CN105887900A - Prestress light and environment-friendly cofferdam - Google Patents

Prestress light and environment-friendly cofferdam Download PDF

Info

Publication number
CN105887900A
CN105887900A CN201510043421.7A CN201510043421A CN105887900A CN 105887900 A CN105887900 A CN 105887900A CN 201510043421 A CN201510043421 A CN 201510043421A CN 105887900 A CN105887900 A CN 105887900A
Authority
CN
China
Prior art keywords
band
annulus column
water
bar
dash
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510043421.7A
Other languages
Chinese (zh)
Inventor
邬志达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510043421.7A priority Critical patent/CN105887900A/en
Publication of CN105887900A publication Critical patent/CN105887900A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a prestress light and environment-friendly cofferdam which can be flexibly combined and is convenient to mount and demount, environment-friendly, safe, economical and practical. According to the cofferdam, two rows of stand columns with rings are connected through straight bars, an auxiliary bridge panel is laid to construct a temporary auxiliary bridge, the water receiving sides of the stand columns with the rings are connected through a telescopic arch rod to form an arch structure, a prestress steel wire rope penetrates the rings of the stand columns with the rings, and tensioning is conducted through a tensioner which is installed on a bank. The telescopic arch rod is provided with an installation ring, an installation hole is formed in the middle of each stand column, and installation rods which are connected with a water blocking curtain can be inserted into the installation holes from top to bottom to install the water blocking curtain. A vertical part of the water blocking curtain is provided with an inflation pipe which can block water after being inflated, dropping pieces and pull ropes are arranged on the other side of the water blocking curtain, the other side of the water blocking curtain is flatly laid at the bottom of a river bed for preventing seepage, and on a water seepage river bed such as gravel, the lower portion of a flatly-laid part of the water blocking curtain is additionally provided with a grout tube for conducting grouting seepage on the river bed.

Description

Prestressed light environmental protection cofferdam
Technical field
The present invention relates to a kind of temporary water retaining cofferdam in river course, water areas project construction, especially with pre-stress stretching device, post, bar combination knot Structure and inflation waterproof composite fabric make water-retaining cofferdam the prestressed light environmental protection cofferdam of band grout pipe antiseepage.
Background technology
At present, in relating to river course, water areas project construction, the traditional material structure such as the commonly used timber of temporary water retaining cofferdam, mound, geotextiles Build, cofferdam construction by ambient conditions affected big, long in time limit, safety standard is low, major project completion after, to Temporary Cofferdam remove cleaning not in place, Discarded object affects river course, water environment.
Summary of the invention:
In order to overcome tradition timber, mound construct temporary water retaining cofferdam by external world's execution conditions affected big, long in time limit, safety standard is low, Temporary Cofferdam Building, tear trouble open, the discarded object that cofferdam is left over affects the shortcoming of water environment, and the present invention provides a kind of prestressed light environmental protection cofferdam, this cofferdam install and Removing convenient and swift, cofferdam can be according to river course, status of the water area by band annulus column, prestress rope, tensioner, scalable arch bar, installation Bar, straight-bar, dash curtain, grout pipe free splicing combine, by execution conditions affected little, the duration is short, safe and reliable, can be widely used in needs In the various Water-related Project construction of Temporary Cofferdam dash, each parts in this prestressed light environmental protection cofferdam can be reused with independent assortment, and cofferdam is torn open Discarded object is not produced, very environmental protection and economical and practical after removing.
The present invention solves technical problem and be the technical scheme is that two rows put on the band annulus column lower end of prestress rope and squeeze into the soil in riverbed In, band annulus column upstream face side connects composition arch structure by scalable arch bar, and the scalable scalable anchor ear of arch bar band, mounting ring, by can Flexible anchor ear, scalable arch bar is connected fixing with band annulus column, and the mounting ring of scalable arch bar may be inserted into mounting rod, is used for installing fixing dash Curtain, the band annulus column side that meets water is opened groove, be may be inserted into the mounting rod connected with dash curtain, wear prestressing force in the annulus of band annulus column Steel wire rope, the two ends of prestress rope are connected with the tensioner being fixed on the bank, provide pulling force for whole cofferdam, prevent cofferdam after tensioner tension Sliding and topple, two rows carry annulus column straight-bar reinforcement by connection, above after bed board as make-shift bridge, on-the-spot needs can be met.Band annulus stands Post and bar combination can repeat to extend, and two ends, cofferdam are fixed with riverbank, and the two ends of prestress rope are connected with the tensioner being fixed on the bank, dash When curtain is installed, a part erects dash, and another part is laid in antiseepage at the bottom of riverbed, is laid in below the part dash curtain at the bottom of riverbed and can install additional Grout pipe, the one of dash curtain setting dash part wears installation set, and another wears gas tube, and gas tube is by expansion after the valve cock inflation on top Can support the standing portion of dash curtain, the standing portion of inflation rear water curtain becomes one can be with the elastomer of stress dash, and dash curtain leads to Crossing installation set to be connected with mounting rod, mounting rod is fixed on band annulus column and scalable arch bar, dash curtain and mounting rod, scalable arch bar, band Annulus column, prestress rope, tensioner, straight-bar composition overall structure, is delivered to water pressure at the fixing end on riverbed and riverbank.Deeper Waters, band annulus column, mounting rod can be socketed increase height, fall part and guarantee that dash curtain is laid on riverbed part and can sink to river bed, then pass through Stay cord is laid on riverbed part dash curtain and pulls open tiling antiseepage in river bed, and in the case of riverbed is grit isotonic water riverbed, dash curtain is laid In the middle of riverbed part, install a grout pipe additional, before drawing water, first pass through grout pipe and carry out the part riverbed of the dash curtain that tiles locally being in the milk Consolidation antiseepage.
The invention has the beneficial effects as follows: the prestressed light environmental protection cofferdam force-bearing situation using prestressing force arch structure is good, component is light, band annulus column, Prestress rope, tensioner, scalable arch bar, straight-bar, mounting rod, dash curtain, grout pipe can be manufactured according to specification standardization, arrive Behind scene, combination meets construction requirement, cofferdam installation, dismounting, convenient transportation as required, will not produce discarded object, and all components are reusable, Very environmental protection and economical and practical.
Accompanying drawing explanation
The present invention is further described with embodiment below in conjunction with the accompanying drawings.
Fig. 1 is the planar configuration schematic diagram of the present invention.
Fig. 2 is the facade organigram of the present invention.
Fig. 3 is scalable arch bar structure chart.
Fig. 4 is the floor map of dash curtain.
Fig. 5 is the structure chart of mounting rod.
Fig. 6 is the sectional view of band annulus column.
Fig. 7 is the top view of Fig. 6.
1. band annulus column in figure, 2 band annulus column, 3. band annulus column, 4. band annulus columns, the most scalable arch bar, 6. straight-bar are the most straight Bar, 8. straight-bar, 9. straight-bar, 10. dash curtain, 11. mounting rods, 12. mounting rods, 13. mounting rods, 14. mounting rods, 15. mounting rods, 16. Pendant part, 17. pendant parts, 18. pendant parts, 19. stay cords, 20. stay cords, 21. stay cords, 22. suspension bridge panels, 23. tensioners, 24. prestress ropes, 25. prestress ropes, 26. prestress ropes, 27. prestress ropes, 28. tensioners, 29. grout pipes.
Detailed description of the invention
In FIG, prestress rope (24), prestress rope (25), prestress rope (26), prestress rope (27) are worn Band annulus column (1), band annulus column (2), band annulus column (3), band annulus column (4) annulus in, band annulus column (1), Band annulus column (2), band annulus column (3), band annulus column (4) lower end squeeze into riverbed with fixed, straight-bar (6), straight-bar (7), straight-bar (8), Straight-bar (9) is connected with band annulus column (1), band annulus column (2), band annulus column (3), band annulus column (4) respectively, lays above Suspension bridge panel (22), scalable arch bar (5) is arranged on band annulus column (1), band annulus column (3) outside, mounting rod (11), mounting rod (12), mounting rod (13), mounting rod (14), mounting rod (15) be connected with the installation set of the relevant position of dash curtain (10) the most respectively, Be inserted in band annulus column (1), band annulus column (2), installing hole in the middle of scalable arch bar (5) fixing, pendant part (16), pendant part (17), Pendant part (18) and stay cord (19), stay cord (20) stay cord (21) are contained in the outer side edges of dash curtain (10), on the riverbed of grit isotonic water, Below dash curtain (10), install grout pipe (29) additional, by grout pipe (29), riverbed carried out watertight grouting, tensioner (23), stretch-draw Device (28) is fixed on the bank, with prestress rope (24), prestress rope (25), prestress rope (26), prestress rope (27) connect.
In fig. 2, band annulus column (1), band annulus column (2) are connected with straight-bar (6), and suspension bridge panel (22) is laid on straight-bar (6) On, mounting rod (14) is inserted in band annulus column (1) installing hole, and the installation set of dash curtain (10) and mounting rod (14) are even pressed, and fall part (17), stay cord (20) be connected with the outside of dash curtain (10), grout pipe (29) is contained in dash curtain (10) below.
When cofferdam is installed, first prestress rope (24), prestress rope (25), prestress rope (26), prestress rope (27) It is through in the annulus of band annulus column (1), band annulus column (2), band annulus column (3), band annulus column (4), then band annulus column (1), band annulus column (2), band annulus column (3), band annulus column (4) lower end squeeze into riverbed, scalable arch bar (5), straight-bar (6), Straight-bar (7), straight-bar (8), straight-bar (9) are installed and are fixed to band annulus column (1), band annulus column (2), band annulus column (3), band circle The correct position of ring column (4), is laid on suspension bridge panel (22) on straight-bar (6), straight-bar (9), in grit riverbed, grout pipe (29) First being fixed on dash curtain (10), tiling is to riverbed the most together, dash curtain (10) respectively with mounting rod (11), mounting rod (12), Mounting rod (13), mounting rod (14), mounting rod (15), pendant part (16), pendant part (17), pendant part (18), stay cord (19), stay cord (20) Stay cord (21) connects, then mounting rod (11), mounting rod (12), mounting rod (13), mounting rod (14), mounting rod (15) respectively Insert in the mounting ring of band annulus column (1), installing hole in the middle of band annulus column (2) and scalable arch bar (5) fixing, then by pendant part (16), Pendant part (17), pendant part (18) and stay cord (19), stay cord (20), stay cord (21) are being paved the side of band dash curtain (10) at the bottom of riverbed Antiseepage, on the riverbed of grit isotonic water, dash curtain (10) installs grout pipe (29) additional, by adding the grout pipe (29) loaded onto to infiltration Riverbed carries out cement-grouting consolidation antiseepage.Tensioner (23), tensioner (28) fix on the coast, prestress rope (24), compressor wire Rope (25), prestress rope (26), prestress rope (27) are connected with tensioner (23), tensioner (28), open tension, finally Inflated to the gas tube on dash curtain (10) by the valve cock on dash curtain (10) top.During cofferdam demolition, first open dash curtain (10) Valve cock the air of dash curtain (10) gas tube is progressively bled off, and reduce dash curtain (10) top, water gradually put into construction side, When after the level of both sides, prestress rope (24), prestress rope (25), prestress rope (26), prestress rope (27) Unclamp with tensioner (23), tensioner (28), extract successively mounting rod (11), mounting rod (12), mounting rod (13), mounting rod (14), Mounting rod (15), takes out dash curtain (10) from water, finally removes scalable arch bar (5), suspension bridge panel (22), straight-bar (6), straight Bar (7), straight-bar (8), straight-bar (9) also extract band annulus column (1), band annulus column (2), band annulus column (3) band annulus column (4), Each parts split after arranging, the most reusable.

Claims (1)

1. a prestressed light environmental protection cofferdam, two rows carry annulus column parallel, connect with straight-bar, as make-shift bridge after slab, upstream face side Connect with scalable arch bar outside band annulus column, form arch structure, the annulus of band annulus column wears prestress rope, and be fixed on the bank Tensioner connect, dash curtain band gas tube, inflation rear water, it is characterized in that: prestressed light environmental protection cofferdam by band annulus column, in advance should Power steel wire rope, tensioner, scalable arch bar, straight-bar, suspension bridge panel, dash curtain, mounting rod, pendant part, stay cord, grout pipe are constituted, and can stretch The scalable anchor ear of contracting arch bar band, mounting ring, scalable arch bar two ends are connected with band annulus column by scalable anchor ear, and prestress rope is through band In the annulus of annulus column, prestress rope two ends are connected with tensioner, and mounting rod inserts the peace in the middle of band annulus column after being connected with dash curtain Fixing in the mounting ring of dress hole and scalable arch bar, band annulus column, the upper and lower end of mounting rod can be socketed at the depth of water and increase, dash curtain one Part erects dash, another part tiling riverbed antiseepage, and dash curtain standing portion one wears installation set, and another wears gas tube, on dash curtain Installing set to be connected with mounting rod, dash curtain is laid in installing at the bottom of river bed water and falls part, stay cord, and grout pipe is arranged on dash curtain and is laid in water Below bottom point.
CN201510043421.7A 2015-01-25 2015-01-25 Prestress light and environment-friendly cofferdam Pending CN105887900A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510043421.7A CN105887900A (en) 2015-01-25 2015-01-25 Prestress light and environment-friendly cofferdam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510043421.7A CN105887900A (en) 2015-01-25 2015-01-25 Prestress light and environment-friendly cofferdam

Publications (1)

Publication Number Publication Date
CN105887900A true CN105887900A (en) 2016-08-24

Family

ID=57002031

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510043421.7A Pending CN105887900A (en) 2015-01-25 2015-01-25 Prestress light and environment-friendly cofferdam

Country Status (1)

Country Link
CN (1) CN105887900A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914453A (en) * 2019-03-18 2019-06-21 中国电建集团华东勘测设计研究院有限公司 A kind of earth rock cofferdam Foundation Anti-seepage curtain and its manufacturing method
CN115162384A (en) * 2022-07-21 2022-10-11 河南省水利第一工程局 Cofferdam structure for pump station forebay water-stop construction and water-stop construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020110424A1 (en) * 2001-02-15 2002-08-15 Page Harry B. Flood protection device, system and mothed therefor
CN2551682Y (en) * 2002-06-12 2003-05-21 李文华 Air bag type water stop dyke-repairing guard fence
US20050058509A1 (en) * 2003-09-15 2005-03-17 Dov Steinberg Floating modular breakwater
CN2848942Y (en) * 2005-06-10 2006-12-20 上海勘测设计研究院 Water guarding cofferdam structure
CN101333818A (en) * 2008-07-17 2008-12-31 北京翔鲲水务建设有限公司 Pile film cofferdam and its construction method
CN203960884U (en) * 2014-06-28 2014-11-26 蒋伟宇 Assembled environmental inflation arch cofferdam

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020110424A1 (en) * 2001-02-15 2002-08-15 Page Harry B. Flood protection device, system and mothed therefor
CN2551682Y (en) * 2002-06-12 2003-05-21 李文华 Air bag type water stop dyke-repairing guard fence
US20050058509A1 (en) * 2003-09-15 2005-03-17 Dov Steinberg Floating modular breakwater
CN2848942Y (en) * 2005-06-10 2006-12-20 上海勘测设计研究院 Water guarding cofferdam structure
CN101333818A (en) * 2008-07-17 2008-12-31 北京翔鲲水务建设有限公司 Pile film cofferdam and its construction method
CN203960884U (en) * 2014-06-28 2014-11-26 蒋伟宇 Assembled environmental inflation arch cofferdam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914453A (en) * 2019-03-18 2019-06-21 中国电建集团华东勘测设计研究院有限公司 A kind of earth rock cofferdam Foundation Anti-seepage curtain and its manufacturing method
CN115162384A (en) * 2022-07-21 2022-10-11 河南省水利第一工程局 Cofferdam structure for pump station forebay water-stop construction and water-stop construction method

Similar Documents

Publication Publication Date Title
CN103741604B (en) Totally-prefabricated assembling type reinforced concrete bridge splicing structure and attaching method thereof
CN203320725U (en) Self-resetting energy consumption support
KR101027800B1 (en) Prefabricated revet construction and method for constructing the same
KR101364805B1 (en) Underground structure construction method with unit wall block
CN105569059A (en) Passive protective net and installation method thereof
KR101353882B1 (en) Method of reinforcement and construction of pillar of neighboring tunnel
CN102966052A (en) Protective method and structure for preventing rockfall dangers at high and steep slope of mountain road
CN105887900A (en) Prestress light and environment-friendly cofferdam
CN206035505U (en) Stride across hangar tunnel structure of debris flow gully
KR20140080472A (en) Method of construction of line type supports at large section tunnel having low flat rate
CN104452775B (en) Pre-loaded support struts and construction method for foundation ditch
ES2394569B1 (en) METHOD FOR THE CONSTRUCTION OF LOWER STEPS AND LOWER STEP BUILT WITH SUCH METHOD
JP2020070705A (en) Method for constructing lightweight fill retaining wall structure
CN106194213B (en) A kind of shed hole structure and construction method across debris flow gully
CN101806040A (en) Underpinning device and method for bridge and building
CN103572761B (en) A kind of method of utilizing Brooker protection network to protect while closing on both wired constructions
KR101326574B1 (en) Foundation structure for pillar
KR101194043B1 (en) Prefabricated Revet Construction and Method for Constructing the same
CN205117354U (en) Reinforcing bar grid crowd with encircle foot strengthens device temporarily
JP4804561B2 (en) Leg frame fixing method in which anchoring member is fixed to ground slope with ground anchor
CN109958461B (en) Coal mine fault water-penetration-preventing structure
JP2011153505A (en) Slope frame fixing method for promoting ground anchor effect by setting expansion and contraction zone on slope frame bottom and adjusting sheath length
CN105297751A (en) Combined type environment-friendly inflatable arch cofferdam
CN204435397U (en) Prestressed light environmental protection cofferdam
CN107587476B (en) Wave-blocking wall with prefabricated reverse arc olecranon structure and design and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160824

WD01 Invention patent application deemed withdrawn after publication
DD01 Delivery of document by public notice

Addressee: Jiang Weiyu

Document name: Notification that Application Deemed to be Withdrawn

DD01 Delivery of document by public notice