CN103258088A - Method for allocating load to double cranes cooperatively operating - Google Patents

Method for allocating load to double cranes cooperatively operating Download PDF

Info

Publication number
CN103258088A
CN103258088A CN2013101528782A CN201310152878A CN103258088A CN 103258088 A CN103258088 A CN 103258088A CN 2013101528782 A CN2013101528782 A CN 2013101528782A CN 201310152878 A CN201310152878 A CN 201310152878A CN 103258088 A CN103258088 A CN 103258088A
Authority
CN
China
Prior art keywords
lifting
crane
prime
shipper
auxilliary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013101528782A
Other languages
Chinese (zh)
Other versions
CN103258088B (en
Inventor
吴敏
何勇
周斌
林艺辉
于艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN201310152878.2A priority Critical patent/CN103258088B/en
Publication of CN103258088A publication Critical patent/CN103258088A/en
Application granted granted Critical
Publication of CN103258088B publication Critical patent/CN103258088B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Control And Safety Of Cranes (AREA)

Abstract

The invention discloses a method for allocating load to double cranes cooperatively operating. The method for allocating the load to the double cranes cooperatively operating includes the following steps of three-dimension scene modeling, crane type selection, crane configuration, calculation of cooperative hoisting motion of the double cranes, calculation cooperative hoisting parameters of the double cranes, hoisting objective point reaching, and end of hoisting. According to the method for allocating the load to the double cranes cooperatively operating, firstly, a relation model of rated load lifting capacity is established through analysis of influencing factors of the rated load lifting capacity, secondly, a real-time loading model of each crane in the process of cooperative operation is researched through combination of analysis of the process of the cooperative operation and crane dynamics characteristics, and therefore safety performance of the hoisting process is improved.

Description

A kind of pair of platform crane work compound load distribution method
Technical field
The present invention relates to Crane Load and distribute field, particularly a kind of pair of platform crane work compound load distribution method.
Background technology
Crane is as a kind of indispensable engineering machinery, vital role in the performance in the developments of the national economy such as petrochemical complex, power construction, water conservancy and hydropower, bridge construction.Along with China's rapid development of economy, China's all trades and professions are in the ascendant, especially aspect construction scales such as metallurgy, nuclear power, harbour are increasing, large-scale lifting is increasing, operating environment is complicated day by day, the separate unit crane does not often satisfy job requirements, and two-shipper or multimachine lifting are increasing.
At present, the two-shipper lifting often takes manually to work out the lifting operation scheme, relies on artificial experience to coordinate to finish lifting.And the two-shipper lifting lacks effectively, scientific guidance, only with artificial experience, has subjectivity and one-sidedness, can not ensure fully that the safety of lifting operation is carried out, and efficient is very low, has increased the cost of lifting.
Two-shipper lifting operation complexity, along with the variation in suspension centre speed and operation orientation, the load that acts on certain suspension centre may change, thereby peril such as disconnected arm takes place because of the load skewness.
In this case, be necessary to analyze the dynamic load that two-shipper is coordinated the lifting operation process on the one hand, prevent certain crane overload and have an accident, thereby propose rational double computer cooperation lifting operation load distribution strategy, science, effectively instruct actual lifting operation.Research and develop a cover on the other hand based on the collaborative hoisting simulation system of virtual reality, by the three-dimensional artificial of collaborative lifting operation process, the formulation of auxiliary lifting operation scheme also has significant meaning to reducing double computer cooperation lifting risk.
Summary of the invention
Technical matters to be solved by this invention is at the prior art deficiency, to provide a kind of pair of platform crane work compound load distribution method, calculate the distribution of load in two platform truck-mounted crane hoisting processes, formulate the lifting operation scheme, instruct actual lifting, reduce double computer cooperation lifting risk.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: a kind of pair of platform crane work compound load distribution method, and this method is:
1) three-dimensional scenic modeling: multi-model crane data are provided, set up the heavy-duty machine model bank with the form of model data file;
2) crane type selecting: the user selects to meet main crane and the auxilliary crane of lifting requirements from the crane model bank according to operating mode;
3) crane configuration: the magnification ratio, the counterweight that require two telescopic crane booms of configuration according to the lifting operation of load capacity, lifting altitude;
4) two platform cranes are worked in coordination with lifting action calculating: use the inverse kinematics principle, according to the desired motion of equipment, namely two-shipper hoists, two-shipper overturns, the two-shipper rotation, determines the concerted action sequence of two cranes;
5) the collaborative lifting of two platform cranes calculation of parameter: according to Principles of Statics calculate that two cranes hoist at two-shipper, load when two-shipper upset, two-shipper rotation;
6) set the lifting impact point, realize lifting simulated operation by keyboard operation, judge whether lifting object reaches set lifting impact point; If enter 7); If not, return 4);
7) finish hoisting process.
As preferred version, in the described step 1), the three-dimensional scenic modeling is divided into two kinds: 1) OpenGL provides five kinds of basic bodies of rectangular parallelepiped, cylinder, circular cone, annulus, ball of drafting; 2) model except rectangular parallelepiped, cylinder, circular cone, annulus, five kinds of basic bodies of ball is by Pro/E analogue formation file.As preferred version, in the described step 5), the concerted action sequence computation process of two cranes is as follows:
1) state that hoists of two-shipper comprises and hoisting synchronously and asynchronous hoisting:
The state variation that hoists synchronously as shown in the formula:
h i = h i ′ + Δh h 0 = h 0 ′ + Δh
Asynchronous hoist state variation as shown in the formula:
h 1 = h 1 ′ + Δh 1 β 0 = arccos Δh 1 - Δh 2 d β 2 = arccos d 2 - ( Δh 1 - Δh 2 ) 2 + L 2 cos β 2 ′ L 2 h 2 = h 1 ′ + Δh 2 ,
Wherein, h i, i=1,2, h 1For lifting the main crane lifting rope length in back, h 2For lifting the auxilliary crane lifting rope length in back, Δ h 1Be main crane hoisting high variable quantity, Δ h 2Be auxilliary crane hoisting high variable quantity, and Δ h 1Δ h 2, β 0For lifting the back lifting object around the angle of the axis on vertical lifting plane, d is the axial line distance of main crane and two lifting points of auxilliary crane, β 2For lifting the elevation angle of the auxilliary crane in back, h i', i=1,2, h 1' for lifting preceding main crane lifting rope length, β ' 2Be the elevation angle of auxilliary crane before lifting, L 2For lifting the auxilliary crane arm support length in back, Δ h is the variable quantity of lifting object lifting height, h 0For lifting the liftoff height of back lifting object, h 0' for lifting the preceding liftoff height of lifting object;
2) state variation of two-shipper upset as shown in the formula:
h 1 = h 1 ′ + Δh β 0 = β β 2 = arccos L 2 cos β 2 ′ + d cos β L 2 h 2 = h 2 ′ - ( L 2 sin β 2 ′ - L 2 sin β 2 ) ,
Wherein, h 2' being auxilliary crane lifting rope length before the lifting, Δ h is the variable quantity of lifting object lifting height, β is the angle that lifting object with respect to the horizontal plane promotes;
3) state variation of two-shipper rotation as shown in the formula:
After the rotation alpha, the coordinate of auxilliary crane suspension centre is shown below:
θ = arctan X d 2 ′ - X d 1 Z d 2 ′ - Z d 1 X d 2 = X d 1 + d * cos ( α + θ ) Z d 2 = Z d 1 + d * sin ( α + θ ) ,
Then at this moment shown in the following formula of state variation of dual systems:
α 0 = α 0 ′ + α β 2 = arccos ( X d 2 - X c 2 ) 2 + ( Z d 2 - Z c 2 ) 2 L 2 α 2 = α 2 ′ + ( X c 2 - X d 2 ) * ( X c 2 - X d 2 ′ ) + ( Z c 2 - Z d 2 ) * ( Z c 2 - Z d 2 ′ ) ( X c 2 - X d 2 ) 2 + ( Z c 2 - Z d 2 ) 2 * ( X c 2 - X d 2 ′ ) 2 + ( Z c 2 - Z d 2 ′ ) 2 h 2 = h 2 ′ + L 2 * ( sin β 2 - sin β 2 ′ ) ,
Wherein, θ is the angle of main crane suspension centre axis and X-axis, α 0For lifting the back lifting object around the angle of vertical direction, α ' 0Be the angle of lifting object before lifting around vertical direction, α is the angle of lifting back lifting object around the suspension centre axis rotation of main crane, P (X D1, Y D1, Z D1) position coordinates of the main crane suspension centre in expression lifting back, Q'(X D2', Y D2', Z D2') the preceding coordinate of assisting the crane suspension centre of expression lifting, Q (X D2, Y D2, Z D2) the back coordinate of assisting the crane suspension centre of expression lifting, O (X C2, Y C2, Z C2) the back centre of gyration coordinate of assisting crane of expression lifting, α 2For lifting the angle of revolution of the auxilliary crane in back, α ' 2Angle of revolution for auxilliary crane before lifting.
As preferred version, in the described step 6), two cranes hoist at two-shipper, the load when two-shipper upset, two-shipper rotation is respectively:
The tensile force f of master's crane when 1) two-shipper hoists ATensile force f with auxilliary crane BBe respectively:
F A = G 2 + hG d tan γ = ( 1 2 + hΔH d 2 ) G F B = G 2 - hG d tan γ = ( 1 2 - hΔH d 2 ) G ,
Wherein, G is lifting object weight, and Δ H is the difference in height because of the asynchronous suspension centre that causes of major-minor crane, and γ is the hoist asynchronous lifting object that causes and lifting object mass axis drift angle, and h is that two lifting eye of crane axis are apart from the distance of lifting object mass axis;
The tensile force f of master's crane when 2) two-shipper overturns ATensile force f with auxilliary crane BBe respectively:
F A = G 2 + hG d tan λ F B = G 2 - hG d tan λ ;
Wherein λ is the angle of lifting object upset;
The tensile force f of master's crane when 3) two-shipper rotates ATensile force f with auxilliary crane BBe respectively:
F A = G 2 F B = G 2 .
Compared with prior art, the beneficial effect that the present invention has is: the present invention formulates the lifting operation scheme by calculating the distribution of load in two platform truck-mounted crane hoisting processes, instructs actual lifting, has reduced the double computer cooperation risk of hoisting.
Description of drawings
Fig. 1 is one embodiment of the invention method flow diagram;
Fig. 2 is one embodiment of the invention crane type selecting process flow diagram;
Fig. 3 is one embodiment of the invention crane configuration flow figure;
Fig. 4 is one embodiment of the invention two-shipper action calculation diagram that hoists synchronously;
Fig. 5 is the asynchronous action calculation diagram that hoists of one embodiment of the invention two-shipper;
Fig. 6 is one embodiment of the invention two-shipper rotary movement calculation diagram;
Fig. 7 is one embodiment of the invention two-shipper spinning movement calculation diagram;
Fig. 8 is one embodiment of the invention two-shipper asynchronous synoptic diagram that hoists;
Fig. 9 is the auxilliary crane unhook synoptic diagram of one embodiment of the invention two-shipper upset.
Embodiment
As shown in Figure 1, one embodiment of the invention method step is as follows:
Step 1: three-dimensional scenic modeling;
Step 2: crane type selecting;
Step 3: crane configuration;
Step 4: the collaborative lifting action of two platform cranes is calculated;
Step 5: the collaborative lifting of two platform cranes calculation of parameter;
Step 6: reach the lifting impact point;
Step 7: lifting finishes.
In step 1, the three-dimensional scenic modeling can be divided into two parts: 1) OpenGL provides the basic body of drafting; 2) pattern of intricate external shape needs to import by third party software analogue formation file.
First comprises rectangular parallelepiped, cylinder, circular cone, annulus, five kinds of basic bodies of ball, and we only need provide corresponding parameter input interface and interactive means, and analogue system just can be called this model and build scene.
Second portion is mainly by d solid modeling, and popular d solid modeling software mainly contains Pro/E, 3D Studio MAX, Open Inventor etc. at present.Pro/E software is widely used in the drafting of three-dimensional scenic, and the three-dimensional feeling of immersion of institute's model of painting is strong, and model is true to nature, and supports several data forms such as .igs .asm, is easy to exploitation.Native system is by the Pro/E modeling, and by Data Format Transform instrument extraction model data, the graphic plotting function that utilizes OpenGL to provide in three-dimensional scenic reads the importing that model data realizes complex scene.
The crane model belongs to such complex model, is the crucial model of analogue system.In order to guarantee that analogue system draws function and can redraw three-dimensional model preferably, native system has extracted the complete model data of crane, comprises that crane plane numeral index, summit, normal, material and material quote five kinds of information.Each plane numeral index data is made up of 9 integers, 3 of fronts are three summit numberings that constitute this plane, middle 3 is the normal numbering on each summit, and 3 of back are texture coordinate, just can realize the drafting of crane model by traversal plane numeral index.Vertex data is the three-dimensional coordinate of each point under the local coordinate system of model object.The method line coordinates of each point of normal data recording, normal coordinate have characterized the amount of summit reception light.Material quality data has characterized the material feature on plane, comprises diffused light parameter, reflected light parameter etc.
This collaborative simulation system provides multi-model crane data, sets up heavy-duty machine model bank (second portion) with the form of model data file.Allow the user simultaneously with the form renewal of the file of standard and safeguard the crane model bank.After lifting emulation began, system read machine type data and calls OpenGL API instrument drafting crane model according to the crane type that the user chooses, and carries out the crane modeling.
In step 2, the crane type selecting is the important composition link of whole lifting flow process, particularly double computer cooperation lifting.Main and auxiliary crane can be selected suitable combination according to existing crane type, can more effective, more safely finish the lifting task.Crane type selecting algorithm in this paper comprises that mainly user's input information module, checking check to be calculated, output as a result, as shown in Figure 2.
The lifting key point information of user's input comprises the key point in lifting start point information, lifting endpoint information and the hoisting process.Lifting object information comprises weight, size of lifting object etc.The lifting pattern that plan is taked is the lifting pattern that the user takes in conjunction with operating environment assessment back plan according to the lifting operation target.User input be crane type selecting process the constraint condition that should observe.
It is the core of this algorithm that module is checked in checking, determines the suitable type selecting of major-minor crane according to the information of user's input.The amplitude that hoists and highly to check mainly be that information according to user's input is estimated maximum hoisting height and lifting amplitude, and then judge whether crane arm support length and the elevation angle are satisfied the lifting scene and lifted mission requirements.Lifting capacity is checked the lifting pattern of mainly taking according to user's plan, information in conjunction with the lifting object key point, whether the elevating capacity by these key points of lifting model validation under the correspondence satisfies lifting requirements, general provision can not crane elevating capacity must comprise rigging, suspension hook, pulley blocks etc. (will leave the load surplus, be traditionally arranged to be 1.25 times) greater than total hanging device and lifting annex.The general type selecting of determining main crane earlier satisfies all cranes of checking checking computations fully and is only and meets lifting requirements in conjunction with further checking the type that auxilliary crane is determined in checking computations, having only according to the type of main crane then.
Through obtaining suitable main and auxiliary crane combination after the type selecting and being fit to the operating mode scope that user's lifting arranges environment.
In step 3, the user import selected crane type, and analogue system is written into the operating mode table data of this type automatically according to lifting requirements.Recorded a large amount of historical floor data of this crane in the operating mode table, the performance of reaction crane.In order to realize the parameter configuration of crane, on the one hand, the user can require parameters such as configuration crane arm support, supporting leg span, counterweight according to lifting operations such as load capacity, lifting altitudes; On the other hand, therefore the crane rated load should not allow crane to be configured according to other operating modes of operating mode off-balancesheet by obtaining in the operating mode table when considering lifting emulation.
Analogue system is by scanning crane operating mode table, according to the configurable crane parameter of existing crane parameter Dynamic Selection.Crane configuration flow figure as shown in Figure 3.
At first according to the scene type operating mode table that is written into, scan the crane operating mode of this type, define a kind of data structure and preserve complete crane operating mode.Every operating mode should comprise flexible ratio, multiplying power, counterweight and the supporting leg span that saves telescopic arm.The user at first disposes the jib operating mode, has disposed the jib parameter one by one, according to the jib parameter that has arranged, upgrades next and saves configurable jib operating mode, and preserve the jib operating mode collection that configures.According to this operating mode collection, dispose parameters such as crane counterweight, multiplying power one by one, finally finish the configuration of all parameters.Because the relevance of every data, when the user will revise existing crane configuration parameter, should be with the parameter zero setting again that has arranged, and parameter reconfiguration returns and revises the crane configuration.
In step 4, when double computer cooperation lifting simulated actions is calculated, use the inverse kinematics principle, determine the concerted action sequence of two cranes according to the desired motion (work in coordination with and hoist, overturn, turn round) of equipment.
In order to describe the action sequence of collaborative hoisting process crane, hanging device better, define a tuple P (X Ci, Y Ci, Z Ci, α i, β i, h i, L i, X 0, Y 0, Z 0, α 0, β 0, h 0) (i=1,2) represent the cooperative system state of hoisting process, wherein, (X Ci, Y Ci, Z Ci) expression main and auxiliary crane centre of gyration coordinate.(α i, β i, L i, h i) expression main and auxiliary crane state, α iFor lifting the angle of revolution of back crane, β iFor lifting the elevation angle of back crane, L iFor lifting back crane arm support length, h iFor lifting the main crane lifting rope length in back.i=1,2。(X 0, Y 0, Z 0) expression lifting object barycentric coordinates.(α 0, β 0, h 0) for lifting the state of back lifting object, wherein α 0For lifting the back lifting object around the angle of vertical direction, β 0For lifting the back lifting object around the angle of the axis on vertical lifting plane, h 0For lifting the liftoff height of back lifting object.
At the collaborative lifting pattern of difference, according to the variation of each quantity of state of desired motion component analysis cooperative system of equipment, and remove to drive main and auxiliary crane and hanging device according to these variable quantities.Suppose Q'(X Ci', Y Ci', Z Ci', α i', β i', h i', L' i, X 0', Y 0', Z 0', α 0', β 0', h 0') state of system before (i=1,2) expression lifting, Q (X Ci, Y Ci, Z Ci, α i, β i, h i, L i, X 0, Y 0, Z 0, α 0, β 0, h 0) state of (i=1,2) expression lifting back system.
1) two-shipper hoists
When hoisting synchronously, the variable quantity of lifting object lifting height is assumed to be Δ h, and then the lifting rope variable quantity of main and auxiliary crane also is Δ h, and the active variable that lifts the process that hoists also is Δ h, and other variable remains unchanged, as shown in Figure 4.
Then this moment dual systems state variation as shown in Equation (1).
h i = h i ′ + Δh h 0 = h 0 ′ + Δh - - - ( 1 )
During asynchronous hoisting, suppose that main crane hoisting high variable quantity is Δ h 1, auxilliary crane hoisting high variable quantity is Δ h 2, suppose Δ h 1Δ h 2This moment, auxilliary crane often will carry out the luffing action in order to guarantee that main and auxiliary lifting rope is to be in vertical state all the time.Because the axial line distance of the main crane of hypothesis and two suspension centres of auxilliary crane is d, as shown in Figure 5.
Then this moment dual systems state variation as shown in Equation (2).
h 1 = h 1 ′ + Δh 1 β 0 = arccos Δh 1 - Δh 2 d β 2 = arccos d 2 - ( Δh 1 - Δh 2 ) 2 + L 2 cos β 2 ′ L 2 h 2 = h 1 ′ + Δh 2 - - - ( 2 )
2) two-shipper upset
During the two-shipper upset, main crane is received rop exercise and is done, cooperate the close to main crane of auxilliary crane, make hanging device produce rollover effect, the variable quantity of lifting object lifting height and lifting object are assumed to be Δ h respectively, β along the angle that surface level promotes at this moment, the axial line distance of establishing main and auxiliary crane two suspension centres simultaneously is d, and the state of main crane is (α 1, β 1, L 1, h 1), as shown in Figure 6.
Then this moment dual systems state variation as shown in Equation (3):
h 1 = h 1 ′ + Δh β 0 = β β 2 = arccos L 2 cos β 2 ′ + d cos β L 2 h 2 = h 2 ′ - ( L 2 sin β 2 ′ - L 2 sin β 2 ) - - - ( 3 )
3) two-shipper rotation
Analogue system, two-shipper rotation are angles of suspension centre axis rotation that the hypothesis hanging device is walked around main crane, to lift the back lifting object around the angle of the suspension centre axis rotation of main crane, are assumed to be α, as shown in Figure 7.
Introduce some P (X D1, Y D1, Z D1) position coordinates of the main crane suspension centre in expression lifting back, Q'(X D2', Y D2', Z D2'), Q (X D2, Y D2, Z D2) coordinate of auxilliary crane suspension centre before and after the expression lifting respectively, the axial line distance of supposing main and auxiliary crane two suspension centres simultaneously is d, the angle of supposing main crane suspension centre axis and X-axis is θ, hoist by collaborative earlier, after hanging device promoted a segment distance, this moment can according to original state and lifting calculate the coordinate of P, Q' apart from variograph, then auxilliary crane is by rotation, luffing and the whole rotary course of lancet operation realization.
After the rotation alpha, the coordinate of auxilliary crane suspension centre as the formula (4).
θ = arctan X d 2 ′ - X d 1 Z d 2 ′ - Z d 1 X d 2 = X d 1 + d * cos ( α + θ ) Z d 2 = Z d 1 + d * sin ( α + θ ) - - - ( 4 )
Then this moment dual systems state variation as shown in Equation (5).
α 0 = α 0 ′ + α β 2 = arccos ( X d 2 - X c 2 ) 2 + ( Z d 2 - Z c 2 ) 2 L 2 α 2 = α 2 ′ + ( X c 2 - X d 2 ) * ( X c 2 - X d 2 ′ ) + ( Z c 2 - Z d 2 ) * ( Z c 2 - Z d 2 ′ ) ( X c 2 - X d 2 ) 2 + ( Z c 2 - Z d 2 ) 2 * ( X c 2 - X d 2 ′ ) 2 + ( Z c 2 - Z d 2 ′ ) 2 h 2 = h 2 ′ + L 2 * ( sin β 2 - sin β 2 ′ ) - - - ( 5 )
In step 5, the parameter of the collaborative lifting of two platform cranes is calculated.Use when two platform cranes are collaborative to lift, the gravity of hanging device is born by two cranes.Collaborative hoisting process, main and auxiliary crane and hanging device orientation constantly change, and the load that main and auxiliary crane is born also constantly changes.Consider that hoisting process speed is comparatively slow, the load when calculating lifting load is often taked Principles of Statics calculation stability position on the engineering multiply by a dynamic load factor k again 1(generally getting 1.1-1.2).
(1) two-shipper hoists
After main and auxiliary crane and hanging device are in place, install and fix main and auxiliary hanger at equipment, and connect main and auxiliary crane hoisting pulley blocks and hanger by rope.Hanger has determined the load of two cranes of original state to the distance of equipment mass axis.The main and auxiliary hanger of This document assumes that equates to the distance of central apparatus mass axis, and the load of main and auxiliary crane is half of hanging device when namely initial.Collaborative hoisting when beginning by the receipts rope of pulley blocks, realized hoisting of lifting object.After each pulley blocks respectively shrank certain-length, hanging device was in equilibrium state, and only was subjected to gravity and rope pulling force, according to the statics balance principle, obtained the load of two platform cranes this moment by the balance of power and moment.
When the length that hoists when two pulley blockss was consistent, because equipment is constant with the rope relative position, so the load of main and auxiliary crane do not change, and namely the load of main and auxiliary crane is half of hanging device.
When the length that hoists when two pulley blockss was inconsistent, equipment had produced certain angle, as shown in Figure 8.
If the pulling force of major-minor crane is F A, F B, the weight of lifting object is G, and two lifting eye of crane axis are h apart from the distance of lifting object mass axis, and the distance of the axis of two suspension centres of main and auxiliary crane is d, the flip angle β of main crane.
Then have according to Principles of Statics
F A + F B = G F A ( d 2 - ΔL ) cos γ = F B ( d 2 + ΔL ) cos γ - - - ( 6 )
Because
h = d 2 ctgθ ΔL = h tan γ - - - ( 7 )
Bring formula (7) into (6), and consider that γ is generally less, get
Figure DEST_PATH_GDA00003318820000123
Then
F A = G 2 + hG d tan γ = ( 1 2 + hΔH d 2 ) G F B = G 2 - hG d tan γ = ( 1 2 - hΔH d 2 ) G - - - ( 8 )
γ is the hoist asynchronous lifting object that causes and lifting object mass axis drift angle.
(2) two-shipper upset
Double computer cooperation upset operation can be divided into two stages, when just beginning, main crane carries out the lancet operation, all the time be in vertical direction in order to ensure main and auxiliary rope, auxilliary crane carries out luffing and lancet operation, when hanging device is turned to certain angle from horizontality gradually, assists crane and breaks off relations, with the hanging device hoisted in position, main crane will bear the weight of entire equipment separately to main crane this moment by other operations.
Begin turning the stage, the load analysis of crane and two-shipper hoist similar when asynchronous, and the pulling force of establishing major-minor crane is respectively F A, F B, the weight of lifting object is G, and two lifting eye of crane axis are h apart from the distance of lifting object mass axis, and main and auxiliary two lifting points are d in the distance of axis, and the lifting object flip angle is λ, then
F A = G 2 + hG d tan λ F B = G 2 - hG d tan λ - - - ( 9 )
When main crane flip angle λ near θ (all longer for the upset hoisted object, general θ is greater than 85 degree), auxilliary crane begins to break off relations, as shown in Figure 9.This moment, hanging device only was subjected to two power effects: the tensile force f of lifting object weight G and main crane AEquipment can be considered the physics single pendulum around main suspension centre swing, tries to achieve easily according to energy conservation, and after the unhook, the pulling force of master's crane rope was when equipment swung to minimum point
F A=(3-2sinλ)G (10)
(3) two-shipper rotation
Suppose that main and auxiliary suspension centre equates to the distance of central apparatus mass axis, namely the load of main and auxiliary crane is half of hanging device during incipient stability.Hanging device through worked in coordination be raised to certain altitude after the time, at this moment, auxilliary crane rotation is realized hanging device around the effect of main crane master suspension centre rotation, auxilliary crane is equipped with luffing and rises hook and operates simultaneously, and hanging device is remained on the surface level.If after having rotated α, according to the statics balance principle, obtain the load of two platform cranes this moment by the balance of power and moment.Two pulling force sums are gravity; The object balance, two ropes all are vertical moment equal and opposite in directions to the hoisting object center of gravity, because the operating distance of power is equal, so two power are equal, are half of hanging device weight.The pulling force of major-minor crane is respectively F A, F B, namely
F A = G 2 F B = G 2 - - - ( 11 )
In two crane work compound processes, each crane load changes along with the variation in suspension centre speed and operation orientation, and certain crane load may increase suddenly, and security incidents such as disconnected arm take place when load surpasses rated load weight under operating mode this moment easily.Therefore, the essence of load distribution be exactly in the requirement hoisting process each crane be within the safe lifting scope, namely specified crane is greater than separately real-time load, and is in and lifts load factor preferably.At first by the influence factor of analyzing influence rated load weight, set up the relational model of rated load weight; Secondly by analyzing the work compound process, in conjunction with the crane dynamics, study each crane real-time load model of work compound process, the security that improves hoisting process.
The concrete application
1) lifting task is introduced
The lifting case is that common petrochemical complex tank body is installed.This tank body is installed case and is required red tank body to lift white tank body back, and vertically upset, makes red tank body upright.Known is 25 meters by the cage body length, and radius is 2 meters, weighs 25 tons.
2) lifting simulation process
The user lifts scene according to reality, and the detail parameters of input lifting object comprises lifting object title, color attribute, size and weight attribute, geometric center coordinate attributes.The user arranges other object informations in the scene according to the lifting environment.The concrete parameter of object is as shown in table 1 in the scene.
Table 1 object scene information
Figure DEST_PATH_GDA00003318820000141
According to the crane type storehouse that the lifting object information of having imported and system provide, the user further imports the lifting operation pattern that lifting parameter information and plan are taked.The crane type selecting is taken all factors into consideration above lifting constraint, lifts preceding rough check in conjunction with the operating mode query function, finishes the type selecting of crane.The type that two same models are chosen in this emulation lifts test, on lifting amplitude, hoisting height and lifting performance, all can meet the demands.The main crane coordinate that arranges in the scene is (30.0,0.0,0.0), and the supporting leg of main crane is for stretching entirely, and five joint telescopic arm magnification ratios of crane are 46%, and counterweight is 56 tons, and the lifting multiplying power is made as 2.Auxilliary crane coordinate is (30.0,0.0,0.0), and the supporting leg of auxilliary crane is for stretching entirely, and five joint telescopic arm magnification ratios of crane are 46%, and counterweight is 100 tons, and the lifting multiplying power is made as 2.The user can revise the crane configuration according to actual lifting operation environment, builds scene.
The user lifts analogue simulation according to the lifting scene of putting up.
When finishing scene and beginning, the coordinate that main and auxiliary crane two hangers are set is (10.4,5,0), (10.4,5,0), and the main and auxiliary crane of simulation process do not stretch the hook operation, and brachium keeps 40.4 meters.In the process that hoists, work in coordination with and hoisted 5 meters; Auxilliary crane is around main crane suspension centre axis rotation 37 degree then; Follow main crane around auxilliary crane suspension centre axis rotation 37 degree, this moment, hanging device was parallel with X-axis; Through the hanging device switching process; The situations of lifting object upset 45 degree then; Auxilliary crane breaks off relations.Be at last by main crane action, hanging device is stable to stand upright on (12,12.5 ,-12), and lifting is finished.The key parameter of the main crane of simulation process is as shown in table 2, and key parameter such as the table 3 of auxilliary crane show.
Table 2 hoisting process master crane state parameter
Figure DEST_PATH_GDA00003318820000151
Table 3 hoisting process is assisted the crane state parameter
Figure DEST_PATH_GDA00003318820000152
After the lifting analog simulation finished, the user can export Hoisting Program, comprises project profile editor and scheme information.Hoisting Program has been preserved relevant informations such as commencement date, unit in charge of construction, personnel's configuration, lifting scene parameter and hoisting process crane erect-position figure, hoisting process pattern, the process key parameter of hoisting engineering automatically.The user can utilize the sectional drawing function of system manually to add the hoisting process pattern according to actual needs simultaneously, improves Hoisting Program, and the final actual lifting operation of guidance that is used for.
Above-mentioned emulation case shows that this hoisting simulation system not only can support double computer cooperation lifting, and system from scene modeling to hoisting process emulation again the operating process to scheme output conform to the lifting operation of reality.Native system provides multiple model data, and the truck-mounted crane data that the user can import other lift emulation.In the above-mentioned lifting case, use the high accurate calculagraph test to carry out operation response speed in program, the result shows that the average response time of each action is about 596ms, can satisfy the needs of three-dimensional real-time emulation system.In addition, native system also provides multiple subsidiary function and mutual design.Simulation process can switch different visual angles to be observed simulation process, makes comprehensive, the observation lifting simulation process with multi-angle of user.Analogue system also provides the sectional drawing function, and the user can lift needs according to reality and obtain the simulation process pattern.Analogue system also provides automatic hold function, to complicated, builds the long scene of required time, and system preserved automatically every one minute.

Claims (4)

1. two platform crane work compound load distribution method is characterized in that this method is:
1) three-dimensional scenic modeling: multi-model crane data are provided, set up the heavy-duty machine model bank with the form of model data file;
2) crane type selecting: the user selects to meet main crane and the auxilliary crane of lifting requirements from the crane model bank according to operating mode;
3) crane configuration: the magnification ratio, the counterweight that require two telescopic crane booms of configuration according to the lifting operation of load capacity, lifting altitude;
4) two platform cranes are worked in coordination with lifting action calculating: use the inverse kinematics principle, according to the desired motion of equipment, namely two-shipper hoists, two-shipper overturns, the two-shipper rotation, determines the concerted action sequence of two cranes;
5) the collaborative lifting of two platform cranes calculation of parameter: according to Principles of Statics calculate that two cranes hoist at two-shipper, load when two-shipper upset, two-shipper rotation;
6) set the lifting impact point, realize lifting simulated operation by keyboard operation, judge whether lifting object reaches set lifting impact point; If enter 7); If not, return 4);
7) finish hoisting process.
2. according to claim 1 pair of platform crane work compound load distribution method, it is characterized in that, in the described step 1), the three-dimensional scenic modeling is divided into two kinds: 1) OpenGL provides five kinds of basic bodies of rectangular parallelepiped, cylinder, circular cone, annulus, ball of drafting; 2) model except rectangular parallelepiped, cylinder, circular cone, annulus, five kinds of basic bodies of ball is by Pro/E analogue formation file.
3. according to claim 1 pair of platform crane work compound load distribution method is characterized in that, in the described step 5), the concerted action sequence computation process of two cranes is as follows:
1) state that hoists of two-shipper comprises and hoisting synchronously and asynchronous hoisting:
The state variation that hoists synchronously as shown in the formula:
h i = h i ′ + Δh h 0 = h 0 ′ + Δh
Asynchronous hoist state variation as shown in the formula:
h 1 = h 1 ′ + Δ h 1 β 0 = arccos Δ h 1 - Δ h 2 d β 2 = arccos d 2 - ( Δ h 1 - Δ h 2 ) 2 + L 2 cos β 2 ′ L 2 h 2 = h 1 ′ + Δ h 2 ,
Wherein, h i, i=1,2, h 1For lifting the main crane lifting rope length in back, h 2For lifting the auxilliary crane lifting rope length in back, Δ h 1Be main crane hoisting high variable quantity, Δ h 2Be auxilliary crane hoisting high variable quantity, and Δ h 1>Δ h 2, β 0For lifting the back lifting object around the angle of the axis on vertical lifting plane, d is the axial line distance of main crane and two lifting points of auxilliary crane, β 2For lifting the elevation angle of the auxilliary crane in back, h ' i, i=1,2, h ' 1Be main crane lifting rope length before lifting, β ' 2Be the elevation angle of auxilliary crane before lifting, L 2For lifting the auxilliary crane arm support length in back, Δ h is the variable quantity of lifting object lifting height, h 0For lifting the liftoff height of back lifting object, h ' 0Be the liftoff height of lifting object before lifting;
2) state variation of two-shipper upset as shown in the formula:
h 1 = h 1 ′ + Δ h β 0 = β β 2 = arccos L 2 cos β 2 ′ + d cos β L 2 h 2 = h 2 ′ - ( L 2 sin β 2 ′ - L 2 sin β 2 ) ,
Wherein, h ' 2Be auxilliary crane lifting rope length before lifting, Δ h is the variable quantity of lifting object lifting height, and β is the flip angle of main crane;
3) state variation of two-shipper rotation as shown in the formula:
After the rotation alpha, the coordinate of auxilliary crane suspension centre is shown below:
θ = arctan X d 2 ′ - X d 1 Z d 2 ′ - Z d 1 X d 2 = X d 1 + d * cos ( α + θ ) Z d 2 = Z d 1 + d * sin ( α + θ ) ,
Then at this moment shown in the following formula of state variation of dual systems:
α 0 = α 0 ′ + α β 2 = arccos ( X d 2 - X c 2 ) 2 + ( Z d 2 - Z c 2 ) 2 L 2 α 2 = α 2 ′ + ( X c 2 - X d 2 ) * ( X c 2 - X d 2 ′ ) + ( Z c 2 - Z d 2 ) * ( Z c 2 - Z d 2 ′ ) ( X c 2 - X d 2 ) 2 + ( Z c 2 - Z d 2 ) 2 * ( X c 2 - X d 2 ′ ) 2 + ( Z c 2 - Z d 2 ′ ) 2 h 2 = h 2 ′ + L 2 * ( sin β 2 - sin β 2 ′ ) ,
Wherein, θ is the angle of main crane suspension centre axis and X-axis, α 0For lifting the back lifting object around the angle of vertical direction, α ' 0Be the angle of lifting object before lifting around vertical direction, α is the angle of lifting back lifting object around the suspension centre axis rotation of main crane, P (X D1, Y D1, Z D1) position coordinates of the main crane suspension centre in expression lifting back, Q ' (X ' D2, Y ' D2, Z ' D2) the preceding coordinate of assisting the crane suspension centre of expression lifting, Q (X D2, Y D2, Z D2) the back coordinate of assisting the crane suspension centre of expression lifting, O (X C2, Y C2, Z C2) the back centre of gyration coordinate of assisting crane of expression lifting, α 2For lifting the angle of revolution of the auxilliary crane in back, α ' 2Angle of revolution for auxilliary crane before lifting.
4. according to claim 1 pair of platform crane work compound load distribution method is characterized in that, in the described step 6), two cranes hoist at two-shipper, the load when two-shipper upset, two-shipper rotation is respectively:
The tensile force f of master's crane when 1) two-shipper hoists ATensile force f with auxilliary crane BBe respectively:
F A = G 2 + hG d tan γ = ( 1 2 + hΔH d 2 ) G F B = G 2 - hG d tan γ = ( 1 2 - hΔH d 2 ) G ,
Wherein, G is lifting object weight, and Δ H is the difference in height because of the asynchronous suspension centre that causes of major-minor crane, and γ hoists the asynchronous lifting object that causes with respect to lifting object mass axis drift angle, and h is that two lifting eye of crane axis are apart from the distance of lifting object mass axis;
The tensile force f of master's crane when 2) two-shipper overturns ATensile force f with auxilliary crane BBe respectively:
F A = G 2 + hG d tan λ F B = G 2 - hG d tan λ ;
Wherein λ is the angle of lifting object upset;
The tensile force f of master's crane when 3) two-shipper rotates ATensile force f with auxilliary crane BBe respectively:
F A = G 2 F B = G 2 .
CN201310152878.2A 2013-04-27 2013-04-27 A kind of double-crane work compound load distribution method Expired - Fee Related CN103258088B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310152878.2A CN103258088B (en) 2013-04-27 2013-04-27 A kind of double-crane work compound load distribution method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310152878.2A CN103258088B (en) 2013-04-27 2013-04-27 A kind of double-crane work compound load distribution method

Publications (2)

Publication Number Publication Date
CN103258088A true CN103258088A (en) 2013-08-21
CN103258088B CN103258088B (en) 2015-10-28

Family

ID=48962002

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310152878.2A Expired - Fee Related CN103258088B (en) 2013-04-27 2013-04-27 A kind of double-crane work compound load distribution method

Country Status (1)

Country Link
CN (1) CN103258088B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103745059A (en) * 2014-01-14 2014-04-23 太原科技大学 Object-oriented computer modeling method based on crane boom
CN103863948A (en) * 2014-03-24 2014-06-18 合肥工业大学 Navigation control device and navigation control method applicable to collaborative transportation of cranes
CN106115489A (en) * 2016-06-16 2016-11-16 西南交通大学 The double car of the railway breakdown that a kind of view-based access control model is measured hangs multiple assist in synchronization control method for coordinating
CN107423919A (en) * 2017-08-23 2017-12-01 太仓苏易信息科技有限公司 A kind of virtual deduction algorithm for multi-person synergy operation
CN110032817A (en) * 2019-04-19 2019-07-19 哈尔滨工程大学 A kind of pair is sling heavy work emulation modelling method
CN110775824A (en) * 2019-09-19 2020-02-11 广州机施建设集团有限公司 Synchronous hoisting method, mechanism and system of double cranes

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080039971A1 (en) * 2003-11-14 2008-02-14 Siemens Technology-To-Business Center Llc Systems and methods for programming motion control
CN102935979A (en) * 2012-09-25 2013-02-20 大连理工大学 Control method facing double moving type crane collaborative operation

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080039971A1 (en) * 2003-11-14 2008-02-14 Siemens Technology-To-Business Center Llc Systems and methods for programming motion control
CN102935979A (en) * 2012-09-25 2013-02-20 大连理工大学 Control method facing double moving type crane collaborative operation

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张成文: "多台起重机协同吊装技术及仿真系统的研究", 《中国优秀硕士学位论文全文数据库 信息科技辑》, 15 July 2012 (2012-07-15) *
王爱红 等: "桥式起重机起升载荷分布拟合与检验", 《机械强度》, no. 6, 31 December 2011 (2011-12-31) *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103745059A (en) * 2014-01-14 2014-04-23 太原科技大学 Object-oriented computer modeling method based on crane boom
CN103745059B (en) * 2014-01-14 2017-05-10 太原科技大学 Object-oriented computer modeling method based on crane boom
CN103863948A (en) * 2014-03-24 2014-06-18 合肥工业大学 Navigation control device and navigation control method applicable to collaborative transportation of cranes
CN106115489A (en) * 2016-06-16 2016-11-16 西南交通大学 The double car of the railway breakdown that a kind of view-based access control model is measured hangs multiple assist in synchronization control method for coordinating
CN106115489B (en) * 2016-06-16 2017-12-19 西南交通大学 A kind of double cars of railway breakdown of view-based access control model measurement hang multiple assist in synchronization control method for coordinating
CN107423919A (en) * 2017-08-23 2017-12-01 太仓苏易信息科技有限公司 A kind of virtual deduction algorithm for multi-person synergy operation
CN110032817A (en) * 2019-04-19 2019-07-19 哈尔滨工程大学 A kind of pair is sling heavy work emulation modelling method
CN110032817B (en) * 2019-04-19 2021-04-06 哈尔滨工程大学 Simulation modeling method for double-crane hoisting operation
CN110775824A (en) * 2019-09-19 2020-02-11 广州机施建设集团有限公司 Synchronous hoisting method, mechanism and system of double cranes

Also Published As

Publication number Publication date
CN103258088B (en) 2015-10-28

Similar Documents

Publication Publication Date Title
CN103226740B (en) A kind of load distribution optimization method of double-crane collaborative operation
CN103258088B (en) A kind of double-crane work compound load distribution method
CN102663196B (en) Automobile crane hoisting simulation method on basis of virtual reality
CN201686411U (en) Crane lifting monitoring system
CN101556704A (en) Method for establishing temporary supporting frame system assembled by steel structures
CN101866179A (en) Boat segmental hoisting simulation system restricted by three-dimensional space
CN107741997A (en) Suitable for crane system variable phase angle response field acquisition methods under the parameter of minizone
CN108320047A (en) A kind of selection method of the optimal travel route of crane based on BIM technology
WO2022242099A1 (en) Allocation and stowage control method for multifunctional full-rotation crane ship, and crane ship
CN107918717A (en) One kind visualization bridge deformation monitoring system
CN107657138A (en) Application of the Virtual Construction equipment and technology based on BIM in steel crossover engineering
CN106709264B (en) Double-crane system variable phase angle response modeling algorithm and random response domain prediction technique
CN102662331B (en) Method for simulating deflection of automobile suspension arm on basis of virual reality
CN110032817A (en) A kind of pair is sling heavy work emulation modelling method
CN110728045A (en) Reverse model selection method for fabricated concrete building tower crane
CN109534184A (en) Cold rolling acid tandem rolling mill memorial archway hanging method based on BIM technology
CN103871108A (en) Simulation method for full steel structure lifting process based on 3D (third-dimensional) visualization technology
Liu et al. Automatic design method and application in complex ship block lifting
Zhao et al. Research on jib performance of crane in hoisting wind generator
CN110407104A (en) The accurate merogenesis hanging method of steel column based on BIM
Lian et al. Crane basic boom static analysis based on ANSYS
Wang et al. Interactive simulation of crawler crane’s lifting based on OpenGL
Wang et al. Study on factors affecting construction schedule of prefabricated buildings based on PCA
CN105480865A (en) Control device of ship crane
Zdravković et al. Research of the force values dependences in hydro cylinders of the mobile elevating work platform articulated boom on the work position and load weight

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151028

Termination date: 20210427