CN103514364B - The grid equipment overload aid decision computational methods of meter and load transfer measure - Google Patents

The grid equipment overload aid decision computational methods of meter and load transfer measure Download PDF

Info

Publication number
CN103514364B
CN103514364B CN201310332739.8A CN201310332739A CN103514364B CN 103514364 B CN103514364 B CN 103514364B CN 201310332739 A CN201310332739 A CN 201310332739A CN 103514364 B CN103514364 B CN 103514364B
Authority
CN
China
Prior art keywords
overload
equipment
measure
under
prevention device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310332739.8A
Other languages
Chinese (zh)
Other versions
CN103514364A (en
Inventor
胥传普
徐伟
王伟
徐泰山
毛俊
鲍颜红
金敏杰
马明
杨莹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nari Technology Co Ltd
Original Assignee
State Grid Shanghai Electric Power Co Ltd
Nanjing NARI Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shanghai Electric Power Co Ltd, Nanjing NARI Group Corp filed Critical State Grid Shanghai Electric Power Co Ltd
Priority to CN201310332739.8A priority Critical patent/CN103514364B/en
Publication of CN103514364A publication Critical patent/CN103514364A/en
Application granted granted Critical
Publication of CN103514364B publication Critical patent/CN103514364B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses the grid equipment overload aid decision computational methods of a kind of meter and load transfer measure, belong to technical field of power system operation control.The present invention, according to the state of equipment, determines load transfer candidate's measure collection;Use DC power flow to calculate the performance indications of candidate's measure, the implementation result of performance preferably candidate's measure is checked, and determine the solution generator of overload problem, the maximum adjustment amount of load active power adjustment measure on this basis;Then, form generator, load adjustment scheme according to the computational accuracy of active power adjustment, obtain numerical procedure, determine final aid decision measure according to the check result of each scheme.The present invention adds active power adjustment measure on the basis of load transfer measure, reduce generator adjustment amount and pressure load, carry out AC power flow check by parallel computation, it is to avoid take turns iteration more, improve economy and the calculating speed of overload aid decision of aid decision measure.

Description

The grid equipment overload aid decision computational methods of meter and load transfer measure
Technical field
The invention belongs to technical field of power system operation control, more precisely, the present invention relates to a kind of suitable Based on by and load transfer measure grid equipment overload aid decision computational methods.
Background technology
It is known that overload aid decision is the critical function that electrical power system on-line safety and stability is analyzed.Work as electricity When overload problem occurring under net current state and forecast failure, by overload aid decision, it is possible in line computation Generator, load active power adjustment measure.
Comparing active power adjustment measure, load transfer controlling measurement cost is less, simple to operate, regulates the speed fast. Throwing according to circuit and transformer stops state, inspecting state and the running status of adjacent factory station equipment, permissible ONLINE RECOGNITION load transfer candidate's measure collection.If putting into operation, a circuit or a transformer cannot solve overload and ask Topic, then determine the active power adjustment amount being fully solved overload problem.Therefore, it is contemplated that pass through meter and load Turn and reduce generator adjustment amount and pressure load for measure, improve the economy of overload aid decision measure.
Summary of the invention
It is an object of the invention to: according to the running status of equipment, ONLINE RECOGNITION load transfer candidate's measure collection, Can turn for adding active power adjustment measure on the basis of load by the equipment of putting into operation, reducing generator adjustment amount and pressure is negative Lotus amount, improves the economy of overload aid decision measure.
Specifically, the present invention is to use following technical scheme to realize, and comprises the following steps:
1) by overload nargin under electrical network current state less than setting threshold value ηcr.1Equipment and forecast failure Lower overload nargin is less than setting threshold value ηcr.1Equipment join overload prevention device concentrate, by under forecast failure Apparatus overload margin of safety minimum of a value is less than setting threshold value ηcr.2Forecast failure join critical failure concentrate, If overload prevention device is concentrated with overload prevention device, then enter step 2);Otherwise, method ends;
Described equipment refers to circuit and transformer;
2) if the switch tool group that Guan Bi and the equipment being in stoppage in transit and maintenance done state are joined directly together just can Equipment investment is run, and the joint that the node that is joined directly together of this equipment is joined directly together with overload prevention device concentrating equipment Point belongs to same electrical island, then this equipment adds the equipment that can put into operation and concentrates, if can be concentrated with by the equipment of putting into operation Can be put into operation equipment, then enter step 3);Otherwise, step 6) is entered;
3) it is respectively directed to concentrate each equipment that can put into operation by the equipment of putting into operation, uses DC power flow estimation to put into operation and set Concentrate the overload nargin of each equipment for overload prevention device after putting into operation, and calculate the comprehensive of equipment that can put into operation Energy index, if overload prevention device concentrates the overload nargin of all devices to be all higher than specifying threshold value ηthres.on, Then enter step 4);Otherwise enter step 5);
Described ηthres.on> ηcr.1
4) after using AC power flow to calculate putting equipment in service, overload prevention device concentrates the overload nargin of each equipment, And calculate the integrated performance index of equipment of can putting into operation, if overload prevention device is concentrated there is overload nargin less than ηcr.1 Equipment, then enter step 5);Otherwise, using put into operation equipment maximum for integrated performance index as final control Measure processed method ends;
5) choose integrated performance index to set as to be checked putting into operation more than the put into operation equipment of given threshold value Standby, enter step 6);
6) if there is put into operation equipment to be checked, the base for load is turned at each equipment measure that puts into operation the most respectively The solution generator of overload problem, the maximum adjustment amount of load active power adjustment measure is determined, the most directly on plinth Determine the solution generator of overload problem, the maximum adjustment amount of load active power adjustment measure;
7) according to generator, the maximum adjustment amount of load active power adjustment measure and the computational accuracy shape of active power adjustment Becoming generator, load adjustment scheme, if there is put into operation equipment to be checked, then to be checked being put into operation Equipment and generator, the combination of load adjustment scheme obtain the numerical procedure needing AC power flow to check, the most directly Connect generator, load adjustment scheme as the numerical procedure needing AC power flow to check, according to control measure Control cost ascending order numerical procedure is ranked up, by parallel computation, each scheme is carried out AC power flow for fault-free and critical failure collection is checked, if obtaining overload nargin more than ηcr.1Calculating Scheme, then terminate parallel computation, using this numerical procedure as the output of final control measure method ends; Otherwise, method ends.
Being further characterized by described step 1) of technique scheme uses different limit values to calculate electrical network With the overload nargin of jth equipment under forecast failure under current state:
When jth equipment is circuit, by formula (1) computation overload margin of safety ηj:
η j = ( 1 - I L I P ) × 100 % - - - ( 1 )
Wherein, when calculating the overload nargin of circuit under electrical network current state, ILFor circuit under current state The electric current of the bigger one end of two ends electric current, IPElectric current is allowed for circuit under normal running (operation) conditions;When calculating, electrical network is pre- When thinking the overload nargin of circuit under fault, ILFor the electric current of the bigger one end of circuit two ends electric current under forecast failure, IPRun for circuit under emergency conditions and allow electric current;
When jth equipment is transformer, pacified by the overload of formula (2) each winding of calculating transformer respectively Full nargin ηj,w, the overload nargin of this transformer equipment is overload nargin in each winding of this transformer Minimum of a value:
η j , w = ( 1 - S T / U T S P / U N , w ) × 100 % - - - ( 2 )
Wherein, the different windings of w indication transformer, UN,wRated voltage for each winding;Work as when calculating electrical network Under front state during the overload nargin of transformer, STAnd UTFor the apparent energy under winding current state and electricity Pressure, SPFor the permission capacity of transformer under normal condition;When calculating the overload of transformer under electrical network forecast failure During margin of safety, STAnd UTFor the apparent energy of winding under forecast failure and voltage, SPFor becoming under emergency conditions The permission capacity of depressor.
Being further characterized by described step 3) and step 4) by formula (3) of technique scheme Calculating can put into operation the integrated performance index of equipment:
p i L = Σ j = 1 N [ S i L , j ( 1 - η j ) ] + Σ k = 1 W Σ j 1 = 1 N k [ S i L , j 1 . k ( 1 - η j 1 . k ) ] - - - ( 3 )
Wherein, iL=1,2 ..., L, L are the sum of equipment of can putting into operation,It is i-thLThe individual equipment that puts into operation comprehensive Performance indications, N is the sum of overload prevention device, η under current statejOverload for jth overload prevention device is abundant Degree,It is i-thLThe overload nargin variable quantity of jth overload prevention device after the individual putting equipment in service that puts into operation;W For the sum of overload critical failure, NkFor the sum of overload prevention device under kth overload critical failure,For jth under kth overload critical failure1The overload nargin of individual overload prevention device,It is iLJth under kth overload critical failure after the individual putting equipment in service that puts into operation1Individual overload prevention device overload nargin Variable quantity.
Being further characterized by described step 6) of technique scheme determines the generating solving overload problem Machine, the step of maximum adjustment amount of load active power adjustment measure are divided into four steps:
, if there is put into operation equipment to be checked, then according to the apparatus overload safety after putting equipment in service in the first step Nargin calculates active power adjustment measure by formula (4) and combines overload under overload under current state and forecast failure Close performance indications;Otherwise, directly by formula (4) calculate active power adjustment measure under current state overload and The integrated performance index of overload under forecast failure:
w i M = Σ j = 1 N [ λ i M , j ( 1 - η j ) ] + Σ k = 1 W Σ j 1 = 1 N k [ λ i M , j 1 . k ( 1 - η j 1 . k ) ] - - - ( 4 )
Wherein, iM=1,2 ..., M, M are the sum of active power adjustment measure,It is i-thMIndividual active power adjustment measure Integrated performance index, N is the sum of overload prevention device, η under current statejOverload for jth overload prevention device Margin of safety,It is i-thMThe individual active power adjustment measure active po wer sensitivity to jth overload prevention device;W was Carry the sum of safety-critical fault, NkFor the sum of overload prevention device under kth overload critical failure, For jth under kth overload critical failure1The overload nargin of individual overload prevention device,It is i-thMIndividual Active power adjustment measure is to jth under kth fault1The active po wer sensitivity of individual equipment;
Second step, is more than the active power adjustment measure alternately measure setting threshold value by integrated performance index, Choose integrated performance index be negative alternative measure as power transmission queue, the generator node in queue is exerted oneself increasing Add and the meritorious reduction of load bus;Choosing integrated performance index is that positive alternative measure is as by electricity queue, team Generator node in row is exerted oneself reduction;
3rd step, is first according to the priority of control measure order from high to low to power transmission queue with by electricity team Alternative measure in row is ranked up, then to controlling the identical alternative measure of priority by cost performance index by greatly Being ranked up to little order, cost performance index is calculated by formula (5):
G i M = | w i M | / C i M - - - ( 5 )
Wherein,It is i-thMThe Readjusting cost of individual active power adjustment measure unit power;
4th step, makees the maximum adjustment amount of power transmission queue with the maximum in the maximum adjustment amount by electricity queue For determining the maximum adjustment amount of numerical procedure.
Being further characterized by described step 7) of technique scheme, for different adjustment amount requirements, By the adjustment order of the control measure determined in step 6), it is sequentially adjusted in power transmission queue and each joint by electricity queue Point so that control Least-cost and cause system frequency deviation to meet due to the active power imbalance of system Service requirement, obtains numerical procedure.
Beneficial effects of the present invention is as follows: the present invention can ONLINE RECOGNITION load transfer candidate's measure collection, negative Lotus turns for adding active power adjustment measure on the basis of measure, reduces generator adjustment amount and pressure load;According to having The computational accuracy that merit adjusts forms generator, load adjustment scheme, carries out AC power flow school by parallel computation Core, it is to avoid take turns iteration more.Therefore, the present invention proposes meter and the grid equipment overload of load transfer measure are auxiliary Help decision-making computational methods can improve economy and the calculating speed of overload aid decision of aid decision measure.
Accompanying drawing explanation
Fig. 1 is the flow chart of the inventive method.
Detailed description of the invention
With reference to the accompanying drawings and combine example the present invention is described in further detail.
What in Fig. 1, step 1 described is less than setting threshold value η by electrical network current state overload nargincr.1's Under equipment and forecast failure, overload nargin is less than setting threshold value ηcr.1Equipment join overload prevention device collection In, by equipment overload nargin minimum of a value under forecast failure less than setting threshold value ηcr.2Forecast failure add Concentrate to critical failure, if overload prevention device is concentrated with overload prevention device, then enter step 2);Otherwise, this is terminated Method.Described equipment refers to circuit and transformer.Overload nargin threshold value ηcr.1, it is used for determining that electrical network is worked as Overload prevention device under front state and forecast failure;Overload nargin threshold value ηcr.2, it is used for determining that participation calculates The forecast failure of aid decision measure integrated performance index.
Different limit values is used to calculate the overload of jth equipment under electrical network current state and forecast failure abundant Degree: when jth equipment is circuit, by formula (1) computation overload margin of safety ηj:
η j = ( 1 - I L I P ) × 100 % - - - ( 1 )
Wherein, when calculating the overload nargin of circuit under electrical network current state, ILFor circuit under current state The electric current of the bigger one end of two ends electric current, IPElectric current is allowed for circuit under normal running (operation) conditions;When calculating, electrical network is pre- When thinking the overload nargin of circuit under fault, ILFor the electric current of the bigger one end of circuit two ends electric current under forecast failure, IPRun for circuit under emergency conditions and allow electric current;
When jth equipment is transformer, pacified by the overload of formula (2) each winding of calculating transformer respectively Full nargin ηj,w, the overload nargin of this transformer equipment is overload nargin in each winding of this transformer Minimum of a value:
η j , w = ( 1 - S T / U T S P / U N , w ) × 100 % - - - ( 2 )
Wherein, the different windings of w indication transformer, UN,wRated voltage for each winding;Work as when calculating electrical network Under front state during the overload nargin of transformer, STAnd UTFor the apparent energy under winding current state and electricity Pressure, SPFor the permission capacity of transformer under normal condition;When calculating the overload of transformer under electrical network forecast failure During margin of safety, STAnd UTFor the apparent energy of winding under forecast failure and voltage, SPFor becoming under emergency conditions The permission capacity of depressor.
If what in Fig. 1, step 2 described is to close to be joined directly together with the equipment being in stoppage in transit and maintenance done state Switch tool group just equipment investment can be run, and the node that is joined directly together of this equipment and overload prevention device collection The node that middle equipment is joined directly together belongs to same electrical island, then this equipment adds the equipment that can put into operation and concentrates, If the equipment that can put into operation can be concentrated with the equipment of putting into operation, then enter step 3);Otherwise, step 6) is entered.
What in Fig. 1, step 3 described is to be respectively directed to concentrate each equipment that can put into operation by the equipment of putting into operation, and uses straight Flow overload prevention device after trend estimates the putting equipment in service that can put into operation and concentrate the overload nargin of each equipment, and calculate Can be put into operation the integrated performance index of equipment, if the overload nargin that overload prevention device concentrates all devices is all higher than Specify threshold value ηthres.on, wherein ηthres.on> ηcr.1, then step 4) is entered;Otherwise, step 5) is entered.Cross Carry margin of safety threshold value ηthres.on, for determining the put into operation equipment that overload can be completely eliminated.
The equipment that can put into operation is calculated comprehensive to transship under overload under current state and forecast failure by formula (3) Performance indications:
p i L = Σ j = 1 N [ S i L , j ( 1 - η j ) ] + Σ k = 1 W Σ j 1 = 1 N k [ S i L , j 1 . k ( 1 - η j 1 . k ) ] - - - ( 3 )
Wherein, iL=1,2 ..., L, L are the sum of equipment of can putting into operation,It is i-thLThe individual equipment that puts into operation comprehensive Performance indications, N is the sum of overload prevention device, η under current statejOverload for jth overload prevention device is abundant Degree,It is i-thLThe overload nargin variable quantity of jth overload prevention device after the individual putting equipment in service that puts into operation;W For the sum of overload critical failure, NkFor the sum of overload prevention device under kth overload critical failure,For jth under kth overload critical failure1The overload nargin of individual overload prevention device,It is iLJth under kth overload critical failure after the individual putting equipment in service that puts into operation1Individual overload prevention device overload nargin Variable quantity.
What in Fig. 1, step 4 described is that after using AC power flow to calculate putting equipment in service, overload prevention device concentrates each to set Standby overload nargin, and calculate the integrated performance index of the equipment that can put into operation, exist if overload prevention device is concentrated Overload nargin is less than ηcr.1Equipment, then enter step 5);Otherwise, can by maximum for integrated performance index The equipment that puts into operation is as final control measure method ends.
What in Fig. 1, step 5 described is to choose the integrated performance index equipment more than given threshold value as treating school The put into operation equipment of core, enters step 6).
If what in Fig. 1, step 6 described is to there is put into operation equipment to be checked, set each putting into operation the most respectively Standby measure turns for determining the solution generator of overload problem, load active power adjustment measure on the basis of load Big adjustment amount, the most directly determines the maximum tune solving the generator of overload problem, load active power adjustment measure Whole amount.Determine that the step of the maximum adjustment amount solving the generator of overload problem, load active power adjustment measure is divided It is four steps:
, if there is put into operation equipment to be checked, then according to the apparatus overload safety after putting equipment in service in the first step Nargin calculates active power adjustment measure by formula (4) and combines overload under overload under current state and forecast failure Close performance indications;Otherwise, directly by formula (4) calculate active power adjustment measure under current state overload and The integrated performance index of overload under forecast failure:
w i M = Σ j = 1 N [ λ i M , j ( 1 - η j ) ] + Σ k = 1 W Σ j 1 = 1 N k [ λ i M , j 1 . k ( 1 - η j 1 . k ) ] - - - ( 4 )
Wherein, iM=1,2 ..., M, M are the sum of active power adjustment measure,It is i-thMIndividual active power adjustment measure Integrated performance index, N is the sum of overload prevention device, η under current statejOverload for jth overload prevention device Margin of safety,It is i-thMThe individual active power adjustment measure active po wer sensitivity to jth overload prevention device;W was Carry the sum of safety-critical fault, NkFor the sum of overload prevention device under kth overload critical failure, For jth under kth overload critical failure1The overload nargin of individual overload prevention device,It is i-thMIndividual Active power adjustment measure is to jth under kth fault1The active po wer sensitivity of individual equipment.
Second step, is more than the active power adjustment measure alternately measure setting threshold value by integrated performance index, Choose integrated performance index be negative alternative measure as power transmission queue, the generator node in queue is exerted oneself increasing Add and the meritorious reduction of load bus;Choosing integrated performance index is that positive alternative measure is as by electricity queue, team Generator node in row is exerted oneself reduction.
3rd step, is first according to the priority of control measure order from high to low to power transmission queue with by electricity team Alternative measure in row is ranked up, then to controlling the identical alternative measure of priority by cost performance index by greatly It is ranked up to little order, by formula (5) calculating cost performance index:
G i M = | w i M | / C i M - - - ( 5 )
Wherein,It is i-thMThe Readjusting cost of individual active power adjustment measure unit power.
4th step, makees the maximum adjustment amount of power transmission queue with the maximum in the maximum adjustment amount by electricity queue For determining the maximum adjustment amount of numerical procedure.
What in Fig. 1, step 7 described is according to generator, the maximum adjustment amount of load active power adjustment measure and to have The computational accuracy that merit adjusts forms generator, load adjustment scheme, if there is put into operation equipment to be checked, Then obtain needing AC power flow to check with generator, the combination of load adjustment scheme by put into operation equipment to be checked Numerical procedure, otherwise directly using generator, load adjustment scheme as the calculating needing AC power flow to check Scheme, is ranked up numerical procedure according to the order that the control cost of control measure is ascending, by also Row calculates and carries out each scheme checking for the AC power flow of fault-free and critical failure collection, if obtaining overload peace Full nargin is more than ηcr.1Numerical procedure, then terminate parallel computation, using this numerical procedure as final control measure Output method ends;Otherwise, method ends
For different adjustment amount requirements, by the adjustment order of the control measure determined in step 6), adjust successively Whole power transmission queue and by electricity queue each node so that control Least-cost and due to system active power not Balance and cause system frequency deviation to meet service requirement, obtain numerical procedure.
Although the present invention is open as above with preferred embodiment, but embodiment is not for limiting the present invention's. Without departing from the spirit and scope of the invention, any equivalence change done or retouching, also belong to this Bright protection domain.Therefore the content that protection scope of the present invention should be defined with claims hereof For standard.

Claims (4)

1. the grid equipment overload aid decision computational methods of meter and load transfer measure, it is characterised in that bag Include following steps:
1) by overload nargin under electrical network current state less than setting threshold value ηcr.1Equipment and forecast failure Lower overload nargin is less than setting threshold value ηcr.1Equipment join overload prevention device concentrate, by under forecast failure Apparatus overload margin of safety minimum of a value is less than setting threshold value ηcr.2Forecast failure join critical failure concentrate, If overload prevention device is concentrated with overload prevention device, then enter step 2);Otherwise, method ends;
Described equipment refers to circuit and transformer;
2) if the switch tool group that Guan Bi and the equipment being in stoppage in transit and maintenance done state are joined directly together just can Equipment investment is run, and the joint that the node that is joined directly together of this equipment is joined directly together with overload prevention device concentrating equipment Point belongs to same electrical island, then this equipment adds the equipment that can put into operation and concentrates, if can be concentrated with by the equipment of putting into operation Can be put into operation equipment, then enter step 3);Otherwise, step 6 is entered);
3) it is respectively directed to concentrate each equipment that can put into operation by the equipment of putting into operation, uses DC power flow estimation to put into operation and set Concentrate the overload nargin of each equipment for overload prevention device after putting into operation, and calculate the comprehensive of equipment that can put into operation Energy index, if overload prevention device concentrates the overload nargin of all devices to be all higher than specifying threshold value ηthres.on, Then enter step 4);Otherwise enter step 5);
Described ηthres.on> ηcr.1
The integrated performance index of equipment of can putting into operation is calculated by formula (3):
p i L = Σ j = 1 N [ S i L , j ( 1 - η j ) ] + Σ k = 1 W Σ j 1 = 1 N k [ S i L , j 1 . k ( 1 - η j 1 . k ) ] - - - ( 3 )
Wherein, iL=1,2 ..., L, L are the sum of equipment of can putting into operation,It is i-thLCombining of the individual equipment that puts into operation Closing performance indications, N is the sum of overload prevention device, η under current statejOverload for jth overload prevention device Nargin,It is i-thLThe overload nargin variable quantity of jth overload prevention device after the individual putting equipment in service that puts into operation; W is the sum of overload critical failure, NkFor overload prevention device total under kth overload critical failure Number,For jth under kth overload critical failure1The overload nargin of individual overload prevention device,For I-thLJth under kth overload critical failure after the individual putting equipment in service that puts into operation1Individual overload prevention device overload is abundant Degree variable quantity;
4) after using AC power flow to calculate putting equipment in service, overload prevention device concentrates the overload nargin of each equipment, And the integrated performance index of the equipment that can be put into operation by formula (3) calculating, if overload prevention device is concentrated there is overload peace Full nargin is less than ηcr.1Equipment, then enter step 5);Otherwise, maximum the putting into operation of integrated performance index is set Standby as final control measure method ends;
5) choose integrated performance index to set as to be checked putting into operation more than the put into operation equipment of given threshold value Standby, enter step 6);
6) if there is put into operation equipment to be checked, the base for load is turned at each equipment measure that puts into operation the most respectively The solution generator of overload problem, the maximum adjustment amount of load active power adjustment measure is determined, the most directly on plinth Determine the solution generator of overload problem, the maximum adjustment amount of load active power adjustment measure;
7) according to generator, the maximum adjustment amount of load active power adjustment measure and the computational accuracy shape of active power adjustment Becoming generator, load adjustment scheme, if there is put into operation equipment to be checked, then to be checked being put into operation Equipment and generator, the combination of load adjustment scheme obtain the numerical procedure needing AC power flow to check, the most directly Connect generator, load adjustment scheme as the numerical procedure needing AC power flow to check, according to control measure Control cost ascending order numerical procedure is ranked up, by parallel computation, each scheme is carried out AC power flow for fault-free and critical failure collection is checked, if obtaining overload nargin more than ηcr.1Calculating Scheme, then terminate parallel computation, using this numerical procedure as the output of final control measure method ends; Otherwise, method ends.
The grid equipment overload aid decision of meter the most according to claim 1 and load transfer measure calculates Method, it is characterised in that described step 1) in use different limit value to calculate under electrical network current state and anticipation The overload nargin of jth equipment under fault:
When jth equipment is circuit, by formula (1) computation overload margin of safety ηj:
η j = ( 1 - I L I P ) × 100 % - - - ( 1 )
Wherein, when calculating the overload nargin of circuit under electrical network current state, ILFor circuit under current state The electric current of the bigger one end of two ends electric current, IPElectric current is allowed for circuit under normal running (operation) conditions;When calculating, electrical network is pre- When thinking the overload nargin of circuit under fault, ILFor the electric current of the bigger one end of circuit two ends electric current under forecast failure, IPRun for circuit under emergency conditions and allow electric current;
When jth equipment is transformer, pacified by the overload of formula (2) each winding of calculating transformer respectively Full nargin ηj,w, the overload nargin of this transformer equipment is overload nargin in each winding of this transformer Minimum of a value:
η j , w = ( 1 - S T / U T S P / U N , w ) × 100 % - - - ( 2 )
Wherein, the different windings of w indication transformer, UN,wRated voltage for each winding;Work as when calculating electrical network Under front state during the overload nargin of transformer, STAnd UTFor the apparent energy under winding current state and electricity Pressure, SPFor the permission capacity of transformer under normal condition;When calculating the overload of transformer under electrical network forecast failure During margin of safety, STAnd UTFor the apparent energy of winding under forecast failure and voltage, SPFor becoming under emergency conditions The permission capacity of depressor.
The grid equipment overload aid decision of meter the most according to claim 1 and load transfer measure calculates Method, it is characterised in that described step 6) in determine solution the generator of overload problem, load active power adjustment The step of the maximum adjustment amount of measure is divided into four steps:
, if there is put into operation equipment to be checked, then according to the apparatus overload safety after putting equipment in service in the first step Nargin calculates active power adjustment measure by formula (4) and combines overload under overload under current state and forecast failure Close performance indications;Otherwise, directly by formula (4) calculate active power adjustment measure under current state overload and The integrated performance index of overload under forecast failure:
w i M = Σ j = 1 N [ λ i M , j ( 1 - η j ) ] + Σ k = 1 W Σ j 1 = 1 N k [ λ i M , j 1 . k ( 1 - η j 1 . k ) ] - - - ( 4 )
Wherein, iM=1,2 ..., M, M are the sum of active power adjustment measure,It is i-thMIndividual active power adjustment measure Integrated performance index, N is the sum of overload prevention device, η under current statejOverload for jth overload prevention device Margin of safety,It is i-thMThe individual active power adjustment measure active po wer sensitivity to jth overload prevention device;W was Carry the sum of safety-critical fault, NkFor the sum of overload prevention device under kth overload critical failure, For jth under kth overload critical failure1The overload nargin of individual overload prevention device,It is i-thMIndividual Active power adjustment measure is to jth under kth fault1The active po wer sensitivity of individual equipment;
Second step, is more than the active power adjustment measure alternately measure setting threshold value by integrated performance index, Choose integrated performance index be negative alternative measure as power transmission queue, the generator node in queue is exerted oneself increasing Add and the meritorious reduction of load bus;Choosing integrated performance index is that positive alternative measure is as by electricity queue, team Generator node in row is exerted oneself reduction;
3rd step, is first according to the priority of control measure order from high to low to power transmission queue with by electricity team Alternative measure in row is ranked up, then to controlling the identical alternative measure of priority by cost performance index by greatly Being ranked up to little order, cost performance index is calculated by formula (5):
G i M = | w i M | / C i M - - - ( 5 )
Wherein,It is i-thMThe Readjusting cost of individual active power adjustment measure unit power;
4th step, makees the maximum adjustment amount of power transmission queue with the maximum in the maximum adjustment amount by electricity queue For determining the maximum adjustment amount of numerical procedure.
The grid equipment overload aid decision of meter the most according to claim 1 and load transfer measure calculates Method, it is characterised in that described step 7) in, for different adjustment amount requirements, by step 6) in really The adjustment order of fixed control measure, is sequentially adjusted in power transmission queue and each node by electricity queue so that control Least-cost and owing to the active power of system is uneven and cause system frequency deviation to meet service requirement, To numerical procedure.
CN201310332739.8A 2013-08-01 2013-08-01 The grid equipment overload aid decision computational methods of meter and load transfer measure Expired - Fee Related CN103514364B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310332739.8A CN103514364B (en) 2013-08-01 2013-08-01 The grid equipment overload aid decision computational methods of meter and load transfer measure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310332739.8A CN103514364B (en) 2013-08-01 2013-08-01 The grid equipment overload aid decision computational methods of meter and load transfer measure

Publications (2)

Publication Number Publication Date
CN103514364A CN103514364A (en) 2014-01-15
CN103514364B true CN103514364B (en) 2016-09-07

Family

ID=49897073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310332739.8A Expired - Fee Related CN103514364B (en) 2013-08-01 2013-08-01 The grid equipment overload aid decision computational methods of meter and load transfer measure

Country Status (1)

Country Link
CN (1) CN103514364B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104280666A (en) * 2014-10-29 2015-01-14 国网上海市电力公司 Auxiliary load transfer decision system used after medium voltage distribution network line breaks down
CN104868471B (en) * 2015-06-15 2017-03-08 国家电网公司 A kind of provincial power network static security aid decision-making method
CN106130002B (en) * 2015-12-15 2018-09-14 国电南瑞科技股份有限公司 A kind of cutting load and dynamic partition control method for coordinating considering electric power safety accident risk
CN106447525B (en) * 2016-08-03 2019-11-01 国电南瑞科技股份有限公司 A kind of power grid dynamic partition policy optimization searching method
CN106570791A (en) * 2016-11-13 2017-04-19 国网江苏省电力公司连云港供电公司 Dynamic adjustment method for structure of regional power grid in allusion to main transformer overload
CN113067333B (en) * 2021-04-29 2022-11-11 国电南瑞科技股份有限公司 Aggregation method, system and storage medium for overload control measures of power system equipment
CN113300367B (en) * 2021-05-11 2022-08-26 国电南瑞科技股份有限公司 Online rapid identification method for key section of power grid and power transmission limit making method and device
CN113410834A (en) * 2021-05-26 2021-09-17 佳源科技股份有限公司 Network reconstruction method and device applied to distribution network terminal
CN113363970B (en) * 2021-06-09 2022-09-06 国电南瑞科技股份有限公司 Decoupling decision method and device for overload prevention control of power system equipment
CN116979526B (en) * 2023-09-21 2024-01-16 国网吉林省电力有限公司松原供电公司 66kV power distribution network load transfer method and system considering load acceptance capacity of plant

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102916431A (en) * 2012-09-20 2013-02-06 中国电力科学研究院 Assisted decision making method for load transfer in regional power grid
CN102938587A (en) * 2012-12-10 2013-02-20 上海市电力公司 Intelligent power grid safety and stability early-warning and control method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7236896B2 (en) * 2003-09-30 2007-06-26 Hewlett-Packard Development Company, L.P. Load management in a power system
US8924033B2 (en) * 2010-05-12 2014-12-30 Alstom Grid Inc. Generalized grid security framework
US8634175B2 (en) * 2011-04-13 2014-01-21 Siemens Industry, Inc. Method and system for programming and implementing automated fault isolation and restoration using sequential logic

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102916431A (en) * 2012-09-20 2013-02-06 中国电力科学研究院 Assisted decision making method for load transfer in regional power grid
CN102938587A (en) * 2012-12-10 2013-02-20 上海市电力公司 Intelligent power grid safety and stability early-warning and control method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《Application of GCN approach for power distribution system contingency load transfer》;Y.-K. Ke;《Iee Proceedings Generation Transmission & Distribution》;20031130;第150卷(第6期);全文 *
《负荷转供在线辅助决策系统在大型电网中的应用》;潘凯岩,刘仲尧;《电气技术》;20130531(第5期);全文 *

Also Published As

Publication number Publication date
CN103514364A (en) 2014-01-15

Similar Documents

Publication Publication Date Title
CN103514364B (en) The grid equipment overload aid decision computational methods of meter and load transfer measure
CN103746368B (en) Method of optimizing static safe and stable operation limit of electric power system
WO2017092527A1 (en) Online evaluation method of safety margin of operating reserve in power system
CN107093895B (en) online transient state safety and stability assessment method based on automatic screening of expected fault set
CN107492888B (en) A kind of voltage weakness zone appraisal procedure of direct current receiving end AC system
CN101969202B (en) Method for recognizing transmission section power limit interval of power system transient stability
CN108173293A (en) Meter and the new energy active power output maximum value on-line calculation method of operation of power networks constraint
CN103870703B (en) A kind of dynamic short-circuit ratio computational methods based on Thevenin's equivalence parameter tracking
CN106682407B (en) Voltage stability assessment method based on Thevenin's equivalence and branch transmission power limit
CN104362642B (en) Dynamic reactive reserved optimizing method for improving long-term voltage stabilization in AC/DC (Alternating Current/Direct Current) power grid
CN108304613A (en) Closed loop network powered operation methods of risk assessment
CN103094905A (en) Selection method of dynamic reactive power compensation configuration point
CN108183512A (en) A kind of reliability estimation method for the electric system for accessing new energy
CN103714490B (en) Large power grid on-line data multi-thread rapid-integration method
CN107104420B (en) I segment protection method of route distance suitable for THE UPFC access
CN107516903B (en) Accurate load control method considering economy and safety and stability of multiple time scales
CN102403720A (en) Hyper-real-time setting method for superposed time sequences based on transient voltage safety margin
CN106875287A (en) A kind of power system switched-mode power supply capacity judging method
CN107181253A (en) A kind of Electric power network planning method based on power network dynamic reliability probability level
CN104849614A (en) Judgment method of small current single-phase grounding fault line selection
CN106410828A (en) Distribution transformer dynamic intelligent compensation and harmonic treatment method
CN109038572A (en) Consider the voltage security range determining method of AC-DC hybrid power grid failure
CN108008251A (en) The fault distance-finding method of mixed power transmission line unknown parameters
CN109787266A (en) Extra-high voltage direct-current complex fault on-line analysis decision-making technique and system
CN106970347A (en) A kind of method of utilization bus unbalance factor investigation transformer station kilowatt-hour meter secondary circuit failure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20171123

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Co-patentee after: NARI Technology Development Co., Ltd.

Patentee after: State Grid Shanghai Municipal Electric Power Company

Address before: 200002 Nanjing East Road, Shanghai, No. 181, No.

Co-patentee before: Nanjing Nari Co., Ltd.

Patentee before: State Grid Shanghai Municipal Electric Power Company

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160907

Termination date: 20200801

CF01 Termination of patent right due to non-payment of annual fee