CN105743086A - Determination method for high frequency generator tripping scheme of hierarchical aggregation external transmission grid power - Google Patents

Determination method for high frequency generator tripping scheme of hierarchical aggregation external transmission grid power Download PDF

Info

Publication number
CN105743086A
CN105743086A CN201410768665.7A CN201410768665A CN105743086A CN 105743086 A CN105743086 A CN 105743086A CN 201410768665 A CN201410768665 A CN 201410768665A CN 105743086 A CN105743086 A CN 105743086A
Authority
CN
China
Prior art keywords
frequency
scheme
cutting machine
power grid
area power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410768665.7A
Other languages
Chinese (zh)
Other versions
CN105743086B (en
Inventor
王青
高凯
何晓洋
黄国林
马世英
张艳军
赵鹏
刘凯
吴国旸
宋墩文
宋新立
叶小晖
苏志达
何凤军
周成
史东宇
宋云亭
李柏青
李亚楼
吴丽华
闫殿涛
那广宇
李青春
王印
徐世来
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI, State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410768665.7A priority Critical patent/CN105743086B/en
Publication of CN105743086A publication Critical patent/CN105743086A/en
Application granted granted Critical
Publication of CN105743086B publication Critical patent/CN105743086B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention provides a determination method for a high frequency generator tripping scheme of a hierarchical aggregation external transmission grid power. The method comprises steps that a district high frequency generator tripping scheme C1 for solving a high frequency problem during district grid power splitting in a regional grid power is set; a high frequency generator tripping participation scheme C2 is set for the regional grid power for cooperatively solving a high frequency problem during splitting of a provincial grid power of the regional grid power and other grid powers; a high frequency generator tripping scheme C3 is set for the regional grid power for solving a high frequency problem during splitting of the regional grid power and a main grid power of the regional grid power of the regional grid power; the district high frequency generator tripping scheme C1, the high frequency generator tripping participation scheme C2 and the high frequency generator tripping scheme C3 are verified and corrected. Through the method, segmental setting for start generator tripping frequency constant values of the high frequency generator tripping scheme of the hierarchical aggregation external transmission grid power is carried out, so the different generator tripping schemes are effectively prevented from generating interference when splitting high frequency faults in different levels occur, and thereby coordination among the different generator tripping schemes for solving different high frequency problems is guaranteed.

Description

A kind of layering collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside
Technical field
A kind of method that the present invention relates to power system safety and stability control field, collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside in particular to a kind of layering.
Background technology
For the safety that load is powered by guarantee, the security and stability control problem of area power grid is just increasingly subject to pay attention to.It is the class area power grid form that some provinces that water resource is abundant exist that layering collects the type electrical network of sending outside, relatively the Hydropower Unit dispersion of low capacity accesses different electric pressure (such as 110kV/220kV/500kV), and the rich electric power outside satisfied local load is outer after collecting step by step delivers to major network.Such area power grid faces the high frequency problem of 3 aspects:
(1) the high frequency problem after the section grid disconnection of local relative low voltage grade;
(2) the high frequency problem after the major network off-the-line of area power grid and place provincial power network;
(3) high frequency problem when this area's electrical network is positioned at sending end when major network generation off-the-line fault.
In prior art, lack and consider the layering of this 3 class high frequency problem as a whole and collect and send type power grid high-frequency cutting machine scheme defining method outside, have impact on effective performance of the high frequency control ability of area power grid.
Accordingly, it is desirable to provide the layering of a kind of improvement collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside.
Summary of the invention
For overcoming above-mentioned the deficiencies in the prior art, the present invention provides a kind of layering to collect the defining method of the high-frequency cutting machine scheme sending type electrical network outside.
Realizing the solution that above-mentioned purpose adopts is:
A kind of layering collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, and it thes improvement is that: said method comprising the steps of:
When I, the section grid disconnection arranging within area power grid, the section high-frequency cutting machine scheme C of the internal high frequency problem occurred of described area power grid reply1
When II, the provincial power network arranging described area power grid place and other grid disconnections, described area power grid assists the high-frequency cutting machine of the high frequency problem of reply provincial power network generation to participate in scheme C2
III, when the major network off-the-line of described area power grid and place provincial power network is set, the high-frequency cutting machine scheme C of the high frequency problem that the reply of described area power grid occurs3
IV, verification also revise described section high-frequency cutting machine scheme C1, described high-frequency cutting machine participate in scheme C2With described high-frequency cutting machine scheme C3
Further, described step I comprises the following steps:
The high-frequency cutting machine scheme C of high frequency problem when S101, the i-th section grid disconnection determining within described area power grid1i, i=1,2,3 ... n;
S102, determine described section high-frequency cutting machine scheme C1=C11∪C12…C1n
Further, described step S101 includes:
S1011, determine the high-frequency cutting machine scheme C of high frequency problem during described section grid disconnection1iStartup cut unit frequency definite value 52 Hz ≤ f C 1 i ≤ 54 Hz ;
S1012, determine described in cut machine point setS1iFor the unit set in the electrical network of section;
S1013, determine described power grid high-frequency cutting machine scheme C1iCut wheel time for 2-4 wheel;
S1014, according to the maximum online power P of section electrical networkupC1imax, it is determined that cut machine total amount 0.8PupC1imax≤PC1i≤PupC1imax
Further, described step II comprises the following steps:
S201, determine described high-frequency cutting machine participate in scheme C2Startup cut unit frequency definite value 50.5Hz < fC2< 51.5Hz;
S202, determine described in cut machine point setS2For the unit set that the main grid structure of this area's electrical network accesses;
S203, determine described high-frequency cutting machine participate in scheme C2Cut wheel time for 1-3 wheel;
S204, determine and cut machine total amount PC2≤PS, PSFor the unit capacity sum that the main grid structure of area power grid accesses.
Further, described step III comprises the following steps:
S301, determine that the increasing of area power grid is joined and cut machine scheme C3a
S302, determine described high-frequency cutting machine scheme C3=C1∪C2∪C3a
Wherein, C1The section high-frequency cutting machine scheme of high frequency problem, C during section grid disconnection within described area power grid2Assist the high-frequency cutting machine of high frequency problem when the provincial power network tackling described area power grid place and other grid disconnections to participate in scheme, C for described area power grid3aJoin for the increasing of described area power grid and cut machine scheme;
S303, according to the maximum online power P of area power gridupC3maxThe high-frequency cutting machine scheme C of area power grid is set3Machine of cutting total amount PC3: 0.8PupC3max≤PC3≤PupC3max
Further, described step S301 includes:
S3011, described area power grid increasing join and cut machine scheme C3aStart and cut unit frequency definite value 52Hz≤fC3a≤54Hz;
S3012, determine and cut machine point setWherein, S2For the unit set that the main grid structure of this area's electrical network mounts, SC2Scheme C is participated in for described high-frequency cutting machine2Machine of cutting some set;
S3013, determine that described increasing is joined and cut machine scheme C3aCut wheel time for 2-4 wheel.
Further, in described step IV, for described layering collect the type electrical network of sending outside set up big mode in summer, summer little mode, winter big mode and winter little mode emulation data, as checking and revise the emulation platform of described high-frequency cutting machine scheme.
Further, in described step IV, the section grid disconnection in area power grid, area power grid off-the-line, provincial power network off-the-line 3 class fault disturbance form are set, with the transient state highest frequency f of electrical network after off-the-lineh, transient state low-limit frequency fl, steady frequency f after disturbanceSThe reference index checked as high-frequency cutting machine scheme and revise;
Further, in described step IV, when satisfying condition: fh< 55Hz&fl> 49Hz&49.5Hz < fs< 50.5Hz, fhFor transient state highest frequency, flFor transient state low-limit frequency, fSFor the steady frequency after disturbance, it is determined that it is good that layering collects the high-frequency cutting machine scheme works sending type electrical network outside, otherwise judges poor effect, is modified.
Further, described correction includes: for the described section power grid high-frequency cutting machine scheme C of described area power grid1, described area power grid when assisting provincial power network and other grid disconnections tackling described area power grid place the high-frequency cutting machine of high frequency problem participate in scheme C2, described area power grid reply area power grid and place provincial power network major network off-the-line time high frequency problem high-frequency cutting machine scheme C3, in given adjusting range, be sequentially adjusted in startup cut unit frequency definite value, cut machine point set, cut wheel time, cut machine total amount, the scheme after adjusting is carried out emulation again and checks, until determine respond well till.
Compared with immediate prior art, the method have the advantages that
1, layering is collected the startup of the high-frequency cutting machine scheme sending type electrical network outside and cuts unit frequency definite value and carried out sectional setting by method provided by the invention, when realizing generation area power grid place provincial power network off-the-line fault, only area power grid assists the high-frequency cutting machine tackling this problem to participate in scheme action, the high-frequency cutting machine scheme of area power grid internal reply section off-the-line fault and area power grid are tackled its high-frequency cutting machine scheme with provincial power network off-the-line fault and are all failure to actuate, when effectively prevent generation various level off-the-line high frequency fault, difference cuts the interference between machine scheme, ensure that the harmony between machine of the cutting scheme of the different high frequency problem of reply.
2, method provided by the invention by collecting machine of the cutting point of the high-frequency cutting machine scheme sending type electrical network outside, cutting wheel time and cut the reasonable setting of machine amount to layering, achieve high-frequency cutting machine scheme and the method for operation and off-the-line pattern are had good adaptability, improve the effectiveness that electrical network controls at high frequency state of emergency lower frequency.
The advantages such as 3, method provided by the invention has Consideration comprehensively, simple to operation, have higher practical value and good market prospect.
Accompanying drawing explanation
Fig. 1 is the flow chart of the defining method that a kind of layering collects the high-frequency cutting machine scheme sending type electrical network outside in the present embodiment;
Fig. 2 is that in the present embodiment, a kind of layering collects the structural relation schematic diagram sending type electrical network outside.
Detailed description of the invention
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described in further detail.
Collecting in layering sends outside under the major network generation off-the-line fault disturbance of the section electrical network and described area power grid generation off-the-line fault, described area power grid place provincial power network and other electrical network generation off-the-line faults, described area power grid and place provincial power network within type electrical network, change in oscillation can be there is in the frequency of described area power grid, if it is bigger that off-the-line section sends power outside, frequency can seriously be ascended to heaven, and threatens the safety of generating set and electrical equipment.Therefore, it is necessary to take effective high-frequency cutting machine measure at sending end electrical network, reduce frequency and ascend to heaven degree, and avoid cutting that machine amount is excessive makes frequency excessively lower.
For the problems referred to above, the present invention provides a kind of layering to collect the defining method of the high-frequency cutting machine scheme sending type electrical network outside.
As it is shown in figure 1, Fig. 1 is the flow chart of the defining method that a kind of layering collects the high-frequency cutting machine scheme sending type electrical network outside in the present embodiment;The defining method of this high-frequency cutting machine scheme comprises the following steps:
When step one, the section grid disconnection arranging within area power grid, the section high-frequency cutting machine scheme C of the internal high frequency problem occurred of described area power grid reply1
When step 2, the provincial power network arranging described area power grid place and other grid disconnections, described area power grid assists the high-frequency cutting machine of the high frequency problem of reply provincial power network generation to participate in scheme C2
Other electrical networks described refer to the external electrical network by exchanging or DC line is connected of the provincial power network with area power grid place.
Step 3, when the major network off-the-line of described area power grid and place provincial power network is set, the high-frequency cutting machine scheme C of the high frequency problem that the reply of described area power grid occurs3
Step 4, verification also revise described section high-frequency cutting machine scheme C1, described high-frequency cutting machine participate in scheme C2With described high-frequency cutting machine scheme C3
In step one, comprise the following steps:
The high-frequency cutting machine scheme C of high frequency problem during section grid disconnection within S101, described area power grid1i, i=1,2,3 ... n;
S102, assume that area power grid total n sends matrix district electrical network outside, the section power grid high-frequency cutting machine scheme C of area power grid1These sections should be contained, it is determined that described section high-frequency cutting machine scheme C1=C11∪C12…C1n
Described step S101 includes:
S1011, determine the high-frequency cutting machine scheme C of high frequency problem during described section grid disconnection1iStartup cut unit frequency definite value fC1i, 52 Hz &le; f C 1 i &le; 54 Hz ;
S1012, determine described in cut machine point setS1iFor the unit set in the electrical network of section;
S1013, determine described power grid high-frequency cutting machine scheme C1iCut wheel time for 2-4 wheel;
S1014, according to the maximum online power P of section electrical networkupC1imaxDetermine and cut machine total amount PC1i: 0.8PupC1imax≤PC1i≤PupC1imax
In step 2, arrange area power grid assist reply provincial power network generation off-the-line fault and this area's electrical network be positioned at high frequency problem during provincial power network sending end high-frequency cutting machine participate in scheme C2.Comprise the following steps:
S201, determine described high-frequency cutting machine participate in scheme C2Startup cut unit frequency definite value 50.5Hz < fC2< 51.5Hz;
S202, determine and cut machine point setS2For the unit set that the main grid structure of this area's electrical network accesses;
S203, determine area power grid assist provincial power network high-frequency cutting machine participate in scheme high-frequency cutting machine participate in scheme C2Cut wheel time for 1-3 wheel;
S204, cut machine total amount PC2Less than the unit capacity sum P that the main grid structure of area power grid accessesS, namely can determine that and cut machine total amount PC2≤PS
In step 3, the high-frequency cutting machine scheme C of high frequency problem when area power grid reply area power grid is set with major network off-the-line3, including 3 parts, C3=C1∪C2∪C3a
Wherein, C1The section high-frequency cutting machine scheme of high frequency problem, C during the section grid disconnection tackling within electrical network for described area power grid2Assist the high-frequency cutting machine of high frequency problem when the provincial power network tackling described area power grid place and other grid disconnections to participate in scheme, C for described area power grid3aJoin for the increasing of described area power grid and cut machine scheme.
The increasing of area power grid is joined and is cut machine scheme C3aDetermination include:
S3011, determine that the increasing of described area power grid is joined and cut machine scheme C3aStart and cut unit frequency definite value 52Hz≤fC3a≤54Hz;
S3012, determine and cut machine point setWherein, S2For the unit set that the main grid structure of this area's electrical network mounts, SC2Scheme C is participated in for described high-frequency cutting machine2Machine of cutting some set;
S3013, determine that described increasing is joined and cut machine scheme C3aCut wheel time for 2-4 wheel.
Finally, according to the maximum online power P of area power gridupC3maxThe high-frequency cutting machine scheme C of area power grid is set3Machine of cutting total amount PC3: 0.8PupC3max≤PC3≤PupC3max
In step 4, the layering for research collects and sends type electrical network outside, sets up 4 set exemplary simulation data, namely big mode in summer, summer little mode, winter big mode, winter little mode emulation data, the emulation platform checked as high-frequency cutting machine scheme and revise.
Section grid disconnection in area power grid, area power grid off-the-line, provincial power network off-the-line 3 class fault disturbance form are set, with the transient state highest frequency f of electrical network after off-the-lineh, transient state low-limit frequency fl, steady frequency f after disturbances, as the reference index of the check of high-frequency cutting machine scheme and correction.
3 condition: f are met when simultaneouslyh< 55Hz, fl> 49Hz, 49.5Hz < fs< 50.5Hz, it is determined that it is good that this layering collects the high-frequency cutting machine scheme works sending type electrical network outside, otherwise judges poor effect, it is necessary to be modified.
Described correction refers to, collects, in layering, the high-frequency cutting machine scheme sending type electrical network outside and determines improperly in situation, for the section power grid high-frequency cutting machine scheme C of area power grid1, area power grid assist reply provincial power network generation off-the-line fault and this area's electrical network be positioned at high frequency problem during provincial power network sending end high-frequency cutting machine participate in scheme C2, area power grid reply area power grid and place provincial power network major network off-the-line time high frequency problem high-frequency cutting machine scheme C3, adjust in given adjusting range, be sequentially adjusted in startup and cut unit frequency definite value, cut machine point set, cut wheel time, cut machine total amount, the scheme after adjusting is carried out emulation again and checks, till configuration is good.
According to said method, collect, in conjunction with a domestic layering, the example that is configured to sending type power grid high-frequency cutting machine scheme outside and be described further.Layering collect send type electrical network outside structural relation as shown in Figure 2.
The water resource of this area's electrical network is enriched, and relatively the Hydropower Unit dispersion of low capacity accesses 110kV/220kV/500kV electric pressure, and the rich electric power outside satisfied local load is outer after collecting step by step delivers to major network.
Area power grid installed capacity is about 3855MW, and there are 3 section electrical networks sending type outside inside, is 1 section, 2 sections and 3 sections, and area power grid sends power outside to provincial power network, and provincial power network sends power outside further to other electrical networks.
This area's electrical network faces the high frequency problem of 3 aspects:
(1) the high frequency problem after 3 section grid disconnections of local;
(2) the high frequency problem after the major network off-the-line of area power grid and place provincial power network;
(3) high frequency problem when this area's electrical network is positioned at sending end when provincial power network generation off-the-line fault.
Formulate high-frequency cutting machine scheme to comprise the following steps:
When step one, the section grid disconnection arranging within area power grid, the section high-frequency cutting machine scheme C of the internal high frequency problem occurred of area power grid reply1
Described section power grid high-frequency cutting machine scheme C1Including 3 parts: 3 high-frequency cutting machine scheme C sent outside during matrix district electrical network off-the-line respectively11、C12And C13, it is configured respectively as shown in table 1 to table 3.
1 section high-frequency cutting machine scheme is set to 3 and takes turns, and cuts machine initiation culture value respectively 52Hz, 52.3Hz, 52.8Hz, cuts machine total amount PC11For 98.5MW, for the maximum online power P of section electrical networkupC11max0.86 times.
The high-frequency cutting machine scheme C of table 11 section11
2 section high-frequency cutting machine schemes are set to 3 and take turns, and cut machine initiation culture value respectively 52Hz, 52.3Hz, 53.5Hz, cut machine total amount PC12For 127.1MW, for the maximum online power P of section electrical networkupC12max0.83 times.
The high-frequency cutting machine scheme C of table 22 section12
3 section high-frequency cutting machine schemes are set to 2 and take turns, and cut machine initiation culture value respectively 52Hz, 53.5Hz, cut machine total amount PC13For 149.5MW, for the maximum online power P of section electrical networkupC13max0.99 times.
The high-frequency cutting machine scheme C of table 33 section13
In step 2, when arranging provincial power network and other grid disconnections at area power grid place, area power grid assists the high-frequency cutting machine of the high frequency problem of reply provincial power network generation to participate in scheme C2, as shown in table 4 below, it is set to 3 and takes turns, cut machine initiation culture value respectively 50.6Hz, 50.7Hz, 50.8Hz, cut machine total amount PC2For 725MW.
Table 4 area power grid assists the high-frequency cutting machine of provincial power network to participate in scheme C2
In step 3, when the major network off-the-line of area power grid and place provincial power network is set, the high-frequency cutting machine scheme C of the high frequency problem that area power grid reply occurs3, C3=C1∪C2∪C3a, wherein, C1For the section power grid high-frequency cutting machine scheme of area power grid, C2When for area power grid assistance reply provincial power network generation off-the-line fault, this area's electrical network is positioned at provincial power network sending end, the high-frequency cutting machine of high frequency problem participates in scheme, C3aJoin for the increasing of area power grid and cut machine scheme.
The increasing of area power grid is joined and is cut machine scheme C3aArrange as shown in table 5 below, be set to 2 and take turns, cut machine initiation culture value respectively 52Hz, 52.8Hz, cut machine total amount PC3aFor 510MW.
The high-frequency cutting machine scheme C of high frequency problem when area power grid reply area power grid is with major network off-the-line3Machine of cutting amount PC3Calculating formula be:For 1610MW, for the maximum online power P of area power gridupC3max0.92 times.
High-frequency cutting machine when table 5 area power grid and major network off-the-line increases formula case C3a
In step 4, the layering for research collects and sends type electrical network outside, sets up 4 set exemplary simulation data, namely big mode in summer, summer little mode, winter big mode, winter little mode data, the emulation platform checked as high-frequency cutting machine scheme and revise.Table 6 gives the flow situations that exemplary simulation mode data area power grid is relevant.
The flow situations that table 6 exemplary simulation mode data area power grid is relevant
Mode Exert oneself (MW) Load (MW) Area power grid sends power (MW) outside
Summer big mode 2558 770 1747
Summer little mode 2344 721 1618
Winter big mode 2085 744 1329
Winter little mode 1666 761 929
Section grid disconnection in area power grid, area power grid off-the-line, provincial power network off-the-line 3 class fault disturbance form are set, with the transient state highest frequency f of electrical network after off-the-lineh, transient state low-limit frequency fl, steady frequency f after disturbances, as the reference index of the check of high-frequency cutting machine scheme and correction.
Simulation result meets 3 Rule of judgment: f simultaneouslyh< 55Hz, fl> 49Hz, 49.5Hz < fs< 50.5Hz, therefore, it is determined that layering to collect the high-frequency cutting machine arrangements sending type electrical network outside good, it is not necessary to further revise.
Finally should be noted that: above example is merely to illustrate the technical scheme of the application but not the restriction to its protection domain; although with reference to above-described embodiment to present application has been detailed description; those of ordinary skill in the field are it is understood that the detailed description of the invention of application still can be carried out all changes, amendment or equivalent replacement by those skilled in the art after reading the application; but these change, revise or equivalent replacement, all within the claims that application is awaited the reply.

Claims (10)

1. a layering collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterised in that: said method comprising the steps of:
When I, the section grid disconnection arranging within area power grid, the section high-frequency cutting machine scheme C of the internal high frequency problem occurred of described area power grid reply1
When II, the provincial power network arranging described area power grid place and other grid disconnections, described area power grid assists the high-frequency cutting machine of the high frequency problem of reply provincial power network generation to participate in scheme C2
III, when the major network off-the-line of described area power grid and place provincial power network is set, the high-frequency cutting machine scheme C of the high frequency problem that the reply of described area power grid occurs3
IV, verification also revise described section high-frequency cutting machine scheme C1, described high-frequency cutting machine participate in scheme C2With described high-frequency cutting machine scheme C3
2. a kind of layering as claimed in claim 1 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterised in that: described step I comprises the following steps:
The high-frequency cutting machine scheme C of high frequency problem when S101, the i-th section grid disconnection determining within described area power grid1i, i=1,2,3 ... n;
S102, determine described section high-frequency cutting machine scheme C1=C11∪C12…C1n
3. a kind of layering as claimed in claim 1 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterised in that: described step S101 includes:
S1011, determine the high-frequency cutting machine scheme C of high frequency problem during described section grid disconnection1iStartup cut unit frequency definite value
S1012, determine described in cut machine point setS1iFor the unit set in the electrical network of section;
S1013, determine described power grid high-frequency cutting machine scheme C1iCut wheel time for 2-4 wheel;
S1014, according to the maximum online power P of section electrical networkupC1imax, it is determined that cut machine total amount 0.8PupC1imax≤PC1i≤PupC1imax
4. a kind of layering as claimed in claim 1 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterised in that: described step II comprises the following steps:
S201, determine described high-frequency cutting machine participate in scheme C2Startup cut unit frequency definite value 50.5Hz < fC2< 51.5Hz;
S202, determine described in cut machine point setS2For the unit set that the main grid structure of this area's electrical network accesses;
S203, determine described high-frequency cutting machine participate in scheme C2Cut wheel time for 1-3 wheel;
S204, determine and cut machine total amount PC2≤PS, PSFor the unit capacity sum that the main grid structure of area power grid accesses.
5. a kind of layering as claimed in claim 1 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterised in that: described step III comprises the following steps:
S301, determine that the increasing of area power grid is joined and cut machine scheme C3a
S302, determine described high-frequency cutting machine scheme C3=C1∪C2∪C3a
Wherein, C1The section high-frequency cutting machine scheme of high frequency problem, C during section grid disconnection within described area power grid2Assist the high-frequency cutting machine of high frequency problem when the provincial power network tackling described area power grid place and other grid disconnections to participate in scheme, C for described area power grid3aJoin for the increasing of described area power grid and cut machine scheme;
S303, according to the maximum online power P of area power gridupC3maxThe high-frequency cutting machine scheme C of area power grid is set3Machine of cutting total amount PC3: 0.8PupC3max≤PC3≤PupC3max
6. a kind of layering as claimed in claim 5 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterised in that: described step S301 includes:
S3011, described area power grid increasing join and cut machine scheme C3aStart and cut unit frequency definite value 52Hz≤fC3a≤54Hz;
S3012, determine and cut machine point setWherein, S2For the unit set that the main grid structure of this area's electrical network mounts, SC2Scheme C is participated in for described high-frequency cutting machine2Machine of cutting some set;
S3013, determine that described increasing is joined and cut machine scheme C3aCut wheel time for 2-4 wheel.
7. a kind of layering as claimed in claim 1 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterized in that: in described step IV, for described layering collect the type electrical network of sending outside set up big mode in summer, summer little mode, winter big mode and winter little mode emulation data, as checking and revise the emulation platform of described high-frequency cutting machine scheme.
8. a kind of layering as claimed in claim 7 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterized in that: in described step IV, section grid disconnection in area power grid, area power grid off-the-line, provincial power network off-the-line 3 class fault disturbance form are set, with the transient state highest frequency f of electrical network after off-the-lineh, transient state low-limit frequency fl, steady frequency f after disturbanceSThe reference index checked as high-frequency cutting machine scheme and revise.
9. a kind of layering as claimed in claim 8 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterised in that: in described step IV, when satisfying condition: fh< 55Hz&fl> 49Hz&49.5Hz < fs< 50.5Hz, fhFor transient state highest frequency, flFor transient state low-limit frequency, fSFor the steady frequency after disturbance, it is determined that it is good that layering collects the high-frequency cutting machine scheme works sending type electrical network outside, otherwise judges poor effect, is modified.
10. a kind of layering as claimed in claim 9 collects the defining method of the high-frequency cutting machine scheme sending type electrical network outside, it is characterised in that: described correction includes: for the described section power grid high-frequency cutting machine scheme C of described area power grid1, described area power grid when assisting provincial power network and other grid disconnections tackling described area power grid place the high-frequency cutting machine of high frequency problem participate in scheme C2, described area power grid reply area power grid and place provincial power network major network off-the-line time high frequency problem high-frequency cutting machine scheme C3, in given adjusting range, be sequentially adjusted in startup cut unit frequency definite value, cut machine point set, cut wheel time, cut machine total amount, the scheme after adjusting is carried out emulation again and checks, until determine respond well till.
CN201410768665.7A 2014-12-11 2014-12-11 It is a kind of to be layered the determining method for collecting the high-frequency cutting machine scheme for sending type power grid outside Active CN105743086B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410768665.7A CN105743086B (en) 2014-12-11 2014-12-11 It is a kind of to be layered the determining method for collecting the high-frequency cutting machine scheme for sending type power grid outside

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410768665.7A CN105743086B (en) 2014-12-11 2014-12-11 It is a kind of to be layered the determining method for collecting the high-frequency cutting machine scheme for sending type power grid outside

Publications (2)

Publication Number Publication Date
CN105743086A true CN105743086A (en) 2016-07-06
CN105743086B CN105743086B (en) 2018-07-10

Family

ID=56241480

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410768665.7A Active CN105743086B (en) 2014-12-11 2014-12-11 It is a kind of to be layered the determining method for collecting the high-frequency cutting machine scheme for sending type power grid outside

Country Status (1)

Country Link
CN (1) CN105743086B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106505569A (en) * 2016-12-28 2017-03-15 云南电力调度控制中心 A kind of method that asynchronous sending end provincial power network high-frequency cutting machine strategy is formulated in analysis

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003122956A (en) * 2001-10-12 2003-04-25 Hitachi Ltd Electric power transaction market system and transaction method
CN102412575A (en) * 2011-11-29 2012-04-11 中国电力科学研究院 Simulation evaluation method for configuration scheme of safe automatic device of transmitting-end power grid high-frequency cutting machine
CN102570454A (en) * 2012-01-10 2012-07-11 中国电力科学研究院 Simulation collocation method for oscillation disconnection device of power system
CN103248055A (en) * 2013-05-13 2013-08-14 南京南瑞集团公司 Method for solving accurate selecting and changing of generator and load after regional power grid splitting
CN103390081A (en) * 2013-07-22 2013-11-13 国家电网公司 Simulation configuration method for constant-value parameter of frequency control device in weak interconnection power grid
CN104201668A (en) * 2014-08-13 2014-12-10 中国南方电网有限责任公司 Isolated grid operation stabilization control method for regional weak tie power grid

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003122956A (en) * 2001-10-12 2003-04-25 Hitachi Ltd Electric power transaction market system and transaction method
CN102412575A (en) * 2011-11-29 2012-04-11 中国电力科学研究院 Simulation evaluation method for configuration scheme of safe automatic device of transmitting-end power grid high-frequency cutting machine
CN102570454A (en) * 2012-01-10 2012-07-11 中国电力科学研究院 Simulation collocation method for oscillation disconnection device of power system
CN103248055A (en) * 2013-05-13 2013-08-14 南京南瑞集团公司 Method for solving accurate selecting and changing of generator and load after regional power grid splitting
CN103390081A (en) * 2013-07-22 2013-11-13 国家电网公司 Simulation configuration method for constant-value parameter of frequency control device in weak interconnection power grid
CN104201668A (en) * 2014-08-13 2014-12-10 中国南方电网有限责任公司 Isolated grid operation stabilization control method for regional weak tie power grid

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
许家政: "佛山电网电厂自动解列与保护配合问题的研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑(月刊)》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106505569A (en) * 2016-12-28 2017-03-15 云南电力调度控制中心 A kind of method that asynchronous sending end provincial power network high-frequency cutting machine strategy is formulated in analysis
CN106505569B (en) * 2016-12-28 2019-01-22 云南电力调度控制中心 A method of asynchronous sending end provincial power network high-frequency cutting machine strategy is formulated in analysis

Also Published As

Publication number Publication date
CN105743086B (en) 2018-07-10

Similar Documents

Publication Publication Date Title
CN102360475B (en) Comprehensive evaluation method for coordination of power supply capacity of urban power transmission and distribution network
CN103236719A (en) Wind power bundling control method after wind power and thermal power accessing to power grid
Jiang et al. Short-term voltage stability-constrained unit commitment for receiving-end grid with multi-infeed HVDCs
CN103887810A (en) Method for judging whether continuous phase changing of direct-current system fails on basis of short-circuit ratio dynamic tracking
CN103269079B (en) Reactive compensation configuration method based on static and transient voltage stability constraint
CN106828123A (en) The high-speed railway tractive power supply system and control method of a kind of distributed photovoltaic power
CN105305427A (en) Peak adjusting method of electrical network by taking external power reception into consideration
CN104036342B (en) A kind of Electric power network planning method based on three-dimensional grid construction network mode
CN103956773B (en) Backup configuration optimization method containing wind power system unit
CN103001234A (en) Method for controlling reactive voltage in ultra-high voltage grid on the basis of improved economic voltage difference
CN201766373U (en) Power quality control device for distributed photovoltaic power grid
CN106099978A (en) Metro braking energy back feed device, control method for reactive-load compensation
CN104392287A (en) 500 kV/220 kV receiving end power grid partitioning method
CN105743086A (en) Determination method for high frequency generator tripping scheme of hierarchical aggregation external transmission grid power
CN104348162B (en) 330kV wind energy turbine set collects control method of transformer station voltage
CN104701859B (en) It is applied to the generating set idle output distribution method of power plant AVC system
CN106447180A (en) Green index evaluation method for urban thermal power generating unit
Habib et al. Demand and application of energy storage technology in renewable energy power system
CN104348180A (en) Distributed power supply grid-connected point and access mode selection method
CN104795823B (en) The newly-increased reactive compensation capacity computational methods of power network minimum based on hierarchy optimization
CN104319822B (en) A kind of across grid power peak modulation capacity dispatching method and equipment
CN103956742B (en) The defining method of power system operation mode under a kind of complicated energy environment
CN102545392A (en) Multi-purpose controllable and schedulable energy storage system and method thereof
Jiang et al. Resilient Control Strategy Based on Power Router for Distribution Network With Renewable Generation
CN205823693U (en) A kind of high-power transformer fan

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant