CN105867185B - A kind of remote energy-saving method for controller switching equipment - Google Patents

A kind of remote energy-saving method for controller switching equipment Download PDF

Info

Publication number
CN105867185B
CN105867185B CN201610217217.7A CN201610217217A CN105867185B CN 105867185 B CN105867185 B CN 105867185B CN 201610217217 A CN201610217217 A CN 201610217217A CN 105867185 B CN105867185 B CN 105867185B
Authority
CN
China
Prior art keywords
controller switching
switching equipment
power consumption
consumption data
electric period
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610217217.7A
Other languages
Chinese (zh)
Other versions
CN105867185A (en
Inventor
卢海权
程俊航
张勇征
韦俊钢
苏海智
马志进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bright Power Construction Co Ltd Of Dongyang City
State Grid Corp of China SGCC
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Dongyang Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Bright Power Construction Co Ltd Of Dongyang City
State Grid Corp of China SGCC
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Dongyang Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bright Power Construction Co Ltd Of Dongyang City, State Grid Corp of China SGCC, Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd, Dongyang Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Bright Power Construction Co Ltd Of Dongyang City
Priority to CN201610217217.7A priority Critical patent/CN105867185B/en
Publication of CN105867185A publication Critical patent/CN105867185A/en
Application granted granted Critical
Publication of CN105867185B publication Critical patent/CN105867185B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers

Abstract

The invention proposes a kind of remote energy-saving methods for controller switching equipment, belong to field of power system.Including obtaining the controller switching equipment in n-quadrant, power consumption data is sent to area monitoring host.Area monitoring host chooses the highest controller switching equipment of power consumption, and the power consumption data of controller switching equipment is sent to control host, the controller switching equipment in excessive power consumption state is determined in order to control host, so that economize on electricity treasured of the activation on excessive power consumption state controller switching equipment carries out energy conservation.By being communicated with control host, it chooses the controller switching equipment in excessive power consumption and economize on electricity processing is carried out to it, to carry out complete energy consumption monitoring and administration of energy conservation to controller switching equipment, energy consumption monitoring IT application in management level is improved, the effect of energy monitoring data is preferably played.

Description

A kind of remote energy-saving method for controller switching equipment
Technical field
The invention belongs to field of power system, in particular to a kind of remote energy-saving method for controller switching equipment.
Background technique
With the development of economy and society, this idea of development of energy-saving and emission-reduction is gradually rooted in the hearts of the people.In the support of government Under guidance, reducing equipment energy consumption becomes the focus of work of each field staff.Development of the electric system as national economy Pillar should more be walked in the work for reducing equipment energy consumption in epoch forward position.
In the prior art, the loss on power system device is related to electric line loss and transformer loss, in order to These two aspects reduces energy consumption, and top priority is to accomplish good energy consumption monitoring, targetedly to implement to save according to monitoring result It can measure.
In current electric power enterprise, energy consumption monitoring theory is also in the stage to relatively lag behind, mainly energy consumption monitoring pipe It manages that the level of IT application is not high, causes what energy monitoring data were unable to fully to play a role.
Summary of the invention
In order to solve problems in the prior art, on the one hand, the present invention provides a kind of remote energy-savings for controller switching equipment Method is based on controller switching equipment end, the remote energy-saving method for controller switching equipment, comprising:
The controller switching equipment in n-quadrant is obtained by data acquisition terminal and counts the power consumption data in the electric period in N, by institute State the area monitoring host that power consumption data is sent to the n-quadrant;
The area monitoring host, which is obtained, counts the power consumption in the electric period first by controller switching equipments whole in the n-quadrant The n-quadrant power consumption data that data are constituted chooses the distribution of the highest preset quantity of power consumption from the power consumption data of the n-quadrant The target controller switching equipment is counted the power consumption data in the electric period described first and is sent to by equipment as target controller switching equipment Control host;
Wherein, N is the natural number greater than zero.
Optionally, enable the data acquisition terminal by comprising the n-quadrant in the target controller switching equipment described Second power consumption data for counting the electric period is sent to the control host.
Optionally, the control host is high-performance computer.
Optionally, the controller switching equipment is to be equipped with the precious power distribution cabinet of the economize on electricity.
Optionally, the power consumption data includes the rated power of the controller switching equipment, actual power, working time.
On the other hand, the invention also provides a kind of remote energy-saving methods for controller switching equipment, are based on control host side, The remote energy-saving method for controller switching equipment, comprising:
The power consumption data in the electric period is counted first to target controller switching equipment to check, and is determined and is in excessive power consumption state Target controller switching equipment;
After the completion of verification, it is in excessive to described in the periodic intervals that the first meter electric period counts the electric period with second The target controller switching equipment of power consumption state sends the precious activation instruction that economizes on electricity.
Optionally, the target device is obtained from data acquisition terminal count the power consumption data in the electric period in majority second;
The target controller switching equipment is counted the power consumption data in the electric period described second to exist with the target current consuming apparatus Described first power consumption data counted in the electric period compares, and determines economize on electricity of the target controller switching equipment after activation economize on electricity is precious Situation.
Optionally, according to the economize on electricity situation, still it is if the target controller switching equipment is counted in the electric period described second The target controller switching equipment is then added in maintenance list by the highest controller switching equipment of power consumption.
Optionally, the controller switching equipment is to be equipped with the precious power distribution cabinet of the economize on electricity.
Optionally, the power consumption data includes the rated power of the controller switching equipment, actual power, working time.
Technical solution provided by the invention has the benefit that
By being communicated with control host, controller switching equipment of the selection in excessive power consumption simultaneously carries out economize on electricity processing to it, To carry out complete energy consumption monitoring and administration of energy conservation to controller switching equipment, energy consumption monitoring IT application in management level is improved, more The effect of good performance energy monitoring data.
Detailed description of the invention
It, below will be to attached drawing needed in embodiment description in order to illustrate more clearly of technical solution of the present invention It is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, general for this field For logical technical staff, without creative efforts, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is a kind of flow diagram of remote energy-saving method for controller switching equipment provided by the invention;
Fig. 2 is a kind of local flow diagram one of remote energy-saving method for controller switching equipment provided by the invention;
Fig. 3 is a kind of local flow diagram two of remote energy-saving method for controller switching equipment provided by the invention.
Specific embodiment
To keep structure and advantage of the invention clearer, structure of the invention is made further below in conjunction with attached drawing Description.
Embodiment one
The present invention provides a kind of remote energy-saving method for controller switching equipment, this power-economizing method by wireless network by being connected The controller switching equipment and control host connect is completed jointly, will be by controller switching equipment end and control host infra for being easy to understand It holds unaided step to be combined to be described.As shown in Figure 1, a kind of remote energy-saving method for controller switching equipment, packet It includes:
11, the controller switching equipment in n-quadrant is obtained by data acquisition terminal and counts the power consumption data in the electric period first, Power consumption data is sent to the area monitoring host of n-quadrant.
12, area monitoring host, which is obtained, counts the power consumption data in the electric period first by controller switching equipments whole in n-quadrant The n-quadrant power consumption data constituted chooses the controller switching equipment conduct of the highest preset quantity of power consumption from the power consumption data of n-quadrant Target controller switching equipment, and target controller switching equipment is counted into the power consumption data in the electric period first and is sent to control host.
13, control host is counted the power consumption data in the electric period first to target controller switching equipment and is checked, and determination is in The target controller switching equipment of excessive power consumption state.
14, after the completion of verification, control host counts the periodic intervals in electric period and the second meter electricity period to being in first The target controller switching equipment of excessive power consumption state sends the precious activation instruction that economizes on electricity.
Before specifically describe to this method, first specific application scenarios are briefly introduced: entire supply district packet N number of region is included, is provided with the area monitoring master for collecting whole controller switching equipment power consumption datas in locating region in each region Machine, area monitoring host and control host communication in all areas.
Based on above-mentioned scene, in each area, the data acquisition terminal on whole controller switching equipments in this region is installed It obtains corresponding controller switching equipment and counts the power consumption data in the electric period first, power consumption data is sent to the area monitoring master of one's respective area Machine.Area monitoring host carries out by height power consumption data after the power consumption data for receiving whole controller switching equipments in one's respective area To low ranking, in order to cut and select the highest several controller switching equipments of power consumption according to preset quantity.For example, working as preset quantity When being 10, then the highest 10 station power distribution equipment of power consumption in one's respective area is selected.
After selecting the controller switching equipment of preset quantity, these controller switching equipments are labeled as target controller switching equipment, and from originally The power consumption data for choosing target controller switching equipment in region in the power consumption data of whole controller switching equipments sends it by wireless network To control host.
After control host receives the power consumption data of target controller switching equipment, the average consumption with region locating for target controller switching equipment Electric data are compared, if the power consumption data of target controller switching equipment is higher than average consumption data, determine target controller switching equipment Really it is in excessive power consumption state.Then control host is saved to the target controller switching equipment transmission having determined that in excessive power consumption state Electric treasured activation instruction plays the role of in order to economizing on electricity precious to the target controller switching equipment in excessive power consumption state energy-efficient.
When noticeable, the time of the precious activation instruction of control host transmission economize on electricity counts the electricity period and second for first and counts electricity Gap between period enables economize on electricity treasured play a role, thus second this is done to catch up with before the second meter electric period starts Count in the electric period, can get economize on electricity is precious carry out electricity-saving state under, the power consumption data of target controller switching equipment, and then with first The power consumption data counted in the electric period compares, to determine the power savings of target controller switching equipment.
Optionally, as shown in Fig. 2, after the operation for completing step 11-14, the above-mentioned remote energy-saving side for controller switching equipment Method, further includes:
21, data acquisition terminal will be all in the second meter electricity comprising the n-quadrant in the target controller switching equipment The power consumption data of phase is sent to the control host.Specific embodiment and the most of phase of step 11 hereinbefore in this step Together, the power consumption data of transmission is only changed to the second meter electric period from the first meter electric period before.
22, control host obtains the n-quadrant comprising target controller switching equipment from data acquisition terminal and counts the electric period second Interior power consumption data.
23, target controller switching equipment is counted power consumption data in the electric period and target current consuming apparatus the second by control host One power consumption data counted in the electric period compares, and determines economize on electricity situation of the target controller switching equipment after activation economize on electricity is precious.It is obtaining Target controller switching equipment is got after the power consumption data in the second meter electricity week, is counted with the target controller switching equipment got before first Power consumption data in the electric period compares, if target controller switching equipment, which counts the power consumption data in the electric period second, is lower than first The power consumption data in the electric period is counted, then illustrates that economize on electricity treasured that is activated, being mounted on target controller switching equipment has played economize on electricity Effect.
Optionally, as shown in figure 3, after the operation for completing step 21-23, the above-mentioned remote energy-saving side for controller switching equipment Method, further includes:
24, it according to economize on electricity situation, is still set if target controller switching equipment is counted in the electric period second for the highest distribution of power consumption Standby, target controller switching equipment is then added in maintenance list by control host.
If it is highest that the power consumption data of target controller switching equipment remains as power consumption in the power consumption data that second counts the electric period Controller switching equipment, therefore control host and target controller switching equipment is added in maintenance list, target controller switching equipment is examined in plan It repairs.
In the present embodiment, in order to rapidly analyze a large amount of power consumption data, control host is high-performance Computer.Also, controller switching equipment is to be equipped with the precious power distribution cabinet of economize on electricity.
In the present embodiment, power consumption data includes the rated power of controller switching equipment, actual power, working time.
The invention proposes a kind of remote energy-saving methods for controller switching equipment, obtain the controller switching equipment in n-quadrant, will Power consumption data is sent to area monitoring host.Area monitoring host chooses the highest controller switching equipment of power consumption, and by controller switching equipment Power consumption data is sent to control host, the controller switching equipment in excessive power consumption state is determined in order to control host, to activate Economize on electricity treasured on excessive power consumption state controller switching equipment carries out energy conservation.By being communicated with control host, selection was in It spends the controller switching equipment of power consumption and economize on electricity processing is carried out to it, to carry out complete energy consumption monitoring and energy-saving pipe to controller switching equipment Reason improves energy consumption monitoring IT application in management level, preferably plays the effect of energy monitoring data.
Each serial number in above-described embodiment is for illustration only, the assembling for not representing each component or the elder generation in use process Sequence afterwards.
The above description is only an embodiment of the present invention, is not intended to limit the invention, all in the spirit and principles in the present invention Within, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention.

Claims (6)

1. a kind of remote energy-saving method for controller switching equipment is based on controller switching equipment end, which is characterized in that described to set for distribution Standby remote energy-saving method, comprising:
The controller switching equipment in n-quadrant is obtained by data acquisition terminal and counts the power consumption data in the electric period in M, by the consumption Electric data are sent to the area monitoring host of the n-quadrant;
The area monitoring host, which is obtained, counts the power consumption data in the electric period first by controller switching equipments whole in the n-quadrant The n-quadrant power consumption data constituted chooses the controller switching equipment of the highest preset quantity of power consumption from the power consumption data of the n-quadrant As target controller switching equipment, and the target controller switching equipment is counted into the power consumption data in the electric period described first and is sent to control Host;
Based on control host side:
The power consumption data in the electric period is counted first to target controller switching equipment to check, and determines the mesh for being in excessive power consumption state Standard configuration electric equipment;
After the completion of verification, the periodic intervals that the electric period counts the electric period with second are counted described first and are in excessive power consumption to described The target controller switching equipment of state sends the precious activation instruction that economizes on electricity;
The target device, which is obtained, from data acquisition terminal counts the power consumption data in the electric period second;
By power consumption data of the target controller switching equipment within the second meter electric period with the target controller switching equipment described First power consumption data counted in the electric period compares, and determines economize on electricity feelings of the target controller switching equipment after activation economize on electricity is precious Condition;
Wherein, M, N are the natural number greater than zero.
2. the remote energy-saving method according to claim 1 for controller switching equipment, which is characterized in that further include:
Enable the data acquisition terminal by comprising the controller switching equipment in the n-quadrant in the target controller switching equipment described Second power consumption data for counting the electric period is sent to the control host.
3. the remote energy-saving method according to claim 1 or 2 for controller switching equipment, which is characterized in that the control master Machine is high-performance computer.
4. the remote energy-saving method according to claim 1 for controller switching equipment, which is characterized in that the controller switching equipment is The precious power distribution cabinet of the economize on electricity is installed.
5. the remote energy-saving method according to claim 1 for controller switching equipment, which is characterized in that the power consumption data packet Include rated power, the actual power, working time of the controller switching equipment.
6. the remote energy-saving method according to claim 1 for controller switching equipment, which is characterized in that further include:
According to the economize on electricity situation, still match if the target controller switching equipment is counted in the electric period described second for power consumption is highest The target controller switching equipment is then added in maintenance list by electric equipment.
CN201610217217.7A 2016-04-07 2016-04-07 A kind of remote energy-saving method for controller switching equipment Active CN105867185B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610217217.7A CN105867185B (en) 2016-04-07 2016-04-07 A kind of remote energy-saving method for controller switching equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610217217.7A CN105867185B (en) 2016-04-07 2016-04-07 A kind of remote energy-saving method for controller switching equipment

Publications (2)

Publication Number Publication Date
CN105867185A CN105867185A (en) 2016-08-17
CN105867185B true CN105867185B (en) 2019-01-18

Family

ID=56636494

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610217217.7A Active CN105867185B (en) 2016-04-07 2016-04-07 A kind of remote energy-saving method for controller switching equipment

Country Status (1)

Country Link
CN (1) CN105867185B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110658417B (en) * 2019-08-15 2023-06-30 杭州柯林电气股份有限公司 Overhead line fault positioning method, system and storage device

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4415896A (en) * 1981-06-09 1983-11-15 Adec, Inc. Computer controlled energy monitoring system
CN101174364A (en) * 2007-08-30 2008-05-07 北京诚信能环科技有限公司 Energy-saving monitoring system
CN201417965Y (en) * 2009-05-22 2010-03-03 山东鲁电电气集团有限公司 All-in-one energy-saving system for supplying and distributing power
CN202041813U (en) * 2011-02-24 2011-11-16 鞍山纳元电力电子有限公司 Comprehensive monitoring device of energy consumption
CN102932447A (en) * 2012-10-30 2013-02-13 无锡威泰迅电力科技有限公司 Distribution room remote data acquisition and analysis system
CN103064363A (en) * 2012-12-07 2013-04-24 广东电网公司佛山供电局 Long-distance intelligent real-time online sensing monitoring system and method of electricity utilization residential quarter switch board room
CN203787958U (en) * 2014-03-03 2014-08-20 苏州工业园区通益电气有限公司 End power-saving distribution system
CN104300675A (en) * 2014-08-28 2015-01-21 深圳供电局有限公司 Power distribution room remote monitoring method and system based on integrated substation system
CN105119284A (en) * 2015-09-17 2015-12-02 王振铎 Novel power saving system
CN204989944U (en) * 2015-08-21 2016-01-20 浙江理工大学 Enterprise -level distribution network remote monitoring system based on ethernet
CN105281346A (en) * 2015-11-27 2016-01-27 国网重庆市电力公司电力科学研究院 Remote rural network power distribution line reactive monitoring system

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4415896A (en) * 1981-06-09 1983-11-15 Adec, Inc. Computer controlled energy monitoring system
CN101174364A (en) * 2007-08-30 2008-05-07 北京诚信能环科技有限公司 Energy-saving monitoring system
CN201417965Y (en) * 2009-05-22 2010-03-03 山东鲁电电气集团有限公司 All-in-one energy-saving system for supplying and distributing power
CN202041813U (en) * 2011-02-24 2011-11-16 鞍山纳元电力电子有限公司 Comprehensive monitoring device of energy consumption
CN102932447A (en) * 2012-10-30 2013-02-13 无锡威泰迅电力科技有限公司 Distribution room remote data acquisition and analysis system
CN103064363A (en) * 2012-12-07 2013-04-24 广东电网公司佛山供电局 Long-distance intelligent real-time online sensing monitoring system and method of electricity utilization residential quarter switch board room
CN203787958U (en) * 2014-03-03 2014-08-20 苏州工业园区通益电气有限公司 End power-saving distribution system
CN104300675A (en) * 2014-08-28 2015-01-21 深圳供电局有限公司 Power distribution room remote monitoring method and system based on integrated substation system
CN204989944U (en) * 2015-08-21 2016-01-20 浙江理工大学 Enterprise -level distribution network remote monitoring system based on ethernet
CN105119284A (en) * 2015-09-17 2015-12-02 王振铎 Novel power saving system
CN105281346A (en) * 2015-11-27 2016-01-27 国网重庆市电力公司电力科学研究院 Remote rural network power distribution line reactive monitoring system

Also Published As

Publication number Publication date
CN105867185A (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN103839189A (en) Distribution automation scheme optimization method and system based on reliability benefit evaluation
CN109871965A (en) A kind of breakdown repair App platform of combination GIS and power customer fault location information
CN104751305A (en) Trouble analysis and repair-based intelligent interaction system and control method thereof
CN203261128U (en) Load-balancing control system for measuring power demand
CN103544652A (en) Power grid industry classification load automatic statistical method and system
CN105157294A (en) Control method and system for multi-online intelligent oil returning and multi-online system
CN112531886B (en) Power distribution station mobile monitoring platform device, system and method
CN102983594A (en) Control method of grid closed loop operation impact current
CN103177401A (en) Distribution network e power failure method for fault maintenance
CN102970699B (en) A kind of fault handling method and distributed base station
CN105320097A (en) Method, cloud platform and system for realization of intelligent control of household appliances
CN108898239A (en) A kind of site selection method for distribution transformer based on data analysis
CN104538957A (en) Power grid model self-adaptive processing method for counting low-frequency low-voltage load shedding capacity
CN101976886B (en) Distributed data collection partitioning mutual backup method for power dispatching automation system
CN102185299B (en) Method and device for processing failures of multi-scheme distribution network
CN105867185B (en) A kind of remote energy-saving method for controller switching equipment
CN101324989A (en) Automatic recognition technique of electrical energy meter in centralized meter reading system
CN111092487A (en) Application of broadband carrier to non-metering function of intelligent electric energy meter
CN104201766B (en) The method determining prepared auto restart sequential and combination is followed the trail of based on power supply point
CN103383461B (en) Tourist group's location acquiring method
CN203025244U (en) Power failure alarm device of power distribution room
CN105488616A (en) Data recording method and device after replacement of drawer type power distribution cabinet
CN205120867U (en) Fault monitoring system with electric loading
CN204789872U (en) Distribution system trouble on -line monitoring system
CN104360189B (en) A kind of grid power blackout event judgment method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant