2017-10-12 | Liebherr-Werk Biberach Gmbh | Method and device for planning and / or controlling and / or simulating the operation of a construction machine |
CN106897817A (en) * | 2017-01-22 | 2017-06-27 | 朗坤智慧科技股份有限公司 | A kind of construction speed Visualized management system and method based on augmented reality |
CN107273640A (en) * | 2017-07-11 | 2017-10-20 | 黄河勘测规划设计有限公司 | Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model |
CN107480370A (en) * | 2017-08-10 | 2017-12-15 | 嘉兴恒创电力设计研究院有限公司 | A kind of construction speed Forecasting Methodology and system based on BIM models |
CN108596423A (en) * | 2018-03-02 | 2018-09-28 | 重庆机电装备技术研究院有限公司 | A kind of trackways engineering construction progress msg management method based on BIM |
Cited By (62)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109933863A (en) * | 2019-02-26 | 2019-06-25 | 杭州吉风建筑科技有限公司 | One kind being used for power plant's construct platform |
CN109784781A (en) * | 2019-03-04 | 2019-05-21 | 中铁隧道局集团有限公司 | A kind of project management system served as theme with project progress, method and storage medium |
CN111724016A (en) * | 2019-03-21 | 2020-09-29 | 上海易智链智能科技发展有限公司 | BIM-based material dynamic management method and system |
CN109978387A (en) * | 2019-03-28 | 2019-07-05 | 浙江鑫润工程管理有限公司 | A kind of BIM engineering information management method and system |
CN110008588A (en) * | 2019-04-04 | 2019-07-12 | 南京林业大学 | Multidimensional integrated highway engineering construction progress msg management system and method |
CN109993449A (en) * | 2019-04-08 | 2019-07-09 | 中交一公局海威工程建设有限公司 | Laboratory equipment management method, BIM Visualization Platform, equipment and medium |
CN110084526B (en) * | 2019-05-05 | 2022-05-31 | 广西路桥工程集团有限公司 | BIM + WBS-based visual project management monitoring system |
CN110084526A (en) * | 2019-05-05 | 2019-08-02 | 广西路桥工程集团有限公司 | A kind of visualization project management monitoring system based on BIM+WBS |
CN110119774A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A kind of contrast difference's method based on Building Information Model 4D progress Yu outdoor scene progress |
CN110119565A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A method of quick association and displaying based on BIM model and project programme |
CN110378588A (en) * | 2019-07-10 | 2019-10-25 | 重庆大学 | A kind of contract spatialization system |
CN110378588B (en) * | 2019-07-10 | 2023-02-03 | 重庆大学 | Contract spatialization system |
CN110443485A (en) * | 2019-07-30 | 2019-11-12 | 上海建工集团股份有限公司 | Engineering construction various dimensions plan correlating method and system |
CN110634186A (en) * | 2019-08-13 | 2019-12-31 | 中铁上海工程局集团有限公司 | Arch cover method underground excavation construction method based on BIM |
CN110428236A (en) * | 2019-08-15 | 2019-11-08 | 宁夏信友监理咨询管理股份有限公司 | A kind of communication engineering construction whole process engineering consulting management system |
CN110505452A (en) * | 2019-08-26 | 2019-11-26 | 广东电网有限责任公司 | A kind of capital construction power transmission engineering Schedule monitoring method and monitoring system |
CN110599027A (en) * | 2019-09-09 | 2019-12-20 | 中铁建设集团有限公司 | Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN110750827A (en) * | 2019-10-10 | 2020-02-04 | 贵州百胜工程建设咨询有限公司 | Progress management method based on BIM |
CN111062090A (en) * | 2019-12-20 | 2020-04-24 | 长江勘测规划设计研究有限责任公司 | Progress management method and device based on BIM |
CN111145354A (en) * | 2019-12-31 | 2020-05-12 | 北京恒华伟业科技股份有限公司 | BIM data model identification method and device |
CN111145354B (en) * | 2019-12-31 | 2024-02-13 | 北京恒华伟业科技股份有限公司 | BIM data model identification method and device |
CN111311187A (en) * | 2020-02-20 | 2020-06-19 | 广州易达建信科技开发有限公司 | Revit-based project progress monitoring method, system and storage medium |
CN112365111A (en) * | 2020-02-28 | 2021-02-12 | 中国二十二冶集团有限公司 | Project progress management method |
CN111340458A (en) * | 2020-03-17 | 2020-06-26 | 中铁城建集团有限公司 | Construction progress informatization management method |
CN111783270B (en) * | 2020-03-17 | 2021-09-03 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN111783270A (en) * | 2020-03-17 | 2020-10-16 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN111444565A (en) * | 2020-03-26 | 2020-07-24 | 北京中交京纬公路造价技术有限公司 | Project collaborative simulation system based on mobile internet |
CN111369226A (en) * | 2020-03-27 | 2020-07-03 | 陕西工业职业技术学院 | BIM-based project progress supervision system |
CN111311203A (en) * | 2020-04-01 | 2020-06-19 | 陕西工业职业技术学院 | BIM-based engineering progress control system |
CN111311203B (en) * | 2020-04-01 | 2023-08-22 | 陕西工业职业技术学院 | Engineering progress management and control system based on BIM |
CN111445218A (en) * | 2020-04-22 | 2020-07-24 | 中铁二十一局集团电务电化工程有限公司 | BIM-based project progress management method, device, equipment and storage medium |
CN111539690A (en) * | 2020-04-28 | 2020-08-14 | 悉地(苏州)勘察设计顾问有限公司 | Construction project collaborative management method and system based on BIM |
CN111967838A (en) * | 2020-07-16 | 2020-11-20 | 译筑信息科技(上海)有限公司 | Intelligent 4D plan management and control method based on BIM |
CN111695884B (en) * | 2020-08-17 | 2020-11-20 | 广东新视野信息科技股份有限公司 | Internet of things big data visualization method and system based on smart construction site |
CN111695884A (en) * | 2020-08-17 | 2020-09-22 | 广东新视野信息科技股份有限公司 | Internet of things big data visualization method and system based on smart construction site |
CN112365113A (en) * | 2020-08-20 | 2021-02-12 | 中国铁道科学研究院集团有限公司电子计算技术研究所 | BIM-based four-power-station-group design simulation and resource dynamic adjustment method and system |
CN112070482A (en) * | 2020-09-10 | 2020-12-11 | 广州市第二装修有限公司 | Engineering project integrated management method and device, computer equipment and storage medium |
CN113177768A (en) * | 2020-11-10 | 2021-07-27 | 国网青海省电力公司 | Intelligent engineering platform based on comprehensive digital management of capital construction whole process |
CN112486613A (en) * | 2020-11-27 | 2021-03-12 | 东南大学 | Engineering project Web end construction progress management method and device and readable storage medium |
CN112507430A (en) * | 2020-12-02 | 2021-03-16 | 国网江西省电力有限公司建设分公司 | Visual fusion method of BIM (building information modeling) model and engineering project |
CN112488664A (en) * | 2020-12-14 | 2021-03-12 | 广西路桥工程集团有限公司 | Project metering system based on WBS |
CN112650820A (en) * | 2020-12-31 | 2021-04-13 | 天津博迈科海洋工程有限公司 | Method for tracking production data of oil-gas module structural part |
CN113268797A (en) * | 2021-05-18 | 2021-08-17 | 广州市第三建筑装修有限公司 | BIM-based indoor decoration project intelligent management method and system |
CN113256131A (en) * | 2021-06-01 | 2021-08-13 | 安徽鑫洋信息工程有限公司 | Intelligent coordination construction system of prefabricated building |
CN113256131B (en) * | 2021-06-01 | 2024-02-02 | 安徽鑫洋信息工程有限公司 | Intelligent coordination construction system of assembled building |
CN113222564A (en) * | 2021-06-09 | 2021-08-06 | 合肥优尔电子科技有限公司 | Progress management system and method based on BIM system |
CN113360583A (en) * | 2021-06-15 | 2021-09-07 | 东南大学 | Construction progress visualization method based on BIM model and monitoring image comparison |
CN113360583B (en) * | 2021-06-15 | 2024-05-14 | 东南大学 | Construction progress visualization method based on BIM model and monitoring image comparison |
CN113379324A (en) * | 2021-07-06 | 2021-09-10 | 山东电力工程咨询院有限公司 | Construction site whole-course monitoring method and system |
CN113450018A (en) * | 2021-07-16 | 2021-09-28 | 中国化学工程第十一建设有限公司 | Project progress processing method, device and equipment and storage medium |
CN113656864B (en) * | 2021-07-27 | 2023-10-13 | 天一建设发展有限公司 | Building construction method, system, computer device and storage medium based on BIM |
CN113656864A (en) * | 2021-07-27 | 2021-11-16 | 天一建设发展有限公司 | Building construction method and system based on BIM, computer device and storage medium |
CN113673967A (en) * | 2021-09-09 | 2021-11-19 | 国网江苏省电力有限公司建设分公司 | BIM technology-based ultrahigh tower construction progress management system and method |
CN114117596A (en) * | 2021-11-15 | 2022-03-01 | 国能大渡河猴子岩发电有限公司 | Real-time monitoring and management method for water conservancy and hydropower engineering |
CN115983429A (en) * | 2022-12-02 | 2023-04-18 | 广东中科云所信息科技有限公司 | BIM model-based construction strategy optimization method, system, terminal and medium |
CN115983429B (en) * | 2022-12-02 | 2024-04-02 | 中东基建科技集团有限公司 | Construction strategy optimization method, system, terminal and medium based on BIM model |
CN115794759A (en) * | 2023-02-08 | 2023-03-14 | 中建深圳装饰有限公司 | BIM-based multi-target construction data sharing transmission method |
CN116029682A (en) * | 2023-03-29 | 2023-04-28 | 北京中昌工程咨询有限公司 | Construction progress management method and system based on BIM technology |
CN117010841A (en) * | 2023-08-31 | 2023-11-07 | 广东中联建建筑工程有限公司 | Method for controlling key line by integrating construction progress plan and BIM model |
CN117408643A (en) * | 2023-12-12 | 2024-01-16 | 长春建业集团股份有限公司 | Progress monitoring management method and system applied to engineering number intelligent management platform |
CN117408643B (en) * | 2023-12-12 | 2024-03-22 | 长春建业集团股份有限公司 | Progress monitoring management method and system applied to engineering number intelligent management platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109377066A (en) | A kind of live Schedule monitoring system and method based on threedimensional model | |
CN105069524B (en) | Planned dispatching optimization method based on big data analysis | |
CN104407576B (en) | A kind of implementation method and control system of universal manufacturing unit | |
CN102880123B (en) | System and method for controlling production process of petrochemical enterprise on basis of manufacturing execution system (MES) workflow | |
CN105786912B (en) | Data collecting conversion method and device | |
CN109710990A (en) | Construction of Rolled Concrete Dam progress-cost cooperative control method based on BIM technology | |
CN107993000A (en) | The method of construction main flat face dynamic coordinate management based on BIM | |
CN109685452A (en) | A kind of power supply company's item data management platform | |
CN109308582A (en) | A kind of manufacturing execution system framework based on modularization Yu serviceization | |
RU2691270C2 (en) | Workflow digital support system | |
KR100836535B1 (en) | 3-dimensional system and method for construction progression managing based gis | |
CN106156408A (en) | The building of the classification of a kind of Component-Based Development and combination works in coordination with constructing system and method | |
KR101717766B1 (en) | Labor-based Progress Measurement for Cost and Schedule Control System in Construction Programs | |
CN108971807A (en) | A kind of site welding construction technology intelligent management control method and management system | |
KR20130016620A (en) | 3d process management method for bim(building information modeling) | |
CN108305043A (en) | Single-piece flow Production MIS | |
CN106447519A (en) | Generating system of three-dimensional sheet metal welding technology | |
CN113610389B (en) | Prefabricated component production quality management system based on BIM and RFID | |
CN105678504A (en) | XML-based field layer, MES, ERP integrated information integration method | |
CN105404966A (en) | Construction method of construction process quality color rendering module based on BIM | |
JP2013045386A (en) | Process design method, process design support system, and process design support device | |
KR101674101B1 (en) | Project management system based information and communication technology | |
CN109799793A (en) | Production plan making device and production plan formulating method | |
CN110930044A (en) | Construction organization resource rapid configuration method and system | |
CN109978387A (en) | A kind of BIM engineering information management method and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190222 |