CN109377066A - A kind of live Schedule monitoring system and method based on threedimensional model - Google Patents

A kind of live Schedule monitoring system and method based on threedimensional model Download PDF

Info

Publication number
CN109377066A
CN109377066A CN201811291756.0A CN201811291756A CN109377066A CN 109377066 A CN109377066 A CN 109377066A CN 201811291756 A CN201811291756 A CN 201811291756A CN 109377066 A CN109377066 A CN 109377066A
Authority
CN
China
Prior art keywords
progress
construction
bim model
schedule
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811291756.0A
Other languages
Chinese (zh)
Inventor
王伟宁
王建军
林广泰
孙辉
罗伟
陆进
陆艺
杨威
杨文达
陈旺平
陈孝强
李雍友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Road and Bridge Engineering Group Co Ltd
Original Assignee
Guangxi Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Road and Bridge Engineering Group Co Ltd filed Critical Guangxi Road and Bridge Engineering Group Co Ltd
Priority to CN201811291756.0A priority Critical patent/CN109377066A/en
Publication of CN109377066A publication Critical patent/CN109377066A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention belongs to engineering project progress control technical fields.A kind of live Schedule monitoring system based on threedimensional model, including BIM model equipment, progress compiling module, construction speed analog module, monitoring management platform and external smart mobile device;BIM model equipment is for generating BIM model;Progress compiling module is used to obtain the related data of BIM model inner member, works out construction schedule;Construction speed analog module is for construction schedule and BIM model to be associated, construction simulation progress;External smart mobile device is used for the actual progress according to the contents of a project to monitoring management platform input site operation;For actual progress to be compared to obtain project progress information with construction schedule, project progress information is shown in BIM model with coloring mode monitoring management platform.The present invention is effectively combined BIM with construction schedule, is realized that the intercommunication of information is shared, is improved the efficiency and precision of project progress monitoring management.

