CN108302771A - Gas heater Compliance control method, apparatus and system - Google Patents
Gas heater Compliance control method, apparatus and system Download PDFInfo
- Publication number
- CN108302771A CN108302771A CN201810097989.0A CN201810097989A CN108302771A CN 108302771 A CN108302771 A CN 108302771A CN 201810097989 A CN201810097989 A CN 201810097989A CN 108302771 A CN108302771 A CN 108302771A
- Authority
- CN
- China
- Prior art keywords
- gas heater
- instruction
- cloud platform
- platform server
- users
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H9/00—Details
- F24H9/20—Arrangement or mounting of control or safety devices
- F24H9/2007—Arrangement or mounting of control or safety devices for water heaters
- F24H9/2035—Arrangement or mounting of control or safety devices for water heaters using fluid fuel
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L67/00—Network arrangements or protocols for supporting network services or applications
- H04L67/01—Protocols
- H04L67/12—Protocols specially adapted for proprietary or special-purpose networking environments, e.g. medical networks, sensor networks, networks in vehicles or remote metering networks
- H04L67/125—Protocols specially adapted for proprietary or special-purpose networking environments, e.g. medical networks, sensor networks, networks in vehicles or remote metering networks involving control of end-device applications over a network
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Thermal Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Computing Systems (AREA)
- General Health & Medical Sciences (AREA)
- Medical Informatics (AREA)
- Computer Networks & Wireless Communication (AREA)
- Signal Processing (AREA)
- Heat-Pump Type And Storage Water Heaters (AREA)
Abstract
The present invention relates to a kind of gas heater Compliance control method, apparatus and systems.Wherein, gas heater Compliance control method, including step:Receive the instruction of binding that cloud platform server is sent;It is that cloud platform server is completed to tie up the instruction of timing feedback in confirmation users to share information and the shared identification code of gas heater to have bound instruction;Based on instruction has been bound, water flow signal is acquired, when water flow signal reaches predetermined threshold value, according to water flow signal to cloud platform server transport start-up request signal;The permission enabled instruction that cloud platform server is returned based on start-up request signal is received, and according to enabled instruction is allowed, starts gas heater;Allow enabled instruction be cloud platform server identification verification users to share information by when the instruction fed back.The present invention improves the intelligence degree for hiring out residence gas heater, reduces O&M cost, mobility user is made to be protected the safe handling of water heater while meeting mobility user demand.
Description
Technical field
The present invention relates to water heater control fields, more particularly to gas heater Compliance control method, apparatus and are
System.
Background technology
Currently, the user of mobility moves residence with more changing jobs, and for most of water heaters for hiring out residence
Since security performance and normal operation cannot be guaranteed, the O&M costs such as part manpower and materials are consumed.
During realization, inventor has found that at least there are the following problems in traditional technology:
Water heater safety in hiring out residence, which lacks, to be ensured, and fails to repair in time.If user voluntarily buys
Water heater need to handle water heater placement issue in resettlement.Therefore, water heater is idle in traditional technology and resource utilization is low,
It cannot be satisfied user's use demands.
Invention content
Based on this, it is necessary to which and problem that utilization rate low inconvenient for use for the water heater of hiring out residence provides a kind of combustion
Gas water heater Compliance control side, device and system.
To achieve the goals above, on the one hand, an embodiment of the present invention provides it is a kind of from gas heater angle implement
Gas heater Compliance control method, includes the following steps:
Receive the instruction of binding that cloud platform server is sent;It is that cloud platform server is confirming that user is total to have bound instruction
It enjoys information and shares the instruction that timing feedback is tied up in identification code completion with gas heater;
Based on instruction has been bound, acquisition water flow signal is believed when water flow signal reaches predetermined threshold value according to water flow
Number to cloud platform server transport start-up request signal;
The permission enabled instruction that cloud platform server is returned based on start-up request signal is received, and is referred to according to allowing to start
It enables, starts gas heater;Allow enabled instruction be cloud platform server identification verification users to share information by when feed back
Instruction.
Receive cloud platform server in one of the embodiments, allows startup to refer to based on what start-up request signal returned
Enable, and according to allow enabled instruction, start gas heater the step of after, further include step:
Monitoring water flow signal in real time closes gas heater when water flow signal interrupts and generates shutdown signal;
Shutdown signal is reported into cloud platform server.
Further include step in one of the embodiments,:
Receive cloud platform server does not allow enabled instruction based on what start-up request signal returned;The enabled instruction is not allowed to be
Instruction of the cloud platform server in the identification verification obstructed out-of-date feedback of users to share information;
According to start-up request signal is not allowed, gas heater is kept to close.
On the other hand, it is total to additionally provide a kind of gas heater implemented from cloud platform server side for the embodiment of the present invention
Control method is enjoyed, is included the following steps:
It obtains gas heater and shares identification code;
The binding instruction and users to share information that user terminal is sent are received, is instructed according to binding, user bound is shared
Information shares identification code with gas heater, and will complete the instruction feedback of binding generated when binding to gas heater;
Gas heater is received based on the start-up request signal bound instruction, transmitted according to water flow signal;
Based on start-up request signal, starts the identification to users to share information and check;
When identification verification passes through, permission enabled instruction is issued to gas heater.
In one of the embodiments, when identification verification passes through, the step for allowing enabled instruction is issued to gas heater
Further include step after rapid:
Record issues first time point when allowing enabled instruction;
Record receives the second time point when the shutdown signal that gas heater reports;
Difference operation is carried out to first time point and the second time point, obtains using water total duration;
The shared cost data that will be converted to water total duration, reports to user terminal.
On the other hand, the embodiment of the present invention additionally provides a kind of shared control of the gas heater implemented from user terminal angle
Method processed, includes the following steps:
By the users to share information of acquisition and binding instruction, it is issued to cloud platform server;
Receive the shared cost data that cloud platform server reports.
On the other hand, it is shared to additionally provide a kind of gas heater implemented from gas heater angle for the embodiment of the present invention
Device, including:
Instruction reception unit is bound, the instruction of binding for receiving the transmission of cloud platform server;Having bound instruction is
Cloud platform server shares the instruction that timing feedback is tied up in identification code completion with gas heater in confirmation users to share information;
Start request unit, has bound instruction for being based on, acquired water flow signal, reach default threshold in water flow signal
When value, according to water flow signal to cloud platform server transport start-up request signal;
Start unit, the permission enabled instruction returned based on start-up request signal for receiving cloud platform server, and root
According to enabled instruction, start gas heater;It is that cloud platform server identifies that verification is logical to users to share information to allow enabled instruction
The instruction of out-of-date return.
On the other hand, it is total to additionally provide a kind of gas heater implemented from cloud platform server side for the embodiment of the present invention
Control device is enjoyed, including:
Information acquisition unit shares identification code for obtaining gas heater;
Feedback unit, the binding instruction for receiving user terminal transmission and users to share information, instruct according to binding,
User bound shared information shares identification code with gas heater, and is extremely fired the instruction feedback of binding that the when of binding generates is completed
Gas water heater;
Instruction reception unit, for receiving gas heater based on having bound instruction, opened according to what water flow signal transmitted
Dynamic request signal;
Recognition unit starts the identification to users to share information and checks for being based on start-up request signal;
Issuance unit is instructed, for when identification verification passes through, permission enabled instruction to be issued to gas heater.
On the other hand, the embodiment of the present invention also provides a kind of gas heater Compliance control implemented from user terminal angle
Device, including:
Users to share information unit is obtained, it is flat to be issued to cloud for the users to share information for that will obtain and binding instruction
Platform server;
It receives and shares cost data unit, the shared cost data reported for receiving the cloud platform server.
On the other hand, the embodiment of the present invention additionally provides a kind of gas heater shared control system, including gas and hot water
Device, user terminal and cloud platform server;Gas heater connects the user terminal by cloud platform server;
Gas heater is for executing from the side in the gas heater Compliance control method that gas heater angle is implemented
Method step;
Cloud platform server is for executing from the gas heater Compliance control method that cloud platform server side is implemented
Method and step;
User terminal is used to execute from the method step in the gas heater Compliance control method that user terminal angle is implemented
Suddenly.
A technical solution in above-mentioned technical proposal have it is following a little and advantageous effect:
It is anti-when completing to bind with the shared identification code of gas heater by users to share information by receiving cloud platform server
The instruction of binding of feedback.Bound instruction based on this, and according to water flow signal start cloud platform server to users to share into
Row identification verification receives the permission enabled instruction that cloud platform server returns and starts gas heater when identification verification passes through.
Users to share information and cloud platform server are associated by various embodiments of the present invention, and flat by cloud using water flow signal
Platform server is realized to the shared control used of gas heater.It uses convenient for the strong user of mobility, is flowed meeting simultaneously
Property user demand while, improve hire out residence gas heater intelligence degree, reduce O&M cost, simultaneously so that
Mobility user ensures the safe handling of water heater.
Description of the drawings
Fig. 1 is the flow for the gas heater Compliance control embodiment of the method 1 that the present invention is implemented from gas heater angle
Schematic diagram;
Fig. 2 is the stream for the gas heater Compliance control embodiment of the method 1 that the present invention is implemented from cloud platform server side
Journey schematic diagram;
Fig. 3 is another flow of the invention from the gas heater Compliance control method that cloud platform server side is implemented
Schematic diagram;
Fig. 4 is that the flow for the gas heater Compliance control embodiment of the method 1 that the present invention is implemented from user terminal angle is shown
It is intended to;
Fig. 5 is the structure for the gas heater Compliance control device embodiment 1 that the present invention is implemented from gas heater angle
Schematic diagram;
Fig. 6 is the knot for the gas heater Compliance control device embodiment 1 that the present invention is implemented from cloud platform server side
Structure schematic diagram;
Fig. 7 is that the structure for the gas heater Compliance control device embodiment 1 that the present invention is implemented from user terminal angle is shown
It is intended to;
Fig. 8 is the structural schematic diagram of the gas heater shared control system embodiment 1 of the present invention.
Specific implementation mode
To facilitate the understanding of the present invention, below with reference to relevant drawings to invention is more fully described.In attached drawing
Give the preferred embodiment of the present invention.But the present invention can realize in many different forms, however it is not limited to this paper institutes
The embodiment of description.On the contrary, purpose of providing these embodiments is make it is more thorough and comprehensive to the disclosure.
Unless otherwise defined, all of technologies and scientific terms used here by the article and belong to the technical field of the present invention
The normally understood meaning of technical staff is identical.Used term is intended merely to description tool in the description of the invention herein
The purpose of the embodiment of body, it is not intended that in the limitation present invention.Term " and or " used herein includes one or more phases
Any and all combinations of the Listed Items of pass.
One application scenarios explanation of gas heater Compliance control method, apparatus and system of the present invention:
For most of families, gas heater has just been needed generally as basic, can directly be bought.But for flowing
Property strong user for, residence is not fixed, and then needs voluntarily to add if hiring out residence and being not equipped with water heater.Although going out to rent
All outfit water heaters, but generally can not ensure that can it normal use, if there are security risks, are investigated,
If the problematic other on-site maintenance of need, or in addition purchase also need the water heater for considering to buy to dispose when being moved again
Problem.In this way, causing many places inconvenient.
Each embodiment of water heater Compliance control method provided by the present application, can be applied to application environment described above
In.Various embodiments of the present invention, can carry out data input by user terminal, gas and hot water type required for input is personal and a
Then people's information delivers cash pledge, thus information input by user is transmitted to cloud platform server, cloud platform service by user terminal
The type that user selectes is installed to appointed place by device according to these information, and builds shared gas heater system, and user is total
Information is enjoyed to be bound with the gas heater.As a result, when user uses the gas heater, cloud platform server need to be passed through
Identification and verification users to share information, start gas heater after determining that users to share information is errorless.By cloud platform server
According to using duration to carry out charging, and cost data is transmitted to user terminal, payment of fees is carried out convenient for user terminal.Separately
Outside, when user's resettlement is without the gas heater, user is obtained by cloud platform server on the subscriber terminal and unbinds information,
The gas heater is recycled, as a result, by investigation maintenance, next round is waited for share order.
It is the gas heater Compliance control embodiment of the method that the present invention is implemented from gas heater angle referring to Fig. 1, Fig. 1
1 flow diagram, as shown in the figure.
The gas heater Compliance control method that the present invention is implemented from gas heater angle, includes the following steps:
Step S110:Receive the instruction of binding that cloud platform server is sent;It is that cloud platform server exists to have bound instruction
Confirm that users to share information shares the instruction that timing feedback is tied up in identification code completion with gas heater.
Specifically, users to share information can with but be not limited to include that gas heater type selected according to demand is believed
Breath, personal information, delivery cash pledge information etc..It is gas heater unique mark in the present invention that gas heater, which shares identification code,
Code, to indicate different gas heaters.Specifically, master controller in gas heater pass through it is connected to it wireless
Instruction has been bound in communication module reception, so as to user it is shared using the gas heater specified when, data are accurate
By cloud platform server transport to and be recorded in corresponding users to share information, convenient for the shared letter used of gas heater
Breath management.
Step S120:Based on instruction has been bound, water flow signal, when water flow signal reaches predetermined threshold value, root are acquired
According to water flow signal to cloud platform server transport start-up request signal.
Specifically, predetermined threshold value meets flow when gas heater starts work for the water flow in water flow signal
Measure threshold value.Master controller in gas heater receives when having bound instruction, connects the water flow sensor of master controller
Acquire water flow signal, the water flow in water flow signal meet gas heater open work when water flow when, master control
Device processed, to cloud platform server transport start-up request signal, and then can reduce information error by wireless communication module, wherein
Wireless communication module can with but be not limited to WIFI communication module.The present invention is based on instruction acquisition water flow signal has been bound, pass
Defeated start-up request signal further improves the information of gas heater Compliance control method of the present invention in the process of implementation
Validity, the accurate service condition information data for obtaining corresponding user so that shared to use the correct information storage of data flow
Area.
Step S130:The permission enabled instruction that cloud platform server is returned based on start-up request signal is received, and according to fair
Perhaps enabled instruction starts gas heater;It is that cloud platform server is logical in identification verification users to share information to allow enabled instruction
The instruction of out-of-date feedback.
Specifically, identification verification users to share information may include:1, whether the gas heater has and users to share
Information is bound;2, whether the selected gas heater of user is consistent with the gas heater;3, whether the user bound
There are upper limit arrearage number records.The present invention is based on the permission enabled instructions that cloud platform server returns, and start gas heater.
Specifically, the master controller in gas heater is received by wireless communication module allows enabled instruction, allows to start based on this
Instruction, starts gas heater operation, and control igniter carries out ignition work and exports hot water.Present invention ensure that in user
Gas heater is opened when shared information is correct, access right is provided for designated user, and improving gas heater and sharing makes
The information security of used time can effectively prevent error starting.
The gas heater Compliance control method that the present invention is implemented from gas heater angle, by receiving cloud platform service
Users to share information and gas heater are shared the instruction of binding that timing feedback is tied up in identification code completion by device.It has been bound based on this
Instruction, and cloud platform server is started according to water flow signal, verification is identified to users to share information, it is logical in identification verification
It is out-of-date, it receives the permission enabled instruction that cloud platform server returns and starts gas heater.The present invention by users to share information with
Cloud platform server is associated, and realizes use shared to gas heater by cloud platform server using water flow signal
Control.Further, the user for being convenient for mobility strong uses, and while meeting mobility user demand, improves taxi
The intelligence degree of residence gas heater, reduces O&M cost.
In a specific embodiment, receive cloud platform server allows startup to refer to based on what start-up request signal returned
Enable, and according to allow enabled instruction, start gas heater the step of after, further include step:
Step 1:Monitoring water flow signal in real time closes gas heater when water flow signal interrupts and generates closing letter
Number.
Specifically, water flow signal can be pulse signal, the frequency of the bigger pulse signal of water flow is higher.Real-time
When monitoring water flow signal, work as pulse-free signal, then it represents that water flow signal interrupts, and passes through gas heater, combustion without flow
Gas water heater is closed.At this point, the master controller of gas heater generates shutdown signal.The present invention can make to shared
Data are monitored, and are effectively obtained operation and are used data.
Step 2:Shutdown signal is reported into cloud platform server.
The gas heater Compliance control method that the present invention is implemented from gas heater angle, passes through the reality of water flow signal
When monitor, obtain the shutdown signal of gas heater, start-stop situation when by the shared use of gas heater reports to cloud
Platform Server.
In a specific embodiment, further include step:
Step 1:Receive cloud platform server does not allow enabled instruction based on what start-up request signal returned;Do not allow to start
Instruction is instruction of the cloud platform server in the identification verification obstructed out-of-date feedback of users to share information;
Step 2:According to start-up request signal is not allowed, gas heater is kept to close.
Specifically, obstructed out-of-date to the identification verification of users to share information in cloud platform server, i.e., users to share is believed
In breath identification code and the combustion gas are not shared with the gas heater bound in gas heater binding or users to share information
Water heater share identification code be not consistent or users to share information in there are upper limit arrearage number record, then gas heater
Wireless communication module receives not allowing enabled instruction and being sent to master controller for cloud platform server return, enables gas heater
In off position, no hot water output.
The gas heater Compliance control method that the present invention is implemented from gas heater angle, it can be ensured that user is to combustion
The shared access right of gas water heater is identified by users to share information and is checked, and is stablized and is accurately that user is defeated
Send hot water.
It is that the gas heater Compliance control method that the present invention is implemented from cloud platform server side is implemented referring to Fig. 2, Fig. 2
The flow diagram of example 1, as shown in the figure.
The gas heater Compliance control method that the present invention is implemented from cloud platform server side, including:
Step S210:It obtains gas heater and shares identification code.
Specifically, can using but be not limited to the Quick Response Code of corresponding gas heater as the shared mark of gas heater
Know code, corresponding Quick Response Code is scanned by user terminal, cloud platform server obtains combustion by the Quick Response Code that user terminal scans
Gas water heater shares identification code.Or gas heater is triggered by button, and pass through the wireless telecommunications mould in gas heater
Block sends gas heater and shares identification code to cloud platform server.
Step S220:The binding instruction and users to share information that user terminal is sent are received, is instructed according to binding, binding
Users to share information shares identification code with gas heater, and hot to combustion gas by the instruction feedback of binding that the when of binding generates is completed
Hydrophone.
It is bound specifically, users to share information is shared identification code with gas heater, i.e., corresponding combustion gas heat
Hydrophone has set up hiring agreement binding with user by cloud platform server, wherein hiring agreement binding indicates that user possesses this
The right to use of gas heater.Further, by binding instruction feedback to gas heater, so that gas heater is effective
The interaction of shared information is accurately carried out by cloud platform server with corresponding user.
Step S230:Gas heater is received based on the startup request letter bound instruction, transmitted according to water flow signal
Number.
Specifically, by the start-up request signal of gas heater, triggers the identification to users to share information and check.This
Invention is realized by cloud platform server shares using management, to establish orderly shared platform gas heater.
Step S240:Based on start-up request signal, starts the identification to users to share information and check.
Specifically, being trigger condition based on step S230, users to share information is identified and is checked so that gas heater
Accurate shared information is executed with user by cloud platform server to interact.
Step S250:When identification verification passes through, permission enabled instruction is issued to gas heater.
Specifically, on the basis of identification verification users to share information is accurate, permission enabled instruction is issued.To
Realize that user uses specified gas heater, which is shared the data used and can transmit
Into the corresponding users to share information of cloud platform server.
The gas heater Compliance control method that the present invention is implemented from cloud platform server side, utilizes cloud platform server
Gas heater is shared into identification code and users to share information is bound, generation has bound instruction feedback to gas heater.
The start-up request signal that gas heater has been bound instruction based on this, transmitted according to water flow signal is received, is started total to user
The identification verification of information is enjoyed, being issued when identification verification passes through allows enabled instruction to gas heater.To ensure user's energy
It is enough to carry out accurate shared information interaction with specified gas heater, improve the accuracy of information transmission.It is flat by cloud simultaneously
Platform server establishes that orderly gas heater is shared to use platform, it is ensured that the validity of data transmission contributes to users to share
Information timely updates.
Referring to Fig. 3, Fig. 3 is the present invention from the gas heater Compliance control method that cloud platform server side is implemented
Another flow diagram, as shown in the figure.
In a specific embodiment, when identification verification passes through, being issued to gas heater allows enabled instruction
Further include step after step:
Step S310:Record issues first time point when allowing enabled instruction.
Specifically, issuing allows first time point when enabled instruction to be the time that gas heater brings into operation
Point, gas heater, which brings into operation, exports hot water.
Step S320:Record receives the second time point when the shutdown signal that gas heater reports.
Specifically, receiving the second time point of the shutdown signal of gas heater, i.e., gas heater has stopped at this time
It only runs, no hot water output.
Step S330:Difference operation is carried out to first time point and the second time point, obtains using water total duration.
Specifically, first time point and the second time point are carried out difference operation by cloud platform server, that is, calculate combustion gas
Water heater brought into operation to the time difference out of service, thus to obtain with water total duration, i.e., total usage time.
Step S340:The shared cost data that will be converted to water total duration, reports to user terminal.
Specifically, water total duration will be used according to charging regulation, it is converted to shared cost data, reports to user terminal,
It is recorded in users to share information simultaneously, as the identification verification in shared use according to information.
The gas heater Compliance control method that the present invention is implemented from cloud platform server side, passes through cloud platform server
According to allow enabled instruction and gas heater shutdown signal, record gas heater start-stop time acquisition water it is total when
It is long, and then reduce to share and use data error.Further, it can be ensured that the accuracy of users to share information, convenient for combustion gas heat
The shared use of hydrophone.
It is the gas heater Compliance control embodiment of the method 1 that the present invention is implemented from user terminal angle referring to Fig. 4, Fig. 4
Flow diagram, as shown in the figure.
The gas heater Compliance control method that the present invention is implemented from user terminal angle, includes the following steps:
Step S410:By the users to share information of acquisition and binding instruction, it is issued to cloud platform server.
Specifically, user can by the client end interface of user terminal be arranged users to share information, and with
Input binding instruction on the client end interface of family terminal, and then user terminal instructs the users to share information got and binding
It is issued to cloud platform server.Wherein, user terminal can with but be not limited to mobile phone, personal computer, tablet device etc..
Step S420:Receive the shared cost data that cloud platform server reports.
It is paid for the use specifically, receiving and sharing cost data with will pass through user terminal, will pay for the use generation
Delivery data be recorded in users to share information by cloud platform server.
The gas heater Compliance control method that the present invention is implemented from user terminal angle, user is issued using user terminal
Shared information and binding instruct, and receive and share cost data, further improve the execution of gas heater Compliance control method
Process, while helping to improve the shared convenience used.
It should be understood that although each step in the flow chart of Fig. 1-4 is shown successively according to the instruction of arrow,
These steps are not that the inevitable sequence indicated according to arrow executes successively.Unless expressly stating otherwise herein, these steps
Execution there is no stringent sequences to limit, these steps can execute in other order.Moreover, at least one in Fig. 1-4
Part steps may include that either these sub-steps of multiple stages or stage are not necessarily in synchronization to multiple sub-steps
Completion is executed, but can be executed at different times, the execution sequence in these sub-steps or stage is also not necessarily successively
It carries out, but can either the sub-step of other steps or at least part in stage be in turn or alternately with other steps
It executes.
It is the gas heater Compliance control device embodiment that the present invention is implemented from gas heater angle referring to Fig. 5, Fig. 5
1 structural schematic diagram, as shown in the figure.
The gas heater Compliance control device that the present invention is implemented from gas heater angle, including:
Instruction reception unit 510 is bound, the instruction of binding for receiving the transmission of cloud platform server;Instruction is bound
The instruction that timing feedback is tied up in identification code completion is shared with gas heater in confirmation users to share information for cloud platform server.
Specifically, users to share information can with but be not limited to include that gas heater type selected according to demand is believed
Breath, personal information, delivery cash pledge information etc..It is gas heater unique mark in the present invention that gas heater, which shares identification code,
Code, to indicate different gas heaters.Specifically, master controller in gas heater pass through it is connected to it wireless
Instruction has been bound in communication module reception, so as to user it is shared using the gas heater specified when, data are accurate
By cloud platform server transport to and be recorded in corresponding users to share information, convenient for the shared letter used of gas heater
Breath management.
Start request unit 520, for being used to, based on instruction has been bound, acquire water flow signal, reach in water flow signal
When to predetermined threshold value, according to water flow signal to cloud platform server transport start-up request signal.
Specifically, predetermined threshold value meets flow when gas heater starts work for the water flow in water flow signal
Measure threshold value.Master controller in gas heater receives when having bound instruction, connects the water flow sensor of master controller
Acquire water flow signal, the water flow in water flow signal meet gas heater open work when water flow when, master control
Device processed, to cloud platform server transport start-up request signal, and then can reduce information error by wireless communication module, wherein
Wireless communication module can with but be not limited to WIFI communication module.The present invention is based on instruction acquisition water flow signal has been bound, pass
Defeated start-up request signal further improves the information of gas heater Compliance control device of the present invention in the process of implementation
Validity, the accurate service condition information data for obtaining corresponding user so that shared to use the correct information storage of data flow
Area.
Start unit 530, the permission enabled instruction returned based on start-up request signal for receiving cloud platform server, and
According to enabled instruction, start gas heater;It is that cloud platform server identifies verification to users to share information to allow enabled instruction
By when the instruction that returns.
Specifically, identification verification users to share information may include:1, whether the gas heater has and users to share
Information is bound;2, whether the selected gas heater of user is consistent with the gas heater;3, whether the user bound
There are upper limit arrearage number records.The present invention is based on the permission enabled instructions that cloud platform server returns, and start gas heater.
Specifically, the master controller in gas heater is received by wireless communication module allows enabled instruction, allows to start based on this
Instruction, starts gas heater operation, and control igniter carries out ignition work and exports hot water.Present invention ensure that in user
Gas heater is opened when shared information is correct, access right is provided for designated user, and improving gas heater and sharing makes
The information security of used time can effectively prevent error starting.
The gas heater Compliance control device that the present invention is implemented from gas heater angle, by having bound command reception
Unit receives cloud platform server and users to share information and the shared identification code completion of gas heater is tied up having tied up for timing feedback
Fixed instruction.Start request unit and instruction has been bound based on this, and cloud platform server is started according to water flow signal, user is total to
It enjoys information and verification is identified, when identification verification passes through, what start unit reception cloud platform server returned allows startup to refer to
It enables and starts gas heater.Users to share information and cloud platform server are associated by the present invention, and utilize water flow signal
It is realized to the shared control used of gas heater by cloud platform server.Further, make convenient for the strong user of mobility
With, while meeting mobility user demand, improve hire out residence gas heater intelligence degree, reduce O&M
Cost.
It is that the gas heater Compliance control device that the present invention is implemented from cloud platform server side is implemented referring to Fig. 6, Fig. 6
The structural schematic diagram of example 1, as shown in the figure.
The gas heater Compliance control device that the present invention is implemented from cloud platform server side, including:
Information acquisition unit 610 shares identification code for obtaining gas heater.
Specifically, can using but be not limited to the Quick Response Code of corresponding gas heater as the shared mark of gas heater
Know code, corresponding Quick Response Code is scanned by user terminal, cloud platform server obtains combustion by the Quick Response Code that user terminal scans
Gas water heater shares identification code.Or gas heater is triggered by button, and pass through the wireless telecommunications mould in gas heater
Block sends gas heater and shares identification code to cloud platform server.
Feedback unit 620, the binding instruction for receiving user terminal transmission and users to share information, refer to according to binding
It enables, user bound shared information shares identification code with gas heater, and will complete the binding instruction feedback generated when binding
To gas heater.
It is bound specifically, users to share information is shared identification code with gas heater, i.e., corresponding combustion gas heat
Hydrophone has set up hiring agreement binding with user by cloud platform server, wherein hiring agreement binding indicates that user possesses this
The right to use of gas heater.Further, by binding instruction feedback to gas heater, so that gas heater is effective
The interaction of shared information is accurately carried out by cloud platform server with corresponding user.
Instruction reception unit 630, for receiving gas heater based on having bound instruction, transmitted according to water flow signal
Start-up request signal.
Specifically, by the start-up request signal of gas heater, triggers the identification to users to share information and check.This
Invention is realized by cloud platform server shares using management, to establish orderly shared platform gas heater.
Recognition unit 640 starts the identification to users to share information and checks for being based on start-up request signal.
Specifically, the start-up request signal that instruction reception unit 630 receives is trigger condition, users to share information is known
It does not check so that gas heater and user execute accurate shared information by cloud platform server and interact.
Issuance unit 650 is instructed, for when identification verification passes through, permission enabled instruction to be issued to gas heater.
Specifically, on the basis of identification verification users to share information is accurate, permission enabled instruction is issued.To
Realize that user uses specified gas heater, which is shared the data used and can transmit
Into the corresponding users to share information of cloud platform server.
The gas heater Compliance control device that the present invention is implemented from cloud platform server side, passes through information acquisition unit
And gas heater is shared identification code using cloud platform server for feedback unit and users to share information is bound, and generates
Instruction feedback has been bound to gas heater.Instruction reception unit receives gas heater and has bound instruction based on this, according to water
The start-up request signal of flow signal transmission.Recognition unit, which starts the identification to users to share information, to be checked, logical in identification verification
Out-of-date, instruction issuance unit, which issues, allows enabled instruction to gas heater.To ensure that user can be with specified combustion gas heat
Hydrophone carries out accurate shared information interaction, improves the accuracy of information transmission.It is established simultaneously by cloud platform server orderly
Gas heater shared use platform, it is ensured that the validity of data transmission contributes to timely updating for users to share information.
It is the gas heater Compliance control device embodiment 1 that the present invention is implemented from user terminal angle referring to Fig. 7, Fig. 7
Structural schematic diagram, as shown in the figure.
The gas heater Compliance control device that the present invention is implemented from user perspective, including:
Users to share information unit 710 is obtained, the users to share information for that will obtain and binding instruction are issued to cloud
Platform Server.
Specifically, user can by the client end interface of user terminal be arranged users to share information, and with
Input binding instruction on the client end interface of family terminal, and then user terminal instructs the users to share information got and binding
It is issued to cloud platform server.Wherein, user terminal can with but be not limited to mobile phone, personal computer, tablet device etc..
It receives and shares cost data unit 720, the shared cost data reported for receiving the cloud platform server.
It is paid for the use specifically, receiving and sharing cost data with will pass through user terminal, will pay for the use generation
Delivery data be recorded in users to share information by cloud platform server.
The gas heater Compliance control device that the present invention is implemented from user terminal angle, user is issued using user terminal
Shared information and binding instruct, and receive and share cost data, further improve the execution of gas heater Compliance control method
Process, while helping to improve the shared convenience used.
It is the structural schematic diagram of the gas heater shared control system embodiment 1 of the present invention referring to Fig. 8, Fig. 8, as schemed institute
Show.
Gas heater shared control system of the present invention, including gas heater 810, user terminal 830 and cloud platform
Server 820;Gas heater logical 810 crosses cloud platform server 820 and connects the user terminal 830.
Gas heater can realize the gas heater Compliance control method implemented from gas heater angle when executing
In each step, details are not described herein.
Cloud platform server can realize the gas heater Compliance control implemented from cloud platform server side when executing
Each step in method, details are not described herein.
User terminal can be realized when executing from the gas heater Compliance control method that user terminal angle is implemented
Each step, details are not described herein.
The gas heater shared control system of the present invention, gas heater connect user's end by cloud platform server
End thereby establishes the shared internet platform of gas heater, and user can create users to share information by user terminal, just
Users to share information is obtained on backstage in cloud platform server, and gas heater Compliance control system is established according to user demand
System, it is user-friendly, while improving and hiring out the convenience that residence uses gas heater.
As a preferred embodiment, gas heater shared control system of the present invention, in bound gas heater
When failure, corresponding failure code information can be passed through the nothing of connection master controller by the master controller in the gas heater
Line communication module is transmitted to cloud platform server, can effectively realize and report for repairment in time so that safe during shared use
It is ensured to reliable.
As a preferred embodiment, gas heater shared control system of the present invention is moved in user, is not necessarily to the combustion gas
When water heater, the gas heater bound can be unbinded by user terminal, when cloud platform server receives unbundlings information,
Enabled instruction would not allow for be transmitted to the master controller of the gas heater, to prevent gas heater error starting.Combustion gas as a result,
The shared use of water heater terminates, and waits entering next shared user's order.
In one embodiment, a kind of computer readable storage medium is provided, computer program is stored thereon with, is calculated
It is realized from each side in the gas heater Compliance control method that gas heater angle is implemented when machine program is executed by processor
Method step.
In one embodiment, a kind of computer readable storage medium is additionally provided, computer program is stored thereon with, is counted
It is realized from the gas heater Compliance control method that cloud platform server side is implemented when calculation machine program is executed by processor
Various method steps.
In one embodiment, a kind of computer readable storage medium is additionally provided, computer program is stored thereon with, is counted
It is realized from each side in the gas heater Compliance control method that user terminal angle is implemented when calculation machine program is executed by processor
Method step.
In the gas heater Compliance control method, apparatus and system of the present invention, by receiving cloud platform server
Users to share information and gas heater are shared into the instruction of binding that timing feedback is tied up in identification code completion.It has been bound and has been referred to based on this
It enables, and cloud platform server is started according to water flow signal, verification is identified to users to share, when identification verification passes through, connect
It receives the permission enabled instruction that cloud platform server returns and starts gas heater.The gas heater Compliance control side of the present invention
Users to share information and cloud platform server are associated by method, device and system, and flat by cloud using water flow signal
Platform server is realized to the shared control used of gas heater.It uses convenient for the strong user of mobility, is flowed meeting simultaneously
Property user demand while, improve hire out residence gas heater intelligence degree, reduce O&M cost, simultaneously so that
Mobility user ensures the safe handling of water heater.
One of ordinary skill in the art will appreciate that realizing all or part of flow in above-described embodiment method, being can be with
Relevant hardware is instructed to complete by computer program, the computer program can be stored in a non-volatile computer
In read/write memory medium, the computer program is when being executed, it may include such as the flow of the embodiment of above-mentioned each method.Wherein,
Any reference to memory, storage, database or other media used in each embodiment provided herein,
Including non-volatile and/or volatile memory.Nonvolatile memory may include read-only memory (ROM), programming ROM
(PROM), electrically programmable ROM (EPROM), electrically erasable ROM (EEPROM) or flash memory.Volatile memory may include
Random access memory (RAM) or external cache.By way of illustration and not limitation, RAM is available in many forms,
Such as static state RAM (SRAM), dynamic ram (DRAM), synchronous dram (SDRAM), double data rate sdram (DDRSDRAM), enhancing
Type SDRAM (ESDRAM), synchronization link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM
(RDRAM), direct memory bus dynamic ram (DRDRAM) and memory bus dynamic ram (RDRAM) etc..
Only several embodiments of the present invention are expressed for above example, the description thereof is more specific and detailed, but can not
Therefore it is construed as limiting the scope of the patent.It should be pointed out that for those of ordinary skill in the art,
Under the premise of not departing from present inventive concept, various modifications and improvements can be made, these are all within the scope of protection of the present invention.
Therefore, the protection domain of patent of the present invention should be determined by the appended claims.
Claims (10)
1. a kind of gas heater Compliance control method, which is characterized in that include the following steps:
Receive the instruction of binding that cloud platform server is sent;Described bound instructs as the cloud platform server in confirmation use
Family shared information shares the instruction that timing feedback is tied up in identification code completion with gas heater;
Instruction has been bound based on described, water flow signal has been acquired, when the water flow signal reaches predetermined threshold value, according to described
Water flow signal is to the cloud platform server transport start-up request signal;
The permission enabled instruction that the cloud platform server is returned based on the start-up request signal is received, and according to the permission
Enabled instruction starts the gas heater;The permission enabled instruction is the cloud platform server described in identification verification
Users to share information by when the instruction fed back.
2. gas heater Compliance control method according to claim 1, which is characterized in that receive the cloud platform service
The permission enabled instruction that device is returned based on the start-up request signal, and according to the permission enabled instruction, start the combustion gas
Further include step after the step of water heater:
The water flow signal is monitored in real time, and the gas heater is closed when the water flow signal interrupts and generates closing
Signal;
The shutdown signal is reported into the cloud platform server.
3. gas heater Compliance control method according to claim 1, which is characterized in that further include step:
Receive the cloud platform server does not allow enabled instruction based on what the start-up request signal returned;It is described not allow to open
Dynamic instruction is the instruction that the cloud platform server checks the obstructed out-of-date feedback of users to share information in identification;
Do not allow start-up request signal according to described, the gas heater is kept to close.
4. a kind of gas heater Compliance control method, which is characterized in that include the following steps:
It obtains gas heater and shares identification code;
The binding instruction and users to share information that user terminal is sent are received, is instructed according to the binding, binds the user
Shared information shares identification code with the gas heater, and will complete the instruction feedback of binding generated when the binding to institute
State gas heater;
The gas heater is received based on the start-up request signal bound instruction, transmitted according to water flow signal;
Based on the start-up request signal, starts the identification to the users to share information and check;
When identification verification passes through, permission enabled instruction is issued to the gas heater.
5. gas heater Compliance control method according to claim 4, which is characterized in that pass through in identification verification
When, further include step after being issued to the gas heater the step of allowing enabled instruction:
Record issues the first time point when permission enabled instruction;
Record receives the second time point when the shutdown signal that the gas heater reports;
Difference operation is carried out to the first time point and second time point, obtains using water total duration;
By the shared cost data being converted to water total duration, the user terminal is reported to.
6. a kind of gas heater Compliance control method, which is characterized in that include the following steps:
By the users to share information of acquisition and binding instruction, it is issued to cloud platform server;
Receive the shared cost data that the cloud platform server reports.
7. a kind of gas heater Compliance control device, which is characterized in that including:
Instruction reception unit is bound, the instruction of binding for receiving the transmission of cloud platform server;It is described to have bound instruction and be
The cloud platform server shares the instruction that timing feedback is tied up in identification code completion with gas heater in confirmation users to share information;
Start request unit, for be based on it is described bound instruction, acquisition water flow signal reaches pre- in the water flow signal
If when threshold value, according to the water flow signal to the cloud platform server transport start-up request signal;
Unit to be launched allows startup to refer to for receiving the cloud platform server based on what the start-up request signal returned
It enables, and according to the enabled instruction, starts the gas heater;The permission enabled instruction is known for the cloud platform server
Do not check to the users to share information by when the instruction that returns.
8. a kind of gas heater Compliance control device, which is characterized in that including:
Information acquisition unit shares identification code for obtaining gas heater;
Feedback unit, the binding instruction for receiving user terminal transmission and users to share information, instruct according to the binding,
It binds the users to share information and shares identification code with the gas heater, and the binding generated when the binding will be completed
Instruction feedback is to the gas heater;
Instruction reception unit is based on described having bound instruction, being transmitted according to water flow signal for receiving the gas heater
Start-up request signal;
Recognition unit starts the identification to the users to share information and checks for being based on the start-up request signal;
Issuance unit is instructed, for when identification verification passes through, permission enabled instruction to be issued to the gas heater.
9. a kind of gas heater Compliance control device, which is characterized in that including:
Users to share information unit is obtained, the users to share information for that will obtain and binding instruction, and it is issued to cloud platform
Server;
It receives and shares cost data unit, the shared cost data reported for receiving the cloud platform server.
10. a kind of gas heater shared control system, which is characterized in that flat including gas heater, user terminal and cloud
Platform server;The gas heater connects the user terminal by the cloud platform server;
The gas heater requires the method and step described in 1 to 3 any one for perform claim;
The cloud platform server requires the method and step described in 4 or 5 for perform claim;
The user terminal requires the method and step described in 6 for perform claim.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810097989.0A CN108302771B (en) | 2018-01-31 | 2018-01-31 | Shared control method, device and system for gas water heater |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810097989.0A CN108302771B (en) | 2018-01-31 | 2018-01-31 | Shared control method, device and system for gas water heater |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108302771A true CN108302771A (en) | 2018-07-20 |
CN108302771B CN108302771B (en) | 2021-03-16 |
Family
ID=62850576
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810097989.0A Active CN108302771B (en) | 2018-01-31 | 2018-01-31 | Shared control method, device and system for gas water heater |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108302771B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109658186A (en) * | 2018-12-11 | 2019-04-19 | 奥特朗电器(广州)有限公司 | A kind of water heater sharing method and system |
CN111107124A (en) * | 2018-10-29 | 2020-05-05 | 青岛经济技术开发区海尔热水器有限公司 | Control method of shared water heater and shared water heater |
CN111174841A (en) * | 2019-12-30 | 2020-05-19 | 金卡智能集团股份有限公司 | Oscillatory flow filtering method for electronic meter at zero flow point |
CN112712649A (en) * | 2020-12-25 | 2021-04-27 | 杭州甘道智能科技有限公司 | Car washing system and method based on block chain |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007329999A (en) * | 2006-06-06 | 2007-12-20 | Sekisui Chem Co Ltd | Solar power selling and buying system of rental collective housing |
CN104110883A (en) * | 2014-03-06 | 2014-10-22 | 芜湖美的厨卫电器制造有限公司 | Gas water heater and control method thereof |
CN204214498U (en) * | 2013-12-31 | 2015-03-18 | 北京市燃气集团有限责任公司 | A kind of combustible gas metering arrangement |
CN104896760A (en) * | 2015-06-18 | 2015-09-09 | 成都广迈科技有限公司 | User voice based adjusting method for intelligent water heater |
CN105020902A (en) * | 2015-06-29 | 2015-11-04 | 张荣华 | Electric water heater |
CN105466028A (en) * | 2014-09-11 | 2016-04-06 | 芜湖美的厨卫电器制造有限公司 | Water heater system, water heater, control method of water heater and wearable equipment |
KR20160081145A (en) * | 2014-12-30 | 2016-07-08 | 롯데알미늄 주식회사 | Boiler and control methood thereof |
CN206145976U (en) * | 2016-07-13 | 2017-05-03 | 佛山市万工电器有限公司 | But remote control's intelligent air can water heater |
CN107103482A (en) * | 2017-06-29 | 2017-08-29 | 甘肃燃具帮信息服务有限公司 | A kind of burnt gas wall hanging furnace cloud maintenance and check system |
CN107301732A (en) * | 2017-06-27 | 2017-10-27 | 重庆科技学院 | A kind of shared direct drinking fountain purchases water management and control method automatically |
KR20170142294A (en) * | 2016-06-17 | 2017-12-28 | 주식회사 경동원 | Room controller of boiler, central server and method for monitoring user |
CN107543322A (en) * | 2016-06-23 | 2018-01-05 | 杨君锋 | A kind of public place water heater |
-
2018
- 2018-01-31 CN CN201810097989.0A patent/CN108302771B/en active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007329999A (en) * | 2006-06-06 | 2007-12-20 | Sekisui Chem Co Ltd | Solar power selling and buying system of rental collective housing |
CN204214498U (en) * | 2013-12-31 | 2015-03-18 | 北京市燃气集团有限责任公司 | A kind of combustible gas metering arrangement |
CN104110883A (en) * | 2014-03-06 | 2014-10-22 | 芜湖美的厨卫电器制造有限公司 | Gas water heater and control method thereof |
CN105466028A (en) * | 2014-09-11 | 2016-04-06 | 芜湖美的厨卫电器制造有限公司 | Water heater system, water heater, control method of water heater and wearable equipment |
KR20160081145A (en) * | 2014-12-30 | 2016-07-08 | 롯데알미늄 주식회사 | Boiler and control methood thereof |
CN104896760A (en) * | 2015-06-18 | 2015-09-09 | 成都广迈科技有限公司 | User voice based adjusting method for intelligent water heater |
CN105020902A (en) * | 2015-06-29 | 2015-11-04 | 张荣华 | Electric water heater |
KR20170142294A (en) * | 2016-06-17 | 2017-12-28 | 주식회사 경동원 | Room controller of boiler, central server and method for monitoring user |
CN107543322A (en) * | 2016-06-23 | 2018-01-05 | 杨君锋 | A kind of public place water heater |
CN206145976U (en) * | 2016-07-13 | 2017-05-03 | 佛山市万工电器有限公司 | But remote control's intelligent air can water heater |
CN107301732A (en) * | 2017-06-27 | 2017-10-27 | 重庆科技学院 | A kind of shared direct drinking fountain purchases water management and control method automatically |
CN107103482A (en) * | 2017-06-29 | 2017-08-29 | 甘肃燃具帮信息服务有限公司 | A kind of burnt gas wall hanging furnace cloud maintenance and check system |
Non-Patent Citations (1)
Title |
---|
赵明军: "云智能热水器关键技术分析", 《云智能热水器的研究与应用》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111107124A (en) * | 2018-10-29 | 2020-05-05 | 青岛经济技术开发区海尔热水器有限公司 | Control method of shared water heater and shared water heater |
CN109658186A (en) * | 2018-12-11 | 2019-04-19 | 奥特朗电器(广州)有限公司 | A kind of water heater sharing method and system |
CN111174841A (en) * | 2019-12-30 | 2020-05-19 | 金卡智能集团股份有限公司 | Oscillatory flow filtering method for electronic meter at zero flow point |
CN111174841B (en) * | 2019-12-30 | 2021-10-19 | 金卡智能集团股份有限公司 | Oscillatory flow filtering method for electronic meter at zero flow point |
CN112712649A (en) * | 2020-12-25 | 2021-04-27 | 杭州甘道智能科技有限公司 | Car washing system and method based on block chain |
Also Published As
Publication number | Publication date |
---|---|
CN108302771B (en) | 2021-03-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108302771A (en) | Gas heater Compliance control method, apparatus and system | |
CN103856500B (en) | A kind of vehicle based on NFC technique uses system and method | |
CN104348825B (en) | Mobile device and verification method for mobile payment system | |
CA1066812A (en) | Apparatus for control and data transfer between a serial data transmission medium and a plurality of devices | |
CN109801388A (en) | Charging method, system, equipment and computer readable storage medium | |
CN109918030B (en) | File printing method and device | |
CN103248680A (en) | Method and system for sharing network disk data | |
CN109218150A (en) | Control method, the shared application method of household electrical appliance, computer readable storage medium and household electrical appliance of household electrical appliance | |
JP5588327B2 (en) | Sharing vehicle authentication system | |
CN108764923A (en) | Method of payment, device, system and storage medium | |
CN104601537B (en) | A kind of control method and relevant device, system of data transfer | |
CN107239984A (en) | A kind of rent method, device and control device | |
CN108397913A (en) | The Compliance control method, apparatus and system of central heater | |
CN107380821A (en) | A kind of old and useless battery retracting device, method and system | |
JP2023060324A5 (en) | ||
CN115009076A (en) | Charging method and device for charging pile, server and storage medium | |
CN106251483B (en) | intelligent selling system | |
CN202495111U (en) | Traffic punishment self-service system | |
CN104468635B (en) | The user right step-up authentication method and system of the network platform | |
JP2019138145A5 (en) | Information processing system, control method thereof, and program | |
CN109658186A (en) | A kind of water heater sharing method and system | |
CN109462629A (en) | Information of vehicles processing method, device and garage system | |
WO2019144753A1 (en) | Method, device and system for managing electronic seal | |
CN101256685B (en) | In-out management system | |
CN115019421A (en) | Vehicle control method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |