CN103234075B - Trenchless pipeline replace equipment with double-ring cutter and method thereof - Google Patents

Trenchless pipeline replace equipment with double-ring cutter and method thereof Download PDF

Info

Publication number
CN103234075B
CN103234075B CN201310113108.7A CN201310113108A CN103234075B CN 103234075 B CN103234075 B CN 103234075B CN 201310113108 A CN201310113108 A CN 201310113108A CN 103234075 B CN103234075 B CN 103234075B
Authority
CN
China
Prior art keywords
pipeline
machine structure
shield machine
old
cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310113108.7A
Other languages
Chinese (zh)
Other versions
CN103234075A (en
Inventor
肖剑
费利东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC COMMUNICATION CONSTRUCTION GROUP CO., LTD.
Original Assignee
MCC COMMUNICATION ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC COMMUNICATION ENGINEERING TECHNOLOGY Co Ltd filed Critical MCC COMMUNICATION ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201310113108.7A priority Critical patent/CN103234075B/en
Publication of CN103234075A publication Critical patent/CN103234075A/en
Application granted granted Critical
Publication of CN103234075B publication Critical patent/CN103234075B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides trenchless pipeline replace equipment with a double-ring cutter and a method thereof. The equipment comprises a shield mechanism provided with an outer ring cutter and an inner ring cutter, a slip casting mechanism and a traction mechanism. The using method of the equipment comprises the following steps: rapidly rotating the cutter at the front end of the shield mechanism under the action of a driving mechanism, rotary-cutting and expanding the stratum on the periphery of the old pipeline wall by the outer ring cutter, cutting the old pipeline wall forward by the hopper-shaped inner ring cutter, and meanwhile squeezing inwards to enable the pipe wall to be crushed, pulling the shield mechanism forward unceasingly to break down the old pipeline wall by a tractor, and meanwhile laying new pipelines connected with the back part of the shield mechanism forwards, unceasingly injecting circulating mud by the slip casting mechanism, lubricating the cutters, and bringing the scraps produced after cutting the old pipeline wall out the pipelines. The equipment has the advantages that the underground pipeline replacement can be finished under the trenchless condition; the efficiency is high; and the influence on the periphery is small.

Description

A kind of more exchange device and using method thereof of non-excavation pipeline with dicyclo cutter
Technical field
The disclosure relates to a kind of more exchange device and using method thereof of non-excavation pipeline with dicyclo cutter, belongs to trenchless technology field.
Background technique
Along with the continuous quickening of urbanization process, in urban underground space, pipeline is increasing, thereby produces the needs that old pipeline is changed.These pipelines that need to change are generally laid on the urban district populous, business is bustling, are often filling other some pipelines at tube circumference, also ride pressing building or below road on pipeline.Excavation construction will cause the breaking-up in traffic congestion, greenery patches and gardens, also may cause breaking-up to underground communal facilitys such as some other pipeline, cables.
Along with the development of trenchless technology and perfect, addressing this problem the best way is exactly the non-excavation pipeline replacing technology of giving birth to therefrom.Because having the advantages such as construction site is little, construction is simple, cost is lower, this technology is widely applied.The non-excavation of old pipeline is changed to be actually at the original position place of old pipeline and is changed, and, taking the old pipe that will change as guide, in the broken old pipe of special-purpose machines and tools, people is drawn in or pushed up to identical diameter or slightly large new pipe and completes replacing operation to replace old pipe.Main non-excavation replacing technology has booster method, eats Guan Fa etc.
Wherein, eating pipe method is to change application and the improvement in field at pipeline in micro-tunneling pipe laying engineering method.This engineering method adopts smear metal cutter that old pipeline to be changed is pulverized.The smear metal cutter of particular design can " be eaten " any obstacle falling in pipeline and soil layer and soil layer.The new pipeline that pipeline chip connects below by cutting head is discharged to earth's surface.The rear portion that new pipeline is connected to excavator is brought into.
Fig. 1 is the existing more schematic diagram of exchange device of pipe method pipeline of eating.As shown in Figure 1, existingly eat shield machine structure that pipe method uses and generally comprise a smear metal 91 and a shield structure body 92.In smear metal 91, smear metal tooth is housed, is used for the old pipeline 4 of smear metal.Smear metal head is placed in the edge of shield structure body 92, and soil layer smear metal is arrived the needed diameter of new pipeline is installed.In smear metal head, be conical heading end 93, when work, be inserted into the old pipeline 4 that will replace, can reduce like this wearing and tearing of smear metal tooth to tension force of pipeline.But, because chip is pushed to outward edge along conical heading end, be unfavorable for the discharge of pipeline chip, easily cause chip to be blocked in the front end of shield machine structure, reduce the efficiency of constructing.
Summary of the invention
In view of above-mentioned, of the present inventionly provide a kind of equipment and method of construction of carrying out non-excavating underground pipe line replacing to eat pipe method, use is arranged on the old pipeline of the outer shroud cutter rotary-cut stratum on shield machine structure, use is fixed on shield machine structure and is funnelform interior ring Tool in Cutting and pushes old pipeline, make its fragmentation, can discharge better so old pipeline chip.
According to an aspect of the present invention, provide a kind of more exchange device of non-excavation pipeline with dicyclo cutter, comprising:
Haulage gear, shield machine structure and slip casting mechanism, wherein,
Described haulage gear is connected to the front end of described shield machine structure by tow rope, pull described shield machine structure to travel forward, and described slip casting mechanism is connected to described shield machine structure from rear end by circulation slurry injection pipe;
Described shield machine structure comprises the cutting tool that is positioned at front end and the driving mechanism that is positioned at rear end, and has tow rope connected element at its front end, has in its back-end new pipe connecting part;
In the time that described shield machine structure travels forward, the broken old pipeline of the cutting tool of front end, the fragment of generation is taken out of by circulation slurry injection pipe by described slip casting mechanism;
In the time that described shield machine structure travels forward, lay the new pipeline that is connected to described shield machine structure rear end simultaneously;
The said equipment is characterised in that,
The cutting tool of described shield machine structure front end comprises outer shroud cutter and interior cutting ring tool, described outer shroud cutter is positioned at shield machine structure front end radial edges, drive rotation by described driving mechanism, be used for cutting old pipeline stratum, channel diameter is expanded to lay new pipeline, described interior cutting ring tool is funnel-like, is positioned at the inner side of described outer shroud cutter and is fixed on described shield machine structure, for cutting and squeeze the tube wall of broken old pipeline.
Described equipment is characterised in that, described outer cutting ring external diameter is slightly larger than needs the new pipe external diameter laid, its internal diameter to be greater than to need the old outer diameter tube changed.
Described equipment is characterised in that, described in be funnelform interior cutting ring tool, its external diameter is greater than needs the old outer diameter tube changed, internal diameter to be less than to need the old internal diameter of the pipeline changed.
According to a further aspect in the invention, provide a kind of the said equipment that uses to carry out the method that non-excavation pipeline is changed, comprise the steps:
Before construction, prepare: understand the situation of stratum and underground water, and the position of underground existing pipeline and other embedded objects, and solve power supply for construction, water;
Excavation of foundation pit: the old pipe ends of changing at needs is dug respectively two working pits, prepares mud pit simultaneously;
Equipment is installed: after the said equipment is in place, described haulage gear, described shield machine structure and described slip casting mechanism are installed, and by tow rope, described haulage gear and described shield machine structure are coupled together, and circulating mud pipe is placed in new pipeline, its grouting port and pulp absorbing hole are respectively installed to the opening of driving mechanism end;
Replace tubes construction: start power supply, haulage gear pulls described shield machine structure to carry out forward construction operation along old pipeline by tow rope, broken old pipeline is also laid new pipeline, and mud circulation is done in the hole of new hole enlargement by described slip casting of while mechanism, takes away the old pipeline chip cutting down;
Construction finishes: described equipment is shifted out to working pit, new pipeline is processed and landfill work hole;
Above-mentioned construction sequence is characterised in that, in above-mentioned replace tubes construction sequence:
With advancing of described shield machine structure, be the described interior cutting ring tool cutting of leak shape and inwardly push old tube wall, by old tube wall fragmentation;
The driving mechanism of described shield machine structure drives described outer shroud cutter fast rotational, and old tube wall is carried out to rotary-cut hole enlargement in stratum around.
Adopt above-mentioned Apparatus and method for to carry out non-excavation pipeline and change, can discharge better old pipeline fragment, avoid stopping up, improve efficiency of construction.
Brief description of the drawings
According to following detailed description of carrying out with reference to accompanying drawing, it is more apparent that the features and advantages of the present invention will become.In the accompanying drawings:
Fig. 1 is the existing more schematic diagram of exchange device of pipe method pipeline of eating.
Fig. 2 is the more schematic diagram of exchange device of non-excavation pipeline according to the first embodiment of the present invention.
Fig. 3 is the structural representation of outer shroud cutter and interior cutting ring tool.
Fig. 4 uses the non-excavation pipeline replacing method of the second embodiment of the present invention to carry out the schematic diagram of pipeline replacing construction.
Embodiment
The present invention is described below with reference to the accompanying drawings.Should be understood that, illustrated invention herein can be by varied form specific implementation, and disclosed any concrete structure, function or both are only representational in this article.Based on explanation herein, those skilled in the art should be understood that, an aspect disclosed herein can be independent of any other side and realize, and two or more aspects in these aspects can combine according to variety of way.Meanwhile, the size of each several part and reality not quite identical in this paper accompanying drawing, and can be because zooming in or out for convenience and for the purpose of clear.
The first embodiment:
Fig. 2 is the more schematic diagram of exchange device of non-excavation pipeline according to the first embodiment of the present invention.
As shown in Figure 2, according to the non-excavation pipeline of the first embodiment of the present invention more exchange device comprise: shield machine structure 1, haulage gear 2 and slip casting mechanism 3.
Wherein, shield machine structure 1 comprises outer shroud cutter 11, interior cutting ring tool 12, driving mechanism 16 and tow rope connected element 13 and new pipe connecting part 14.Haulage gear 2 comprises distractor 22 and tow rope 21.Slip casting mechanism 3 comprises grouting pump 31 and circulation slurry injection pipe 32.
Outer shroud cutter 11 and interior cutting ring tool 12 drive rotation by driving mechanism 16;
Fig. 3 is the structural representation of outer shroud cutter and interior cutting ring tool.As shown in Figure 3, outer shroud cutter 11 is arranged on shield machine structure 1 front end radially outer edge, and side is interior cutting ring tool 12 therein, and interior cutting ring tool 12 is funnel-like.
The front end center of shield machine structure 1 is fixed with tow rope connected element 13, and the distractor 22 of described haulage gear 2 is connected with it by tow rope 21, travels forward to drag shield machine structure 1;
Shield machine structure 1 connects the new pipeline 5 of laying by the new pipe connecting part 14 of its rear end;
The circulating mud pipe 32 of slip casting mechanism 3 enters driving mechanism 1 in new pipeline 5, and its grouting port and pulp absorbing hole stretch out by the opening of described driving mechanism end, can carry out mud circulation by the grouting pump 31 of described slip casting mechanism 3.
When work, distractor 22 drags shield machine structure 1 by tow rope 21 and travels forward along the axis of old pipeline 4; In the proal process of shield machine structure 1, driving mechanism 16 drives outer shroud cutter 11 and interior cutting ring tool 12 fast rotational, cutting ring tool 11 carries out rotary-cut hole enlargement in stratum around to old tube wall, is funnelform interior cutting ring tool 12 and cuts the tube wall of old pipeline 4 and inwardly push and make tube wall fragmentation; Along with advancing of shield machine structure 1, the new pipeline 5 that is connected to its rear end is also laid forward; Meanwhile, slip casting mechanism 3 is used grouting pump 31 that mud is circulated and injected in the hole of new hole enlargement by circulating mud pipe 32, and lubricated cutter reduces the frictional force on new pipe 5 and stratum, and the old pipeline of fragmentation is taken out of.
The second embodiment:
According to the method for construction described in the present embodiment, do not need pipeline to do and excavate the replacing that can complete pipeline completely.
Fig. 4 uses the non-excavation pipeline replacing method of the second embodiment of the present invention to carry out the schematic diagram of pipeline replacing construction.With reference to figure 4, use non-excavation pipeline of the present invention more exchange device carry out pipeline and change when construction, carry out as follows:
First, do the front preparation of construction: understand the situation of stratum and underground water, and the position of underground existing pipeline and other embedded objects, and solve power supply for construction, water;
Then, excavation of foundation pit: two working pits 61 and 62 are dug respectively in the old pipeline rear and front end of changing at needs, prepare mud pit simultaneously.
Afterwards, erection unit: described pipeline more exchange device in place after, first shield machine structure 1 is transported in working pit 62, be arranged in the position coaxial with old pipeline, then distractor (winch) 22 is fixed on to working pit 61 edges, and by angle pulley, with the shield machine structure 1 of tow rope connection tractor 22 and described equipment; And the circulating mud pipe of described equipment 32 is placed in new pipeline 5, the grouting port of circulating mud pipe 32 and grout outlet are respectively installed on driving mechanism 16.
Afterwards, start construction: start power supply, the driving mechanism 16 of the shield machine structure 1 of described equipment drives outer shroud cutter 11 and interior cutting ring tool 12 fast rotational, outer shroud cutter 11 carries out rotary-cut hole enlargement in stratum around to old tube wall; The distractor 22 of described equipment pulls described shield machine structure 1 constantly to advance by tow rope 21, the interior cutting ring tool 12 of described shield machine structure 1 cutting old pipeline 4 tube wall in by old tube wall attrition crushing; New pipeline 5 is connected to the rear end of described shield machine structure 1, and lays forward new pipeline with the motion of shield machine structure 1; Meanwhile, the slip casting mechanism 3 of described equipment is used grouting pump 31 by circulating mud pipe 32, mud constantly to be circulated in the hole of new hole enlargement, and the resistance advancing to reduce new pipeline 5 lubricates cutter, and takes away the chip of the old pipeline 4 cutting down.
Finally, construction finishes: described equipment is shifted out to working pit, new pipeline is processed and landfill work hole.
Although as above describe having carried out according to embodiments of the invention with reference to accompanying drawing, it will be appreciated by those skilled in the art that the embodiment that foregoing invention is proposed, can also on the basis that does not depart from content of the present invention, make various improvement.Therefore, protection scope of the present invention should be determined by the content of appending claims.

Claims (4)

1. a more exchange device of non-excavation pipeline with dicyclo cutter, comprising:
Haulage gear, shield machine structure and slip casting mechanism, wherein,
Described haulage gear is connected to the front end of described shield machine structure by tow rope, pull described shield machine structure to travel forward, and the rear end of described shield machine structure is connected with new pipeline, and described slip casting mechanism is connected to described shield machine structure from rear end by circulation slurry injection pipe;
Described shield machine structure comprises the cutting tool that is positioned at front end and the driving mechanism that is positioned at rear end, and described driving mechanism drives described cutting tool fast rotational;
In the time that described shield machine structure travels forward, the broken old pipeline of the cutting tool of front end, the fragment of generation is taken out of by circulation slurry injection pipe by described slip casting mechanism;
In the time that described shield machine structure travels forward, lay the new pipeline that is connected to its rear end simultaneously;
The said equipment is characterised in that,
The cutting tool of described shield machine structure front end comprises outer shroud cutter and interior cutting ring tool, described outer shroud cutter is positioned at shield machine structure front end radial edges, be used for cutting old pipeline stratum, channel diameter is expanded to lay new pipeline, described interior cutting ring tool is funnel-like, be positioned at the inner side of described outer shroud cutter, for cutting and squeeze the tube wall of broken old pipeline.
2. equipment according to claim 1, is characterized in that, described outer cutting ring external diameter is slightly larger than the new pipe external diameter that needs laying, and its internal diameter is greater than the old outer diameter tube that needs replacing.
3. equipment according to claim 1, is characterized in that, described in be funnelform interior cutting ring tool, its external diameter be greater than need change old outer diameter tube, internal diameter be less than need change old internal diameter of the pipeline.
4. right to use requires equipment described in 1 to carry out the method that non-excavation pipeline is changed, and comprises the steps:
Before construction, prepare: understand the situation of stratum and underground water, and the position of underground existing pipeline and other embedded objects, and solve power supply for construction, water;
Excavation of foundation pit: the old pipe ends of changing at needs is dug respectively two working pits, prepares mud pit simultaneously;
Equipment is installed: after equipment as claimed in claim 1 is in place, described haulage gear, described shield machine structure and described slip casting mechanism are installed, and by tow rope, described haulage gear and described shield machine structure are coupled together, and circulating mud pipe is placed in new pipeline, its grouting port and pulp absorbing hole are respectively installed to the opening of driving mechanism end;
Replace tubes construction: start power supply, described haulage gear pulls described shield machine structure to carry out forward construction operation along old pipeline by tow rope, broken old pipeline is also laid new pipeline, and mud circulation is done in the hole of new hole enlargement by described slip casting of while mechanism, takes away the old pipeline chip cutting down;
Construction finishes: described equipment is shifted out to working pit, new pipeline is processed and landfill work hole;
Above-mentioned construction sequence is characterised in that, in above-mentioned replace tubes construction sequence:
With advancing of described shield machine structure, be the described interior cutting ring tool cutting of leak shape and inwardly push old tube wall, by old tube wall fragmentation;
The driving mechanism of described shield machine structure drives described outer shroud cutter fast rotational, and old tube wall is carried out to rotary-cut hole enlargement in stratum around.
CN201310113108.7A 2013-04-02 2013-04-02 Trenchless pipeline replace equipment with double-ring cutter and method thereof Active CN103234075B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310113108.7A CN103234075B (en) 2013-04-02 2013-04-02 Trenchless pipeline replace equipment with double-ring cutter and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310113108.7A CN103234075B (en) 2013-04-02 2013-04-02 Trenchless pipeline replace equipment with double-ring cutter and method thereof

Publications (2)

Publication Number Publication Date
CN103234075A CN103234075A (en) 2013-08-07
CN103234075B true CN103234075B (en) 2014-11-19

Family

ID=48882127

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310113108.7A Active CN103234075B (en) 2013-04-02 2013-04-02 Trenchless pipeline replace equipment with double-ring cutter and method thereof

Country Status (1)

Country Link
CN (1) CN103234075B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106764054A (en) * 2017-01-04 2017-05-31 陕西中科非开挖技术股份有限公司 A kind of piping foundation method for non-excavating construction
CN110919290B (en) * 2019-11-19 2021-04-16 中国地质大学(武汉) Cutting swallowing tube type pipeline updating device
CN110725387B (en) * 2019-11-26 2021-02-26 中铁十八局集团有限公司 Aircraft nose suitable for fragmentation method updates reinforced concrete pipeline
CN112664215A (en) * 2020-12-29 2021-04-16 天津倚通科技发展有限公司 Laying method of trenchless new pipeline
CN114719082A (en) * 2021-01-05 2022-07-08 中国石油天然气集团有限公司 Pipe replacing machine
CN113145244B (en) * 2021-04-02 2022-06-03 长江生态环保集团有限公司 Universal crushing head and method for flexible and rigid pipe construction by pipe cracking method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1269003A (en) * 1995-04-28 2000-10-04 Tti管线施工技术有限公司 Method and apparatus for cleaning public pipeline and then changed with polyolefin pipeline
LV12649B (en) * 2000-05-17 2001-05-20 Suis-Rīga, Sia Method for trenchless replacement of pipe-line and device for realization thereof
RU2230966C1 (en) * 2002-10-30 2004-06-20 Красноярский государственный технический университет Pipeline trenchless replacement method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005336884A (en) * 2004-05-27 2005-12-08 Hitachi Constr Mach Co Ltd Underground buried pipe conduit renewing method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1269003A (en) * 1995-04-28 2000-10-04 Tti管线施工技术有限公司 Method and apparatus for cleaning public pipeline and then changed with polyolefin pipeline
LV12649B (en) * 2000-05-17 2001-05-20 Suis-Rīga, Sia Method for trenchless replacement of pipe-line and device for realization thereof
RU2230966C1 (en) * 2002-10-30 2004-06-20 Красноярский государственный технический университет Pipeline trenchless replacement method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开2005-336884A 2005.12.08 *

Also Published As

Publication number Publication date
CN103234075A (en) 2013-08-07

Similar Documents

Publication Publication Date Title
CN103234075B (en) Trenchless pipeline replace equipment with double-ring cutter and method thereof
CN103234076B (en) Device for exchanging underground pipelines without trenching and application method thereof
CN105297807B (en) A kind of integrated pipe canal open cut development machine with automatic backfill function
CN204212700U (en) Drill bit in a kind of conduit jacking
CN102562084B (en) TBM (tunnel boring machine) cutter expansion and contraction device
CN112483104B (en) Pipe-inserting method pipeline updating heading machine and construction method
CN203924301U (en) A kind of propelling with volume rises cooperating type pipeline displacement prosthetic device
CN205876328U (en) Hard rock pipe pushing jack rectifying system
CN204164493U (en) A kind of sniffer for jacking construction
CN202810846U (en) Excavating equipment
CN210003208U (en) non-broken path cable pipeline laying drilling device
CN110454184A (en) A kind of subway entrance people row short tunnel excavating gear
KR101416716B1 (en) rotary table of excavation device of having water jet
CN206464606U (en) A kind of tube cutting machine built in well casing
CN204941554U (en) A kind of for Double-cutter structure inside and outside underground pipeline excavating gear
CN210344519U (en) Pipe jacking device for underground pipeline construction
CN107322078A (en) A kind of endless knife cutting pipeline rehabilitation device and pipe repairing method
CN204510210U (en) The anchor cable construction device that a kind of pore-forming, installation, slip casting are three-in-one
CN107100634A (en) A kind of weak broken wall rock location TBM constructing devices
CN206647612U (en) Dual-purpose type push pipe head
CN106735522A (en) A kind of built-in tube cutting machine of well casing
CN203476336U (en) Shield tunneling machine for shaft
CN207204790U (en) A kind of flexible strength milling dredge
CN207212370U (en) Antipriming between a kind of large diameter steel pipe pipe curtain spigot-and-socket pipe
CN206328792U (en) The coiling apparatus of pipeline can be laid

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 100085, Beijing economic and Technological Development Zone, 1 Kangding street, 2 buildings, six or seven floors

Patentee after: MCC COMMUNICATION CONSTRUCTION GROUP CO., LTD.

Address before: 100028, Beijing, Chaoyang District, No. 28, west of China Metallurgical Building, 18 and 19

Patentee before: MCC Communication Engineering Technology Co., Ltd.