CN102830281B - A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system - Google Patents

A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system Download PDF

Info

Publication number
CN102830281B
CN102830281B CN201210299841.8A CN201210299841A CN102830281B CN 102830281 B CN102830281 B CN 102830281B CN 201210299841 A CN201210299841 A CN 201210299841A CN 102830281 B CN102830281 B CN 102830281B
Authority
CN
China
Prior art keywords
meter
electric energy
communication
intelligent electric
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210299841.8A
Other languages
Chinese (zh)
Other versions
CN102830281A (en
Inventor
张平
陈凯
宋锡强
梁胜民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING HUAHONG INSTRUMENT Co.,Ltd.
Original Assignee
Holley Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Holley Technology Co Ltd filed Critical Holley Technology Co Ltd
Priority to CN201210299841.8A priority Critical patent/CN102830281B/en
Priority to CN201510028124.5A priority patent/CN104678167B/en
Publication of CN102830281A publication Critical patent/CN102830281A/en
Application granted granted Critical
Publication of CN102830281B publication Critical patent/CN102830281B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Arrangements For Transmission Of Measured Signals (AREA)

Abstract

The invention discloses a kind of intelligent electric energy meter, comprise signal gathering unit, for accessing electric network power line; Signal processing unit, for receiving, calculating and the digital signal value of processing signals collecting unit; Communication terminal, for receiving communication request or sending data; Control module, obtain the external data information of intelligent electric energy meter for controlling and send data, described control module is connected with signal processing unit and communication terminal.The invention also discloses a kind of utility meter kilowatt meter reading-out system, comprise terminal system and aforementioned intelligent electric energy meter, also comprise by the M-BUS bus in addition water meter, gas meter and the hotlist that connect of communication, described intelligent electric energy meter is by carrying out communication between wireless network and terminal system.Different utility meters without the need to using power information data acquisition equipment and data concentrator equipment, and is connected in M-BUS bus and carries out control and management by the present invention, has power consumption lower, communication robust, simple for structure, the advantage that cost is low.

Description

A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system
Technical field
The present invention relates to utility commodity (such as water, electricity, rock gas etc.) surveying instrument instrument field, in more specific words it, the present invention relates to the intelligent electric energy meter of a kind of alternate data collector or concentrator devices, and comprise the automatic meter reading system of this intelligent electric energy meter.
Background technology
The remote meter reading mode of civilian instrument carries out communication by a data acquisition unit by RS485 bus and data are copied and accepted, and then these data sent to a data concentrator devices, then carry out communication and data upload by concentrator and data managing terminal system.And contrary, the order of data managing terminal system also needs by terminal system, and---this annexation of concentrator---collector---electric energy meter sends and transmits.
Therefore, need assembling collector and concentrator devices in addition, for the user of dispersion is installed, the ammeter of its indoor installing is extremely not suitable for the communication scheme re-using RS485 or similar wireless mode, arbitrary grade of intermediate node fault all can cause rear class table meter to carry out digital independent, even and if employ GPRS communication modes, then need to install independent GPRS external module equally, and needing the special SIM card of embedding and battery to use, cost is higher.
And all send data to collector equipment by table meter in current civilian instrument field, the most novel technology is the effective connection using the form of heartbeat frame to maintain a data communication, namely often cross one-period timed sending self-defining inquiry frame, avoid answering equipment to interrupt this because waiting as long for and connect.If it will be understood by those skilled in the art that and send data in this way, a large amount of heartbeat frames will increase communication realize and expense undoubtedly, such as, use GPRS network to carry out communication, then the information that sends needs to pay communication fee to network operator.Meanwhile, this mode causes continuing to increase of the data processing amount of front end processor in AMR system.
Summary of the invention
The present invention is intended to the defect solving prior art existence, designs a kind of intelligent electric energy meter and installs centralized automatic meter-reading (AMR) system of this intelligent electric energy meter, eliminate data acquisition equipment and concentrator that in prior art, AMR system must use.In a preferred embodiment of the invention, using the equipment of intelligent electric energy meter as a server or client class, it directly can be set up with external data collection management terminal and effectively be connected reliably in real time, eliminate the process that data send and sorting processes, avoid data transmission may produced problem and power consumption simultaneously, simultaneously can not because having installed multiple assembly the cost of increase table meter and volume weight.
In another preferred embodiment of the present invention, by the mode of M-BUS bus, multiple utility meter (such as water meter, gas meter or hotlist) is connected to intelligent electric energy meter of the present invention, copies technology in the data connection realizing multiple table.Similarly, by mode setting data collecting device in an effective coverage of bus, obtain the data message of other instrument (comprising electric energy meter), data acquisition of the prior art and sorting function device can be substituted like this, also eliminate the puzzlement of field wiring.
In order to realize above-mentioned purpose of design, technical scheme 1 of the present invention, design a kind of intelligent electric energy meter, be equiped with intercouple processor together and controller wherein, processor is used for receiving and process electric power energy consumption data information, and receiving the data command of controller transmission, simultaneous processor can control again the data message that described controller obtains external source, or external device terminal sends data command.
In order to realize above-mentioned purpose of design, technical scheme 2 of the present invention, is designed a kind of utility meter kilowatt meter reading-out system system, which includes the utility meter of aforesaid intelligent electric energy meter and other types, connected by bus mode.
Technical scheme 1: a kind of intelligent electric energy meter, it is arranged between electric network power line and power grid user load, comprising: signal gathering unit, for accessing electric network power line, obtaining further its electric current and voltage signal and converting electric power digital signal value to; Signal processing unit, for receiving these electric power digital signal values and carrying out calculating and data processing; Communication terminal, for receiving communication request or sending data; Comprise further: control module, obtain the external data information of described intelligent electric energy meter for controlling and send data, described control module is connected with signal processing unit and communication terminal by several interfaces.
Further, in a preferred embodiment of the invention, comprise transformer PT and the power-supply device of the operating voltage for providing intelligent electric energy meter intraware, for line voltage and electric current being converted into the operating voltage of 5V and 15V needed for signal processing unit and control module.
Further, in a preferred embodiment of the invention, set a power control terminal in a control unit, for the communication voltage of communication control end, because the frequency needed for dissimilar communication is different with power consumption, so need to judge communication type in advance by control module, carry out PORT COM setting subsequently, then Communication Control is carried out to communication terminal.
Further, in a preferred embodiment of the invention, comprise the LCD display for showing electric energy consumption consumption and external data information, it and control module are electrically connected to each other.
Further, in a preferred embodiment of the invention, respectively UART interface is set on signal processing unit and control module, for mutual transmission and the reception of data message between the two.In a FLASH unit or RAM of signal processing unit, setting data gathers module and interface class, setting data process module and interface class order in FLASH or RAM of control module.
In a preferred embodiment of the invention, when electric energy meter normally works, signal processing unit sends data acquisition command CHECK_M to control module, or communication interface class order SMS_PROMPT, to control control module, data acquisition is carried out to external unit, such as carry out electric quantity data to other electric energy meters in an effective communication region to gather, make intelligent electric energy meter of the present invention realize the function of a data acquisition equipment with this.
In another preferred embodiment of the present invention, when electric energy meter normally works, control module sends data processing command STAT_M to signal processing unit, makes electric energy meter of the present invention as a data concentrator devices, realize the sorting to electric power energy consumption data and process using this.
Technical scheme 2: a kind of utility meter kilowatt meter reading-out system, it comprises terminal system, and comprises foregoing intelligent electric energy meter, comprises water meter, gas meter and hotlist further.Wherein, described intelligent electric energy meter and water meter, gas meter and hotlist be by M-BUS bus in addition communication be connected, described intelligent electric energy meter is by carrying out communication between wireless network and terminal system.
Further, in a preferred embodiment of the invention, be equiped with for receiving and the response unit of reply data information in described water meter, gas meter and hotlist, described intelligent electric energy meter obtains public commodity consumption data message, in this, as a data acquisition equipment by M-BUS bus to water meter, gas meter and hotlist.
Further, in a preferred embodiment of the invention, described intelligent electric energy meter is that control module by wherein arranging sends data message to water meter, gas meter and hotlist and obtains order.
Further, in a preferred embodiment of the invention, described intelligent electric energy meter is by being connected with WLAN, WIFI, 3G or ADSL wireless mode between its communication terminal with terminal system.
The preferred embodiments of the present invention have abandoned the power information data acquisition equipment and data concentrator equipment that current kilowatt meter reading-out system must use, and are connected in M-BUS bus by different utility meters.1) the public commodity consumption data message of other utility meters is obtained by installing special integrated unit in ammeter, in this, as a data acquisition equipment.2) by the communication module of ammeter inside installing, can make it directly to carry out effective communication with terminal main station system and (such as pass through the networks such as GSM, 3G, WIFI, or the simplest PLC communication), and utilize the sorting function of inside chip realization to data, the function of a data concentrator devices is instead of with this.3) in the order of table meter inner setting, abandon in routine techniques and needed timed sending heartbeat frame to obtain response message, ensure telecommunication network table meter consistently online, and utilize bus power line to power, power consumption is lower, and communication robust, the present invention is simple for structure, reduce cost, there is significant social and economic benefits.
Accompanying drawing explanation
The preferred embodiment of the present invention will embodied in detail below by way of the mode with reference to accompanying drawing, and the identical function components/modules in figure is marked with same-sign, wherein
Fig. 1 is the functional structure schematic diagram of intelligent electric energy meter of the present invention;
Fig. 2 is the structure principle chart of kilowatt meter reading-out system of the present invention;
Fig. 3 is that the data of kilowatt meter reading-out system of the present invention send and the process flow diagram of replying.
Embodiment
Fig. 1 schematically shows the preferred embodiment of intelligent electric energy meter of the present invention, and it is arranged between electric network power line SPL and power grid user load LD, comprising:
Signal gathering unit 10, it is for accessing electric network power line SPL, obtains further its electric current I and voltage U signal and converts electric current I to xand voltage U xdigital signal value;
Signal processing unit 11, be preferably a CPU or dsp chip, it is for receiving these electric power digital signal values I xand U xand carry out calculating and data processing, by formula P=∑ I xu xform tire out multiplied go out the power consumption of power grid user, and show that electric energy consumption consumption and other administration of power networks terminals need the data message obtained by an integrator, such as reactive power, volt-ampere characteristic etc., these need the operation of CPU intraware function to draw;
Communication terminal 12, for receiving communication request or sending data, preferably includes an antenna element and communication chip;
Control module 13, is preferably a system-level MCU chip, obtains, or the data of inter-process are sent to external unit for controlling to the external data information of intelligent electric energy meter of the present invention.Control module 13 is connected with signal processing unit 11 and communication terminal 12 by several interfaces 131.
Further, in a preferred embodiment of the invention, comprise transformer PT and the power supply 15 of the operating voltage for providing intelligent electric energy meter intraware, for line voltage and electric current being converted into the operating voltage of 5V and 15V needed for dsp chip 11 and MCU chip 13.
Further, in a preferred embodiment of the invention, a power control terminal 132 is set in MCU chip 13, for the communication voltage of communication control end 12, because the frequency needed for dissimilar communication is different with power consumption, so need to judge communication type in advance by MCU chip 13, carry out PORT COM setting subsequently, then Communication Control is carried out to communication terminal 12.
Further, in a preferred embodiment of the invention, comprise the display 16 for showing electric energy consumption consumption and external data information, it and MCU chip 13 are electrically connected to each other.
Further, in a preferred embodiment of the invention, respectively UART interface is set on dsp chip 11 and MCU chip 13, for mutual transmission and the reception of data message between the two.In a FLASH unit or RAM of dsp chip 11, setting data gathers module and interface class, setting data process module and interface class in FLASH or RAM of MCU chip 13.
Such as, in a preferred embodiment of the invention, when electric energy meter normally works, dsp chip 11 sends data acquisition command CHECK_M to MCU chip 13, or communication interface class order SMS_PROMPT, carry out data acquisition to control MCU chip 13 pairs of external units, such as, electric quantity data is carried out to other electric energy meters in an effective communication region and gather, make electric energy meter of the present invention realize the function of a data acquisition equipment with this.
Such as, in another preferred embodiment of the present invention, when electric energy meter normally works, MCU chip 13 sends data processing command STAT_M to dsp chip 11, make electric energy meter of the present invention as a data concentrator devices using this, realize the sorting to electric power energy consumption data and process.
Fig. 2 schematically shows a kind of utility meter kilowatt meter reading-out system, and it comprises terminal system 5, and comprises foregoing intelligent electric energy meter 1, comprises water meter 2, gas meter 3 and hotlist 4 further.Wherein, intelligent electric energy meter 1 and water meter 2, gas meter 3 and hotlist 4 be by M-BUS bus form in addition communication be connected, intelligent electric energy meter 1 is by carrying out communication between wireless network and terminal system 5.
Further, in a preferred embodiment of the invention, be equiped with for receiving and the response unit 21,31,41 of reply data information in water meter 2, gas meter 3 and hotlist 4 respectively, intelligent electric energy meter 1 obtains public commodity consumption data message by M-BUS bus to water meter 2, gas meter 3 and hotlist 4, using as a data acquisition equipment.
Further, in a preferred embodiment of the invention, described intelligent electric energy meter 1 is that control module 13 by wherein arranging sends data message to water meter 2, gas meter 3 and hotlist 4 and obtains order.
Further, in a preferred embodiment of the invention, described intelligent electric energy meter 1 is by being connected with WLAN, WIFI, 3G or ADSL wireless mode between its communication terminal 12 with terminal system 5.
Further, in a preferred embodiment of the invention, M-BUS bus adopts wired or wireless mode, a kind of optional architectural can be provided simultaneously, increasing an encryption device at electric energy meter 1 and between water meter 2, gas meter 3 or hotlist 4, obtaining data in order to prevent system peripherals by improper means.
Under any circumstance, the communication baud rate of M-BUS bus is fixed as 2400, is set to even parity check, 8 data bit and 1 position of rest.
Further, in a preferred embodiment of the invention, AES-128 encryption mechanism is adopted or without encryption mechanism in communication process, the byte of encryption is only directed to application layer data content, wherein CRC check byte is not encrypted, if application layer data content is not the integral multiple of 16 bytes, then need to adopt frame byte to fill; Adopt two, CI territory label: the data adopting particular frame byte representation ammeter 1 to other types utility meter 2,3,4 are encryptions.
The equipment that M-BUS bus connects, except electric energy meter 1, all be provided with unique key, obtain key when equipment starts communication, such as, encipher interface class can be set as 0xyyH, wherein 0x represents the interface class order of encryption, and yy represents the data length of encryption, can set a minimum length value, initializing set is 00, needs system to edit out key value according to data header.
In a preferred embodiment of the invention, 1) ammeter 1 sends initialization operation frame to other types utility meter, such as gas meter 3, should unit 31 when receiving these Frames, need reply sheet byte frame E5H, need the communication state of initialization gas meter 3 simultaneously, prepare to start communication;
The Frame that ammeter sends is (wherein startcharacter represents frame head, and stopcharacter represents postamble):
FIELD start character C field A field CS stop character
DATA-HEX 10 40 xx xx 16
2) after the device initialize in bus completes, response unit 31 sends data message current for gas meter 3 to ammeter 1; Ammeter adopts request, and the request of data sent is:
start character C field A field CS stop character
10 5B PAddress School Affairs 16
When gas meter 3 is once receive this claim frame, need to reply, reply content fixes gas consumption+Current Temperatures uncompensated gas consumption+gas meter 3 valve state of 12 byte-header content+current temperature compensation, replys data content:
3) when gas meter 3 receives as above Frame, then replied by response unit 31, need the address data in DATA district being set to gas meter 3 equipment simultaneously, communication is carried out in this address of use and gas meter 3 by ammeter 1 afterwards.
4) valve of gas meter 3 needs to carry out Long-distance Control by the control module (MCU chip) 13 of ammeter 1, terminal system 5 controls ammeter 1 by the mode of transmission information, this information is sent to gas meter 3 by described ammeter 1 again, and to carry out Long-distance Control, ammeter 1 sends Frame and is:
Wherein the XX data setting in DATA district is 00-closing valve; 01-valve opening door; 02-keeps current state.
5) ammeter 1 is after system time changes, and needs to carry out time calibration, after gas meter 3 receives the new clock information of ammeter 1, if the mistiming exceeds 60s, then needs set clock error flag, and using the time of ammeter 1 as the new time.
6) after gas meter 3 is resetted by ammeter 1, then the address distributed before resets, and the key of encryption resets, and reverts to original state, now ammeter 1 transmission control frame (special long frame), and gas meter 3 replys the correct information received.
These are only the preferred embodiment of the present invention, being intended to embody outstanding technique effect of the present invention and advantage, is not the restriction to technical scheme of the present invention.Those skilled in the art will appreciate that all are based on the amendment done by the technology of the present invention content, change or substitute technology feature, all should be covered by the technology category of claims of the present invention opinion.

Claims (5)

1. one kind is applied to the intelligent electric energy meter of M-BUS bus, it is arranged between electric network power line and power grid user load, comprise: signal gathering unit (10), for accessing electric network power line, obtaining further its electric current and voltage signal and converting electric power digital signal value to; Signal processing unit (11), for receiving these electric power digital signal values and carrying out calculating and data processing; Communication terminal (12), for receiving communication request or sending data; It is characterized in that comprising further: control module (13), the external data information of described intelligent electric energy meter is obtained for controlling and sends data, described control module (13) is connected with signal processing unit (11) and communication terminal (12) by several interfaces (131), described signal processing unit (11) controls again the data message that described control module obtains outside M-BUS bus, or the device end externally in M-BUS bus sends data command, wherein:
When this intelligent electric energy meter normally works, signal processing unit (11) sends data acquisition command CHECK_M to control module (13), or communication interface class order SMS_PROMPT, to control control module (13), data acquisition is carried out to the device end in outside M-BUS bus, make this intelligent electric energy meter as a data acquisition equipment using this;
Control module (13) sends data processing command STAT_M to signal processing unit (11), to make this intelligent electric energy meter as a data concentrator devices, realizes the sorting to energy consumption data and process, wherein:
A setting power control terminal (132) in control module (13), for the communication voltage of communication control end (12), frequency needed for dissimilar communication is different with power consumption, communication type is judged in advance by control module (13), carry out PORT COM setting subsequently, then Communication Control is carried out to communication terminal (12).
2. be applied to the intelligent electric energy meter of M-BUS bus as claimed in claim 1, it is characterized in that: comprise the display (16) for showing electric energy consumption consumption and external data information further, it and control module (13) are electrically connected to each other.
3. the utility meter kilowatt meter reading-out system for M-BUS bus communication, it comprises terminal system (5), and comprise intelligent electric energy meter as claimed in claim 1 (1), comprise water meter (2) further, gas meter (3) and hotlist (4), it is characterized in that: described intelligent electric energy meter (1) and water meter (2), gas meter (3) and hotlist (4) be by M-BUS bus in addition communication connect, described intelligent electric energy meter (1) is by carrying out communication between wireless network and terminal system (5), wherein said water meter (2), be equiped with for receiving the response unit (21 with reply data information in gas meter (3) and hotlist (4), 31, 41), described intelligent electric energy meter (1) obtains public commodity consumption data message by M-BUS bus to water meter (2), gas meter (3) and hotlist (4), using as a data acquisition equipment, the means of communication of wherein said utility meter kilowatt meter reading-out system comprise step:
1) intelligent electric energy meter (1) sends initialization operation frame to gas meter (3), when response unit (31) receives these operation frames, reply sheet byte frame E5H, the communication state of initialization gas meter simultaneously (3), prepares to start communication;
2) after the device initialize in described M-BUS bus completes, response unit (31) sends data message current for gas meter (3) to intelligent electric energy meter (1), electric energy meter adopts Frame request method, when gas meter (3) is replied once receive this Frame, reply content fixes gas consumption+Current Temperatures uncompensated gas consumption+gas meter valve state of 12 byte-header content+current temperature compensation;
3) when gas meter (3) receives as above Frame, then replied by response unit (31), need the address data in DATA district being set to gas meter (3) equipment, intelligent electric energy meter (1) will use this address and gas meter (3) to carry out communication afterwards simultaneously;
4) valve of gas meter (3) carries out Long-distance Control by the control module (13) of intelligent electric energy meter (1), a terminal system (5) controls intelligent electric energy meter (1) by the mode of transmission information, this information is sent to gas meter (3) by described intelligent electric energy meter (1) again, to carry out Long-distance Control.
4. as claimed in claim 3 for the utility meter kilowatt meter reading-out system of M-BUS bus communication, it is characterized in that: described intelligent electric energy meter (1) is that the control module (13) by wherein arranging sends data message acquisition order to water meter (2), gas meter (3) and hotlist (4).
5., as claimed in claim 3 for the utility meter kilowatt meter reading-out system of M-BUS bus communication, it is characterized in that: described intelligent electric energy meter (1) is by being connected with WLAN, WIFI, 3G or ADSL wireless mode between its communication terminal (12) with terminal system (5).
CN201210299841.8A 2012-08-22 2012-08-22 A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system Active CN102830281B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201210299841.8A CN102830281B (en) 2012-08-22 2012-08-22 A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system
CN201510028124.5A CN104678167B (en) 2012-08-22 2012-08-22 A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210299841.8A CN102830281B (en) 2012-08-22 2012-08-22 A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201510028124.5A Division CN104678167B (en) 2012-08-22 2012-08-22 A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system

Publications (2)

Publication Number Publication Date
CN102830281A CN102830281A (en) 2012-12-19
CN102830281B true CN102830281B (en) 2016-04-13

Family

ID=47333486

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210299841.8A Active CN102830281B (en) 2012-08-22 2012-08-22 A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system

Country Status (1)

Country Link
CN (1) CN102830281B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103424615A (en) * 2013-08-07 2013-12-04 健雄职业技术学院 Intelligent electric meter based on WIFI (wireless fidelity) and 3G (3rd generation) networks
CN103728903A (en) * 2013-12-26 2014-04-16 华立仪表集团股份有限公司 User terminal
CN107230340A (en) * 2017-04-07 2017-10-03 国网浙江省电力公司电力科学研究院 A kind of electric energy meter copied available for multilist collection and system
CN108694780A (en) * 2018-05-18 2018-10-23 吉林同益光电科技有限公司 A kind of display equipment and display methods

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1304030A (en) * 2000-01-11 2001-07-18 南宁市广通软技术公司 Radio network automatic meter transcription device
CN2854541Y (en) * 2005-08-05 2007-01-03 深圳市艾能迪科技有限公司 Intelligent heat measuring meter
CN201945631U (en) * 2010-07-27 2011-08-24 林琳 Multichannel intelligence ammeter
CN202815088U (en) * 2012-08-22 2013-03-20 华立仪表集团股份有限公司 Smart electric energy meter and meter reading system for public utility instruments

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130021956A1 (en) * 2011-07-20 2013-01-24 Elster Solutions, Llc Synchronized comunication for mesh connected transceiver

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1304030A (en) * 2000-01-11 2001-07-18 南宁市广通软技术公司 Radio network automatic meter transcription device
CN2854541Y (en) * 2005-08-05 2007-01-03 深圳市艾能迪科技有限公司 Intelligent heat measuring meter
CN201945631U (en) * 2010-07-27 2011-08-24 林琳 Multichannel intelligence ammeter
CN202815088U (en) * 2012-08-22 2013-03-20 华立仪表集团股份有限公司 Smart electric energy meter and meter reading system for public utility instruments

Also Published As

Publication number Publication date
CN102830281A (en) 2012-12-19

Similar Documents

Publication Publication Date Title
CN203573481U (en) ZigBee technology-based wireless meter reading system
CN208766825U (en) A kind of LoRa meeting southern network mark standard and carrier wave dual mode communication module
CN201707782U (en) Intelligent meter reading system based on GPRS (General Packet Radio Service)
CN201600774U (en) Double-channel automatic meter reading system
CN102128978A (en) Energy consumption metering system supporting two-way communication
CN206332860U (en) LoRa gateways
CN102830281B (en) A kind of intelligent electric energy meter and utility meter kilowatt meter reading-out system
CN104678167A (en) Intelligent electric energy meter and public utility meter reading system
CN107240242A (en) A kind of wireless kilowatt meter reading-out system and method based on micropower wireless network
CN102571844A (en) Remote program updating device for data acquisition and transmission instrument
CN202677599U (en) Self-adapting watt-hour meter collector
CN207518633U (en) Support the ammeter data acquisition terminal of DLMS/COSEM agreements
CN206331579U (en) LoRa universal nodes
CN202815088U (en) Smart electric energy meter and meter reading system for public utility instruments
CN201965753U (en) Acquisition device
Zhao et al. Data acquisition and transmission system for building energy consumption monitoring
CN203104520U (en) Intelligent main station system
CN204559893U (en) Wireless communication device, table meter inquiry unit and table meter inquiry system
CN105049307A (en) Intelligent electric quantity acquisition system
CN108449434A (en) A kind of building energy consumption data collecting system
CN208126632U (en) A kind of centralized procurement terminal and remotely collect extraction system
CN104581907A (en) Wireless communicator, meter inquiry device and meter inquiry system
CN201886612U (en) Double-connector concentrated data copying and forwarding component for concentrated data copying system
CN203055150U (en) Power consumption information data repeater
CN111650871A (en) Remote communication monitoring system for operation of distributed ground source heat pump machine room

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: HOLLEY Technology Park No. 181 310012 Hangzhou city Zhejiang District of Yuhang province Wuchang Avenue

Applicant after: HOLLEY METERING LIMITED

Address before: HOLLEY Technology Park No. 181 310012 Hangzhou city Zhejiang District of Yuhang province Wuchang Avenue

Applicant before: Holley Metering Ltd.

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210708

Address after: No.258 longfengqiao, Beibei District, Chongqing 400799

Patentee after: CHONGQING HUAHONG INSTRUMENT Co.,Ltd.

Address before: 310012 Huali Science Park, 181 Wuchang Avenue, Yuhang District, Hangzhou City, Zhejiang Province

Patentee before: Holley Technology Co.,Ltd.