CN103761618A - Control method and system of science and technology item - Google Patents

Control method and system of science and technology item Download PDF

Info

Publication number
CN103761618A
CN103761618A CN201410032862.2A CN201410032862A CN103761618A CN 103761618 A CN103761618 A CN 103761618A CN 201410032862 A CN201410032862 A CN 201410032862A CN 103761618 A CN103761618 A CN 103761618A
Authority
CN
China
Prior art keywords
trl
technology
electrical network
item
science
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410032862.2A
Other languages
Chinese (zh)
Inventor
罗兵
龚婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSG Electric Power Research Institute
Research Institute of Southern Power Grid Co Ltd
Original Assignee
Research Institute of Southern Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Research Institute of Southern Power Grid Co Ltd filed Critical Research Institute of Southern Power Grid Co Ltd
Priority to CN201410032862.2A priority Critical patent/CN103761618A/en
Publication of CN103761618A publication Critical patent/CN103761618A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a control method and system of a science and technology item. The control method and system of the science and technology item comprises the steps that a plurality of key technology points are determined, evaluation indexes of each key technology point are established based on three dimensions, namely the professional technology field, the scientific and technological achievement type and the TRL, and the evaluation indexes are stored into a database; item information and stage achievements in the item implementation process are collected and transmitted to the database; the evaluation indexes and the stage achievements are invoked, the TRL grades of the key technology points are divided according to the stage achievements, and the three dimensions of the key technology points are synchronously updated; each stage achievement and the TRLs of the key technology points are checked, and the checked results are transmitted to the database. The construction process of a technological shelf system comprises the steps of the data in the database are summarized, and forming the technological shelf system used for managing and evaluating the power grid science and technology item by adopting a Fusion Chart assembly. The control method and system of the science and technology item comprehensively reflect the sustainable innovation ability and the potential value of scientific research technology, and are favorable for improvement of scientific research investment benefits and efficiency.

Description

A kind of electrical network science and technology item control method and system
Technical field
The present invention relates to electric power network technique field, particularly relate to a kind of electrical network science and technology item control method and system.
Background technology
Electrical network science and technology item is the basis of electrical network scientific research, innovation, science and technology item and achievement carried out effectively, controlled accurately and management, and be the important channel of improving scientific and technical innovation level.Along with the continuous expansion of electrical network scale, electrical network science and technology item quantity also increases day by day, and the technology of Project Process and achievement control is also increasingly mature.Science and technology item overall process, comprehensive management and control are the bases of assessment item level, at present electrical network science and technology item being carried out in the scheme of management and control, project data and relevant human resource data are made a report on by program accountability people periodic manual, financial data is made a report on by hand by financial staff, the unified technical management department that is aggregated into.This control mode, because data are made a report on take subjectivity as main, lacks and evaluates foundation, while data do not have integrated, and information is obstructed, and each departmental staff can only recognize the data of own part, bring difficulty to science and technology item management and control, and had influence on the level of electrical network scientific and technical innovation.Therefore, the management and control of existing electrical network science and technology item belongs to typical artificial subjective management process, and the present invention is directed to this artificial subjectivity management, utilizes digitized technological means, realizes the intelligent management and control of electrical network science and technology item.
Summary of the invention
Technical matters to be solved by this invention is to provide a kind of electrical network science and technology item control method and system, for solving the management and control problem of electrical network industry science and technology item, particularly in conjunction with database technology, TRL technology and FusionChart chart component technology etc. solve in the management and control of existing electrical network industry science and technology item data cannot be integrated, evaluate subjective, too rely on the technical matterss such as artificial running.
The technical scheme that the present invention solves the problems of the technologies described above is as follows: a kind of electrical network science and technology item control method, and object is to build a technology commodity shelf system for management and evaluation electrical network science and technology item, and concrete steps comprise:
Project verification management process: determine some gordian technique points of electrical network science and technology item, and set up the evaluation index of each gordian technique point based on tri-dimensions of the ready horizontal TRL of professional skill field, scientific and technological achievement type and technology, evaluation index is stored into database.This step defines evaluation index, and the evaluation index that makes to be stored into database is follow-up unique evaluation criterion, thereby has solved the problem of artificial Assessment of Changes index in existing electrical network science and technology item management and control process.
Implement management process: gather project information and stage achievement in the project implementation process, and project information and stage achievement are transferred to database storage.
Index step of updating: from data base call evaluation index and stage achievement, divide the TRL grade of gordian technique point according to stage achievement, and synchronously upgrade three dimensions of gordian technique point, realize the real-time update of evaluation index.This step has completed the analysis to stage achievement by TRL technology, and real-time update evaluation index, this evaluation index is still follow-up unique evaluation criterion, but its real-time update is conducive to suit the stage achievement of every one-phase, thus evaluation phase achievement more exactly.
Concluding a research item management process: check and accept the TRL of each stage achievement and gordian technique point, and examination achievement is transferred to database storage.Implement management process corresponding to the management to each stage, concluding a research item management process is the checking to each stage, and the product acceptance data of acquisition is stored in database, can compare and analyze with evaluation index, stage achievement, project information etc.
Technology commodity shelf system construction step: gather in front four steps and be stored into the data in database, file, analyze and evaluate, the data that draw based on filing, analysis and evaluation again, adopt FusionChart chart assembly to be formed for the technology commodity shelf system of management and evaluation electrical network science and technology item.
On the basis of technique scheme, the present invention can also do following improvement.
Further, described project verification management process also comprises: the TRL retrieval science and technology item achievement storehouse of putting by gordian technique, science and technology item TRL to same technical field carries out lateral continuity comparison, obtain technology trends and the technological growth point in this field, and the technology trends of acquisition and technological growth point are transferred to database storage.
Further, described project verification management process also comprises TRL is defined the level, and the current TRL progression of definite gordian technique point and expection TRL progression, more current TRL progression and expection TRL progression are transferred to database storage.
Further, described enforcement management process also comprises according to the TRL grade of the corresponding electrical network science and technology item of TRL classification of different gordian technique points, if that is: the TRL grade of each gordian technique point is not identical, get the TRL grade of minimum TRL grade as corresponding electrical network science and technology item, otherwise directly get the TRL grade of each gordian technique as the TRL grade of corresponding electrical network science and technology item.
Further, the project information in described implementation process comprises implementation plan, monthly magazine, commercial matters information and/or payment funding information.
Technical scheme of the present invention also comprises a kind of electrical network science and technology item control system; for building a technology commodity shelf system for management and evaluation electrical network science and technology item, comprise that the project verification administration module, enforcement administration module, index update module, concluding a research item administration module and the technology commodity shelf system that connect successively build module;
Project verification administration module: for determining some gordian technique points of electrical network science and technology item, and set up the evaluation index of each gordian technique point based on tri-dimensions of the ready horizontal TRL of professional skill field, scientific and technological achievement type and technology, then evaluation index is stored into database;
Implement administration module: for gathering project information and the stage achievement of the project implementation process, and project information and stage achievement are transferred to database storage;
Index update module: for from data base call evaluation index and stage achievement, divide the TRL grade of gordian technique point according to stage achievement, and synchronously upgrade three dimensions of gordian technique point, realize the real-time update of evaluation index;
Concluding a research item administration module: for checking and accepting the TRL of each stage achievement and gordian technique point, and examination achievement is transferred to database;
Technology commodity shelf system builds module: for gathering front four modules, be stored into the data in database, file, analyze and evaluate, the data that draw based on filing, analysis and evaluation again, adopt FusionChart chart assembly to be formed for the technology commodity shelf system of management and evaluation electrical network science and technology item.
Further, described project verification administration module is the TRL retrieval science and technology item achievement storehouse for putting by gordian technique also, science and technology item TRL to same technical field carries out lateral continuity comparison, obtain technology trends and the technological growth point in this field, and the technology trends of acquisition and technological growth point are transferred to database storage.
Further, described project verification administration module is also for TRL is defined the level, and the current TRL progression of definite gordian technique point and expection TRL progression, more current TRL progression and expection TRL progression are transferred to database storage.
Further, described enforcement administration module is also for according to the TRL grade of the corresponding electrical network science and technology item of TRL classification of different gordian technique points, if that is: the TRL grade of each gordian technique point is not identical, get the TRL grade of minimum TRL grade as corresponding electrical network science and technology item, otherwise directly get the TRL grade of each gordian technique as the TRL grade of corresponding electrical network science and technology item.
Further, the project information in described implementation process comprises implementation plan, monthly magazine, commercial matters information and/or payment funding information.
The invention has the beneficial effects as follows: the present invention, take the technical field of the special industry of electrical network, the ready level of science and technology item technology, three key elements of scientific and technological achievement type as basis, realizes the key elements such as the upper technology maturity of understanding in real time and control the science and technology item of the various dimensions such as different majors segmentation field, carrier, achievement form, time cycle of macroscopic view, goods shelf products degree, technology added value; On microcosmic, can grasp the lot of essential factors such as research course, achievement in research, technology succession and sharing capability, the technological growth point of single technical research point comprehensively.The technology shelf that design by the present invention, realize Scientific Research And Technical Achievements and technical capability quantitatively evaluating and management, realize the analysis of scientific research technology layout, trend analysis, technical development and inheritance capability horizontal analysis, realize data integration, to scientific and technological research direction, science and technology item project verification, provide guidance foundation, scientific research technology continued ability to innovate and potential value be can reflect comprehensively, scientific research investment benefit and efficiency improved.
Accompanying drawing explanation
Fig. 1 is the schematic flow sheet of electrical network science and technology item control method of the present invention;
Fig. 2 is the project verification model schematic diagram that three dimensions based on gordian technique point of the present invention are set up;
Fig. 3 is the structural representation of electrical network science and technology item control system of the present invention;
Fig. 4 is the workflow schematic diagram of electrical network science and technology item control system of the present invention.
Embodiment
Below in conjunction with accompanying drawing, principle of the present invention and feature are described, example, only for explaining the present invention, is not intended to limit scope of the present invention.
The present embodiment provides a kind of electrical network science and technology item control method, object is to build a technology commodity shelf system for management and evaluation electrical network science and technology item, as shown in Figure 1, concrete steps comprise: project verification management process, enforcement management process, index step of updating, concluding a research item management process and technology commodity shelf system construction step.
One, project verification management process.
This step is mainly to determine some gordian technique points of electrical network science and technology item, and based on tri-dimensions of the ready horizontal TRL of professional skill field, scientific and technological achievement type and technology, set up the evaluation index of each gordian technique point, evaluation index is stored into database by data bus.As shown in Figure 2, be respectively x, y, z axle and illustrated three dimensions of the ready level of professional skill field, scientific and technological achievement type and technology of gordian technique point, and provided respectively the relevant parameter of these three dimensions, be that patented technology field is divided into that Electric Power Network Planning technology, electric system computation model are set up, large electrical network wide area monitoring technology ..., the field such as systematic analysis, scientific and technological achievement type is divided into three kinds of hardware, software and methods, and the ready level of technology adopts 9 grades altogether.And about the deciding grade and level of TRL, need determine according to the actual conditions of corresponding enterprise, such as the statement of progression, progression with substantially describe and the corresponding equipment of each progression, software, method requirement etc., there is no unified standard, each enterprise should be according to practice and data analysis situation etc., and design is applicable to the TRL deciding grade and level of self.
Described project verification management process also comprises: the TRL retrieval science and technology item achievement storehouse of putting by gordian technique, the science and technology item TRL of same technical field is carried out to lateral continuity comparison, and obtain technology trends and the technological growth point in this field; And TRL is defined the level, and the current TRL progression of definite gordian technique point and expection TRL progression.Here, the technology trends of acquisition, technological growth point, current TRL progression and expection TRL progression all need to transfer to database storage by data bus.
The project verification administrative section of the corresponding scientific research project management process of this step is in fact to have set up a project verification model.According to foregoing description, in actual project verification, declare the stage, need in application form, increase the information such as technical field, gordian technique point and TRL declare.The evaluation index (three dimensions) of gordian technique point, be stored into database, and after the data formation technology commodity shelf system of finally storing by database, can in technology commodity shelf system, the form with functional module show, project manager is in the project application stage, click corresponding functional module, can obtain from technology commodity shelf system gordian technique point, professional skill field, scientific and technological achievement type and the ready level of technology of relevant item, for project verification provides foundation.Should be noted, in the application form and application for developing of national science and technology item, the content of existing TRL and gordian technique point, grid company project, institute's mean terms object stage of declaring need the relevant informations such as increase " technical field, " " gordian technique point title " and " current TRL ", " expection TRL " make a report on.Project leader is with reference to the data that obtain from technology commodity shelf system, fill in project verification application form, and submit to Acceptance application to workflow to examine, by examining rear project leader, prepare examination data, by the full-time tissue of science and technology item management, check and accept meeting (proceeding to Review Workflow), project verification examination, take application form as foundation, is investigated technical field, gordian technique point, TRL, confirms to agree to project verification.The project that experts' evaluation is passed through enters declares storehouse.
Two, implement management process and index step of updating.
Implementing management process is mainly project information and the stage achievement gathering in the project implementation process, and project information and stage achievement are transferred to database storage by data bus; Index step of updating is mainly from data base call evaluation index and stage achievement, divides the TRL grade of gordian technique point according to stage achievement, and synchronously upgrades three dimensions of gordian technique point, realizes the real-time update of evaluation index.In addition, implementing management process also comprises according to the TRL grade of the corresponding electrical network science and technology item of TRL classification of different gordian technique points, if that is: the TRL grade of each gordian technique point is not identical, get the TRL grade of minimum TRL grade as corresponding electrical network science and technology item, otherwise directly get the TRL grade of each gordian technique as the TRL grade of corresponding electrical network science and technology item.And project information in described implementation process comprises implementation plan, monthly magazine, commercial matters information and/or payment funding information etc.
The implementation process management phase of the corresponding scientific research project management process of these two steps, is specifically related to implementation plan and formulates the stage (or claiming to open the topic stage) and intermediate inspection evaluation stage.
Implementation plan is formulated the stage: project manager is according to project verification model, make a report on implementation plan, implementation plan should comprise technical field, gordian technique point (WBS), TRL and stage achievement list, and foundation is take task as guiding, to submit the work program of thing as the year-by-year of evaluation foundation to.In addition, implementation plan also should comprise task, milestone, fund three main clues.
The intermediate inspection evaluation stage: project leader fills in intermediate inspection application form, and submit to Acceptance application to workflow to examine, by examining rear project leader, prepare examination data, by the full-time tissue of science and technology item management, check and accept meeting (proceeding to Review Workflow), intermediate inspection is take application form as foundation, gordian technique point, TRL are investigated, confirm to agree to pass through, the project that experts' evaluation is passed through enters declares storehouse.
Three, concluding a research item management process.
This step is mainly used for checking and accepting the TRL of each stage achievement and gordian technique point, and examination achievement is transferred to database by data bus.
In the concluding a research item stage of the corresponding scientific research project management process of this step, need complete and check and accept and filing.Examination should be take implementation plan as foundation, project leader fills in Acceptance application table to the project that can check and accept, and submit to Acceptance application to workflow to examine, by examining rear project leader, prepare examination data, by the full-time tissue of science and technology item management, check and accept meeting (proceeding to Review Workflow), examination, take implementation plan as foundation, is investigated gordian technique point, TRL and stage achievement, confirms concluding.
Four, technology commodity shelf system construction step
This step is mainly used for gathering in front four steps and is stored into the data in database, file, analyze and evaluate, the data that draw based on filing, analysis and evaluation again, adopt FusionChart chart assembly to be formed for the technology commodity shelf system of management and evaluation electrical network science and technology item.Specifically comprise the data such as the evaluation index of real-time update, project information, stage achievement, checking achievement and TRL grade are carried out to Classifying Sum, and consolidation is unified system documentation, corresponding data is analyzed, to be evaluated accordingly.
The structure of technology shelf is realized by FusionChart chart assembly, and this chart assembly, by Adobe Flash, with the data input of XML form, is realized pictorialization, mobilism and the interactivity of data display.By using FusionChart can generate easily the icons such as beautiful histogram, curve map, show that data are directly perceived, clear.By the effect of FusionChart chart assembly, the technology commodity shelf system forming has been stored the mass data recalling from database, and in shelf mode to data and the correlation analysis to it and the evaluation storage of classifying, very clear, to facilitate relevant responsible official's calling data, and clearly shown project performance simultaneously.
As shown in Figure 3; the present embodiment has also provided a kind of electrical network science and technology item control system simultaneously; it is corresponding one by one with the technical scheme of above-mentioned electrical network science and technology item control method, comprises that the project verification administration module, enforcement administration module, index update module, concluding a research item administration module and the technology commodity shelf system that connect successively build module;
Project verification administration module: for determining some gordian technique points of electrical network science and technology item, and set up the evaluation index of each gordian technique point based on tri-dimensions of the ready horizontal TRL of professional skill field, scientific and technological achievement type and technology, then evaluation index is stored into database;
Implement administration module: for gathering project information and the stage achievement of the project implementation process, and project information and stage achievement are transferred to database storage;
Index update module: for from data base call evaluation index and stage achievement, divide the TRL grade of gordian technique point according to stage achievement, and synchronously upgrade three dimensions of gordian technique point, realize the real-time update of evaluation index;
Concluding a research item administration module: for checking and accepting the TRL of each stage achievement and gordian technique point, and examination achievement is transferred to database;
Technology commodity shelf system builds module: for gathering front four modules, be stored into the data in database, file, analyze and evaluate, the data that draw based on filing, analysis and evaluation again, adopt FusionChart chart assembly to be formed for the technology commodity shelf system of management and evaluation electrical network science and technology item.
In this electrical network science and technology item control system, can be by project verification administration module, implement administration module, index update module, concluding a research item administration module and technology commodity shelf system and build module integration on the conventional scientific research comprehensive management platform in this area, utilize this scientific research comprehensive management platform to complete the structure of completing technology commodity shelf system, much more no longer the five steps of the corresponding above-mentioned electrical network science and technology item control method of the concrete function of each module and implementation detail, state here.
The final purpose of the present embodiment is to build a technology commodity shelf system for management and evaluation electrical network science and technology item, the technology commodity shelf system forming is integrated with the evaluation index of the gordian technique point of setting up based on tri-dimensions of the ready horizontal TRL of professional skill field, scientific and technological achievement type and technology and based on the definite project verification model of this evaluation index, is also integrated with according to project verification model and implements stage achievement, project information, each stage TRL grade and the final examination achievement that electrical network science and technology item obtains.The data that this technology commodity shelf system shows that to be similar to shelf mode it has, and be integrated with analysis and the evaluation according to corresponding data, carried out simultaneously.Person skilled can, by the corresponding data in scientific research comprehensive management platform calling technology commodity shelf system, also can in real time, clearly obtain project status by technology commodity shelf system simultaneously.
As shown in Figure 4, be the communication situation between scientific research comprehensive management platform and technology commodity shelf system, the concrete implementation step of its representative, as described below.
1.: when project manager sets up the project in scientific research total management system, from technology commodity shelf system, obtain same area project verification information, comprise the ready level of technology of project information (comprising the project scheduling, implementation process, achievement etc.), gordian technique point etc.;
2.: project is opened after topic, the milestone plan of project, project, achievement plan, fund planning are synchronized to technology commodity shelf system, in technology commodity shelf system, save as and grinding project information;
3.: after project intermediate inspection, the intermediate inspection result of project need be synchronized to technology commodity shelf system grinding in project information;
4.: the information of project monthly magazine, comprises that the information such as research progress, number percent, of that month research contents synchronously save as the project information of technology commodity shelf system; By the progress of project, the information that comprises commercial progress, bid and contract signing is synchronously the project information of technology commodity shelf system; By the payment funding information of project and fund completion rate etc., it is synchronously the project information of technology commodity shelf system;
5.: the stage achievement information of process achievement is synchronously the project information of technology commodity shelf system, with shelf form, represents;
6.: after the project acceptance inspection, all information of project, comprise the project scheduling, implementation process, achievement etc., enter technology commodity shelf system, by technology commodity shelf system, carry out domain analysis, Analysis on Results, project analysis and gordian technique point analysis etc.
The foregoing is only preferred embodiment of the present invention, in order to limit the present invention, within the spirit and principles in the present invention not all, any modification of doing, be equal to replacement, improvement etc., within all should being included in protection scope of the present invention.

Claims (8)

1. an electrical network science and technology item control method, is characterized in that, for building a technology commodity shelf system for management and evaluation electrical network science and technology item, concrete steps comprise:
Project verification management process: determine some gordian technique points of electrical network science and technology item, and set up the evaluation index of each gordian technique point based on tri-dimensions of the ready horizontal TRL of professional skill field, scientific and technological achievement type and technology, evaluation index is stored into database;
Implement management process: gather project information and stage achievement in the project implementation process, and project information and stage achievement are transferred to database storage;
Index step of updating: from data base call evaluation index and stage achievement, divide the TRL grade of gordian technique point according to stage achievement, and synchronously upgrade three dimensions of gordian technique point, realize the real-time update of evaluation index;
Concluding a research item management process: check and accept the TRL of each stage achievement and gordian technique point, and examination achievement is transferred to database storage;
Technology commodity shelf system construction step: gather in front four steps and be stored into the data in database, file, analyze and evaluate, the data that draw based on filing, analysis and evaluation again, adopt FusionChart chart assembly to be formed for the technology commodity shelf system of management and evaluation electrical network science and technology item.
2. electrical network science and technology item control method according to claim 1, it is characterized in that, described project verification management process also comprises: the TRL retrieval science and technology item achievement storehouse of putting by gordian technique, science and technology item TRL to same technical field carries out lateral continuity comparison, obtain technology trends and the technological growth point in this field, and the technology trends of acquisition and technological growth point are transferred to database storage.
3. electrical network science and technology item control method according to claim 1, it is characterized in that, described project verification management process also comprises TRL is defined the level, and the current TRL progression of definite gordian technique point and expection TRL progression, more current TRL progression and expection TRL progression are transferred to database storage.
4. electrical network science and technology item control method according to claim 1, it is characterized in that, described enforcement management process also comprises according to the TRL grade of the corresponding electrical network science and technology item of TRL classification of different gordian technique points, if that is: the TRL grade of each gordian technique point is not identical, get the TRL grade of minimum TRL grade as corresponding electrical network science and technology item, otherwise directly get the TRL grade of each gordian technique as the TRL grade of corresponding electrical network science and technology item.
5. an electrical network science and technology item control system, it is characterized in that, for building a technology commodity shelf system for management and evaluation electrical network science and technology item, comprise that the project verification administration module, enforcement administration module, index update module, concluding a research item administration module and the technology commodity shelf system that connect successively build module:
Project verification administration module: for determining some gordian technique points of electrical network science and technology item, and set up the evaluation index of each gordian technique point based on tri-dimensions of the ready horizontal TRL of professional skill field, scientific and technological achievement type and technology, then evaluation index is stored into database;
Implement administration module: for gathering project information and the stage achievement of the project implementation process, and project information and stage achievement are transferred to database storage;
Index update module: for from data base call evaluation index and stage achievement, divide the TRL grade of gordian technique point according to stage achievement, and synchronously upgrade three dimensions of gordian technique point, realize the real-time update of evaluation index;
Concluding a research item administration module: for checking and accepting the TRL of each stage achievement and gordian technique point, and examination achievement is transferred to database;
Technology commodity shelf system builds module: for gathering front four modules, be stored into the data in database, file, analyze and evaluate, the data that draw based on filing, analysis and evaluation again, adopt FusionChart chart assembly to be formed for the technology commodity shelf system of management and evaluation electrical network science and technology item.
6. electrical network science and technology item control system according to claim 5, it is characterized in that, described project verification administration module is the TRL retrieval science and technology item achievement storehouse for putting by gordian technique also, science and technology item TRL to same technical field carries out lateral continuity comparison, obtain technology trends and the technological growth point in this field, and the technology trends of acquisition and technological growth point are transferred to database storage.
7. electrical network science and technology item control system according to claim 5, it is characterized in that, described project verification administration module is also for TRL is defined the level, and the current TRL progression of definite gordian technique point and expection TRL progression, more current TRL progression and expection TRL progression are transferred to database storage.
8. electrical network science and technology item control system according to claim 5, it is characterized in that, described enforcement administration module is also for according to the TRL grade of the corresponding electrical network science and technology item of TRL classification of different gordian technique points, if that is: the TRL grade of each gordian technique point is not identical, get the TRL grade of minimum TRL grade as corresponding electrical network science and technology item, otherwise directly get the TRL grade of each gordian technique as the TRL grade of corresponding electrical network science and technology item.
CN201410032862.2A 2014-01-23 2014-01-23 Control method and system of science and technology item Pending CN103761618A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410032862.2A CN103761618A (en) 2014-01-23 2014-01-23 Control method and system of science and technology item

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410032862.2A CN103761618A (en) 2014-01-23 2014-01-23 Control method and system of science and technology item

Publications (1)

Publication Number Publication Date
CN103761618A true CN103761618A (en) 2014-04-30

Family

ID=50528852

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410032862.2A Pending CN103761618A (en) 2014-01-23 2014-01-23 Control method and system of science and technology item

Country Status (1)

Country Link
CN (1) CN103761618A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106529895A (en) * 2016-09-23 2017-03-22 中国农业科学院农业信息研究所 Science and technology project information management method based on two-dimensional code
CN107688896A (en) * 2017-08-10 2018-02-13 南方电网科学研究院有限责任公司 Science Research Information Management System, method, storage medium and its computer equipment
CN110097265A (en) * 2019-04-19 2019-08-06 中国电子产品可靠性与环境试验研究所((工业和信息化部电子第五研究所)(中国赛宝实验室)) Acquisition methods, device and the storage medium of the ready degree of Project Technical
CN110414757A (en) * 2018-04-28 2019-11-05 南方电网科学研究院有限责任公司 A kind of management system and management method of technology project verification risk control
CN111401842A (en) * 2020-03-14 2020-07-10 中国铁道科学研究院集团有限公司铁道建筑研究所 Science and technology type enterprise project overall process management system
CN114926012A (en) * 2022-05-16 2022-08-19 广东省技术经济研究发展中心 Intelligent acceptance and review method and system for research and development project and readable storage medium
CN116187299A (en) * 2023-03-07 2023-05-30 广东省技术经济研究发展中心 Scientific and technological project text data verification and evaluation method, system and medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070203912A1 (en) * 2006-02-28 2007-08-30 Thuve Matthew L Engineering manufacturing analysis system
CN102402732A (en) * 2010-09-14 2012-04-04 中国船舶工业综合技术经济研究院 Method and system for evaluating scientific research projects
CN102567837A (en) * 2010-12-31 2012-07-11 青岛海尔软件有限公司 Science and technology project management system
CN102890753A (en) * 2012-10-24 2013-01-23 北京信息控制研究所 Technology readiness level (TRL) determination method based on technology readiness attribute
CN103391317A (en) * 2013-07-11 2013-11-13 厦门大学 Evaluation method and device for system technology maturity

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070203912A1 (en) * 2006-02-28 2007-08-30 Thuve Matthew L Engineering manufacturing analysis system
CN102402732A (en) * 2010-09-14 2012-04-04 中国船舶工业综合技术经济研究院 Method and system for evaluating scientific research projects
CN102567837A (en) * 2010-12-31 2012-07-11 青岛海尔软件有限公司 Science and technology project management system
CN102890753A (en) * 2012-10-24 2013-01-23 北京信息控制研究所 Technology readiness level (TRL) determination method based on technology readiness attribute
CN103391317A (en) * 2013-07-11 2013-11-13 厦门大学 Evaluation method and device for system technology maturity

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
文爱军等: "国家电网公司科研项目管理系统研究与实现", 《电信科学》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106529895A (en) * 2016-09-23 2017-03-22 中国农业科学院农业信息研究所 Science and technology project information management method based on two-dimensional code
CN107688896A (en) * 2017-08-10 2018-02-13 南方电网科学研究院有限责任公司 Science Research Information Management System, method, storage medium and its computer equipment
CN110414757A (en) * 2018-04-28 2019-11-05 南方电网科学研究院有限责任公司 A kind of management system and management method of technology project verification risk control
CN110097265A (en) * 2019-04-19 2019-08-06 中国电子产品可靠性与环境试验研究所((工业和信息化部电子第五研究所)(中国赛宝实验室)) Acquisition methods, device and the storage medium of the ready degree of Project Technical
CN111401842A (en) * 2020-03-14 2020-07-10 中国铁道科学研究院集团有限公司铁道建筑研究所 Science and technology type enterprise project overall process management system
CN114926012A (en) * 2022-05-16 2022-08-19 广东省技术经济研究发展中心 Intelligent acceptance and review method and system for research and development project and readable storage medium
CN116187299A (en) * 2023-03-07 2023-05-30 广东省技术经济研究发展中心 Scientific and technological project text data verification and evaluation method, system and medium
CN116187299B (en) * 2023-03-07 2024-03-15 广东省技术经济研究发展中心 Scientific and technological project text data verification and evaluation method, system and medium

Similar Documents

Publication Publication Date Title
CN103761618A (en) Control method and system of science and technology item
CN103942716B (en) A kind of enterprise tax administration control platform and realize the method for enterprise tax administration control
Rad et al. Designing a hybrid system dynamic model for analyzing the impact of strategic alignment on project portfolio selection
CN105069524B (en) Planned dispatching optimization method based on big data analysis
CN103679373B (en) Produce the full chain budgetary data processing system and method for capital construction standard costs system
CN112465011B (en) Project risk prediction method and system based on project research and development process
Drobyazko et al. Formation of hybrid costing system accounting model at the enterprise
CN102855525B (en) A kind of resident's load prediction analytic system and method
CN109493003A (en) Item data management method and terminal device
CN111291994A (en) Multi-project management system and method suitable for agile development mode in big data environment
CN109816266A (en) The method and system of engineering economy data real time contrast are carried out using time dimension
CN109558412A (en) The data growing method and device of assembled architecture construct platform
CN103177307B (en) Workflow control system
CN110390475A (en) A kind of early warning and decision support method based on group's big data
CN112183916A (en) Land reserve life cycle management system
Dounos et al. Factors for the design of CMMI-based software process improvement initiatives
CN110599041A (en) Enterprise target management method, cloud and system based on artificial intelligence technology
CN106991516A (en) A kind of investment planning method and system based on power network resources
CN104462372A (en) Method and system for project schedule control based on file driving
CN115577971A (en) Staff ability dynamic value evaluation system based on algorithm model
CN103455606B (en) A kind of large database concept creates and data managing method
CN110298562A (en) A kind of distribution network construction audit grid-based management method
Ng et al. Relationships between interdependency, reliability, and vulnerability of infrastructure systems: Case study of biofuel infrastructure development
Chengmeng An analysis of the cost of the application of ERP system
Christodoulou et al. Resource-constrained scheduling of construction projects and simulation of the entropy impact on a project’s duration and cost

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140430