CN103605814B CN201310670691.1A CN201310670691A CN103605814B CN 103605814 B CN103605814 B CN 103605814B CN 201310670691 A CN201310670691 A CN 201310670691A CN 103605814 B CN103605814 B CN 103605814B
Authority
CN
China
Prior art keywords
file
icd
former
information
amended
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310670691.1A
Other languages
Chinese (zh)
Other versions
CN103605814A (en
Inventor
邹晖
吴劲晖
檀庭芳
王巍巍
纪陵
毛海波
陈彩霞
吴建伟
刘威
柯梦晗
祝碧贤
杜浩良
徐峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Guodiannanzi Software Engineering Co Ltd
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Maintenance Branch of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Nanjing Guodiannanzi Software Engineering Co Ltd
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Maintenance Branch of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Guodiannanzi Software Engineering Co Ltd, State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, Maintenance Branch of State Grid Zhejiang Electric Power Co Ltd filed Critical Nanjing Guodiannanzi Software Engineering Co Ltd
Priority to CN201310670691.1A priority Critical patent/CN103605814B/en
Publication of CN103605814A publication Critical patent/CN103605814A/en
Application granted granted Critical
Publication of CN103605814B publication Critical patent/CN103605814B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/10File systems; File servers
    • G06F16/16File or folder operations, e.g. details of user interfaces specifically adapted to file systems
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Human Resources & Organizations (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Public Health (AREA)
  • Human Computer Interaction (AREA)
  • Data Mining & Analysis (AREA)
  • Databases & Information Systems (AREA)
  • General Engineering & Computer Science (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses an information processing method and an information processing system in a substation transformation process. The information processing method comprises the following steps that after the original ICD (IED Capability Description) document of target power equipment is modified, the obtained original ICD document of the target power equipment is compared with the modified ICD, first modified information which is modified previously in the modified ICD is confirmed, and then, the modification part in the modified ICD is directly imported into the corresponding part of an original SCD (Substation Configuration Description) document without importing the non-modified part, so that the problems of the increase of difficulty and workload of the field adjustment work, the reduction of efficiency of the field adjustment work and influence on the working efficiency of the substation transformation works as in the substation transformation process, when the original ICD document of the target power equipment needs to be modified a plurality of times, the corresponding part of the original SCD document is replaced with the modified ICD document a plurality of times and the original configuration of the target power equipment is correspondingly adjusted according to the ICD document modified each time in the prior art can be solved.

Description

A kind of information processing method during Transfomer Substation Reconstruction and system
Technical field
The present invention relates to Transfomer Substation Reconstruction technical field, the letter during more particularly to a kind of Transfomer Substation Reconstruction Breath processing method and system.
Background technology
With the fast development of electrical network, intelligent grid has become the Developing mainstream of power system, in order to adapt to intelligent grid Development, old-fashioned Transfomer Substation Reconstruction need to be become intelligent substation.It will usually need to intelligent power equipment during changing ICD(IED Capability Description, intelligent power equipment ability description)File is modified, due to becoming to whole The description of the configuration of all devices in power station is all in SCD(Substation Configuration Description, transformer station Configuration description)In file, so, once the former ICD file modification of certain power equipment, whole transformer station will necessarily be affected SCD file, now the appropriate section in the SCD file of this transformer station be necessary for modifying.For this reason, in prior art, generally Be all that the appropriate section in SCD file is deleted, more again import amended ICD file, so again to related subnet and GOOSE(Generic Object Oriented Substation Event, general towards transformer station's object time)Empty terminal Reconfigure and debug, to meet real work demand.
However, in actual transformation process, generally all the former ICD file of power equipment repeatedly can be changed, now, existing There is technology to be accomplished by repeatedly making amended ICD file replace SCD file appropriate section, and replacement is required for debugging this every time Power equipment configured after subnet and/or GOOSE void terminal arrangement(I.e. communication configuration and/or GOOSE configuration), increase Add difficulty and the workload of field adjustable work, reduce the efficiency of field adjustable work, especially in the transformation of transformer station Later stage needs ICD file is modified, and through so repeatedly working, leverages the work efficiency of Transfomer Substation Reconstruction engineering.
Content of the invention
In view of this, the invention provides the information processing method during a kind of Transfomer Substation Reconstruction and system, solve Correspondence after the ICD file modification of target power equipment it is necessary in the former SCD file of deletion transformer station in prior art Partial information, imports amended ICD file again, and also will again debug the amended with this of this target power equipment The related original configuration of ICD file, considerably increases difficulty and the workload of field adjustable work, reduces field adjustable work Efficiency, have impact on the technical problem of the efficiency of Transfomer Substation Reconstruction engineering.
For achieving the above object, the present invention provides following technical scheme:
A kind of information processing method during Transfomer Substation Reconstruction, methods described includes:
Obtain target power equipment former ICD file and amended ICD file;
Described former ICD file and described amended ICD file are compared, determine described amended ICD file In the first modification information;
Will be new with described first modification information corresponding part, generation in the described first modification information former SCD file of importing SCD file.
Preferably, after described acquisition target power equipment former ICD file and amended ICD file, and to institute State former ICD file and described amended ICD file is compared, determine the first modification in described amended ICD file Before information, methods described also includes:
According to preset requirement, judge whether to retain original configuration of described target power equipment;
If it is not, then described amended ICD file is introduced directly into civilian with described amended ICD in former SCD file The corresponding part of part;
According to the described amended ICD file importing in described former SCD file, to mesh described in described former SCD file Original configuration of mark power equipment is modified and is debugged, and generates new SCD file;
If it is, being directly entered described described former ICD file and described amended ICD file being compared, really The first modification information step in fixed described amended ICD file continues executing with.
Preferably, original configuration of described target power equipment includes communication configuration and/or GOOSE configuration.
Preferably, after generating new SCD file, methods described also includes:
Described new SCD file is compared with described former SCD file, determines second in described new SCD file Modification information;
Described second modification information is imported part corresponding with described second modification information in background data base.
Preferably, after generating new SCD file, methods described also includes:
Described new SCD file is compared with described former SCD file, determines the 3rd in described new SCD file Modification information;
By described 3rd modification information import background data base, and replace in described background data base with described 3rd modification The corresponding configuration information of information.
A kind of information processing system during Transfomer Substation Reconstruction, described system includes:
Acquiring unit:For obtaining target power equipment former ICD file and amended ICD file;
Relatively determining unit:Enter for the described former ICD file obtaining and amended ICD file to described acquiring unit Row compares, and determines the first modification information in described amended ICD file;
First information import unit:For described the first modification information comparing determining unit determination is imported former SCD literary composition Part corresponding with described first modification information in part, generates new SCD file.
Preferably, described system also includes:
First judging unit:For according to preset requirement, judging whether to retain original configuration of described target power equipment;
Second information modification unit:For when the judged result of described judging unit is no, by described amended ICD File is introduced directly into part corresponding with described amended ICD file in former SCD file;
Configuration information changes unit:For according to the described amended ICD file importing in described former SCD file, right Described in described former SCD file, the configuration information of original configuration of target electronic device is modified, and generates new SCD file.
Preferably, original configuration of described target power equipment includes:Communication configuration and/or GOOSE configuration.
Preferably, described system also includes:
Second judging unit:For being compared with described former SCD file to described new SCD file, determine described new SCD file in the second modification information;
Second information import unit:The second modification information for determining described second judging unit imports back-end data Part corresponding with described second modification information in storehouse.
Preferably, described system also includes:
3rd judging unit:For being compared with described former SCD file to described new SCD file, determine described new SCD file in the 3rd modification information;
3rd information import unit:The 3rd modification information for determining the 3rd judging unit imports background data base, And replace configuration information corresponding with described 3rd modification information in described background data base.
Understand via above-mentioned technical scheme, compared with prior art, the present disclosure provides a kind of Transfomer Substation Reconstruction During information processing method and system, after former ICD file modification to target power equipment, by this target obtaining Power equipment former ICD file and amended ICD file are compared, and determine in this amended ICD file and do change First modification information, afterwards, the transfer portion in amended ICD file is that the first modification information is introduced directly into former SCD literary composition The corresponding part of part, non-transfer portion need not import, thus solving during Transfomer Substation Reconstruction, target power is set When standby former ICD file is repeatedly changed, former SCD file need to repeatedly be replaced by this amended ICD file by prior art Corresponding part, and original configuration of this target power equipment is correspondingly debugged according to the ICD file of each modification, and increased existing The difficulty of field debugging efforts and workload, reducing the efficiency of field adjustable work, that is, avoiding the duplication of labour, improve The work efficiency of Transfomer Substation Reconstruction engineering.
Brief description
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing Have technology description in required use accompanying drawing be briefly described it should be apparent that, drawings in the following description be only this Inventive embodiment, for those of ordinary skill in the art, on the premise of not paying creative work, can also basis The accompanying drawing providing obtains other accompanying drawings.
Fig. 1 is the flow chart of the embodiment 1 of information processing method during a kind of Transfomer Substation Reconstruction of the present invention;
Fig. 2 is the flow chart of the embodiment 2 of information processing method during a kind of Transfomer Substation Reconstruction of the present invention;
Fig. 3 is the structural representation of the embodiment 1 of information processing system during a kind of Transfomer Substation Reconstruction of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation description is it is clear that described embodiment is only a part of embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of not making creative work Embodiment, broadly falls into the scope of protection of the invention.
The embodiment of the invention discloses information processing method and system during a kind of Transfomer Substation Reconstruction, when to target power The former ICD of equipment(IED Capability Description, intelligent power equipment ability description)After file modification, by right This target power equipment former ICD file obtaining and amended ICD file are compared, and determine this amended ICD file In did change the first modification information, afterwards, the transfer portion in amended ICD file is that the first modification information is direct Import former SCD(Substation Configuration Description, substation configuration description)The corresponding part of file , non-transfer portion need not import, thus solving the former ICD literary composition during Transfomer Substation Reconstruction, to target power equipment When part is repeatedly changed, the corresponding part of former SCD file need to repeatedly be replaced by this amended ICD file by prior art, and Correspondingly debug original configuration of this target power equipment according to the ICD file of each modification, and increased field adjustable work Difficulty and workload, reduce field adjustable work efficiency, that is, avoiding the duplication of labour, improve Transfomer Substation Reconstruction The work efficiency of engineering.
As shown in figure 1, the flow process for the embodiment 1 of information processing method during a kind of Transfomer Substation Reconstruction of the present invention Figure, the method can include:
Step S11:Obtain target power equipment former ICD file and amended ICD file.
Step S12:Former ICD file and amended ICD file are compared, determine in this amended ICD file The first modification information.
Step S13:This first modification information is imported corresponding part in former SCD file, generates new SCD literary composition Part.
The ICD literary composition of certain power equipment during old-fashioned Transfomer Substation Reconstruction is intelligent substation, often occurs Part needs situation about changing, and because transformer station is all generally using SCL language(Substation Configuration Description Language, substation configuration description language)To the IED in this transformer station(Intelligent Electronic Devices, intelligent power equipment)Configuration information be described, formed describe this IED function information ICD File, then by these ICD file generateds one be SCD file to whole transformer station configuration describing document, so, once target is electric The ICD file of power equipment changes, and the SCD file of its place transformer station is necessary for changing.In this regard, at the information of prior art Reason method is all to import amended ICD file every time in SCD file, substitutes civilian with this amended ICD in this SCD file The corresponding part of part, and again debug all and device-dependent configuration of this target power, such as communication configuration and/or GOOSE (Generic Object Oriented Substation Event, general towards transformer station's object time)Configuration, to meet The work requirements of intelligent grid.
However, in actual applications, it is not that entire contents are modified generally to the modification of former ICD file, because And, the original information of modification information and non-transfer portion that amended ICD file can include transfer portion is former ICD file pair Answer the information of part, then, prior art will be deleted with entirely amended ICD file corresponding part in SCD file, is substituted for In the mode of amended ICD file, necessarily having partial content in amended SCD file is and the phase in former SCD file Answer the content identical of part, thus, for this part identical content, above-mentioned replacement operation is actually insignificant, Belong to idle work operation.So, after the ICD file to this target power equipment is repeatedly changed, the operation of this idle work will Repeatedly the work efficiency of Transfomer Substation Reconstruction can be leveraged;And, every time amended ICD file is imported SCD literary composition It is necessary to the configuration related to this amended ICD file in tested target power equipment will be re-started after part Debugging, considerably increases difficulty and the workload of field adjustable work, reduces the efficiency of field adjustable work, thus further Have impact on the work efficiency of Transfomer Substation Reconstruction.
For this reason, the embodiment of the present invention is by comparing to the former ICD file of target power equipment and amended ICD file Relatively, so that it is determined that the content going out transfer portion in amended ICD file is the first modification information, and only by this first modification letter Breath imports the corresponding part in former SCD file, need not non-transfer portion content in amended ICD file, without deletion Corresponding part in former SCD file, it is to avoid the generation of idle work operation, improves the work efficiency of Transfomer Substation Reconstruction;And, Due to not deleting information in former SCD file, thus, it remains the device-dependent configuration of this target power, and it need not be carried out Repeating to debug, decrease field adjustable workload, improve the efficiency of field adjustable work, thus further increasing power transformation Stand transformation work efficiency.
As shown in Fig. 2 the flow process for the embodiment 2 of information processing method during a kind of Transfomer Substation Reconstruction of the present invention Figure, the method can include:
Step S21:Obtain target power equipment former ICD file and amended ICD file.
Step S22:According to preset requirement, judge whether to retain original configuration of this target power equipment, if it is, holding Row step S25, if it is not, then be directly entered step S23.
Wherein, this preset requirement can be to be actually needed to determine during Transfomer Substation Reconstruction, target power equipment Original configuration can include communication configuration and/or GOOSE configuration.
Step S23:Amended ICD file is introduced directly into corresponding part in former SCD file.
Step S24:According to the amended ICD file importing in former SCD file, to target power in this former SCD file Original configuration of equipment is modified and is debugged, and generates new SCD file.
In actual applications, due to not retaining original configuration of target power equipment, so, when entirely amended It is necessary to according to amended ICD file, to target power equipment, original configuration is repaiied after ICD file all imports SCD file Change and debug.During this of the embodiment of the present invention, when importing amended ICD file every time, former SCD file need not be deleted In appropriate section, as long as being introduced directly into this amended ICD file, decreasing the operating procedure of Transfomer Substation Reconstruction, carrying High work efficiency.
Step S25:Former ICD file and amended ICD file are compared, determine in this amended ICD file The first modification information.
Step S26:This first modification information is imported corresponding part in former SCD file, generates new SCD literary composition Part.
In embodiments of the present invention, the processing method relatively with above-mentioned steps S23~S24, step S25~step S26 institute The change content of the processing method providing is fewer, needs the configuration again debugged also relatively less, more improves transformer station The work efficiency of transformation, in actual applications, according to the practical situation of Transfomer Substation Reconstruction, and can select suitable processing method.
Wherein, in actual applications, obtain the new SCD file of transformer station by said method after, system configuration utility The instantiation configuration file of IED would generally be generated according to this SCD file(Configured IED Description file, letter Claim CID file), to control IED normal work.
Step S27:New SCD file is compared with former SCD file, determines that second in this new SCD file is repaiied Convert to breath.
Step S28:This second modification information is imported corresponding part in background data base.
In the practical application of transformer station, its SCD file generally will store in background data base, to become from now on Information needed is called from this background data base, thus ensureing the safe and reliable operation of this transformer station in the running in power station.
In embodiments of the present invention, equally in order to reduce idle work operation, improve work efficiency, it only will be amended In SCD file with respect to the transfer portion of former SCD file be second modification information import background data base, need not entirely be changed Rear SCD file imports corresponding prime information in background data base, and background data base without deletion, thus decreasing work Measure, improve the work efficiency of Transfomer Substation Reconstruction.
As another embodiment of the present invention, according to actual needs, being compared with former SCD file to new SCD file, Determine the 3rd modification information in this new SCD file(I.e. the second modification information)Afterwards, the 3rd modification information can also be led Enter background data base, and replace corresponding configuration information in this background data base.Its step S27 with the embodiment of the present invention ~step S28 belongs to the scope of the present invention, and the mode that the present invention does not import background data base to the second modification information is entered Row limits.
In the embodiment of the present invention, after the ICD file to target power equipment is modified, and this target power is being set When the SCD file of standby place transformer station is modified, by judging whether the original configuration needing to retain target power equipment, when When judged result is to be, then directly by the transfer portion of amended ICD file(I.e. the first modification information)Import SCD file, The non-transfer portion in amended ICD file need not be imported, and letter corresponding with this transfer portion in SCD file need not be deleted Breath, thus remaining original configuration of target power equipment, greatly reducing field adjustable workload and difficulty, improve scene The work efficiency of debugging, thus improve the work efficiency of Transfomer Substation Reconstruction;And when judged result for no when, then will entirely change ICD file afterwards is introduced directly into SCD file, without deleting appropriate section in this SCD file, corresponding prior art, also carries The high work efficiency of Transfomer Substation Reconstruction.In addition, after the completion of to SCD file modification, the method that the present invention is imported by increment, only The transfer portion of this SCD file is imported background data base, thus further increasing the work efficiency of Transfomer Substation Reconstruction.
As shown in figure 3, the structural representation of the information processing system during being a kind of Transfomer Substation Reconstruction of the present invention, this is System can include:
Acquiring unit S31:For obtaining target power equipment former ICD file and amended ICD file.
In actual applications, as another embodiment of the present invention, this system can also include:
First judging unit:For according to preset requirement, judging whether to retain original configuration of target power equipment.
Wherein, as further embodiment of this invention, this system can execute corresponding operating, tool by a system configuration utility Body, in the transformation process to transformer station, can be by a kind of function of " updating IED " of this system configuration utility design, at it The target power equipment needing to update is provided on the function interface providing, obtains corresponding amended ICD file, at this moment this is joined Instrument of putting generally ejects a reservation selection of configuration being provided with " retaining communication configuration " and " retaining GOOSE configuration " two options Window, now, staff can therefrom select, according to preset requirement, the original configuration needing to retain.
Second information modification unit:For judging unit judged result be no when, will be direct for amended ICD file Import corresponding part in former SCD file.
Configuration information changes unit:For according to the amended ICD file importing in former SCD file, to former SCD file Original configuration of middle target electronic device is modified and is debugged, and generates new SCD file.
Relatively determining unit S32:Carry out for the former ICD file obtaining and amended ICD file to acquiring unit S31 Relatively, determine the first modification information in amended ICD file.
Still with above-mentioned another embodiment, when the judged result of the first judging unit is to be, that is, retain target power equipment Communication configuration and GOOSE configuration, just can trigger this and compare determining unit S32.
First information import unit S33:For the first modification information comparing the determination of determining unit S32 is imported former SCD Part corresponding with the first modification information in file, generates new SCD file.
After completing the modification to the SCD file of transformer station, also need to be conducted into background data base, for this reason, this system Can also include:
Second judging unit:For being compared with former SCD file to the new SCD file generating, determine this new SCD The second modification information in file.
Wherein, this second modification information is the transfer portion in the new SCD file generating.
Second information import unit:The second modification information for determining the second judging unit imports in background data base Corresponding part.
Or, this system can also include:
3rd judging unit:For being compared with former SCD file to the new SCD file generating, determine this new SCD The 3rd modification information in file.
Wherein, the 3rd modification information is identical with the second modification information.
3rd information import unit:The 3rd modification information for determining the 3rd judging unit imports background data base, And replace corresponding configuration information in background data base.
In the embodiment of the present invention, when acquiring unit obtain target power equipment former ICD file and amended ICD file it Afterwards, by comparing determining unit, the former ICD file of target power equipment and amended ICD file are compared, determine In amended ICD file, the content of transfer portion is the first modification information, and by first information import unit only by this first Modification information imports the corresponding part in former SCD file, need not non-transfer portion content in amended ICD file, also no The corresponding part in former SCD file need to be deleted, it is to avoid the generation of idle work operation, improve the work effect of Transfomer Substation Reconstruction Rate;It is additionally, since and do not delete information in former SCD file, thus, it remains the device-dependent configuration of this target power, need not It is carried out repeat to debug, decreasing field adjustable workload, improve the efficiency of field adjustable work, thus further carrying The high work efficiency of Transfomer Substation Reconstruction.
It should be noted that further for words such as " first ", " second ", " the 3rd " occurring in the above embodiment of the present invention Language, it is not offered as orbution, and it is only to play difference effect.And the above embodiment of the present invention is a kind of exemplary Example, should not be taken as limiting, given particular content should in no way limit the purpose of the application.For example, described unit draw Point, only a kind of division of logic function, actual can have other dividing mode when realizing, and for example multiple units combine one Rise;In addition, multiple units can or assembly can in conjunction with or be desirably integrated into another system, or some features can be neglected Slightly, or do not execute.And, herein, term " inclusion ", "comprising" or its any other variant are intended to nonexcludability Comprise so that including a series of process of key elements, method, article or equipment not only include those key elements, but also Including other key elements being not expressly set out, or also include for this process, method, article or intrinsic the wanting of equipment Element, here will no longer repeat one by one, and those skilled in the art are creative making great efforts determination so long as not paying, and belong to the present invention Protection domain.
In this specification, each embodiment is described by the way of going forward one by one, and what each embodiment stressed is and other The difference of embodiment, between each embodiment identical similar portion mutually referring to.For system disclosed in embodiment For, because it corresponds to the method disclosed in Example, so description is fairly simple, say referring to method part in place of correlation Bright.
Described above to the disclosed embodiments, makes professional and technical personnel in the field be capable of or uses the present invention. Multiple modifications to these embodiments will be apparent from for those skilled in the art, as defined herein General Principle can be realized without departing from the spirit or scope of the present invention in other embodiments.Therefore, the present invention It is not intended to be limited to the embodiments shown herein, and be to fit to and principles disclosed herein and features of novelty phase one The scope the widest causing.

Claims (8)

1. the information processing method during a kind of Transfomer Substation Reconstruction is it is characterised in that methods described includes:
Obtain target power equipment former ICD file and amended ICD file;
According to preset requirement, judge whether to retain original configuration of described target power equipment;
If it is not, then by described amended ICD file be introduced directly in former SCD file with described amended ICD file pair The part answered;
According to the described amended ICD file importing in described former SCD file, to the electricity of target described in described former SCD file Original configuration of power equipment is modified and is debugged, and generates new SCD file;
If it is, being compared to described former ICD file and described amended ICD file, determine described amended ICD literary composition The first modification information in part;
Will be civilian with described first modification information corresponding part, the new SCD of generation in the described first modification information former SCD file of importing Part.
2. method according to claim 1 is it is characterised in that original configuration of described target power equipment includes communication and joins Put and/or GOOSE configuration.
3. method according to claim 1 and 2 is it is characterised in that after generating new SCD file, methods described is also Including:
Described new SCD file is compared with described former SCD file, determines the second modification in described new SCD file Information;
Described second modification information is imported part corresponding with described second modification information in background data base.
4. method according to claim 1 and 2 is it is characterised in that after generating new SCD file, methods described is also Including:
Described new SCD file is compared with described former SCD file, determines the 3rd modification in described new SCD file Information;
By described 3rd modification information import background data base, and replace in described background data base with described 3rd modification information Corresponding configuration information.
5. the information processing system during a kind of Transfomer Substation Reconstruction is it is characterised in that described system includes:
Acquiring unit:For obtaining target power equipment former ICD file and amended ICD file;
Relatively determining unit:Compare for the described former ICD file obtaining and amended ICD file to described acquiring unit Relatively, determine the first modification information in described amended ICD file;
First information import unit:For described the first modification information comparing determining unit determination is imported in former SCD file Part corresponding with described first modification information, generates new SCD file;
Described system also includes:
First judging unit:For according to preset requirement, judging whether to retain original configuration of described target power equipment;
Second information modification unit:For when the judged result of described judging unit is no, by described amended ICD file It is introduced directly into part corresponding with described amended ICD file in former SCD file;
Configuration information changes unit:For according to the described amended ICD file importing in described former SCD file, to described The configuration information of original configuration of target power equipment described in former SCD file is modified, and generates new SCD file.
6. system according to claim 5 is it is characterised in that original configuration of described target power equipment includes:Communication Configuration and/or GOOSE configuration.
7. the system according to claim 5 or 6 is it is characterised in that described system also includes:
Second judging unit:For being compared with described former SCD file to described new SCD file, determine described new SCD The second modification information in file;
Second information import unit:The second modification information for determining described second judging unit imports in background data base Part corresponding with described second modification information.
8. the system according to claim 5 or 6 is it is characterised in that described system also includes:
3rd judging unit:For being compared with described former SCD file to described new SCD file, determine described new SCD The 3rd modification information in file;
3rd information import unit:The 3rd modification information for determining the 3rd judging unit imports background data base, and replaces Change configuration information corresponding with described 3rd modification information in described background data base.
CN201310670691.1A 2013-12-10 2013-12-10 Information processing method and information processing system in substation transformation process Active CN103605814B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310670691.1A CN103605814B (en) 2013-12-10 2013-12-10 Information processing method and information processing system in substation transformation process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310670691.1A CN103605814B (en) 2013-12-10 2013-12-10 Information processing method and information processing system in substation transformation process

Publications (2)

Publication Number Publication Date
CN103605814A CN103605814A (en) 2014-02-26
CN103605814B true CN103605814B (en) 2017-02-15

Family

ID=50124036

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310670691.1A Active CN103605814B (en) 2013-12-10 2013-12-10 Information processing method and information processing system in substation transformation process

Country Status (1)

Country Link
CN (1) CN103605814B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104065163B (en) * 2014-06-19 2016-08-17 国家电网公司 Delivery method on a kind of intelligent substation warning information
CN104657176A (en) * 2015-02-09 2015-05-27 南京南瑞继保电气有限公司 File updating method and electronic equipment
CN106294750B (en) * 2016-08-10 2019-08-06 国家电网公司 ICD model file familial defect upgrade-system and method
CN106888113B (en) * 2017-01-21 2019-10-29 国网浙江省电力公司绍兴供电公司 A kind of method and device for intelligent substation business configuration
CN110896363B (en) * 2019-11-25 2022-07-29 东方电子股份有限公司 Plug-and-play access configuration method for IEC61850 intelligent device
CN115499520B (en) * 2022-11-21 2023-03-10 北京蓝天航空科技股份有限公司 Interface control file updating method and device, electronic equipment and storage medium

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102867274A (en) * 2012-07-27 2013-01-09 江苏省电力公司电力科学研究院 Management and graphical display system for intelligent substation SCL (substation configuration description language) configuration files
CN103399888A (en) * 2013-07-19 2013-11-20 广东电网公司电力科学研究院 Differential synchronization method and system for power grid model data

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102867274A (en) * 2012-07-27 2013-01-09 江苏省电力公司电力科学研究院 Management and graphical display system for intelligent substation SCL (substation configuration description language) configuration files
CN103399888A (en) * 2013-07-19 2013-11-20 广东电网公司电力科学研究院 Differential synchronization method and system for power grid model data

Also Published As

Publication number Publication date
CN103605814A (en) 2014-02-26

Similar Documents

Publication Publication Date Title
CN103605814B (en) Information processing method and information processing system in substation transformation process
CN105335584B (en) Distribution network systems line chart generates optimization device and method
CN105576660B (en) Local distribution network in-circuit emulation analytical equipment and system
CN106451556A (en) Method and apparatus for determining capability of receiving distributed power supply by distributed network feeder line
US20150294037A1 (en) System and method for automated substation design and configuration
CN102930111B (en) The generation method of transformer station's SCD model file and device
CN103217649A (en) Method and device for displaying electric quantity, and mobile device
CN104267365A (en) Portable small current earth-fault line selection closed loop performance tester
CN108388688A (en) A kind of active distribution network reliability estimation method
CN103746421A (en) Intelligent recognition system for optimal charging current and method thereof
CN105355021A (en) ZigBee-based remote wireless meter reading system and performance detection method thereof
CN104392307B (en) A kind of reliability estimation method based on distribution network automated engineering
CN104715144A (en) Power distribution network closed loop power flow simulation algorithm based on real-time running data
CN104504524A (en) Reliability assessment method and load curtailing method applied to active distribution network
CN108427821B (en) Digital-analog hybrid simulation method and system for operation characteristics of alternating-current/direct-current hybrid power grid
CN110048884A (en) Resist the intelligent distribution network communication network planing method of random attack and premeditated network attack
CN103036228A (en) Method for determining location of transformer substation and length of power supply circuit in power system planning process
CN103560497B (en) A kind of short circuit current method for limiting based on power network topology adjustment
CN109116139A (en) A kind of PoE interchanger band of low cost carries the ageing testing method of PD
CN102509168A (en) Improved integer programming method-based optimum PMU (Power Management Unit) placement method
CN105990878A (en) Charging method based on step current automatic adjustment, system and mobile terminal
CN109657332B (en) Method and system for decoupling electromagnetic transient automatic modeling of large-scale power grid
CN104218546B (en) A kind of self-healing recovery control method of intelligent distribution network
CN103778055B (en) A kind of key-press test method and device
CN106855592B (en) Dynamic simulation test wave recording message playback method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant