CN105022901A - Rapid generation system for railway transportation oriented equipment loading and strengthening scheme - Google Patents

Rapid generation system for railway transportation oriented equipment loading and strengthening scheme Download PDF

Info

Publication number
CN105022901A
CN105022901A CN201510515317.3A CN201510515317A CN105022901A CN 105022901 A CN105022901 A CN 105022901A CN 201510515317 A CN201510515317 A CN 201510515317A CN 105022901 A CN105022901 A CN 105022901A
Authority
CN
China
Prior art keywords
equipment
module
scheme
loading
transportation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510515317.3A
Other languages
Chinese (zh)
Inventor
杜淑幸
吴启俊
丁永亮
崔佳姗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xidian University
Original Assignee
Xidian University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xidian University filed Critical Xidian University
Priority to CN201510515317.3A priority Critical patent/CN105022901A/en
Publication of CN105022901A publication Critical patent/CN105022901A/en
Pending legal-status Critical Current

Links

Landscapes

  • Train Traffic Observation, Control, And Security (AREA)

Abstract

The invention discloses a rapid generation system for a railway transportation oriented equipment loading and strengthening scheme The system comprises a welcome interface module, a scheme generation module, a historical scheme module, a scheme management module, a user management module, an over-limit test module and a help information module. The system can substantially improve the equipment loading and transporting efficiency of railway transportation and reasonable use of vehicle resources, effectively solves the problems of non-standard generation of schemes for daily equipment railway transportation, low efficiency and poor reusability due to multiple equipment models, large quantity of constitutional units and unfixed transportation units, greatly shortens the traffic transportation preparation time for equipment railway transportation, saves locomotive resources and improves the mobile support capability effectively.

Description

Equipment towards transportation by railroad loads and Scheme of Strengthening quick-speed generation system
Technical field
The present invention relates to rail transportation system, the equipment be specially towards transportation by railroad loads and Scheme of Strengthening quick-speed generation system.
Background technology
Transportation by railroad is the Main Means of large-scale, a large amount of equipment long distance fast reserve transfer.But because transportation equipment model is many, component units quantity is large, unit forms complex structure, delivery unit is not fixed, the generation that always there is loading and Scheme of Strengthening is lack of standardization, ageing low, the technical matters such as reusability is poor.
Summary of the invention
The equipment towards transportation by railroad is the object of the present invention is to provide to load and reinforce quick-speed generation system, utilize friendly interactive interface, for user provides the equipment optimization loading pattern of multiple hommization, and adopt intelligent loading technology, generate transportation by railroad loading and Scheme of Strengthening quickly and efficiently, real-time outputting standard pattern.
The present invention is by the following technical solutions for achieving the above object:
Equipment towards transportation by railroad loads and Scheme of Strengthening quick-speed generation system, comprise and welcome interface module, schemes generation module, history scheme module, project management module, user management module, the test module that transfinites, help information module, welcome interface module to be used for doing each functional module function and operation simply introducing explanation; Schemes generation module is used for, to the various shipments changes occurred in equipment transportation by railroad loading, for user provides the very strong schemes generation function of adaptability, meeting the different loading demand of user; History scheme module, for preserving and manage the equipment Alternatives-carriers For Submarine generated in the past, is conveniently checked, and can recall use existing program;
Project management module is used for the management of all equipments in system, equipment unit, and all equipments and equipment unit are all by this interface typing and management; User management module, for setting keeper, user of service to the different rights of Dynamic System, realizes the registration of user, interpolation, the setting of deletion password and amendment; Transfinite three grade the transfinite standards of test module for passing through according to railway tunnel vehicle safety, carries out overrun testing, to ensure the safety of train driving to loading equipment.
As the further scheme of the present invention, described schemes generation module is the approach that user provides that three kinds generate equipment transportation by railroad loading pattern, that standard mode is loaded, the way of recommendation is loaded and artificial selection is loaded respectively, the all corresponding different loading strategy of each load mode, needs for different loadings.
As the further scheme of the present invention, described project management module is in order to reduce the switching times in interface, equipment, equipment unit concentrate on several districts at same interface, realize the inquiry of equipment and equipment unit, interpolation, deletion, amendment, Refresh Data multiple function respectively, click the function buttons such as inquiry, interpolation, deletion, amendment, system can cut corresponding function interface.
As the further scheme of the present invention, described in transfinite test module each schemes generation time automatically carry out overrun testing, comprise width overrun and detect and height overrun testing, report is not transfinited, and warning has transfinites or seriously transfinite.
As the further scheme of the present invention, described history scheme module, for preserving and manage the equipment Alternatives-carriers For Submarine generated in the past, improves the utilization ratio of loading pattern; Except standard mode loading pattern, all can inquire whether user preserves the program for way of recommendation loading and artificial selection loading pattern system, if preserve, system can call history scheme database, automatically records load mode, equipment and unit title, AutoCAD figure, dimensional data and WORD specification documents.
The invention has the beneficial effects as follows: this system can significantly the shipment efficiency of hoisting device transportation by railroad and the reasonable employment of vehicle resources, effective solution is because equipment model is many, component units quantity large, delivery unit is not fixed, the problem that daily equipment transportation by railroad schemes generation is lack of standardization, efficiency is low and reusability is poor, that greatly shortens equipment transportation by railroad ships setup time, save Locomotive Resource, effectively improve the motor-driven supportability of equipment.
Accompanying drawing explanation
Fig. 1 is present system composition frame chart.
Embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is further elaborated.
As shown in Figure 1, equipment towards transportation by railroad loads and Scheme of Strengthening quick-speed generation system, comprise and welcome interface module, schemes generation module, history scheme module, project management module, user management module, the test module that transfinites, help information module, welcome interface module to be used for doing each functional module function and operation simply introducing explanation; Schemes generation module is used for the various shipments changes to occurring in equipment transportation by railroad loading, for user provides the very strong schemes generation function of adaptability, and the demand that the difference meeting user is loaded; History scheme module, for preserving and manage the equipment Alternatives-carriers For Submarine generated in the past, is conveniently checked, and can recall use existing program; Except standard mode loading pattern, all can inquire whether user preserves the program for way of recommendation loading and artificial selection loading pattern system, if preserve, system can call history scheme database, automatic record load mode, equipment and unit title, AutoCAD figure, dimensional data and WORD specification documents etc., this is that follow-up use brings conveniently, improves efficiency of loading;
Project management module is used for the management of all equipments in system, equipment unit, and all equipments and equipment unit are all by this interface typing and management; User management module, for setting keeper, user of service to the different rights of Dynamic System, realizes the registration of user, interpolation, the setting of deletion password and amendment; Project management module is in order to reduce the switching times in interface, equipment, equipment unit concentrate on several districts at same interface, realize the inquiry of equipment and equipment unit, interpolation, deletion, amendment, Refresh Data multiple function respectively, click inquiry, interpolation, deletion, modify feature button, system can cut corresponding function interface.
Transfinite three grade the transfinite standards of test module for passing through according to railway tunnel vehicle safety, overrun testing is carried out to loading equipment, to ensure the safety of train driving, automatically overrun testing is completed during each schemes generation of the test module that transfinites, comprise width overrun to detect and height overrun testing, report is not transfinited, and warning has transfinites or seriously transfinite.
Schemes generation module is the approach that user provides that three kinds generate equipment transportation by railroad loading pattern, that standard mode is loaded, the way of recommendation is loaded and artificial selection is loaded respectively, the all corresponding different loading strategy of each load mode, needs for different loadings.
Standard load mode is optimized for the said units of complete equipment the transportation by railroad loading pattern distributing and combine and obtain.Usual equipment production unit can provide single model to equip the loading assigned references of said units, when utilizing " equipment towards transportation by railroad loads and Scheme of Strengthening quick-speed generation system " to generate outfit traffic program, generally, can prioritizing selection standard mode.If the standard mode of have selected, system first can from standard scheme storehouse, search coupling is carried out to all unit loading transport that needs, the match is successful, system extracts all unit informations matched from database, as the view of correspondence, lantern slide and corresponding dimensional data etc., and confirms for user at the magic lantern of interactive window display equipment and same data message, in this interface, also can carry out the amendment of supplemental characteristic with reference to loading magic lantern.Click " opening CAD figure " button, program just loads AutoCAD automatically, and carry out Parametric drive via the program of AutoLISP secondary development, this process is mainly reflected in the loading of segment, parameterized equipment and equipment unit three-view diagram automatic pattern location, automatically intended size, Auto dimension.If physical size needs amendment, internal system can use thread dispatching AutoCAD application program, real-time size is stored by adding temporary table when preview scheme, call AutoLISP to be again filled up in CAD drawing file by the dimensional data be stored in temporary table, the parametrization realizing size is revised automatically.All complete, and user only needs under AutoCAD, click the CAD graphic scheme of preserving or printing formation.Can return parent window subsequently to select to click " opening specification documents ", program can load the specification documents that Microsoftword forms loading pattern automatically, confirms to print just to complete whole schemes generation.
Load mode is recommended to be the optimization suggested design adopted for the combined shipment of polytypic equipment unit.The element number of polytypic equipment is many, system can carry out Automatic Optimal combo to the unit of the unit of polytypic equipment or non-outfit, unit after automatic marshalling adheres to the unit of different equipment separately, form resource and use minimum marshalling, and preferentially in history scheme, search coupling generates used reference scheme before.To the equipment assembly unit not having in storehouse to mate, by program extraction unit segment in unit figure database, the information such as size, carry out analytical calculation, show that the volume coordinate of unit in three-view diagram puts parameter according to the actual structure parameters of load units, then, program loads AutoCAD automatically, and carry out Parametric drive by the program of AutoLISP secondary development, complete the automatic loading of unit segment, the parametrization automatic pattern location of equipment unit three-view diagram on two-dimentional locomotive, automatic intended size, Auto dimension, finally form the CAD figure recommending load mode.All complete, user only needs under AutoCAD, click the CAD graphic scheme of preserving or printing formation, then return parent window to select to click " opening specification documents ", program can load the specification documents that Microsoft word forms loading pattern automatically, confirms to print just to complete whole schemes generation.
By the transportation by railroad scheme of the new combo unit of Program Generating, history scheme can be become stored in history scheme base after preserving, select for loading later.Recommend load mode use when Multiple Type equipment needs transportation by railroad simultaneously best.
Artificial selection load mode according to the marshalling hope of user to load units, can be carried out the loading pattern of designating unit combo voluntarily by user.It is exactly that user selects all unit of equipment needing transport first voluntarily in bezel, cluster that artificial selection is loaded, then manual type is clicked, in new window interface, go out to represent the lantern slide of each unit, user just in visualization interface, can pull the lantern slide mouse of the expression equipment unit for loading into combo loading frame.Once manually unit be pulled into the loading frame of same locomotive flat board, whether system automatic measurement & calculation exceeds locomotive overall length and width, and points out in time.If transfinited, user can destruction operation, again chooses; If met, system is the information such as extraction unit segment, size in load units graphic data base automatically, then automatically AutoCAD is loaded, and carry out Parametric drive by the program of AutoLISP secondary development, complete parametrization automatic pattern location, automatically intended size, the Auto dimension in the loading of unit segment, equipment unit three-view diagram two dimension locomotive, finally form the CAD figure under artificial loading mode.All complete, user only needs under AutoCAD, click the CAD graphic scheme of preserving or printing formation, then return parent window to select to click " opening specification documents ", program can load the specification documents that Microsoft word forms loading pattern automatically, confirm to print and just complete whole schemes generation, the transportation by railroad scheme of the new combo unit of process generation thus, also can become history scheme for selecting later after preserving.
In addition, under each loading pattern, all allow user in visual dialog box, contrast physical size and carry out corresponding size and redefine, and then control the location dimension of assembling.In modification of dimension process, system error detection function, to ensure that the size conforms locomotive revised requires the wide high limit with tunnel, amended size parameterisable drives the generation of CAD figure simultaneously.
The present invention loads and Scheme of Strengthening quick-speed generation system towards the equipment of transportation by railroad:
(1) interfacing between C# language program and AutoCAD2010 mapping software, AutoLisp list processing language, SQLServer2008 R2 database, Microsoft office word and data transmission problems is solved.For user designs friendly Dynamic System and administration interface, the system user of making really can realize user's multiwindow flexibly, easily, multitask switches visual Dynamic System.
(2) use AutoLisp language as the secondary development tool of AutoCAD2010 drawing application software, realize parametric drafting and the driving of AutoCAD figure.Utilize parametric technology to solve automatic pattern location, automatically intended size, the Auto dimension of equipment cell view, and the parametrization of size revise problem automatically.
(3) due to equipment and unit is numerous and diverse, assembling scheme is flexible, data for information such as equipment cell view and parameter etc. store, construct different graphic data bases to meet system to difference equipment and different demand of equipping cell view and parameter extraction, solve the problem of exchanges data and storage when equipment is non-standard to be loaded.
(4) in reality, transportation equipment and unit can not be completely fixed, and need optimization to load in mixture, have employed optimized algorithm, solve the problem of loading combo optimization and rapid creation of project to this system during the transport simultaneously of polytypic equipment.Combo optimized algorithm carries out searching of optimal matching based on locomotive space, delivery unit characteristic (quality, volume, form and particular/special requirement), best of breed between quick formation load units, improves the formation efficiency of the level of resources utilization and loading pattern.
(5) the automatic test problems of equipment overrun condition is solved.System sets up the database of overrun testing, and open the CAD three-view diagram drawing of generation user before, system carries out height to each loading equipment automatically, wide correspondence transfinites test, and reports testing result.Warning is proposed to out-of-range equipment, ensures the safety of train driving.
By facts have proved, this system works is stablized, friendly interface, simple to operation, perfect in shape and function, schemes generation mode is flexible, speed is fast, automaticity is high, generation scheme key element is complete, format specification, particularly when polytypic equipment promptly transports, use this project invention work efficiency to increase substantially at double, the more efficiency of unit is more obvious.
Obviously, embodiment described above is only the present invention's part embodiment, instead of whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtained under creative work prerequisite, belong to the scope of protection of the invention.

Claims (5)

1. the equipment towards transportation by railroad loads and Scheme of Strengthening quick-speed generation system, it is characterized in that, comprise and welcome interface module, schemes generation module, history scheme module, project management module, user management module, the test module that transfinites, help information module, welcome interface module to be used for doing each functional module function and operation simply introducing explanation; Schemes generation module is used for, to the various shipments changes occurred in equipment transportation by railroad loading, for user provides the very strong schemes generation function of adaptability, meeting the different loading demand of user; History scheme module, for preserving and manage the equipment Alternatives-carriers For Submarine generated in the past, is conveniently checked, and can recall use existing program;
Project management module is used for the management of all equipments in system, equipment unit, and all equipments and equipment unit are all by this interface typing and management; User management module, for setting keeper, user of service to the different rights of Dynamic System, realizes the registration of user, interpolation, the setting of deletion password and amendment; Transfinite three grade the transfinite standards of test module for passing through according to railway tunnel vehicle safety, carries out overrun testing, to ensure the safety of train driving to loading equipment.
2. the equipment towards transportation by railroad according to claim 1 loads and Scheme of Strengthening quick-speed generation system, it is characterized in that, described schemes generation module is the approach that user provides that three kinds generate equipment transportation by railroad loading pattern, that standard mode is loaded, the way of recommendation is loaded and artificial selection is loaded respectively, the all corresponding different loading strategy of each load mode, needs for different loadings.
3. the equipment towards transportation by railroad according to claim 1 loads and Scheme of Strengthening quick-speed generation system, it is characterized in that, described project management module is in order to reduce the switching times in interface, equipment, equipment unit concentrate on several districts at same interface, realize the inquiry of equipment and equipment unit, interpolation, deletion, amendment, Refresh Data multiple function respectively, click
Inquiry, interpolation, deletion, modify feature button, system can cut corresponding function interface.
4. the equipment towards transportation by railroad according to claim 1 loads and Scheme of Strengthening quick-speed generation system, it is characterized in that, automatically overrun testing is carried out during each schemes generation of the described test module that transfinites, comprise width overrun to detect and height overrun testing, report is not transfinited, and warning has transfinites or seriously transfinite.
5. the equipment towards transportation by railroad according to claim 1 loads and Scheme of Strengthening quick-speed generation system, it is characterized in that, described history scheme module is for preserving and manage the equipment Alternatives-carriers For Submarine generated in the past, except standard mode loading pattern, all can inquire whether user preserves the program for way of recommendation loading and artificial selection loading pattern system, if preserve, system can call history scheme database, automatically records load mode, equipment and unit title, AutoCAD figure, dimensional data and WORD specification documents.
CN201510515317.3A 2015-08-20 2015-08-20 Rapid generation system for railway transportation oriented equipment loading and strengthening scheme Pending CN105022901A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510515317.3A CN105022901A (en) 2015-08-20 2015-08-20 Rapid generation system for railway transportation oriented equipment loading and strengthening scheme

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510515317.3A CN105022901A (en) 2015-08-20 2015-08-20 Rapid generation system for railway transportation oriented equipment loading and strengthening scheme

Publications (1)

Publication Number Publication Date
CN105022901A true CN105022901A (en) 2015-11-04

Family

ID=54412868

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510515317.3A Pending CN105022901A (en) 2015-08-20 2015-08-20 Rapid generation system for railway transportation oriented equipment loading and strengthening scheme

Country Status (1)

Country Link
CN (1) CN105022901A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110029832A (en) * 2019-05-29 2019-07-19 江苏工程职业技术学院 A kind of concrete structure reinforcement scheme generation method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080255818A1 (en) * 2007-04-11 2008-10-16 Jefferson Stanley T Test System Design Tool With Model-Based Tool Support

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080255818A1 (en) * 2007-04-11 2008-10-16 Jefferson Stanley T Test System Design Tool With Model-Based Tool Support

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
李笑红: "铁路货物装载加固方案评估方法的研究", 《铁道学报》 *
王花兰: "铁路阔大货物装载加固方案比选方法的研究", 《兰州铁道学院学报(自然科学版)》 *
管利众 等: "雷达装备铁路运输装载及加固方案快速生成系统的设计", 《电子技术与软件工程》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110029832A (en) * 2019-05-29 2019-07-19 江苏工程职业技术学院 A kind of concrete structure reinforcement scheme generation method

Similar Documents

Publication Publication Date Title
CN107292003B (en) Automatic generation method of power grid station wiring diagram
CN101483342A (en) Geographical information system used for electric system
WO2016165321A1 (en) Method and apparatus for establishing requirement meta model for high-speed train
CN103309988A (en) Method for automatically generating rail traffic line database
CN109491735B (en) Integrated data generation and verification integrated monitoring human-computer interface configuration implementation method
CN114186984B (en) Two-dimensional and three-dimensional integrated collaborative design system for architectural design enterprise
CN102289548A (en) Automatic distribution network diagram to single line diagram conversion method based on AutoCAD
CN110263076B (en) Method for automatically generating data analysis report
CN103927185A (en) Network topology modeling device based on energy management and guiding method thereof
CN110334911A (en) A kind of method of management of production line and system
CN104166549A (en) Meteorological element contour surface analysis platform and construction method
CN104376508A (en) Automatic network distribution production first-aid repair message power grid system and method
CN104376415A (en) Cable book management system
CN107436785B (en) Revit software information interaction system and interaction method based on information system
CN115393560A (en) BIM model drawing marking method, device, equipment and readable storage medium
CN101697275B (en) System for issuing passenger information
CN101625712A (en) Computer plotting system and computer plotting method for making signssigns
CN104881739A (en) Marketing and distribution data consistency verification method based on IEC61970-61968 CIM standard
CN113642850A (en) Data fusion method and terminal for power distribution network planning
CN108681888B (en) Remanufacturing-oriented manufacturing execution system for whole process flow
CN114299743A (en) Three-dimensional operation monitoring system for urban rail transit
CN105022901A (en) Rapid generation system for railway transportation oriented equipment loading and strengthening scheme
CN104616099A (en) Power grid tide data comparison and analysis graphic display method
WO2016165317A1 (en) Method and apparatus for establishing high-speed train demand data instances
CN111784192A (en) Industrial park emergency plan executable system based on dynamic evolution

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151104

RJ01 Rejection of invention patent application after publication