CN107939379A - A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method and system - Google Patents

A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method and system Download PDF

Info

Publication number
CN107939379A
CN107939379A CN201711071035.4A CN201711071035A CN107939379A CN 107939379 A CN107939379 A CN 107939379A CN 201711071035 A CN201711071035 A CN 201711071035A CN 107939379 A CN107939379 A CN 107939379A
Authority
CN
China
Prior art keywords
perforation
steam
msub
ceng
tubing string
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711071035.4A
Other languages
Chinese (zh)
Inventor
杨清玲
朱静
何金宝
吕孝明
王伟迪
霍艳皎
周轶青
金璐
乔沐
冯紫微
邹杨
田文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN201711071035.4A priority Critical patent/CN107939379A/en
Publication of CN107939379A publication Critical patent/CN107939379A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/06Measuring temperature or pressure
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/24Enhanced recovery methods for obtaining hydrocarbons using heat, e.g. steam injection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/06Measuring temperature or pressure
    • E21B47/07Temperature

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geophysics (AREA)
  • Control Of Turbines (AREA)

Abstract

The present invention discloses a kind of thick oil heat production steam injection well and inhales vapour water swelling elastomer detection method and system, which, which inhales vapour water swelling elastomer detection method, includes:Test equipment is transferred in tubing string and obtains the temperature, pressure data of fluid and test well section secondary speed value in tubing string;Fluid state in tubing string is determined according to the temperature, pressure data;Each perforation Ceng Dingdi circle secondary speeds and corresponding injection quantity of steam are determined according to test well section secondary speed value;The suction vapour water swelling elastomer of each perforation layer is determined according to fluid state, each perforation Ceng Dingdi circle secondary speeds and corresponding injection quantity of steam in the tubing string.The thick oil heat production steam injection well inhale vapour water swelling elastomer detection method and system can each perforated interval of network analysis (perforation layer) inhale vapour water swelling elastomer, provide foundation so as to be analyzed for steam injection efficiency evaluation and reservoir producing status.

Description

A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method and system
Technical field
The present invention relates to the Technology of Heavy Oil Recovery field, more particularly to a kind of thick oil heat production steam injection well to inhale the detection of vapour water swelling elastomer Method and system.
Background technology
Viscous crude refers under formation condition that viscosity is more than 50 mpas, or degassed crude viscosity is under reservoir temperature The high viscosity heavy crude of 1000~10000 mpas.
In oilfield development process, since viscous crude has the characteristics such as viscosity height and poor fluidity, use steam injection heating power more Mining type is exploited.Since each reservoir properties difference is big, vapour (water suction) situation of suction certainly exists difference, therefore understands each The suction vaporous condition of a reservoir is extremely important, very big to instructing oil field production steam injection to have the function that, but does not have energy yet at present The technology that enough suction vapour water swelling elastomers to each reservoir are detected.
The content of the invention
In view of the deficiencies in the prior art, it is an object of the present invention to provide a kind of thick oil heat production steam injection well to inhale the detection of vapour water swelling elastomer Method and system, so as to each perforated interval of network analysis (perforation layer) inhales vapour water swelling elastomer, so as to be evaluated for steam injection efficiency And the analysis of reservoir producing status provides foundation.
To reach above-mentioned purpose, the present invention uses following scheme:
A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method, including:
Test equipment is transferred in tubing string and obtains the temperature, pressure data of fluid and test well section secondary speed in tubing string Value;
Fluid state in tubing string is determined according to the temperature, pressure data;
Each perforation Ceng Dingdi circle secondary speeds and corresponding injection steam are determined according to test well section secondary speed value Amount;
According to fluid state, each perforation Ceng Dingdi circle secondary speeds and corresponding injection steam in the tubing string Amount determines the suction vapour water swelling elastomer of each perforation layer.
As a preferred embodiment, the step that fluid state in tubing string is determined according to the temperature, pressure data Suddenly include:
It is steam condition that tube fluid is determined when the temperature, pressure data meet the following formula;And in the temperature Degree pressure data is unsatisfactory for determining that tube fluid is high-temperature-hot-water state during the following formula;
T ± Δs T=195.94P0.225-17.8
Wherein, T is the temperature value in tubing string, DEG C;P be tubing string in pressure value, MPa;Δ T is temperature error, DEG C;
It is correspondingly, described according to fluid state in the tubing string, each perforation Ceng Dingdi circle secondary speeds and right The injection quantity of steam answered determines that the suction vapour water swelling elastomer step of each perforation layer includes:
When tube fluid is steam condition, the suction vaporous condition of each perforation layer is calculated;
When tube fluid is high-temperature-hot-water, the water swelling elastomer of each perforation layer is calculated;
There is steam in partial completion layer, when partial completion layer has high-temperature-hot-water, more than high-temperature-hot-water position Perforation layer absorbs whole steam treatments, and calculates the suction vaporous condition of each perforation layer more than high-temperature-hot-water position.
As a preferred embodiment, described determine each perforation Ceng Dingdi circle according to test well section secondary speed value The step of secondary speed and corresponding injection quantity of steam, includes:
Horn mouth to secondary speed between the first perforation Ceng Ding circle is averaged, which is denoted as the first perforation Ceng Ding circle turbines and turns Fast Ro, corresponding total injection quantity of steam Q;Secondary speed is averaged between first perforation Ceng Di circle and the second perforation Ceng Ding circle, the value The secondary speed value R1 of the first perforation Ceng Di circle is denoted as, then the first perforation layer secondary speed difference DELTA R1=Ro-R1, corresponding first Perforation layer injection quantity of steam Q1;Secondary speed is averaged between second perforation Ceng Di circle and the 3rd perforation Ceng Ding circle, the value conduct The secondary speed value R2 of second perforation Ceng Di circle, then the second perforation layer secondary speed difference DELTA R2=R1-R2, corresponds to the second perforation Layer injection quantity of steam Q2;The rest may be inferred, until the perforated zone that all test well sections are related to is disposed.
As a preferred embodiment, further include:With two connect completely perforation layer when, then take contact surface whirlpool Wheel speed is as two perforation Ceng Dingdi circle secondary speeds.
As a preferred embodiment, further include:When the whole following secondary speed of perforation layer still remains, rounding Secondary speed average value below a perforation layer is denoted as benchmark secondary speed Ra, then the secondary speed value of whole perforation layer record is equal Subtract Ra.
As a preferred embodiment, in the temperature that test equipment is transferred in tubing string and obtains fluid in tubing string In pressure data and test well section secondary speed value step, the test equipment includes temperature, pressure tester and turbine Flowmeter.
As a preferred embodiment, the temperature, pressure tester is at the uniform velocity transferred in tubing string and is obtained in tubing string The temperature, pressure data of fluid;The lowering velocity of the temperature, pressure tester is within 360 ms/min.
As a preferred embodiment, the turbine flowmeter is at the uniform velocity transferred in tubing string and obtains test well section whirlpool Wheel speed value;Lowering velocity of the turbine flowmeter more than horn mouth within 30 ms/min, below horn mouth under Speed is put within 10 ms/min.
As a preferred embodiment, when fluid state is steam condition in the tubing string, steam condition is calculated The suction vaporous condition of corresponding perforation layer;The suction vaporous state includes inhaling vapour percentage, steam absorbing amount, inhales vapour intensity;And utilize as follows Formula, which calculates, to be inhaled vapour percentage, steam absorbing amount, inhales vapour intensity;
In above formula, aiTo inhale vapour percentage, zero dimension;R0Make even for horn mouth to secondary speed between the first perforation Ceng Ding circle Average, revolutions per second;ΔRiFor the difference of i-th of perforation Ceng Dingdi circle secondary speed, revolutions per second;
In above formula, QiFor i-th of perforation layer steam absorbing amount, ton hour;Q is steam injection well well head steam injection, ton hour;
In above formula, biTo inhale vapour intensity, ton hour/rice;hiFor i-th of perforation layer effective thickness, rice.
As a preferred embodiment, when fluid state is steam condition in the tubing string, steam condition is calculated The water swelling elastomer of corresponding perforation layer;The water suction state includes water suction percentage, water absorption, injection index;And utilize as follows Formula calculates water suction percentage, water absorption, injection index;
In above formula, aiFor the percentage that absorbs water, zero dimension;R0Make even for horn mouth to secondary speed between the first perforation Ceng Ding circle Average, revolutions per second;ΔRiFor the difference of i-th of perforation Ceng Dingdi circle secondary speed, revolutions per second;
In above formula, QiFor i-th of perforation layer water absorption, ton hour;Q is wellhead of water injection well steam injection, ton hour;
In above formula, biFor injection index, ton hour/rice;hiFor i-th of perforation layer effective thickness, rice.
As a preferred embodiment, further include:Determine the state that is hampered of the test equipment decentralization process;
It is correspondingly, described according to fluid state in the tubing string, each perforation Ceng Dingdi circle secondary speeds and right The injection quantity of steam answered determines that the suction vapour water swelling elastomer step of each perforation layer is:
According to fluid state in the tubing string, the state that is hampered, each perforation Ceng Dingdi circle secondary speeds and Corresponding injection quantity of steam determines the suction vapour water swelling elastomer of each perforation layer.
As a preferred embodiment, the state that is hampered for determining the test equipment decentralization process includes: When test equipment decentralization depth is not reaching to last perforation layer, the position that is hampered in the test equipment decentralization process is determined;
It is correspondingly, described according to fluid state, the state that is hampered, each perforation Ceng Dingdi circle whirlpools in the tubing string Wheel speed and corresponding injection quantity of steam determine that the suction vapour water swelling elastomer step of each perforation layer includes:
When being hampered position between two perforation layers, then the suction of each perforation layer more than position that determines to be hampered respectively Vaporous condition, and comprehensive suction vaporous condition is calculated the perforation layer below the position that is hampered.
As a preferred embodiment, the state that is hampered for determining the test equipment decentralization process includes: When test equipment decentralization depth is not reaching to last perforation layer, the position that is hampered in the test equipment decentralization process is determined;
It is correspondingly, described according to fluid state, the state that is hampered, each perforation Ceng Dingdi circle whirlpools in the tubing string Wheel speed and corresponding injection quantity of steam determine that the suction vapour water swelling elastomer step of each perforation layer includes:In the position that is hampered at certain When inside a perforation layer, then the suction vapour situation of each perforation layer more than the perforation layer is calculated, and to the perforation layer and its following Perforation layer calculate and comprehensive inhale vaporous condition.
The state that is hampered for determining the test equipment decentralization process includes:The comprehensive vaporous condition of inhaling includes comprehensive inhale Vapour percentage, comprehensive steam absorbing amount, comprehensive suction vapour intensity;The synthesis inhales vaporous condition calculation formula:
az=1- ∑s ai
Wherein, azVapour percentage, a are inhaled to be comprehensiveiFor the suction vapour percentage of more than position that is hampered i-th of perforation layer;
Qz=Q- ∑s Qi
Wherein, QzFor comprehensive steam absorbing amount, QiFor more than the position that is hampered i-th of perforation layer water absorption, ton hour;Q is water filling Well well head steam injection, ton hour;
Iz=Qz/Hz
Wherein, IzVapour intensity, h are inhaled to be comprehensivezFor the effective thickness of the following perforation layer in the position that is hampered, rice.
A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detecting system, including:
Acquisition module, the temperature, pressure data of fluid and test in tubing string are obtained for transferring test equipment in tubing string Well section secondary speed value;
Fluid state determining module, for determining fluid state in tubing string according to the temperature, pressure data;
First computing module, for according to test well section secondary speed value determine each perforation Ceng Dingdi circle secondary speeds with And corresponding injection quantity of steam;
Second computing module, for according to fluid state, each perforation Ceng Dingdi circle secondary speeds in the tubing string And corresponding injection quantity of steam determines the suction vapour water swelling elastomer of each perforation layer.
In summary as can be seen that the application corresponds to turbine flow metering rotating speed according to perforated interval top bottom depth Interval divides, and using analytic approach of successively decreasing, establishes a set of thick oil heat production steam injection well and inhales vapour state testing method, this method further contemplates Whether instrument is hampered and is hampered position difference etc. in test process, and judges in tubing string according to temperature, pressure data in tubing string Fluid state, and then judge specific suction vapour water suction situation, there is very important practical value.
With reference to following explanation and attached drawing, only certain exemplary embodiments of this invention is disclose in detail, specifies the original of the present invention Reason can be in a manner of adopted.It should be understood that embodiments of the present invention are not so limited in scope.In appended power In the range of the spirit and terms that profit requires, embodiments of the present invention include many changes, modifications and are equal.
The feature for describing and/or showing for a kind of embodiment can be in a manner of same or similar one or more Used in a other embodiment, it is combined with the feature in other embodiment, or substitute the feature in other embodiment.
It should be emphasized that term "comprises/comprising" refers to the presence of feature, one integral piece, step or component when being used herein, but simultaneously It is not excluded for the presence or additional of one or more further features, one integral piece, step or component.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is attached drawing needed in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those skilled in the art, without having to pay creative labor, can be with root Other attached drawings are obtained according to these attached drawings.
Fig. 1 is that one embodiment of the present invention provides a kind of thick oil heat production steam injection well suction vapour water swelling elastomer detection method flow Figure;
Fig. 2 is that another embodiment of the present invention provides a kind of thick oil heat production steam injection well suction vapour water swelling elastomer detection method stream Cheng Tu;
Fig. 3 is that another embodiment of the present invention provides a kind of thick oil heat production steam injection well suction vapour water swelling elastomer detection method stream Cheng Tu;
Fig. 4 is that another embodiment of the present invention provides a kind of thick oil heat production steam injection well suction vapour water swelling elastomer detecting system mould Block schematic diagram.
Embodiment
In order to make those skilled in the art more fully understand the technical solution in the present invention, below in conjunction with of the invention real The attached drawing in example is applied, the technical solution in the embodiment of the present invention is clearly and completely described, it is clear that described implementation Example is only part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this area is common Technical staff's all other embodiments obtained on the premise of creative work is not made, should all belong to guarantor of the present invention The scope of shield.
It should be noted that when element is referred to as " being arranged at " another element, it can be directly on another element Or there may also be element placed in the middle.When an element is considered as " connection " another element, it can be directly connected to To another element or it may be simultaneously present centering elements.Term as used herein " vertical ", " horizontal ", " left side ", For illustrative purposes only, it is unique embodiment to be not offered as " right side " and similar statement.
Unless otherwise defined, all of technologies and scientific terms used here by the article is with belonging to technical field of the invention The normally understood implication of technical staff is identical.Term used in the description of the invention herein is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.Term as used herein "and/or" includes one or more The arbitrary and all combination of relevant Listed Items.
Please refer to Fig.1, Fig. 3, one embodiment of the present invention provides a kind of thick oil heat production steam injection well and inhales the inspection of vapour water swelling elastomer Survey method, includes the following steps:
S10, transfer the temperature, pressure data of fluid in test equipment acquisition tubing string in tubing string and test well section turbine Tachometer value.
In step S10, the test equipment includes temperature, pressure tester and turbine flowmeter.Specifically, The temperature, pressure tester is at the uniform velocity transferred in tubing string and obtains the temperature, pressure data of fluid in tubing string;The temperature, pressure is surveyed The lowering velocity of instrument is tried within 360 ms/min.
The turbine flowmeter is at the uniform velocity transferred in tubing string and obtains test well section secondary speed value;The turbine flowmeter Lowering velocity more than horn mouth is within 30 ms/min, and the lowering velocity below horn mouth is within 10 ms/min.
S20, according to the temperature, pressure data determine fluid state in tubing string.
In step S20, fluid state can be divided into high-temperature-hot-water state, steam condition in tubing string, and then according to height Water state is warmed, steam condition calculates corresponding water swelling elastomer or inhales vaporous condition.
S30, according to test well section secondary speed value determine each perforation Ceng Dingdi circle secondary speeds and corresponding injection Quantity of steam;
It is described that each perforation Ceng Dingdi circle secondary speeds are determined according to test well section secondary speed value in step S30 And corresponding the step of injecting quantity of steam, includes:
Horn mouth to secondary speed between the first perforation Ceng Ding circle is averaged, which is denoted as the first perforation Ceng Ding circle turbines and turns Fast Ro, corresponding total injection quantity of steam Q;Secondary speed is averaged between first perforation Ceng Di circle and the second perforation Ceng Ding circle, the value The secondary speed value R1 of the first perforation Ceng Di circle is denoted as, then the first perforation layer secondary speed difference DELTA R1=Ro-R1, corresponding first Perforation layer injection quantity of steam Q1;Secondary speed is averaged between second perforation Ceng Di circle and the 3rd perforation Ceng Ding circle, the value conduct The secondary speed value R2 of second perforation Ceng Di circle, then the second perforation layer secondary speed difference DELTA R2=R1-R2, corresponds to the second perforation Layer injection quantity of steam Q2;The rest may be inferred, until the perforated zone that all test well sections are related to is disposed.
Further, step S30 is further included:With two connect completely perforation layer when, then take contact surface turbine to turn Speed is used as two perforation Ceng Dingdi circle secondary speeds.
Further, step S30 is further included:When the whole following secondary speed of perforation layer still remains, rounding is penetrated Secondary speed average value below aperture layer is denoted as benchmark secondary speed Ra, then the secondary speed value of whole perforation layer record subtracts Ra。
It should be noted that between step S30 and step S20 and indefinite front and rear execution sequence, the two can be former Order performs afterwards, can also perform at the same time, the application is simultaneously not intended to be limited in any.
S40, according to fluid state, each perforation Ceng Dingdi circle secondary speeds and corresponding injection in the tubing string Quantity of steam determines the suction vapour water swelling elastomer of each perforation layer.
Wherein, when fluid state is steam condition in the tubing string, the suction vapour of perforation layer corresponding to steam condition is calculated Situation;The suction vaporous state includes inhaling vapour percentage, steam absorbing amount, inhales vapour intensity;And utilization equation below calculating suction vapour percentage, Steam absorbing amount, inhale vapour intensity;
In above formula, aiTo inhale vapour percentage, zero dimension;R0Make even for horn mouth to secondary speed between the first perforation Ceng Ding circle Average, revolutions per second;ΔRiFor the difference of i-th of perforation Ceng Dingdi circle secondary speed, revolutions per second;
In above formula, QiFor i-th of perforation layer steam absorbing amount, ton hour;Q is steam injection well well head steam injection, ton hour;
In above formula, biTo inhale vapour intensity, ton hour/rice;hiFor i-th of perforation layer effective thickness, rice.
Wherein, when fluid state is steam condition in the tubing string, the water suction of perforation layer corresponding to steam condition is calculated Situation;The water suction state includes water suction percentage, water absorption, injection index;And utilization equation below calculating water suction percentage, Water absorption, injection index;
In above formula, aiFor the percentage that absorbs water, zero dimension;R0Make even for horn mouth to secondary speed between the first perforation Ceng Ding circle Average, revolutions per second;ΔRiFor the difference of i-th of perforation Ceng Dingdi circle secondary speed, revolutions per second;
In above formula, QiFor i-th of perforation layer water absorption, ton hour;Q is wellhead of water injection well steam injection, ton hour;
In above formula, biFor injection index, ton hour/rice;hiFor i-th of perforation layer effective thickness, rice.
Embodiment of continuing from the preceding paragraph describes, in the step that fluid state in tubing string is determined according to the temperature, pressure data Suddenly in (i.e. described step S20), it is steam condition that tube fluid is determined when the temperature, pressure data meet the following formula;With And determine that tube fluid is high-temperature-hot-water state when the temperature, pressure data are unsatisfactory for the following formula;
T ± Δs T=195.94P0.225-17.8
Wherein, T is the temperature value in tubing string, DEG C;P be tubing string in pressure value, MPa;Δ T is temperature error, DEG C;
Furthermore it is also possible to fluid state is judged according to the pressure value and the positive negative correlativing relation of temperature value obtained.Specifically, The temperature value obtained while the test pressure value of acquisition gradually increases is gradually reduced (the two is negatively correlated), then judges in tubing string The fluid state of relevant position (position for pressure and temperature negative correlation occur) is high-temperature-hot-water.Wherein, Δ T can be according to steam injection Tubing string historical test data determines, or determines based on experience value, it is preferred that Δ T can be less than 5 degrees Celsius, specifically, Δ T is 2 degrees Celsius.
It is correspondingly, described according to fluid state in the tubing string, each perforation Ceng Dingdi circle secondary speeds and right The injection quantity of steam answered determines that the suction vapour water swelling elastomer step (i.e. described step S40) of each perforation layer includes:In tube fluid When being steam condition, the suction vaporous condition of each perforation layer is calculated.When tube fluid is high-temperature-hot-water, each perforation is calculated The water swelling elastomer of layer.There is steam in partial completion layer, when partial completion layer has high-temperature-hot-water, according to high-temperature-hot-water position with On perforation layer absorb whole steam treatments, and the suction vaporous condition for calculating each perforation layer more than high-temperature-hot-water position (and is pressed It is allocated according to percentage).
In a preferred embodiment, as shown in Figure 2 and Figure 3, it is the various situations occurred in reply test process, protects Card test smoothly completes, and it is further comprising the steps of which inhales vapour water swelling elastomer detection method:
S25, the state that is hampered for determining the test equipment decentralization process.
It is correspondingly, described according to fluid state in the tubing string, each perforation Ceng Dingdi circle secondary speeds and right The injection quantity of steam answered determines that the suction vapour water swelling elastomer step of each perforation layer is:According to fluid state in the tubing string, described Be hampered state, each perforation Ceng Dingdi circle secondary speeds and the corresponding suction vapour for injecting quantity of steam and determining each perforation layer Water swelling elastomer.
In a specific embodiment, shown in Fig. 3, the step S25 includes:It is not reaching in test equipment decentralization depth During last perforation layer, the position that is hampered in the test equipment decentralization process is determined.
It is correspondingly, described according to fluid state, the state that is hampered, each perforation Ceng Dingdi circle whirlpools in the tubing string Wheel speed and corresponding injection quantity of steam determine that the suction vapour water swelling elastomer step of each perforation layer includes:
When being hampered position between two perforation layers, then the suction of each perforation layer more than position that determines to be hampered respectively Vaporous condition, and comprehensive suction vaporous condition is calculated the perforation layer below the position that is hampered.
In another feasible embodiment, as shown in figure 3, the step S25 includes:Do not have in test equipment decentralization depth When reaching last perforation layer, the position that is hampered in the test equipment decentralization process is determined.
It is correspondingly, described according to fluid state, the state that is hampered, each perforation Ceng Dingdi circle whirlpools in the tubing string Wheel speed and corresponding injection quantity of steam determine that the suction vapour water swelling elastomer step of each perforation layer includes:In the position that is hampered at certain When inside a perforation layer, then the suction vapour situation of each perforation layer more than the perforation layer is calculated, and to the perforation layer and its following Perforation layer calculate and comprehensive inhale vaporous condition.
Wherein, for above-described embodiment, comprehensive vaporous condition of inhaling can be comprehensive suction vapour percentage, comprehensive steam absorbing amount, synthesis Inhale vapour intensity.Specifically, the synthesis inhales vaporous condition is considered as single perforation layer by all perforation layers below the position that is hampered, so that its Percentage more than the position that is hampered be able to can be calculated by calculating after the suction vaporous condition of each perforation layer according to parameters total value The synthesis inhales vaporous condition.
As shown in figure 3, the comprehensive vaporous condition of inhaling inhales vapour percentage, comprehensive steam absorbing amount, comprehensive suction vapour intensity including comprehensive; The synthesis inhales vaporous condition calculation formula:az=1- ∑s ai;Wherein, azVapour percentage, a are inhaled to be comprehensiveiFor more than the position that is hampered The suction vapour percentage of i perforation layer;Qz=Q- ∑s Qi;Wherein, QzFor comprehensive steam absorbing amount, QiFor more than the position that is hampered i-th of perforation Layer water absorption, ton hour;Q is wellhead of water injection well steam injection, ton hour;Iz=Qz/Hz;Wherein, IzIt is strong for comprehensive suction vapour Degree, hzFor the effective thickness of the following perforation layer in the position that is hampered, rice.
In summary as can be seen that present embodiment carries out turbine flow metering rotating speed according to perforated interval top bottom depth Corresponding interval division, using analytic approach of successively decreasing, establishes a set of thick oil heat production steam injection well and inhales vapour state testing method, this method is also Consider whether instrument is hampered and is hampered position difference etc. in test process, and judge pipe according to temperature, pressure data in tubing string Fluid state in column, and then judge specific suction vapour (water) situation, there is very important practical value.
As shown in figure 4, another embodiment of the present invention, which also provides a kind of thick oil heat production steam injection well, inhales the inspection of vapour water swelling elastomer Examining system, including:Acquisition module 100, the temperature, pressure data for obtaining fluid in tubing string for transferring test equipment in tubing string And test well section secondary speed value;Fluid state determining module 200, for being determined according to the temperature, pressure data in tubing string Fluid state;First computing module 300, for determining that each perforation Ceng Dingdi circle turbines turn according to test well section secondary speed value Fast and corresponding injection quantity of steam;Second computing module 400, for according to fluid state in the tubing string, described each penetrate Aperture layer Ding Di circle secondary speeds and corresponding injection quantity of steam determine the suction vapour water swelling elastomer of each perforation layer.
The thick oil heat production steam injection well inhales vapour water swelling elastomer detecting system and may be referred to above-mentioned thick oil heat production steam injection well suction vapour suction The description of aqueous condition detection method, is no longer repeated herein.
In summary as can be seen that present embodiment considers that instrument is hampered and the different situations such as fluid state in tubing string, build Set of system thick oil heat production steam injection well is found and has inhaled vaporous condition detection system, so as to be steam injection efficiency evaluation and reservoir producing status point Analysis provides foundation.
Herein cited any digital value all include between lower limit to upper limit value with the lower value of an incremented and The all values of upper value, there are the interval of at least two units between any lower value and any much higher value.For example, such as Fruit elaborates that the quantity of component or the value of process variable (such as temperature, pressure, time etc.) are from 1 to 90, preferably from 20 To 80, more preferably from 30 to 70, then purpose is arrived in order to illustrate also clearly listing such as 15 to 85,22 in the specification 68th, 43 to 51,30 to 32 is equivalent.For the value less than 1, it is 0.0001,0.001,0.01,0.1 suitably to think a unit. These are only intended to the example clearly expressed, it is believed that the numerical value enumerated between minimum and peak is possible to Combination is all expressly set forth in the specification in a similar manner.
Unless otherwise indicated, all scopes all include all numerals between endpoint and endpoint.It is used together with scope " about " or " approximation " be suitable for two endpoints of the scope.Thus, " about 20 to 30 " are intended to covering " about 20 to about 30 ", including at least the endpoint indicated.
All articles and reference disclosed, including patent application and publication, for various purposes by quoting knot Together in this.Identified element, component, component or step and reality should be included by describing the term " substantially by ... form " of combination Other elements, component, component or the step of the basic novel feature of the combination are not influenced in matter.Using term "comprising" or " comprising " describes the combination of element here, component, component or step it is also contemplated that substantially by these elements, component, component Or the embodiment that step is formed.Here by using term " can with ", it is intended to it is described any to illustrate that " can with " includes Attribute is all optional.
Multiple element, component, component or step can be provided by single integrated component, component, component or step.It is alternative Ground, single integrated component, component, component or step can be divided into separated multiple element, component, component or step.It is used for The open "a" or "an" for describing element, component, component or step is not said to exclude other elements, component, component Or step.
It should be understood that above description is to illustrate rather than to be limited.By reading above-mentioned retouch State, many embodiments and many applications outside the example provided all will be aobvious and easy for a person skilled in the art See.Therefore, the scope of this teaching should not be determined with reference to foregoing description, but should with reference to appended claims and this The four corner of the equivalent that a little claims are possessed determines.It is for comprehensive purpose, all articles and special with reference to including The disclosure of profit application and bulletin is all by reference to being incorporated herein.Theme disclosed herein is omitted in preceding claims Any aspect is not intended to abandon the body matter, also should not be considered as inventor the theme is not thought of as it is disclosed A part for subject matter.

Claims (15)

1. a kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method, it is characterised in that including:
Test equipment is transferred in tubing string and obtains the temperature, pressure data of fluid and test well section secondary speed value in tubing string;
Fluid state in tubing string is determined according to the temperature, pressure data;
Each perforation Ceng Dingdi circle secondary speeds and corresponding injection quantity of steam are determined according to test well section secondary speed value;
It is true according to fluid state, each perforation Ceng Dingdi circle secondary speeds and corresponding injection quantity of steam in the tubing string The suction vapour water swelling elastomer of fixed each perforation layer.
2. thick oil heat production steam injection well as claimed in claim 1 inhales vapour water swelling elastomer detection method, it is characterised in that:
Described the step of determining fluid state in tubing string according to the temperature, pressure data, includes:
It is steam condition that tube fluid is determined when the temperature, pressure data meet the following formula;And in the temperature pressure Force data is unsatisfactory for determining that tube fluid is high-temperature-hot-water state during the following formula;
T ± Δs T=195.94P0.225-17.8
Wherein, T is the temperature value in tubing string, DEG C;P be tubing string in pressure value, MPa;Δ T is temperature error, DEG C;
It is correspondingly, described according to fluid state in the tubing string, each perforation Ceng Dingdi circle secondary speeds and corresponding Injection quantity of steam determines that the suction vapour water swelling elastomer step of each perforation layer includes:
When tube fluid is steam condition, the suction vaporous condition of each perforation layer is calculated;
When tube fluid is high-temperature-hot-water, the water swelling elastomer of each perforation layer is calculated;
There is steam in partial completion layer, when partial completion layer has high-temperature-hot-water, according to perforation more than high-temperature-hot-water position Layer absorbs whole steam treatments, and calculates the suction vaporous condition of each perforation layer more than high-temperature-hot-water position.
3. thick oil heat production steam injection well as claimed in claim 1 inhales vapour water swelling elastomer detection method, it is characterised in that:The basis Test well section secondary speed value determines that the step of each perforation Ceng Dingdi circle secondary speeds and corresponding injection quantity of steam includes:
Horn mouth to secondary speed between the first perforation Ceng Ding circle is averaged, which is denoted as the first perforation Ceng Ding circle secondary speeds Ro, corresponding total injection quantity of steam Q;Secondary speed is averaged between first perforation Ceng Di circle and the second perforation Ceng Ding circle, value note For the secondary speed value R1 of the first perforation Ceng Di circle, then the first perforation layer secondary speed difference DELTA R1=Ro-R1, corresponds to first and penetrates Aperture layer injection quantity of steam Q1;Secondary speed is averaged between second perforation Ceng Di circle and the 3rd perforation Ceng Ding circle, and the value is as The secondary speed value R2 of two perforation Ceng Di circle, then the second perforation layer secondary speed difference DELTA R2=R1-R2, corresponds to the second perforation layer Inject quantity of steam Q2;The rest may be inferred, until the perforated zone that all test well sections are related to is disposed.
4. thick oil heat production steam injection well as claimed in claim 3 inhales vapour water swelling elastomer detection method, it is characterised in that:Further include: With two connect completely perforation layer when, then take contact surface secondary speed as two perforation Ceng Dingdi circle secondary speeds.
5. thick oil heat production steam injection well as claimed in claim 3 inhales vapour water swelling elastomer detection method, it is characterised in that:Further include: When the whole following secondary speed of perforation layer still remains, the secondary speed average value below rounding perforation layer is denoted as benchmark whirlpool Wheel speed Ra, then the secondary speed value that whole perforation layer records subtract Ra.
6. thick oil heat production steam injection well as claimed in claim 1 inhales vapour water swelling elastomer detection method, it is characterised in that:It is described Decentralization test equipment obtains the temperature, pressure data of fluid in tubing string and tests in well section secondary speed value step, institute in tubing string Stating test equipment includes temperature, pressure tester and turbine flowmeter.
7. thick oil heat production steam injection well as claimed in claim 6 inhales vapour water swelling elastomer detection method, it is characterised in that:In tubing string At the uniform velocity transfer the temperature, pressure tester and obtain the temperature, pressure data of fluid in tubing string;The temperature, pressure tester Lowering velocity is within 360 ms/min.
8. thick oil heat production steam injection well as claimed in claim 6 inhales vapour water swelling elastomer detection method, it is characterised in that:In tubing string At the uniform velocity transfer the turbine flowmeter and obtain test well section secondary speed value;Under the turbine flowmeter is more than horn mouth Speed is put within 30 ms/min, the lowering velocity below horn mouth is within 10 ms/min.
9. thick oil heat production steam injection well as claimed in claim 2 inhales vapour water swelling elastomer detection method, it is characterised in that:In the pipe When fluid state is steam condition in column, the suction vaporous condition of perforation layer corresponding to steam condition is calculated;The suction vaporous state includes Inhale vapour percentage, steam absorbing amount, inhale vapour intensity;And calculated using equation below and inhale vapour percentage, steam absorbing amount, inhale vapour intensity;
<mrow> <msub> <mi>a</mi> <mi>i</mi> </msub> <mo>=</mo> <mfrac> <mrow> <msub> <mi>&amp;Delta;R</mi> <mi>i</mi> </msub> </mrow> <msub> <mi>R</mi> <mn>0</mn> </msub> </mfrac> <mo>&amp;times;</mo> <mn>100</mn> <mi>%</mi> </mrow>
In above formula, aiTo inhale vapour percentage, zero dimension;R0It is averaged for horn mouth to secondary speed between the first perforation Ceng Ding circle, Revolutions per second;ΔRiFor the difference of i-th of perforation Ceng Dingdi circle secondary speed, revolutions per second;
<mrow> <msub> <mi>Q</mi> <mi>i</mi> </msub> <mo>=</mo> <mfrac> <mrow> <msub> <mi>&amp;Delta;R</mi> <mi>i</mi> </msub> </mrow> <msub> <mi>R</mi> <mn>0</mn> </msub> </mfrac> <mi>Q</mi> </mrow>
In above formula, QiFor i-th of perforation layer steam absorbing amount, ton hour;Q is steam injection well well head steam injection, ton hour;
<mrow> <msub> <mi>b</mi> <mi>i</mi> </msub> <mo>=</mo> <mfrac> <msub> <mi>Q</mi> <mi>i</mi> </msub> <msub> <mi>h</mi> <mi>i</mi> </msub> </mfrac> </mrow>
In above formula, biTo inhale vapour intensity, ton hour/rice;hiFor i-th of perforation layer effective thickness, rice.
10. thick oil heat production steam injection well as claimed in claim 2 inhales vapour water swelling elastomer detection method, it is characterised in that:Described When fluid state is steam condition in tubing string, the water swelling elastomer of perforation layer corresponding to steam condition is calculated;The water suction state bag Include water suction percentage, water absorption, injection index;And calculate water suction percentage, water absorption, injection index using equation below;
<mrow> <msub> <mi>a</mi> <mi>i</mi> </msub> <mo>=</mo> <mfrac> <mrow> <msub> <mi>&amp;Delta;R</mi> <mi>i</mi> </msub> </mrow> <msub> <mi>R</mi> <mn>0</mn> </msub> </mfrac> <mo>&amp;times;</mo> <mn>100</mn> <mi>%</mi> </mrow>
In above formula, aiFor the percentage that absorbs water, zero dimension;R0It is averaged for horn mouth to secondary speed between the first perforation Ceng Ding circle, Revolutions per second;ΔRiFor the difference of i-th of perforation Ceng Dingdi circle secondary speed, revolutions per second;
<mrow> <msub> <mi>Q</mi> <mi>i</mi> </msub> <mo>=</mo> <mfrac> <mrow> <msub> <mi>&amp;Delta;R</mi> <mi>i</mi> </msub> </mrow> <msub> <mi>R</mi> <mn>0</mn> </msub> </mfrac> <mi>Q</mi> </mrow>
In above formula, QiFor i-th of perforation layer water absorption, ton hour;Q is wellhead of water injection well steam injection, ton hour;
<mrow> <msub> <mi>b</mi> <mi>i</mi> </msub> <mo>=</mo> <mfrac> <msub> <mi>Q</mi> <mi>i</mi> </msub> <msub> <mi>h</mi> <mi>i</mi> </msub> </mfrac> </mrow>
In above formula, biFor injection index, ton hour/rice;hiFor i-th of perforation layer effective thickness, rice.
11. the thick oil heat production steam injection well as described in claim 9 or 10 inhales vapour water swelling elastomer detection method, it is characterised in that:Also Including:Determine the state that is hampered of the test equipment decentralization process;
It is correspondingly, described according to fluid state in the tubing string, each perforation Ceng Dingdi circle secondary speeds and corresponding Injection quantity of steam determines that the suction vapour water swelling elastomer step of each perforation layer is:
According to fluid state, the state that is hampered, each perforation Ceng Dingdi circle secondary speeds and correspondence in the tubing string Injection quantity of steam determine the suction vapour water swelling elastomer of each perforation layer.
12. thick oil heat production steam injection well as claimed in claim 11 inhales vapour water swelling elastomer detection method, it is characterised in that:It is described true The state that is hampered of the fixed test equipment decentralization process includes:Last perforation layer is not reaching in test equipment decentralization depth When, determine the position that is hampered in the test equipment decentralization process;
Correspondingly, described turn according to fluid state, the state that is hampered, each perforation Ceng Dingdi circle turbines in the tubing string Fast and corresponding injection quantity of steam determines that the suction vapour water swelling elastomer step of each perforation layer includes:
When being hampered position between two perforation layers, then the suction vaporous of each perforation layer more than position that determines to be hampered respectively Condition, and comprehensive suction vaporous condition is calculated the perforation layer below the position that is hampered.
13. thick oil heat production steam injection well as claimed in claim 11 inhales vapour water swelling elastomer detection method, it is characterised in that:It is described true The state that is hampered of the fixed test equipment decentralization process includes:Last perforation layer is not reaching in test equipment decentralization depth When, determine the position that is hampered in the test equipment decentralization process;
Correspondingly, described turn according to fluid state, the state that is hampered, each perforation Ceng Dingdi circle turbines in the tubing string Fast and corresponding injection quantity of steam determines that the suction vapour water swelling elastomer step of each perforation layer includes:Being hampered, position is penetrated at some When inside aperture layer, then the suction vapour situation of each perforation layer more than the perforation layer is calculated, and to the perforation layer and its following penetrate Aperture layer calculates comprehensive suction vaporous condition.
14. the thick oil heat production steam injection well as described in claim 12 or 13 inhales vapour water swelling elastomer detection method, it is characterised in that:Institute State comprehensive vaporous condition of inhaling and inhale vapour percentage, comprehensive steam absorbing amount, comprehensive suction vapour intensity including comprehensive;The synthesis inhales vaporous condition and calculates public affairs Formula is:
az=1- ∑s ai
Wherein, azVapour percentage, a are inhaled to be comprehensiveiFor the suction vapour percentage of more than position that is hampered i-th of perforation layer;
Qz=Q- ∑s Qi
Wherein, QzFor comprehensive steam absorbing amount, QiFor more than the position that is hampered i-th of perforation layer water absorption, ton hour;Q is water injection well well Mouth steam injection, ton hour;
Iz=Qz/Hz
Wherein, IzVapour intensity, h are inhaled to be comprehensivezFor the effective thickness of the following perforation layer in the position that is hampered, rice.
15. a kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detecting system, it is characterised in that including:
Acquisition module, the temperature, pressure data of fluid and test well section in tubing string are obtained for transferring test equipment in tubing string Secondary speed value;
Fluid state determining module, for determining fluid state in tubing string according to the temperature, pressure data;
First computing module, for determining each perforation Ceng Dingdi circle secondary speeds and right according to test well section secondary speed value The injection quantity of steam answered;
Second computing module, for according to fluid state in the tubing string, each perforation Ceng Dingdi circle secondary speeds and Corresponding injection quantity of steam determines the suction vapour water swelling elastomer of each perforation layer.
CN201711071035.4A 2017-11-03 2017-11-03 A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method and system Pending CN107939379A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711071035.4A CN107939379A (en) 2017-11-03 2017-11-03 A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711071035.4A CN107939379A (en) 2017-11-03 2017-11-03 A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method and system

Publications (1)

Publication Number Publication Date
CN107939379A true CN107939379A (en) 2018-04-20

Family

ID=61933215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711071035.4A Pending CN107939379A (en) 2017-11-03 2017-11-03 A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method and system

Country Status (1)

Country Link
CN (1) CN107939379A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825178A (en) * 2018-06-01 2018-11-16 中国石油天然气股份有限公司 Perforating methods and device
CN112836343A (en) * 2021-01-06 2021-05-25 中国石油天然气股份有限公司 Oil reservoir exploitation condition evaluation method and device for heavy oil steam injection well

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4409825A (en) * 1981-07-06 1983-10-18 Conoco Inc. Down hole steam quality measurement
CN87108005A (en) * 1986-11-26 1988-08-03 切夫尔昂研究公司 Determine the method for steam injection section
US4817713A (en) * 1987-08-19 1989-04-04 Chevron Research Company Steam injection profiling
US5138876A (en) * 1990-08-27 1992-08-18 Shell Oil Company Method and apparatus for measuring steam profiles in steam injection wells
CN2269463Y (en) * 1996-06-07 1997-12-03 辽河石油勘探局钻采工艺研究院 Four parameter testing instrument for high temperature and high pressure
CN2742136Y (en) * 2004-06-02 2005-11-23 中国石油天然气股份有限公司 High temperature gas injection well five parameter gas entry profile combined logging instrument
CN102322254A (en) * 2011-06-01 2012-01-18 陕西华晨石油科技有限公司 Downhole steam entry profile monitoring method
US20120160011A1 (en) * 2010-12-23 2012-06-28 Andrew Colin Whittaker Apparatus and Method for Generating Steam Quality Delivered to A Reservoir
CN203808979U (en) * 2014-03-10 2014-09-03 中国石油天然气股份有限公司 Downhole turbine flowmeter
EP3101222A1 (en) * 2015-06-05 2016-12-07 Geomax Energy Systems LLC - Oman Steam quality - measuring device
CN106761639A (en) * 2016-12-26 2017-05-31 中国石油天然气股份有限公司 Combustion in situ electric igniter and monitoring system
CN107101686A (en) * 2017-06-30 2017-08-29 荆州市明德科技有限公司 Thermal production well steam mass flow measurement target-type flow sensor and target type meter

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4409825A (en) * 1981-07-06 1983-10-18 Conoco Inc. Down hole steam quality measurement
CN87108005A (en) * 1986-11-26 1988-08-03 切夫尔昂研究公司 Determine the method for steam injection section
US4817713A (en) * 1987-08-19 1989-04-04 Chevron Research Company Steam injection profiling
US5138876A (en) * 1990-08-27 1992-08-18 Shell Oil Company Method and apparatus for measuring steam profiles in steam injection wells
CN2269463Y (en) * 1996-06-07 1997-12-03 辽河石油勘探局钻采工艺研究院 Four parameter testing instrument for high temperature and high pressure
CN2742136Y (en) * 2004-06-02 2005-11-23 中国石油天然气股份有限公司 High temperature gas injection well five parameter gas entry profile combined logging instrument
US20120160011A1 (en) * 2010-12-23 2012-06-28 Andrew Colin Whittaker Apparatus and Method for Generating Steam Quality Delivered to A Reservoir
CN102322254A (en) * 2011-06-01 2012-01-18 陕西华晨石油科技有限公司 Downhole steam entry profile monitoring method
CN203808979U (en) * 2014-03-10 2014-09-03 中国石油天然气股份有限公司 Downhole turbine flowmeter
EP3101222A1 (en) * 2015-06-05 2016-12-07 Geomax Energy Systems LLC - Oman Steam quality - measuring device
CN106761639A (en) * 2016-12-26 2017-05-31 中国石油天然气股份有限公司 Combustion in situ electric igniter and monitoring system
CN107101686A (en) * 2017-06-30 2017-08-29 荆州市明德科技有限公司 Thermal production well steam mass flow measurement target-type flow sensor and target type meter

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
凌建军: "《实用稠油热采工程》", 31 December 1995, 石油工业出版社 *
张庆: "注入剖面对参数组合测井及综合解释", 《油气田地面工程》 *
朱光等: "两参数仪器在稠油热采测井中的应用", 《石油仪器》 *
郭宏帅等: "关于吸汽剖面测试中油层吸汽量计算方法研究", 《中外能源》 *
霍广荣等: "《胜利油田稠油油藏热力开采技术》", 30 September 1999, 石油工业出版社 *
马明: "高温高压双参数测量仪的研究及其在稠油热采中的应用", 《油气井测试》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825178A (en) * 2018-06-01 2018-11-16 中国石油天然气股份有限公司 Perforating methods and device
CN108825178B (en) * 2018-06-01 2020-11-03 中国石油天然气股份有限公司 Perforation method and device
CN112836343A (en) * 2021-01-06 2021-05-25 中国石油天然气股份有限公司 Oil reservoir exploitation condition evaluation method and device for heavy oil steam injection well

Similar Documents

Publication Publication Date Title
CN108798634B (en) Single-hole-single-layer mean value well testing interpretation method for fracture-cavity reservoir
CN106599449B (en) Well test interpretation method for karst cave volume calculation
CN108920849B (en) Method for determining hole flow in stratum through fracture-cavity reservoir well testing
WO2016192077A1 (en) Method for establishing and solving numerical well-testing model of horizontal well for tight gas hydraulic fracturing
CN105893679B (en) Well Test Data Analysis Method is corrected in low yield horizontal well afterflow
CN104504611B (en) A kind of determining gas well whether the method for hydrops and its hydrops degree
CN103161435B (en) A kind of heavy crude heat extraction straight well Well Test Data Analysis Method
CN104834807A (en) Stress sensitive reservoir stratum relative permeability calculation method based on fractal theory
CN107939379A (en) A kind of thick oil heat production steam injection well inhales vapour water swelling elastomer detection method and system
WO2019242296A1 (en) Method for obtaining relationship model between water injection well and oil production well, and method for determining production rate and water injection amount
CN107831103B (en) A kind of precision assessment method of pressure pulse decaying gas permeability test device
CN110984973A (en) Determination method for single-well controlled reserve of fracture-cave carbonate gas reservoir
CN108518218B (en) Unconventional oil and gas reservoir multi-section fracturing horizontal well single well dynamic reserve determination method
CN106640021B (en) The calculation method and device of open flow parameter after pressure
CN105760645B (en) A kind of Well Test Data Analysis Method based on the extensive well testing of pressure and creation data well testing
CN104463345B (en) A kind of method and device for predicting stratum oil-water interface position
CN104237301A (en) In-situ thermal response testing method for layered rock and soil thermophysical properties
CN103161436B (en) A kind of heavy crude heat extraction horizontal well Well Test Data Analysis Method
CN105178930B (en) Steam thermal parameter computational methods and device in the steam injection pipeline of ground
CN106529184A (en) Method for calculating productivity of water-producing gas well of tilted water-bearing gas reservoir
CN106124349A (en) Determine the critical erosion rate of gas well, the method and device of flow
RU2014144308A (en) SYSTEM AND METHOD FOR ANALYSIS OF PRESSURE DATA IN A COLLECTOR
CN114427445A (en) Method and system for calculating infinite stratum dynamic capacity of fracture-cavity oil reservoir
CN105089591A (en) Method for determining annular gas-liquid interface of steam injection well
CN105626050B (en) The method and device of crustal stress is calculated using differential strain analysis method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180420