CN102073768A - Automatic arch dam pouring block plotting device and plotting method - Google Patents
Automatic arch dam pouring block plotting device and plotting method Download PDFInfo
- Publication number
- CN102073768A CN102073768A CN 201110005919 CN201110005919A CN102073768A CN 102073768 A CN102073768 A CN 102073768A CN 201110005919 CN201110005919 CN 201110005919 CN 201110005919 A CN201110005919 A CN 201110005919A CN 102073768 A CN102073768 A CN 102073768A
- Authority
- CN
- China
- Prior art keywords
- arch dam
- pour
- information
- dimensional
- module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention relates to the technology of modeling, and discloses an automatic arch dam pouring block plotting method, and solves the problems of heavy workload, high difficulty and prone errors caused by manual drawing in the prior art. The technical scheme comprises the main points that: the arch dam pouring block plotting method comprises the following steps of: a. constructing a basic database including arch dam modeling-related data information; b. establishing a three-dimensional model of an overall arch dam; c. inputting the information of a pouring block which needs to be plotted, and extracting the three-dimensional structural information of the pouring block from the three-dimensional model of the overall arch dam; d. outputting the acquired three-dimensional structural information of the pouring block, and generating two-dimensional drawing paper through a two-dimensional plotting module; and e. marking the generated two-dimensional drawing paper and counting basic information, and indicating on a drawing. In addition, the invention also discloses an automatic arch dam pouring block plotting device. The method and the device realize automatic arch dam pouring block plotting, speed up a design schedule, reduce design cost, reduce error rate, improve production efficiency and are suitable for planning to build an arch dam.
Description
Technical field
The present invention relates to modeling technique, relate to a kind of arch dam pour automatic map delivery device specifically and go out drawing method.
Background technology
Along with the planning to build and setting up of some large-scale arch dams in recent years, the arch dam construction has obtained developing rapidly.Arch dam is because the requirement of topographic(al) feature and section stress optimal design, often make cross dimensions design more complicated, particularly dome dam, its up and down dam facing be space curved surface.Because the build complexity, design and construction need a large amount of high-precision project data and engineering drawing.And these project data and engineering drawing are to be finished by very vast and numerous calculating and drawing work, and especially being plotted in of drawing remains in the conventional art by manually finishing, and workload is big, and difficulty is high and easily make mistakes.Therefore the numerical evaluation of processing of arch dam computer graphical and arch dam pour just seems very meaningful with the research work that three-dimensional picture shows and output combines.
Summary of the invention
Technical matters to be solved by this invention is: propose a kind of arch dam pour automatic map delivery device and go out drawing method, solve and adopt artificial the drawing to cause the problem that workload is big, difficulty is high, easily make mistakes in the conventional art.
The present invention solves the problems of the technologies described above the technical scheme that is adopted: arch dam pour automatic map delivery device comprises that database module, three-dimensional data processing module, two dimension go out module, information labeling module; Described database module, three-dimensional data processing module, two dimension go out module and are connected successively with the information labeling module; Described database module is used to provide arch dam modeling related data information; The arch dam modeling related data information that described three-dimensional data processing module provides according to database module is set up the whole three-dimensional model of arch dam, and extracts pour three-dimensional structure information according to default pour position from block mold; Described two dimension goes out module the three-dimensional structure information output of the pour that extracts is generated two-dimentional drawing; Described information labeling module marks with essential information the two-dimentional drawing that generates and adds up.
Arch dam pour automatic map delivery method may further comprise the steps:
A. make up the master database that comprises arch dam modeling related data information;
B. set up the whole three-dimensional model of arch dam;
C. import the pour information that to publish picture, from the whole three-dimensional model of arch dam, extract pour three-dimensional structure information;
D. with the pour three-dimensional structure information output of obtaining, go out module by two dimension and generate two-dimentional drawing;
E. the two-dimentional drawing that generates is marked and the essential information statistics, and be illustrated on the drawing.
Among the step a, described arch dam modeling related data information comprises arch dam bodily form data, transverse joint data and grout groove data.
Among the step a, described arch dam modeling related data information adopts the storage of EXCEL table.
Among the step c, described pour three-dimensional structure information comprises pour dimensional data, upstream and downstream sealing data and grout groove data.
Among the step c, the pour information that described need are published picture comprises elevation at the bottom of pour place monolith numbering, pour crest level and the pour.
Among the step e, the content that the two-dimentional drawing that generates is marked comprises: monolith numbering, elevation and reference mark numbering.
Among the step e, the essential information statistics comprises that reference mark coordinate statistics generates with relevant form.
Among the step b, adopt CATIA software to set up the whole three-dimensional model of arch dam.
Among the step e, the content that the two-dimentional drawing that generates marks is upgraded synchronously automatically with the change of pour three-dimensional structure information.
The invention has the beneficial effects as follows: realized arch dam pour automatic map delivery, accelerated design schedule, reduced design cost, and reduced error rate, enhanced productivity.
Description of drawings
Fig. 1 is an arch dam pour automatic map delivery apparatus structure block diagram of the present invention;
Fig. 2 is an arch dam pour automatic map delivery method flow diagram of the present invention.
Embodiment
The invention will be further described below in conjunction with drawings and Examples.
The present invention is directed to and adopt artificial the drawing to cause the defective that workload is big, difficulty is high, easily make mistakes in the conventional art, propose a kind of arch dam pour automatic map delivery device and gone out drawing method, realized arch dam pour automatic map delivery, accelerate design schedule, reduce design cost, and the minimizing error rate is enhanced productivity.
As shown in Figure 1, arch dam pour automatic map delivery device comprises that database module, three-dimensional data processing module, two dimension go out module, information labeling module; Described database module, three-dimensional data processing module, two dimension go out module and are connected successively with the information labeling module.
Described database module is used to provide arch dam modeling related data information; The arch dam modeling related data information that described three-dimensional data processing module provides according to database module is set up the whole three-dimensional model of arch dam, and extracts pour three-dimensional structure information according to default pour position from block mold; Described two dimension goes out module the three-dimensional structure information output of the pour that extracts is generated two-dimentional drawing; Described information labeling module marks with essential information the two-dimentional drawing that generates and adds up.
Fig. 2 has provided the arch dam pour automatic map delivery method flow among the present invention, on concrete enforcement, may further comprise the steps: make up database 1.: promptly make up the master database that comprises arch dam modeling related data information; 2. set up arch dam model: promptly set up the whole three-dimensional model of arch dam; 3. import pour information: i.e. the pour information that input need be published picture; 4. extract pour three-dimensional structure information: promptly from the whole three-dimensional model of arch dam, extract pour three-dimensional structure information; 5. export three-dimensional structure information: the pour three-dimensional structure information output that is about to obtain; 6. generate two-dimentional drawing: promptly go out module and generate two-dimentional drawing by two dimension; 7. to two-dimentional drawings marked: promptly the two-dimentional drawing that generates is marked and the essential information statistics, and be illustrated on the drawing.
Embodiment:
1. make up a master database,, comprise arch dam bodily form data in this master database for the follow-up whole three-dimensional model of arch dam of setting up provides the data support, transverse joint data and grout groove data, statistics can be with the form storage of these data with the EXCEL table for convenience;
2. based on the data message in the step 1, set up the whole three-dimensional model (can adopt CATIA software to come modeling) of arch dam, and as required, the pour information that input need be published picture comprises pour place monolith numbering, elevation at the bottom of pour crest level and the pour;
3. the pour information according to input in the step 2 extracts pour three-dimensional structure information from the whole three-dimensional model of arch dam, comprises pour dimensional data, upstream and downstream sealing data and grout groove data;
4. with the pour three-dimensional structure information output of obtaining, go out module by two dimension and generate two-dimentional drawing, X-Y scheme lateral lattice are determined according to water power industry drafting standard;
5. the two-dimentional drawing that generates is marked with essential information and add up, and be illustrated on the drawing, wherein Biao Zhu content comprises monolith numbering, elevation and reference mark numbering, the essential information statistics comprises reference mark coordinate statistics, and the relevant form (being reference mark coordinate statistical form) of generation, the content and the reference mark coordinate statistical representation of these marks are intended on the drawing, promptly form perfect pour structural drawing.
Behind pour three-dimensional structure information-change, the content that the information labeling module marks the two-dimentional drawing that generates (monolith numbering, elevation and reference mark numbering) is also upgraded synchronously automatically.
Claims (10)
1. arch dam pour automatic map delivery device is characterized in that: comprise that database module, three-dimensional data processing module, two dimension go out module, information labeling module; Described database module, three-dimensional data processing module, two dimension go out module and are connected successively with the information labeling module; Described database module is used to provide arch dam modeling related data information; The arch dam modeling related data information that described three-dimensional data processing module provides according to database module is set up the whole three-dimensional model of arch dam, and extracts pour three-dimensional structure information according to default pour position from block mold; Described two dimension goes out module the three-dimensional structure information output of the pour that extracts is generated two-dimentional drawing; Described information labeling module marks with essential information the two-dimentional drawing that generates and adds up.
2. arch dam pour automatic map delivery method is characterized in that: may further comprise the steps:
A. make up the master database that comprises arch dam modeling related data information;
B. set up the whole three-dimensional model of arch dam;
C. import the pour information that to publish picture, from the whole three-dimensional model of arch dam, extract pour three-dimensional structure information;
D. with the pour three-dimensional structure information output of obtaining, go out module by two dimension and generate two-dimentional drawing;
E. the two-dimentional drawing that generates is marked and the essential information statistics, and be illustrated on the drawing.
3. arch dam pour automatic map delivery method as claimed in claim 2 is characterized in that: among the step a, described arch dam modeling related data information comprises arch dam bodily form data, transverse joint data and grout groove data.
4. as claim 2 or 3 described arch dam pour automatic map delivery methods, it is characterized in that: among the step a, described arch dam modeling related data information adopts the storage of EXCEL table.
5. as claim 2 or 3 described arch dam pour automatic map delivery methods, it is characterized in that: among the step c, described pour three-dimensional structure information comprises pour dimensional data, upstream and downstream sealing data and grout groove data.
6. as claim 2 or 3 described arch dam pour automatic map delivery methods, it is characterized in that: among the step c, the pour information that described need are published picture comprises elevation at the bottom of pour place monolith numbering, pour crest level and the pour.
7. as claim 2 or 3 described arch dam pour automatic map delivery methods, it is characterized in that: among the step e, the content that the two-dimentional drawing that generates is marked comprises: monolith numbering, elevation and reference mark numbering.
8. arch dam pour automatic map delivery method as claimed in claim 7 is characterized in that: among the step e, the essential information statistics comprises that reference mark coordinate statistics generates with relevant form.
9. as claim 2 or 3 described arch dam pour automatic map delivery methods, it is characterized in that: among the step b, adopt CATIA software to set up the whole three-dimensional model of arch dam.
10. as claim 2 or 3 described arch dam pour automatic map delivery methods, it is characterized in that: among the step e, the content that the two-dimentional drawing that generates marks is upgraded synchronously automatically with the change of pour three-dimensional structure information.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110005919 CN102073768A (en) | 2011-01-13 | 2011-01-13 | Automatic arch dam pouring block plotting device and plotting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110005919 CN102073768A (en) | 2011-01-13 | 2011-01-13 | Automatic arch dam pouring block plotting device and plotting method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102073768A true CN102073768A (en) | 2011-05-25 |
Family
ID=44032306
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110005919 Pending CN102073768A (en) | 2011-01-13 | 2011-01-13 | Automatic arch dam pouring block plotting device and plotting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102073768A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103853868A (en) * | 2013-07-10 | 2014-06-11 | 成都希盟泰克科技发展有限公司 | Drawing method for isoheight two-dimensional engineering drawing based on CATIA (Computer-graphics Aided Three-dimensional Interactive Application) |
CN107480374A (en) * | 2017-08-14 | 2017-12-15 | 中国铁道科学研究院铁道建筑研究所 | A kind of bridge BIM model creation methods based on CATIA |
CN110284465A (en) * | 2019-06-28 | 2019-09-27 | 中国电建集团成都勘测设计研究院有限公司 | Arch dam pour construction control method |
CN110781535A (en) * | 2018-07-27 | 2020-02-11 | 西安海平方网络科技有限公司 | Model plotting method and device, computer equipment and readable storage medium |
CN111899342A (en) * | 2020-06-29 | 2020-11-06 | 中铁第一勘察设计院集团有限公司 | Graph establishing method and device based on central database |
CN113165420A (en) * | 2018-11-29 | 2021-07-23 | 李成培 | Shaped object in three-dimensional transparent space and manufacturing method thereof |
CN116842915A (en) * | 2023-07-04 | 2023-10-03 | 中国电建集团西北勘测设计研究院有限公司 | CATIAV 6-based batch labeling method for hydraulic and hydroelectric engineering drawings |
CN116842915B (en) * | 2023-07-04 | 2024-05-10 | 中国电建集团西北勘测设计研究院有限公司 | Water conservancy and hydropower engineering drawing batch labeling method based on CATIA V6 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1858803A (en) * | 2006-04-04 | 2006-11-08 | 天津大学 | Three dimension uniform model construction method of water conservancy hydropower engineering geological information |
CN101727677A (en) * | 2008-10-20 | 2010-06-09 | 车德福 | Method for mutual conversion between two-dimensional view and three--dimensional view in mine model |
CN101762265A (en) * | 2008-10-27 | 2010-06-30 | 任凌云 | Method of interconversion between two-dimensional drawing and three-dimensional model in mine model |
-
2011
- 2011-01-13 CN CN 201110005919 patent/CN102073768A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1858803A (en) * | 2006-04-04 | 2006-11-08 | 天津大学 | Three dimension uniform model construction method of water conservancy hydropower engineering geological information |
CN101727677A (en) * | 2008-10-20 | 2010-06-09 | 车德福 | Method for mutual conversion between two-dimensional view and three--dimensional view in mine model |
CN101762265A (en) * | 2008-10-27 | 2010-06-30 | 任凌云 | Method of interconversion between two-dimensional drawing and three-dimensional model in mine model |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103853868A (en) * | 2013-07-10 | 2014-06-11 | 成都希盟泰克科技发展有限公司 | Drawing method for isoheight two-dimensional engineering drawing based on CATIA (Computer-graphics Aided Three-dimensional Interactive Application) |
CN103853868B (en) * | 2013-07-10 | 2016-10-26 | 成都希盟泰克科技发展有限公司 | Equal pitch contour two-dimensional engineering graphic based on CATIA goes out drawing method |
CN107480374A (en) * | 2017-08-14 | 2017-12-15 | 中国铁道科学研究院铁道建筑研究所 | A kind of bridge BIM model creation methods based on CATIA |
CN107480374B (en) * | 2017-08-14 | 2020-06-02 | 中国铁道科学研究院铁道建筑研究所 | Bridge BIM model creation method based on CATIA |
CN110781535A (en) * | 2018-07-27 | 2020-02-11 | 西安海平方网络科技有限公司 | Model plotting method and device, computer equipment and readable storage medium |
CN113165420A (en) * | 2018-11-29 | 2021-07-23 | 李成培 | Shaped object in three-dimensional transparent space and manufacturing method thereof |
CN110284465A (en) * | 2019-06-28 | 2019-09-27 | 中国电建集团成都勘测设计研究院有限公司 | Arch dam pour construction control method |
CN111899342A (en) * | 2020-06-29 | 2020-11-06 | 中铁第一勘察设计院集团有限公司 | Graph establishing method and device based on central database |
CN116842915A (en) * | 2023-07-04 | 2023-10-03 | 中国电建集团西北勘测设计研究院有限公司 | CATIAV 6-based batch labeling method for hydraulic and hydroelectric engineering drawings |
CN116842915B (en) * | 2023-07-04 | 2024-05-10 | 中国电建集团西北勘测设计研究院有限公司 | Water conservancy and hydropower engineering drawing batch labeling method based on CATIA V6 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110580376B (en) | Revit and Dynamo-based pile foundation model creation method | |
CN109784004B (en) | BIM technology-based special-shaped metal roof installation construction method | |
CN102073768A (en) | Automatic arch dam pouring block plotting device and plotting method | |
CN104252558B (en) | A kind of non-standard construction fender member digital control processing preprocess method based on BIM platform | |
CN107194074B (en) | Method for establishing parametric model of toe board of panel dam by using CATIA three-dimensional software | |
CN106777779B (en) | Railway culvert design method based on BIM | |
CN106202831A (en) | A kind of pipeline layout optimization method based on BIM | |
CN104537191A (en) | Drawing method for three-dimensional rebar model schematic diagram | |
CN108536973A (en) | The construction drawing detailing method of curved surface steel box bridge | |
CN104408240A (en) | Data conversion and extraction method for model based definition (MBD) | |
CN105608274A (en) | Tribon M3 ship design software based quick lofting method for molded line of anchor platform | |
CN110188423A (en) | A kind of linear engineering structure fast B IM modeling method based on FEM meshing | |
CN109918760A (en) | Reinforcing bar modeling method based on Revit interoperability | |
CN110489890A (en) | Steel bifurcated structure automatic map delivery method | |
CN108647450A (en) | A kind of pre-buried big foundation bolt construction method based on BIM technology | |
CN110990933A (en) | Modeling method for shield tunnel | |
CN105956278A (en) | Detailed design method of mechanical and electrical engineering pipeline system based on Autodesk Revit | |
CN113626911A (en) | Concrete 3D printing path optimization method based on first principal stress vector distribution | |
CN106837375A (en) | A kind of method for automatic modeling of shield tunnel concrete pipe sheet tectonic model | |
CN103631996A (en) | Product structure and process parallel design method based on model maturity | |
CN110990923A (en) | Rapid engineering calculation method, system and medium for hyperbolic arch dam of water conservancy and hydropower engineering | |
CN102147825A (en) | Method for rapidly making drawing of beam structural part and optimizing drawing | |
CN103761769A (en) | Method for engraving three-dimensional landform | |
CN102722621A (en) | Method for visualizing computed result of finite element method | |
CN104281727A (en) | Method for designing tire die on basis of Excel and CAD (computer aided design) platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20110525 |