CN109376967B - Method for evaluating environmental protection characteristics of power grid planning - Google Patents

Method for evaluating environmental protection characteristics of power grid planning Download PDF

Info

Publication number
CN109376967B
CN109376967B CN201811530660.5A CN201811530660A CN109376967B CN 109376967 B CN109376967 B CN 109376967B CN 201811530660 A CN201811530660 A CN 201811530660A CN 109376967 B CN109376967 B CN 109376967B
Authority
CN
China
Prior art keywords
environmental protection
carbon emission
power grid
renewable energy
evaluating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811530660.5A
Other languages
Chinese (zh)
Other versions
CN109376967A (en
Inventor
田鑫
李雪亮
吴健
李琨
曾军
赵龙
王艳
郑志杰
张�杰
牟宏
汪湲
高效海
张丽娜
张玉跃
付一木
魏鑫
袁振华
孙东磊
牟颖
刘冬
张栋梁
张家宁
王男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811530660.5A priority Critical patent/CN109376967B/en
Publication of CN109376967A publication Critical patent/CN109376967A/en
Application granted granted Critical
Publication of CN109376967B publication Critical patent/CN109376967B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • Y02P90/82Energy audits or management systems therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • Y02P90/84Greenhouse gas [GHG] management systems

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Development Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a method for evaluating environmental protection characteristics of power grid planning, which comprises the following steps: s1, calculating the ratio of the online electric quantity of the renewable energy and the energy abandoning rate of the renewable energy to evaluate the admitting ability of the renewable energy; s2, calculating carbon emission in the system operation and power grid operation processes, and evaluating the carbon emission; s3, evaluating the influence on the surrounding environment in the construction process of the power grid planning project by combining six indexes of noise, a power frequency electric field, a power frequency magnetic field, equipment environmental protection rate, land utilization efficiency and city landscape cooperative scheduling; and S4, generating an evaluation report according to the evaluation results of the steps S1-S3. The method not only evaluates the acceptance capability of different schemes on renewable energy sources, the carbon emission and other indexes, but also evaluates the adverse effect on the surrounding environment in the construction process of the power grid planning project.

Description

Method for evaluating environmental protection characteristics of power grid planning
Technical Field
The invention mainly relates to the related fields of power system operation analysis, reliability evaluation and the like, in particular to a method for evaluating environmental protection characteristics of power grid planning.
Background
The power grid planning scheme has important significance for promoting the consumption of renewable energy and reducing carbon emission, so the environmental protection of the planning scheme needs to be evaluated. In addition, the construction of power transmission and transformation projects inevitably needs to enter densely populated areas, and the influence of the power transmission and transformation projects on natural ecology such as land, water sources and the like and the influence of electromagnetic interference caused by high-voltage power transmission lines on human health and daily life are all problems needing attention.
At present, the research on the environmental protection of a power grid generally considers directly generated environmental pollution or influence, and the evaluation on the environmental protection of power grid planning is not accurate, so that certain social influence can be generated when the power grid is implemented on the ground.
Disclosure of Invention
In order to solve the problems, the invention provides a method for evaluating environmental protection characteristics of power grid planning, which not only evaluates the acceptance capability of different schemes on renewable energy sources, carbon emission and other indexes, but also evaluates the adverse effects on the surrounding environment in the construction process of a power grid planning project.
The technical scheme of the invention is realized by the following modes:
the invention provides a method for evaluating environmental protection characteristics of power grid planning, which comprises the following steps:
s1, calculating the ratio of the online electric quantity of the renewable energy and the energy abandoning rate of the renewable energy to evaluate the admitting ability of the renewable energy;
s2, calculating carbon emission in the system operation and power grid operation processes, and evaluating the carbon emission;
s3, evaluating the influence on the surrounding environment in the construction process of the power grid planning project by combining six indexes of noise, a power frequency electric field, a power frequency magnetic field, equipment environmental protection rate, land utilization efficiency and city landscape cooperative scheduling;
and S4, generating an evaluation report according to the evaluation results of the steps S1-S3.
Further, the specific implementation process of step S1 is as follows: and respectively calculating a net electric quantity ratio a1 of renewable energy sources and a renewable energy abandon rate a2, wherein the renewable energy receiving capacity a3 is (a1+ a2)/2 is 100.
Further, the calculation formula of the renewable energy abandon rate is as follows:
Figure BDA0001905572890000021
further, the specific implementation process of step S2 is as follows:
obtaining system running carbon emission through system running simulation, and converting the system running carbon emission into a system running carbon emission score according to the percentage;
respectively calculating the grid loss carbon emission and the SF6 leakage rate, wherein the running carbon emission score of the power grid is (grid loss carbon emission + SF6 leakage rate)/2 x 100;
and (4) calculating the score of the carbon emission size, namely (the system operation carbon emission score + the power grid operation carbon emission score)/2.
Further, the calculation formula of the grid loss carbon emission is as follows: and grid loss carbon emission is grid loss electricity quantity and grid reference emission factor.
Further, the formula for calculating the leakage rate of SF6 is as follows:
Figure BDA0001905572890000031
further, the specific implementation process of step S3 is as follows:
s31: collecting operation sounds of construction machinery and power equipment, wherein when the operation sounds completely accord with the building construction site boundary noise limit value, the noise score is 100, otherwise, the noise score is 0;
s32: collecting or calculating the vertical component of the electric field intensity at a position 1.5m away from the ground, and when the vertical component is smaller than the national standard limit, the power frequency electric field is divided into 100, otherwise, the power frequency electric field is 0;
s33: respectively calculating the magnetic field generated by the current of each wire by applying an ampere loop law, and then superposing the results to obtain the magnetic field intensity around the wire, wherein when the magnetic field intensity is less than a power frequency limit value of 0.1mT, the power frequency magnetic field is divided into 100, otherwise, the power frequency magnetic field is 0;
s34: counting the environmental protection rate of the equipment, wherein when the environmental protection rate of the equipment is greater than the proportion specified by the national environmental protection, the environmental protection rate of the equipment is 100, otherwise, the environmental protection rate of the equipment is 0;
s35: using formulas
Figure BDA0001905572890000032
Calculating land resource utilization efficiency, wherein the land resource utilization efficiency is divided into 100 land resource utilization efficiency;
s36: randomly sampling various types of landscape live-action photos in a planning range, finally selecting representative landscapes as sample materials for evaluation, and predicting the coordination degree of a planned line and the urban landscape by adopting a picture stacking method to obtain an urban landscape coordination degree score;
s36: and scoring the influence on the surrounding environment in the construction process of the power grid planning project to be the sum of the scores in the steps S31-S35.
Further, the specific implementation process of step S4 is as follows: a summary table containing the index names and their scores is generated based on the scores of the respective indexes in steps S1-S3.
The invention has the beneficial effects that:
the scheme is based on the acceptance capability of renewable energy sources, carbon emission and other indexes, the environmental protection performance of the planning scheme is evaluated, in addition, the construction of the power transmission and transformation project inevitably enters densely populated areas, the influence of the power transmission and transformation project on natural ecology such as land and water sources and the influence of electromagnetic interference caused by high-voltage power transmission lines on human health and daily life are all problems needing attention, and therefore, the method and the system evaluate the influence of the power grid planning project on the surrounding environment in the construction process by combining six indexes of noise, a power frequency electric field, a power frequency magnetic field, equipment environmental protection rate, land utilization efficiency and city landscape co-scheduling, and realize comprehensive and careful evaluation on the environmental protection performance.
Drawings
FIG. 1 is an overall flow diagram of the method of the present invention.
Detailed Description
The following detailed description of the embodiments of the present invention is provided in conjunction with the accompanying drawings, and the following disclosure provides specific embodiments of the apparatus and method for implementing the invention, so that those skilled in the art can more clearly understand how to implement the invention. To simplify the disclosure of the present invention, the components and arrangements of specific examples are described below. Furthermore, the present invention may repeat reference numerals and/or letters in the various examples. This repetition is for the purpose of simplicity and clarity and does not in itself dictate a relationship between the various embodiments or configurations discussed. It should be noted that the components illustrated in the figures are not necessarily drawn to scale. Descriptions of well-known components and processing techniques and procedures are omitted so as to not unnecessarily limit the invention. It should be understood that while the invention has been described in conjunction with the preferred specific embodiments thereof, that these are set forth merely for purposes of illustration and are not intended to limit the scope of the invention.
Examples
As shown in fig. 1, the present invention provides a method for evaluating environmental protection characteristics of power grid planning, where the method includes:
and S1, calculating the ratio of the online electric quantity of the renewable energy and the energy abandoning rate of the renewable energy to evaluate the admitting ability of the renewable energy. The specific implementation process is as follows: and respectively calculating a net electric quantity ratio a1 of renewable energy sources and a renewable energy abandon rate a2, wherein the renewable energy receiving capacity a3 is (a1+ a2)/2 is 100.
The ratio of the renewable energy on-grid electricity quantity refers to the ratio of the renewable energy on-grid electricity quantity to the total power supply quantity of a power grid. In the operation process of the power grid, the phenomena of wind abandonment, light abandonment and the like can be inevitably generated. In the process of planning the power grid, the energy abandon rate of the renewable energy sources should be reduced as much as possible, and the consumption capacity of the power grid to the renewable energy sources is improved. The energy rejection of renewable energy sources is defined as:
Figure BDA0001905572890000051
and S2, calculating the carbon emission during the operation of the system and the operation of the power grid, and estimating the carbon emission.
The specific implementation process of step S2 is as follows:
1) different power grid planning schemes have influence on the receiving capacity of different types of power supplies, and a good power grid planning scheme is coordinated with the power supply structure and the layout, so that a low-carbon power supply is received as much as possible, and the carbon emission of the system operation is reduced. The carbon emission during system operation refers to the carbon emission caused by the supply load of the system under the planning scheme of the power grid to be selected. The index may be calculated by running simulations and then converted to a system running carbon emission score in percent.
2) The power grid also causes carbon emission during operation, and mainly comprises two types: one is the generation extra carbon emissions due to grid line loss; the other type is SF6 leakage caused by SF6 equipment widely adopted in the operation process of the power grid. And respectively calculating the grid loss carbon emission and the SF6 leakage rate, wherein the running carbon emission score of the power grid is (grid loss carbon emission + SF6 leakage rate)/2 x 100.
Wherein, the calculation formula of the network loss carbon emission is as follows: and grid loss carbon emission is grid loss electricity quantity and grid reference emission factor. The formula for calculating the SF6 leakage rate is as follows:
Figure BDA0001905572890000061
3) and (4) calculating the score of the carbon emission size, namely (the system operation carbon emission score + the power grid operation carbon emission score)/2.
And S3, evaluating the influence on the surrounding environment in the construction process of the power grid planning project by combining six indexes of noise, power frequency electric field, power frequency magnetic field, equipment environmental protection rate, land utilization efficiency and city landscape co-scheduling.
The specific implementation process of step S3 is as follows:
s31: in the construction of power grid planning projects, large equipment such as cranes are generally used, and the surrounding environment is severely interfered by mechanical noise generated by the equipment during use. Meanwhile, some power equipment also generates various noises and the like during operation, such as various noises generated by a transformer and a reactor. Therefore, during the construction of the power grid project, the design of the used instruments, equipment and structures is guaranteed to meet various national noise requirements.
The scoring principle of the step is as follows: collecting the operation sounds of construction machinery and power equipment, and when the operation sounds all accord with the noise limit value of the construction site boundary, the noise score is 100, otherwise, the noise score is 0.
S32: the power frequency electric field of the three-phase alternating current transmission line is the result of the combined action of the charges of the three-phase wires, and for the electric field, the earth can be similar to a conductor, the direction of the electric field intensity of the ground surface is basically vertical to the ground, and the maximum value of the electric field intensity is approximately equal to the component vertical to the ground in the vicinity of 1.5m above the ground. Therefore, in the environmental impact evaluation, the vertical component of the electric field strength at 1.5m from the ground is generally used as the evaluation value of the power frequency electric field. The size of the power frequency electric field generated by the power transmission line is related to various factors such as voltage grade, wire distance to ground, wire arrangement mode, line return number and the like, and a method combining analog analogy and theoretical calculation can be generally adopted.
The scoring principle of the step is as follows: and collecting or calculating the vertical component of the electric field intensity at a position 1.5m away from the ground, and when the vertical component is smaller than the national standard limit value, the power frequency electric field score is 100, otherwise, the power frequency electric field score is 0.
S33: under the power frequency condition, the magnetic field of the line is generated only by current, the ampere loop law can be applied to calculate the magnetic field generated by the current of each wire respectively, and the results are superposed to obtain the magnetic field intensity around the wires. The power frequency limit value of 0.1mT of the international radiation protection association for public radiation all day is generally used as the evaluation standard of the power frequency magnetic field.
The scoring principle of the step is as follows: respectively calculating the magnetic field generated by the current of each wire by applying an ampere loop law, and then superposing the results to obtain the magnetic field intensity around the wire, wherein when the magnetic field intensity is less than a power frequency limit value of 0.1mT, the power frequency magnetic field is divided into 100, otherwise, the power frequency magnetic field is 0;
s34: the environmental protection rate of the equipment refers to the proportion of equipment, building materials and auxiliary construction equipment which are installed and used in the project construction and construction process and reach the relevant environmental protection regulations of the state.
The scoring principle of the step is as follows: and (4) counting the environmental protection rate of the equipment, wherein when the environmental protection rate of the equipment is greater than the proportion specified by the national environmental protection, the environmental protection rate of the equipment is 100, otherwise, the environmental protection rate of the equipment is 0.
S35: the power transmission network planning project occupies farmlands, woodlands and houses along the line, and obviously, the scheme with less resource occupation is better. Meanwhile, the larger the transmission electric quantity of the transmission line occupying the same area is, the more sufficient the utilization of the changed line is. Therefore, the environmental protection performance of the planning scheme can be measured by adopting the land resource utilization efficiency, and the expression is as follows:
Figure BDA0001905572890000071
in the formula, K is the total number of the newly added line corridors.
The scoring principle of the step is as follows: using formulas
Figure BDA0001905572890000072
And calculating the land resource utilization efficiency, wherein the land resource utilization efficiency is divided into 100 land resource utilization efficiencies.
S36: the city landscape coordinated dispatching is mainly embodied in the aspect of visual influence, and comprises subjective perception factors such as visual beauty, psychological comfort and the like. Randomly sampling various types of landscape live-action photos in a planning range, finally selecting representative landscapes as sample materials for evaluation, and predicting the coordination degree of a planned line and the urban landscape by adopting a picture stacking method to obtain the urban landscape coordination degree score.
S36: and scoring the influence on the surrounding environment in the construction process of the power grid planning project to be the sum of the scores in the steps S31-S35.
S4: a summary table containing the index names and their scores is generated based on the scores of the respective indexes in steps S1-S3.
Moreover, the scope of the present application is not intended to be limited to the particular embodiments of the process, machine, manufacture, composition of matter, means, methods and steps described in the specification. As one of ordinary skill in the art will readily appreciate from the disclosure of the present invention, processes, machines, manufacture, compositions of matter, means, methods, or steps, presently existing or later to be developed, that perform substantially the same function or achieve substantially the same result as the corresponding embodiments described herein may be utilized according to the present invention. Accordingly, the appended claims are intended to include within their scope such processes, machines, manufacture, compositions of matter, means, methods, or steps.

Claims (6)

1. A method for evaluating environmental protection characteristics of power grid planning is characterized by comprising the following steps:
s1, calculating the ratio of the online electric quantity of the renewable energy and the energy abandoning rate of the renewable energy to evaluate the admitting ability of the renewable energy;
the specific implementation process of step S1 is as follows: respectively calculating a net electric quantity ratio a1 of renewable energy sources and a renewable energy abandon rate a2, wherein the renewable energy receiving capacity a3 is (a1+ a2)/2 is 100;
the formula for calculating the energy abandon rate of the renewable energy source is as follows:
Figure FDA0003129255960000011
s2, calculating carbon emission in the system operation and power grid operation processes, and evaluating the carbon emission;
s3, evaluating the influence on the surrounding environment in the construction process of the power grid planning project by combining six indexes of noise, a power frequency electric field, a power frequency magnetic field, equipment environmental protection rate, land utilization efficiency and city landscape cooperative scheduling;
and S4, generating an evaluation report according to the evaluation results of the steps S1-S3.
2. The method for evaluating the environmental protection characteristics of power grid planning as claimed in claim 1, wherein the step S2 is implemented by:
obtaining system running carbon emission through system running simulation, and converting the system running carbon emission into a system running carbon emission score according to the percentage;
respectively calculating the grid loss carbon emission and the SF6 leakage rate, wherein the running carbon emission score of the power grid is (grid loss carbon emission + SF6 leakage rate)/2 x 100;
and (4) calculating the score of the carbon emission size, namely (the system operation carbon emission score + the power grid operation carbon emission score)/2.
3. The method for evaluating the environmental protection characteristics of power grid planning as claimed in claim 2, wherein the calculation formula of the grid loss carbon emission is as follows: and grid loss carbon emission is grid loss electricity quantity and grid reference emission factor.
4. The method for evaluating environmental protection characteristics of power grid planning as claimed in claim 2, wherein the calculation formula of the SF6 leakage rate is as follows:
Figure FDA0003129255960000021
5. the method for evaluating the environmental protection characteristics of power grid planning as claimed in claim 1, wherein the step S3 is implemented by:
s31: collecting operation sounds of construction machinery and power equipment, wherein when the operation sounds completely accord with the building construction site boundary noise limit value, the noise score is 100, otherwise, the noise score is 0;
s32: collecting or calculating the vertical component of the electric field intensity at a position 1.5m away from the ground, and when the vertical component is smaller than the national standard limit, the power frequency electric field is divided into 100, otherwise, the power frequency electric field is 0;
s33: respectively calculating the magnetic field generated by the current of each wire by applying an ampere loop law, and then superposing the results to obtain the magnetic field intensity around the wire, wherein when the magnetic field intensity is less than a power frequency limit value of 0.1mT, the power frequency magnetic field is divided into 100, otherwise, the power frequency magnetic field is 0;
s34: counting the environmental protection rate of the equipment, wherein when the environmental protection rate of the equipment is greater than the proportion specified by the national environmental protection, the environmental protection rate of the equipment is 100, otherwise, the environmental protection rate of the equipment is 0;
s35: using formulas
Figure FDA0003129255960000022
Calculating land resource utilization efficiency, wherein the land resource utilization efficiency is divided into 100 land resource utilization efficiency, and K is the total number of newly added line corridors;
s36: randomly sampling various types of landscape live-action photos in a planning range, finally selecting representative landscapes as sample materials for evaluation, and predicting the coordination degree of a planned line and the urban landscape by adopting a picture stacking method to obtain an urban landscape coordination degree score;
s36: and scoring the influence on the surrounding environment in the construction process of the power grid planning project to be the sum of the scores in the steps S31-S35.
6. The method for evaluating the environmental protection characteristics of power grid planning as claimed in claim 1, wherein the step S4 is implemented by: a summary table containing the index names and their scores is generated based on the scores of the respective indexes in steps S1-S3.
CN201811530660.5A 2018-12-14 2018-12-14 Method for evaluating environmental protection characteristics of power grid planning Active CN109376967B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811530660.5A CN109376967B (en) 2018-12-14 2018-12-14 Method for evaluating environmental protection characteristics of power grid planning

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811530660.5A CN109376967B (en) 2018-12-14 2018-12-14 Method for evaluating environmental protection characteristics of power grid planning

Publications (2)

Publication Number Publication Date
CN109376967A CN109376967A (en) 2019-02-22
CN109376967B true CN109376967B (en) 2021-09-14

Family

ID=65374661

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811530660.5A Active CN109376967B (en) 2018-12-14 2018-12-14 Method for evaluating environmental protection characteristics of power grid planning

Country Status (1)

Country Link
CN (1) CN109376967B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102315642A (en) * 2011-06-27 2012-01-11 山东电力研究院 Environmental impact assessment method of power grid planning scheme
CN103544373A (en) * 2013-09-09 2014-01-29 河海大学 Method for assessing cleanliness of intelligent power distribution network
CN108846569A (en) * 2018-06-07 2018-11-20 华北电力大学(保定) A kind of power distribution network low-carbon environment-friendly horizontal dynamic appraisal procedure
CN108985532A (en) * 2017-06-02 2018-12-11 上海交通大学 Net source lotus scheduling evaluation system and method based on carbon emission

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8600572B2 (en) * 2010-05-27 2013-12-03 International Business Machines Corporation Smarter-grid: method to forecast electric energy production and utilization subject to uncertain environmental variables

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102315642A (en) * 2011-06-27 2012-01-11 山东电力研究院 Environmental impact assessment method of power grid planning scheme
CN103544373A (en) * 2013-09-09 2014-01-29 河海大学 Method for assessing cleanliness of intelligent power distribution network
CN108985532A (en) * 2017-06-02 2018-12-11 上海交通大学 Net source lotus scheduling evaluation system and method based on carbon emission
CN108846569A (en) * 2018-06-07 2018-11-20 华北电力大学(保定) A kind of power distribution network low-carbon environment-friendly horizontal dynamic appraisal procedure

Also Published As

Publication number Publication date
CN109376967A (en) 2019-02-22

Similar Documents

Publication Publication Date Title
Rönnberg et al. On waveform distortion in the frequency range of 2 kHz–150 kHz—Review and research challenges
Yang et al. Aggregation and amplification of wind-turbine harmonic emission in a wind park
Acosta et al. Performance assessment of micro and small-scale wind turbines in urban areas
CN112487659B (en) Optimal design method and system for offshore wind farm current collection system
Blavette et al. Impact of a medium-size wave farm on grids of different strength levels
Boström et al. Linear generator connected to a resonance-rectifier circuit
CN102013700A (en) Large-and-medium-sized photovoltaic power station grid-connected characteristic research and electric energy quality evaluation method
CN107230999B (en) Regional distributed photovoltaic maximum capacity access evaluation method
Armstrong et al. Assessing the impact of the grid-connected pacific marine energy center wave farm
CN102315642B (en) Environmental impact assessment method of power grid planning scheme
CN102904254A (en) Method for simulating harmonics of power system to be connected with electrified railway
CN106295231A (en) A kind of marine wind electric field resonance suppressing method based on modal calculation
Au et al. Establishing harmonic distortion level of distribution network based on stochastic aggregate harmonic load models
Jasiński et al. Global power quality index application in virtual power plant
CN109376967B (en) Method for evaluating environmental protection characteristics of power grid planning
CN109870615A (en) Harmonic contributions assessment method suitable for industrial and mining enterprises
Chant et al. Impacts of increased photovoltaic panel utilisation on utility grid operations-a case study
Yang et al. Analysis of Thevenin equivalent network of a distribution system for solar integration studies
Nambiar et al. Quantification of voltage fluctuations caused by a wave farm connected to weak, rural electricity networks
Modi et al. Revisiting damping performance of the Queensland network under wind power penetration
CN107220785A (en) Coordinate power transmission network safety and the reasonable operational efficiency evaluation method and system of development
Huan et al. Modeling wind power plants in harmonic resonance study-A case study in Thailand
CN205160334U (en) Impact turns into electricity generation floor of electric energy
Zafeiratou et al. Wind offshore energy in the Northern Aegean Sea islanding region
Egorov et al. The Georgian power system hydro power plants install capacity review

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant