CN107553484B - Robot operation motion path planning method and system - Google Patents

Robot operation motion path planning method and system Download PDF

Info

Publication number
CN107553484B
CN107553484B CN201610499370.3A CN201610499370A CN107553484B CN 107553484 B CN107553484 B CN 107553484B CN 201610499370 A CN201610499370 A CN 201610499370A CN 107553484 B CN107553484 B CN 107553484B
Authority
CN
China
Prior art keywords
operated
point
time value
specific time
moving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610499370.3A
Other languages
Chinese (zh)
Other versions
CN107553484A (en
Inventor
冯春雨
李学威
何伟全
陈廷辉
张鹏
付杰
周楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Siasun Robot and Automation Co Ltd
Original Assignee
Shenyang Siasun Robot and Automation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Siasun Robot and Automation Co Ltd filed Critical Shenyang Siasun Robot and Automation Co Ltd
Priority to CN201610499370.3A priority Critical patent/CN107553484B/en
Publication of CN107553484A publication Critical patent/CN107553484A/en
Application granted granted Critical
Publication of CN107553484B publication Critical patent/CN107553484B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a robot operation motion path planning method and a system, a master controller calculates a moving time stamp of a first point to be operated according to an expected speed, and if the moving time stamp is larger than a first specific time value and smaller than a second specific time value, the controller controls a driver to drive a motor shaft to act; if the time value is less than the first specific time value, the controller controls the driver to maintain the original working state; if the time value is larger than the second specific time value, the controller controls the driver to interpolate N second to-be-operated points behind the first to-be-operated point to serve as the first to-be-operated point in the next path planning process, comparison of moving time stamps is carried out, whether interpolation of a new operation point is carried out or operation is carried out or the original state is maintained, so that a path curve of the next to-be-operated point is corrected again.

Description

Robot operation motion path planning method and system
Technical Field
The application relates to the technical field of industrial robots, in particular to a robot operation motion path planning method and system.
Background
At present, automation technology is rapidly developed, in the field, a robot system is an automatic operation system composed of a robot, peripheral equipment and tools, the robot, particularly an industrial robot, is generally a multi-axis mechanical arm, an axis of the robot is mainly composed of a gear box and a servo motor, the robot system also comprises a plurality of parts which move and rotate independently, and a robot control system is mainly composed of a main controller and a servo drive controller.
At present, leading robot control systems at home and abroad, particularly industrial robot control systems, are developing towards the directions of further improving control precision, having better safety, being more convenient for input and output, and the like. In order to achieve the purpose that the robot completes the designated operation, the robot needs to be established with the operation of how to move. The traditional mode is through the teaching box, under the teaching mode, control every joint motion, the continuous recording operation point. After recording a plurality of work points of the entire job, the type of movement between the work points, the movement speed, and the like may be set. The hand teaching technology developed at present is more and more popular, the principle is that a force sensor is added at the tail end of a robot, when the hand teaching function is started, a worker pulls the tail end of the robot by using a hand, the force sensor collects data and then sends the data to a robot controller, the controller calculates the direction and the size of a tension vector and drives the robot to move, and the tail end of the robot moves (including rotates) in the tension direction, namely follows the hand movement of the worker. In the process, the controller records the whole motion path, and after the teaching is finished, the path recorded by the controller is the teaching task.
In general, teaching tasks are executed in two ways: one is reproduction of the hand grip teaching, i.e. the controller issues as a job to be executed after increasing or decreasing the time interval between the points of the recording path. When the time interval is not changed, the operation executed by the robot is completely reproduced when the hand is taught, and after the interval is increased or decreased, the operation is slowly released or quickly released when the hand is taught; the other is that the path of the teaching task is not changed, but the speed in the whole path is re-planned, and the teaching is not referred to when the hand pulls fast and when the hand pulls slow. In some special application environments, such as welding, material filling and the like, the tail end of the robot needs to be at a constant speed to ensure the operation effect, and the hand-held teaching operation in the special application needs to be executed according to a second mode, namely, the speed in the whole path is re-planned.
In the second implementation, the type of movement and speed of movement between the work points needs to be re-planned. A simple way is to pick distinctive points in the path, such as inflection points, and use these points to plan a path. The method can discard a plurality of collected path points and also has an influence on the restoration of the path. The other mode is that a path curve is calculated by utilizing the collected path points, a new operation point is calculated according to the expected speed, and then the operation point is reversely solved into a joint value. The disadvantage of this method is that the amount of calculation is too large, which affects the work efficiency.
Disclosure of Invention
The invention provides a robot operation motion path planning method and system aiming at the problems that the existing operation point re-planning technology is complex to realize, the calculated amount is too large, the working efficiency is influenced and the like, and solves the problems that the existing operation point re-planning technology is complex to realize, the calculated amount is too large, the communication time is long, the working efficiency is influenced and the like.
In one aspect, the present invention provides a robot work motion path planning method, including:
the master controller calculates a moving timestamp of a first point to be operated;
if the moving timestamp is greater than a first specific time value and less than a second specific time value, the master controller controls a driver corresponding to the first to-be-operated point to drive a motor shaft to act; the second specific time value is greater than the first specific time value;
if the moving timestamp is smaller than the first specific time value, the master controller controls the driver corresponding to the first to-be-operated point to maintain the original working state;
if the moving timestamp is greater than the second specific time value, the master controller controls a driver corresponding to the first point to be operated to interpolate N second points to be operated after the first point to be operated so as to take the N second points to be operated as the first point to be operated in the next path planning process to re-plan the operation movement path of the robot, wherein N is an integer greater than zero.
As an alternative embodiment, the general controller calculates the moving time stamp of the first point-to-be-operated, and includes:
detecting through a sensor, and recording spatial position points of the M first points to be operated in a sampling teaching process; wherein M is an integer greater than zero;
calculating the position distance between two first points to be operated corresponding to the adjacent operation time;
obtaining a set expected speed in unit time;
obtaining the movement timestamp from the position separation and the desired velocity.
In another aspect, the present invention further provides a system for planning a motion path of a robot operation, including:
the master controller is used for calculating the moving timestamp of the first point to be operated;
the master controller is further configured to determine whether the moving timestamp is within a range from the first specific time value to the second specific time value; if the moving timestamp is greater than the first specific time value and less than the second specific time value, the master controller is further used for controlling a driver corresponding to the first to-be-operated point to drive a motor shaft to act;
the driver is controlled by the controller to drive a motor shaft to act;
if the moving timestamp is smaller than the first specific time value, the master controller is further used for controlling the driver corresponding to the first to-be-operated point to maintain the original working state;
the moving timestamp is greater than the second specific time value, and the controller is further configured to control the driver corresponding to the first point to be operated to interpolate N second points to be operated after the first point to be operated, so that the N second points to be operated are used as the first points to be operated in the next path planning process, and the operation motion path of the robot is re-planned;
and the driver is further configured to interpolate, by the controller, N second points to be operated after the first point to be operated according to a result that the moving timestamp determined by the controller is greater than the second specific time value, so as to take the N second points to be operated as the first point to be operated in a next path planning process, and to re-plan an operation movement path of the robot, where N is an integer greater than zero.
As an optional implementation manner, the system further includes a sensor, configured to perform detection and record spatial position points of the M first to-be-operated points in a sampling teaching process; wherein M is an integer greater than zero;
the master controller is further configured to calculate a position distance between two first to-be-operated points corresponding to adjacent operation time, obtain an expected speed in a set unit time, and obtain the moving timestamp according to the position distance and the expected speed.
The invention provides a robot operation motion path planning method and a system, wherein a master controller is used for calculating a moving timestamp of a first point to be operated; (ii) a If the moving timestamp is greater than a first specific time value and less than a second specific time value, controlling the driver to drive a motor shaft to act; the second specific time value is greater than the first specific time value; if the moving timestamp is smaller than the first specific time value, controlling the driver to maintain the original working state; if the moving timestamp is greater than the second specific time value, controlling the driver to interpolate N second points to be operated after the first point to be operated so as to use the N second points to be operated as the first points to be operated in the next path planning process to re-plan the operation movement path of the robot, comparing the calculated moving timestamp with the specific time, selecting to interpolate a new point to maintain the original state to re-correct the path curve of the next point to be operated, and having the advantages of simple steps and convenient calculation.
Drawings
Fig. 1 is a flowchart of a method for planning a motion path of a robot operation according to an embodiment of the present invention;
fig. 2 is a flowchart of another robot work movement path planning method according to an embodiment of the present invention;
fig. 3 is a structural diagram of a robot operation movement path planning system according to an embodiment of the present invention.
Detailed Description
The embodiments set forth below represent the necessary information to enable those skilled in the art to practice the invention and illustrate the best mode of practicing the invention. Upon reading the following description in light of the accompanying drawing figures, those skilled in the art will understand the concepts of the invention and will recognize applications of these concepts not particularly addressed herein. It should be understood that these concepts and applications fall within the scope of the disclosure and the accompanying claims. The present invention will be further described with reference to the following examples.
Referring to fig. 1, fig. 1 is a flowchart of a robot operation movement path planning method according to an embodiment of the present invention. As shown in fig. 1, the method for planning the motion path of the robot work provided by this embodiment includes:
110. the master controller calculates a moving timestamp t of a first point to be operated;
120. judging the sizes of the moving timestamp T and the first and second specific time values T1 and T2;
if the moving timestamp T is greater than the first specific time value T1 and less than the second specific time value T2, performing the following step 130;
130. controlling the driver to drive a motor shaft to act; the second specific time value T2 is greater than the first specific time value T1;
if the moving timestamp T is less than the first specific time value T1, performing the following step 140;
140. controlling a driver to maintain the original working state;
if the moving timestamp T is greater than a second specific time value T2, performing the following step 150;
150. the driver is controlled to interpolate N second points to be operated after the first point to be operated so as to take the N second points to be operated as the first points to be operated in the next path planning process and plan the operation movement path of the robot again; wherein N is an integer greater than zero. In this embodiment, the controller, while controlling the driver, issues a key value of the standby operation point so that the driver performs a key action according to the key value.
As an alternative implementation, referring to fig. 2, fig. 2 is a flowchart of another robot work motion path planning method provided in an embodiment of the present invention, and as shown in fig. 2, based on step 110 shown in fig. 1, the method further includes the following steps, that is, the step of calculating, by the overall controller, a moving time stamp t of the first point to be worked includes:
111. detecting through a sensor, and recording spatial position points of M first points to be operated in a sampling teaching process; wherein M is an integer greater than zero;
112. calculating the position distance between two first points to be operated corresponding to the adjacent operation time;
113. obtaining a set expected speed in unit time;
114. the movement time stamp t is obtained from the position separation and the desired velocity.
On the other hand, an embodiment of the present invention further provides a system for planning a motion path of a robot operation, please refer to fig. 3. Fig. 3 is a structural diagram of a robot operation movement path planning system according to an embodiment of the present invention. As shown in fig. 3, the robot working motion path planning system 100 provided by this embodiment includes an overall controller 310 and a driver 320, where the overall controller 310 is configured to calculate a moving time stamp t of a first point to be worked; the general controller 310 is configured to determine whether the moving timestamp T is within a range from a first specific time value T1 to a second specific time value T2; the overall controller 310 is further configured to determine whether the moving timestamp is within a range from the first specific time value to the second specific time value; if the moving timestamp is greater than the first specific time value and less than the second specific time value, the overall controller 310 is further configured to control the driver 320 corresponding to the first to-be-operated point to drive a motor shaft to act; the driver 320 is also used for driving a motor shaft to act if the moving time stamp T is greater than the first specific time value T1 and less than the second specific time value T2 according to the judgment of the overall controller 310; if the moving timestamp is less than the first specific time value, the general controller 310 is further configured to control the driver 320 corresponding to the first to-be-operated point to maintain an original operating state; the driver 320 is further configured to maintain the original working state according to the result that the moving timestamp T judged by the overall controller 310 is smaller than the first specific time value T1; if the moving timestamp is greater than the second specific time value, the overall controller 310 is further configured to control the driver 320 corresponding to the first point to be operated to interpolate N second points to be operated after the first point to be operated, so as to use the N second points to be operated as the first point to be operated in the next path planning process, so as to re-plan the operation motion path of the robot; the driver 320 is further configured to interpolate N second points to be operated after the first point to be operated according to the result that the moving timestamp T determined by the overall controller 310 is greater than the second specific time value T2, so as to use the N second points to be operated as the first points to be operated in the next path planning process, so as to re-plan the operation movement path of the robot, where N is an integer greater than zero.
As an optional implementation manner, the robot working motion path planning system 100 provided in this implementation manner further includes a sensor, configured to detect, and record spatial position points of the M first points to be worked in the sampling teaching process; wherein M is an integer greater than zero; the general controller 310 is further configured to calculate a position distance between two first to-be-operated points corresponding to adjacent operation times, obtain a desired speed in a set unit time, and obtain the moving timestamp t according to the position distance and the desired speed.
In summary, in the method and system for planning the operation movement path of the robot according to the embodiments of the present invention, the master controller calculates the moving timestamp of the first point to be operated; (ii) a If the moving timestamp is greater than a first specific time value and less than a second specific time value, controlling the driver to drive a motor shaft to act; the second specific time value is greater than the first specific time value; if the moving timestamp is smaller than the first specific time value, controlling the driver to maintain the original working state; if the moving timestamp is greater than the second specific time value, controlling the driver to interpolate N second points to be operated after the first point to be operated so as to use the N second points to be operated as the first points to be operated in the next path planning process to re-plan the operation movement path of the robot, comparing the calculated moving timestamp with the specific time, selecting to interpolate a new point to maintain the original state to re-correct the path curve of the next point to be operated, and having the advantages of simple steps and convenient calculation.
It should be understood that the above examples are only for clearly illustrating the present invention and are not intended to limit the embodiments of the present invention. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And such obvious variations or modifications which fall within the spirit of the invention are intended to be covered by the scope of the present invention.

Claims (4)

1. A robot work motion path planning method is characterized by comprising the following steps:
the master controller calculates a moving timestamp of a first point to be operated;
if the moving timestamp is greater than a first specific time value and less than a second specific time value, the master controller controls a driver corresponding to the first to-be-operated point to drive a motor shaft to act; the second specific time value is greater than the first specific time value;
if the moving timestamp is smaller than the first specific time value, the master controller controls the driver corresponding to the first to-be-operated point to maintain the original working state;
if the moving timestamp is greater than the second specific time value, the master controller controls a driver corresponding to the first point to be operated to interpolate N second points to be operated after the first point to be operated so as to take the N second points to be operated as the first point to be operated in the next path planning process to re-plan the operation movement path of the robot, wherein N is an integer greater than zero.
2. The method for planning a movement path for robot work according to claim 1, wherein the calculating the moving time stamp of the first point to be worked by the general controller comprises:
detecting through a sensor, and recording spatial position points of the M first points to be operated in a sampling teaching process; wherein M is an integer greater than zero;
calculating the position distance between two first points to be operated corresponding to the adjacent operation time;
obtaining a set expected speed in unit time;
obtaining the movement timestamp from the position separation and the desired velocity.
3. A robot work motion path planning system, comprising:
the master controller is used for calculating the moving timestamp of the first point to be operated;
the master controller is further used for judging whether the moving timestamp is in a range from a first specific time value to a second specific time value; if the moving timestamp is greater than the first specific time value and less than the second specific time value, the master controller is further configured to control a driver corresponding to the first to-be-operated point to drive a motor shaft to act;
the driver is controlled by the controller to drive a motor shaft to act;
if the moving timestamp is smaller than the first specific time value, the master controller is further used for controlling the driver corresponding to the first to-be-operated point to maintain the original working state;
if the moving timestamp is greater than the second specific time value, the general controller is further configured to control the driver corresponding to the first point to be operated to interpolate N second points to be operated after the first point to be operated, so that the N second points to be operated are used as the first point to be operated in the next path planning process, and the operation motion path of the robot is re-planned;
and the driver is further configured to interpolate, by the controller, N second points to be operated after the first point to be operated according to a result that the moving timestamp determined by the controller is greater than the second specific time value, so as to take the N second points to be operated as the first point to be operated in a next path planning process, and to re-plan an operation movement path of the robot, where N is an integer greater than zero.
4. The robot work motion path planning system according to claim 3, further comprising a sensor for detecting and recording spatial position points of the M first points to be worked during the sampling teaching; wherein M is an integer greater than zero;
the master controller is further configured to calculate a position distance between two first to-be-operated points corresponding to adjacent operation time, obtain an expected speed in a set unit time, and obtain the moving timestamp according to the position distance and the expected speed.
CN201610499370.3A 2016-06-30 2016-06-30 Robot operation motion path planning method and system Active CN107553484B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610499370.3A CN107553484B (en) 2016-06-30 2016-06-30 Robot operation motion path planning method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610499370.3A CN107553484B (en) 2016-06-30 2016-06-30 Robot operation motion path planning method and system

Publications (2)

Publication Number Publication Date
CN107553484A CN107553484A (en) 2018-01-09
CN107553484B true CN107553484B (en) 2020-07-07

Family

ID=60968569

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610499370.3A Active CN107553484B (en) 2016-06-30 2016-06-30 Robot operation motion path planning method and system

Country Status (1)

Country Link
CN (1) CN107553484B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112556706B (en) * 2019-09-10 2023-12-26 菜鸟智能物流控股有限公司 Navigation method, device, equipment and machine-readable medium
CN110879571B (en) * 2019-12-16 2021-03-02 华南理工大学广州学院 Method for obtaining circular arc walking line segment of writing robot based on circular arc interpolation
CN111331596B (en) * 2020-01-22 2021-05-18 深圳国信泰富科技有限公司 Automatic track correction method and system for robot
CN111890154B (en) * 2020-07-31 2021-08-31 广东博智林机器人有限公司 Polishing method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FI83175C (en) * 1989-09-12 1991-06-10 Aitec Oy Procedure for path control of a robotic cell
US6182008B1 (en) * 1999-06-25 2001-01-30 Microsoft Corporation Ordering destinations along a route using a shortest line approximation
CN101224576B (en) * 2008-01-25 2010-09-29 北京邮电大学 Teaching track optimized controlling method of magnetic-controlled spraying robot
CN103778843B (en) * 2012-10-25 2017-02-15 西安航天精密机电研究所 Industrial robot demonstration and reappearance method
CN204390096U (en) * 2014-12-22 2015-06-10 库卡罗伯特有限公司 Track stops the executor group of at least one executor conditionally
CN104772754B (en) * 2015-03-26 2016-05-11 北京欣奕华科技有限公司 A kind of robot teaching device and teaching method
CN104951918A (en) * 2015-06-11 2015-09-30 上海德马物流技术有限公司 Time window path planning method
CN105619409B (en) * 2016-02-24 2017-07-14 佛山市科莱机器人有限公司 Manual teaching robot's action optimized treatment method

Also Published As

Publication number Publication date
CN107553484A (en) 2018-01-09

Similar Documents

Publication Publication Date Title
CN107553484B (en) Robot operation motion path planning method and system
JP6333795B2 (en) Robot system with simplified teaching and learning performance improvement function by learning
CN108422420B (en) Robot system having learning control function and learning control method
US9701014B2 (en) Robot control device for preventing misjudgment by collision judging part
CN103147577B (en) Control method, equipment, system and construction machinery for multi-joint mechanical arm support
JP5311294B2 (en) Robot contact position detector
JP4056542B2 (en) Offline teaching device for robots
US20090125146A1 (en) Method of and Apparatus for Automated Path Learning
JP2016013613A (en) Robot control method, robot device, program, recording medium, and method for manufacturing assembled component
JP5875714B2 (en) Servo control device and servo control method
CN105122160A (en) Numerical control apparatus
CN109551485B (en) Motion control method, device and system and storage medium
US11059142B2 (en) Controller, machine learning device, and system
US9604362B2 (en) Method and apparatus for failure handling of a robot
JP2006215807A (en) Robot control device and control method
CN107671838B (en) Robot teaching recording system, teaching process steps and algorithm flow thereof
CN105479431A (en) Inertial navigation type robot demonstration equipment
US20210039256A1 (en) Robot control method
TWI554856B (en) Apparatus and method for transforming nc programs
JP6476635B2 (en) Robot control apparatus and control method
JP6088601B2 (en) Robot controller that suppresses tool tip deflection in robot with traveling axis
CN112847370A (en) Mobile robot path planning method based on deep learning
CN107825431B (en) Workpiece deburring system and method based on intelligent robot self-feedback speed control
JP7222427B2 (en) Control system, control device and control method
WO2018173165A1 (en) Teaching program, teaching method, and robot system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant