CN107959307A - A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost - Google Patents

A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost Download PDF

Info

Publication number
CN107959307A
CN107959307A CN201711284150.XA CN201711284150A CN107959307A CN 107959307 A CN107959307 A CN 107959307A CN 201711284150 A CN201711284150 A CN 201711284150A CN 107959307 A CN107959307 A CN 107959307A
Authority
CN
China
Prior art keywords
formula
power
risk
cost
distribution network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711284150.XA
Other languages
Chinese (zh)
Inventor
李锰
王利利
李秋燕
田春筝
李鹏
蒋小亮
李科
付科源
全少理
郭勇
孙义豪
丁岩
郭新志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201711284150.XA priority Critical patent/CN107959307A/en
Publication of CN107959307A publication Critical patent/CN107959307A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • H02J3/383
    • H02J3/386
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/388Islanding, i.e. disconnection of local power supply from the network
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of meter and the DG Optimal Configuration Methods of power distribution network operation risk cost, step are as follows;S1, constructs power distribution network operation risk cost model under DG grid-connect modes;S2, constructs operation risk cost model under DG off-grid operation patterns;S3, according to the object function and constraints of step S1 and step S2 construction power distribution network operation risk costs;S4, solves step S3 using particle cluster algorithm is improved, obtains the particle with adaptive optimal control value change rate, the corresponding particle is exactly allocation plan.The present invention establishes the distributed generation resource Optimal Allocation Model for considering power distribution network operation risk cost, it is incorporated into the power networks using DG with risk cost during off-grid operation as object function, power supply allowed capacity, active power balance, node voltage be not out-of-limit in a distributed manner, circuit nonoverload and reversal tidal current be not out-of-limit etc. be constraints DG multiple-objection optimization allocation models, and constructed multi-objective Model is handled using Pareto multiple attributive decision making methods, realize distributing rationally for DG.

Description

A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost
Technical field
The invention belongs to distribution network technology field, and in particular to the DG optimizations of a kind of meter and power distribution network operation risk cost are matched somebody with somebody Put method.
Background technology
Distributed generation resource DG (distribution generation) to optimization energy resource supply structure, reply climate change, Preserve the ecological environment, promote the sustainable development of socio-economy to have a very important role].With distributed generation technology water Flat continuous lifting, conventional electric power generation will increasingly have clear superiority with the generation mode that distributed power generation is combined.DG is grid-connected With reduction system losses and electric grid investment, be conducive to adjust the positive effects such as peak valley, raising system security and reliability, with This will also bring the problems such as power quality reduction, trend two-way flow, fault current increase, isolated island benefit at the same time.Since DG connects Enter grid-connected position and partition capacity that the influence to power distribution network is heavily dependent on DG, therefore, in the distribution network planning stage Consider that DG is distributed rationally to be of great significance.
But in terms of plan model, planned, and lacked with operation risk or the minimum simple target of operating cost more To the comprehensive consideration of multi objective.Distribution net work structure is complicated, and operation data volume is big, can be more efficient there is an urgent need for finding a kind of optimization algorithm Optimized model is solved exactly.
The content of the invention
The present invention provides a kind of meter and the DG Optimal Configuration Methods of power distribution network operation risk cost, takes into full account distributed light Volt power generation and wind power generation output, using the operation risk cost of grid-connect mode and off-network pattern as target, wherein, grid-connect mode Operation risk cost include power distribution network operating cost and DG fluctuation produce operation risk cost;The operation wind of off-network pattern Becoming this by inches includes the out-of-limit risk of node voltage, branch overload risk and loses load risk cost, using Pareto multiple attribute decision making (MADM)s Method handles constructed multi-objective Model, realizes distributing rationally for DG.
In order to solve the above technical problems, the technical solution adopted in the present invention is as follows:
The DG Optimal Configuration Methods of a kind of meter and power distribution network operation risk cost, step are as follows:
S1, constructs power distribution network operation risk cost model under DG grid-connect modes;
Power distribution network operation risk cost includes power distribution network operating cost and operation risk cost;
S1.1, calculates power distribution network annual operating cost Closs
Concretely comprise the following steps:
S1.1.1, calculates circuit operating cost CL, calculation formula is as follows:
In formula:CpuFor electricity price;τmaxHourage is lost for the annual peak load of i-th branch;ΔPLiFor on i-th branch Active loss;
S1.1.2, calculates power purchase expense Cen, calculation formula is as follows:
Cen=Tmax×(P∑NEW-P∑DG)×Cpu(2);
In formula:TmaxFor peak load annual utilization hours;P∑NEWFor load increment;P∑DGContribute for DG;
S1.1.3, calculates the operation and maintenance expenses C of DGDG
The DG is at least one of wind turbine, photo-voltaic power supply and gas turbine;
When DG is wind turbine, the operation and maintenance expenses of wind turbine only consider equipment investment, operation and maintenance cost, wind turbine year with year cost Cost CWTCalculation formula be:
In formula:aWTFor the cost of wind turbine;rWT,0For discount rate;mWTFor the fan operation time limit;uWTFor the operation and maintenance expenses of wind turbine With being generally taken as 5%aWT;NWTFor required wind turbine quantity;
When DG is photo-voltaic power supply, the year cost C of photo-voltaic power supplyPVCalculation formula be:
In formula:aPVFor the cost of photovoltaic;rPV,0For discount rate;mPVFor the photovoltaic motor operation time limit;uPVFor the O&M of photovoltaic Expense, is generally taken as 5%aPV;NPVFor required photovoltaic plant quantity;
When DG is gas turbine, the year cost C of gas turbineMTIncluding equipment cost and combustion gas expense, calculation formula is:
CMT=Cf,MT+Ct,MT(5);
In formula:Cf,MTFor the natural gas expense of system year operation;Ct,MTFor the year investment cost of system equipment;
S1.1.4, with reference to step S1.1.1-S1.1.3, obtains power distribution network annual operating cost Closs
Closs=CDG+CL+Cen(6);
In formula:CDGUsed for the operation and maintenance expenses of DG;CLUsed for circuit operation and maintenance expenses;CenFor power purchase expense.
S1.2, calculates power distribution network and considers the operation risk cost C that DG power generation fluctuating characteristics introducerisk, calculation formula is:
Crisk,i=Pr,DGi·PRE,DGi·Cb·ti(7);
In formula:PRE,DGiContribute for i-th of the expected of DG;CbTo call unit costs needed for stand-by power supply;tiFor i-th of DG Year run time;Pr,DGiRepresent that i-th of DG with uncertain feature contributes less than the expected probability contributed;
When DG is wind turbine, wind turbine is contributed is less than the expected probability contributed:
In formula:f(PWT) be wind-driven generator output output power probability density, then when wind turbine accesses power distribution network, system is transported Row risk cost is:
When DG is photo-voltaic power supply, photo-voltaic power supply is contributed is less than the expected probability contributed:
In formula:f(PPV) be photovoltaic output output power probability density, then when photo-voltaic power supply access power distribution network when system operation Risk cost is:
S1.3, with reference to step S1.1 and step S1.2, obtains power distribution network operation risk cost model under DG grid-connect modes;
In formula:ClossFor the annual operating cost of power distribution network;Crisk,iTo consider the operation risk of DG power generation fluctuating characteristic introducings Cost;N is the DG number of units with output fluctuation;
S2, constructs operation risk cost model under DG off-grid operation patterns;
Frisk=min (ωS,VRS,VS,LRS,LS,FRS,F) (13);
In formula:RS,VFor the out-of-limit risk of node voltage;RS,LRisk is overloaded for branch;RS,FTo lose load risk;ωS,VFor The weight of the out-of-limit risk indicator of node voltage, ωS,LThe weight of risk indicator is overloaded for branch;ωS, F areLoss load risk refers to Target weight, and ωS,VS,LS,F=1;
S3, constructs the object function and constraints of power distribution network operation risk cost;
S3.1 constructs the object function of power distribution network operation risk cost, and formula is:
F=min (ωCFlossRFrisk) (14);
In formula:FlossTo consider the system total operating cost of DG operation risk costs;FriskTo consider the system of off-grid operation Operation risk value;F is the catalogue scale value that DG is distributed rationally, and the final purpose of optimization is to make overall goal function minimum;
S3.2, constructs bound for objective function;
The constraints includes DG constraints, power-balance constraint, node voltage constrains, branch transimission power constrains and anti- To trend constraint;
S3.2.1, construction DG constraints;
The DG constraints include total capacity, wind-driven generator number, photo-voltaic power supply number and the micro-gas-turbine of DG accesses Board number;
S3.2.1.1, the constraint of the total capacity of construction DG accesses;
Since wind-power electricity generation and photovoltaic generation are also influenced by wind speed, intensity of illumination, if DG capacity accountings are excessive, Shi Biying The power quality of acoustic system, therefore the total capacity that DG need to be controlled to access, formula are:
In formula:SDGiFor i-th DG output power;Sl,maxFor power distribution network peak load total amount;η is penetration coefficient;
S3.2.1.2, constructs the constraint of wind-driven generator number, and formula is:
0≤NWT≤NWT,max(16);
In formula:NWTFor wind turbine number of units;NWT,maxFor the maximum allowable installation number of units of wind turbine;
S3.2.1.3, the number constraint of construction photo-voltaic power supply, formula are:
0≤NPV≤NPV,max(17);
In formula:NPVFor photo-voltaic power supply number of units;NPV,maxFor the maximum allowable installation number of units of photo-voltaic power supply;
S3.2.1.4, the number of units constraint of construction miniature gas turbine, formula are:
0≤NMT≤NMT,max(18);
In formula:NMTFor gas turbine number of units;NMT,maxFor the maximum allowable installation number of units of gas turbine;
S3.2.2, constructs power-balance constraint, and formula is:
In formula:PG,iFor node injecting power;PlossFor network loss;PLDFor workload demand;PDGiFor DG injecting powers, due to The injecting power of wind-driven generator and photovoltaic motor is all stochastic variable, therefore above formula is described as in the form of probability:
In formula:Pr0To meet the probability level of workload demand;
S3.2.3, the constraint of structure node voltage, formula are:
Uimin≤Ui≤Uimax(21);
In formula:Ui,minFor the upper limit of node i voltage;Ui,maxFor the lower limit of node i voltage;
S3.2.4, the transimission power constraint of construction branch, formula are:
|Pl,i|≤Pl,imax(22);
In formula:Pl,iFor the transimission power of i-th branch;Pl,imaxFor the transimission power upper limit of i-th branch;
S3.2.5, construction reversal tidal current constraint, formula are:
In formula:PDG,i+QDGiFor the DG injecting powers at node i;PLD,i+QLD,iFor the load power of node i;PL,i+QL,i The power in circuit downstream is injected for node i;Smax iFor the maximum capacity of circuit i;μ is the limit value that can send power;
S4, solves step S3 using particle cluster algorithm is improved, obtains the particle with adaptive optimal control value change rate, The corresponding particle is exactly allocation plan;
S4.1, in the case where DG accesses the constraints of power grid total capacity and power grid individual node access capacity, random generation is just Beginning particle populations;
The scale of population is set as m, then m particle in population population, its structure are:
(a1,a2,…,ai,…,an|b1,b2,…,bi,…,bn) (24);
In formula:I numbers for metric grid nodes, and i=1 ..., n;biType for the DG accessed at node i, with Three kinds of wind-driven generator, photo-voltaic power supply and miniature gas burner DG are subjected to calculating processing as different nodes;aiRepresent i-th The multiple of the unit rated capacity of DG, a are accessed on a nodeiTake [0, PDG,maxi/Pave] integer value in section, PDG,maxiFor Node i allows the maximum power of access, PaveFor DG unit rated capacities;
S4.2, carries out Load flow calculation, obtains the Pareto optimal solution sets of object function, and calculate in Pareto optimal solution sets The adaptive value of each particle, chooses optimal particle;
S4.3, according to the speed of current optimal particle more new particle and position;
S4.4, calculates the crowding distance of particle in Pareto optimal solution sets and updates external archival collection;
S4.4.1, calculates and appoints two particle distance d in Pareto optimal solution setsij, calculation formula is:
In formula, FlossTo consider the system total operating cost of DG operation risk costs;FriskTo consider the system of off-grid operation Operation risk value;To consider the maximum of the system total operating cost of DG operation risk costs;To consider DG operations The minimum value of the system total operating cost of risk cost;To consider the maximum of the system operation value-at-risk of off-grid operation;To consider the minimum value of the system operation value-at-risk of off-grid operation;
S4.4.2, calculates the crowding distance D of particle i in Pareto optimal solution setsi
Wherein, d1It is any one particle i in Pareto optimal solution sets and with a distance from its first near particle a, calculates Formula is:
d1=min { dij|j∈Qset,j≠i} (27);
d2For any one particle i in Pareto optimal solution sets and with a distance from its second near particle b, calculation formula For:
d2=min { dij|dij>d1,j∈Qset,j≠i} (28);
S4.4.3, according to the crowding distance D being calculatediValue, in Pareto optimal solution sets solution carry out by greatly to Small sequence, rejects the small solution of crowding distance, obtains global maximal solution;
S4.4.4, is saved in external archival by global maximal solution and concentrates;
S4.5, obtains each particle adaptive optimal control value change rate in Pareto optimal solution sets;
S4.6, judges whether adaptive optimal control value change rate is less than threshold value, if being less than threshold value, carries out TSP question and sentences Disconnected whether iteration is completed, if completing, the corresponding particle of output adaptive optimal control value change rate, the corresponding particle is exactly to configure Scheme, if not completing iteration, repeat step S4.2-S4.5;If more than threshold value, then judge whether that iteration is completed, if completing, The corresponding particle of adaptive optimal control value change rate is then exported, the corresponding particle is exactly allocation plan, if not completing iteration, is weighed Multiple step S4.2-S4.5.
The present invention establishes the distributed generation resource Optimal Allocation Model for considering power distribution network operation risk cost, with the grid-connected fortune of DG Row is object function with risk cost during off-grid operation, in a distributed manner power supply allowed capacity, active power balance, node electricity Press not out-of-limit, circuit nonoverload and reversal tidal current is not out-of-limit etc. is the DG multiple-objection optimization allocation models of constraints, and adopt Constructed multi-objective Model is handled with Pareto multiple attributive decision making methods, realizes distributing rationally for DG.And pass through Simulation example shows that this method optimizes network structure, reduces operating cost;During failure, it ensure that the power supply of important load can By property, breakdown loss is reduced, realizes distributing rationally for DG.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is attached drawing needed in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, without creative efforts, may be used also To obtain other attached drawings according to these attached drawings.
Fig. 1 is the multi-objective particle swarm algorithm flow chart of the present invention.
PG&E69 Node power distribution system node diagrams when Fig. 2 emulates for the present invention.
Fig. 3 is index comparison diagram before and after the optimization of the invention for emulating an example.
Embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art obtained under the premise of not making the creative labor it is all its His embodiment, belongs to the scope of protection of the invention.
The DG Optimal Configuration Methods of a kind of meter and power distribution network operation risk cost, are by the power distribution network method of operation point containing DG It is incorporated into the power networks and off-grid operation both of which for DG:1) it is incorporated into the power networks under pattern, DG provides electricity for load jointly with power distribution network Energy;2) off-grid operation pattern, that is, distribution network failure state, at this time power distribution network generally powered with radial networks, step is as follows:
S1, constructs power distribution network operation risk cost model under DG grid-connect modes;
Power distribution network operation risk cost includes power distribution network operating cost and operation risk cost;
S1.1, calculates power distribution network annual operating cost Closs
Concretely comprise the following steps:
S1.1.1, calculates circuit operating cost CL, calculation formula is as follows:
In formula:CpuFor electricity price;τmaxHourage is lost for the annual peak load of i-th branch;ΔPLiFor on i-th branch Active loss;
S1.1.2, calculates power purchase expense Cen, calculation formula is as follows:
Cen=Tmax×(P∑NEW-P∑DG)×Cpu(2);
In formula:TmaxFor peak load annual utilization hours;P∑NEWFor load increment;P∑DGContribute for DG;
S1.1.3, calculates the operation and maintenance expenses C of DGDG
The DG is at least one of wind turbine, photo-voltaic power supply and gas turbine;
When DG is wind turbine, the operation and maintenance expenses of wind turbine only consider equipment investment, operation and maintenance cost, wind turbine year with year cost Cost CWTCalculation formula be:
In formula:aWTFor the cost of wind turbine;rWT,0For discount rate;mWTFor the fan operation time limit;uWTFor the operation and maintenance expenses of wind turbine With being generally taken as 5%aWT;NWTFor required wind turbine quantity;
When DG is photo-voltaic power supply, the year cost C of photo-voltaic power supplyPVCalculation formula be:
In formula:aPVFor the cost of photovoltaic;rPV,0For discount rate;mPVFor the photovoltaic motor operation time limit;uPVFor the O&M of photovoltaic Expense, is generally taken as 5%aPV;NPVFor required photovoltaic plant quantity;
When DG is gas turbine, the year cost C of gas turbineMTIncluding equipment cost and combustion gas expense, calculation formula is:
CMT=Cf,MT+Ct,MT(5);
In formula:Cf,MTFor the natural gas expense of system year operation;Ct,MTFor the year investment cost of system equipment;
S1.1.4, with reference to step S1.1.1-S1.1.3, obtains power distribution network annual operating cost Closs
Closs=CDG+CL+Cen(6);
In formula:CDGUsed for the operation and maintenance expenses of DG;CLUsed for circuit operation and maintenance expenses;CenFor power purchase expense.
S1.2, calculates power distribution network and considers the operation risk cost C that DG power generation fluctuating characteristics introducerisk, calculation formula is:
Crisk,i=Pr,DGi·PRE,DGi·Cb·ti(7);
In formula:PRE,DGiContribute for i-th of the expected of DG;CbTo call unit costs needed for stand-by power supply;tiFor i-th of DG Year run time;Pr,DGiRepresent that i-th of DG with uncertain feature contributes less than the expected probability contributed;
The risk cost of distribution network planning refers to that planning is influenced be subject to expectation factor is difficult in advance so that actual to receive Benefit has deviated from expected income, thus bears economic loss or obtains the uncertainty of extra returns.Due to DG contribute it is random Property and fluctuation, when DG contribute do not reach desired value when, be ensure power distribution network still in being run under optimum state, in systems Corresponding stand-by power supply is called, resulting extra charge is then known as system risk cost.
Operation risk cost CriskCount and risk cost be mainly derived from environment or other factors and influence, when DG contributes When not reaching desired value, the expense for calling stand-by power supply is exactly operation risk cost Crisk
When DG is wind turbine, wind turbine is contributed is less than the expected probability contributed:
In formula:f(PWT) be wind-driven generator output output power probability density, then when wind turbine accesses power distribution network, system is transported Row risk cost is:
When DG is photo-voltaic power supply, photo-voltaic power supply is contributed is less than the expected probability contributed:
In formula:f(PPV) be photovoltaic output output power probability density, then when photo-voltaic power supply access power distribution network when system operation Risk cost is:
S1.3, with reference to step S1.1 and step S1.2, obtains power distribution network operation risk cost model under DG grid-connect modes;
In formula:ClossFor the annual operating cost of power distribution network;Crisk,iTo consider the operation risk of DG power generation fluctuating characteristic introducings Cost;N is the DG number of units with output fluctuation;
S2, constructs operation risk cost model under DG off-grid operation patterns;
Frisk=min (ωS,VRS,VS,LRS,LS,FRS,F) (13);
In formula:RS,VFor the out-of-limit risk of node voltage;RS,LRisk is overloaded for branch;RS,FTo lose load risk;ωS,VFor The weight of the out-of-limit risk indicator of node voltage, ωS,LThe weight of risk indicator is overloaded for branch;ωS, F areLoss load risk refers to Target weight, and ωS,VS,LS,F=1.
Power distribution network containing DG is under off-grid operation pattern, and the power grid of trouble point downstream will be disconnected with major network, under trouble point The DG of trip will continue to provide electric energy to the user area of former dead electricity.In order to maintain the power-balance and power quality inside off-network, And make off-grid operation DG and energy storage device must cooperate under specified voltage and frequency, it then follows certain control operation Specification.
When failure occurs, power distribution network is transitioned into by plan off-network or unplanned off-grid operation state by off-network division, from And realize restoring electricity for power failure load.To realize the bumpless transfer between DG grid-connect modes and off-network pattern, in power distribution network The possible breakdown state of each selection should preferentially carry out off-network division, and accident is put into contingency set, formulate off-network division Scheme collection, and then on the basis of the power distribution network under the off-grid operation mode after division, finally obtain Risk of outage loss degree.
S3, constructs the object function and constraints of power distribution network operation risk cost;
S3.1 constructs the object function of power distribution network operation risk cost, and formula is:
F=min (ωCFlossRFrisk) (14);
In formula:FlossTo consider the system total operating cost of DG operation risk costs;FriskTo consider the system of off-grid operation Operation risk value;F is the catalogue scale value that DG is distributed rationally, and the final purpose of optimization is to make overall goal function minimum;
S3.2, constructs bound for objective function;
The constraints includes DG constraints, power-balance constraint, node voltage constrains, branch transimission power constrains and anti- To trend constraint;
S3.2.1, construction DG constraints;
The DG constraints include total capacity, wind-driven generator number, photo-voltaic power supply number and the micro-gas-turbine of DG accesses Board number;
S3.2.1.1, the constraint of the total capacity of construction DG accesses;
Since wind-power electricity generation and photovoltaic generation are also influenced by wind speed, intensity of illumination, if DG capacity accountings are excessive, Shi Biying The power quality of acoustic system, therefore the total capacity that DG need to be controlled to access, formula are:
In formula:SDGiFor i-th DG output power;Sl,maxFor power distribution network peak load total amount;η is penetration coefficient;
S3.2.1.2, constructs the constraint of wind-driven generator number, and formula is:
0≤NWT≤NWT,max(16);
In formula:NWTFor wind turbine number of units;NWT,maxFor the maximum allowable installation number of units of wind turbine;
S3.2.1.3, the number constraint of construction photo-voltaic power supply, formula are:
0≤NPV≤NPV,max(17);
In formula:NPVFor photo-voltaic power supply number of units;NPV,maxFor the maximum allowable installation number of units of photo-voltaic power supply;
S3.2.1.4, the number of units constraint of construction miniature gas turbine, formula are:
0≤NMT≤NMT,max(18);
In formula:NMTFor gas turbine number of units;NMT,maxFor the maximum allowable installation number of units of gas turbine;
S3.2.2, constructs power-balance constraint, and formula is:
In formula:PG,iFor node injecting power;PlossFor network loss;PLDFor workload demand;PDGiFor DG injecting powers, due to The injecting power of wind-driven generator and photovoltaic motor is all stochastic variable, therefore above formula is described as in the form of probability:
In formula:Pr0To meet the probability level of workload demand;
S3.2.3, the constraint of structure node voltage, formula are:
Uimin≤Ui≤Uimax(21);
In formula:Ui,minFor the upper limit of node i voltage;Ui,maxFor the lower limit of node i voltage;
S3.2.4, the transimission power constraint of construction branch, formula are:
|Pl,i|≤Pl,imax(22);
In formula:Pl,iFor the transimission power of i-th branch;Pl,imaxFor the transimission power upper limit of i-th branch;
S3.2.5, construction reversal tidal current constraint, formula are:
In formula:PDG,i+QDGiFor the DG injecting powers at node i;PLD,i+QLD,iFor the load power of node i;PL,i+QL,i The power in circuit downstream is injected for node i;Smax iFor the maximum capacity of circuit i;μ is the limit value that can send power;
S4, solves step S3 using particle cluster algorithm is improved, obtains the particle with adaptive optimal control value change rate, The corresponding particle is exactly allocation plan;
S4.1, in the case where DG accesses the constraints of power grid total capacity and power grid individual node access capacity, random generation is just Beginning particle populations;
The scale of population is set as m, then m particle in population population, its structure are:
(a1,a2,…,ai,…,an|b1,b2,…,bi,…,bn) (24);
In formula:I numbers for metric grid nodes, and i=1 ..., n;biType for the DG accessed at node i, with Three kinds of wind-driven generator, photo-voltaic power supply and miniature gas burner DG are subjected to calculating processing as different nodes;aiRepresent i-th The multiple of the unit rated capacity of DG, a are accessed on a nodeiTake [0, PDG,maxi/Pave] integer value in section, PDG,maxiFor Node i allows the maximum power of access, PaveFor DG unit rated capacities;
S4.2, carries out Load flow calculation, obtains the Pareto optimal solution sets of object function, and calculate in Pareto optimal solution sets The adaptive value of each particle, chooses optimal particle;
S4.3, according to the speed of current optimal particle more new particle and position;
S4.4, calculates the crowding distance of particle in Pareto optimal solution sets and updates external archival collection;
S4.4.1, calculates and appoints two particle distance d in Pareto optimal solution setsij, calculation formula is:
In formula, FlossTo consider the system total operating cost of DG operation risk costs;FriskTo consider the system of off-grid operation Operation risk value;To consider the maximum of the system total operating cost of DG operation risk costs;To consider DG operations The minimum value of the system total operating cost of risk cost;To consider the maximum of the system operation value-at-risk of off-grid operation;To consider the minimum value of the system operation value-at-risk of off-grid operation;
S4.4.2, calculates the crowding distance D of particle i in Pareto optimal solution setsi
Wherein, d1It is any one particle i in Pareto optimal solution sets and with a distance from its first near particle a, calculates Formula is:
d1=min { dij|j∈Qset,j≠i} (27);
d2For any one particle i in Pareto optimal solution sets and with a distance from its second near particle b, calculation formula For:
d2=min { dij|dij>d1,j∈Qset,j≠i} (28);
S4.4.3, according to the crowding distance D being calculatediValue, in Pareto optimal solution sets solution carry out by greatly to Small sequence, rejects the small solution of crowding distance, obtains global maximal solution;
S4.4.4, is saved in external archival by global maximal solution and concentrates;
S4.5, obtains each particle adaptive optimal control value change rate in Pareto optimal solution sets;
S4.6, judges whether adaptive optimal control value change rate is less than threshold value, if being less than threshold value, carries out TSP question and sentences Disconnected whether iteration is completed, if completing, the corresponding particle of output adaptive optimal control value change rate, the corresponding particle is exactly to configure Scheme, if not completing iteration, repeat step S4.2-S4.5;If more than threshold value, then judge whether that iteration is completed, if completing, The corresponding particle of adaptive optimal control value change rate is then exported, the corresponding particle is exactly allocation plan, if not completing iteration, is weighed Multiple step S4.2-S4.5.
Illustrated below with emulating example.
The present invention is as shown in Figure 2 with the validity of 69 node verification methods of PG&E, example structure.Improve particle cluster algorithm Parameter is arranged to:Population scale is 100, maximum iteration tmax=100, maximum inertia weight wmax=0.9, minimum is used Property weight wmin=0.4, accelerator coefficient c1=c2=2, adaptive optimal control value change rate K=0.1, initial aberration rate pm0=0.4, The minimum value p that aberration rate allowsm,min=0.1.
Load is 3802+j3694kVA, rated voltage 12.66kV in example.DG maximums access capacity is no more than system The 25% of total load, then maximum active access capacities of the DG in power grid is 950.5kW.Assuming that the capacity of single DG to be selected is The integral multiple of 10kW, i.e. unit rated capacity are Pave=10kW, the DG accessed at each node are no more than 250kW, that is, encode aiThe integer value in [0,25] section is taken, andValue be the integer value in [0,95] section.
Assuming that the installation node to be selected of all types of DG is as shown in table 1 in example, the load level and load of each node load Weight system is as shown in table 2.
The installation node to be selected of table 1DG
The load level and weight coefficient of 2 node of table
Load level Weight coefficient Node serial number
First order load 500 5~8,12~14,47~48,50~51,57,61~67
Two stage loads 30 9~11,15~19,21,30,32~34,39~41,42~45,53~55,58
Three stage loads 1 20th, 22~29,31,35~38,46,49,52,56,59~60,68
Contingency set includes 5 faulty lines, as overstriking circuit in Fig. 2, its line failure rate are as shown in table 3.
3 forecast failure collection of table
Failure is numbered Faulty line Probability of malfunction
1 L15,16 1.25×10-4
2 L24,25 1.74×10-4
3 L28,29 1.43×10-4
4 L46,47 1.16×10-4
5 L66,67 1.56×10-4
And analyzed with two schemes.
Scheme one:Miniature gas turbine (MT) and wind-driven generator (WT) hybrid optimization;Scheme two:Miniature gas turbine (MT) and photo-voltaic power supply (PV) hybrid optimization.
The position of DG and capacity are as shown in table 4 and table 5 after optimization, and desired value after optimization is as shown in figure 3, be
4 scheme of table, one result of study
5 scheme of table, two result of study
From table 4, table 5, from the structural analysis of DG, optimum results based on miniature gas turbine, wind-driven generator and Photo-voltaic power supply accounting is slightly smaller.In wind-driven generator, photo-voltaic power supply and the overlapping node of gas turbine building site, prioritization scheme institute The DG of selection is miniature gas turbine rather than wind-driven generator and photo-voltaic power supply, this is because wind-driven generator and photo-voltaic power supply Randomness is larger, and the fluctuation of output power is larger, there are certain risk cost, to electric network composition improvement not as micro- Type gas turbine is good.
From figure 3, it can be seen that compared to any DG is not installed when, system operation expense has declined, and operation risk have it is bright Aobvious decline.It can be seen that reasonable Arrangement DG can improve the network structure of area power grid well so that network operation expense is significantly Decline, although the uncertainty of wind-driven generator, photo-voltaic power supply adds risk cost, it changes system network architecture It is kind more obvious.
Table 6 and table 7 count and off-grid operation in the case of DG distribute result rationally and do not count and off-grid operation in the case of DG Distribute result rationally.
Table 6 is counted and the optimum results of off-grid operation
Table 7 is not counted and the optimum results of off-grid operation
In table 6 and table 7, numeral before bracket is the node serial number of DG on-positions, the digital representation access in bracket The DG capacity of the node.In the optimum results for considering node off-grid operation, DG access capacities are amounted to and accounted in first order load node The percentage for optimizing total capacity is 57.7% and 62.9%, this is because first order load weight coefficient is big, caused by causality loss Much larger than two, three stage loads, when great power grid accident occurs, DG can provide the backup power supply of abundance, can maintain power distribution network Middle important load power supply, reduces dead electricity loss to the greatest extent.It can be seen that the power distribution network operation risk assessment model for considering off-grid operation is used, The position of rational planning DG and capacity, can ensure the power supply reliability of important load, effectively in the case of major accident The loss that reduction accident produces.
From emulation example, present invention optimization network structure, reduces operating cost;During failure, it ensure that important negative The power supply reliability of lotus, reduces breakdown loss, realizes distributing rationally for DG.
Moreover, of the present invention is to improve multi-objective particle swarm algorithm.
Particle cluster algorithm achieves good effect in many single-object problems, but is asked in processing multiple-objection optimization During topic, globally optimal solution more than one, optimum results are no longer unique, but a Pareto optimal solution set, it is therefore desirable to it Certain improvement is carried out, specific improvement is as follows:
1) coding mode
In traditional binary coding scheme, with each node in a binary representation system, this encoding scheme meeting Make code length long with increasing for node, so as to influence the speed calculated.Therefore, the present invention is encoded using ten Scheme.
2) selection of globally optimal solution
Assuming that Qset is non-dominant disaggregation, wherein any one particle i (i ∈ Qset) is defined the particle with from it first Distance closely with the second near particle a and b (i ≠ a, b) is respectively d1And d2, i.e.,:
d1=min { dij|j∈Qset,j≠i};
d2=min { dij|dij>d1,j∈Qset,j≠i};
Then crowding distances of the particle i in non-dominant disaggregation Qset is defined as:
For the optimization problem of this paper two targets studied, dijFor:
In formula, Floss、FriskFor two object functions selected by this paper, target isPoint Maximum and minimum value that Wei be in the target function value.
According to the crowding distance D being calculatediValue, descending sequence is carried out to the solution that non-domination solution is concentrated, is picked Except the small solution of crowding distance, global maximal solution is obtained.
3) exterior elite archival strategy
An external archival collection is established, the elite particle produced in evolutionary process is preserved, prevents particle cluster algorithm Algorithm is degenerated in evolutionary process.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention With within principle, any modification, equivalent replacement, improvement and so on, should all be included in the protection scope of the present invention god.

Claims (6)

1. the DG Optimal Configuration Methods of a kind of meter and power distribution network operation risk cost, it is characterised in that step is as follows:
S1, constructs power distribution network operation risk cost model under DG grid-connect modes;
In formula:ClossFor the annual operating cost of power distribution network;Crisk,iTo consider the operation risk cost of DG power generation fluctuating characteristic introducings; N is the DG number of units with output fluctuation;
S2, constructs operation risk cost model under DG off-grid operation patterns;
Frisk=min (ωS,VRS,VS,LRS,LS,FRS,F) (13);
In formula:RS,VFor the out-of-limit risk of node voltage;RS,LRisk is overloaded for branch;RS,FTo lose load risk;ωS,VFor node The weight of voltage limit risk index, ωS,LThe weight of risk indicator is overloaded for branch;ωS, F areLose the power of load risk indicator Weight, and ωS,VS,LS,F=1;
S3, according to the object function and constraints of step S1 and step S2 construction power distribution network operation risk costs;
S4, solves step S3 using particle cluster algorithm is improved, obtains the particle with adaptive optimal control value change rate, the grain Corresponding son is exactly allocation plan.
2. the DG Optimal Configuration Methods of meter according to claim 1 and power distribution network operation risk cost, it is characterised in that In step S1, power distribution network operation risk cost includes power distribution network operating cost and operation risk cost;Concretely comprise the following steps:
S1.1, calculates power distribution network annual operating cost Closs
Closs=CDG+CL+Cen(6);
In formula:CDGUsed for the operation and maintenance expenses of DG;CLUsed for circuit operation and maintenance expenses;CenFor power purchase expense;
S1.2, calculates power distribution network and considers the operation risk cost C that DG power generation fluctuating characteristics introducerisk, calculation formula is:
Crisk,i=Pr,DGi·PRE,DGi·Cb·ti(7);
In formula:PRE,DGiContribute for i-th of the expected of DG;CbTo call unit costs needed for stand-by power supply;tiFor the year of i-th of DG Run time;Pr,DGiRepresent that i-th of DG with uncertain feature contributes less than the expected probability contributed;
When DG is wind turbine, wind turbine is contributed is less than the expected probability contributed:
In formula:f(PWT) be wind-driven generator output output power probability density, then when wind turbine access power distribution network when system operation wind Become by inches and be originally:
When DG is photo-voltaic power supply, photo-voltaic power supply is contributed is less than the expected probability contributed:
In formula:f(PPV) be photovoltaic output output power probability density, then when photo-voltaic power supply access power distribution network when system operation risk Cost is:
S1.3, with reference to step S1.1 and step S1.2, obtains power distribution network operation risk cost model under DG grid-connect modes;
In formula:ClossFor the annual operating cost of power distribution network;Crisk,iTo consider the operation risk cost of DG power generation fluctuating characteristic introducings; N is the DG number of units with output fluctuation.
3. the DG Optimal Configuration Methods of meter according to claim 2 and power distribution network operation risk cost, it is characterised in that In step S1.1, concretely comprise the following steps:
S1.1.1, calculates circuit operating cost CL, calculation formula is as follows:
In formula:CpuFor electricity price;τmaxHourage is lost for the annual peak load of i-th branch;ΔPLiFor having on i-th branch Work(is lost;
S1.1.2, calculates power purchase expense Cen, calculation formula is as follows:
In formula:TmaxFor peak load annual utilization hours;P∑NEWFor load increment;P∑DGContribute for DG;
S1.1.3, calculates the operation and maintenance expenses C of DGDG
The DG is at least one of wind turbine, photo-voltaic power supply and gas turbine;
When DG is wind turbine, the operation and maintenance expenses of wind turbine year cost only considers equipment investment, operation and maintenance cost, wind turbine year cost CWTCalculation formula be:
In formula:aWTFor the cost of wind turbine;rWT,0For discount rate;mWTFor the fan operation time limit;uWTUsed for the operation and maintenance expenses of wind turbine, generally It is taken as 5%aWT;NWTFor required wind turbine quantity;
When DG is photo-voltaic power supply, the year cost C of photo-voltaic power supplyPVCalculation formula be:
In formula:aPVFor the cost of photovoltaic;rPV,0For discount rate;mPVFor the photovoltaic motor operation time limit;uPVUsed for the operation and maintenance expenses of photovoltaic, Generally it is taken as 5%aPV;NPVFor required photovoltaic plant quantity;
When DG is gas turbine, the year cost C of gas turbineMTIncluding equipment cost and combustion gas expense, calculation formula is:
CMT=Cf,MT+Ct,MT(5);
In formula:Cf,MTFor the natural gas expense of system year operation;Ct,MTFor the year investment cost of system equipment;
S1.1.4, with reference to step S1.1.1-S1.1.3, obtains power distribution network annual operating cost Closs
Closs=CDG+CL+Cen(6);
In formula:CDGUsed for the operation and maintenance expenses of DG;CLUsed for circuit operation and maintenance expenses;CenFor power purchase expense.
4. the DG Optimal Configuration Methods of meter according to claim 1 and power distribution network operation risk cost, it is characterised in that In step S3, concretely comprise the following steps:
S3.1 constructs the object function of power distribution network operation risk cost, and formula is:
F=min (ωCFlossRFrisk) (14);
In formula:FlossTo consider the system total operating cost of DG operation risk costs;FriskTo consider the system operation of off-grid operation Value-at-risk;F is the catalogue scale value that DG is distributed rationally, and the final purpose of optimization is to make overall goal function minimum;
S3.2, constructs bound for objective function;
The constraints includes DG constraints, power-balance constraint, node voltage constraint, the constraint of branch transimission power and reverse tide Stream constraint.
5. the DG Optimal Configuration Methods of meter according to claim 4 and power distribution network operation risk cost, it is characterised in that In step S3.2, concretely comprise the following steps:
S3.2.1, construction DG constraints;
The DG constraints include total capacity, wind-driven generator number, photo-voltaic power supply number and the micro-gas-turbine board of DG accesses Number;
S3.2.1.1, the constraint of the total capacity of construction DG accesses;
Since wind-power electricity generation and photovoltaic generation are also influenced by wind speed, intensity of illumination, if DG capacity accountings are excessive, certainly will influence be The power quality of system, therefore the total capacity that DG need to be controlled to access, formula are:
In formula:SDGiFor i-th DG output power;Sl,maxFor power distribution network peak load total amount;η is penetration coefficient;
S3.2.1.2, constructs the constraint of wind-driven generator number, and formula is:
0≤NWT≤NWT,max(16);
In formula:NWTFor wind turbine number of units;NWT,maxFor the maximum allowable installation number of units of wind turbine;
S3.2.1.3, the number constraint of construction photo-voltaic power supply, formula are:
0≤NPV≤NPV,max(17);
In formula:NPVFor photo-voltaic power supply number of units;NPV,maxFor the maximum allowable installation number of units of photo-voltaic power supply;
S3.2.1.4, the number of units constraint of construction miniature gas turbine, formula are:
0≤NMT≤NMT,max(18);
In formula:NMTFor gas turbine number of units;NMT,maxFor the maximum allowable installation number of units of gas turbine;
S3.2.2, constructs power-balance constraint, and formula is:
In formula:PG,iFor node injecting power;PlossFor network loss;PLDFor workload demand;PDGiFor DG injecting powers, since wind-force is sent out The injecting power of motor and photovoltaic motor is all stochastic variable, therefore above formula is described as in the form of probability:
In formula:Pr0To meet the probability level of workload demand;
S3.2.3, the constraint of structure node voltage, formula are:
Uimin≤Ui≤Uimax(21);
In formula:Ui,minFor the upper limit of node i voltage;Ui,maxFor the lower limit of node i voltage;
S3.2.4, the transimission power constraint of construction branch, formula are:
|Pl,i|≤Pl,imax(22);
In formula:Pl,iFor the transimission power of i-th branch;Pl,imaxFor the transimission power upper limit of i-th branch;
S3.2.5, construction reversal tidal current constraint, formula are:
In formula:PDG,i+QDGiFor the DG injecting powers at node i;PLD,i+QLD,iFor the load power of node i;PL,i+QL,iFor section The power in point i injection circuits downstream;Smax iFor the maximum capacity of circuit i;μ is the limit value that can send power.
6. the DG Optimal Configuration Methods of meter according to claim 1 and power distribution network operation risk cost, it is characterised in that In step S4, concretely comprise the following steps:S4.1, power grid total capacity and the constraints of power grid individual node access capacity are accessed in DG Under, it is random to generate primary population;
The scale of population is set as m, then m particle in population population, its structure are:
(a1,a2,…,ai,…,an|b1,b2,…,bi,…,bn) (24);
In formula:I numbers for metric grid nodes, and i=1 ..., n;biType for the DG accessed at node i, by wind Three kinds of power generator, photo-voltaic power supply and miniature gas burner DG carry out calculating processing as different nodes;aiRepresent i-th of node The multiple of the unit rated capacity of upper access DG, aiTake [0, PDG,maxi/Pave] integer value in section, PDG,maxiPermit for node i Perhaps the maximum power accessed, PaveFor DG unit rated capacities;
S4.2, carries out Load flow calculation, obtains the Pareto optimal solution sets of object function, and calculate each grain in Pareto optimal solution sets The adaptive value of son, chooses optimal particle;
S4.3, according to the speed of current optimal particle more new particle and position;
S4.4, calculates the crowding distance of particle in Pareto optimal solution sets and updates external archival collection;
S4.4.1, calculates and appoints two particle distance d in Pareto optimal solution setsij, calculation formula is:
In formula, FlossTo consider the system total operating cost of DG operation risk costs;FriskTo consider the system operation of off-grid operation Value-at-risk;To consider the maximum of the system total operating cost of DG operation risk costs;For consider DG operation risks into The minimum value of this system total operating cost;To consider the maximum of the system operation value-at-risk of off-grid operation;To examine Consider the minimum value of the system operation value-at-risk of off-grid operation;
S4.4.2, calculates the crowding distance D of particle i in Pareto optimal solution setsi
Wherein, d1For any one particle i in Pareto optimal solution sets and with a distance from its first near particle a, calculation formula For:
d1=min { dij|j∈Qset,j≠i} (27);
d2For any one particle i in Pareto optimal solution sets and with a distance from its second near particle b, calculation formula is:
d2=min { dij|dij>d1,j∈Qset,j≠i} (28);
S4.4.3, according to the crowding distance D being calculatediValue, descending row is carried out to the solution in Pareto optimal solution sets Sequence, rejects the small solution of crowding distance, obtains global maximal solution;
S4.4.4, is saved in external archival by global maximal solution and concentrates;
S4.5, obtains each particle adaptive optimal control value change rate in Pareto optimal solution sets;
S4.6, judges whether adaptive optimal control value change rate is less than threshold value, if being less than threshold value, carrying out TSP question and judgement is No iteration is completed, if completing, the corresponding particle of output adaptive optimal control value change rate, the corresponding particle is exactly allocation plan, If do not complete iteration, repeat step S4.2-S4.5;If more than threshold value, then judge whether that iteration is completed, if completing, export The corresponding particle of adaptive optimal control value change rate, the corresponding particle is exactly allocation plan, if not completing iteration, repeat step S4.2-S4.5。
CN201711284150.XA 2017-12-07 2017-12-07 A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost Pending CN107959307A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711284150.XA CN107959307A (en) 2017-12-07 2017-12-07 A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711284150.XA CN107959307A (en) 2017-12-07 2017-12-07 A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost

Publications (1)

Publication Number Publication Date
CN107959307A true CN107959307A (en) 2018-04-24

Family

ID=61957573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711284150.XA Pending CN107959307A (en) 2017-12-07 2017-12-07 A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost

Country Status (1)

Country Link
CN (1) CN107959307A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109473992A (en) * 2019-01-21 2019-03-15 国网河北省电力有限公司经济技术研究院 A kind of method, system and terminal device improving power distribution network toughness
CN109672184A (en) * 2018-12-12 2019-04-23 国网江西省电力有限公司电力科学研究院 One kind distribution network voltage control method of photovoltaic containing high proportion and system
CN109995076A (en) * 2018-12-12 2019-07-09 云南电网有限责任公司电力科学研究院 A kind of photovoltaic based on energy storage collects system power and stablizes output cooperative control method
CN110474367A (en) * 2019-08-05 2019-11-19 广东工业大学 A kind of micro-capacitance sensor capacity configuration optimization method considering risk of loss
CN110826780A (en) * 2019-10-24 2020-02-21 华北电力大学 Injection upper limit optimization method and system during distributed power supply communication fault
CN111313409A (en) * 2020-03-05 2020-06-19 国网河北省电力有限公司 High-proportion controllable source load access petal type power distribution network fault self-healing method and system
CN116404646A (en) * 2023-06-08 2023-07-07 国网江西省电力有限公司电力科学研究院 Power system scheduling method and system considering standby risk

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109672184A (en) * 2018-12-12 2019-04-23 国网江西省电力有限公司电力科学研究院 One kind distribution network voltage control method of photovoltaic containing high proportion and system
CN109995076A (en) * 2018-12-12 2019-07-09 云南电网有限责任公司电力科学研究院 A kind of photovoltaic based on energy storage collects system power and stablizes output cooperative control method
CN109672184B (en) * 2018-12-12 2022-03-11 国网江西省电力有限公司电力科学研究院 Photovoltaic power distribution network voltage control method and system
CN109473992A (en) * 2019-01-21 2019-03-15 国网河北省电力有限公司经济技术研究院 A kind of method, system and terminal device improving power distribution network toughness
CN110474367A (en) * 2019-08-05 2019-11-19 广东工业大学 A kind of micro-capacitance sensor capacity configuration optimization method considering risk of loss
CN110474367B (en) * 2019-08-05 2024-01-05 广东工业大学 Micro-grid capacity configuration optimization method considering risk loss
CN110826780A (en) * 2019-10-24 2020-02-21 华北电力大学 Injection upper limit optimization method and system during distributed power supply communication fault
CN111313409A (en) * 2020-03-05 2020-06-19 国网河北省电力有限公司 High-proportion controllable source load access petal type power distribution network fault self-healing method and system
CN111313409B (en) * 2020-03-05 2023-03-24 国网河北省电力有限公司 High-proportion controllable source load access petal type power distribution network fault self-healing method and system
CN116404646A (en) * 2023-06-08 2023-07-07 国网江西省电力有限公司电力科学研究院 Power system scheduling method and system considering standby risk
CN116404646B (en) * 2023-06-08 2023-10-20 国网江西省电力有限公司电力科学研究院 Power system scheduling method and system considering standby risk

Similar Documents

Publication Publication Date Title
CN107959307A (en) A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost
CN109146706A (en) A kind of Transmission Expansion Planning in Electric method considering the flexibility equilibrium of supply and demand
CN104361403B (en) A kind of optimization packet configuration method of distributed power source and micro-capacitance sensor
CN106487005A (en) A kind of Electric power network planning method considering T-D tariff
CN109948849B (en) Power distribution network frame planning method considering energy storage access
CN107437824A (en) A kind of computational methods of the Area distribution formula power supply allowed capacity based on genetic algorithm
CN102510108B (en) Method for calculating maximum wind power installed capacity of district power network
CN113131468B (en) Multi-target power distribution network power supply recovery method considering user power failure loss
Zarei et al. Multi‐objective optimization model for distribution network reconfiguration in the presence of distributed generations
CN106803130A (en) Distributed power source accesses the planing method of power distribution network
CN109034587A (en) A kind of active distribution system Optimization Scheduling for coordinating a variety of controllables
Huang et al. An optimal operation method of cascade hydro-PV-pumped storage generation system based on multi-objective stochastic numerical P systems
CN112836957B (en) Regional comprehensive energy system planning method considering power supply reliability
CN113364043A (en) Micro-grid group optimization method based on condition risk value
Wang et al. Optimal distribution network expansion planning incorporating distributed generation
Xing et al. A rolling optimization method of reserve capacity considering wind power frequency control
CN109713720A (en) A kind of balance of electric power and ener method of new-energy grid-connected operation
CN109472716A (en) A kind of production capacity end power distribution method multifactor based on the considerations of genetic algorithm
CN110929968A (en) Comprehensive regulation and control method and system for multi-energy combined supply of smart city
Di et al. Multi-objective collaborative control scheduling optimization considering wind power grid-connected energy storage access
CN111030191B (en) Cell power grid planning method based on multi-target cooperation and self-optimization operation
Thorat et al. Optimization of fuel cost incorporating with wind, solar PV and Electric vehicle energy sources using improved artificial bee colony algorithm
Fan et al. Research on collaborative planning of power source, grid and load for Shanghai distribution network
CN110350575A (en) Meter and wind-powered electricity generation receive the transmission system planing method of ability and Demand Side Response
Cheng et al. Power and energy balance of active distribution network considering operation-control strategy

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180424

RJ01 Rejection of invention patent application after publication