CN104636576A - Rapid subway construction risk evaluation method based on weighted average method - Google Patents

Rapid subway construction risk evaluation method based on weighted average method Download PDF

Info

Publication number
CN104636576A
CN104636576A CN201310554814.5A CN201310554814A CN104636576A CN 104636576 A CN104636576 A CN 104636576A CN 201310554814 A CN201310554814 A CN 201310554814A CN 104636576 A CN104636576 A CN 104636576A
Authority
CN
China
Prior art keywords
data
subway
server
risk evaluation
risk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310554814.5A
Other languages
Chinese (zh)
Inventor
林跃春
赵磊
徐少华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian Academy Of Reconnaissance And Mapping Co Ltd
Original Assignee
Dalian Academy Of Reconnaissance And Mapping Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian Academy Of Reconnaissance And Mapping Co Ltd filed Critical Dalian Academy Of Reconnaissance And Mapping Co Ltd
Priority to CN201310554814.5A priority Critical patent/CN104636576A/en
Publication of CN104636576A publication Critical patent/CN104636576A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a rapid subway construction risk evaluation method based on a weighted average method. The rapid subway construction risk evaluation method includes the following steps of arranging a multi-element sensor on site, transmitting detection data to a subway on-site data collection server in a wired or wireless mode, filtering data transmitted back by the multi-element sensor through the subway on-site data collection server, sending the processed data to a risk evaluation server, classifying and integrating the detection data sent back by the subway on-site data collection server through the risk evaluation server, converting the data into a data array suitable for being calculated through a weighted average method fusion method, conducting risk evaluation on the data through the risk evaluation server by means of the weighted average method fusion method, sending the rapid risk evaluation result to a detection and monitoring central computer, and conducting the further processing through a computer central processing unit. The rapid subway construction risk evaluation method has the advantages that use is convenient, the processing speed is high, and the technology achievement is easy.

Description

Based on the subway work risk fast evaluation method of method of weighted mean
Technical field
The present invention relates to a kind of subway work risk fast evaluation method based on method of weighted mean.
Background technology
The time in early stage of building subway is longer, due to needs planning and government's examination & approval, even also needs test.From ferment that putting into practice breaks ground and need the time grown very much, short then several years, the long then more than ten years are also possible.Due to the structure of subway, and cause very easily because these factor generation tragedies.The construction of subway is divided into: 1, the simplest directly method of open cut backfill is bright cut and fill (open cut backfill).Hollow place is excavated in general Shi street to this method, then builds tunnel structure below, just road surface is spread again after there are enough supporting forces in tunnel.Except road is opened by pick, other underground structures such as electric wire, telephone wire, water pipe etc. all need to reconfigure.The material building this tunnel is generally concrete or steel, but older system also has and to use fragment of brick and iron.2, brill digs method: another kind of method first digs a vertical shaft in somewhere, ground, then at shaft bottom tunneling.Modal method is for using drilling and digging machine (shield machine, shield machine), and one side is excavated one side and preprepared assembly is arranged in tunnel wall.For the place that depth of building is intensive, bore the method for construction digging method or even unique feasible.The advantage Shi Dui street of this method or the impact of other underground installations very little, even can build at the bottom; The design in tunnel also has more writing space, such as station can than station and station between tunnel higher, help train leaving from station time accelerate and enter the station time slow down.But this method of digging neither be impeccable, one of them often needs to pay attention to underground water mitigation; In addition at some harder rock stratum excavation, explosive may be needed.Underground air supply problem even tunnel cave also likely causes workman's injures and deaths.In addition, for the place that building height is intensive, during excavation except will noticing and avoiding impacting the building structure of building site surrounding, the public utilities at place sometimes also to be planned as a whole, the water delivery at the bottom of ground, the migration of transmission of electricity pipeline, to make way to build passage of train.
So just can see the importance drawing preliminary preparation, and this most important thing is exactly site reconnaissance work, whether the data of exploration are accurate, very large on the impact of design and construction.Along with the development of electronic devices and components, the precision of sensor increases substantially, and existing exploration level has accomplished the degree that single parameter error is ignored.But, geology actual state, usually by composite factor shadow, carries out simulation modelling with regard to needs to different geological condition like this, and the data of collection are as the training data of model and analysis data, the accurate model of final acquisition, then change geologic parameter, checking arrangement and method for construction, this process need is analyzed one by one to contingent situation, checking is trained one by one by the parameter of model to change, do degree of accuracy so high, practical operation is effective, but the cycle is oversize.
Information fusion is that the Incomplete information of multiple support channels, multi-faceted collection is in addition comprehensive, eliminates the information of redundancy and the contradiction that may exist between multi-source information, and in addition complementary to it, reduces the process that its uncertain system environment facies describe complete consistance.Information fusion can improve the decision-making of intelligent system, planning, the rapidity of reaction and positive plan risk, and being a cross discipline relating to information science, computer science and robotization science, is the important directions that current information society must be studied.The generation of multisource information fusion technology improves the accuracy of intelligent system decision-making, reduces risk of policy making.The high scheme of construction risk is tentatively got rid of by information fusion, retain the arrangement and method for construction that feasibility is higher, and then by training checking one by one above by the parameter of model to feasible scheme, doing like this and guaranteeing that degree of accuracy is high, raise the efficiency simultaneously, reduce proving period in early stage.
Method of weighted mean signal level fusion method the most simply, most direct-vision method is method of weighted mean.For subway work risk rapid evaluation provides technical support.
Summary of the invention
The present invention is directed to the proposition of above problem, and development is based on the subway work risk fast evaluation method of method of weighted mean.The technical solution used in the present invention is as follows:
Based on a subway work risk fast evaluation method for method of weighted mean, it is characterized in that comprising the steps:
1) detection data are transferred to subway on-site data gathering server by wired or wireless mode by on-the-spot multielement bar of laying, subway on-site data gathering server carries out filtration treatment to multielement bar returned data, then the data after process is sent to risk assessment server;
2) risk assessment server is classified to the detection data that the transmission of subway on-site data gathering server is returned and integrates, and is converted to the data array being suitable for method of weighted mean calculating fusion;
3) then risk assessment server adopts method of weighted mean fusion method to carry out risk assessment process to above-mentioned data, concrete processing procedure comprises: the redundant information that one group of data provides is weighted on average by the method, result is worth as fusion, and the method is a kind of method directly operated data source;
4) risk rapid evaluation result is issued test and monitoring central computer by ultimate risk evaluating server, is for further processing by computer center's processing unit.
Also comprise in step 3):
Merge the data step of unlike signal level.
Described scene is laid multielement bar and is comprised displacement meter, taseometer, ventage piezometer, reinforcing rib meter, pressure cell and flowmeter.
Based on the subway work risk fast evaluation method of method of weighted mean, to on-the-spot returned data fusion treatment, tentatively get rid of the scheme that construction risk is high, retain the arrangement and method for construction that feasibility is higher, and then by training checking one by one above by the parameter of model to feasible scheme, do like this and guarantee that degree of accuracy is high, raise the efficiency simultaneously, reduce proving period in early stage.The method also has in addition: easy to use, processing speed, technology realize the feature such as easy and be suitable for extensive popularization.
Accompanying drawing explanation
Fig. 1 is the structured flowchart of system of the present invention;
Fig. 2 is realization flow figure of the present invention.
Embodiment
As depicted in figs. 1 and 2 based on the subway work risk fast evaluation method of method of weighted mean, comprise the steps:
1) detection data are transferred to subway on-site data gathering server by wired or wireless mode by on-the-spot multielement bar of laying, subway on-site data gathering server carries out filtration treatment to multielement bar returned data, then the data after process is sent to risk assessment server;
2) risk assessment server is classified to the detection data that the transmission of subway on-site data gathering server is returned and integrates, and is converted to the data array being suitable for method of weighted mean calculating fusion;
3) then risk assessment server adopts method of weighted mean fusion method to carry out risk assessment process to above-mentioned data, concrete processing procedure comprises: the redundant information that one group of data provides is weighted on average by the method, result is worth as fusion, and the method is a kind of method directly operated data source;
4) risk rapid evaluation result is issued test and monitoring central computer by ultimate risk evaluating server, is for further processing by computer center's processing unit.
Also comprise in step 3):
Merge the data step of unlike signal level.
Described scene is laid multielement bar and is comprised displacement meter, taseometer, ventage piezometer, reinforcing rib meter, pressure cell and flowmeter.
The above; be only the present invention's preferably embodiment; but protection scope of the present invention is not limited thereto; anyly be familiar with those skilled in the art in the technical scope that the present invention discloses; be equal to according to technical scheme of the present invention and inventive concept thereof and replace or change, all should be encompassed within protection scope of the present invention.

Claims (3)

1., based on a subway work risk fast evaluation method for method of weighted mean, it is characterized in that comprising the steps:
1) detection data are transferred to subway on-site data gathering server by wired or wireless mode by on-the-spot multielement bar of laying, subway on-site data gathering server carries out filtration treatment to multielement bar returned data, then the data after process is sent to risk assessment server;
2) risk assessment server is classified to the detection data that the transmission of subway on-site data gathering server is returned and integrates, and is converted to the data array being suitable for method of weighted mean calculating fusion;
3) then risk assessment server adopts method of weighted mean fusion method to carry out risk assessment process to above-mentioned data, concrete processing procedure comprises: the redundant information that one group of data provides is weighted on average by the method, result is worth as fusion, and the method is a kind of method directly operated data source;
4) risk rapid evaluation result is issued test and monitoring central computer by ultimate risk evaluating server, is for further processing by computer center's processing unit.
2. a kind of subway work risk fast evaluation method based on method of weighted mean according to claim 1, is characterized in that also comprising in step 3):
Merge the data step of unlike signal level.
3. a kind of subway work risk fast evaluation method based on method of weighted mean according to claim 1, is characterized in that described scene is laid multielement bar and comprised displacement meter, taseometer, ventage piezometer, reinforcing rib meter, pressure cell and flowmeter.
CN201310554814.5A 2013-11-07 2013-11-07 Rapid subway construction risk evaluation method based on weighted average method Pending CN104636576A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310554814.5A CN104636576A (en) 2013-11-07 2013-11-07 Rapid subway construction risk evaluation method based on weighted average method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310554814.5A CN104636576A (en) 2013-11-07 2013-11-07 Rapid subway construction risk evaluation method based on weighted average method

Publications (1)

Publication Number Publication Date
CN104636576A true CN104636576A (en) 2015-05-20

Family

ID=53215317

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310554814.5A Pending CN104636576A (en) 2013-11-07 2013-11-07 Rapid subway construction risk evaluation method based on weighted average method

Country Status (1)

Country Link
CN (1) CN104636576A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106228025A (en) * 2016-08-06 2016-12-14 傅崇辉 The method for quick of a kind of nitrosodimethylamine carcinogenic risk and device
CN106295188A (en) * 2016-08-12 2017-01-04 傅崇辉 The simple detection method of a kind of indoor particle float carcinogenic risk and device
CN112946779A (en) * 2021-01-28 2021-06-11 中煤科工集团重庆研究院有限公司 Point domain identification system and method for tunnel safety monitoring

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106228025A (en) * 2016-08-06 2016-12-14 傅崇辉 The method for quick of a kind of nitrosodimethylamine carcinogenic risk and device
CN106295188A (en) * 2016-08-12 2017-01-04 傅崇辉 The simple detection method of a kind of indoor particle float carcinogenic risk and device
CN112946779A (en) * 2021-01-28 2021-06-11 中煤科工集团重庆研究院有限公司 Point domain identification system and method for tunnel safety monitoring
CN112946779B (en) * 2021-01-28 2024-02-20 中煤科工集团重庆研究院有限公司 Point domain identification system and method for tunnel security monitoring

Similar Documents

Publication Publication Date Title
CN111058855B (en) Deformation control method and evaluation system for shield underpassing structure
CN103713335B (en) Comprehensive advance geological detection system carried by tunnel boring machine
CN101914912B (en) In-situ testing method for deep underground engineering during rockburst preparation and evolution process
CN104747184B (en) Measurement-while-drilling method and device for three-dimensional wave velocity imaging of rock mass in front of tunnel face
CN103016063B (en) Monitoring system for construction safety
CN105974056B (en) Tunnel water bursting disaster precursor information monitoring model pilot system and test method
CN107861157B (en) A kind of underground water seal cave depot operation phase micro seismic monitoring method
CN108930539A (en) A method of it is controlled based on BIM Tunnel Overbreak & Underbreak
CN110927821A (en) BIM + GIS-based advanced geological forecast information system for tunnel construction
CN107346032A (en) A kind of wireless controlled passes the Tunnel prediction system and method for acceleration transducer
CN113960695A (en) Fine exploration method for water-rich karst in complex urban environment
CN111335928B (en) Horizontal geological survey arrangement method for deep-buried underground cave depot
CN102880918B (en) Based on the deep excavation risk evaluation method that data fusion is analyzed
CN104636576A (en) Rapid subway construction risk evaluation method based on weighted average method
CN103630938A (en) Imaging system and imaging method for well earthquake using hammer head of down-hole hammer as focus
CN104636511A (en) Rapid subway construction risk evaluation method based on Dasarathy model
CN103225510A (en) Construction method of tunnel construction risk map for TBM (tunnel boring machine)
CN104636997A (en) Rapid subway construction risk assessment method based on Kalman filtering method
CN104636998A (en) Subway construction rapid risk assessment method based on neural network
CN104637020A (en) Rapid subway construction risk assessment method based on bayesian estimation method
Khoo et al. Geotechnical challenges and innovations in urban underground construction–The Klang Valley Mass Rapid Transit project
CN104636996A (en) Subway construction rapid risk assessment method based on fuzzy logic
CN104636995A (en) Rapid subway construction risk assessment method based on JDL (joint directors of laboratories) model
CN104636994A (en) Rapid subway construction risk assessment method based on evidence reasoning method
CN109269434B (en) Direct-attached rock wall deformation laser scanning system and application method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150520