CN104836858B - A kind of electronic regulation system of support team's cooperation - Google Patents

A kind of electronic regulation system of support team's cooperation Download PDF

Info

Publication number
CN104836858B
CN104836858B CN201510246212.2A CN201510246212A CN104836858B CN 104836858 B CN104836858 B CN 104836858B CN 201510246212 A CN201510246212 A CN 201510246212A CN 104836858 B CN104836858 B CN 104836858B
Authority
CN
China
Prior art keywords
power plant
server
client
regulation
eps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510246212.2A
Other languages
Chinese (zh)
Other versions
CN104836858A (en
Inventor
宋霏
潘嘉杰
王宇帆
张淑慧
喻文竹
蒋翔
皋琴
李志忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Shen Nuclear Energy Engineering Technology Co ltd
Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Original Assignee
Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Nuclear Engineering Research and Design Institute Co Ltd filed Critical Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Priority to CN201510246212.2A priority Critical patent/CN104836858B/en
Publication of CN104836858A publication Critical patent/CN104836858A/en
Application granted granted Critical
Publication of CN104836858B publication Critical patent/CN104836858B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/12Protocols specially adapted for proprietary or special-purpose networking environments, e.g. medical networks, sensor networks, networks in vehicles or remote metering networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/02Protocols based on web technology, e.g. hypertext transfer protocol [HTTP]
    • H04L67/025Protocols based on web technology, e.g. hypertext transfer protocol [HTTP] for remote control or remote monitoring of applications
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L51/00User-to-user messaging in packet-switching networks, transmitted according to store-and-forward or real-time protocols, e.g. e-mail
    • H04L51/04Real-time or near real-time messaging, e.g. instant messaging [IM]
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Signal Processing (AREA)
  • Strategic Management (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Game Theory and Decision Science (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Computing Systems (AREA)
  • General Health & Medical Sciences (AREA)
  • Medical Informatics (AREA)
  • Testing And Monitoring For Control Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of electronic regulation system of support team cooperation, including power plant's instrument control network system and power plant's LAN system, power plant's instrument control network system and power plant's LAN system form a T-EPS system;Power plant's instrument control network system and power plant's LAN system pass through unidirectional gateway communication;The T-EPS system is made of multiple client-servers;The server is constituted by primary server and from server;The T-EPS system uses the client end/server end framework of multilayer;It is provided with data service layer and bussiness processing layer in the server, functional interface layer and interface display layer are provided in client computer.The electronic regulation system of support team's cooperation of the invention, reduces the improper communication between Team Member, promotes Team Context consciousness, improves team's overall efficiency, the generation of human-equation error is avoided, to improve the overall security and economy of nuclear power plant.

Description

A kind of electronic regulation system of support team's cooperation
Technical field
The present invention relates to a kind of electronic regulation system, in particular to a kind of electronic regulation system of support team's cooperation System, belongs to the management in the emergency services such as nuclear power plant main control room personnel, the technical support centre outside MCR, Police Command Center With the art communication systems field of technical support personnel.
Background technique
Master-control room of nuclear power plant is a kind of highly complex, uncertain environment, and the completion of operator's task needs crewmember Between work in coordination and could complete;Teams and groups of nuclear power plant are generally divided into operator (such as when operating normally by several member compositions Reactor operator, steam turbine operator, electrical system operator), secondary value length/value length/machine group leader, technical adviser on duty, value The roles such as the form master/operation manager;In addition, in power plant, region also has multidigit site operation people on the spot, and responsibility is to master control Room no signal processed or without control equipment monitoring, to support main control room operations staff.Under accident conditions, the people of main control room Number also will increase, such as liaison man, observer.And the division of above-mentioned role is mainly according to the difference for being then task type;Due to The limitation of technological means, papery regulation plays always important role, especially in the main control room of legacy analog device, Operator is completely dependent on papery regulation and runs, and the papery regulation in different operator's hands is all consistent.Due to instruction Instrument and controller are distributed in different dish platforms, everyone can only see the partial information of power plant, the modality for co-operation one of team As be that operators, which collect required plant information and report, gives value length, and in the finger for being worth length under the instruction of long/secondary value length of value Under showing, specific control operation is carried out.Whole team is generally linked up using stringent three-stage, and higher ditch passband is maintained Rate, and good communication is also to maintain one of the important means of Team Context consciousness;It is more next after main control room digitlization More power plant starts using electronic regulation system.In September, 2011, IEEE have issued IEEE Guide for Human Factors Applications of Computerized Operating Procedure Systems(COPS)at Nuclear Power Generatink Stations and Other Nuclear Facilities(IEEE Std.1786- 2011), which provides guidance from the angle of Human Engineering for the design and use of electronic regulation system, and will be each at present The electronic regulation system that state is developed, form is different has taken out three classes electronization regulation system according to functional hierarchy;But These systems are that all crewmembers are each provided with consistent terminal function and man-machine interface, do not account for following factor: 1, The task feature of different Team Members is inconsistent: it only needs to pay close attention to oneself current task as operator, and value length needs to pay close attention to The operating status of entire power plant, and distribute, the task of hormany operating person;All users are superfluous using unified interface bring information Remaining and afunction brings inconvenience for operation.2, for team collaboration of nuclear power plant: the different piece of a regulation is by different behaviour Vertical member executes;Different operators execute several parts of parallel regulations;One operator executes master ga(u)ge journey, other operators execute one to More parts of called cuckoo journeys;Typical task such as reactor operator is responsible for the monitoring and operation of primary Ioops, steam turbine manipulation The monitoring and operation of the responsible secondary circuit of member, and open heap when, both needs to be fitted to each other.Since system lacks setting for this respect Meter considers, only coordinates the operation between crewmember by administrative provisions at present, both inconvenient, is also easy error.3, there is power plant Negative effect of the electronic regulation system of multidate information to team communication: after MCR digitlization, especially electronic regulation collection After power plant's dynamic parameter, each member can see all layers needed for power plant and agendum on its station Secondary information and implementing result, the subjective desire linked up and slump in demand, the influence to Team Context consciousness are more bright It is aobvious.And every member increases member's independence in face of the mode of operation of oneself VDU, and the transparency reduces, to operation teams and groups Team's characteristic cause negative effect.So digitlization also brings some potential safety problems;The appearance of the above problem, one Aspect is to introduce regulation electronization without sufficiently analysis to affect teams and groups' operation, is on the other hand defended tenaciously in papery regulation Stereotyped thinking in without making full use of digitized advantage;Meanwhile as the range of electronic regulation system is gradually by answering Anxious operating standard (EOP), misoperation regulation (AOP), extend to overall operation regulation (GOP), system operating standard (SOP) and Major accident directive/guide (SAMG), the above problem seem more and more prominent.
Summary of the invention
(1) technical problems to be solved
To solve the above problems, the invention proposes a kind of electronic regulation systems of support team cooperation, according to team The difference of member's responsibility and task provides the electronic regulation system of function difference, convenience is provided for operation, to reduce team Improper communication between member promotes Team Context consciousness, improves team's overall efficiency, avoid the generation of human-equation error, thus Improve the overall security and economy of nuclear power plant.
(2) technical solution
The electronic regulation system of support team's cooperation of the invention, including power plant's instrument control network system and power plant's local area network System, it is characterised in that: power plant's instrument control network system and power plant's LAN system form a T-EPS system;The power plant Instrument control network system and power plant's LAN system pass through unidirectional gateway communication;The T-EPS system is by multiple client computer and service Device is constituted;The server is constituted by primary server and from server.
Further, the client computer is the active station in power plant's instrument control network system and power plant's LAN system.
Further, the server uses redundancy configuration structure
(3) beneficial effect
Compared with prior art, the electronic regulation system of support team of the invention cooperation, has the advantage that
(1) user is divided into value length, operator, management/support staff's three classes according to the difference of task feature by T-EPS, The discrepant interface of tool and function are provided for every class user;
(2) value length can assign the task to specific operator in regulation, step and sub-step level, and T-EPS also exists Authorization operator's information that regulation, step or sub-step are designated in all pages specifies the power and responsibility that regulation executes, prevents nothing The maloperation of authorized person;
(3) the execution logic chart of the regulation level an of traffic coverage is provided, is clearly designated between more parts of regulations Execution relationship (as called, parallel), for operation, teams and groups provide good situation awareness;
(4) the flow chart information of more parts of regulations can be presented according to regulation or user role simultaneously in a width page, And designate the relationship between the execution state of every part of regulation and regulation;The team collaboration of operation teams and groups, such as one are supported well The different piece of part regulation is executed by different operators;Different operators execute several parts of parallel regulations;One operator executes Master ga(u)ge journey, other operators execute the called cuckoo journey of one to multiple part;Value is long, management/support staff checks what regulation executed Total looks;
(5) it provides regulation state browsing and regulation executes two kinds of tracing modes of monitoring, provided for the user of different role The different mode of information content;
(6) Status Change prompt information is provided in page marking area, it is ensured that the transparency of teams and groups' operation;
(7) instant information communication module is provided, provides another means for team communication.
Detailed description of the invention
Fig. 1 is the overall construction drawing of this system;
Fig. 2 is the architecture diagram of this system;
Fig. 3 is this system client general picture page example figure;
Fig. 4 is this system client regulation page example figure.
Specific embodiment
Embodiment 1:
The electronic regulation system of support team's cooperation as depicted in figs. 1 and 2, a kind of electronization of support team's cooperation Regulation system, including power plant's instrument control network system and power plant's LAN system, it is characterised in that: power plant's instrument control network system A T-EPS system is formed with power plant's LAN system;Power plant's instrument control network system and power plant's LAN system pass through unidirectional Gateway communication;The T-EPS system is made of multiple client-servers;The server is by primary server and from server It constitutes;The T-EPS system uses the client end/server end framework of multilayer;Data service layer is provided in the server And bussiness processing layer, functional interface layer and interface display layer are provided in client computer;It primary server and is calculated simultaneously from server, Only calculated result is supplied to client by primary server when normal operation;Server mainly undertakes data acquisition, data processing, number According to storage, application program load, application-monitoring function;The processing result that primary server transmits then is presented to use by client computer Family provides interactive man-machine interface;Meanwhile information is reached power plant by power plant's instrument control grid by unidirectional gateway by T-EPS Local area network, user can also browse related data on LAN client;In use, only being had in the offer of nuclear power plant's main control room The client of the client of control function, remaining region only has browsing function;Data service layer provides most basic data Base management system service;Bussiness processing layer is then responsible for all major functions of T-EPS system, the functional interface layer phase with client It connects;It improves the safety of database, improves the concatenation ability of system, while also enabling the core code of system maximum Reuse to degree;Functional interface layer realizes the communication function between client and server, and does for interface display layer Simple data mart modeling and processing work.Interface display layer is according to different user roles, by data result and interactive interface Now give user.
Wherein, the client computer is the active station in power plant's instrument control network system and power plant's LAN system;The service Device uses redundancy configuration structure.
Embodiment 1:
In nuclear power plant, main control room teams and groups be equipped with it is not quite identical, the identical post of action may also title not Unanimously, but user from task feature is divided into following a few classes by this system:
In the present invention support team cooperation electronic regulation system, other than regulation text information is presented, also from Power plant's I&C system obtains power plant's real time information, while can provide regulation entry condition and specific steps based on these information Judge automatically as a result, and specific plant information is display together with protocol steps, provide support for operator;In addition, electronics Power plant's control (if having) can be carried out by the soft-controller in system by changing regulation system, or by calling electronic regulation system The power plant with control function except system shows picture or hard switching to realize power plant's control;Conditional electronic regulation system Details are not described herein for basic function, and following table mainly lists the function difference of T-EPS three types client:
Client general picture is mainly made of with the regulation page such as Fig. 4 the general picture page as shown in Figure 3;When based on T-EPS entrance Condition judges automatically result recommendation or personnel judge after entering some regulation that operator then will be linked into rule by the general picture page The journey page is specifically monitored, and also can return to the Global Information that the general picture page checks operation;Each function of T-EPS it is specific and Speech:
Regulation state browsing is all open to all users:
As shown in figure 3, the T-EPS general picture page: by list mode, the state for presenting all regulations (such as activates, is complete At, it is idle etc.), the currently active step, the information of the currently active step responsibility operator.By way of flow chart, this is presented Logical relation between traffic coverage regulation, the state of these regulations, the currently active step, the currently active step responsibility operator etc. Information.
As shown in figure 4, the regulation page: can arbitrarily browse all regulations can simultaneously for the regulation of this traffic coverage To view the responsibility operator of protocol steps status information (be completed, activate, unfinished) and step.Meanwhile power plant's state Information is then embedded in electronic regulation system checks for all users.
This function can make total looks that all users understand operation and regulation executes, while avoid as " management/backer Member " provides the electronic computer system information of redundancy.
It is the function that electronic regulation system engineer station provides that regulation, which executes historical viewings, for backstage personnel inquiry;But It is to increase team's transparency, this system is each provided with this function in the client of all users;Value is long and operator institute into The various operations such as capable regulation activates, regulation jumps, step judges, can all be recorded by system.All users are convenient to Check that the regulation of a certain operator or entire teams and groups executes history.
As the leader of teams and groups, the long permission with the distribution of regulation task of value.Be worth length can regulation level or The permission that regulation executes is given into a certain operator in step, the level of sub-step, system will be in the general picture page and/or regulation page Face marks responsibility operator, and the responsibility operator that permission is only assigned is able to carry out relevant regulation and executes operation (such as step judgement, step jump, be manually entered information<on the spot feedback, remarks>, executes soft-controller in step etc.).One As for, value is long and without specific guidelines, but commands operator, supervises, coordinates.But T-EPS is Value is long to provide the highest permission of regulation execution, i.e., when value length thinks necessary, can surmount responsibility operator and advise Process control.
In order to increase the transparency, value is long, and there is regulation to execute function for monitoring;That is, value length can on the VDU of oneself, to appoint The regulation executive condition of meaning operator is completely monitored.All users can be by regulation state browsing function to other people Regulation executive condition browsed.The difference of the two is that regulation state browsing only provides the main information of regulation execution (i.e. System state change category information), and regulation executes monitoring and is then similar to and copies screen monitoring, value is long can also be seen that choose operator that A bit will not caused by the operation that changes of T-EPS system mode choose a certain logic module if a certain step but do not activated in point, Mouse movement etc..Value is long while there is regulation to execute the permission of monitoring and regulation state browsing, he/her can be as needed, two Easily switched between person.
One difference greatly of T-EPS and conditional electronic regulation system is to provide more regulations browsing moulds in the regulation page Formula;Traditional electronic regulation system, a case where regulation is only able to display in VDU, if currently there is multiple regulations to be activated, It then needs to return to system homepage to switch again.And T-EPS, special consideration should be given to the demand of team collaboration, regulation page schematic diagram is shown in figure 4.It is status bar above the page, lower left is regulation flow chart, and right side is then information alert region from top to bottom, chooses step detailed Thin information area (including T-EPS judges automatically logic) and timely information communication zone.
In status bar, can by the currently active regulation option and active user (only include the directory operator of regulation: Value is long and operator) icon, select the regulation flow chart to show simultaneously.And in regulation process graph region, it can show one Or the flow chart of multiple regulations, and indicate the relationship between regulation.
Information alert region real-time display of the T-EPS in regulation page upper right side alerts/pays attention to information, Status Change information With lasting monitoring Step Information;If selected state changes, when having more parts of activation regulations in system and/or have multidigit responsibility operator When, T-EPS will be according to operation process, and automatic prompt such as " OP1 completes E-0 step 16 ", " OP2 is jumped, and E-0 step 33 arrives E-3 Information as step 1 ".User also may bring up complete documentation, check prompt information earlier.
T-EPS provides instant information communication module in the page lower right corner, is linked up for Team Member, such as " SS: on the spot Operator confirms that personnel have withdrawn ".This module can be hidden, and will do it prompt when having new information.
The above-described embodiments are merely illustrative of preferred embodiments of the present invention, not to structure of the invention Think and range is defined.Without departing from the design concept of the invention, ordinary people in the field is to technology of the invention The all variations and modifications that scheme is made, should all drop into protection scope of the present invention, the claimed technology contents of the present invention, It is all described in the claims.

Claims (3)

1. a kind of electronic regulation system of support team's cooperation, including power plant's instrument control network system and power plant's LAN system, It is characterized by: power plant's instrument control network system and power plant's LAN system form a T-EPS system;Power plant's instrument control net Network system and power plant's LAN system pass through unidirectional gateway communication;The T-EPS system is made of multiple client-servers; The server is constituted by primary server and from server;The T-EPS system uses the client end/server end frame of multilayer Structure;It is provided with data service layer and bussiness processing layer in the server, functional interface layer is provided in client computer and interface is aobvious Show layer;It primary server and is calculated simultaneously from server, only calculated result is supplied to client by primary server when normal operation;Clothes Business device undertakes data acquisition, data processing, data storage, application program load, application-monitoring function;Client computer will then be led The processing result of server transport is presented to the user, and provides interactive man-machine interface;Meanwhile T-EPS will be believed by unidirectional gateway Breath reaches power plant's local area network by power plant's instrument control grid, and user can also browse related data on LAN client;It uses When, the client with control function only is provided in nuclear power plant's main control room, the client in remaining region only has browsing function; Data service layer provides most basic data base management system service;Bussiness processing layer is then responsible for all masters of T-EPS system Function is wanted, is connected with the functional interface layer of client;Functional interface layer realizes the communication function between client and server, And some simple data mart modelings and processing work are done for interface display layer.
2. the electronic regulation system of support team according to claim 1 cooperation, it is characterised in that: the client computer is Active station in power plant's instrument control network system and power plant's LAN system.
3. the electronic regulation system of support team's cooperation according to claim 1, it is characterised in that: the server is adopted Use redundancy configuration structure.
CN201510246212.2A 2015-05-14 2015-05-14 A kind of electronic regulation system of support team's cooperation Active CN104836858B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510246212.2A CN104836858B (en) 2015-05-14 2015-05-14 A kind of electronic regulation system of support team's cooperation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510246212.2A CN104836858B (en) 2015-05-14 2015-05-14 A kind of electronic regulation system of support team's cooperation

Publications (2)

Publication Number Publication Date
CN104836858A CN104836858A (en) 2015-08-12
CN104836858B true CN104836858B (en) 2019-01-15

Family

ID=53814487

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510246212.2A Active CN104836858B (en) 2015-05-14 2015-05-14 A kind of electronic regulation system of support team's cooperation

Country Status (1)

Country Link
CN (1) CN104836858B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109636322A (en) * 2018-11-27 2019-04-16 岭澳核电有限公司 Nuclear power plant's malfunction protocol information system and nuclear power plant's malfunction protocol information-based method
CN110490489A (en) * 2019-08-28 2019-11-22 上海核工程研究设计院有限公司 A kind of nuclear power plant's major accident information system

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7813817B2 (en) * 2006-05-19 2010-10-12 Westinghouse Electric Co Llc Computerized procedures system
CN101986331B (en) * 2010-10-25 2013-11-13 中国电力科学研究院 Power grid simulation calculation cooperative work system
CN103929403A (en) * 2013-01-14 2014-07-16 上海核工程研究设计院 Portable nuclear power plant electronization regulation system
CN103929405A (en) * 2013-01-14 2014-07-16 上海核工程研究设计院 Portable electronized procedure system based on power plant dynamic data
CN103345952B (en) * 2013-06-24 2015-09-30 上海核工程研究设计院 A kind of operator's auxiliary computing system based on model
CN103676863B (en) * 2013-12-03 2017-04-12 上海核工程研究设计院 Nuclear plant alarm display device utilizing digitized technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
计算机化规程系统在AP1000中的应用;文芳;《中国核电》;20120331;第5卷(第1期);第68-73页

Also Published As

Publication number Publication date
CN104836858A (en) 2015-08-12

Similar Documents

Publication Publication Date Title
CN104600840B (en) A kind of intelligent scheduling anti-misoperation management system and method
CN109740837B (en) Power grid province and land network command and safety error prevention method based on regulation and control integration
CN101329564B (en) Computer room management system
CN102957205B (en) A kind of method and system setting up electricity distribution network model
CN103761624A (en) Implementing method of integrated power grid dispatching operation intelligent mistaken-early-warning preventing system
CN104463759A (en) Decision-making and command all-in-one machine based on digital schema and operation method of all-in-one machine
CN103840955B (en) The operation maintenance system and operation maintenance management method of distributed IT system
CN101887547A (en) Assistant decision system for condition-based maintenance and risk evaluation of power transmission and transformation equipment
CN103578039B (en) A kind of power networks risk prewarning analysis system
CN104615617A (en) Dispatch monitoring information processing system for substation equipment
CN103279333B (en) A kind of method of the multinode sequential control based on SCADA system
CN104933535A (en) An intelligent monitoring operation ticket management method and a system thereof
CN104836858B (en) A kind of electronic regulation system of support team&#39;s cooperation
CN111047143A (en) Power grid OMS-based regional and county team index management system
AU2021290248A1 (en) System for intelligent work order based on graphical strategy programming engine and working method thereof
CN101354643B (en) Method for monitoring BPEL process flow operation time based on state aspect
Hugo et al. A method to select human–system interfaces for nuclear power plants
CN105186686B (en) A kind of dispatching of power netwoks intelligent error preventing policy system based on full mesh topology
CN108734395A (en) Electric network emergency management and emergency drilling system
Morschheuser et al. Challenges and solutions of document and workflow management in a manufacturing enterprise: a case study
CN115309357B (en) Intelligent console, information processing system and method thereof and monitoring hall
CN102968087B (en) A kind of Aptitude Operation Order Sheet System preventing maloperation
CN103809973A (en) Graphic control interface design system and graphic control interface design operation method thereof
CN203027292U (en) Portable electronized regulation system of nuclear power plant
CN106329731A (en) Substation model interaction and management device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No. 29 Hong Cao Road, Xuhui District, Shanghai

Patentee after: SHANGHAI NUCLEAR ENGINEERING RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Address before: No. 29 Hong Cao Road, Xuhui District, Shanghai

Patentee before: Shanghai Nuclear Engineering Research & Design Institute

CP01 Change in the name or title of a patent holder
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: An electronic procedure system supporting team cooperation

Effective date of registration: 20210916

Granted publication date: 20190115

Pledgee: Bank of China Limited by Share Ltd. Shanghai Xuhui branch

Pledgor: SHANGHAI NUCLEAR ENGINEERING RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Registration number: Y2021310000073

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220906

Granted publication date: 20190115

Pledgee: Bank of China Limited by Share Ltd. Shanghai Xuhui branch

Pledgor: SHANGHAI NUCLEAR ENGINEERING RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Registration number: Y2021310000073

PC01 Cancellation of the registration of the contract for pledge of patent right
TR01 Transfer of patent right

Effective date of registration: 20221109

Address after: No. 29 Hong Cao Road, Xuhui District, Shanghai

Patentee after: SHANGHAI NUCLEAR ENGINEERING RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Patentee after: Shanghai Shen Nuclear Energy Engineering Technology Co.,Ltd.

Address before: No. 29 Hong Cao Road, Xuhui District, Shanghai

Patentee before: SHANGHAI NUCLEAR ENGINEERING RESEARCH & DESIGN INSTITUTE Co.,Ltd.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: No. 29 Hong Cao Road, Xuhui District, Shanghai

Patentee after: Shanghai Nuclear Engineering Research and Design Institute Co.,Ltd.

Patentee after: Shanghai Shen Nuclear Energy Engineering Technology Co.,Ltd.

Address before: No. 29 Hong Cao Road, Xuhui District, Shanghai

Patentee before: SHANGHAI NUCLEAR ENGINEERING RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Patentee before: Shanghai Shen Nuclear Energy Engineering Technology Co.,Ltd.

CP01 Change in the name or title of a patent holder