CN105117280A - Virtual machine migration device and method - Google Patents

Virtual machine migration device and method Download PDF

Info

Publication number
CN105117280A
CN105117280A CN201510521724.5A CN201510521724A CN105117280A CN 105117280 A CN105117280 A CN 105117280A CN 201510521724 A CN201510521724 A CN 201510521724A CN 105117280 A CN105117280 A CN 105117280A
Authority
CN
China
Prior art keywords
migration
virtual machine
strategy
information
action
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510521724.5A
Other languages
Chinese (zh)
Inventor
何冠宇
李福辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yonyou Network Technology Co Ltd
Original Assignee
Yonyou Network Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yonyou Network Technology Co Ltd filed Critical Yonyou Network Technology Co Ltd
Priority to CN201510521724.5A priority Critical patent/CN105117280A/en
Publication of CN105117280A publication Critical patent/CN105117280A/en
Pending legal-status Critical Current

Links

Landscapes

  • Data Exchanges In Wide-Area Networks (AREA)

Abstract

The invention provides a virtual machine migration device which comprises a monitoring and collecting unit, an analysis unit, a decision unit and an execution unit, wherein the monitoring and collecting unit is used for monitoring the network data accessing to and outgoing a virtual machine, extracting information required by the migration of the virtual machine and collecting the information; the analysis unit is used for analyzing on the basis of the information collected from the network data accessing to and outgoing the virtual machine, extracting information required by the migration of the virtual machine in the analysis result and distributing the information; the decision unit is used for deciding whether to made a virtual machine migration decision or not on the basis of the information extracted from the analysis result and a pre-configured strategy; and the execution unit is used for executing a practical virtual machine migration action according to the virtual machine migration decision result. The invention further provides a virtual machine migration method. Through the technical scheme provided by the invention, the migration of the virtual machines of multi-object types can be completed by fully utilizing single-object types on the basis of the existing virtual machine migration manner, and a general and uniform migration train of thought for the migration of the multi-object participated virtual machines of complicated object types can be established.

Description

Virtual machine (vm) migration apparatus and method
Technical field
The present invention relates to field of computer technology, particularly, relate to a kind of virtual machine (vm) migration device and a kind of virtual machine migration method.
Background technology
Under cloud computing mode, application, data and IT resource are supplied to user in the mode of service by network and use.A large amount of computational resource composition IT resource pools, for the highly virtualized resource of dynamic creation, and is supplied to user's use.
Under IaaS, virtual machine is as a kind of IT resource, is applied for by user, distributes to user and uses.
The deployment of current virtual machine is by the static policies such as horizontal or vertical, namely after user applies for virtual machine, policy deployment virtual machine is disposed to suitable physical machine according to preassigned static state, once after disposing virtual machine, namely virtual machine is positioned on corresponding physical host and runs during virtual machine creating.
If virtual machine will move to other physical machine and run, then need keeper to pass through manual operations, specify the object physical host of the virtual machine that will move and migration, thus complete and once move.At least there is following problem in this mode:
(1) all selected by keeper by the virtual machine moved and the object physical host moved to, keeper needs to determine according to what to move, such as, move according to energy consumption saving, carry out moving etc. according to accounts information.Keeper also will check whether the condition of migration meets, and be such as whether object physical host has enough resource operation virtual machines etc., subjectivity is too large, and cannot avoid judging and misoperation.
If (2) will move a large amount of virtual machine, then keeper's workload is huge, further increases the possibility of the misoperation in transition process.
(3) migration determines do not have unified policy mechanism by keeper oneself completely, lacks robotization.
Therefore, need a kind of new virtual machine migration technology, on existing virtual machine (vm) migration mode basis, the virtual machine (vm) migration that single object type completes multi-object type can be made full use of, set up general, the unified migration thinking of the complex object class virtual machine (vm) migration that multi-object type participates in.
Summary of the invention
The present invention is just based on the problems referred to above, propose a kind of new virtual machine migration technology, can on existing virtual machine (vm) migration mode basis, make full use of the virtual machine (vm) migration that single object type completes multi-object type, set up general, the unified migration thinking of the complex object class virtual machine (vm) migration that multi-object type participates in.
In view of this, the present invention proposes a kind of virtual machine (vm) migration device, comprising: monitor collecting unit, for monitoring the network data of turnover virtual machine, information needed during extraction virtual machine (vm) migration also gathers, and collection gained information is carried out gathering and issuing; Analytic unit, for always gathering gained information based on the network data from turnover virtual machine and analyze, information needed issuing during virtual machine (vm) migration in extraction and analysis result; Decision package, for based on extracting gained information and pre-configured strategy in analysis result, determines the decision-making whether making virtual machine (vm) migration; Performance element, for according to the result of decision whether making virtual machine (vm) migration, performs actual virtual machine (vm) migration action.In this technical scheme, by the monitoring to virtual machine network data behaviour in service, collection, analysis, according to strategy, Autonomic Migration Framework virtual machine to suitable object physical host, thus avoids keeper's misoperation, reduces management workload, reduce O&M complicacy, improve O&M robotization.
In technique scheme, preferably, described monitor collecting unit, specifically comprises: Network Data Control module, for monitoring the network data of turnover virtual machine; Information acquisition module, for extracting virtual machine (vm) migration information needed in the network data from turnover virtual machine; This virtual machine (vm) migration information needed, comprises source IP, the object IP of message, source MAC, object MAC, source TCP/UDP port numbers, object TCP/UDP port numbers and timestamp; Information summarizing module, issues after the virtual machine (vm) migration information needed of extraction being gathered.In this technical scheme, the network data of turnover virtual machine is carried out to the function of collection analysis, and the function had the data pick-up key message collected, and these information package are sent to analytic unit in batches, can fast processing information, and the information gathered must be full and accurate.
In technique scheme, preferably, described analytic unit, specifically comprises: information analysis module, for analyzing the virtual machine (vm) migration information needed extracted; Information extraction modules, for information needed during virtual machine (vm) migration in extraction and analysis result; Information needed during virtual machine (vm) migration in this analysis result, comprises in preset time period and has the data traffic of predetermined amount to be sent to another virtual machine from a virtual machine, or the TCP that predetermined time respective virtual machine accepts other virtual machine of respective amount connects; Information sending module, for will extract information package after, send in batches.In this technical scheme, decision package can be sent to by analyzing the information obtained, determining whether carry out virtual machine (vm) migration by decision package, the path that network data is undertaken by multiple physical network device forwarding can be shortened, reduce network equipment energy consumption, reduce propagation delay time, improve communication efficiency.
In technique scheme, preferably, described decision package, specifically comprise: migration decision-making module, for based in analysis result during virtual machine (vm) migration information needed carry out table lookup operation, if a certain item in hit table, then represent and meet the condition of migration strategy, when can move, the instruction can moved based on the migration action executing of this pointed is sent to performance element; Feedback information processing module, for the execution result fed back based on performance element, record moves successfully or failed information, and upgrades the current state of migration strategy; The operation of the current state of this renewal migration strategy, comprise: when receiving performance element Successful migration virtual machine when physical host meets the condition of migration strategy and feedback moves successful information, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, to receive when physical host does not meet the condition of migration strategy performance element at preset timed intervals interval how long attempt migration action success and feedback migration successful information time, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, receive performance element when physical host does not meet the condition of migration strategy at preset timed intervals interval how long attempt moving baulk and feedback migration failed information time, corresponding migration strategy is deleted, record migration strategy state is unsuccessfully, record failed daily record, and mail notification staff.In this technical scheme, by configuration and the state updating of migration strategy, networking forward-path can be shortened, reduce forwarded time delay, improve communication efficiency.
In technique scheme, preferably, described performance element, specifically comprises: object physical host checking module, for before performing the instruction of moving based on the migration action executing of a certain pointed, check whether the object physical host moved to meets pre-conditioned; This is pre-conditioned comprises CPU, whether internal memory, disk, Internet resources are enough, and/or whether load transfinites; Virtual machine (vm) migration module, for when object physical host meets pre-conditioned, the migration of virtual machine is carried out in the instruction that the migration action executing based on a certain pointed moves; When object physical host does not meet pre-conditioned, then at interval of again attempting preset times after preset duration and the migration action of the instruction of moving based on the migration action executing of a certain pointed; Migration information feedback module, for meeting at object physical host pre-conditioned and carry out the migration success of virtual machine based on the instruction that the migration action executing of a certain pointed moves after, moving successful information feed back first to decision package; And/or, do not meet pre-conditioned at object physical host and again move successfully, again will move successful information feed back to decision package; And/or, do not meet pre-conditioned at object physical host and again move unsuccessfully, by information feed back failed for migration to decision package; Further, described decision package, specifically also comprises: migration strategy configuration module, for configuration emigration strategy, and by the migration strategy configured in advance of configuration in table; The condition of the corresponding migration strategy of each list item of table, and with the action of pointed migration strategy; The operation of this configuration emigration strategy, comprises configuration many migration strategys, and/or different but many strategies that migration action is identical of configuration emigration condition; Described migration strategy has priority, if many migration strategys all meet transition condition, then carries out the migration action that the highest transition condition of priority is corresponding; Described migration strategy comprises transition condition and migration action; Described transition condition comprises the network traffics in the unit interval between two virtual machines, the number of communications in the unit interval between two virtual machines, certain virtual machine broadcast or multicast network flow in the unit interval; Described migration action comprise in real time or in certain time period to meeting the virtual machine (vm) migration of transition condition to where, and by the multiple stage physical machine of the virtual machine (vm) migration to the same network segment that meet transition condition or same physical machine; Further, described decision package, for pre-configured virtual machine fetch strategy; Based on extracting gained information and pre-configured strategy in analysis result, determine the decision-making whether making virtual machine (vm) migration.In this technical scheme, can to the real-time monitoring of virtual machine network data, according to the migration strategy of monitor data and administrator configurations, realize the dynamic migration of virtual machine, reach raising resource utilization, reduce the resource consumption of physical network device, improve the object of communication efficiency.
According to a further aspect of the invention, also proposed a kind of virtual machine migration method, comprise: step 202: monitor the network data of turnover virtual machine, information needed during extraction virtual machine (vm) migration also gathers, and collection gained information is carried out gathering and issuing; Step 204: always gather gained information based on the network data from turnover virtual machine and analyze, information needed issuing during virtual machine (vm) migration in extraction and analysis result; Step 206: based on extracting gained information and pre-configured strategy in analysis result, determines the decision-making whether making virtual machine (vm) migration; Step 208: according to the result of decision whether making virtual machine (vm) migration, perform actual virtual machine (vm) migration action.In this technical scheme, by the monitoring to virtual machine network data behaviour in service, collection, analysis, according to strategy, Autonomic Migration Framework virtual machine to suitable object physical host, thus avoids keeper's misoperation, reduces management workload, reduce O&M complicacy, improve O&M robotization.
In technique scheme, preferably, described step 202, specifically comprises: step 302: the network data of monitoring turnover virtual machine; Step 304: extract virtual machine (vm) migration information needed from the network data of turnover virtual machine; This virtual machine (vm) migration information needed, comprises source IP, the object IP of message, source MAC, object MAC, source TCP/UDP port numbers, object TCP/UDP port numbers and timestamp; Step 306: issue after the virtual machine (vm) migration information needed of extraction is gathered.In this technical scheme, the network data of turnover virtual machine is carried out to the function of collection analysis, and the function had the data pick-up key message collected, and these information package are sent to analytic unit in batches, can fast processing information, and the information gathered must be full and accurate.
In technique scheme, preferably, described step 204, specifically comprises: step 402: analyze the virtual machine (vm) migration information needed extracted; Step 404: information needed during virtual machine (vm) migration in extraction and analysis result; Information needed during virtual machine (vm) migration in this analysis result, comprises in preset time period and has the data traffic of predetermined amount to be sent to another virtual machine from a virtual machine, or the TCP that predetermined time respective virtual machine accepts other virtual machine of respective amount connects; Step 406: after the information package of extraction, in batches send.In this technical scheme, decision package can be sent to by analyzing the information obtained, determining whether carry out virtual machine (vm) migration by decision package, the path that network data is undertaken by multiple physical network device forwarding can be shortened, reduce network equipment energy consumption, reduce propagation delay time, improve communication efficiency.
In technique scheme, preferably, described step 206, specifically comprise: step 504: based in analysis result during virtual machine (vm) migration information needed carry out table lookup operation, if a certain item in hit table, then represent the condition meeting migration strategy, when can move, the instruction can moved based on the migration action executing of this pointed is sent to performance element; Step 506: based on the execution result of performance element feedback, record moves successfully or failed information, and upgrades the current state of migration strategy; The operation of the current state of this renewal migration strategy, comprise: when receiving performance element Successful migration virtual machine when physical host meets the condition of migration strategy and feedback moves successful information, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, to receive when physical host does not meet the condition of migration strategy performance element at preset timed intervals interval how long attempt migration action success and feedback migration successful information time, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, receive performance element when physical host does not meet the condition of migration strategy at preset timed intervals interval how long attempt moving baulk and feedback migration failed information time, corresponding migration strategy is deleted, record migration strategy state is unsuccessfully, record failed daily record, and mail notification staff.In this technical scheme, by configuration and the state updating of migration strategy, networking forward-path can be shortened, reduce forwarded time delay, improve communication efficiency.
In technique scheme, preferably, described step 208, specifically comprises: step 602: before performing the instruction of moving based on the migration action executing of a certain pointed, checks whether the object physical host moved to meets pre-conditioned; This is pre-conditioned comprises CPU, whether internal memory, disk, Internet resources are enough, and/or whether load transfinites; Step 604: when object physical host meets pre-conditioned, the migration of virtual machine is carried out in the instruction that the migration action executing based on a certain pointed moves; When object physical host does not meet pre-conditioned, then at interval of again attempting preset times after preset duration and the migration action of the instruction of moving based on the migration action executing of a certain pointed; Step 606: meet pre-conditioned at object physical host and carry out the migration success of virtual machine based on the instruction that the migration action executing of a certain pointed moves after, successful information feed back will be moved first to decision package; And/or, do not meet pre-conditioned at object physical host and again move successfully, again will move successful information feed back to decision package; And/or, do not meet pre-conditioned at object physical host and again move unsuccessfully, by information feed back failed for migration to decision package; Further, described step 206, specifically also comprises: step 502: configuration emigration strategy, and by the migration strategy configured in advance of configuration in table; The condition of the corresponding migration strategy of each list item of table, and with the action of pointed migration strategy; The operation of this configuration emigration strategy, comprises configuration many migration strategys, and/or different but many strategies that migration action is identical of configuration emigration condition; Described migration strategy has priority, if many migration strategys all meet transition condition, then carries out the migration action that the highest transition condition of priority is corresponding; Described migration strategy comprises transition condition and migration action; Described transition condition comprises the network traffics in the unit interval between two virtual machines, the number of communications in the unit interval between two virtual machines, certain virtual machine broadcast or multicast network flow in the unit interval; Described migration action comprise in real time or in certain time period to meeting the virtual machine (vm) migration of transition condition to where, and by the multiple stage physical machine of the virtual machine (vm) migration to the same network segment that meet transition condition or same physical machine; Further, described step 206: pre-configured virtual machine fetch strategy; Based on extracting gained information and pre-configured strategy in analysis result, determine the decision-making whether making virtual machine (vm) migration.In this technical scheme, can to the real-time monitoring of virtual machine network data, according to the migration strategy of monitor data and administrator configurations, realize the dynamic migration of virtual machine, reach raising resource utilization, reduce the resource consumption of physical network device, improve the object of communication efficiency.
By above technical scheme, on existing virtual machine (vm) migration mode basis, the virtual machine (vm) migration that single object type completes multi-object type can be made full use of, set up general, the unified migration thinking of the complex object class virtual machine (vm) migration that multi-object type participates in.
Accompanying drawing explanation
Fig. 1 shows the block diagram of virtual machine (vm) migration device according to an embodiment of the invention;
Fig. 2 shows the process flow diagram of virtual machine migration method according to an embodiment of the invention;
Fig. 3 shows the process flow diagram of monitor collecting unit according to an embodiment of the invention;
Fig. 4 shows the process flow diagram of analytic unit according to an embodiment of the invention;
Fig. 5 shows the process flow diagram of decision package according to an embodiment of the invention;
Fig. 6 shows the process flow diagram of performance element according to an embodiment of the invention;
Fig. 7 shows the particular flow sheet of the virtual machine (vm) migration process of data analysis Network Based according to an embodiment of the invention.
Embodiment
In order to more clearly understand above-mentioned purpose of the present invention, feature and advantage, below in conjunction with the drawings and specific embodiments, the present invention is further described in detail.It should be noted that, when not conflicting, the feature in the embodiment of the application and embodiment can combine mutually.
Set forth a lot of detail in the following description so that fully understand the present invention; but; the present invention can also adopt other to be different from other modes described here and implement, and therefore, protection scope of the present invention is not by the restriction of following public specific embodiment.
Fig. 1 shows the block diagram of virtual machine (vm) migration device according to an embodiment of the invention.
As shown in Figure 1, virtual machine (vm) migration device 100 according to an embodiment of the invention, comprising: monitor collecting unit 102, for monitoring the network data of turnover virtual machine, information needed during extraction virtual machine (vm) migration also gathers, and collection gained information is carried out gathering and issuing; Analytic unit 104, for always gathering gained information based on the network data from turnover virtual machine and analyze, information needed issuing during virtual machine (vm) migration in extraction and analysis result; Decision package 106, for based on extracting gained information and pre-configured strategy in analysis result, determines the decision-making whether making virtual machine (vm) migration; Performance element 108, for according to the result of decision whether making virtual machine (vm) migration, performs actual virtual machine (vm) migration action.In this technical scheme, by the monitoring to virtual machine network data behaviour in service, collection, analysis, according to strategy, Autonomic Migration Framework virtual machine to suitable object physical host, thus avoids keeper's misoperation, reduces management workload, reduce O&M complicacy, improve O&M robotization.
In technique scheme, preferably, monitor collecting unit 102, specifically comprises: Network Data Control module 1022, for monitoring the network data of turnover virtual machine; Information acquisition module 1024, for extracting virtual machine (vm) migration information needed in the network data from turnover virtual machine; This virtual machine (vm) migration information needed, comprises source IP, the object IP of message, source MAC, object MAC, source TCP/UDP port numbers, object TCP/UDP port numbers and timestamp; Information summarizing module 1026, issues after the virtual machine (vm) migration information needed of extraction being gathered.In this technical scheme, the network data of turnover virtual machine is carried out to the function of collection analysis, and the function had the data pick-up key message collected, and these information package are sent to analytic unit in batches, can fast processing information, and the information gathered must be full and accurate.
In technique scheme, preferably, analytic unit 104, specifically comprises: information analysis module 1042, for analyzing the virtual machine (vm) migration information needed extracted; Information extraction modules 1044, for information needed during virtual machine (vm) migration in extraction and analysis result; Information needed during virtual machine (vm) migration in this analysis result, comprises in preset time period and has the data traffic of predetermined amount to be sent to another virtual machine from a virtual machine, or the TCP that predetermined time respective virtual machine accepts other virtual machine of respective amount connects; Information sending module 1046, for will extract information package after, send in batches.In this technical scheme, decision package can be sent to by analyzing the information obtained, determining whether carry out virtual machine (vm) migration by decision package, the path that network data is undertaken by multiple physical network device forwarding can be shortened, reduce network equipment energy consumption, reduce propagation delay time, improve communication efficiency.
In technique scheme, preferably, decision package 106, specifically comprise: migration decision-making module 1064, for based in analysis result during virtual machine (vm) migration information needed carry out table lookup operation, if a certain item in hit table, then represent and meet the condition of migration strategy, when can move, the instruction can moved based on the migration action executing of this pointed is sent to performance element; Feedback information processing module 1066, for the execution result fed back based on performance element, record moves successfully or failed information, and upgrades the current state of migration strategy; The operation of the current state of this renewal migration strategy, comprise: when receiving performance element Successful migration virtual machine when physical host meets the condition of migration strategy and feedback moves successful information, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, to receive when physical host does not meet the condition of migration strategy performance element at preset timed intervals interval how long attempt migration action success and feedback migration successful information time, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, receive performance element when physical host does not meet the condition of migration strategy at preset timed intervals interval how long attempt moving baulk and feedback migration failed information time, corresponding migration strategy is deleted, record migration strategy state is unsuccessfully, record failed daily record, and mail notification staff.In this technical scheme, by configuration and the state updating of migration strategy, networking forward-path can be shortened, reduce forwarded time delay, improve communication efficiency.
In technique scheme, preferably, performance element 108, specifically comprises: object physical host checking module 1082, for before performing the instruction of moving based on the migration action executing of a certain pointed, check whether the object physical host moved to meets pre-conditioned; This is pre-conditioned comprises CPU, whether internal memory, disk, Internet resources are enough, and/or whether load transfinites; Virtual machine (vm) migration module 1084, for when object physical host meets pre-conditioned, the migration of virtual machine is carried out in the instruction that the migration action executing based on a certain pointed moves; When object physical host does not meet pre-conditioned, then at interval of again attempting preset times after preset duration and the migration action of the instruction of moving based on the migration action executing of a certain pointed; Migration information feedback module 1086, for meeting at object physical host pre-conditioned and carry out the migration success of virtual machine based on the instruction that the migration action executing of a certain pointed moves after, moving successful information feed back first to decision package; And/or, do not meet pre-conditioned at object physical host and again move successfully, again will move successful information feed back to decision package; And/or, do not meet pre-conditioned at object physical host and again move unsuccessfully, by information feed back failed for migration to decision package; Further, decision package 106, specifically also comprises: migration strategy configuration module 1062, for configuration emigration strategy, and by the migration strategy configured in advance of configuration in table; The condition of the corresponding migration strategy of each list item of table, and with the action of pointed migration strategy; The operation of this configuration emigration strategy, comprises configuration many migration strategys, and/or different but many strategies that migration action is identical of configuration emigration condition; Migration strategy has priority, if many migration strategys all meet transition condition, then carries out the migration action that the highest transition condition of priority is corresponding; Migration strategy comprises transition condition and migration action; Transition condition comprises the network traffics in the unit interval between two virtual machines, the number of communications in the unit interval between two virtual machines, certain virtual machine broadcast or multicast network flow in the unit interval; Migration action comprise in real time or in certain time period to meeting the virtual machine (vm) migration of transition condition to where, and by the multiple stage physical machine of the virtual machine (vm) migration to the same network segment that meet transition condition or same physical machine; Further, decision package 106, for pre-configured virtual machine fetch strategy; Based on extracting gained information and pre-configured strategy in analysis result, determine the decision-making whether making virtual machine (vm) migration.In this technical scheme, can to the real-time monitoring of virtual machine network data, according to the migration strategy of monitor data and administrator configurations, realize the dynamic migration of virtual machine, reach raising resource utilization, reduce the resource consumption of physical network device, improve the object of communication efficiency.
Fig. 2 shows the process flow diagram of virtual machine migration method according to an embodiment of the invention.
As shown in Figure 2, virtual machine migration method according to an embodiment of the invention, comprising: step 202: monitor the network data of turnover virtual machine, and information needed during extraction virtual machine (vm) migration also gathers, and collection gained information is carried out gathering and issuing; Step 204: always gather gained information based on the network data from turnover virtual machine and analyze, information needed issuing during virtual machine (vm) migration in extraction and analysis result; Step 206: based on extracting gained information and pre-configured strategy in analysis result, determines the decision-making whether making virtual machine (vm) migration; Step 208: according to the result of decision whether making virtual machine (vm) migration, perform actual virtual machine (vm) migration action.In this technical scheme, by the monitoring to virtual machine network data behaviour in service, collection, analysis, according to strategy, Autonomic Migration Framework virtual machine to suitable object physical host, thus avoids keeper's misoperation, reduces management workload, reduce O&M complicacy, improve O&M robotization.
In technique scheme, preferably, see Fig. 3, step 202, specifically comprises: step 302: the network data of monitoring turnover virtual machine; Step 304: extract virtual machine (vm) migration information needed from the network data of turnover virtual machine; This virtual machine (vm) migration information needed, comprises source IP, the object IP of message, source MAC, object MAC, source TCP/UDP port numbers, object TCP/UDP port numbers and timestamp; Step 306: issue after the virtual machine (vm) migration information needed of extraction is gathered.In this technical scheme, the network data of turnover virtual machine is carried out to the function of collection analysis, and the function had the data pick-up key message collected, and these information package are sent to analytic unit in batches, can fast processing information, and the information gathered must be full and accurate.
In technique scheme, preferably, see Fig. 4, step 204, specifically comprises: step 402: analyze the virtual machine (vm) migration information needed extracted; Step 404: information needed during virtual machine (vm) migration in extraction and analysis result; Information needed during virtual machine (vm) migration in this analysis result, comprises in preset time period and has the data traffic of predetermined amount to be sent to another virtual machine from a virtual machine, or the TCP that predetermined time respective virtual machine accepts other virtual machine of respective amount connects; Step 406: after the information package of extraction, in batches send.In this technical scheme, decision package can be sent to by analyzing the information obtained, determining whether carry out virtual machine (vm) migration by decision package, the path that network data is undertaken by multiple physical network device forwarding can be shortened, reduce network equipment energy consumption, reduce propagation delay time, improve communication efficiency.
In technique scheme, preferably, see Fig. 5, step 206, specifically comprise: step 504: based in analysis result during virtual machine (vm) migration information needed carry out table lookup operation, if a certain item in hit table, then represent and meet the condition of migration strategy, when can move, the instruction can moved based on the migration action executing of this pointed is sent to performance element; Step 506: based on the execution result of performance element feedback, record moves successfully or failed information, and upgrades the current state of migration strategy; The operation of the current state of this renewal migration strategy, comprise: when receiving performance element Successful migration virtual machine when physical host meets the condition of migration strategy and feedback moves successful information, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, to receive when physical host does not meet the condition of migration strategy performance element at preset timed intervals interval how long attempt migration action success and feedback migration successful information time, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, receive performance element when physical host does not meet the condition of migration strategy at preset timed intervals interval how long attempt moving baulk and feedback migration failed information time, corresponding migration strategy is deleted, record migration strategy state is unsuccessfully, record failed daily record, and mail notification staff.In this technical scheme, by configuration and the state updating of migration strategy, networking forward-path can be shortened, reduce forwarded time delay, improve communication efficiency.
In technique scheme, preferably, see Fig. 6, step 208, specifically comprises: step 602: before performing the instruction of moving based on the migration action executing of a certain pointed, checks whether the object physical host moved to meets pre-conditioned; This is pre-conditioned comprises CPU, whether internal memory, disk, Internet resources are enough, and/or whether load transfinites; Step 604: when object physical host meets pre-conditioned, the migration of virtual machine is carried out in the instruction that the migration action executing based on a certain pointed moves; When object physical host does not meet pre-conditioned, then at interval of again attempting preset times after preset duration and the migration action of the instruction of moving based on the migration action executing of a certain pointed; Step 606: meet pre-conditioned at object physical host and carry out the migration success of virtual machine based on the instruction that the migration action executing of a certain pointed moves after, successful information feed back will be moved first to decision package; And/or, do not meet pre-conditioned at object physical host and again move successfully, again will move successful information feed back to decision package; And/or, do not meet pre-conditioned at object physical host and again move unsuccessfully, by information feed back failed for migration to decision package; Further, step 206, specifically also comprises: step 502: configuration emigration strategy, and by the migration strategy configured in advance of configuration in table; The condition of the corresponding migration strategy of each list item of table, and with the action of pointed migration strategy; The operation of this configuration emigration strategy, comprises configuration many migration strategys, and/or different but many strategies that migration action is identical of configuration emigration condition; Migration strategy has priority, if many migration strategys all meet transition condition, then carries out the migration action that the highest transition condition of priority is corresponding; Migration strategy comprises transition condition and migration action; Transition condition comprises the network traffics in the unit interval between two virtual machines, the number of communications in the unit interval between two virtual machines, certain virtual machine broadcast or multicast network flow in the unit interval; Migration action comprise in real time or in certain time period to meeting the virtual machine (vm) migration of transition condition to where, and by the multiple stage physical machine of the virtual machine (vm) migration to the same network segment that meet transition condition or same physical machine; Further, step 206: pre-configured virtual machine fetch strategy; Based on extracting gained information and pre-configured strategy in analysis result, determine the decision-making whether making virtual machine (vm) migration.In this technical scheme, can to the real-time monitoring of virtual machine network data, according to the migration strategy of monitor data and administrator configurations, realize the dynamic migration of virtual machine, reach raising resource utilization, reduce the resource consumption of physical network device, improve the object of communication efficiency.
Technical scheme of the present invention, provide a kind of virtual machine migration technology of data analysis Network Based, be specially in a kind of cloud computing system and carry out analyzing according to network data behaviour in service thus the technology making virtual machine (vm) migration (is namely analyzed virtual machine network data behaviour in service in cloud computing system, according to strategy, Autonomic Migration Framework virtual machine is to the technology of suitable object physical host), may be used in cloud computing system, improve communication efficiency, reduce resource consumption.In the inventive solutions, by the analysis to network data behaviour in service, problems of the prior art can be solved.
Technical scheme of the present invention, by the monitoring to virtual machine network data behaviour in service, collection, analysis, according to strategy, Autonomic Migration Framework virtual machine to suitable object physical host, thus avoids keeper's misoperation, reduce management workload, reduce O&M complicacy, improve O&M robotization, and reach raising resource utilization, reduce the resource consumption of physical network device, improve the object of communication efficiency.
Technical scheme of the present invention mainly comprises following unit:
(1) monitor collecting unit: the network data of turnover virtual machine is monitored, necessary information is extracted to network data, the information of collection is aggregated into network data analysis unit and further analyzes.
(2) analytic unit: the information of collection analyzed, extracts the information made a policy for decision package and issues decision package.
(3) decision package: the strategy of the information that decision package provides according to analytic unit and configured in advance, determines the decision-making whether making migration.
(4) performance element: the decision-making made according to decision package, performs actual migration action.
Such as, see Fig. 7, the workflow of technical solution of the present invention is described in detail as follows:
First be the configuration management of keeper to migration strategy.Keeper is configuration emigration strategy on decision package, article one, migration strategy comprises the migration action triggering condition and the execution of moving, trigger condition is used to the foundation determining whether to perform migration action, only meet the condition of pre-configured migration strategy in the result analyzed network data sended over analytic unit, the action of migration could be performed.The condition of migration strategy can be the network traffics in the unit interval between two virtual machines, ftp is such as used to transmit large files between two virtual machines, may also be the number of communications between two virtual machines in the unit interval, such as between two virtual machines carry out frequently data base read-write operation, also can be broadcast traffic of certain virtual machine etc.When the action of migration strategy moves if mainly comprising, by the virtual machine moved, and the object physical host moved to.Thus determine which platform virtual machine when where is moved to.Such as keeper can specify in morning 2:00-3:00 to the multiple stage physical host of the virtual machine (vm) migration to the same network segment that meet migration strategy condition, or on same physical host.
Migration strategy must carry out configured in advance by keeper on decision package.Keeper can configure many strategies, and every bar strategy has different priority, mates successively according to priority orders, if there is a tactful condition to be met, then perform corresponding action, if all policy conditions do not meet, then can not perform migration action.
Monitor collecting unit starts to monitor and gathers the network data of turnover virtual machine, and therefrom extracts key message, such as, extract the source IP of message, object IP, source MAC, object MAC, source TCP/UDP port numbers, object TCP/UDP port numbers, timestamp etc., is sent to analytic unit after gathering.
The summary information that analytic unit analysis collects, by analysis, extracts the information made a policy for decision package and sends to decision package.Data traffic, number of communications etc. that such as analytic unit can analyze sometime between section two virtual machines make a policy for decision package.
Decision package is made migration virtual machine according to the decision-making of keeper's configured in advance or is continued the decision of monitoring.If the network data of virtual machine meets the decision-making of configured in advance, then decision package notice performance element makes corresponding action, when is included in, and moves on which or which platform virtual machine to which or which platform physical machine.
Performance element performs the migration action that decision package sends over.Sometime by some or certain virtual machine (vm) migration in some or certain physical machine.
By above-mentioned steps, achieve the real-time monitoring to virtual machine network data, according to the migration strategy of monitor data and administrator configurations, realize the dynamic migration of virtual machine.
And for example, the specific implementation of technical solution of the present invention is as follows:
First, keeper's configuration emigration strategy on decision package.Decision package is formed primarily of table, the condition of the corresponding migration strategy of each list item of table, and with the action of pointed migration strategy.The migration strategy of administrator configurations by configured in advance in table.Decision package carries out table lookup operation to the input data that analytic unit sends, if a certain item in hit table, then represents the condition meeting migration strategy, can move, the migration action of this pointed can be handed down to performance element and perform migration.
Keeper can configure many migration strategys, also can different but many strategies that migration action is identical of configuration emigration condition.The migration strategy of configuration has priority, if the condition of many migration strategys is all satisfied, then carries out the migration action that the highest transition condition of priority is corresponding.
Migration strategy comprises transition condition and migration action.Transition condition can comprise the network traffics in the unit interval between two virtual machines, the number of communications in the unit interval between two virtual machines, certain virtual machine broadcast or multicast network flow etc. in the unit interval.Migration action can comprise in real time or in certain time period meeting the virtual machine (vm) migration of transition condition to where.Can by the multiple stage physical machine of the virtual machine (vm) migration to the same network segment that meet transition condition, or in same physical machine, thus shorten networking forward-path, reduce forwarded time delay, improve communication efficiency.
Second, realize monitor collecting unit function, this element needs to have the function of the network data of turnover virtual machine being carried out to collection analysis, and has the function to the data pick-up key message collected, here key message mainly refers to the content of TCP/IP header, such as the most frequently used source IP, object IP, source MAC, object MAC, source TCP/UDP port numbers, object TCP/UDP port numbers etc., and the message attribute information such as timestamp.These information package are sent to analytic unit by monitor collecting unit in batches.Therefore monitor collecting unit must can fast processing information, and the information gathered must be full and accurate.
3rd, Realization analysis Elementary Function, the key message of this element to the network data of the turnover virtual machine that collecting unit sends is analyzed, and then draw the input data made a policy for decision package, the data analysis that such as analytic unit can send according to collecting unit goes out has a large amount of data traffics to be sent to another virtual machine from a virtual machine in section sometime, or certain a section of time virtual machine receives the TCP connection of other a large amount of virtual machines, then these information can be sent to decision package by analytic unit, determine whether carry out virtual machine (vm) migration by decision package.
4th, realize performance element function, performance element mainly carries out final execution to the migration action that decision package issues, performance element can according to the migration action of decision package by virtual machine at the time-shift of specifying to certain physical host of specifying or multiple stage physical host.Before migration, performance element can check whether the object physical host moved to satisfies condition, whether such as CPU, internal memory, disk, Internet resources are enough, whether load transfinites etc., just can carry out the migration of virtual machine when physical host satisfies condition, and moves successfully and can inform decision package, decision package will record this time successful information of migration, and by corresponding migration strategy Disable, record migration strategy state is Success, shows that decision-making runs succeeded.If physical host condition does not meet, then performance element can every minor tick 30s, again attempt the action of 2 migrations, if run succeeded, then notify that decision package runs succeeded, and by corresponding migration strategy Disable, record migration strategy state is Success, if still cannot perform the action of migration, performance element can notify that decision package migration does not run succeeded.Decision package, also can by corresponding migration strategy Disable after receiving the failed notice of performance element migration, and record migration strategy state is Failure, records failed daily record, and notifies keeper by mail he.
By monitor collecting unit, the monitoring of turnover virtual-machine data and the collection of key message are extracted, with analytic unit, the information extracted is analyzed, decision package is according to the decision-making of predefined, the data of analysis are carried out decision-making, send the action allowing performance element specifically perform migration that performs an action, achieve the Autonomic Migration Framework of virtual machine, the network bandwidth and energy consumption are saved, reduce propagation delay time, raising business efficiency, transition process does not need manual intervention, improves O&M robotization, reduces business risk.
Compared with prior art, the Advantageous Effects that technical scheme of the present invention at least can obtain comprises:
(1) technical scheme of the present invention, by the monitoring to virtual machine network data, the network service between analyzing virtual machine, thus by dynamic migration of virtual machine on same network segment physical host or same physical host.Shorten the path that network data is undertaken by multiple physical network device forwarding, reduce network equipment energy consumption, reduce propagation delay time, improve communication efficiency, and whole transition process does not need manual intervention, reduce administration configuration workload, reduce the possibility of human operational error, reduce managing risk, realize robotization O&M.
(2) traditional virtual machine (vm) migration mode, needs manually to monitor virtual machine, analyze, and the manual migration completed virtual machine; Reason is complicated, and subjective factor is large, easy misjudgment, and operation is also easily slipped up, and also cannot realize the O&M of robotization.The method that technical scheme of the present invention provides achieves automatic monitoring virtual machine network data, automatically completes virtual machine (vm) migration, meets the demand of enterprise's O&M robotization, reduces enterprise energy consumption, improves business efficiency.
More than be described with reference to the accompanying drawings technical scheme of the present invention, considered in correlation technique there is no easy, the unified solution for complicated type metadata migration.Existing virtual machine (vm) migration cannot complete the virtual machine (vm) migration process that complicated type participates in.Therefore, the present invention proposes a kind of virtual machine (vm) migration device and a kind of virtual machine migration method, can on existing virtual machine (vm) migration mode basis, make full use of the virtual machine (vm) migration that single object type completes multi-object type, set up general, the unified migration thinking of the complex object class virtual machine (vm) migration that multi-object type participates in.
The foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, for a person skilled in the art, the present invention can have various modifications and variations.Within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. a virtual machine (vm) migration device, is characterized in that, comprising:
Monitor collecting unit, for monitoring the network data of turnover virtual machine, information needed during extraction virtual machine (vm) migration also gathers, and collection gained information is carried out gathering and issuing;
Analytic unit, for always gathering gained information based on the network data from turnover virtual machine and analyze, information needed issuing during virtual machine (vm) migration in extraction and analysis result;
Decision package, for based on extracting gained information and pre-configured strategy in analysis result, determines the decision-making whether making virtual machine (vm) migration;
Performance element, for according to the result of decision whether making virtual machine (vm) migration, performs actual virtual machine (vm) migration action.
2. virtual machine (vm) migration device according to claim 1, is characterized in that, described monitor collecting unit, specifically comprises:
Network Data Control module, for monitoring the network data of turnover virtual machine;
Information acquisition module, for extracting virtual machine (vm) migration information needed in the network data from turnover virtual machine; This virtual machine (vm) migration information needed, comprises source IP, the object IP of message, source MAC, object MAC, source TCP/UDP port numbers, object TCP/UDP port numbers and timestamp;
Information summarizing module, issues after the virtual machine (vm) migration information needed of extraction being gathered.
3. virtual machine (vm) migration device according to claim 1 and 2, is characterized in that, described analytic unit, specifically comprises:
Information analysis module, for analyzing the virtual machine (vm) migration information needed extracted;
Information extraction modules, for information needed during virtual machine (vm) migration in extraction and analysis result; Information needed during virtual machine (vm) migration in this analysis result, comprises in preset time period and has the data traffic of predetermined amount to be sent to another virtual machine from a virtual machine, or the TCP that predetermined time respective virtual machine accepts other virtual machine of respective amount connects;
Information sending module, for will extract information package after, send in batches.
4. virtual machine (vm) migration device according to claim 1 and 2, is characterized in that, described decision package, specifically comprises:
Migration decision-making module, for based in analysis result during virtual machine (vm) migration information needed carry out table lookup operation, if a certain item in hit table, then represent the condition meeting migration strategy, when can move, the instruction can moved based on the migration action executing of this pointed is sent to performance element;
Feedback information processing module, for the execution result fed back based on performance element, record moves successfully or failed information, and upgrades the current state of migration strategy;
The operation of the current state of this renewal migration strategy, comprise: when receiving performance element Successful migration virtual machine when physical host meets the condition of migration strategy and feedback moves successful information, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, to receive when physical host does not meet the condition of migration strategy performance element at preset timed intervals interval how long attempt migration action success and feedback migration successful information time, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, receive performance element when physical host does not meet the condition of migration strategy at preset timed intervals interval how long attempt moving baulk and feedback migration failed information time, corresponding migration strategy is deleted, record migration strategy state is unsuccessfully, record failed daily record, and mail notification staff.
5. virtual machine (vm) migration device according to claim 4, is characterized in that, described performance element, specifically comprises:
Object physical host checking module, for before performing the instruction of moving based on the migration action executing of a certain pointed, checks whether the object physical host moved to meets pre-conditioned; This is pre-conditioned comprises CPU, whether internal memory, disk, Internet resources are enough, and/or whether load transfinites;
Virtual machine (vm) migration module, for when object physical host meets pre-conditioned, the migration of virtual machine is carried out in the instruction that the migration action executing based on a certain pointed moves; When object physical host does not meet pre-conditioned, then at interval of again attempting preset times after preset duration and the migration action of the instruction of moving based on the migration action executing of a certain pointed;
Migration information feedback module, for meeting at object physical host pre-conditioned and carry out the migration success of virtual machine based on the instruction that the migration action executing of a certain pointed moves after, moving successful information feed back first to decision package; And/or, do not meet pre-conditioned at object physical host and again move successfully, again will move successful information feed back to decision package; And/or, do not meet pre-conditioned at object physical host and again move unsuccessfully, by information feed back failed for migration to decision package;
Further,
Described decision package, specifically also comprises:
Migration strategy configuration module, for configuration emigration strategy, and by the migration strategy configured in advance of configuration in table; The condition of the corresponding migration strategy of each list item of table, and with the action of pointed migration strategy; The operation of this configuration emigration strategy, comprises configuration many migration strategys, and/or different but many strategies that migration action is identical of configuration emigration condition;
Described migration strategy has priority, if many migration strategys all meet transition condition, then carries out the migration action that the highest transition condition of priority is corresponding; Described migration strategy comprises transition condition and migration action; Described transition condition comprises the network traffics in the unit interval between two virtual machines, the number of communications in the unit interval between two virtual machines, certain virtual machine broadcast or multicast network flow in the unit interval; Described migration action comprise in real time or in certain time period to meeting the virtual machine (vm) migration of transition condition to where, and by the multiple stage physical machine of the virtual machine (vm) migration to the same network segment that meet transition condition or same physical machine;
Further,
Described decision package, for pre-configured virtual machine fetch strategy; Based on extracting gained information and pre-configured strategy in analysis result, determine the decision-making whether making virtual machine (vm) migration.
6. a virtual machine migration method, is characterized in that, comprising:
Step 202: the network data of turnover virtual machine is monitored, information needed during extraction virtual machine (vm) migration also gathers, and collection gained information is carried out gathering and issuing;
Step 204: always gather gained information based on the network data from turnover virtual machine and analyze, information needed issuing during virtual machine (vm) migration in extraction and analysis result;
Step 206: based on extracting gained information and pre-configured strategy in analysis result, determines the decision-making whether making virtual machine (vm) migration;
Step 208: according to the result of decision whether making virtual machine (vm) migration, perform actual virtual machine (vm) migration action.
7. virtual machine migration method according to claim 6, is characterized in that, described step 202, specifically comprises:
Step 302: the network data of monitoring turnover virtual machine;
Step 304: extract virtual machine (vm) migration information needed from the network data of turnover virtual machine; This virtual machine (vm) migration information needed, comprises source IP, the object IP of message, source MAC, object MAC, source TCP/UDP port numbers, object TCP/UDP port numbers and timestamp;
Step 306: issue after the virtual machine (vm) migration information needed of extraction is gathered.
8. the virtual machine migration method according to claim 6 or 7, is characterized in that, described step 204, specifically comprises:
Step 402: the virtual machine (vm) migration information needed extracted is analyzed;
Step 404: information needed during virtual machine (vm) migration in extraction and analysis result; Information needed during virtual machine (vm) migration in this analysis result, comprises in preset time period and has the data traffic of predetermined amount to be sent to another virtual machine from a virtual machine, or the TCP that predetermined time respective virtual machine accepts other virtual machine of respective amount connects;
Step 406: after the information package of extraction, in batches send.
9. the virtual machine migration method according to claim 6 or 7, is characterized in that, described step 206, specifically comprises:
Step 504: based in analysis result during virtual machine (vm) migration information needed carry out table lookup operation, if a certain item in hit table, then represent the condition meeting migration strategy, when can move, the instruction can moved based on the migration action executing of this pointed is sent to performance element;
Step 506: based on the execution result of performance element feedback, record moves successfully or failed information, and upgrades the current state of migration strategy;
The operation of the current state of this renewal migration strategy, comprise: when receiving performance element Successful migration virtual machine when physical host meets the condition of migration strategy and feedback moves successful information, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, to receive when physical host does not meet the condition of migration strategy performance element at preset timed intervals interval how long attempt migration action success and feedback migration successful information time, deleted by corresponding migration strategy, record migration strategy state is successfully; And/or, receive performance element when physical host does not meet the condition of migration strategy at preset timed intervals interval how long attempt moving baulk and feedback migration failed information time, corresponding migration strategy is deleted, record migration strategy state is unsuccessfully, record failed daily record, and mail notification staff.
10. virtual machine migration method according to claim 9, is characterized in that, described step 208, specifically comprises:
Step 602: before performing the instruction of moving based on the migration action executing of a certain pointed, checks whether the object physical host moved to meets pre-conditioned; This is pre-conditioned comprises CPU, whether internal memory, disk, Internet resources are enough, and/or whether load transfinites;
Step 604: when object physical host meets pre-conditioned, the migration of virtual machine is carried out in the instruction that the migration action executing based on a certain pointed moves; When object physical host does not meet pre-conditioned, then at interval of again attempting preset times after preset duration and the migration action of the instruction of moving based on the migration action executing of a certain pointed;
Step 606: meet pre-conditioned at object physical host and carry out the migration success of virtual machine based on the instruction that the migration action executing of a certain pointed moves after, successful information feed back will be moved first to decision package; And/or, do not meet pre-conditioned at object physical host and again move successfully, again will move successful information feed back to decision package; And/or, do not meet pre-conditioned at object physical host and again move unsuccessfully, by information feed back failed for migration to decision package;
Further,
Described step 206, specifically also comprises:
Step 502: configuration emigration strategy, and by the migration strategy configured in advance of configuration in table; The condition of the corresponding migration strategy of each list item of table, and with the action of pointed migration strategy; The operation of this configuration emigration strategy, comprises configuration many migration strategys, and/or different but many strategies that migration action is identical of configuration emigration condition;
Described migration strategy has priority, if many migration strategys all meet transition condition, then carries out the migration action that the highest transition condition of priority is corresponding; Described migration strategy comprises transition condition and migration action; Described transition condition comprises the network traffics in the unit interval between two virtual machines, the number of communications in the unit interval between two virtual machines, certain virtual machine broadcast or multicast network flow in the unit interval; Described migration action comprise in real time or in certain time period to meeting the virtual machine (vm) migration of transition condition to where, and by the multiple stage physical machine of the virtual machine (vm) migration to the same network segment that meet transition condition or same physical machine;
Further,
Described step 206: pre-configured virtual machine fetch strategy; Based on extracting gained information and pre-configured strategy in analysis result, determine the decision-making whether making virtual machine (vm) migration.
CN201510521724.5A 2015-08-24 2015-08-24 Virtual machine migration device and method Pending CN105117280A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510521724.5A CN105117280A (en) 2015-08-24 2015-08-24 Virtual machine migration device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510521724.5A CN105117280A (en) 2015-08-24 2015-08-24 Virtual machine migration device and method

Publications (1)

Publication Number Publication Date
CN105117280A true CN105117280A (en) 2015-12-02

Family

ID=54665281

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510521724.5A Pending CN105117280A (en) 2015-08-24 2015-08-24 Virtual machine migration device and method

Country Status (1)

Country Link
CN (1) CN105117280A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170109832A (en) * 2016-03-22 2017-10-10 삼성전자주식회사 An apparatus for relocating virtual machines and method thereof
CN107426012A (en) * 2017-05-27 2017-12-01 深信服科技股份有限公司 A kind of fault recovery method and its device based on super fusion architecture
CN108009002A (en) * 2017-11-29 2018-05-08 顺丰科技有限公司 A kind of live migration of virtual machine method, apparatus, equipment and storage medium
CN109783199A (en) * 2019-03-28 2019-05-21 浪潮商用机器有限公司 A kind of virtual machine migration method and device
CN112506648A (en) * 2020-11-20 2021-03-16 鹏城实验室 Traffic stateless migration method of virtual network function instance and electronic equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101739287A (en) * 2008-11-13 2010-06-16 国际商业机器公司 Device, system and method for managing virtual machines
CN101876921A (en) * 2009-04-29 2010-11-03 华为技术有限公司 Method, device and system for migration decision-making of virtual machine
CN102082692A (en) * 2011-01-24 2011-06-01 华为技术有限公司 Method and equipment for migrating virtual machines based on network data flow direction, and cluster system
CN103095821A (en) * 2013-01-05 2013-05-08 国都兴业信息审计系统技术(北京)有限公司 Continuous auditing system based on virtual machine migration recognition

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101739287A (en) * 2008-11-13 2010-06-16 国际商业机器公司 Device, system and method for managing virtual machines
CN101876921A (en) * 2009-04-29 2010-11-03 华为技术有限公司 Method, device and system for migration decision-making of virtual machine
CN102082692A (en) * 2011-01-24 2011-06-01 华为技术有限公司 Method and equipment for migrating virtual machines based on network data flow direction, and cluster system
CN103095821A (en) * 2013-01-05 2013-05-08 国都兴业信息审计系统技术(北京)有限公司 Continuous auditing system based on virtual machine migration recognition

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170109832A (en) * 2016-03-22 2017-10-10 삼성전자주식회사 An apparatus for relocating virtual machines and method thereof
KR102532641B1 (en) 2016-03-22 2023-05-15 삼성전자 주식회사 An apparatus for relocating virtual machines and method thereof
CN107426012A (en) * 2017-05-27 2017-12-01 深信服科技股份有限公司 A kind of fault recovery method and its device based on super fusion architecture
CN107426012B (en) * 2017-05-27 2020-06-09 深信服科技股份有限公司 Fault recovery method and device based on super-fusion architecture
CN108009002A (en) * 2017-11-29 2018-05-08 顺丰科技有限公司 A kind of live migration of virtual machine method, apparatus, equipment and storage medium
CN109783199A (en) * 2019-03-28 2019-05-21 浪潮商用机器有限公司 A kind of virtual machine migration method and device
CN112506648A (en) * 2020-11-20 2021-03-16 鹏城实验室 Traffic stateless migration method of virtual network function instance and electronic equipment
CN112506648B (en) * 2020-11-20 2022-05-03 鹏城实验室 Traffic stateless migration method of virtual network function instance and electronic equipment

Similar Documents

Publication Publication Date Title
US11700303B1 (en) Distributed data analysis for streaming data sources
CN103152352B (en) A kind of perfect information security forensics monitor method based on cloud computing environment and system
CN105117280A (en) Virtual machine migration device and method
CN104639374B (en) A kind of application deployment management system
CN104901838B (en) Enterprise network security event management system and its method
CN107508722B (en) Service monitoring method and device
US8892737B2 (en) Network sniffer for performing service level management
US7693996B2 (en) Service level management system
CN100365975C (en) Delivering system of webpage information of internet
CN107547589A (en) A kind of data acquisition treatment method and device
CN102891873A (en) Method for storing log data and log data storage system
CN103546343B (en) The network traffics methods of exhibiting of network traffic analysis system and system
CN106202444A (en) A kind of implementation method of data base's O&M monitoring
CN106612199A (en) Network monitoring data collection and analysis system and method
CN102497427A (en) Method and device for realizing data acquisition services of renewable energy source monitoring system
KR101357135B1 (en) Apparatus for Collecting Log Information
CN108924007A (en) The big data acquisition of communication operation information and storage system and method
CN102902615A (en) Failure alarm method and system for Lustre parallel file system
CN106603319A (en) Fault processing method, management server, and logic server
CN109800133A (en) A kind of method, one-stop monitoring alarm platform and the system of unified monitoring alarm
CN105512000A (en) Method and device for collecting abnormal information of operating system, and computer
CN109714208A (en) A kind of equipment is included in method, storage medium and the electronic equipment of network management
EP2645631A2 (en) A method and a system for automating an enterprise network optimization
CN114615013B (en) Comprehensive auditing method and system for network shooting range
WO2013166784A1 (en) Device and method for automatically performing configuration management by policy

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151202

RJ01 Rejection of invention patent application after publication