Prior art keywords
lease
pipe
assets
pipe gallery
management module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711365726.5A
Other languages
Chinese (zh)
Other versions
CN108153841A (en
Inventor
李惠娟
刘佳
陈坤
刘长鑫
张鑫
魏铭均
杨芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Spaceflight System Engineering Co ltd
Original Assignee
Suzhou Spaceflight System Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Spaceflight System Engineering Co ltd filed Critical Suzhou Spaceflight System Engineering Co ltd
Priority to CN201711365726.5A priority Critical patent/CN108153841B/en
Publication of CN108153841A publication Critical patent/CN108153841A/en
Application granted granted Critical
Publication of CN108153841B publication Critical patent/CN108153841B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/26Visual data mining; Browsing structured data
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Economics (AREA)
  • Data Mining & Analysis (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Databases & Information Systems (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Educational Administration (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a three-dimensional scene-based pipe gallery management system and a route planning method thereof, wherein the system comprises: the system comprises a three-dimensional modeling module, an asset information management module, a route planning module, a lease management module and a cost management module; the method comprises the steps that a new lease application is provided, corridor planning and approval are required, routing planning requirements are set, corridor pipeline routing planning analysis is carried out according to the total routing planning of a pipe corridor and the current use situation of the assets of the pipe corridor, and analysis results are displayed in a list and a three-dimensional scene; and selecting assets to be rented in the analysis result, and automatically generating a route planning analysis report. The invention can clearly and accurately master the operation condition and the charging condition of the assets of the pipe gallery and the construction distribution condition of the pipelines of the pipe gallery, scientifically and reasonably finish the routing distribution of the assets of the pipe gallery, realize the dynamic update and the intensive utilization of the assets of the pipe gallery and ensure the use of the pipe gallery to be according and certified.

Description

Pipe gallery management system based on three-dimensional scene and routing planning method thereof
Technical Field
The invention belongs to the field of application of a comprehensive pipe rack, and particularly relates to a pipe rack management system based on a three-dimensional scene and a routing planning method thereof.
Background
At present, the heavy construction of domestic utility tunnel management is lightly operated, and utility tunnel construction cost is huge, along with each city utility tunnel construction scale constantly increases, has proposed higher requirement to how to use the operation that the information-based means realizes that the utility tunnel is reasonable, the efficient.
The attributes of the pipelines in the comprehensive pipe gallery are complex, the number of important nodes is large, and different investment, construction and operation subjects bring great troubles to subsequent operation management.
After the piping lane drops into the operation, the operation situation, the charge situation and the construction distribution condition of income corridor pipeline of piping lane asset can't accurate grasp to piping lane operation administrative unit. When new pipeline needs the corridor, the piping lane operation administration unit needs acquire the piping lane current use situation according to piping lane total route planning, through the piping lane completion drawing or directly get into the piping lane scene, again the manual work carry out the route design and the distribution of corridor pipeline. This too relies on the experience and the technical merit of the approval personnel, and is inefficient, causes the maldistribution and the wasting of resources of piping lane resource easily.
The existing urban underground comprehensive pipe gallery informatization system mainly focuses on the aspects of safety monitoring of a pipe gallery and operation and maintenance management of the pipe gallery, and the informatization system and method for pipe gallery asset operation are less involved.
Disclosure of Invention
On the basis, it is necessary that in the process of operating the assets of the pipe gallery, an operation management unit cannot accurately master the operation condition and the charging condition of the assets of the pipe gallery and the construction distribution condition of the pipelines of the pipe gallery; when new pipeline needs to go into the corridor, need acquire the piping lane current use situation through the drawing or get into the piping lane scene, rely on the manual work to go into the corridor pipeline route planning again, inefficiency easily causes the uneven and wasting of resources scheduling problem of piping lane resource distribution, provides a high-efficient, directly perceived, the piping lane management system and scientific, reasonable route planning method of intellectuality, realizes becoming more meticulous, intensification, visual management of piping lane asset, ensures that the operation of piping lane asset can be based on, can be checked with the evidence.
The invention is realized in this way, a three-dimensional scene-based pipe gallery management system, which includes:
the three-dimensional modeling module is connected with the asset information management module and used for carrying out three-dimensional modeling on pipe gallery components (pipe gallery bodies, pipe racks and gallery pipelines) by utilizing modeling software according to a pipe gallery design drawing to build a three-dimensional virtual model of the comprehensive pipe gallery; according to the total routing planning of the pipe gallery, defining and storing a logical relation among a pipe gallery body, a pipe frame and a pipeline, completing attribute addition and assignment of pipe gallery components, and generating structured data; importing the three-dimensional model data and the structured data into a three-dimensional scene-based pipe gallery management system;
the asset information management module is connected with the routing planning module and provides various means such as space query, attribute query, space and attribute combined query and the like for querying the asset information of the pipe rack; browsing asset information based on the three-dimensional scene; when the property information of the assets is changed, updating and maintaining the assets;
the route planning module is connected with the lease management module and used for setting route planning requirements according to lease application information provided by the lease management module based on a three-dimensional scene, and performing route planning analysis on the pipeline of the corridor by combining the total route planning of the pipe corridor and the current use situation of the pipe corridor;
the lease management module is connected with the asset information management module and used for providing informatization management for the lease process of the management gallery assets and carrying out lease approval and contract signing according to the route distributed by the route planning module; informing the asset use state information change to an asset information management module;
and the fee management module is connected with the lease management module and used for setting a fee standard and finishing the payment management of the lease related fee according to the lease contract signed by the lease management module.
Further, in the lease management module, the informationized management information provided for the corridor asset lease process includes lease application, lease approval and contract management information.
Furthermore, the charge management module comprises functions of charge standard management, rent management, arrearage alarm and the like.
Another object of the present invention is to provide a route planning method, which includes the following steps:
step 1: if a new lease application exists, the corridor is required to be planned and examined and approved;
step 2: and setting routing planning requirements. Setting information such as the type, the length, the pipe diameter, the pipe hole number, the lease starting date, the lease ending date and the like of the pipeline to be routed according to the lease application information;
and step 3: and (4) route planning analysis. Performing corridor pipeline route planning analysis according to the total route planning of the pipe corridor, the current use situation of the assets of the pipe corridor and the set planning requirement;
and 4, step 4: and displaying the analysis result. Analyzing to obtain the information of the un-rented pipe gallery assets meeting the planning requirement, and displaying and viewing the analysis result through a list and a three-dimensional scene;
and 5: an asset to be leased is selected. Selecting assets to be rented, and highlighting the selected assets in the list and the three-dimensional scene;
step 6: and storing the analysis result. Storing the analysis result, automatically generating a route planning analysis report according to the selected asset information and a predefined template, and acquiring the route planning analysis result by a lease management module;
and 7: and (6) ending.
Further, in step 3, the total routing plan of the pipe gallery is three-dimensionally modeled according to the pipe gallery design data (DWG document) and imported into the system for pipe gallery asset initialization information.
Further, in step 3, the status quo of the use of the pipe gallery assets is automatically updated when the contract state changes. The status of use of the assets of the pipe gallery comprises information such as spatial distribution, lease status, lease duration and the like of the assets.
Compared with the prior art, the invention has the following positive effects:
1. the information is comprehensively and visually displayed, and the spatial distribution of the assets of the pipe gallery is clear at a glance. The multi-attribute combined query, the spatial query, the attribute and spatial combined query and other multi-hand query modes are provided, the technologies such as geographic information, virtual reality and the like are combined, the asset information of the pipe gallery is comprehensively and visually displayed in a three-dimensional scene, and the spatial distribution of the assets of the pipe gallery is clear at a glance.
2. The refined and intensive management of the pipe gallery assets is realized. The management corridor asset information and the lease information are dynamically updated and managed through an informatization system, the 'home bottom' of the management corridor asset is easily mastered, and the management corridor asset operation is ensured to be according to or certified.
3. The routing planning is scientific and reasonable, and the examination and approval efficiency of the routing planning is effectively improved. The system provides scientific and reasonable analysis for the route planning, reduces the workload of examination and approval personnel for on-site confirmation through paper drawings and pipe corridors, reduces the dependence on the experience and technical level of the examination and approval personnel, and effectively improves the examination and approval efficiency of the route planning.
Drawings
Fig. 1 is a schematic diagram of a three-dimensional scene-based pipe gallery management system according to an embodiment of the present invention.
In the figure: 1. a three-dimensional modeling module; 2. an asset information management module; 3. a route planning module; 4. a lease management module; 5. and a fee management module.
Fig. 2 is a flowchart of a route planning method according to an embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to the following embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
The following detailed description of the principles of the invention is provided in connection with the accompanying drawings.
As shown in fig. 1, the three-dimensional scene-based pipe gallery management system provided by the embodiment of the present invention includes a three-dimensional modeling module 1, an asset information management module 2, a route planning module 3, a lease management module 4, and a cost management module 5.
The three-dimensional modeling module is connected with the asset information management module and used for carrying out three-dimensional modeling on pipe gallery components (pipe gallery bodies, pipe racks and gallery pipelines) by utilizing modeling software according to a pipe gallery design drawing to build a three-dimensional virtual model of the comprehensive pipe gallery; according to the total routing planning of the pipe gallery, defining and storing a logical relation among a pipe gallery body, a pipe frame and a pipeline, completing attribute addition and assignment of pipe gallery components, and generating structured data; importing the three-dimensional model data and the structured data into a three-dimensional scene-based pipe gallery management system;
the asset information management module is connected with the routing planning module and provides various means such as space query, attribute query, space and attribute combined query and the like for querying the asset information of the pipe rack; browsing asset information based on the three-dimensional scene; when the property information of the assets is changed, updating and maintaining the assets;
the route planning module is connected with the lease management module and used for setting route planning requirements according to lease application information provided by the lease management module based on a three-dimensional scene, and performing route planning analysis on the pipeline of the corridor by combining the total route planning of the pipe corridor and the current use situation of the pipe corridor;
the lease management module is connected with the asset information management module and used for providing informatization management for the lease process of the management gallery assets and carrying out lease approval and contract signing according to the route distributed by the route planning module; informing the asset use state information change to an asset information management module;
and the fee management module is connected with the lease management module and used for setting a fee standard and finishing the payment management of the lease related fee according to the lease contract signed by the lease management module.
Further, in this embodiment, the information management information provided for the corridor asset rental process includes information of rental application, rental approval, and contract management. The lease management module is used for registering and inputting lease applications, carrying out lease approval according to routing planning analysis results, completing registration and filing of lease contracts, carrying out contract expiration reminding before the contracts expire and the like.
Further, in this embodiment, the fee management module includes functions of tariff standard management, rent management, arrearage alarm, and the like. The expense management module is used for setting an asset lease charge standard of the pipe gallery, completing rent payment registration and carrying out arrearage alarm reminding aiming at the contract which is not paid on time.
The route planning method used by the system route planning module is described below with reference to fig. 2. The method mainly comprises the following steps:
step 1: if a new lease application exists, the corridor is required to be planned and examined and approved;
step 2: and setting routing planning requirements. Setting information such as the type, the length, the pipe diameter, the pipe hole number, the lease starting date, the lease ending date and the like of the pipeline to be routed according to the lease application information;
and step 3: and (4) route planning analysis. Performing corridor pipeline route planning analysis according to the total route planning of the pipe corridor, the current use situation of the assets of the pipe corridor and the set planning requirement;
and 4, step 4: and displaying the analysis result. Analyzing to obtain the information of the un-rented pipe gallery assets meeting the planning requirement, and displaying and viewing the analysis result through a list and a three-dimensional scene;
and 5: an asset to be leased is selected. Selecting assets to be rented, and highlighting the selected assets in the list and the three-dimensional scene;
step 6: and storing the analysis result. Storing the analysis result, automatically generating a route planning analysis report according to the selected asset information and a predefined template, and acquiring the route planning analysis result by a lease management module;
and 7: and (6) ending.
Further, in step 3, the total routing plan of the pipe gallery is three-dimensionally modeled according to the pipe gallery design data (DWG document) and imported into the system for pipe gallery asset initialization information.
Further, in step 3, the status quo of the use of the pipe gallery assets is automatically updated when the contract state changes. The status of use of the assets of the pipe gallery comprises information such as spatial distribution, lease status, lease duration and the like of the assets.
The invention can clearly and accurately master the operation condition and the charging condition of the assets of the pipe gallery and the construction distribution condition of the pipelines of the pipe gallery, scientifically and reasonably finish the routing distribution of the assets of the pipe gallery, realize the dynamic update and the intensive utilization of the assets of the pipe gallery and ensure the use of the pipe gallery to be according and certified.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (1)

1. A three-dimensional scene-based pipe gallery management system, comprising:
the three-dimensional modeling module is connected with the asset information management module and used for carrying out three-dimensional modeling on a pipe gallery component by utilizing modeling software according to a pipe gallery design drawing to build a three-dimensional virtual model of the comprehensive pipe gallery, wherein the pipe gallery component comprises a pipe gallery body, a pipe frame and a gallery inlet pipeline; according to the total routing planning of the pipe gallery, defining and storing a logical relation among a pipe gallery body, a pipe frame and a pipeline, completing attribute addition and assignment of pipe gallery components, and generating structured data; importing the three-dimensional model data and the structured data into a three-dimensional scene-based pipe gallery management system;
the asset information management module is connected with the routing planning module and is used for providing space query, attribute query and space and attribute combined query to perform management gallery asset information query; browsing asset information based on the three-dimensional scene; when the property information of the assets is changed, updating and maintaining the assets;
the route planning module is connected with the lease management module and used for setting route planning requirements according to lease application information provided by the lease management module based on a three-dimensional scene, and performing route planning analysis on the pipeline of the corridor by combining the total route planning of the pipe corridor and the current use situation of the pipe corridor;
the lease management module is connected with the asset information management module and used for providing informatization management for the lease process of the management gallery assets and carrying out lease approval and contract signing according to the route distributed by the route planning module; informing the asset use state information change to an asset information management module;
the fee management module is connected with the lease management module and used for setting a fee standard and completing payment management of lease related fees according to a lease contract signed by the lease management module;
in the lease management module, the informationized management information provided for the corridor asset lease process comprises lease application, lease approval and contract management information;
the charge management module comprises functions of charge standard management, rent management and arrearage alarm;
the route planning method comprises the following steps:
step 1: if a new lease application exists, the corridor is required to be planned and examined and approved;
step 2: setting routing planning requirements
Setting the type, length, pipe diameter, pipe hole number, lease starting date and lease ending date information of the pipeline to be routed according to the lease application information;
and step 3: route planning analysis
Performing corridor pipeline route planning analysis according to the total route planning of the pipe corridor, the current use situation of the assets of the pipe corridor and the set planning requirement; the total routing plan of the pipe rack is to perform three-dimensional modeling according to the design data of the pipe rack and import the initialization information of the assets of the pipe rack of the system; when the contract state changes, the current use situation of the pipe gallery assets is automatically updated, and the current use situation of the pipe gallery assets comprises the space distribution, the lease state and the lease term information of the assets;
and 4, step 4: presenting the results of the analysis
Analyzing to obtain the information of the un-rented pipe gallery assets meeting the planning requirement, and displaying and viewing the analysis result through a list and a three-dimensional scene;
and 5: selecting assets to be rented
Selecting assets to be rented, and highlighting the selected assets in the list and the three-dimensional scene;
step 6: saving analysis results
Storing the analysis result, automatically generating a route planning analysis report according to the selected asset information and a predefined template, and acquiring the route planning analysis result by a lease management module;
and 7: and (6) ending.
CN201711365726.5A 2017-12-18 2017-12-18 Pipe gallery management system based on three-dimensional scene and routing planning method thereof Active CN108153841B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711365726.5A CN108153841B (en) 2017-12-18 2017-12-18 Pipe gallery management system based on three-dimensional scene and routing planning method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711365726.5A CN108153841B (en) 2017-12-18 2017-12-18 Pipe gallery management system based on three-dimensional scene and routing planning method thereof

Publications (2)

Publication Number Publication Date
CN108153841A CN108153841A (en) 2018-06-12
CN108153841B true CN108153841B (en) 2020-11-03

Family

ID=62467512

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711365726.5A Active CN108153841B (en) 2017-12-18 2017-12-18 Pipe gallery management system based on three-dimensional scene and routing planning method thereof

Country Status (1)

Country Link
CN (1) CN108153841B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111177286A (en) * 2018-11-12 2020-05-19 上海云绅智能科技有限公司 Multifunctional indoor map generation method and device
CN111814287A (en) * 2020-07-14 2020-10-23 南京科远智慧科技集团股份有限公司 Three-dimensional space pipe gallery laying rate calculation method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104571062A (en) * 2015-01-26 2015-04-29 杭州创博科技有限公司 Town comprehensive pipe rack monitoring control and alarm system
CN206224595U (en) * 2016-10-31 2017-06-06 成都慧途科技有限公司 Comprehensive underground pipenet information management system based on GIS three-dimensional visualizations
CN107016502A (en) * 2017-03-30 2017-08-04 中建地下空间有限公司 A kind of pipe gallery intelligent management system
CN107435340A (en) * 2017-07-10 2017-12-05 广州地铁设计研究院有限公司 The pipeline outlet structure and its method of a kind of non-excavation type pipe gallery

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9730078B2 (en) * 2007-08-31 2017-08-08 Fisher-Rosemount Systems, Inc. Configuring and optimizing a wireless mesh network

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104571062A (en) * 2015-01-26 2015-04-29 杭州创博科技有限公司 Town comprehensive pipe rack monitoring control and alarm system
CN206224595U (en) * 2016-10-31 2017-06-06 成都慧途科技有限公司 Comprehensive underground pipenet information management system based on GIS three-dimensional visualizations
CN107016502A (en) * 2017-03-30 2017-08-04 中建地下空间有限公司 A kind of pipe gallery intelligent management system
CN107435340A (en) * 2017-07-10 2017-12-05 广州地铁设计研究院有限公司 The pipeline outlet structure and its method of a kind of non-excavation type pipe gallery

Also Published As

Publication number Publication date
CN108153841A (en) 2018-06-12

Similar Documents

Publication Publication Date Title
CN105022769B (en) A kind of City Underground Pipeline interactive system and its method
Kang et al. BIM perspective definition metadata for interworking facility management data
CN109559069B (en) Production management method and device based on assembly type building platform and terminal equipment
CN102262563B (en) Method for data interaction and modeling of dispatching subsystem
Wang et al. Exploring the application of digital data management approach for facility management in Shanghai’s high-rise buildings
CN108153841B (en) Pipe gallery management system based on three-dimensional scene and routing planning method thereof
Wilson et al. A simple energy usage toolkit from manufacturing simulation data
CN109920269A (en) A kind of virtual parking space management system in parking lot and device
Del Grosso et al. Infrastructure management integrating SHM and BIM procedures
CN104486429A (en) Public and unified video service cloud platform
CN102354387A (en) Multi-dimensional platform data mining method and system of power grid dispersed power supply information
CN116562802A (en) Intelligent construction application platform of track traffic based on BIM
Liu et al. Facility sustainment management system automated population from building information models
Young et al. A parking model hierarchy
CN113361935B (en) Electric power energy scheduling method, device and energy scheduling system
CN113177715B (en) Municipal works planning management system in earlier stage based on BIM and GIS
CN113743791A (en) Business evaluation method and device for business work order, electronic equipment and medium
Asen Building information modeling based integration and visualization for facilities management
CN112396296A (en) Resource scheduling system based on BIM
CN112434978A (en) Efficient office room allocation method and system
Tecim Geographical information system based decision support system for tourism planning and development
CN109683853A (en) A kind of software operation functional definition method and system based on modeling
CN111090654B (en) Real-time data archiving system based on GIS
CN115797106B (en) Automatic generation method, device and equipment for distribution network infrastructure scheme and readable storage medium
Zhang BIM-based Fine Cost Management of the Whole Process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Li Huijuan

Inventor after: Liu Jia

Inventor after: Chen Kun

Inventor after: Liu Changxin

Inventor after: Zhang Xin

Inventor after: Wei Mingjun

Inventor after: Yang Fang

Inventor before: Li Huijuan

Inventor before: Liu Jia

Inventor before: Chen Kun

Inventor before: Liu Changxin

Inventor before: Zhang Xin

Inventor before: Wei Mingjun

Inventor before: Yang Fang

GR01 Patent grant
GR01 Patent grant