CN109242356A - Construction of the highway safe production management system based on mobile Internet - Google Patents

Construction of the highway safe production management system based on mobile Internet Download PDF

Info

Publication number
CN109242356A
CN109242356A CN201811246552.5A CN201811246552A CN109242356A CN 109242356 A CN109242356 A CN 109242356A CN 201811246552 A CN201811246552 A CN 201811246552A CN 109242356 A CN109242356 A CN 109242356A
Authority
CN
China
Prior art keywords
plant maintenance
information
engineering machinery
task
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811246552.5A
Other languages
Chinese (zh)
Inventor
黎泽芝
冯丽霞
冯平均
蒋春阳
刘路海
刘玉华
郑欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811246552.5A priority Critical patent/CN109242356A/en
Publication of CN109242356A publication Critical patent/CN109242356A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Testing And Monitoring For Control Systems (AREA)

Abstract

The present invention provides a kind of construction of the highway safe production management system based on mobile Internet, it mainly include communication module, memory module and task formulate module, communication module is for receiving the plant maintenance information that each engineering machinery periodically uploads, memory module is for storing the received plant maintenance information of communication module, task formulates the previous plant maintenance information that module is used to store according to the received current period plant maintenance information of communication module and memory module, make the plant maintenance task of each engineering machinery, and plant maintenance task is issued to each corresponding engineering machinery by communication module, memory module is also used to store tasks and formulates the plant maintenance task that module is formulated.The system can carry out unified management and record, and distribute maintenance task on schedule, to improve the efficiency and accuracy of engineering mechanical device maintenance from the maintenance condition for macroscopically grasping current each engineering machinery to maintenance, the maintenance of engineering machinery.

Description

Construction of the highway safe production management system based on mobile Internet
Technical field
The present invention relates to project management technique fields, in particular to the construction of the highway based on mobile Internet, which is kept the safety in production, manages Reason system.
Background technique
Construction of the highway refers to that energy is built in the work such as prospecting, measurement, design, maintenance, the management of Highway Structural Material, construction of the highway The height of power also has very important influence to regional transport development ability.Engineering machinery is the important composition portion of equipment manufacturing industry Point.In summary, all cubic meter of stone construction works, pavement construction and maintenance, the operation of flow-type lift and various architectural engineerings institute Mechanized equipment, referred to as engineering machinery necessary to the comprehensive mechanized construction engineering needed.
During implementing construction of the highway, need that the engineering machinery for implementing construction of the highway is managed, safeguarded and examined It repairs, to guarantee that construction of the highway carries out in which can follow the prescribed order as scheduled.By taking construction of the highway as an example, during construction of the highway, meeting A variety of different engineering machinery are used, it can be equipped with indispensable, critical dress in the construction process in each engineering machinery It sets, mechanism and component, in the case where these devices, mechanism and intact component, engineering machinery can run well, and each work In the case that journey machinery can run well and work, construction of the highway can be carried out normally as scheduled.
The mode for being managed maintenance to the engineering machinery for implementing construction of the highway at present is by manually to each participation The engineering machinery of construction of the highway safeguarded, overhauls the record of aspect, using the shortcomings that such mode is that working efficiency is lower, and The generation for the problems such as being easy error, may result in equipment missing inspection;Also, the maintenance situation of each engineering machinery cannot be total to completely It enjoys, can not be from the maintenance situation for macroscopically understanding all engineering machinery, and then construction of the highway is effectively arranged to appoint by dispatching Business.
Summary of the invention
(1) goal of the invention
To overcome above-mentioned at least one defect of the existing technology, maintenance, the maintenance of engineering machinery are unified Management and record, improve the efficiency and accuracy of engineering mechanical device maintenance, the present invention provides following technical schemes.
(2) technical solution
The invention discloses the construction of the highway safe production management systems based on mobile Internet, comprising: communication module is deposited It stores up module and task formulates module;
The communication module is for receiving the plant maintenance information that each engineering machinery periodically uploads, the memory module For storing the received plant maintenance information of the communication module, the task formulates module for connecing according to the communication module The current period plant maintenance information of receipts and the previous plant maintenance information of memory module storage, make each engineering machine The plant maintenance task of tool, and the plant maintenance task is issued to each corresponding engineering machinery by the communication module, The memory module is also used to store the task and formulates the plant maintenance task that module is formulated;Wherein,
The plant maintenance information includes at least one of the following: self-test status information, overhaul of the equipments historical information, and operation is gone through History information.
In a kind of possible embodiment, the plant maintenance task is suitable for the engineering machinery within the setting period Plant maintenance work.
In a kind of possible embodiment, the period that the engineering machinery uploads the plant maintenance information is Tt, in institute It states in the plant maintenance information of upload, the upload period of the self-test status information is T1, the upload of the inspection history information Period is T2, and the upload period of the history run information is T3, wherein T3 > T2 > T1, Tt > T1.
In a kind of possible embodiment, the plant maintenance task includes following at least a kind of equipment to engineering machinery It is overhauled: power device, transmission mechanism, walking mechanism, control device, instrument and meter.
In a kind of possible embodiment, the system further include: display module, it is following one or more for showing: institute The received current period plant maintenance information of communication module and/or previous plant maintenance information are stated, the task formulates module system The fixed current period plant maintenance task and/or previous plant maintenance task.
In a kind of possible embodiment, the system further include: be provided to the alarm module of each engineering machinery, be used for Fault message is sent to the communication module when breaking down in its affiliated engineering machinery operational process;Wherein, the failure Information includes at least one of the following: device numbering, device name, device type, equipment fault point, equipment fault reason.
In a kind of possible embodiment, the system further include: accessory management module, for according to each engineering machinery All kinds of accessory loss quantity of the plant maintenance Information Statistics uploaded and/or speed, and number is lost according to all kinds of accessories The quantity in stock of amount and/or all kinds of accessories of speed configuration.
In a kind of possible embodiment, the system further include: be provided to the Internet of Things module of each engineering machinery, use Appoint in the communication module transmission plant maintenance information, and the plant maintenance that the reception communication module issues Business.
In a kind of possible embodiment, the communication module is also used to receive the position letter that the engineering machinery is sent Breath, the task formulate module and obtain the environment letter of the engineering machinery present position according to the location information of the engineering machinery Breath, and described in formulating jointly according to the current period plant maintenance information, the previous plant maintenance information and the environmental information Plant maintenance task;Wherein, the environmental information includes at least one of the following: temperature, humidity, intensity of illumination, height above sea level.
In a kind of possible embodiment, the system further include: risk profile module, for being connect according to the communication module The current period plant maintenance information of receipts and the previous plant maintenance information and/or previous plant maintenance of memory module storage Task, the Safety Risk in Production of predictive engine machinery in the construction process;Wherein,
The Safety Risk in Production includes: that equipment fault risk and/or equipment use supersaturated risk.
(3) beneficial effect
Construction of the highway safe production management system provided by the invention based on mobile Internet can be based on internet Under the basis of communication, from the maintenance condition for macroscopically grasping current each engineering machinery, unite to maintenance, the maintenance of engineering machinery One management and record, and maintenance task is distributed on schedule, to improve the efficiency and accuracy of engineering mechanical device maintenance, it is suitable for Engineering machinery is rationally and effectively dispatched during construction of the highway, while can also predict that the safety for implementing construction of the highway is raw Wind-producing danger, to carry out the planning of task.
Detailed description of the invention
