CN102121268A - Method for replacing sewage pipeline - Google Patents
Method for replacing sewage pipeline Download PDFInfo
- Publication number
- CN102121268A CN102121268A CN 201110042203 CN201110042203A CN102121268A CN 102121268 A CN102121268 A CN 102121268A CN 201110042203 CN201110042203 CN 201110042203 CN 201110042203 A CN201110042203 A CN 201110042203A CN 102121268 A CN102121268 A CN 102121268A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- old
- new
- working pit
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a method for replacing a sewage pipeline, which does not disturb residents or destroy foundation of surrounding buildings, does not influence traffic, hardly pollutes the environment and has low construction cost. The method comprises the following steps: (1) dividing a sewage pipeline into a plurality of construction sections according to diameter differences and break points of the sewage pipeline; (2) forming a first work pit and a second work pit at two ends of each construction section; (3) putting a new pipeline in the first work pit; (4) assembling tube drawing bench equipment in the second work pit; (5) inserting tools for crushing and expanding pipelines into an old pipeline from the second work pit to crush the old pipeline; and (6) drawing a new pipeline to the position of the old pipeline by the tube drawing bench equipment.
Description
Technical field
The invention belongs to the technical field of construction work, relate to a kind of method of changing sewage conduct particularly.
Background technology
Domestic many underground sewers wear out and seepage with age at present, are badly in need of the sewage conduct that more renews.But, because generally there are a lot of residential quarters, commercial facility, traffic route etc. in the ground at underground sewer place, if whole excavation will have a strong impact on the people's life, destroy surrounding building basis and underground utilities, disturb traffic, contaminated environment, construction cost is huge.
Summary of the invention
Technology of the present invention is dealt with problems and is: overcome the deficiencies in the prior art, provide a kind of and do not disturb residents, do not destroy surrounding building basis and underground utilities, do not disturb traffic, the method for of low pollution environment, replacing sewage conduct that construction cost is cheap.
Technical solution of the present invention is: the method for this replacing sewage conduct may further comprise the steps:
(1) diameter difference and the break according to sewage conduct is divided into some construction sections;
(2) at the two ends of each construction section first working pit, second working pit are set respectively;
(3) in first working pit, put into new pipeline;
(4) bench equipment is installed in second working pit;
(5) instrument with broken and expand tube inserts in the old pipeline from second working pit, carries out the fragmentation of old pipeline;
(6) utilize bench equipment new pipeline to be drawn in the position of old pipeline.
Because this method is only to dig two holes, directly more renew pipeline in the position of old pipeline, so do not disturb residents, do not destroy surrounding building basis and underground utilities, do not disturb traffic, of low pollution environment, construction cost be cheap.
The specific embodiment
Below technical scheme of the present invention is described in further detail.
The method of this replacing sewage conduct may further comprise the steps:
(1) diameter difference and the break according to sewage conduct is divided into some construction sections;
(2) at the two ends of each construction section first working pit, second working pit are set respectively;
(3) in first working pit, put into new pipeline;
(4) bench equipment is installed in second working pit;
(5) instrument with broken and expand tube inserts in the old pipeline from second working pit, carries out the fragmentation of old pipeline;
(6) utilize bench equipment new pipeline to be drawn in the position of old pipeline.The expand tube tool that is about to a cone inserts and is guide in the old pipeline, makes old pipeline breaking by pulling force, and broken pipeline fragment is squeezed on every side in the soil, adopts bench equipment that new pipeline is drawn in old pipeline location, finishes the replacing construction of sewage conduct.
The setting that it is noted that working pit should be avoided road and commercial doorway, makes things convenient for resident trip; With caliber is one section; What pipeline had a break divides one section in addition, changes pulling force when excessive, the mouth of pipe may occur and stagger, and repaiies and changes after straight again.
Preferably, step (3) also comprises the port of new pipeline planished, heats, holds presses cooling, and fusion one under the automatic pressurization of hydraulic pressure then is again with new pipe joint sweat soldering.
Preferably, make the diameter of expand tube head of instrument of broken and expand tube greater than the diameter of old pipeline in the step (5).Purpose is that enough environment spaces are provided when changing pipeline, reduces the new pipeline replaced and the frictional force between the stratum.
Preferably, new pipeline adopts hdpe pipe.Be PE tubing, characteristics are that corrosion-resistant, high temperature resistant, non-scaling, life-span are long.
Employing this method construction has solved eighties sewage conduct because of the aging leakage problems of pipeline, during the maintain and replace underground utilities, and " belly breaking " construction again.This method, it is little to have the construction operation face, digging-free, short construction period, integrated cost is low, many advantages such as is widely used, can reduce to greatest extent to the interference of traffic with to the pollution of environment, reduced the sorrow people that construction brings, reduced, reduced construction cost surrounding building basis and the crisscross destruction of underground utilities.To the protection fee and the removal expense of underground utilities, abolish old pipe and more renew pipe and once finish when having reduced excavation simultaneously, the duration is short, and integrated cost is low.
The above; it only is preferred embodiment of the present invention; be not that the present invention is done any pro forma restriction, every foundation technical spirit of the present invention all still belongs to the protection domain of technical solution of the present invention to any simple modification, equivalent variations and modification that above embodiment did.
Claims (4)
1. a method of changing sewage conduct is characterized in that, may further comprise the steps:
(1) diameter difference and the break according to sewage conduct is divided into some construction sections;
(2) at the two ends of each construction section first working pit, second working pit are set respectively;
(3) in first working pit, put into new pipeline;
(4) bench equipment is installed in second working pit;
(5) instrument with broken and expand tube inserts in the old pipeline from second working pit, carries out the fragmentation of old pipeline;
(6) utilize bench equipment new pipeline to be drawn in the position of old pipeline.
2. method according to claim 1 is characterized in that, step (3) also comprises the port of new pipeline planished, heats, holds presses cooling, and fusion one under the automatic pressurization of hydraulic pressure then is again with new pipe joint sweat soldering.
3. method according to claim 1 and 2 is characterized in that, the diameter of expand tube head of instrument that makes broken and expand tube in the step (5) is greater than the diameter of old pipeline.
4. method according to claim 1 is characterized in that, new pipeline adopts hdpe pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110042203 CN102121268A (en) | 2011-02-22 | 2011-02-22 | Method for replacing sewage pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110042203 CN102121268A (en) | 2011-02-22 | 2011-02-22 | Method for replacing sewage pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102121268A true CN102121268A (en) | 2011-07-13 |
Family
ID=44249919
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110042203 Pending CN102121268A (en) | 2011-02-22 | 2011-02-22 | Method for replacing sewage pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102121268A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103453217A (en) * | 2012-05-30 | 2013-12-18 | 深圳市钻通工程机械股份有限公司 | Fastener-free quick-release draw bar |
CN103696486A (en) * | 2013-12-13 | 2014-04-02 | 柳州市五环水暖器材经营部 | Method for replacing sewage conduits |
CN105864562A (en) * | 2016-06-15 | 2016-08-17 | 长春高祥特种管道有限公司 | Method for repairing underground steel pipeline by non-excavation insertion |
CN106368241A (en) * | 2016-01-27 | 2017-02-01 | 郑州市市政工程总公司 | Inspection well for fast-connected newly-built pipeline and construction method thereof |
CN108222220A (en) * | 2018-01-31 | 2018-06-29 | 杭州市市政工程集团有限公司 | The construction method of new and old sewage pipe connection in a kind of sewage pipe displacement transformation |
CN109248766A (en) * | 2018-09-29 | 2019-01-22 | 山东大学 | A kind of hydraulic shock tube expander and underground piping no-dig technique replace system |
CN109958881A (en) * | 2017-12-25 | 2019-07-02 | 上海梅山钢铁股份有限公司 | Solved the stable device and method of wall pipeline pressure |
CN110747965A (en) * | 2019-10-31 | 2020-02-04 | 中铁十八局集团建筑安装工程有限公司 | Expansion-draw pipe construction process for reconstruction and expansion of drainage pipe network |
CN111945901A (en) * | 2020-07-27 | 2020-11-17 | 北京天恒建设集团有限公司 | Waterproof construction method for floor penetrating drainage main pipe hole of toilet in old community |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4507019A (en) * | 1983-02-22 | 1985-03-26 | Expand-A-Line, Incorporated | Method and apparatus for replacing buried pipe |
CN1269003A (en) * | 1995-04-28 | 2000-10-04 | Tti管线施工技术有限公司 | Method and apparatus for cleaning public pipeline and then changed with polyolefin pipeline |
-
2011
- 2011-02-22 CN CN 201110042203 patent/CN102121268A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4507019A (en) * | 1983-02-22 | 1985-03-26 | Expand-A-Line, Incorporated | Method and apparatus for replacing buried pipe |
US4507019B1 (en) * | 1983-02-22 | 1987-12-08 | ||
CN1269003A (en) * | 1995-04-28 | 2000-10-04 | Tti管线施工技术有限公司 | Method and apparatus for cleaning public pipeline and then changed with polyolefin pipeline |
Non-Patent Citations (2)
Title |
---|
《施工技术》 19971031 杨印臣 埋地管道不开挖原位大修或更换技术 第39-41页 1-4 , 第10期 * |
《油气田地面工程》 19970731 杨印臣 美国埋地管道不开挖原位大修或更换技术 第12页右栏倒数第2段-第13页左栏第3段 1-4 第16卷, 第4期 * |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103453217A (en) * | 2012-05-30 | 2013-12-18 | 深圳市钻通工程机械股份有限公司 | Fastener-free quick-release draw bar |
CN103696486A (en) * | 2013-12-13 | 2014-04-02 | 柳州市五环水暖器材经营部 | Method for replacing sewage conduits |
CN106368241A (en) * | 2016-01-27 | 2017-02-01 | 郑州市市政工程总公司 | Inspection well for fast-connected newly-built pipeline and construction method thereof |
CN105864562A (en) * | 2016-06-15 | 2016-08-17 | 长春高祥特种管道有限公司 | Method for repairing underground steel pipeline by non-excavation insertion |
CN105864562B (en) * | 2016-06-15 | 2018-08-28 | 长春高祥特种管道有限公司 | A kind of interspersed method for repairing underground steel pipe of no-dig technique |
CN109958881B (en) * | 2017-12-25 | 2021-11-16 | 上海梅山钢铁股份有限公司 | Device and method for solving problem of stable pressure of through-wall pipeline |
CN109958881A (en) * | 2017-12-25 | 2019-07-02 | 上海梅山钢铁股份有限公司 | Solved the stable device and method of wall pipeline pressure |
CN108222220A (en) * | 2018-01-31 | 2018-06-29 | 杭州市市政工程集团有限公司 | The construction method of new and old sewage pipe connection in a kind of sewage pipe displacement transformation |
CN108222220B (en) * | 2018-01-31 | 2024-04-02 | 杭州市市政工程集团有限公司 | Construction method for connecting new sewage pipe and old sewage pipe in displacement transformation of sewage pipe |
CN109248766A (en) * | 2018-09-29 | 2019-01-22 | 山东大学 | A kind of hydraulic shock tube expander and underground piping no-dig technique replace system |
CN109248766B (en) * | 2018-09-29 | 2024-01-26 | 山东大学 | Hydraulic impact pipe expander and underground pipeline non-excavation replacement system |
CN110747965A (en) * | 2019-10-31 | 2020-02-04 | 中铁十八局集团建筑安装工程有限公司 | Expansion-draw pipe construction process for reconstruction and expansion of drainage pipe network |
CN111945901A (en) * | 2020-07-27 | 2020-11-17 | 北京天恒建设集团有限公司 | Waterproof construction method for floor penetrating drainage main pipe hole of toilet in old community |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102121268A (en) | Method for replacing sewage pipeline | |
CN205261132U (en) | Non - excavation repair system of method of inserting expands | |
CN104652415B (en) | High-polymer membrane bag grouting method is repaired in underground piping sedimentation | |
CN105673935B (en) | Split slotting method underground utilities replacing options | |
CN103696486A (en) | Method for replacing sewage conduits | |
CN106088293A (en) | A kind of small-bore sewage conduct restorative procedure | |
CN105179875A (en) | Non-excavation repairing method for deformation collapse of weak stratum drainage pipe | |
CN104727425A (en) | Traction-type non-excavation pipeline repairing method | |
CN104500094A (en) | Lining connecting structure applicable to jacking pipe for implementing connection passage | |
CN202627165U (en) | Device for repairing completely collapsed and large-deformation pipes without excavating whole pipes | |
CN204371357U (en) | Be suitable for the lining cutting syndeton that push pipe implements service channel | |
CN103629474B (en) | For repairing the restorative procedure connecting aqueduct of impaired cast iron fire protection pipeline | |
CN205858656U (en) | A kind of attachment means for connecting immersible pump and drain pipe and immersible pump thereof | |
CN210151883U (en) | Inner lining repairing mechanism for rain sewage pipeline | |
KR20150133996A (en) | Method for repaering a non-excavation drainpipecapable | |
CN109058583B (en) | Tool pipe for hand-digging type pipe jacking construction | |
CN109027419A (en) | A kind of hand pick formula pipe jacking construction method | |
KR101186482B1 (en) | Trenchless replacing method for underground pipe | |
CN203008925U (en) | Shield barrier-free launching apparatus | |
CN109577457A (en) | A kind of method of efficient replacement sewage conduct | |
CN109868881B (en) | Repairing method of lining repairing mechanism of rainwater and sewage pipeline | |
CN107270028A (en) | A kind of automatically walk pipeline rehabilitation device and pipe repairing method | |
CN203498985U (en) | Local repair structure for steel lining of exhaust pipeline | |
CN203546725U (en) | Backfilling grouting device capable of being recycled | |
Obradović | A short review: Techniques for trenchless sewer rehabilitation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20110713 |