CN103199468B CN201310073583.6A CN201310073583A CN103199468B CN 103199468 B CN103199468 B CN 103199468B CN 201310073583 A CN201310073583 A CN 201310073583A CN 103199468 B CN103199468 B CN 103199468B
Authority
CN
China
Prior art keywords
chute
slide construction
gag lever
lever post
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310073583.6A
Other languages
Chinese (zh)
Other versions
CN103199468A (en
Inventor
鲁大伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Honor Device Co Ltd
Original Assignee
Huawei Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei Technologies Co Ltd filed Critical Huawei Technologies Co Ltd
Priority to CN201310073583.6A priority Critical patent/CN103199468B/en
Publication of CN103199468A publication Critical patent/CN103199468A/en
Application granted granted Critical
Publication of CN103199468B publication Critical patent/CN103199468B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The invention discloses a kind of chute, it comprises limiting section, sliding part and resettlement section.Limiting section comprises body and position limiting structure, and position limiting structure extends from the inwall of body towards sliding part and comprises the first gag lever post and second gag lever post relative with the first gag lever post.Sliding part and limiting section are slidably connected and comprise operating body and slide construction, and slide construction extends from the bottom of operating body towards limiting section and corresponding with position limiting structure.Slide construction comprises the first slide construction second slide construction relative with the first slide construction.First gag lever post can slide by relative first slide construction, and the second gag lever post can slide by relatively described second slide construction, and resettlement section is enclosed cabling space, for accommodating cable.The invention provides and additionally provide a kind of communication equipment.Chute provided by the invention and communication equipment, utilize resettlement section to be enclosed cabling space, thus prevent cable from landing chute.

Description

Chute and communication equipment
Technical field
The present invention relates to the communications field, particularly relate to a kind of chute and communication equipment.
Background technology
Along with the development of information technology, the interface of the veneer in communication equipment gets more and more, port density is also more and more higher, the cabling quantity of whole communication equipment is caused sharply to increase, the cabling space of chute how is made to carry more cable, and ensure the safety of cable and the convenient of operation, all become the key factor affecting communication equipment overall performance.Please refer to Figure 14, existing chute is generally provided with an accepting hole 900 put into for cable, but accepting hole 900 is open cabling space, and when cabling quantity is too much, cable exceedes the height of accepting hole 900, and cable is very easily from landing chute.
Summary of the invention
Technical problem to be solved by this invention is, there is the problem of cable from chute landing for solving prior art.
To achieve these goals, embodiment of the present invention provides following technical scheme:
On the one hand, provide a kind of chute, it is installed on the rack of communication equipment, for combing cable, it is characterized in that: described chute comprises limiting section, at least one sliding part and at least one resettlement section, described limiting section comprises body and at least one position limiting structure, described position limiting structure extends from the inwall of described body towards described sliding part, described position limiting structure comprises the first gag lever post and second gag lever post relative with the first gag lever post, described sliding part and described limiting section are slidably connected, described sliding part comprises operating body and slide construction, described slide construction to extend and corresponding with described position limiting structure from the bottom of described operating body towards described limiting section, described slide construction comprises the first slide construction second slide construction relative with described first slide construction, described first gag lever post can slide by relatively described first slide construction, described second gag lever post can slide by relatively described second slide construction, described resettlement section is enclosed cabling space, for accommodating cable, described first gag lever post comprises stop hook, described stop hook is positioned at the end of described first gag lever post, the end of described stop hook is provided with barb, described first slide construction also comprises the second projection, described second projection deviates from described second slide construction from the inwall of described first chute and protrudes and the middle part being positioned at described first slide construction, when described chute is in open mode, described in described barbs hold, second is protruding.
In the implementation that the first is possible, described first gag lever post comprises convex the first boss to described second gag lever post, described second gag lever post comprises convex the second boss to described first gag lever post, and the width of described first boss is equal with the width of described second boss.
In conjunction with the implementation that the first is possible, in the implementation that the second is possible, described first slide construction comprises the first chute, described second slide construction comprises the second chute, the width of described first chute is equal with the width of described second chute, described first boss is contained in described first chute, and described second boss is contained in described second chute.
In conjunction with the implementation that the first is possible, in the implementation that the third is possible, described first gag lever post comprises location division, the first groove and the second groove, and described location division is near described body, and described first groove and described second groove are positioned at the two ends of described location division.
In conjunction with the implementation that the third is possible, in the 4th kind of possible implementation, described first slide construction also comprises the first projection, described first projection deviates from described second slide construction from the inwall of described first chute and protrudes and the end away from described operating body being positioned at described first slide construction, wherein, when described first projection is contained in described second groove, described chute is in open mode; When described first projection is contained in described first groove, described chute is in closed condition.
In conjunction with the 5th kind of possible implementation, in the 6th kind of possible implementation, described first slide construction also comprises a pair operating portion, and described operating position is protruding near described second in a pair of described first slide construction relative sidewall, for manipulating described second protruding.
In conjunction with the 4th kind of possible implementation, in the 7th kind of possible implementation, described first gag lever post also comprises the first inclined-plane, described first inclined-plane is positioned at the end of described first gag lever post and described second gag lever post dorsad, described sliding part also comprises a pair first oblique portions, described first oblique portion extends obliquely from the two opposite side walls of described first slide construction and the intersection of described operating body, and when described chute is in closed condition, described first inclined-plane inserts between the described first oblique portion.
In conjunction with the 4th kind of possible implementation, in the 8th kind of possible implementation, described second gag lever post also comprises the second inclined-plane, described second inclined-plane is positioned at the end of described second gag lever post and described first gag lever post dorsad, described sliding part also comprises a pair second oblique portions, described second oblique portion extends obliquely from the two opposite side walls of described second slide construction and the intersection of described operating body, and when described chute is in closed condition, described second inclined-plane inserts between the described second oblique portion.
In conjunction with the implementation that the third is possible, in the 9th kind of possible implementation, described first gag lever post also comprises the 3rd groove, and described 3rd groove is located at described location division and between described first groove and described second groove.
In conjunction with the 9th kind of possible implementation, in the tenth kind of possible implementation, described first slide construction also comprises the first projection, described first projection deviates from described second slide construction from the inwall of described first chute and protrudes and the end away from described operating body being positioned at described first slide construction, wherein, when described first projection is contained in described second groove, described chute is in open mode; When described first projection is contained in described first groove or the 3rd groove, described chute is in closed condition.
In the 11 kind of possible implementation, described sliding part also comprises gap, and described gap is between described first slide construction and described second slide construction.
In conjunction with the 11 kind of possible implementation, in the 12 kind of possible implementation, described sliding part also comprises multiple reinforcement, and described reinforcement between described first slide construction and described second slide construction, and splits described gap.
On the other hand, provide a kind of communication equipment, it comprises rack and at least one is installed on above-mentioned chute in described rack.
Chute provided by the invention and communication equipment, utilize resettlement section to be enclosed cabling space, thus prevent cable from landing chute.
Accompanying drawing explanation
In order to be illustrated more clearly in the technical scheme in the embodiment of the present invention, below the accompanying drawing used required in describing embodiment is briefly described, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the schematic diagram of communication equipment provided by the invention;
Fig. 2 is the decomposing schematic representation of the first execution mode of chute provided by the invention;
Fig. 3 is another angle schematic diagram of the chute in Fig. 2;
Fig. 4 is the cross-sectional schematic of the chute in Fig. 2;
Fig. 5 is the open mode schematic diagram of the chute in Fig. 2;
Fig. 6 is the cross-sectional schematic of the chute in Fig. 4;
Fig. 7 is the closed condition schematic diagram of the chute in Fig. 2;
Fig. 8 is the cross-sectional schematic of the chute in Fig. 7;
Fig. 9 is another angle cross-sectional schematic of the chute in Fig. 7
Figure 10 is the cabling schematic diagram in cable communication equipment in FIG;
Figure 11 is the cabling schematic diagram of cable in chute;
Figure 12 is the schematic diagram of the second execution mode of chute provided by the invention;
Figure 13 is the schematic diagram of the third execution mode of chute provided by the invention;
Cabling schematic diagram in Figure 14 communication equipment that to be cable provide in prior art.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, be clearly and completely described the technical scheme in the embodiment of the present invention, obviously, described embodiment is only the present invention's part embodiment, instead of whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtained under creative work prerequisite, belong to the scope of protection of the invention.
Please refer to Fig. 1 and Fig. 8, the communication equipment 800 that embodiment of the present invention provides, it comprises rack 700 and multiple chute 100.Chute 100 is installed on rack 700, for the cable in combing communication equipment 800.
Please also refer to Fig. 2 to Fig. 4, the chute 100 that embodiment of the present invention provides, it comprises limiting section 10, sliding part 30 and resettlement section 50, and resettlement section 50 is for accommodating cable.
Limiting section 10 is installed on rack 700, and comprises body 12, first gag lever post 14 and second gag lever post 16 relative with the first gag lever post 14.
In the present embodiment, the first gag lever post 14 and the second gag lever post 16 are referred to as position limiting structure 15.Position limiting structure 15 extends from the bottom of body 12 towards sliding part 30.
Body 12 comprises the first installing hole 120 and the second installing hole 124.In the present embodiment, the first installing hole 120 is screwed hole, and the second installing hole 124 is hardy hole.During installation, by the second installing hole 124, chute 100 is hung on rack 700, an installed part 90, as screw, is fixed in the first installing hole 120, so that chute 100 is fixed on rack 700.
First gag lever post 14 extends from the madial wall of body 12 towards sliding part 30, and comprises convex the first boss 140 (please refer to Fig. 9) to the second gag lever post 16.
First boss 140 comprises location division 141, first groove 142, second groove 144, slope 146, position-arresting part 148 and stop hook 149.Location division 141 is near body 12, and the first groove 142 is positioned at one end near body 12, location division 141, and the second groove 144 is positioned at the other end of location division 141 near slope 146, and namely the first groove 142 and the second groove 144 are positioned at the two ends of location division 141.Slope 146 is for connecting position-arresting part 148 and location division 141 and between the second groove 144 and position-arresting part 148, the difference in height namely between location division 141 and position-arresting part 148 is connected by slope 146.
In the present embodiment, the first groove 142 and the second groove 144 are semicircle.
The height of position-arresting part 148 is less than the height of location division 141, and stop hook 149 is positioned at the end of position-arresting part 148, and namely stop hook 149 is positioned at the end of the first gag lever post 14.The height of stop hook 149 is equal with the height of location division 141, stop hook 149 is towards the second gag lever post 16, stop hook 149 is the first vertical plane 1490 towards a side of body 12, and the another side deviating from body 12 is inclined-plane, thus forms barb 1492 at the end of stop hook 149.
First gag lever post 14 also comprises the first inclined-plane 147, inclined-plane 147, first and is positioned at the end of the first gag lever post 14 and the second gag lever post 16 dorsad.First inclined-plane 147 near one end of body 12 higher than the other end.
Second gag lever post 16 extends from the madial wall of body 12 towards sliding part 30, and comprises the second boss 160 (please refer to Fig. 9).Second boss 160 is convex equal with the width of the second boss 160 to the width of the first gag lever post 14, first boss 140.
Second gag lever post 16 also comprises the second inclined-plane 167, inclined-plane 167, second and is positioned at the end of the second gag lever post 16 and the first gag lever post 14 dorsad.Second inclined-plane 167 near one end of body 12 higher than the other end.
Sliding part 30 and limiting section 10 are slidably connected, and comprise operating body 31, first slide construction 32 and second slide construction 34 relative with the first slide construction 32.Operating body 31 for operating sliding part 30, as promote or pull sliding part 30.The height of operating body 31 equals the height of body 12.
First slide construction 32 and the second slide construction 34 are referred to as slide construction 33, slide construction 33 extends from the bottom of operating body 31 towards limiting section 10 and corresponding with position limiting structure 15, and namely position limiting structure 15 and body 12 position relationship in the height direction and slide construction 33 are corresponding with operating body 31 position relationship in the height direction.
First slide construction 32 comprises the first chute 320, second slide construction 34 and comprises the second chute 340.The width of the first chute 320 is equal with the width of the second chute 340, and slightly larger than the width of the first boss 140 and the second boss 160.During assembling, the first boss 140 of the first gag lever post 14 is contained in the first chute 320, and the second boss 160 of the second gag lever post 16 is contained in the second chute 340, thus limiting section 10 and sliding part 30 is assembled into one.At this assembling position, the first gag lever post 14 can slide by relative first slide construction 32, and the second gag lever post 16 can slide by relative second slide construction 34.
First slide construction 32 also comprises the first projection 322, second protruding 324 and a pair protruding 322 semicircular in shape of operating portion 326, first, and is positioned at the end away from operating body 31 of the first slide construction 32.Second projection 324 is positioned at the middle part of the first slide construction 32.First protruding 322 and second protruding 324 all deviates from the second slide construction 34 from the inwall of the first chute 320 protrudes.Second projection 324 comprises the second vertical plane 3240, second vertical plane 3240 oriented manipulation body 31.Described operating portion 326 is positioned at the relative sidewall of a pair of the first slide construction 32 and near the second projection 324, for manipulating the second projection 324.
Sliding part 30 also comprises a pair first oblique portions 36 and a pair second oblique portions 38, described first oblique portion 36 extends obliquely from the two opposite side walls of the first slide construction 32 and the intersection of operating body 31, and each first height of oblique portion 36 near operating body 31 one end is greater than the height of the other end.After installation, one end that one end that the first inclined-plane 147 is slightly high is slightly low near each first oblique portion 36, and the height of first slightly high one end, inclined-plane 147 is higher than the height of first slightly low one end, oblique portion 36.
Described second oblique portion 38 extends obliquely from the two opposite side walls of the second slide construction 34 and the intersection of operating body 31.Each second height of oblique portion 38 near operating body 31 one end is greater than the height of the other end.After installation, one end that one end that the second inclined-plane 167 is slightly high is slightly low near each second oblique portion 38, and the height of second slightly high one end, inclined-plane 167 is higher than the height of second slightly low one end, oblique portion 38.
In the present embodiment, the cross section in the first oblique portion 36 and the second oblique portion 38 is all triangular in shape, especially, and the cross section all at right angles triangle in the first oblique portion 36 and the second oblique portion 38.
Sliding part 30 also comprises gap 37 and multiple reinforcement 39, gap 37 is between the first slide construction 32 and the second slide construction 34, be beneficial to the first protruding 322 and second protruding 324 strains of the first slide construction 32, and then be beneficial to limiting section 10 relative sliding portion 30 and slide.
Reinforcement 39 between the first slide construction 32 and the second slide construction 34, for connecting the first slide construction 32 and the second slide construction 34.
Resettlement section 50 is surrounded, for accommodating cable by limiting section 10 and sliding part 30.The resettlement section 50 of single chute 100 is semienclosed cabling space, fit together when chute 100 is installed in rack 700 or with another chute 100, resettlement section 50 is closed, and namely resettlement section 50 becomes enclosed cabling space by semienclosed cabling space.In other words, resettlement section 50 is the enclosed cabling space jointly surrounded by limiting section 10, sliding part 30 and rack 700, or resettlement section 50 is the enclosed cabling space jointly surrounded by limiting section 10, sliding part 30 and adjacent traces frame 100.
Please also refer to Fig. 5 and Fig. 6, for chute 100 is in the schematic diagram of open mode.During assembling, sliding part 30 is inserted position limiting structure 15 and pushes away sliding part 30, the first projection 322 is made to cross stop hook 149, slope 146 until the first projection 322 is contained in the second groove 144, second projection 324 is crossed stop hook 149 and makes the barb 1492 of stop hook 149 hook the second vertical plane 3240 of the second projection 324 simultaneously, thus sliding part 30 is installed on limiting section 10 slidably.In this open mode, the first vertical plane 1490 of stop hook 149 and the second vertical plane 3240 of the second projection 324 form back-off, skid off position limiting structure 15 for preventing sliding part 30.Meanwhile, because the first projection 322 is contained in the second groove 144, thus limit slippage portion 30 skids off position limiting structure 15.In other words, in this open mode, sliding part 30, under the effect not having external force, can not relative limit structure 15 slide.
Please refer to Fig. 7 and Fig. 8, for chute 100 is in the schematic diagram of closed condition.Continue to push away sliding part 30 until the first projection 322 is contained in the first groove 142, simultaneously the body 12 of sliding part 30 near one end of the first projection 322 against limiting section 10.In this closed condition, because the first projection 322 is contained in the first groove 142, thus limit slippage portion 30 skids off position limiting structure 15.
During use, as cable put into chute 100, only coil holder 100 need be moved to open mode from closed condition, namely sliding part 30 is pulled, first protruding 322 there is strain and skids off the first groove 142 until the first projection 322 slips into the second groove 144, thus chute 100 is just in open mode.In open mode, cable can be put into chute.After installing cable, only coil holder 100 need be moved to closed condition from open mode, namely promote sliding part 30, first protruding 322 strain occurs and skids off the second groove 144 until the first projection 322 slips into the first groove 142, thus chute 100 is just in closed condition.
During dismounting, chute 100 is first made to be in open mode, second protruding 324 is made to produce strain from both sides press operating part 326 again, when the second vertical plane 3240 of the second projection 324 departs from the barb 1492 of stop hook 149, sliding part 30 is extracted out from position limiting structure 15, just completes the dismounting of chute 100.
Please also refer to Figure 10, because cable is positioned in resettlement section 50, and resettlement section 50 is enclosed cabling space, and when cabling quantity is too much, cable also can not from two side landing, and the cable be namely contained in resettlement section 50 can not landing from resettlement section 50.In other words, cable is fixed in chute 100, no matter in use or in transportation, cable all can not from landing chute 100.
Please also refer to Figure 11, because the two side of the first slide construction 32 and the first slide construction 32 is respectively being provided with the first oblique portion 36 and the second oblique portion 38 near operating body 31 place.When described chute 100 is in closed condition, it is inner that the first inclined-plane 147 of position limiting structure 15 inserts the first oblique portion 36, and the cable being positioned over described chute 100 inside to be interlocked lifting by the first inclined-plane 147 and the first oblique portion 36, thus avoids the risk of clamp.In like manner, the second inclined-plane 167 inserts between the second oblique portion 38, is positioned over cable below chute 100 and is interlocked lifting by the second inclined-plane 167 and the second oblique portion 38, thus avoid the risk of clamp.
Please refer to Figure 12, the chute 100a that the second execution mode of the present invention provides, the chute 100a that described the second execution mode provides is substantially identical with the structure of the chute 100 (please refer to Fig. 2) that the first execution mode provides, the functional similarity realized, its difference is, chute 100a comprises limiting section 10a, multiple sliding part 30a and multiple resettlement section 50a, limiting section 10a comprises body 12a and multiple position limiting structure 15a, each position limiting structure 15a, corresponding sliding part 30a and corresponding resettlement section 50a forms a wiring unit, thus realize the use arranged side by side of multiple wiring unit.
Please refer to Figure 13, the chute 100b that the third execution mode of the present invention provides, the chute 100b that the third execution mode described provides is substantially identical with the structure of the chute 100 (please refer to Fig. 2) that the first execution mode provides, the functional similarity realized, its difference is, first gag lever post 14b also comprises the 3rd groove 140b, described 3rd groove 140b is located at described location division 141b and between the first groove 142b and the second groove 143b, first protruding 33b can accommodate the first groove 142b respectively, in second groove 143b and the 3rd groove 140b, thus the size of the cabling space of resettlement section 50b can be changed, during use, cabling space can be selected flexibly according to the actual requirements.Wherein, when described first protruding 33b is contained in described second groove 143b, described chute 100b is in open mode; When described first protruding 33b is contained in described first groove 142b or the 3rd groove 140b, described chute 100b is in closed condition.
Above-described execution mode, does not form the restriction to this technical scheme protection range.The amendment done within any spirit at above-mentioned execution mode and principle, equivalently to replace and improvement etc., within the protection range that all should be included in this technical scheme.

Claims (13)

1. a chute, be installed on the rack of communication equipment, for combing cable, it is characterized in that: described chute comprises limiting section, at least one sliding part and at least one resettlement section, described limiting section comprises body and at least one position limiting structure, described position limiting structure extends from the inwall of described body towards described sliding part, described position limiting structure comprises the first gag lever post and second gag lever post relative with the first gag lever post, described sliding part and described limiting section are slidably connected, described sliding part comprises operating body and slide construction, described slide construction to extend and corresponding with described position limiting structure from the bottom of described operating body towards described limiting section, described slide construction comprises the first slide construction second slide construction relative with described first slide construction, described first gag lever post can slide by relatively described first slide construction, described second gag lever post can slide by relatively described second slide construction, described resettlement section is enclosed cabling space, for accommodating cable, described first gag lever post comprises stop hook, described stop hook is positioned at the end of described first gag lever post, the end of described stop hook is provided with barb, described first slide construction also comprises second protruding and the first chute, described second projection deviates from described second slide construction from the inwall of described first chute and protrudes and the middle part being positioned at described first slide construction, when described chute is in open mode, described in described barbs hold, second is protruding.
2. chute as claimed in claim 1, it is characterized in that, described first gag lever post comprises convex the first boss to described second gag lever post, and described second gag lever post comprises convex the second boss to described first gag lever post, and the width of described first boss is equal with the width of described second boss.
3. chute as claimed in claim 2, it is characterized in that, described second slide construction comprises the second chute, and the width of described first chute is equal with the width of described second chute, described first boss is contained in described first chute, and described second boss is contained in described second chute.
4. chute as claimed in claim 2, it is characterized in that, described first gag lever post comprises location division, the first groove and the second groove, and described location division is near described body, and described first groove and described second groove are positioned at the two ends of described location division.
5. chute as claimed in claim 4, it is characterized in that, described first slide construction also comprises the first projection, described first projection deviates from described second slide construction from the inwall of described first chute and protrudes and the end away from described operating body being positioned at described first slide construction, wherein, when described first projection is contained in described second groove, described chute is in open mode; When described first projection is contained in described first groove, described chute is in closed condition.
6. chute as claimed in claim 5, it is characterized in that, described first slide construction also comprises a pair operating portion, and described operating position is protruding near described second in a pair of described first slide construction relative sidewall, protruding for manipulating described second.
7. chute as claimed in claim 5, it is characterized in that, described first gag lever post also comprises the first inclined-plane, described first inclined-plane is positioned at the end of described first gag lever post and described second gag lever post dorsad, described sliding part also comprises a pair first oblique portions, described first oblique portion extends obliquely from the two opposite side walls of described first slide construction and the intersection of described operating body, and when described chute is in closed condition, described first inclined-plane inserts between the described first oblique portion.
8. chute as claimed in claim 5, it is characterized in that, described second gag lever post also comprises the second inclined-plane, described second inclined-plane is positioned at the end of described second gag lever post and described first gag lever post dorsad, described sliding part also comprises a pair second oblique portions, described second oblique portion extends obliquely from the two opposite side walls of described second slide construction and the intersection of described operating body, and when described chute is in closed condition, described second inclined-plane inserts between the described second oblique portion.
9. chute as claimed in claim 4, it is characterized in that, described first gag lever post also comprises the 3rd groove, and described 3rd groove is located at described location division and between described first groove and described second groove.
10. chute as claimed in claim 9, it is characterized in that, described first slide construction also comprises the first projection, described first projection deviates from described second slide construction from the inwall of described first chute and protrudes and the end away from described operating body being positioned at described first slide construction, wherein, when described first projection is contained in described second groove, described chute is in open mode; When described first projection is contained in described first groove or the 3rd groove, described chute is in closed condition.
11. chutes as claimed in claim 1, it is characterized in that, described sliding part also comprises gap, and described gap is between described first slide construction and described second slide construction.
12. chutes as claimed in claim 11, it is characterized in that, described sliding part also comprises multiple reinforcement, and described reinforcement between described first slide construction and described second slide construction, and splits described gap.
13. 1 kinds of communication equipments, comprise rack, it is characterized in that: described communication equipment also comprises at least one and is installed on the chute described in claim 1 to 12 any one in described rack.
CN201310073583.6A 2013-03-07 2013-03-07 Chute and communication equipment Active CN103199468B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310073583.6A CN103199468B (en) 2013-03-07 2013-03-07 Chute and communication equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310073583.6A CN103199468B (en) 2013-03-07 2013-03-07 Chute and communication equipment

Publications (2)

Publication Number Publication Date
CN103199468A CN103199468A (en) 2013-07-10
CN103199468B true CN103199468B (en) 2016-03-30

Family

ID=48721872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310073583.6A Active CN103199468B (en) 2013-03-07 2013-03-07 Chute and communication equipment

Country Status (1)

Country Link
CN (1) CN103199468B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105262018A (en) * 2015-11-25 2016-01-20 扬中市扬子铝加工有限公司 Aluminium alloy wiring frame

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2746720Y (en) * 2004-11-10 2005-12-14 樊邦弘 Fixing fastener
CN1726625A (en) * 2002-12-11 2006-01-25 潘都依特有限公司 Cable support system
CN201066771Y (en) * 2007-08-07 2008-05-28 王卫东 T release-prevention and disassembly glass steel cable supporter
CA2586898A1 (en) * 2007-04-30 2008-10-30 Belden Cdt Canada Inc. Adjustable cable manager
CN201150159Y (en) * 2008-02-02 2008-11-12 杭州华三通信技术有限公司 Wiring frame and electronic apparatus containing the same
CN202488623U (en) * 2012-02-15 2012-10-10 中兴通讯股份有限公司 Cabling rack and communication device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6946605B2 (en) * 2003-12-01 2005-09-20 Ortronics, Inc. Cable management system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1726625A (en) * 2002-12-11 2006-01-25 潘都依特有限公司 Cable support system
CN2746720Y (en) * 2004-11-10 2005-12-14 樊邦弘 Fixing fastener
CA2586898A1 (en) * 2007-04-30 2008-10-30 Belden Cdt Canada Inc. Adjustable cable manager
CN201066771Y (en) * 2007-08-07 2008-05-28 王卫东 T release-prevention and disassembly glass steel cable supporter
CN201150159Y (en) * 2008-02-02 2008-11-12 杭州华三通信技术有限公司 Wiring frame and electronic apparatus containing the same
CN202488623U (en) * 2012-02-15 2012-10-10 中兴通讯股份有限公司 Cabling rack and communication device

Also Published As

Publication number Publication date
CN103199468A (en) 2013-07-10

Similar Documents

Publication Publication Date Title
CN102829043B (en) Engagement structure
CN201349370Y (en) Dust-proof structure and electronic equipment with same
CN203073740U (en) Self-service express delivery cabinet and combined cabinet of self-service express delivery cabinets
CN202421594U (en) Communication tray, drawer cabinet and communication rack
CN103199468B (en) Chute and communication equipment
CN104332759A (en) Positioning mechanism for USB (Universal Serial Bus) connection
CN204272526U (en) Controller for motor and electronic equipment
CN204065967U (en) Electronic equipment and fixing module
CN206524503U (en) A kind of adapter
CN204289809U (en) There is the connector of secondary lock construction
CN109508160A (en) Display integrates connecting line
CN104037549B (en) Pin connector
CN204045811U (en) Rj45 network interface and electronic product
CN203950990U (en) Pin connector, socket connector and connector combination
CN205178164U (en) Wire terminal connector
CN210806202U (en) Combined four-in-one automatic tripping welding socket
CN104103951A (en) Connector
US20140057481A1 (en) Connector
CN202957431U (en) Terminal device connector
CN105811144A (en) Connector having secondary lock structure
CN207910148U (en) A kind of knockdown winding displacement
EP2793338A2 (en) Fitting for mounting electrical elements or the like with a rectangular prismatic body in horizontal and vertical supports
CN203445281U (en) Four-core connector
CN213863410U (en) Carrying handle
CN204946483U (en) Casing pre-installation syndeton

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210425

Address after: Unit 3401, unit a, building 6, Shenye Zhongcheng, No. 8089, Hongli West Road, Donghai community, Xiangmihu street, Futian District, Shenzhen, Guangdong 518040

Patentee after: Honor Device Co.,Ltd.

Address before: 518129 Bantian HUAWEI headquarters office building, Longgang District, Guangdong, Shenzhen

Patentee before: HUAWEI TECHNOLOGIES Co.,Ltd.

TR01 Transfer of patent right