It is exemplary below with reference to the embodiment of attached drawing description, it is intended to for the explanation and illustration present invention, and cannot manage Solution is the limitation to protection scope of the present invention.
Fig. 1 is the construction of the highway safe production management system first embodiment provided by the present application based on mobile Internet Structural block diagram.
Fig. 2 is the construction of the highway safe production management system second embodiment provided by the present application based on mobile Internet Structural block diagram.
Specific embodiment
To keep the purposes, technical schemes and advantages of the invention implemented clearer, below in conjunction in the embodiment of the present invention Attached drawing, technical solution in the embodiment of the present invention is further described in more detail.
It should be understood that in the accompanying drawings, from beginning to end same or similar label indicate same or similar element or Element with the same or similar functions.Described embodiments are some of the embodiments of the present invention, rather than whole implementation Example, in the absence of conflict, the features in the embodiments and the embodiments of the present application can be combined with each other.Based in the present invention Embodiment, every other embodiment obtained by those of ordinary skill in the art without making creative efforts, It shall fall within the protection scope of the present invention.
The division of module, unit or assembly herein is only a kind of division of logic function, in actual implementation may be used To there is other division modes, such as multiple modules and/or unit can be combined or are integrated in another system.As separation The module of part description, unit, component are also possible to indiscrete may be physically separated.It is shown as a unit Component can be physical unit, may not be physical unit, it can is located at a specific place, may be distributed over grid In unit.Therefore some or all of units can be selected to realize the scheme of embodiment according to actual needs.
The construction of the highway production safety management system based on mobile Internet provided below with reference to Fig. 1 the present invention is described in detail The first embodiment of system.The present embodiment is mainly used in engineering machinery, can be under the basis based on internet communication, from macroscopic view The upper maintenance condition for grasping current each engineering machinery carries out unified management and record, and presses to maintenance, the maintenance of engineering machinery Phase distributes maintenance task, to improve the efficiency and accuracy of engineering mechanical device maintenance, is suitable for during construction of the highway to work Journey machinery is rationally and effectively dispatched.
As shown in Figure 1, the construction of the highway safe production management system provided in this embodiment based on mobile Internet, mainly Include: communication module, memory module and task formulate module.
Communication module is for receiving the plant maintenance information that each engineering machinery periodically uploads.
By taking construction of the highway as an example, a variety of different engineering machinery can be used during construction of the highway, including but unlimited In: responsible transport: tank car, concrete mixing and transporting car, bulk powder goods tanker, concrete mixer, dumper, dump truck, Loading machine, scraper etc.;It is responsible for excavation: rock drill, excavator, boulder cracker etc.;It is responsible for carrying: crane etc.;It is negative Duty construction: piling machine, bull-dozer, land leveller, road roller, finisher, chute forming machine etc.;It is responsible for cleaning: road obstacle clearing vehicle, road Road sweeper etc.;It is responsible for auxiliary: electric power rush-repair vehicle, breakdown lorry, electric welding engineering truck etc..Above-mentioned engineering machinery is worked in coordination Work is to complete construction of the highway.
No matter whether engineering machinery is participating in construction of the highway, is required to regularly be safeguarded, overhaul, therefore each It is provided with the communication module based on internet and the application management system in engineering machinery and is wirelessly connected row information transmission of going forward side by side Information transceiving device, information transceiving device periodically or on demand to communication module send belonging to engineering machinery setting whithin a period of time Standby maintenance information, plant maintenance information is to be able to reflect the information of the plant maintenance executive condition of engineering machinery, and communication module is then Receive the plant maintenance information that each engineering machinery periodically uploads.
It is understood that the plant maintenance information of engineering machinery refer to that engineering machinery includes each be set to need The equipment for wanting periodic inspection, such as key equipment, component etc..
The plant maintenance information that information transceiving device uploads includes following one or more: self-test status information, equipment inspection Repair historical information, history run information.Self-test status information is the inspection that engineering machinery periodically carries out that the self-test of central control system obtains Look into as a result, include can unique identification go out the information such as device numbering, device name, device type, the self-detection result of equipment, if certain A above-mentioned equipment starting for needing periodic inspection is abnormal then to be shown in inspection result.Overhaul of the equipments historical information is to hold The result of row plant maintenance task, wherein plant maintenance task includes that should execute the information of plant maintenance, and overhaul of the equipments is gone through History information record be practical execution plant maintenance record, including servicing time, overhaul reason, member replacing information, Overhaul of the equipments historical information can also include the information such as equipment failure rate statistics.The information that history run information includes can have very It is a variety of, the information such as time, equipment enabling time, Workload Account are always used for example including equipment.
Memory module is for storing the received plant maintenance information of communication module.
After communication module receives the plant maintenance information of engineering machinery upload, storage mould is sent by plant maintenance information Block, memory module store plant maintenance information, to formulate for backup and subsequent task.
Task formulates what module was used to store according to the received current period plant maintenance information of communication module and memory module Previous plant maintenance information makes the plant maintenance task of each engineering machinery.Since information transceiving device is periodically to communication mould Block sending device safeguard information, therefore the plant maintenance information be last time sending device maintenance information time to current time it Between the plant maintenance information namely current period plant maintenance information that are occurred, received before current time and be stored in storage Module is previous plant maintenance information.
Plant maintenance task is the information that the equipment that can indicate engineering machinery needs to be serviced.With engineering machinery A's For motor M and hydraulic pump P, motor M needs every two weeks plus a lubricating oil, hydraulic pump P need each week plus a lubricating oil, Then the plant maintenance task of engineering machinery A, which will include, adds a lubricating oil to motor M every two weeks and adds to hydraulic pump P each week The maintenance task of lubricating oil, while will also include to motor M and hydraulic pump P being overhauled for task primary every two weeks.
If current period plant maintenance information and previous plant maintenance information show that the motor M of engineering machinery A is protected by periodic maintenance It supports, then the plant maintenance task of current period can then set maintenance period as usual, if current period plant maintenance information and previous equipment dimension It protects information and shows motor M more times not according to task instruction progress maintenance, then the plant maintenance task of current period may shorten The maintenance period of motor M.
Task formulates module after making corresponding plant maintenance task for each engineering machinery, by plant maintenance task It is issued to each corresponding engineering machinery by communication module, while being sent to memory module also to store the current period of each engineering machinery Plant maintenance task.
In one embodiment, plant maintenance task is suitable for plant maintenance work of the engineering machinery within the setting period Make.
Plant maintenance task can be to be issued once daily, is also possible to be appointed according to may include in plant maintenance task Be engaged in period of item issues the period determine the plant maintenance task, specifically, plant maintenance task to issue the period usually big In being equal to each maintenance for including in task, overhauling in task items in the smallest period, such as engineering machinery A, if plant maintenance is appointed Business is only possible to the task items comprising motor M and hydraulic pump P are refueled and overhauled, then the plant maintenance task of engineering machinery A Can be issue in each week it is primary, issue primary or even every four weeks every two weeks and issue once.If each week issues once, then It can include the task items refueled to motor M in the plant maintenance task issued every time, but can not include and refuel to hydraulic pump P Task items, but add to hydraulic pump P in plant maintenance task next time comprising the task items refueled to hydraulic pump P It includes primary that the task items of oil, which are every primary equipment maintenance task,.If issuing primary, the then equipment issued every time every two weeks It can include the task items that motor M and hydraulic pump P are refueled and overhauled in maintenance task, and refuel to motor M The task items task amount that can arrange out two weeks, to meet to motor M the needs of being refueled weekly.
The plant maintenance mission dispatching period of different types of engineering machinery may be different, such as the equipment of engineering machinery A1 Maintenance task is to issue once in each week, and the plant maintenance task of engineering machinery A2 is to issue every two weeks once.It is understood that , the plant maintenance information of different types of engineering machinery uploads the period may also be different.
In one embodiment, the period of engineering machinery uploading device maintenance information is Tt.Also, in the equipment of upload It safeguards in information, the upload period of self-test status information is T1, and the upload period of inspection history information is T2, history run information The upload period be T3, wherein T3 > T2 > T1, Tt > T1.
Specifically, requiring self-test since engineering machinery A starts every time, a self-test is at least carried out daily, and remember Record self-detection result, i.e. T1=1;The each Zhou Shangchuan of the inspection history information of engineering machinery A is primary, i.e. T2=7;Engineering machinery A's History run information uploads primary, i.e. T3=14 as the information for not generating content mutation at any time every two weeks.At this point, if work The communication module that plant maintenance information is uploaded to management system by the information transceiving device of journey machinery A each week is primary, i.e. Tt= 7, then each issue of plant maintenance information will include Tt/T1=7 self-detection result and inspection history information, and history run Information is then in every T3/Tt=2 times plant maintenance information comprising primary, it is understood that is that plant maintenance information includes Item of information can upload the difference in period with it and upload the difference in period and different it includes item of information.
If as described above, plant maintenance information is uploaded to management system by the information transceiving device of engineering machinery A each week Communication module it is primary, then the task of management system is formulated module and can be formulated with each week and issue primary equipment maintenance task, With corresponding to the period of plant maintenance information, after receiving the plant maintenance information of engineering machinery A, tieed up immediately according to the equipment Shield information and previous plant maintenance information make current period plant maintenance task and are issued to engineering machinery A.
In one embodiment, plant maintenance task includes examining to following at least a kind of equipment of engineering machinery It repairs: power device, transmission mechanism, walking mechanism, control device, instrument and meter.
During implementing construction of the highway, a variety of different engineering machinery cooperatings are needed, and different types of work The equipment that journey machinery includes is also not exactly the same, therefore for task of including in the plant maintenance task of different engineering machinery Item is also different, and the key equipment and component mainly having to it to maintenance, the maintenance of engineering machinery are safeguarded, overhauled, Key equipment and component include at least power device (motor, air pump, hydraulic pump etc.), transmission mechanism (gearbox etc.), walking Mechanism (wheel etc.), control device (central control system of engineering machinery), in instrument and meter (all types of sensors etc.) A kind of or multiclass, therefore management system is handed down in the plant maintenance task of engineering machinery and also has corresponding task items, engineering It equally can include corresponding item of information that machinery, which is uploaded in the plant maintenance information of management system,.
The mode overhauled to the above-mentioned key equipment of engineering machinery can be to be carried out by presetting sensor The mode of detection is detected, such as velocity sensor, displacement sensor, angular-rate sensor, pressure sensor etc., can also be with It is the mechanisms such as limit switch.
In one embodiment, which further includes display module, display module for showing with the next item down or Multinomial: the received current period plant maintenance information of communication module and/or previous plant maintenance information, task formulate the sheet that module is formulated Phase plant maintenance task and/or previous plant maintenance task.
Management system, can be by current period plant maintenance information that communication module receives, storage mould equipped with display module Current period plant maintenance task, the memory module that previous plant maintenance information, the task execution module of block storage are formulated store past It shows to phase plant maintenance task choosing, in order to which administrative staff monitor the dimension of each engineering machinery in current period in real time Protect the maintenance history situation of situation and previous each engineering machinery.
In one embodiment, which further includes the alarm module for being provided to each engineering machinery, alarm module Fault message is sent to communication module when for breaking down in its affiliated engineering machinery operational process.
Specifically, if engineering machinery A during the work time, be equipped with motor M break down and shut down, engineering machine The alarm module of tool A can monitor the failure (such as by preset sensor for real-time monitoring motor M working order), And the failure is reported to communication module, and then administrative staff is made to learn the situation.Wherein, fault message include following one or It is multinomial: device numbering, device name, device type, equipment fault point, equipment fault reason.It, can be with by the above fault message Administrative staff are made to learn which kind of failure when which kind of equipment of which engineering machinery positioned at which construction site having occurred, with Play the role of warning informing, while the statistics of Improving Equipment failure for middle control personnel.It is understood that alarm module is not etc. Be same as the plant maintenance information periodically uploaded, but when have Times.
The fault message that alarm module reports can be directly displayed on above-mentioned display module, can also pass through hair simultaneously The modes such as sound, luminous, vibration have made alarm sounds to administrative staff.
In one embodiment, which further includes accessory management module, and accessory management module is used for according to each All kinds of accessory loss quantity of the plant maintenance Information Statistics that engineering machinery uploads and/or speed, and number is lost according to all kinds of accessories The quantity in stock of amount and/or all kinds of accessories of speed configuration.
If certain class equipment of engineering machinery is damaged in use or finds to need replacing in maintenance process, need New accessory is extracted from accessory library to place under repair replacement, while the use of this accessory is recorded in plant maintenance information, and It is reported to management system, management system can be united by loss quantity and loss rate of the accessory management module to all kinds of accessories Meter, the faster accessory of loss rate can correspondingly some quantitys in stock of multi-configuration, to meet the replacement speed of accessory, and loss rate Slower accessory can correspondingly configure some quantitys in stock less, to reduce unnecessary inventory space.
In one embodiment, which further includes being provided to the Internet of Things module of each engineering machinery, for Communication module sending device safeguards information, and receives the plant maintenance task that communication module issues.
The above-mentioned information transceiving device for interacting with communication module is Internet of Things module, and Internet of Things module is management The module of system subordinate is partly or wholly equipped with Internet of Things module in each engineering machinery, equipped with Internet of Things module Engineering machinery plant maintenance information and accepting device maintenance task are connect and sent with communication module by Internet of Things module. Internet of Things module can be connect with the central control system of engineering machinery, and to obtain the self-test status information of engineering machinery, overhaul of the equipments is gone through History information and history run information, Internet of Things module is also connect with the sensor for monitoring each key equipment, component, for recording Equipment fault situation.
In one embodiment, communication module is also used to receive the location information of engineering machinery transmission, and task formulates mould Block obtains the environmental information of engineering machinery present position according to the location information of engineering machinery, and believes according to current period plant maintenance Breath, previous plant maintenance information and environmental information formulate plant maintenance task jointly.Wherein, environmental information includes following at least one : temperature, humidity, intensity of illumination, height above sea level.
The geographical location for implementing construction of the highway is different, then climatic environment may also be different, extent of corrosion, damage to equipment Degree and indirect influence degree are also different, thus influence whether the period system of part or all of task items in plant maintenance task It is fixed.Example engineering machinery A's has motor M, and motor M is more sensitive to temperature, and at different temperature, motor M is tieed up The period for protecting maintenance is different, therefore when formulating the plant maintenance task of engineering machinery A, needs to the maintenance task item of motor M In view of mean temperature of the present position engineering machinery A in the following plant maintenance duty cycle, if temperature is compared with Gao Zexu Increase the frequency of maintenance, to prevent motor M overheat from burning.Similarly, humidity is higher for humidity, intensity of illumination, height above sea level, equipment Easier to be rusted, intensity of illumination is stronger, and device temperature is higher, and height above sea level is higher, and oxygen is thinner, and equipment is less susceptible to It is corroded.
The construction of the highway production safety management system based on mobile Internet provided below with reference to Fig. 2 the present invention is described in detail The second embodiment of system.The present embodiment is mainly used in engineering machinery, can be under the basis based on internet communication, from macroscopic view The upper maintenance condition for grasping current each engineering machinery carries out unified management and record, and presses to maintenance, the maintenance of engineering machinery Phase distributes maintenance task, to improve the efficiency and accuracy of engineering mechanical device maintenance, is suitable for during construction of the highway to work Journey machinery is rationally and effectively dispatched, while can also predict to implement the Safety Risk in Production of construction of the highway, to carry out work Make the planning of task.
As shown in Fig. 2, the construction of the highway safe production management system provided in this embodiment based on mobile Internet, mainly Include: communication module, memory module, task formulate module and risk profile module.
Communication module is for receiving the plant maintenance information that each engineering machinery periodically uploads.
No matter whether engineering machinery is participating in construction of the highway, is required to regularly be safeguarded, overhaul, therefore each It is provided with the communication module based on internet and the application management system in engineering machinery and is wirelessly connected row information transmission of going forward side by side Information transceiving device, information transceiving device periodically or on demand to communication module send belonging to engineering machinery setting whithin a period of time Standby maintenance information, plant maintenance information is to be able to reflect the information of the plant maintenance executive condition of engineering machinery, and communication module is then Receive the plant maintenance information that each engineering machinery periodically uploads.
It is understood that the plant maintenance information of engineering machinery refer to that engineering machinery includes each be set to need The equipment for wanting periodic inspection, such as key equipment, component etc..
The plant maintenance information that information transceiving device uploads includes following one or more: self-test status information, equipment inspection Repair historical information, history run information.Self-test status information is the inspection that engineering machinery periodically carries out that the self-test of central control system obtains Look into as a result, include can unique identification go out the information such as device numbering, device name, device type, the self-detection result of equipment, if certain A above-mentioned equipment starting for needing periodic inspection is abnormal then to be shown in inspection result.Overhaul of the equipments historical information is to hold The result of row plant maintenance task, wherein plant maintenance task includes that should execute the information of plant maintenance, and overhaul of the equipments is gone through History information record be practical execution plant maintenance record, including servicing time, overhaul reason, member replacing information, Overhaul of the equipments historical information can also include the information such as equipment failure rate statistics.The information that history run information includes can have very It is a variety of, the information such as time, equipment enabling time, Workload Account are always used for example including equipment.
Memory module is for storing the received plant maintenance information of communication module.
After communication module receives the plant maintenance information of engineering machinery upload, storage mould is sent by plant maintenance information Block, memory module store plant maintenance information, to formulate for backup and subsequent task.
Task formulates what module was used to store according to the received current period plant maintenance information of communication module and memory module Previous plant maintenance information makes the plant maintenance task of each engineering machinery.Since information transceiving device is periodically to communication mould Block sending device safeguard information, therefore the plant maintenance information be last time sending device maintenance information time to current time it Between the plant maintenance information namely current period plant maintenance information that are occurred, received before current time and be stored in storage Module is previous plant maintenance information.
Plant maintenance task is the information that the equipment that can indicate engineering machinery needs to be serviced.With engineering machinery A's For motor M and hydraulic pump P, motor M needs every two weeks plus a lubricating oil, hydraulic pump P need each week plus a lubricating oil, Then the plant maintenance task of engineering machinery A, which will include, adds a lubricating oil to motor M every two weeks and adds to hydraulic pump P each week The maintenance task of lubricating oil, while will also include to motor M and hydraulic pump P being overhauled for task primary every two weeks.
If current period plant maintenance information and previous plant maintenance information show that the motor M of engineering machinery A is protected by periodic maintenance It supports, then the plant maintenance task of current period can then set maintenance period as usual, if current period plant maintenance information and previous equipment dimension It protects information and shows motor M more times not according to task instruction progress maintenance, then the plant maintenance task of current period may shorten The maintenance period of motor M.
Task formulates module after making corresponding plant maintenance task for each engineering machinery, by plant maintenance task It is issued to each corresponding engineering machinery by communication module, while being sent to memory module also to store the current period of each engineering machinery Plant maintenance task.
Risk profile module is used to store according to the received current period plant maintenance information of communication module and memory module past Phase plant maintenance information, or the previous equipment stored according to the received current period plant maintenance information of communication module and memory module Maintenance task or the received current period plant maintenance information of communication module, the previous plant maintenance information of memory module storage with And previous plant maintenance task, carry out the Safety Risk in Production of predictive engine machinery in the construction process.Wherein, Safety Risk in Production It include: that equipment fault risk and/or equipment use supersaturated risk.
Current period plant maintenance message reflection engineering machinery previous feedback cycle in plant maintenance executive condition, Previous plant maintenance information then reflect engineering machinery the previous longer period in plant maintenance executive condition, the two Combine the plant maintenance for being able to reflect out engineering machinery in one section of longer period before current time in any period Executive condition.And according to plant maintenance executive condition before, it can be public to implementation of the engineering machinery within following a period of time The Safety Risk in Production that may occur in the construction of road makes a degree of prediction.
For example, the motor M of engineering machinery A from for the first time enable since last 24 weeks, tieed up every time according to equipment since enabling Shield task carries out maintenance maintenance, and failure has not occurred since enabling, therefore can predict within the following short time Motor M will not break down, and equipment fault risk is lower, while the daily runing time of motor M up to 8 hours, therefore equipment Relatively low using supersaturated risk, on the whole, expecting for the Safety Risk in Production of motor M is lower.And engineering machinery A's is hydraulic Pump P from for the first time enable since last 156 weeks, since enabling sometimes not according to plant maintenance task progress maintenance maintenance, And ten failures occurred since enabling, wherein occurring three times nearest, therefore can predict hydraulic within the following short time Pump P may break down, and equipment fault risk is higher, while it is 12 hours that the daily runing time of hydraulic pump P is most short, therefore is set Standby also higher using supersaturated risk, on the whole, the pre- of the Safety Risk in Production of hydraulic pump P haggles over height.
In one embodiment, plant maintenance task is suitable for plant maintenance work of the engineering machinery within the setting period Make.
In one embodiment, the period of engineering machinery uploading device maintenance information is Tt.Also, in the equipment of upload It safeguards in information, the upload period of self-test status information is T1, and the upload period of inspection history information is T2, history run information The upload period be T3, wherein T3 > T2 > T1, Tt > T1.
In one embodiment, plant maintenance task includes examining to following at least a kind of equipment of engineering machinery It repairs: power device, transmission mechanism, walking mechanism, control device, instrument and meter.
In one embodiment, which further includes display module, display module for showing with the next item down or Multinomial: the received current period plant maintenance information of communication module and/or previous plant maintenance information, task formulate the sheet that module is formulated Phase plant maintenance task and/or previous plant maintenance task.
The Safety Risk in Production for each engineering machinery that display module can also predict risk profile module is shown.
In one embodiment, which further includes the alarm module for being provided to each engineering machinery, alarm module Fault message is sent to communication module when for breaking down in its affiliated engineering machinery operational process.Wherein, fault message Including following one or more: device numbering, device name, device type, equipment fault point, equipment fault reason.
In one embodiment, which further includes accessory management module, and accessory management module is used for according to each All kinds of accessory loss quantity of the plant maintenance Information Statistics that engineering machinery uploads and/or speed, and number is lost according to all kinds of accessories The quantity in stock of amount and/or all kinds of accessories of speed configuration.
In one embodiment, which further includes being provided to the Internet of Things module of each engineering machinery, for Communication module sending device safeguards information, and receives the plant maintenance task that communication module issues.
In one embodiment, communication module is also used to receive the location information of engineering machinery transmission, and task formulates mould Block obtains the environmental information of engineering machinery present position according to the location information of engineering machinery, and believes according to current period plant maintenance Breath, previous plant maintenance information and environmental information formulate plant maintenance task jointly.Wherein, environmental information includes following at least one : temperature, humidity, intensity of illumination, height above sea level.
The communication module, memory module, task of the present embodiment formulate module, display module, alarm module, accessory and manage mould The function and concrete configuration of the components such as block and Internet of Things module can refer to aforementioned first embodiment described function and specific Configuration is configured, and is no longer repeated one by one.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any In the technical scope disclosed by the present invention, any changes or substitutions that can be easily thought of by those familiar with the art, all answers It is included within the scope of the present invention.Therefore, protection scope of the present invention should be with the scope of protection of the claims It is quasi-.

Claims (10)

1. a kind of construction of the highway safe production management system based on mobile Internet characterized by comprising communication module, Memory module and task formulate module;
For receiving the plant maintenance information that each engineering machinery periodically uploads, the memory module is used for the communication module The received plant maintenance information of the communication module is stored, the task formulates module for received according to the communication module Current period plant maintenance information and the previous plant maintenance information of memory module storage, make each engineering machinery Plant maintenance task, and the plant maintenance task is issued to each corresponding engineering machinery by the communication module, it is described Memory module is also used to store the task and formulates the plant maintenance task that module is formulated;Wherein,
The plant maintenance information includes at least one of the following: self-test status information, overhaul of the equipments historical information, history run letter Breath.
2. the system as claimed in claim 1, which is characterized in that the plant maintenance task is suitable for the engineering machinery and is setting Plant maintenance work within timing section.
3. the system as claimed in claim 1, which is characterized in that the engineering machinery uploads the period of the plant maintenance information For Tt, in the plant maintenance information of the upload, the upload period of the self-test status information is T1, the repair history letter The upload period of breath is T2, and the upload period of the history run information is T3, wherein T3 > T2 > T1, Tt > T1.
4. the system as claimed in claim 1, which is characterized in that the plant maintenance task include to engineering machinery with down toward Few one kind equipment is overhauled: power device, transmission mechanism, walking mechanism, control device, instrument and meter.
5. the system as claimed in claim 1, which is characterized in that the system further include: display module, for showing with the next item down It is or multinomial: the received current period plant maintenance information of communication module and/or previous plant maintenance information, the task system The current period plant maintenance task and/or previous plant maintenance task that cover half block is formulated.
6. the system as claimed in claim 1, which is characterized in that the system further include: be provided to the report of each engineering machinery Alert module, sends fault message to the communication module when for breaking down in its affiliated engineering machinery operational process;Its In, the fault message includes at least one of following: device numbering, device name, device type, equipment fault point, equipment event Hinder reason.
7. the system as claimed in claim 1, which is characterized in that the system further include: accessory management module, for according to each institute All kinds of accessory loss quantity of the plant maintenance Information Statistics and/or speed of engineering machinery upload are stated, and according to described all kinds of The quantity in stock of quantity and/or all kinds of accessories of speed configuration is lost in accessory.
8. the system as claimed in claim 1, which is characterized in that the system further include: be provided to the object of each engineering machinery Networking module, for sending the plant maintenance information, and the institute that the reception communication module issues to the communication module State plant maintenance task.
9. system as claimed in claim 1 or 8, which is characterized in that the communication module is also used to receive the engineering machinery The location information of transmission, the task are formulated module and are obtained locating for the engineering machinery according to the location information of the engineering machinery The environmental information of position, and according to the current period plant maintenance information, the previous plant maintenance information and the environmental information The plant maintenance task is formulated jointly;Wherein, the environmental information includes at least one of the following: temperature, humidity, and illumination is strong Degree, height above sea level.
10. the system as claimed in claim 1, which is characterized in that the system further include: risk profile module, for according to institute State the received current period plant maintenance information of communication module and the memory module storage previous plant maintenance information and/or Previous plant maintenance task, the Safety Risk in Production of predictive engine machinery in the construction process;Wherein,
The Safety Risk in Production includes: that equipment fault risk and/or equipment use supersaturated risk.
CN201811246552.5A 2018-10-25 2018-10-25 Construction of the highway safe production management system based on mobile Internet Pending CN109242356A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811246552.5A CN109242356A (en) 2018-10-25 2018-10-25 Construction of the highway safe production management system based on mobile Internet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811246552.5A CN109242356A (en) 2018-10-25 2018-10-25 Construction of the highway safe production management system based on mobile Internet

Publications (1)

Publication Number Publication Date
CN109242356A true CN109242356A (en) 2019-01-18

Family

ID=65081756

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811246552.5A Pending CN109242356A (en) 2018-10-25 2018-10-25 Construction of the highway safe production management system based on mobile Internet

Country Status (1)

Country Link
CN (1) CN109242356A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112769882A (en) * 2019-11-01 2021-05-07 科美诊断技术股份有限公司 Medical data uploading method and device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102918470A (en) * 2010-06-02 2013-02-06 特灵国际有限公司 System and process for monitoring and scheduling maintenance on mechanical equipment
CN104077660A (en) * 2014-07-04 2014-10-01 李阳 Equipment spare part management method
CN104698879A (en) * 2013-12-06 2015-06-10 大连灵动科技发展有限公司 Engineering machinery management method
CN106952028A (en) * 2017-03-13 2017-07-14 杭州安脉盛智能技术有限公司 Dynamoelectric equipment failure is examined and health control method and system in advance
CN107169576A (en) * 2017-04-18 2017-09-15 交通运输部公路科学研究所 The maintenance decision system and method for a kind of commerial vehicle maintenance period
CN107918800A (en) * 2017-11-15 2018-04-17 上海振华重工(集团)股份有限公司 The maintenance system and maintenance method of harbour machinery
CN108549951A (en) * 2018-03-09 2018-09-18 璇飞(武汉)科技有限公司 A kind of marine electric equipment life-span prediction method and device based on Primary Component
CN108591104A (en) * 2018-04-18 2018-09-28 广东寰球智能科技有限公司 A kind of Research on Fan Fault Forecasting based on cloud platform and health management system arranged, method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102918470A (en) * 2010-06-02 2013-02-06 特灵国际有限公司 System and process for monitoring and scheduling maintenance on mechanical equipment
CN104698879A (en) * 2013-12-06 2015-06-10 大连灵动科技发展有限公司 Engineering machinery management method
CN104077660A (en) * 2014-07-04 2014-10-01 李阳 Equipment spare part management method
CN106952028A (en) * 2017-03-13 2017-07-14 杭州安脉盛智能技术有限公司 Dynamoelectric equipment failure is examined and health control method and system in advance
CN107169576A (en) * 2017-04-18 2017-09-15 交通运输部公路科学研究所 The maintenance decision system and method for a kind of commerial vehicle maintenance period
CN107918800A (en) * 2017-11-15 2018-04-17 上海振华重工(集团)股份有限公司 The maintenance system and maintenance method of harbour machinery
CN108549951A (en) * 2018-03-09 2018-09-18 璇飞(武汉)科技有限公司 A kind of marine electric equipment life-span prediction method and device based on Primary Component
CN108591104A (en) * 2018-04-18 2018-09-28 广东寰球智能科技有限公司 A kind of Research on Fan Fault Forecasting based on cloud platform and health management system arranged, method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘燕鸣: "《汽车运输业技术管理》", 30 September 1992 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112769882A (en) * 2019-11-01 2021-05-07 科美诊断技术股份有限公司 Medical data uploading method and device

Similar Documents

Publication Publication Date Title
US6728619B2 (en) Failure measure outputting method, output system, and output device
US8732260B2 (en) Interactive maintenance management alarm handling
JP4756793B2 (en) Construction machine management equipment
CN101753364B (en) Equipment state analyzing and predicting and source distributing method and system
US20090037206A1 (en) Method of forecasting maintenance of a machine
JP5109197B2 (en) Work machine management device and work machine communication device
US20070124000A1 (en) Processes for project-oriented job-site management
JPWO2006085469A1 (en) Centralized management system for work machine malfunction information
US9146554B2 (en) Aggregate processing control system
JP5406318B2 (en) Work machine management device and work machine communication device
JP2006327361A (en) System, method and program for diagnosis and maintenance of ship
CN108928744A (en) A kind of container crane inline diagnosis and maintenance system based on big data
JP2020052592A (en) Construction equipment utilization state management system and management method
CN205809657U (en) Watercraft remote monitoring system
CN109242356A (en) Construction of the highway safe production management system based on mobile Internet
Foltz Investigation of mechanical breakdowns leading to lock closures
CN102707701A (en) Storage monitoring management system and method
WO2001073632A1 (en) Patrol service schedule preparation method, preparation system and preparation device
WO2022209167A1 (en) Component service life prediction system and maintenance assistance system
JP5792113B2 (en) Construction machine maintenance management device, maintenance management system and maintenance management method thereof
CN114198081B (en) Working life monitoring system for rotary drilling rig executive component
CN212083974U (en) Port loading and unloading equipment control system based on PLC
Carter Maintenance Technology Advances Help Mines Predict, Plan, Prepare
Carter Remote possibilities
JP2002203066A (en) Equipment information distribution system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination