CN102277867A - Construction method for collapsible loess foundation - Google Patents

Construction method for collapsible loess foundation Download PDF

Info

Publication number
CN102277867A
CN102277867A CN2011101238422A CN201110123842A CN102277867A CN 102277867 A CN102277867 A CN 102277867A CN 2011101238422 A CN2011101238422 A CN 2011101238422A CN 201110123842 A CN201110123842 A CN 201110123842A CN 102277867 A CN102277867 A CN 102277867A
Authority
CN
China
Prior art keywords
pile
stake
mud jacking
soil
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011101238422A
Other languages
Chinese (zh)
Other versions
CN102277867B (en
Inventor
胡长明
李修波
梅源
林�源
赵浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Architecture and Technology
Original Assignee
Xian University of Architecture and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology filed Critical Xian University of Architecture and Technology
Priority to CN 201110123842 priority Critical patent/CN102277867B/en
Publication of CN102277867A publication Critical patent/CN102277867A/en
Application granted granted Critical
Publication of CN102277867B publication Critical patent/CN102277867B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction method for a collapsible loess foundation. The construction method comprises the following steps of: firstly, performing foundation treatment on a loess field with collapsibility by using a super downhole dynamic consolidation (SDDC) pile; secondly, collecting undisturbed soil on site, normally performing an indoor experiment to measure an inter-pile soil compaction coefficient and an SDDC pile body compaction coefficient, evaluating the collapsibility, and if any one of the three indexes cannot meet a design requirement, performing pile compensation construction on the SDDC pile until the design requirement is met; and finally, pouring the pile and mudjacking. The method has the advantages of economy, environment friendliness, high treatment depth, good treatment effect, large bearing potential, high complicated load resistance and the like. By application of the method, various side effects caused by the collapsibility of the deep collapsible loess field can be eliminated, and requirements of upper-part high rise buildings on the bearing capability and settlement of the foundation can be met.

Description

A kind of job practices of collapsible loess foundation
Technical field
The present invention relates to the building lot process field, be specially the job practices of a kind of SDDC of employing stake and filling pile ' s after grouting technical tie-up Combined Treatment loess foundation settlement by soaking.
Background technology
In the northwest, North China regular meeting runs into the Loess Subgrade problem; generally including the low humidity collapsible loess is main purpose to eliminate or to reduce saturated yielding distortion harm; need improve the ground of bearing capacity of foundation soil simultaneously handles problems; and weak loess (the especially saturated loess of high humility; how to be transformed saturation ratio S by the full water of collapsible loess r﹥ 80%) handle problems to improve bearing capacity of foundation soil, to reduce harmful compressive strain the ground that is purpose.Because the many and general cohesive soil of the latter's engineering properties is similar, mainly should consider the compressive strain of ground, can treat by weak cohesive soil, the former should consider mainly that then ground is out of shape by the saturated yielding after the water-soaked.
The processing method of traditional collapsible loess foundation mainly contains following method:
(1) bed course, the compacting of (2) weight top layer, (3) are strong to be rammed, (4) compaction pile, (5) chemical consolidation, (6) pre-immersion, (7) pile foundation.
More than in the processing method to collapsible loess foundation, method (1) and method (2) are handled depth as shallow, should not be used for the deep place of collapsible loess; Method (3) is big to the negative effect of environment, should not reach the urban district around existing building and use; The used filler of method (4) is single, and undesirable to the compacted effect of inter-pile soil, elimination ground settlement by soaking that only can be limited; Method (5) disposal cost costliness generally will not adopt; The place peripheral ground sinks to ftractureing during method (6) immersion, and causes " metalling run out " Durchgangshohle easily, influences the safety of surrounding buildings thing; Method (7) is handled deep Collapsible Loess District, and especially in the self weight collapse loess place, for overcoming the adverse effect that the negative skin friction of pile is brought, required stake is longer, less economical.
More than in the traditional treatment method at collapsible loess foundation, especially to the deep place of self weight collapse loess, still do not have cost-effective method for processing foundation and can satisfy the requirement of high-rise building (towering structure) bearing capacity of foundation soil and settling amount, therefore, the processing method of seeking a kind of new collapsible loess foundation is the focus that those skilled in the art pay close attention to.
Summary of the invention
At shortcoming or the deficiency that above-mentioned prior art exists, the object of the present invention is to provide a kind of SDDC of employing stake and filling pile ' s after grouting technical tie-up to handle the job practices of collapsible loess foundation.
In order to realize above-mentioned task, the present invention is achieved by following technical scheme:
A kind of job practices of collapsible loess foundation is characterized in that, this method at first adopts SDDC stake method that ground is carried out in the loess place with settlement by soaking and handles; Then, gather undisturbed soil at the scene, carry out laboratory test by standard, record the compacted coefficient of inter-pile soil, SDDC stake pile body coefficient of consolidation, and carry out the settlement by soaking evaluation, if having when not satisfying design specifications in three indexs, then carry out the piling construction of SDDC stake, until meeting design requirement; Carry out the filling pile ' s after grouting construction then.
The step of its concrete construction is as follows:
Step 1 is verified geologic information, in conjunction with design parameters, selects suitable drilling construction facility;
Step 2, obstruction is on the ground removed in smooth place, and undreground works and pipeline in the scope of mark disposal field keep levelling of the land;
Step 3 is measured unwrapping wire, makes control axis, piling site boundary and sign;
Step 4, the construction equipment of selecting in the applying step one, impact holing.The drilling construction facility generally adopt the stake machine of band pile frame, and jump bit is selected the overweight hammer of olive shape for use.Pile-forming machine perching, align, after the leveling, the lifting weight arrives design height and (can be promoted to generally that 10m ~ 18m), the overweight hammer of olive shape is automatically-unhooked, pour in the soil by the kinetic energy of the overweight hammer of olive shape, carry out aforesaid operations repeatedly, reach designing requirement until hole depth;
Step 5, the layering filler, ram pile:
To insert a hole by the quantitative filler layering that design is mixed and stirred with standard hopper or dumper, the overweight hammer of the olive shape when using pore-forming then is with filler compaction in layers one by one, until becoming the SDDC stake.And each hole should be rammed and be filled to more than the design elevation of top 0.5m at least; Wherein, the sequence of construction of pore-forming and filling tamped is carried out at interval;
Step 6, construction machinery move to next stake position, and repeating step four, step 5 are all finished until the SDDC stake;
Step 7, the pile body filler sample and the inter-pile soil sample of SDDC stake are gathered in the excavation prospect pit, do indoor conventional soil test, and specific requirement is as follows:
(1) it is some to get the pile body filler sample of inter-pile soil and SDDC stake by standard, does indoor conventional soil test, and the compacted coefficient that its result should satisfy inter-pile soil is not less than 0.93, and the coefficient of consolidation of the pile body of SDDC stake is not less than 0.97;
(2) settlement by soaking evaluation.For further determining the elimination degree of settlement by soaking, the not disturbed soil sample of Three S's DDC stake centre of form place inter-pile soil is gathered in ground on the scene excavation prospect pit, carry out indoor conventional soil test,, judge whether the elimination degree of settlement by soaking meets design requirement according to laboratory test results.
If above each index meets design requirement, then carry out the construction of filling pile ' s after grouting; Otherwise carry out the piling construction of SDDC stake;
Step 8 before carrying out filling pile construction, adopts the thick C15 concrete of 100mm that cure process is carried out on the ground of adopting the SDDC stake and handling;
Step 9 adopts total powerstation to utilize the crossing point of axes of appointment to do the control point, and to the setting-out of grout pile position, location, the stake position direction range error of castinplace pile is not less than 5mm, and with spike mark is one by one carried out in the stake position;
Step 10 is made reinforcing cage, checks and accepts stand-by.Adopt the pre-pipe laying mud jacking of pile body, promptly by the mud jacking degree of depth requirement of design, madjack pipe is fixed on the reinforcing cage, squeezing unit is transferred with reinforcing cage.Adopt screwed connection to avoid welding between the madjack pipe;
Step 11, the pore-forming facility are in place, and keep boring machine steady, not run-off the straight, displacement;
Step 12 is adjusted boring machine, to good grout pile position, starts boring machine with the contraposition circle, reach controlling depth after, carry out hole operation clearly;
Step 13, mobile pore-forming facility are to next grout pile position, and repeating step 11 and step 12 are until the pore-forming operation of finishing all castinplace piles;
Step 14 is transferred the reinforcing bar cage hoisting of making in advance that installs Grouting Pipe, ties up mortar cushion block or plastic clip before reinforcing cage is put into, and during install reinforcing cage, the mating holes position, hangs and directly holds up surely, slowly sinks, and avoids colliding hole wall; When reinforcing cage is put into design attitude, should fix immediately; Weld junction between two sections reinforcing cages, to guarantee the correct position of reinforcing cage, guarantees that protective layer thickness meets the requirements;
Step 15, madjack pipe tries the water.Should do the test of trying the water when every joint madjack pipe is transferred with reinforcing cage,, should check then whether madjack pipe has sand holes, screwed connection whether to seal if find that water column descends or water column disappears.
Reinforcing cage is placed and is carried out in the metapore that finishes needing once more the water surface in the inspection eye after the second time, finished in clear hole, and it is suitable for reading that madjack pipe is sealed with plug in no abnormal back;
Step 10 six, the concreting castinplace pile.With putting a slide tube concreting castinplace pile, before putting the slide tube, check and measure the thickness of loosened soil in the boring once more, carry out when reaching designing requirement, concreting is adopted and is carried out continuously, when concreting is pushed up to the stake of castinplace pile, the stake top design elevation that should suitably surpass castinplace pile is to guarantee that after cutting laitance the stake top mark height of castinplace pile adheres to specification.Simultaneously, make the test block of same match ratio, per tour must not be less than one group;
Step 10 seven, packer permeability test, packer permeability test carry out in 24 hours behind pile.Must carry out packer permeability test before the formal mud jacking, to check the unimpeded situation of pipeline and one way valve.
If during the situation that in stake side or stake end reaming takes place, collapse hole or fullness coefficient is bigger, need pay special attention to carry out in advance packer permeability test, carry out to guarantee to wash open thicker concrete coating in intact 5 hours in concreting.
Break through force value and the unimpeded situation of pipeline by special messenger's record during test;
Step 10 eight, repeating step 14, step 15, step 10 six, step 10 seven are finished the pile work of each castinplace pile, are the ready work of back mud jacking construction simultaneously;
Step 10 nine, back mud jacking construction.Take the mode of secondary grouting,, obtain better effect to give full play to the effect of slip casting.
(1) just annotate: the concrete curing of castinplace pile pile body began mud jacking after 3~5 days, at the bottom of will being injected into by high-pressure pump and pre-buried madjack pipe by the good cement paste of design configurations or go in the stake side soil layer, if compound mud jacking then generally carries out a side pressure slurry earlier, carry out pile base grouting after 12 hours again.Pressure is little when just annotating, slurries by rare to thick.To keep a close eye on the variation of grouting pressure, grouting amount when just annotating, and note slip casting rhythm.Should be provided with during pile grouting dial gage detect stake on the amount of lifting, avoid excessive.
(2) secondary grouting: the best Grouting Pipe with slip casting for the first time of the Grouting Pipe of slip casting for the second time is symmetrically distributed.Grouting amount is generally primary 1 ∕, 3~1 ∕ 4 for the second time, and water/binder ratio can suitably improve.
(3) mud jacking of same pile order: earlier last side pipe is carried out mud jacking, descend side pipe then, hold the pipe mud jacking at last; The mud jacking order of same cushion cap stake: stake rear center stake earlier.
Step 2 ten stops mud jacking.The total control principle that stops mud jacking is based on the mud jacking amount, and pressure is controlled to be auxilliary.But the mud jacking parameter also should be according to the geological conditions choose reasonable, if the stake end during for closely knit gravel boulder bed, should be the major control index with the mud jacking amount; The stake side should be the major control index with mud jacking pressure then when being closely knit loess formation.
After mud jacking finishes immediately to the madjack pipe plug of screwing on, in order to avoid reduce grouting result because of overfall.
Step 2 11, repeating step 19, step 2 ten are finished the construction working of each filling pile ' s after grouting continuously.
The high-rise building (towering structure) that adopts method of the present invention can effectively solve on the deep collapsible loess place requires harsh problem to aspects such as bearing capacity of foundation soil, settling amount, ambient influnences.Can effectively to shorten stake after this method long because of adopting again, so the economic benefit that it brought is more remarkable than additive method.
Description of drawings
Fig. 1 is a SDDC stake layout schematic diagram;
Fig. 2 is a ground processing profiles schematic diagram;
Fig. 3 is that madjack pipe is buried schematic diagram underground.
Mark among the figure is represented respectively: 1, inter-pile soil, 2, the SDDC stake, 3, the ground bottom do not have the natural soil layer of settlement by soaking ,4, castinplace pile, 5, Grouting Pipe.
The present invention is described in detail with embodiment with reference to the accompanying drawings.
The specific embodiment
(the Super Down-hole Dynamic Compaction of the super dynamic compaction of deep layer in the hole, be called for short SDDC), it is to pass through impact holing with kinetic energy, over pressure, the strong compacted mechanism of action, from deep to shallow, successively ram pile by force, kinetic energy at over pressure makes the inter-pile soil side produce very big dynamic passive earth pressure in the rammer process by force, forces the downward and peripheral densification of filler to be extruded, and the inter-pile soil mechanics index of physics is improved fully.Can be widely used in assorted filling out, the processing of all kinds of special foundations such as liquefaction, saturated yielding weakness, expansion.This method applicability is strong, handle that the degree of depth is big, treatment effect good, environmental protection, to advantages such as ambient influnence are little, good in economic efficiency, be familiar with by people gradually in recent years, and treatment effect is good.The present invention introduces the super dynamic compaction of deep layer in the hole in the pile foundation method, and the loess foundation settlement by soaking is handled, and through facts have proved, has obtained satisfied effect.
King-pile of the present invention basis pattern is looked specific requirement, can take stake-patten, stake-beam basis, stake-foundation of wall, stake-raft foundation, stake-box foundation etc., mode such as the corresponding mode of laying out pile can adopt under the post and lay out pile, lay out pile under the wall, full hall lays out pile, local full hall lays out pile.
Referring to Fig. 1, Fig. 2 and Fig. 3, the job practices of collapsible loess foundation of the present invention, the settlement by soaking of employing SDDC stake and castinplace pile (is example with the bored pile) post-grouting technology Combined Treatment collapsible loess foundation specifically comprises the following steps:
One, the construction of SDDC stake 2.
Step 1 is verified geologic information, in conjunction with design parameters, selects suitable drilling construction facility;
Step 2, obstruction is on the ground removed in smooth place, and undreground works and pipeline in the scope of mark disposal field keep levelling of the land;
Step 3 is measured unwrapping wire, makes control axis, piling site boundary and sign;
Step 4, the construction equipment of selecting in the applying step one, impact holing.The drilling construction facility generally adopt the stake machine of band pile frame, and jump bit is selected the overweight hammer of olive shape for use.Pile-forming machine perching, align, after the leveling, the lifting weight arrives design height and (can be promoted to generally that 10m ~ 18m), the overweight hammer of olive shape is automatically-unhooked, pour in the soil by the kinetic energy of the overweight hammer of olive shape, carry out aforesaid operations repeatedly, reach designing requirement until hole depth;
Step 5, the layering filler is rammed pile.To insert a hole by quantitative filler (can not select bulk stiff materials such as fragment of brick, rubble, the concrete block for use) layering that design is mixed and stirred with standard hopper or dumper as filler, the overweight hammer of olive shape when using pore-forming then is with filler compaction in layers one by one, until becoming SDDC stake 2.Each hole should be rammed and be filled to more than the design elevation of top 0.5m at least; Wherein, the sequence of construction of pore-forming and filling tamped is carried out at interval;
Step 6, the construction machinery displacement.Repeating step four, step 5 are all finished until SDDC stake 2;
Step 7, excavation prospect pit are gathered the pile body filler sample of SDDC stake 2 and the soil body that inter-pile soil 1(top has settlement by soaking) sample, do indoor conventional soil test, specific requirement is as follows:
(1) get inter-pile soil 1 by standard and SDDC stake 2 pile body filler samples are some, do indoor conventional soil test, the compacted coefficient that its result should satisfy inter-pile soil 1 is not less than 0.93, and the coefficient of consolidation of the pile body of SDDC stake 2 is not less than 0.97;
(2) settlement by soaking evaluation.For further determining the elimination degree of settlement by soaking, the not disturbed soil sample of Three S's DDC stake 2 centre of form place inter-pile soils 1 is gathered in ground on the scene excavation prospect pit, carry out indoor conventional soil test,, judge whether the elimination degree of settlement by soaking meets design requirement according to laboratory test results.
If above each index meets design requirement, then carry out the construction of drill-pouring post-pressure grouting; Otherwise carry out the piling construction of SDDC stake 2;
Step 8 before carrying out bored pile 4 construction, adopts the thick C15 concrete of 100mm that cure process is carried out on the ground of adopting SDDC stake 2 and handling;
Two, bored pile 4 back mud jacking constructions
Step 9 adopts total powerstation to utilize the crossing point of axes of appointment to do the control point, and to 4 position setting-outs of bored pile, location, the stake position direction range error of bored pile 4 is not less than 5mm, and with spike mark is one by one carried out in the stake position;
Step 10, reinforcing cage are made, are checked and accepted:
Adopt the pre-pipe laying mud jacking of pile body, promptly by the mud jacking degree of depth requirement of design, Grouting Pipe 5 is fixed on the reinforcing cage, squeezing unit is transferred with reinforcing cage.Adopt screwed connection to avoid welding between the Grouting Pipe 5;
Step 11, auger is in place, and keeps auger steady, not run-off the straight, displacement;
Step 12, straightening boring frame tappet, starts auger and creeps into, is unearthed 4 positions of good bored pile with the contraposition circle, reach controlling depth after, after clear soil is dallied in the bottom, hole, stop to bore, carry brill; The hole quality safeguard measure is:
1) reaches loosened soil thickness deeply with sounding line/hammer gaging hole and should not surpass 100mm;
2) in the retaining hole height of mud liquid level prevent shrinkage cavity, the hole of collapsing;
Step 13, mobile auger is to 4 positions of next bored pile, and repeating step 11 and step 12 are until the pore-forming operation of finishing all bored piles 4;
Step 14 is transferred the reinforcing bar cage hoisting of making in advance that installs Grouting Pipe 5, ties up mortar cushion block or plastic clip before reinforcing cage is put into, and during install reinforcing cage, the mating holes position, hangs and directly holds up surely, slowly sinks, and avoids colliding hole wall; When reinforcing cage is put into design attitude, should fix immediately; Weld junction between two sections reinforcing cages, to guarantee the correct position of reinforcing cage, guarantees that protective layer thickness meets the requirements;
Step 15, Grouting Pipe 5 is tried the water.Should do the test of trying the water when every joint madjack pipe 5 is transferred with reinforcing cage,, should check then whether madjack pipe 5 has sand holes, screwed connection whether to seal if find that water column descends or water column disappears.
Reinforcing cage is placed and to be carried out in the metapore that finishes needing once more the water surface in the inspection eye after second time, finished in clear hole, and it is suitable for reading to seal Grouting Pipe 5 with plug after no abnormal;
Step 10 six, concreting.With putting a slide tube concreting, before putting the slide tube, check and measure the thickness of loosened soil in the boring once more, carry out when reaching designing requirement, concreting is adopted and is carried out continuously, when concreting is pushed up to the stake of bored pile 4, the stake top design elevation that should suitably surpass bored pile 4 is to guarantee that after cutting laitance the stake top mark height of bored pile 4 adheres to specification.Simultaneously, make the test block of same match ratio, per tour must not be less than one group;
Step 10 seven, packer permeability test: packer permeability test carries out in 24 hours behind pile.Must carry out packer permeability test before the formal mud jacking, to check the unimpeded situation of pipeline and one way valve.
If during the situation that in stake side or stake end reaming takes place, collapse hole or fullness coefficient is bigger, need pay special attention to carry out in advance packer permeability test, carry out to guarantee to wash open thicker concrete coating in intact 5 hours in concreting.
Break through force value and the unimpeded situation of pipeline by special messenger's record during test;
Step 10 eight, repeating step 14, step 15, step 10 six, step 10 seven are finished the pile work of each bored pile 4, are the ready work of back mud jacking construction simultaneously;
Step 10 nine, back mud jacking construction.Take the mode of secondary grouting,, obtain better effect to give full play to the effect of slip casting.
(1) just annotate: bored pile 4 pile concrete maintenances began mud jacking after 3~5 days, at the bottom of will being injected into by high-pressure pump and pre-buried madjack pipe 5 by the good cement paste of design configurations or go in the stake side soil layer, if compound mud jacking, then generally carry out a side pressure slurry earlier, carry out pile base grouting after 12 hours again.Pressure is little when just annotating, slurries by rare to thick.To keep a close eye on the variation of grouting pressure, grouting amount when just annotating, and note slip casting rhythm.Should be provided with during pile grouting dial gage detect stake on the amount of lifting, avoid excessive.
(2) secondary grouting: the Grouting Pipe 5 best Grouting Pipe 5 with slip casting for the first time of slip casting for the second time are symmetrically distributed.Grouting amount is generally primary 1 ∕, 3~1 ∕ 4 for the second time, and water/binder ratio can suitably improve.
(3) mud jacking of same pile order: earlier last side pipe is carried out mud jacking, descend side pipe then, hold the pipe mud jacking at last; The mud jacking order of same cushion cap stake: stake rear center stake earlier.
Step 2 ten stops mud jacking.The total control principle that stops mud jacking is based on the mud jacking amount, and pressure is controlled to be auxilliary.But the mud jacking parameter also should be according to the geological conditions choose reasonable, if the stake end during for closely knit gravel boulder bed, should be the major control index with the mud jacking amount; When being closely knit loess formation because of the stake side should be the major control index with mud jacking pressure then.
After finishing, gives by mud jacking madjack pipe 5 plug of screwing on immediately, in order to avoid reduce grouting result because of overfall.
Step 2 11, repeating step 19, step 2 ten are finished each bored pile 4 construction working of mud jacking afterwards continuously.
Winter, Pluvial construction precautions:
(1) teletostage is built rod when coagulating soil when temperature is lower than below 0 ℃, should take the heat tracing measure.When building, concrete temperature is carried out by winter constructure scheme regulation.Before reaching design strength 50%, the stake top must not endure cold; When temperature should be taked the slow setting measure to concrete during still in 30 ℃ as the case may be.
(2) the Pluvial strictness is adhered to causing the hole of collapsing with the regulation of boring with concreting in case pour water behind the pore-forming.The on-the-spot various measures that draining must be arranged prevent that the surface water from flowing in the groove, causes slope collapse or basic native depression, boring machine inclination etc.
In addition the Pluvial when the place has ponding or soil moisture in layer higher, it is serious that impact holing is inhaled the hammer phenomenon, can adopt rig boring this moment, but must suitably increase the number of times of ramming to filler in the hole;
When adopting method of the present invention to construct, the filler of SDDC stake 2 is not selected fragment of brick, rubble, concrete block or other bulk stiff materials for use.
During the bored concrete pile foundation design, ground after SDDC stake 2 processing is considered as composite foundation, and a position of not considering SDDC stake 2 arranges that treatment region soil body mechanics index of physics adopts average, and the ground bottom does not have the mechanics index of physics employing geological mapping of the natural soil layer 3 of settlement by soaking the data that provide are provided.
With way of example the present invention is specified above, but the invention is not restricted to above-mentioned specific embodiment.
Be that principle of the present invention is described below.
The super dynamic compaction of deep layer (SDDC) is in pore forming process in the hole, force in the hole undisturbed soil side direction to be extruded, the soil body in the Zhou Yiding scope is squeezed, disturbance and reinventing, when filler, force in the hole filler lateral compression hole wall once more, the all soil bodys in larger scope of stake are squeezed once more, disturbance and reinventing, strong huge tamping energy volume production living ripple and the dynamic stress of ramming acts on repeatedly, force soil skeleton to produce plastic strain, thereby improve the compactness and the shear strength of soil, improve the deformation characteristic of soil, the beading pile body and inter-pile soil interlock mutually that form, the bearing capacity height, the strong compacted effect during because of pore-forming, it is more effective than additive method that this method is eliminated collapsibility of loess effect aspect.Its reinforcement mechanism mainly contains following 4 points:
(1) in pore-forming and the formation of pile to the compacted effect of the power on former;
(2) pile body filling metathesis (comprise pile body and clamp-on the aggregate of inter-pile soil);
When (3) adopting dirt, the aquation of quicklime and gelatification (chemical replacement).In Collapsible Loess District, when improving soil body physical mechanics proterties, can effectively eliminate settlement by soaking by the ground that the SDDC method is handled.Then, on the SDDC pile composite foundation that forms, adopt the design and construction of the castinplace pile of post-grouting technology associating.
Adopt the castinplace pile reinforcement mechanism of compound mud jacking technology to mainly contain in the back mud jacking work progress:
(1) infiltration consolidation;
(2) compacted packing action;
(3) splitting reinforced action;
(4) expand end hole enlargement effect.
Under above-mentioned mechanism effect, the physical mechanics proterties of foundation soil body is further improved, the settlement by soaking of slip casting place loess is further eliminated, the bearing capacity of castinplace pile is largely increased, and the pile foundation settling amount significantly reduces under the identical load.
In sum, adopt the job practices of loess foundation settlement by soaking of the present invention to compare with traditional method, its novelty contribution is:
(1) under effect aspect above-mentioned two, the settlement by soaking of loess foundation is eliminated, and then the pile-side negative friction problem that is caused because of the loess foundation settlement by soaking solved, so pile foundation can design by the conventional pile foundation of not considering the negative skin friction of pile;
(2) because castinplace pile has adopted SDDC stake and filling pile ' s after grouting technical tie-up Combined Treatment, so the pile foundation settling amount significantly reduces under the significantly raising of pile capacity, identical load action.Therefore, satisfy can effectively shorten under the prerequisite of code requirement the stake long, significantly increase economic efficiency.To have a bearing capacity big and resist the strong characteristics of complicated weight bearing power because of pile foundation again, carry out appropriate design according to engineering characteristic after, can satisfy top high-rise building (towering structure) to the stability on basis and the requirement of differential subsidence.

Claims (3)

1. the job practices of a collapsible loess foundation is characterized in that, this method at first adopts SDDC stake method that ground is carried out in the loess place with settlement by soaking and handles; Then, gather undisturbed soil at the scene, carry out laboratory test by standard, record compacted coefficient of inter-pile soil and SDDC stake pile body coefficient of consolidation, and carry out the settlement by soaking evaluation, if having when not satisfying design specifications in three indexs, then carry out the piling construction of SDDC stake, until meeting design requirement; Carry out the construction of filling pile ' s after grouting then.
2. the method for claim 1 is characterized in that, concrete job practices may further comprise the steps:
Step 1 is verified geologic information, in conjunction with design parameters, selects suitable drilling construction facility;
Step 2, obstruction is on the ground removed in smooth place, and undreground works and pipeline in the scope of mark disposal field keep levelling of the land;
Step 3 is measured unwrapping wire, makes control axis, piling site boundary and sign;
Step 4, the construction equipment of selecting in the applying step one, impact holing, drilling construction facility generally adopt the stake machine of band pile frame, and jump bit is selected the overweight hammer of olive shape for use, pile-forming machine perching, align, after the leveling, the lifting weight arrives design height, and the overweight hammer of olive shape is automatically-unhooked, pours in the soil by the kinetic energy of the overweight hammer of olive shape, carry out aforesaid operations repeatedly, reach designing requirement until hole depth;
Step 5, the layering filler, ram pile:
To insert a hole by the quantitative filler layering that design is mixed and stirred with standard hopper or dumper, the overweight hammer of the olive shape when using pore-forming then is with filler compaction in layers one by one, until pile; And each hole should be rammed and be filled to more than the design elevation of top 0.5m at least; Wherein, the sequence of construction of pore-forming and filling tamped is carried out at interval;
Step 6, construction machinery move to next stake position, and repeating step four, step 5 are all finished until stake;
Step 7, the pile body filler sample and the inter-pile soil sample of excavation prospect pit collecting pile are done indoor conventional soil test, and specific requirement is as follows:
(1) it is some to get the pile body filler sample of inter-pile soil and stake by standard, does indoor conventional soil test, and the compacted coefficient that its result should satisfy inter-pile soil is not less than 0.93, and the coefficient of consolidation of pile body of stake is not less than 0.97;
(2) settlement by soaking evaluation: for further determining the elimination degree of settlement by soaking, the not disturbed soil sample of three stake centre of form place inter-pile soils is gathered in ground on the scene excavation prospect pit, carry out indoor conventional soil test,, judge whether the elimination degree of settlement by soaking meets design requirement according to laboratory test results;
If above each index meets design requirement, then carry out the construction of filling pile ' s after grouting; Otherwise carry out the piling construction of stake;
Step 8 before carrying out filling pile construction, adopts the thick C15 concrete of 100mm that cure process is carried out on the ground of adopting pile and handling;
Step 9 adopts total powerstation to utilize the crossing point of axes of appointment to do the control point, and to the setting-out of grout pile position, location, the stake position direction range error of castinplace pile is not less than 5mm, and with spike mark is one by one carried out in the stake position;
Step 10 adopts the pre-pipe laying mud jacking of pile body, promptly by the mud jacking degree of depth requirement of design, madjack pipe is fixed on the reinforcing cage, and squeezing unit is transferred with reinforcing cage, adopts screwed connection to avoid welding between the madjack pipe;
Step 11, the pore-forming facility are in place, and keep boring machine steady, not run-off the straight, displacement;
Step 12 is adjusted boring machine, to good grout pile position, starts boring machine with the contraposition circle, reach controlling depth after, carry out hole operation clearly;
Step 13, mobile pore-forming facility are to next castinplace pile position, and repeating step 11 and step 12 are until the pore-forming operation of finishing all castinplace piles;
Step 14 is transferred the reinforcing bar cage hoisting of making in advance that installs Grouting Pipe, ties up mortar cushion block or plastic clip before reinforcing cage is put into, and during install reinforcing cage, the mating holes position, hangs and directly holds up surely, slowly sinks, and avoids colliding hole wall; When reinforcing cage is put into design attitude, should fix immediately; Weld junction between two sections reinforcing cages, to guarantee the correct position of reinforcing cage, guarantees that protective layer thickness meets the requirements;
Step 15, madjack pipe tries the water: should do the test of trying the water when every joint madjack pipe is transferred with reinforcing cage, if find that water column descends or water column disappears, should check then whether madjack pipe has sand holes, screwed connection whether to seal;
Reinforcing cage is placed and is carried out in the metapore that finishes needing once more the water surface in the inspection eye after the second time, finished in clear hole, and it is suitable for reading that madjack pipe is sealed with plug in no abnormal back;
Step 10 six, concreting: with putting a slide tube concreting, before putting the slide tube, check and measure the thickness of loosened soil in the boring once more, carry out when reaching designing requirement, concreting is adopted and is carried out continuously, when concreting is pushed up to the stake of castinplace pile, should suitably surpass the stake top design elevation of castinplace pile, to guarantee that after cutting laitance the stake top mark height of castinplace pile adheres to specification; Simultaneously, make the test block of same match ratio, per tour must not be less than one group;
Step 10 seven, packer permeability test: packer permeability test carries out in 24 hours behind pile, must carry out packer permeability test before the formal mud jacking, to check the unimpeded situation of pipeline and one way valve, if during the situation that in stake side or stake end reaming takes place, collapse hole or fullness coefficient is bigger, need pay special attention to carry out in advance packer permeability test, carry out to guarantee to wash open thicker concrete coating in intact 5 hours in concreting;
Break through force value and the unimpeded situation of pipeline by special messenger's record during test;
Step 10 eight, repeating step 14, step 15, step 10 six, step 10 seven are finished the pile work of each castinplace pile, are the ready work of back mud jacking construction simultaneously;
Step 10 nine, back mud jacking construction: take the mode of secondary grouting, comprising:
(1) just annotate: the concrete curing of castinplace pile pile body began mud jacking after 3~5 days, at the bottom of will being injected into by high-pressure pump and pre-buried madjack pipe by the good cement paste of design configurations or go in the stake side soil layer, if adopt compound mud jacking, then carry out a side pressure slurry earlier, carry out pile base grouting after 12 hours again; Pressure is little when just annotating, slurries by rare to thick; To keep a close eye on the variation of grouting pressure, grouting amount when just annotating, and note slip casting rhythm, should be provided with during pile grouting dial gage detect stake on the amount of lifting, avoid excessive;
(2) secondary grouting: the Grouting Pipe of slip casting for the second time is symmetrically distributed with the Grouting Pipe of slip casting for the first time, and grouting amount is generally primary 1 ∕, 3~1 ∕ 4 for the second time, and water/binder ratio suitably improves;
(3) mud jacking of same pile order: earlier last side pipe is carried out mud jacking, descend side pipe then, hold the pipe mud jacking at last; The mud jacking order of same cushion cap stake: stake rear center stake earlier;
Step 2 ten stops mud jacking: the total control principle that stops mud jacking is that pressure is controlled to be auxilliary based on the mud jacking amount, but the mud jacking parameter is according to the geological conditions choose reasonable, if the stake end during for closely knit gravel boulder bed, should be the major control index with the mud jacking amount; The stake side should be the major control index with mud jacking pressure then when being closely knit loess formation;
After mud jacking finishes immediately to the madjack pipe plug of screwing on, in order to avoid reduce squeezing quality because of overfall;
Step 2 11, repeating step 19, step 2 ten are finished the construction working of each filling pile ' s after grouting continuously.
3. the method for claim 1 is characterized in that, the filler of described pile is not selected fragment of brick, rubble, concrete block or other bulk stiff materials for use.
CN 201110123842 2011-05-13 2011-05-13 Construction method for collapsible loess foundation Expired - Fee Related CN102277867B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110123842 CN102277867B (en) 2011-05-13 2011-05-13 Construction method for collapsible loess foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110123842 CN102277867B (en) 2011-05-13 2011-05-13 Construction method for collapsible loess foundation

Publications (2)

Publication Number Publication Date
CN102277867A true CN102277867A (en) 2011-12-14
CN102277867B CN102277867B (en) 2013-10-09

Family

ID=45103570

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110123842 Expired - Fee Related CN102277867B (en) 2011-05-13 2011-05-13 Construction method for collapsible loess foundation

Country Status (1)

Country Link
CN (1) CN102277867B (en)

Cited By (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535315A (en) * 2012-01-10 2012-07-04 江苏建筑职业技术学院 Treatment method for suspending concrete pavement slab
CN103790148A (en) * 2014-01-07 2014-05-14 西安科技大学 Combined treatment construction method for collapsible loess foundation
CN104727295A (en) * 2015-03-26 2015-06-24 中化岩土工程股份有限公司 Pre-hole-forming padding substitution hammer flattener dynamic compaction method
CN105954499A (en) * 2016-06-26 2016-09-21 兰州理工大学 Method and device for evaluating collapsible site after carrying out fracturing grouting reinforcement on collapsible loess site
CN106989993A (en) * 2017-05-22 2017-07-28 中铁西北科学研究院有限公司 A kind of coefficient of collapsibility of loess layering in-situ testing device and method of testing
CN107059912A (en) * 2017-03-20 2017-08-18 中国十七冶集团有限公司 A kind of people's goods elevator foundation slip casting reinforcing and processing method for being seated soft soil horizon
CN107974888A (en) * 2017-12-01 2018-05-01 江苏中路工程技术研究院有限公司 Construction method of the strength concrete pile as roadbed filling
CN110106882A (en) * 2019-04-28 2019-08-09 云南建投第一勘察设计有限公司 A kind of gas lift reverse circulation device for cast-in-situ bored pile
CN112227356A (en) * 2019-07-15 2021-01-15 河北建设勘察研究院有限公司 Gravel grouting steel pipe pile and preparation method thereof
US11079725B2 (en) 2019-04-10 2021-08-03 Deere & Company Machine control using real-time model
CN113494134A (en) * 2021-07-05 2021-10-12 浙江东南网架股份有限公司 Inverse installation method of variable cross-section steel pipe forked support column
US11178818B2 (en) 2018-10-26 2021-11-23 Deere & Company Harvesting machine control system with fill level processing based on yield data
CN113931164A (en) * 2021-11-01 2022-01-14 西宁碧胜房地产开发有限公司 Club-footed pile construction method for pre-soaking and compacting collapsible loess
US11234366B2 (en) 2019-04-10 2022-02-01 Deere & Company Image selection for machine control
CN114016489A (en) * 2021-11-24 2022-02-08 华侨大学 Datum point fixing device for settlement monitoring
US11240961B2 (en) 2018-10-26 2022-02-08 Deere & Company Controlling a harvesting machine based on a geo-spatial representation indicating where the harvesting machine is likely to reach capacity
US20220110251A1 (en) 2020-10-09 2022-04-14 Deere & Company Crop moisture map generation and control system
US11467605B2 (en) 2019-04-10 2022-10-11 Deere & Company Zonal machine control
US11474523B2 (en) 2020-10-09 2022-10-18 Deere & Company Machine control using a predictive speed map
US11477940B2 (en) 2020-03-26 2022-10-25 Deere & Company Mobile work machine control based on zone parameter modification
CN115305761A (en) * 2022-06-23 2022-11-08 中化地质河南局集团有限公司 Collapsible loess roadbed construction method
US11589509B2 (en) 2018-10-26 2023-02-28 Deere & Company Predictive machine characteristic map generation and control system
US11635765B2 (en) 2020-10-09 2023-04-25 Deere & Company Crop state map generation and control system
US11641800B2 (en) 2020-02-06 2023-05-09 Deere & Company Agricultural harvesting machine with pre-emergence weed detection and mitigation system
US11650587B2 (en) 2020-10-09 2023-05-16 Deere & Company Predictive power map generation and control system
US11653588B2 (en) 2018-10-26 2023-05-23 Deere & Company Yield map generation and control system
US11675354B2 (en) 2020-10-09 2023-06-13 Deere & Company Machine control using a predictive map
US11672203B2 (en) 2018-10-26 2023-06-13 Deere & Company Predictive map generation and control
US11711995B2 (en) 2020-10-09 2023-08-01 Deere & Company Machine control using a predictive map
US11727680B2 (en) 2020-10-09 2023-08-15 Deere & Company Predictive map generation based on seeding characteristics and control
US11927459B2 (en) 2020-10-09 2024-03-12 Deere & Company Machine control using a predictive map
US11946747B2 (en) 2020-10-09 2024-04-02 Deere & Company Crop constituent map generation and control system
US11957072B2 (en) 2020-02-06 2024-04-16 Deere & Company Pre-emergence weed detection and mitigation system
US11983009B2 (en) 2020-10-09 2024-05-14 Deere & Company Map generation and control system

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11778945B2 (en) 2019-04-10 2023-10-10 Deere & Company Machine control using real-time model
US11874669B2 (en) 2020-10-09 2024-01-16 Deere & Company Map generation and control system
US11849671B2 (en) 2020-10-09 2023-12-26 Deere & Company Crop state map generation and control system
US11889788B2 (en) 2020-10-09 2024-02-06 Deere & Company Predictive biomass map generation and control
US11864483B2 (en) 2020-10-09 2024-01-09 Deere & Company Predictive map generation and control system
US11592822B2 (en) 2020-10-09 2023-02-28 Deere & Company Machine control using a predictive map
US11844311B2 (en) 2020-10-09 2023-12-19 Deere & Company Machine control using a predictive map
US11825768B2 (en) 2020-10-09 2023-11-28 Deere & Company Machine control using a predictive map
US11845449B2 (en) 2020-10-09 2023-12-19 Deere & Company Map generation and control system
US11849672B2 (en) 2020-10-09 2023-12-26 Deere & Company Machine control using a predictive map
US11895948B2 (en) 2020-10-09 2024-02-13 Deere & Company Predictive map generation and control based on soil properties
US11889787B2 (en) 2020-10-09 2024-02-06 Deere & Company Predictive speed map generation and control system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1116674A (en) * 1995-10-04 1996-02-14 司炳文 Method for handling foundation
JP2003129461A (en) * 2001-10-25 2003-05-08 Tanaka Juki Kensetsu Kk Construction method for soil compaction
JP2003147756A (en) * 2001-11-19 2003-05-21 Fudo Constr Co Ltd Compacted sand pile creating construction method
CN101660307A (en) * 2009-08-06 2010-03-03 新兴河北工程技术有限公司 Treatment method of collapsible loess foundation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1116674A (en) * 1995-10-04 1996-02-14 司炳文 Method for handling foundation
JP2003129461A (en) * 2001-10-25 2003-05-08 Tanaka Juki Kensetsu Kk Construction method for soil compaction
JP2003147756A (en) * 2001-11-19 2003-05-21 Fudo Constr Co Ltd Compacted sand pile creating construction method
CN101660307A (en) * 2009-08-06 2010-03-03 新兴河北工程技术有限公司 Treatment method of collapsible loess foundation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
俞宗卫等,1: "孔内深层超强夯法在湿陷性黄土地区工程中的应用", 《建筑结构》, vol. 39, no. 01, 25 January 2009 (2009-01-25), pages 96 - 98 *

Cited By (37)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535315A (en) * 2012-01-10 2012-07-04 江苏建筑职业技术学院 Treatment method for suspending concrete pavement slab
CN102535315B (en) * 2012-01-10 2015-01-21 江苏建筑职业技术学院 Treatment method for suspending concrete pavement slab
CN103790148A (en) * 2014-01-07 2014-05-14 西安科技大学 Combined treatment construction method for collapsible loess foundation
CN104727295A (en) * 2015-03-26 2015-06-24 中化岩土工程股份有限公司 Pre-hole-forming padding substitution hammer flattener dynamic compaction method
CN105954499A (en) * 2016-06-26 2016-09-21 兰州理工大学 Method and device for evaluating collapsible site after carrying out fracturing grouting reinforcement on collapsible loess site
CN107059912A (en) * 2017-03-20 2017-08-18 中国十七冶集团有限公司 A kind of people's goods elevator foundation slip casting reinforcing and processing method for being seated soft soil horizon
CN106989993B (en) * 2017-05-22 2023-08-11 嘉兴学院 Loess collapse coefficient layering in-situ test device and test method
CN106989993A (en) * 2017-05-22 2017-07-28 中铁西北科学研究院有限公司 A kind of coefficient of collapsibility of loess layering in-situ testing device and method of testing
CN107974888A (en) * 2017-12-01 2018-05-01 江苏中路工程技术研究院有限公司 Construction method of the strength concrete pile as roadbed filling
US11240961B2 (en) 2018-10-26 2022-02-08 Deere & Company Controlling a harvesting machine based on a geo-spatial representation indicating where the harvesting machine is likely to reach capacity
US11672203B2 (en) 2018-10-26 2023-06-13 Deere & Company Predictive map generation and control
US11653588B2 (en) 2018-10-26 2023-05-23 Deere & Company Yield map generation and control system
US11589509B2 (en) 2018-10-26 2023-02-28 Deere & Company Predictive machine characteristic map generation and control system
US11178818B2 (en) 2018-10-26 2021-11-23 Deere & Company Harvesting machine control system with fill level processing based on yield data
US11467605B2 (en) 2019-04-10 2022-10-11 Deere & Company Zonal machine control
US11234366B2 (en) 2019-04-10 2022-02-01 Deere & Company Image selection for machine control
US11079725B2 (en) 2019-04-10 2021-08-03 Deere & Company Machine control using real-time model
US11650553B2 (en) 2019-04-10 2023-05-16 Deere & Company Machine control using real-time model
CN110106882A (en) * 2019-04-28 2019-08-09 云南建投第一勘察设计有限公司 A kind of gas lift reverse circulation device for cast-in-situ bored pile
CN112227356A (en) * 2019-07-15 2021-01-15 河北建设勘察研究院有限公司 Gravel grouting steel pipe pile and preparation method thereof
US11641800B2 (en) 2020-02-06 2023-05-09 Deere & Company Agricultural harvesting machine with pre-emergence weed detection and mitigation system
US11957072B2 (en) 2020-02-06 2024-04-16 Deere & Company Pre-emergence weed detection and mitigation system
US11477940B2 (en) 2020-03-26 2022-10-25 Deere & Company Mobile work machine control based on zone parameter modification
US11650587B2 (en) 2020-10-09 2023-05-16 Deere & Company Predictive power map generation and control system
US11927459B2 (en) 2020-10-09 2024-03-12 Deere & Company Machine control using a predictive map
US11983009B2 (en) 2020-10-09 2024-05-14 Deere & Company Map generation and control system
US20220110251A1 (en) 2020-10-09 2022-04-14 Deere & Company Crop moisture map generation and control system
US11946747B2 (en) 2020-10-09 2024-04-02 Deere & Company Crop constituent map generation and control system
US11675354B2 (en) 2020-10-09 2023-06-13 Deere & Company Machine control using a predictive map
US11474523B2 (en) 2020-10-09 2022-10-18 Deere & Company Machine control using a predictive speed map
US11711995B2 (en) 2020-10-09 2023-08-01 Deere & Company Machine control using a predictive map
US11635765B2 (en) 2020-10-09 2023-04-25 Deere & Company Crop state map generation and control system
US11727680B2 (en) 2020-10-09 2023-08-15 Deere & Company Predictive map generation based on seeding characteristics and control
CN113494134A (en) * 2021-07-05 2021-10-12 浙江东南网架股份有限公司 Inverse installation method of variable cross-section steel pipe forked support column
CN113931164A (en) * 2021-11-01 2022-01-14 西宁碧胜房地产开发有限公司 Club-footed pile construction method for pre-soaking and compacting collapsible loess
CN114016489A (en) * 2021-11-24 2022-02-08 华侨大学 Datum point fixing device for settlement monitoring
CN115305761A (en) * 2022-06-23 2022-11-08 中化地质河南局集团有限公司 Collapsible loess roadbed construction method

Also Published As

Publication number Publication date
CN102277867B (en) 2013-10-09

Similar Documents

Publication Publication Date Title
CN102277867B (en) Construction method for collapsible loess foundation
CN102080373B (en) Construction method for jointly treating collapsibility of loess foundation by using DDC (Downhole Dynamic Compaction) pile and pile foundation
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN103184734A (en) Implanted and grouted compound pile and construction method
CN104532957B (en) Existing building sets up basement reversed construction method
CN106988302A (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN103074882A (en) Construction method for reinforcing island-type perennial frozen-soil foundation by adopting gravel piles
CN206070508U (en) Device for reinforcing foundation
CN106759461A (en) Resist grand supporting construction
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN113152450A (en) Application of prestressed concrete pipe pile planting technology in complex foundation
CN113863706B (en) Construction method and application device of existing building low-clearance lower rotary-jet static pressure composite pile
CN101701460A (en) Construction method for controlling peripheral ground subsidence in foundation pit construction
CN203213101U (en) Embedding grouting combined pile
CN104652427A (en) Construction method of drilling pile
CN201339186Y (en) Soft rock concrete replacement pile composite foundation
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN105064332A (en) Construction method for bearing base piles of square pile bodies
CN103790148A (en) Combined treatment construction method for collapsible loess foundation
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN110889235A (en) Underground pile foundation construction engineering design method
Kordahi Underpinning strategies for buildings with deep foundations
CN110230320B (en) Construction method of high-speed railway contact net support foundation structure
Krutov et al. Foundations formed from piles cast in punched holes.

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131009

Termination date: 20140513