Description

A kind of live Schedule monitoring system and method based on threedimensional model
Technical field
The invention belongs to engineering project progress control technical fields, and in particular to a kind of live progress based on threedimensional model Monitoring system and method.
Background technique
The Schedule monitoring of engineering project is controlled in the three controls-control of investment, progress monitoring and quality of project management In, it plays a very important role.Often there is various factor for influencing construction speed, traditional construction in work progress Live Schedule monitoring method often exist progress update not in time, the problems such as construction schedule adjustment capability is not good enough.It is constructing In the process, often because of a variety of causes, the realization evolved to construction speed causes to impact, such as planning defect, construction ring Border variation, field condition adjustment, resource provisioning influence etc., need to adjust construction plan in time, but since progress updates Not in time, and based on the construction schedule that construction network figure is worked out, it cannot intuitively reflect and construction schedule is caused to deviate Key factor, thus targeted construction program cannot be compiled in time.
Summary of the invention
For overcome the deficiencies in the prior art, the live Schedule monitoring system based on threedimensional model that the present invention provides a kind of And method, it effectively by BIM in conjunction with construction schedule, can realize that the intercommunication of information is shared, to reach engineering construction Real-time progress overall process, round-the-clock, total involvement target, while can be improved the efficiency and essence of project progress monitoring management Degree.
In order to realize appeal purpose, the invention provides the following technical scheme:
A kind of live Schedule monitoring system based on threedimensional model, including BIM model equipment, progress compiling module, construction Progress analog module, monitoring management platform and external smart mobile device;The BIM model equipment and the progress compiling module Connection, the progress compiling module are connect with the monitoring management platform with external smart mobile device;
The BIM model equipment generates BIM model, and BIM model is stored in service for obtaining modelling data In device;
The progress compiling module is used to obtain the related data of BIM model inner member, works out construction schedule;
The construction speed analog module is used for according to BIM model and construction schedule, by construction schedule and BIM Model is associated, and each of work progress is worked and is shown with visualizing the building element virtual construction process of image Show, additional time, dimension, passed through construction simulation analysis construction speed of the building element under scheduling;
External smart mobile device for automatic collection construction site Internet of Things perception data and according to the contents of a project to prison The actual progress of keyholed back plate platform input site operation;
Monitoring management platform is for actual progress to be compared to obtain project progress information, engineering with construction schedule Progress msg is shown in BIM model with coloring mode.
The live Schedule monitoring method based on threedimensional model that the present invention also provides a kind of, this method comprises the following steps:
S1. modelling data are obtained, establish BIM model, and BIM model is stored in server;
S2. according to the related data of BIM model inner member, construction schedule is worked out;
S3. according to BIM model and construction schedule, construction schedule and BIM model are associated, and will construction The work of each of process shows that additional time, dimension, passed through to visualize the building element virtual construction process of image Construction simulation analysis construction speed of the building element under scheduling;
S4. the actual progress of site operation is inputted to monitoring management platform by external smart mobile device;
S5. the BIM model for being associated with construction schedule is directed into monitoring management platform, carries out Schedule monitoring, it will Actual progress is compared to obtain project progress information with construction schedule, and project progress information is in BIM model with coloring Mode is shown.
Further, in the step S2, the concrete operations of construction schedule are worked out are as follows: use the decomposition mould of WBS first Project decomposition at multiple enforceable components, is judged and is inputted the planned value of duration by formula;In conjunction with resource factors, space factor With the influence of technological factor, milestone node being determined, then determining each component deadline, creation time list simultaneously presses outline Form is organized, and forms construction schedule, and whether the arrangement of time for checking construction schedule is reasonable.
Further, in the step S3, by Visual Simulation or Time liner software by construction speed Plan is associated with BIM model.The project plan can be shown in the work progress under scheduling by 3D component Come, the inter-related task that thus mode generates automatically associates on BIM model equipment, when encounter design alteration or construction drawing modification When, by adjusting construction speed figure, scheduling can also change automatically.
Further, in the step S5, project progress include the duration in advance, normally complete with the duration lag three parts, For the ease of intuitive compartment analysis, color that project progress uses is different, project progress with coloring mode BIM model component Middle display, wherein the duration shifts to an earlier date part to be indicated with green, and normally completing part indicates that the duration, lagging portion was with red with yellow It is highlighted to indicate.
Further, the duration lags, then the project progress analysis software mounted by monitoring management platform is analyzed, raw At progress hysteresis reason analytical statement and progress correction report, construction schedule adjusted is formed, and be updated to three-dimensional BIM In model, while correction report being associated in BIM model, staff is facilitated to consult.
Compared with prior art, the invention has the following advantages:
1. the present invention is inputted by passing through the Internet of Things perception data of external smart mobile device automatic collection construction site The actual progress of site operation carries out sorted generalization and arrangement to the data of acquisition, construction speed is combined with BIM model, The work progress at scene is resolved into several progress component nodes in conjunction with WBS, is compiled into establishment project construction schedule, favorably In discovery construction gap, takes timely measure, carry out correction adjustment;Design alteration, construction drawing change are being encountered, it also can be quick Ground associated modification schedule.
2. work out project construction schedule, using WBS resolution model by Project decomposition at the component for being easier to management Node.In work progress, metering, construction speed, data are mounted around WBS process, unified to carry out calling in for data;It constructs The 4D construction simulation of progress, can recognize in advance in work progress there may be the problem of, ancillary staff compiles more For the construction schedule of efficiently and accurately.
3. field personnel logs in monitoring management platform, typing scene work by external smart mobile device, such as mobile phone Journey progress msg, while by the inclined of component coloring mode display engineering actual progress in three-dimensional BIM model and target advance Difference facilitates staff that can get information about engineering overall progress in time, timely solution of finding the problem, convenient for project progress Real time monitoring.Project progress is mounted by monitoring management platform and analyzes software, and when project progress deviates target advance, generation is entangled Report partially, instructs staff to adjust in time.Reduce the time loss of pilot process bring, can effectively improve engineering construction into Degree.
Detailed description of the invention
Fig. 1 is a kind of flow diagram of the live Schedule monitoring based on threedimensional model of the present invention.
Specific embodiment
The invention will be further described with embodiment with reference to the accompanying drawing.It should be noted that specific reality of the invention It applies example and is intended merely to the clearer description technique scheme of energy, and cannot function as a kind of limitation of the scope of the present invention.
A kind of live Schedule monitoring system based on threedimensional model, including BIM model equipment, progress compiling module, construction Progress analog module, monitoring management platform and external smart mobile device;The BIM model equipment and the progress compiling module Connection, the progress compiling module are connect with the monitoring management platform with external smart mobile device;
The BIM model equipment generates BIM model, and BIM model is stored in service for obtaining modelling data In device;
The progress compiling module is used to obtain the related data of BIM model inner member, works out construction schedule;
The construction speed analog module is used for according to BIM model and construction schedule, by construction schedule and BIM Model is associated, and each of work progress is worked and is shown with visualizing the building element virtual construction process of image Show, additional time, dimension, passed through construction simulation analysis construction speed of the building element under scheduling;
External smart mobile device for automatic collection construction site Internet of Things perception data and according to the contents of a project to prison The actual progress of keyholed back plate platform input site operation;
Monitoring management platform is for actual progress to be compared to obtain project progress information, engineering with construction schedule Progress msg is shown in BIM model with coloring mode.
The present invention is shared by the intercommunication that BIM in conjunction with construction schedule, can be realized to information, to reach engineering Construct real-time progress overall process, round-the-clock, total involvement target, at the same can be improved project progress monitoring management efficiency and Precision.
Referring to Fig. 1, the present invention also provides a kind of live Schedule monitoring method based on threedimensional model, this method includes such as Lower step:
S1. modelling data are obtained, establish BIM model, and BIM model is stored in server;
S2. according to the related data of BIM model inner member, construction schedule is worked out;
S3. according to BIM model and construction schedule, construction schedule and BIM model are associated, and will construction The work of each of process shows that additional time, dimension, passed through to visualize the building element virtual construction process of image Construction simulation analysis construction speed of the building element under scheduling;
S4. the actual progress of site operation is inputted to monitoring management platform by external smart mobile device;
S5. the BIM model for being associated with construction schedule is directed into monitoring management platform, carries out Schedule monitoring, it will Actual progress is compared to obtain project progress information with construction schedule, and project progress information is in BIM model with coloring Mode is shown.
In the step S2, the concrete operations of construction schedule are worked out are as follows: first divided project with the resolution model of WBS Solution judges and inputs the planned value of duration at multiple enforceable components;In conjunction with resource factors, space factor and technological factor Influence, determine milestone node, then determine each component deadline, creation time list and by the form of outline by its group It knits, forms construction schedule, and whether the arrangement of time for checking construction schedule is reasonable.
In the step S5, project progress include the duration in advance, normally complete with the duration lag three parts, for the ease of straight Compartment analysis is seen, the color that project progress uses is different, and project progress is shown in the component of BIM model with coloring mode, In, the duration shifts to an earlier date part to be indicated with green, and normally complete part is indicated with yellow, and duration lagging portion is indicated so that red is highlighted. It should be noted that project progress coloring is for the ease of distinguishing different process schedules, coloring selection is not unique.
When there is the case where duration lag, then the project progress analysis software mounted by monitoring management platform is divided Analysis generates progress hysteresis reason analytical statement and progress correction report, forms construction schedule adjusted, and be updated to three It ties up in BIM model, while correction report being associated in BIM model, staff is facilitated to consult.
Above description is the detailed description for the present invention preferably possible embodiments, but embodiment is not limited to this hair Bright patent claim, it is all the present invention suggested by technical spirit under completed same changes or modifications change, should all belong to In the covered the scope of the patents of the present invention.

Claims (6)

1. a kind of live Schedule monitoring system based on threedimensional model, which is characterized in that worked out including BIM model equipment, progress Module, construction speed analog module, monitoring management platform and external smart mobile device;The BIM model equipment and it is described into Compiling module connection is spent, the progress compiling module is connect with the monitoring management platform with external smart mobile device;
The BIM model equipment generates BIM model, and BIM model is stored in server for obtaining modelling data It is interior;
The progress compiling module is used to obtain the related data of BIM model inner member, works out construction schedule;
The construction speed analog module is used for according to BIM model and construction schedule, by construction schedule and BIM model It is associated, and each of work progress is worked and is shown with visualizing the building element virtual construction process of image, Additional time, dimension, passed through construction simulation analysis construction speed of the building element under scheduling;
External smart mobile device for automatic collection construction site Internet of Things perception data and according to the contents of a project to monitoring pipe The actual progress of platform input site operation;
Monitoring management platform is for actual progress to be compared to obtain project progress information, project progress with construction schedule Information is shown in BIM model with coloring mode.
2. a kind of live Schedule monitoring method based on threedimensional model as described in claim 1, which is characterized in that including as follows Step:
S1. modelling data are obtained, establish BIM model, and BIM model is stored in server;
S2. according to the related data of BIM model inner member, construction schedule is worked out;
S3. according to BIM model and construction schedule, construction schedule and BIM model are associated, and by work progress Each of work show that dimension, passes through building additional time with the building element virtual construction process for visualizing image Construction simulation analysis construction speed of the component under scheduling;
S4. the actual progress of site operation is inputted to monitoring management platform by external smart mobile device;
S5. the BIM model for being associated with construction schedule is directed into monitoring management platform, carries out Schedule monitoring, it will be practical Progress is compared to obtain project progress information with construction schedule, and project progress information is in BIM model with coloring mode Display.
3. a kind of live Schedule monitoring method based on threedimensional model according to claim 2, which is characterized in that the step In rapid S2, the concrete operations of construction schedule are worked out are as follows: use the resolution model of WBS by Project decomposition at multiple implementable first Component, judge and input the planned value of duration;In conjunction with the influence of resource factors, space factor and technological factor, in determining Then journey upright stone tablet node determines each component deadline, creation time list is simultaneously organized by the form of outline, and formation is applied Work schedule, and whether the arrangement of time for checking construction schedule is reasonable.
4. a kind of live Schedule monitoring method based on threedimensional model according to claim 2, which is characterized in that the step In rapid S3, construction schedule and BIM model are associated by Visual Simulation or Time liner software.
5. a kind of live Schedule monitoring method based on threedimensional model according to claim 2, which is characterized in that the step In rapid S5, project progress include the duration in advance, normally complete and lag three parts with the duration, project progress is with coloring mode in BIM It is shown in the component of model, wherein the duration shifts to an earlier date part to be indicated with green, and normally complete part is indicated with yellow, duration lag Part is indicated so that red is highlighted.
6. a kind of live Schedule monitoring method based on threedimensional model according to claim 5, which is characterized in that the duration is stagnant Afterwards, then the project progress analysis software mounted by monitoring management platform is analyzed, and progress hysteresis reason analytical statement is generated It rectifies a deviation and reports with progress, form construction schedule adjusted, and be updated in three-dimensional BIM model, while correction being reported It is associated in BIM model.
CN201811291756.0A 2018-10-31 2018-10-31 A kind of live Schedule monitoring system and method based on threedimensional model Pending CN109377066A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811291756.0A CN109377066A (en) 2018-10-31 2018-10-31 A kind of live Schedule monitoring system and method based on threedimensional model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811291756.0A CN109377066A (en) 2018-10-31 2018-10-31 A kind of live Schedule monitoring system and method based on threedimensional model

Publications (1)

Publication Number Publication Date
CN109377066A true CN109377066A (en) 2019-02-22

Family

ID=65396777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811291756.0A Pending CN109377066A (en) 2018-10-31 2018-10-31 A kind of live Schedule monitoring system and method based on threedimensional model

Country Status (1)

Country Link
CN (1) CN109377066A (en)

Cited By (51)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109784781A (en) * 2019-03-04 2019-05-21 中铁隧道局集团有限公司 A kind of project management system served as theme with project progress, method and storage medium
CN109933863A (en) * 2019-02-26 2019-06-25 杭州吉风建筑科技有限公司 One kind being used for power plant's construct platform
CN109978387A (en) * 2019-03-28 2019-07-05 浙江鑫润工程管理有限公司 A kind of BIM engineering information management method and system
CN109993449A (en) * 2019-04-08 2019-07-09 中交一公局海威工程建设有限公司 Laboratory equipment management method, BIM Visualization Platform, equipment and medium
CN110008588A (en) * 2019-04-04 2019-07-12 南京林业大学 Multidimensional integrated highway engineering construction progress msg management system and method
CN110084526A (en) * 2019-05-05 2019-08-02 广西路桥工程集团有限公司 A kind of visualization project management monitoring system based on BIM+WBS
CN110119774A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A kind of contrast difference's method based on Building Information Model 4D progress Yu outdoor scene progress
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN110378588A (en) * 2019-07-10 2019-10-25 重庆大学 A kind of contract spatialization system
CN110428236A (en) * 2019-08-15 2019-11-08 宁夏信友监理咨询管理股份有限公司 A kind of communication engineering construction whole process engineering consulting management system
CN110443485A (en) * 2019-07-30 2019-11-12 上海建工集团股份有限公司 Engineering construction various dimensions plan correlating method and system
CN110505452A (en) * 2019-08-26 2019-11-26 广东电网有限责任公司 A kind of capital construction power transmission engineering Schedule monitoring method and monitoring system
CN110599027A (en) * 2019-09-09 2019-12-20 中铁建设集团有限公司 Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system
CN110634186A (en) * 2019-08-13 2019-12-31 中铁上海工程局集团有限公司 Arch cover method underground excavation construction method based on BIM
CN110750827A (en) * 2019-10-10 2020-02-04 贵州百胜工程建设咨询有限公司 Progress management method based on BIM
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN111062090A (en) * 2019-12-20 2020-04-24 长江勘测规划设计研究有限责任公司 Progress management method and device based on BIM
CN111145354A (en) * 2019-12-31 2020-05-12 北京恒华伟业科技股份有限公司 BIM data model identification method and device
CN111311187A (en) * 2020-02-20 2020-06-19 广州易达建信科技开发有限公司 Revit-based project progress monitoring method, system and storage medium
CN111311203A (en) * 2020-04-01 2020-06-19 陕西工业职业技术学院 BIM-based engineering progress control system
CN111340458A (en) * 2020-03-17 2020-06-26 中铁城建集团有限公司 Construction progress informatization management method
CN111369226A (en) * 2020-03-27 2020-07-03 陕西工业职业技术学院 BIM-based project progress supervision system
CN111445218A (en) * 2020-04-22 2020-07-24 中铁二十一局集团电务电化工程有限公司 BIM-based project progress management method, device, equipment and storage medium
CN111444565A (en) * 2020-03-26 2020-07-24 北京中交京纬公路造价技术有限公司 Project collaborative simulation system based on mobile internet
CN111539690A (en) * 2020-04-28 2020-08-14 悉地(苏州)勘察设计顾问有限公司 Construction project collaborative management method and system based on BIM
CN111695884A (en) * 2020-08-17 2020-09-22 广东新视野信息科技股份有限公司 Internet of things big data visualization method and system based on smart construction site
CN111724016A (en) * 2019-03-21 2020-09-29 上海易智链智能科技发展有限公司 BIM-based material dynamic management method and system
CN111783270A (en) * 2020-03-17 2020-10-16 江西武大扬帆科技有限公司 Construction progress digital simulation method based on BIM technology
CN111967838A (en) * 2020-07-16 2020-11-20 译筑信息科技(上海)有限公司 Intelligent 4D plan management and control method based on BIM
CN112070482A (en) * 2020-09-10 2020-12-11 广州市第二装修有限公司 Engineering project integrated management method and device, computer equipment and storage medium
CN112365113A (en) * 2020-08-20 2021-02-12 中国铁道科学研究院集团有限公司电子计算技术研究所 BIM-based four-power-station-group design simulation and resource dynamic adjustment method and system
CN112365111A (en) * 2020-02-28 2021-02-12 中国二十二冶集团有限公司 Project progress management method
CN112488664A (en) * 2020-12-14 2021-03-12 广西路桥工程集团有限公司 Project metering system based on WBS
CN112486613A (en) * 2020-11-27 2021-03-12 东南大学 Engineering project Web end construction progress management method and device and readable storage medium
CN112507430A (en) * 2020-12-02 2021-03-16 国网江西省电力有限公司建设分公司 Visual fusion method of BIM (building information modeling) model and engineering project
CN112650820A (en) * 2020-12-31 2021-04-13 天津博迈科海洋工程有限公司 Method for tracking production data of oil-gas module structural part
CN113177768A (en) * 2020-11-10 2021-07-27 国网青海省电力公司 Intelligent engineering platform based on comprehensive digital management of capital construction whole process
CN113222564A (en) * 2021-06-09 2021-08-06 合肥优尔电子科技有限公司 Progress management system and method based on BIM system
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113268797A (en) * 2021-05-18 2021-08-17 广州市第三建筑装修有限公司 BIM-based indoor decoration project intelligent management method and system
CN113360583A (en) * 2021-06-15 2021-09-07 东南大学 Construction progress visualization method based on BIM model and monitoring image comparison
CN113379324A (en) * 2021-07-06 2021-09-10 山东电力工程咨询院有限公司 Construction site whole-course monitoring method and system
CN113450018A (en) * 2021-07-16 2021-09-28 中国化学工程第十一建设有限公司 Project progress processing method, device and equipment and storage medium
CN113656864A (en) * 2021-07-27 2021-11-16 天一建设发展有限公司 Building construction method and system based on BIM, computer device and storage medium
CN113673967A (en) * 2021-09-09 2021-11-19 国网江苏省电力有限公司建设分公司 BIM technology-based ultrahigh tower construction progress management system and method
CN114117596A (en) * 2021-11-15 2022-03-01 国能大渡河猴子岩发电有限公司 Real-time monitoring and management method for water conservancy and hydropower engineering
CN115794759A (en) * 2023-02-08 2023-03-14 中建深圳装饰有限公司 BIM-based multi-target construction data sharing transmission method
CN115983429A (en) * 2022-12-02 2023-04-18 广东中科云所信息科技有限公司 BIM model-based construction strategy optimization method, system, terminal and medium
CN116029682A (en) * 2023-03-29 2023-04-28 北京中昌工程咨询有限公司 Construction progress management method and system based on BIM technology
CN117010841A (en) * 2023-08-31 2023-11-07 广东中联建建筑工程有限公司 Method for controlling key line by integrating construction progress plan and BIM model
CN117408643A (en) * 2023-12-12 2024-01-16 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105512822A (en) * 2015-12-14 2016-04-20 国家电网公司 Construction progress management method based on visualization technology
CN105550802A (en) * 2015-12-09 2016-05-04 中铁隧道集团有限公司 Method for checking construction progress in underground-excavated metro station inter-zone tunnel model
CN106897817A (en) * 2017-01-22 2017-06-27 朗坤智慧科技股份有限公司 A kind of construction speed Visualized management system and method based on augmented reality
DE102016004382A1 (en) * 2016-04-08 2017-10-12 Liebherr-Werk Biberach Gmbh Method and device for planning and / or controlling and / or simulating the operation of a construction machine
CN107273640A (en) * 2017-07-11 2017-10-20 黄河勘测规划设计有限公司 Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model
CN107480370A (en) * 2017-08-10 2017-12-15 嘉兴恒创电力设计研究院有限公司 A kind of construction speed Forecasting Methodology and system based on BIM models
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105550802A (en) * 2015-12-09 2016-05-04 中铁隧道集团有限公司 Method for checking construction progress in underground-excavated metro station inter-zone tunnel model
CN105512822A (en) * 2015-12-14 2016-04-20 国家电网公司 Construction progress management method based on visualization technology
DE102016004382A1 (en) * 2016-04-08 2017-10-12 Liebherr-Werk Biberach Gmbh Method and device for planning and / or controlling and / or simulating the operation of a construction machine
CN106897817A (en) * 2017-01-22 2017-06-27 朗坤智慧科技股份有限公司 A kind of construction speed Visualized management system and method based on augmented reality
CN107273640A (en) * 2017-07-11 2017-10-20 黄河勘测规划设计有限公司 Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model
CN107480370A (en) * 2017-08-10 2017-12-15 嘉兴恒创电力设计研究院有限公司 A kind of construction speed Forecasting Methodology and system based on BIM models
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Cited By (62)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109933863A (en) * 2019-02-26 2019-06-25 杭州吉风建筑科技有限公司 One kind being used for power plant's construct platform
CN109784781A (en) * 2019-03-04 2019-05-21 中铁隧道局集团有限公司 A kind of project management system served as theme with project progress, method and storage medium
CN111724016A (en) * 2019-03-21 2020-09-29 上海易智链智能科技发展有限公司 BIM-based material dynamic management method and system
CN109978387A (en) * 2019-03-28 2019-07-05 浙江鑫润工程管理有限公司 A kind of BIM engineering information management method and system
CN110008588A (en) * 2019-04-04 2019-07-12 南京林业大学 Multidimensional integrated highway engineering construction progress msg management system and method
CN109993449A (en) * 2019-04-08 2019-07-09 中交一公局海威工程建设有限公司 Laboratory equipment management method, BIM Visualization Platform, equipment and medium
CN110084526B (en) * 2019-05-05 2022-05-31 广西路桥工程集团有限公司 BIM + WBS-based visual project management monitoring system
CN110084526A (en) * 2019-05-05 2019-08-02 广西路桥工程集团有限公司 A kind of visualization project management monitoring system based on BIM+WBS
CN110119774A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A kind of contrast difference's method based on Building Information Model 4D progress Yu outdoor scene progress
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN110378588A (en) * 2019-07-10 2019-10-25 重庆大学 A kind of contract spatialization system
CN110378588B (en) * 2019-07-10 2023-02-03 重庆大学 Contract spatialization system
CN110443485A (en) * 2019-07-30 2019-11-12 上海建工集团股份有限公司 Engineering construction various dimensions plan correlating method and system
CN110634186A (en) * 2019-08-13 2019-12-31 中铁上海工程局集团有限公司 Arch cover method underground excavation construction method based on BIM
CN110428236A (en) * 2019-08-15 2019-11-08 宁夏信友监理咨询管理股份有限公司 A kind of communication engineering construction whole process engineering consulting management system
CN110505452A (en) * 2019-08-26 2019-11-26 广东电网有限责任公司 A kind of capital construction power transmission engineering Schedule monitoring method and monitoring system
CN110599027A (en) * 2019-09-09 2019-12-20 中铁建设集团有限公司 Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN110750827A (en) * 2019-10-10 2020-02-04 贵州百胜工程建设咨询有限公司 Progress management method based on BIM
CN111062090A (en) * 2019-12-20 2020-04-24 长江勘测规划设计研究有限责任公司 Progress management method and device based on BIM
CN111145354A (en) * 2019-12-31 2020-05-12 北京恒华伟业科技股份有限公司 BIM data model identification method and device
CN111145354B (en) * 2019-12-31 2024-02-13 北京恒华伟业科技股份有限公司 BIM data model identification method and device
CN111311187A (en) * 2020-02-20 2020-06-19 广州易达建信科技开发有限公司 Revit-based project progress monitoring method, system and storage medium
CN112365111A (en) * 2020-02-28 2021-02-12 中国二十二冶集团有限公司 Project progress management method
CN111340458A (en) * 2020-03-17 2020-06-26 中铁城建集团有限公司 Construction progress informatization management method
CN111783270B (en) * 2020-03-17 2021-09-03 江西武大扬帆科技有限公司 Construction progress digital simulation method based on BIM technology
CN111783270A (en) * 2020-03-17 2020-10-16 江西武大扬帆科技有限公司 Construction progress digital simulation method based on BIM technology
CN111444565A (en) * 2020-03-26 2020-07-24 北京中交京纬公路造价技术有限公司 Project collaborative simulation system based on mobile internet
CN111369226A (en) * 2020-03-27 2020-07-03 陕西工业职业技术学院 BIM-based project progress supervision system
CN111311203A (en) * 2020-04-01 2020-06-19 陕西工业职业技术学院 BIM-based engineering progress control system
CN111311203B (en) * 2020-04-01 2023-08-22 陕西工业职业技术学院 Engineering progress management and control system based on BIM
CN111445218A (en) * 2020-04-22 2020-07-24 中铁二十一局集团电务电化工程有限公司 BIM-based project progress management method, device, equipment and storage medium
CN111539690A (en) * 2020-04-28 2020-08-14 悉地(苏州)勘察设计顾问有限公司 Construction project collaborative management method and system based on BIM
CN111967838A (en) * 2020-07-16 2020-11-20 译筑信息科技(上海)有限公司 Intelligent 4D plan management and control method based on BIM
CN111695884B (en) * 2020-08-17 2020-11-20 广东新视野信息科技股份有限公司 Internet of things big data visualization method and system based on smart construction site
CN111695884A (en) * 2020-08-17 2020-09-22 广东新视野信息科技股份有限公司 Internet of things big data visualization method and system based on smart construction site
CN112365113A (en) * 2020-08-20 2021-02-12 中国铁道科学研究院集团有限公司电子计算技术研究所 BIM-based four-power-station-group design simulation and resource dynamic adjustment method and system
CN112070482A (en) * 2020-09-10 2020-12-11 广州市第二装修有限公司 Engineering project integrated management method and device, computer equipment and storage medium
CN113177768A (en) * 2020-11-10 2021-07-27 国网青海省电力公司 Intelligent engineering platform based on comprehensive digital management of capital construction whole process
CN112486613A (en) * 2020-11-27 2021-03-12 东南大学 Engineering project Web end construction progress management method and device and readable storage medium
CN112507430A (en) * 2020-12-02 2021-03-16 国网江西省电力有限公司建设分公司 Visual fusion method of BIM (building information modeling) model and engineering project
CN112488664A (en) * 2020-12-14 2021-03-12 广西路桥工程集团有限公司 Project metering system based on WBS
CN112650820A (en) * 2020-12-31 2021-04-13 天津博迈科海洋工程有限公司 Method for tracking production data of oil-gas module structural part
CN113268797A (en) * 2021-05-18 2021-08-17 广州市第三建筑装修有限公司 BIM-based indoor decoration project intelligent management method and system
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113256131B (en) * 2021-06-01 2024-02-02 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of assembled building
CN113222564A (en) * 2021-06-09 2021-08-06 合肥优尔电子科技有限公司 Progress management system and method based on BIM system
CN113360583A (en) * 2021-06-15 2021-09-07 东南大学 Construction progress visualization method based on BIM model and monitoring image comparison
CN113360583B (en) * 2021-06-15 2024-05-14 东南大学 Construction progress visualization method based on BIM model and monitoring image comparison
CN113379324A (en) * 2021-07-06 2021-09-10 山东电力工程咨询院有限公司 Construction site whole-course monitoring method and system
CN113450018A (en) * 2021-07-16 2021-09-28 中国化学工程第十一建设有限公司 Project progress processing method, device and equipment and storage medium
CN113656864B (en) * 2021-07-27 2023-10-13 天一建设发展有限公司 Building construction method, system, computer device and storage medium based on BIM
CN113656864A (en) * 2021-07-27 2021-11-16 天一建设发展有限公司 Building construction method and system based on BIM, computer device and storage medium
CN113673967A (en) * 2021-09-09 2021-11-19 国网江苏省电力有限公司建设分公司 BIM technology-based ultrahigh tower construction progress management system and method
CN114117596A (en) * 2021-11-15 2022-03-01 国能大渡河猴子岩发电有限公司 Real-time monitoring and management method for water conservancy and hydropower engineering
CN115983429A (en) * 2022-12-02 2023-04-18 广东中科云所信息科技有限公司 BIM model-based construction strategy optimization method, system, terminal and medium
CN115983429B (en) * 2022-12-02 2024-04-02 中东基建科技集团有限公司 Construction strategy optimization method, system, terminal and medium based on BIM model
CN115794759A (en) * 2023-02-08 2023-03-14 中建深圳装饰有限公司 BIM-based multi-target construction data sharing transmission method
CN116029682A (en) * 2023-03-29 2023-04-28 北京中昌工程咨询有限公司 Construction progress management method and system based on BIM technology
CN117010841A (en) * 2023-08-31 2023-11-07 广东中联建建筑工程有限公司 Method for controlling key line by integrating construction progress plan and BIM model
CN117408643A (en) * 2023-12-12 2024-01-16 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform
CN117408643B (en) * 2023-12-12 2024-03-22 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform

Similar Documents

Publication Publication Date Title
CN109377066A (en) A kind of live Schedule monitoring system and method based on threedimensional model
CN105069524B (en) Planned dispatching optimization method based on big data analysis
CN104407576B (en) A kind of implementation method and control system of universal manufacturing unit
CN102880123B (en) System and method for controlling production process of petrochemical enterprise on basis of manufacturing execution system (MES) workflow
CN105786912B (en) Data collecting conversion method and device
CN109710990A (en) Construction of Rolled Concrete Dam progress-cost cooperative control method based on BIM technology
CN107993000A (en) The method of construction main flat face dynamic coordinate management based on BIM
CN109685452A (en) A kind of power supply company's item data management platform
CN109308582A (en) A kind of manufacturing execution system framework based on modularization Yu serviceization
RU2691270C2 (en) Workflow digital support system
KR100836535B1 (en) 3-dimensional system and method for construction progression managing based gis
CN106156408A (en) The building of the classification of a kind of Component-Based Development and combination works in coordination with constructing system and method
KR101717766B1 (en) Labor-based Progress Measurement for Cost and Schedule Control System in Construction Programs
CN108971807A (en) A kind of site welding construction technology intelligent management control method and management system
KR20130016620A (en) 3d process management method for bim(building information modeling)
CN108305043A (en) Single-piece flow Production MIS
CN106447519A (en) Generating system of three-dimensional sheet metal welding technology
CN113610389B (en) Prefabricated component production quality management system based on BIM and RFID
CN105678504A (en) XML-based field layer, MES, ERP integrated information integration method
CN105404966A (en) Construction method of construction process quality color rendering module based on BIM
JP2013045386A (en) Process design method, process design support system, and process design support device
KR101674101B1 (en) Project management system based information and communication technology
CN109799793A (en) Production plan making device and production plan formulating method
CN110930044A (en) Construction organization resource rapid configuration method and system
CN109978387A (en) A kind of BIM engineering information management method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190222