CN101820317A CN201010149574A CN201010149574A CN101820317A CN 101820317 A CN101820317 A CN 101820317A CN 201010149574 A CN201010149574 A CN 201010149574A CN 201010149574 A CN201010149574 A CN 201010149574A CN 101820317 A CN101820317 A CN 101820317A
Authority
CN
China
Prior art keywords
protection
management system
network management
group
controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201010149574A
Other languages
Chinese (zh)
Inventor
张滨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZTE Corp
Original Assignee
ZTE Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZTE Corp filed Critical ZTE Corp
Priority to CN201010149574A priority Critical patent/CN101820317A/en
Publication of CN101820317A publication Critical patent/CN101820317A/en
Priority to PCT/CN2010/077495 priority patent/WO2011113272A1/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L41/00Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
    • H04L41/06Management of faults, events, alarms or notifications
    • H04L41/0654Management of faults, events, alarms or notifications using network fault recovery
    • H04L41/0668Management of faults, events, alarms or notifications using network fault recovery by dynamic selection of recovery network elements, e.g. replacement by the most appropriate element after failure
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04BTRANSMISSION
    • H04B10/00Transmission systems employing electromagnetic waves other than radio-waves, e.g. infrared, visible or ultraviolet light, or employing corpuscular radiation, e.g. quantum communication
    • H04B10/03Arrangements for fault recovery
    • H04B10/032Arrangements for fault recovery using working and protection systems

Abstract

The invention discloses a method and a system for realizing protection switching (PS) of protection groups. The method comprises the following steps: receiving protection switching events sent by a protection controller after performing protection switching on the protection groups through a network management system; verifying whether all the protection groups are successful in protection switching or not according to the protection switching events; and if not, notifying the protection controller to execute protection switching operation on the protection groups which fails to be performed with the protection switching. According to the technical scheme provided by the invention, the problem of incapability of realizing switching on services due to various reasons in the relevant technologies is solved, thus being capable of improving the success rate of protection switching of the protection groups.

Description

Realize the method and system that the protection of protection group is switched
Technical field
The present invention relates to the communications field, in particular to a kind of method and system that realize that the protection of protection group is switched.
Background technology
In optical transmission device, all can backup usually to business, realize protection to business, when guaranteeing that Working service interrupts, it is professional to be switched to protection, allows professional unbroken operation.
When bearer service, Working service and protection are professional all to be moved simultaneously, and when the professional generation of service aisle was interrupted, switching services was to protecting on the passage.At present, optical network management system and optical network device all provide defencive function, realize various types of protection operational modes.At present, various types of protections all are could trigger to switch under the situation of the professional normal operation of protection.
Along with the development of optical communication technique, the equipment network mode is complicated day by day flexibly, and increasing engineering has all been enabled kinds of protect mode and operation simultaneously, and many shared circuits of business.
In the correlation technique, when line interruption, may cause many business simultaneously and switch simultaneously.Specifically can be referring to Fig. 1.
The flow chart that Fig. 1 switches for optical network system protection in the correlation technique.As shown in Figure 1, when operating path (passage) breaks down, when Working service interrupts, mainly comprise following processing:
Step S102: when the protection channel abnormal, it is professional not to be switched to protection, does not report PSE Protection Switch Event;
Step S104: when protecting passage just often, it is professional to be switched to protection, reports PSE Protection Switch Event simultaneously.
As shown in Figure 1, because many business trigger simultaneously and switch, the protection controller can report a large amount of protections to switch message, causes efficient to reduce, even might cause protection to switch inefficacy because losing message.Simultaneously; it all is to be based upon under the normal operation state of protection passage that present protection is switched; if the protection channel abnormal even working line interrupts, is switched also and can not taken place; and; whether the protection passage is unusual, judged by the protection controller, if judge this moment unusual; even the protection passage is normal, switches also and can not take place.For the business of runing,, be exactly very serious fault if interrupt.
Summary of the invention
At professional owing to a variety of causes can't realize successfully that the problem of switching proposes the present invention in the correlation technique, for this reason, the method and system that provide a kind of improved realization protection group protection to switch are provided main purpose of the present invention, one of to address the above problem at least.
According to an aspect of the present invention, provide a kind of method that realizes that the protection of protection group is switched.
The method that protection is switched according to realization protection group according to the present invention comprises: network management system receive the protection controller the protection group is protected switch after the PSE Protection Switch Event of transmission; According to PSE Protection Switch Event verification protection group whether all protection switch successfully; If there are not whole successful execution, then notice protection controller protection group that successful execution protection is not switched repeats the protection switching operation.
According to a further aspect in the invention, provide a kind of system that realizes that the protection of protection group is switched.
The system that realization protection group protection according to the present invention is switched comprises: the protection controller, be used for after protection group execute protection is switched, send PSE Protection Switch Event to network management system, receive the protection group that the notice that comes from network management system switches successful execution protection not and repeat the protection switching operation; Network management system is used for whether whole successful execution protection is switched according to the PSE Protection Switch Event verification protection group that receives, if there are not whole successful execution, then sends notice to the protection controller.
By the present invention; if operating path (passage) interrupts, can switch according to the professional situation of protection, switch finish after; network management system can protect group to switch verification according to the PSE Protection Switch Event that reports, and protects after verification is finished and switches processing.Solve professional because a variety of causes in the correlation technique and can't successfully realize the problem of switching, and then can effectively improve the success rate that the protection of protection group is switched.
Other features and advantages of the present invention will be set forth in the following description, and, partly from specification, become apparent, perhaps understand by implementing the present invention.Purpose of the present invention and other advantages can realize and obtain by specifically noted structure in the specification of being write, claims and accompanying drawing.
Description of drawings
Accompanying drawing described herein is used to provide further understanding of the present invention, constitutes the application's a part, and illustrative examples of the present invention and explanation thereof are used to explain the present invention, do not constitute improper qualification of the present invention.In the accompanying drawings:
The flow chart that Fig. 1 switches for optical network system protection in the correlation technique;
The flow chart of the method that Fig. 2 switches for the protection according to the realization protection group of the embodiment of the invention;
Fig. 3 is the flow chart according to the network management system monitoring and protecting path of the embodiment of the invention;
Fig. 4 is for realizing the flow chart of the method that the protection of protection group is switched according to the preferred embodiment of the invention;
The structured flowchart of the system that Fig. 5 switches for the protection according to the realization protection group of the embodiment of the invention;
Fig. 6 is for realizing the structured flowchart of the system that the protection of protection group is switched according to the preferred embodiment of the invention;
Fig. 7 is the schematic diagram of the related subsystem of service protection of the network management system of example according to the present invention.
Embodiment
Need to prove that under the situation of not conflicting, embodiment and the feature among the embodiment among the application can make up mutually.Describe the present invention below with reference to the accompanying drawings and in conjunction with the embodiments in detail.
Along with the development of optical communication technique, the equipment network mode is complicated day by day flexibly, and common optical-fiber network is by optical network management system and optical network device.In the correlation technique, optical network management system and optical network device all provide defencive function, realize various types of protection operational modes.In the system that is made up of protection controller and network management system, the protection controller is switched the protection group execute protection that needs execute protection and switch, and still, is not that all protections are organized the protection of whole successful execution and switched.
The flow chart of the method that Fig. 2 switches for the protection according to the realization protection group of the embodiment of the invention.This method mainly comprises following processing:
Step S202: network management system receive the protection controller the protection group is protected switch after the PSE Protection Switch Event of transmission;
Step S204: according to PSE Protection Switch Event verification protection group whether all protection switch successfully;
Step S206: if there are not whole successful execution, then notice protection controller protection group that successful execution protection is not switched repeats the protection switching operation.
In the correlation technique; after protection controller execute protection is switched; the result is not switched in protection and carry out verification; and protect once more and switch; and in the present embodiment for whether all protection switch success and carried out verification, thereby solved the problem that protection group that correlation technique switches for successful execution protection not can not correctly start protection.Adopt the method for the embodiment of the invention, can effectively improve the success rate that the protection of protection group is switched, and can reduce O﹠M personnel's the upkeep operation time effectively.
Preferably, above-mentioned steps S204 may further include following processing:
(1) network management system is determined the protection group number that needs execute protection to switch;
(2) network management system judges whether the PSE Protection Switch Event number that reports is consistent with protection group number;
(3) if then network management system determines that protection organizes the protection of whole successful execution and switch;
(4) otherwise, then network management system determines that the protection group does not have the protection of whole successful execution to switch.
In preferred implementation process, the whole protection group execute protection switching operations of protection controller to needing execute protection to switch, and the protection group is switched success or not put down in writing with the daily record form.The protection group that the successful execution protection is switched is sent to network management system with the PSE Protection Switch Event form.Network management system is determined all protection groups according to the PSE Protection Switch Event of protection controller report, and whether whole successful execution protection is switched.
By above-mentioned processing, network management system is carried out verification to the protection group after switching, and can determine not switch the protection group of success, thereby for follow-up switching provides foundation, has reached the effect of automatic detection protection group switch status.
Preferably, before network management system need to determine protection group number that execute protection switches, can also comprise following processing:
(1) calculates each professional transmission path;
(2) calculate the veneer port that is associated in the transmission path;
(3) veneer port and protection group are mated, determine the protection group that to switch when each veneer port breaks down.
In preferred implementation process; the protection group that need switch when network management system needs in advance definite each veneer port to break down promptly needs to generate the condition that many protections group is switched simultaneously, that is to say; when certain port triggering is switched, should there be what protection groups to switch simultaneously simultaneously.
By above-mentioned processing, can judge current which protection group and should switch, thereby can determine whether the protection group has all been carried out protection and switched, effectively improved the success rate that the protection of protection group is switched.
Preferably, in the check results of execution in step S204 for being that then network management system directly is back to user side with check results.
By above-mentioned processing, can the real-time prompting user protect the state of switching, thereby can improve user experience.
Preferably, above-mentioned steps S206 may further include following processing:
(1) the protection controller receives the protection group id that the not successful execution protection come from network management system is switched;
(2) the protection controller carries out verification to the protection group of protection group id correspondence, and check results is fed back to network management system to generate daily record;
(3) the protection group execute protection switching operation of protection controller to confirming that not successful execution protection is switched.
In preferred implementation process, two kinds of implementations can be arranged, first kind of scheme is: after the network management system verification, directly notice protection controller protection group that successful execution protection is not switched repeats the protection switching operation.Wherein, the successful execution protection protection group of switching not is to obtain (specifically can referring to above-mentioned steps S202-step S206) after the network management system verification.
Second kind of scheme is: after the network management system verification; the protection group id that the protection of successful execution is not switched is sent to the protection controller; the protection controller is carrying out the verification second time to the protection group of these protection group id correspondences, and the protection group execute protection switching operation to confirming that not successful execution protection is switched.For example, network management system verification for the first time have protection group 1, protection group 3, protection group 4 not the successful execution protection switch, then the identification information with protection group 1, protection group 3, protection group 4 is sent to the protection controller, the protection controller carries out the verification second time to protection group 1, protection group 3, protection group 4, perhaps twice check results is identical, then protects controller that 4 execute protection switching operations are organized in protection group 1, protection group 3, protection; Perhaps twice check results difference after the verification of protection controller, has only not successful execution protection switching operation of protection group 1, protection group 3, then protects controller that 3 execute protections are organized in protection group 1, protection and switches.
By the interaction process of network management system with the protection controller, carry out twice verification, the accuracy of verification can be improved, thereby the operating efficiency that follow-up execute protection is switched can be improved.
Preferably, before execution in step S206, can also comprise following processing:
(1) network management system detects the alarm status in protection path every predetermined amount of time;
(2) after each the detection, network management system notice protection controller detects the alarm status in protection path;
(3) protect the testing result of controller inconsistent if NMS is unified, then network management system generates the inconsistent prompting incident of alarm status;
(4) if the testing result unanimity that NMS is unified and protected controller, the then alarm status in network management system record protection path;
(5) network management system is determined the protection path of can execute protection switching according to testing result.
By above-mentioned processing; network management system and the state of protecting controller real-time monitoring and protecting group middle controller veneer and service board; the running status that guarantees the controller veneer is consistent with single board state; determine the protection path of can execute protection switching further to improve protection by this scheme and to switch success rate.
Further describe above-mentioned preferred embodiment below in conjunction with Fig. 3.
Fig. 3 is the flow chart according to the network management system monitoring and protecting path of the embodiment of the invention.This monitoring flow process can comprise following processing:
Step S302: the current protection group that disposes of equipment, business to be protected, network management system can regularly be monitored the protection path, and simultaneously the protection controller is monitored;
Step S304: the alarm status in network management system periodic monitor protection path, and synchronously alarm status information is notified to the protection controller and carries out the secondary verification;
Step S306: if protect the path with nowhere to turn to the police, and the testing result of network management system is consistent with protection controller testing result, and then webmaster record protection path in daily record is normal;
Step S308: if protect the path with nowhere to turn to the police, but the result that network management system is monitored is inconsistent with protection monitoring control devices result, and then webmaster produces event prompt network management protection state and protects controller state inconsistent;
Step S310: if there is alarm in the protection path, and the testing result of network management system is consistent with the testing result of protection controller, and then webmaster provides event prompt according to the alarm that reports and protects the path unusual.
Step S312: if there is alarm in the protection path; but the result of network management system monitoring is inconsistent with protection monitoring control devices result; then to produce event prompt network management protection state inconsistent and the protection path status is unusual with the protection controller state for webmaster, points out current alarm status simultaneously.
By above-mentioned processing, the state of monitoring and protecting group middle controller veneer and service board can guarantee that the running status of controller veneer is consistent with single board state in real time.Determine which protection path can switch by execute protection, thereby can improve the protection success rate of switching, and can effectively reduce O﹠M personnel's the upkeep operation time.
Fig. 4 is for realizing the flow chart of the method that the protection of protection group is switched according to the preferred embodiment of the invention.This method comprises following processing:
Step S402: if Working service interrupts, can switch, if the protection channel abnormal is not then switched according to the professional situation of protection;
Step S404:, then switch and report the incident of switching if the protection passage is normal;
Step S406: switch finish after, network management system protects group to switch verification according to the PSE Protection Switch Event that reports;
Step S408: if the protection group is all normally switched, then direct log of network management system and real-time display result are by the user;
Step S410: switch if also have protection to organize not successful execution protection, then network management system offers the protection controller with unusual protection group information, carries out secondary by the protection controller and switches verification;
Step S412: after the verification of protection controller is finished, report relevant information to give network management system, and generate the log record check results by network management system.
Step S414: the protection group execute protection switching operation that the protection controller is switched the not successful execution protection of confirming.
Wherein, checking procedure is the switch status of verification protection group not only, also will carry out and protect the mutual of controller.Hence one can see that, and present embodiment adopts above-mentioned second kind of scheme.Adopt second kind of scheme; can improve the verification correctness; because network management system is to carry out verification according to the PSE Protection Switch Event that the protection controller is uploaded; in the process that has a plurality of protection groups to switch simultaneously; system works efficient is lower; may lose message in upload procedure, therefore in the case, the verification accuracy of network management system may be not high.
In preferred implementation process; after step S414; the situation that may still exist the protection group successfully not switch; at this moment; can point out the user to carry out associative operation; also can continue the protection group of successfully not switching protected and switch, perhaps send PSE Protection Switch Event to network management system, the operation that repeats verification and switch.Specifically can according to circumstances decide.
In order to help to understand above preferred embodiment of the present invention, further describe two embodiment of the present invention below, the inventor is through test, and discovery has obtained good effect.
Embodiment one
(1) work at present business and protection business are moved; the professional state of webmaster (being network management system) periodic monitor protection; and synchronously carry out communication with the protection controller, guarantee the detected protection service condition of webmaster and protect the detected protection service condition of controller in full accord.
(2) if testing result is in full accord, and protection is professional normal, and then network management system does not have any prompting.
(3) if testing result is in full accord, but protect service exception, then network management system is shown to the user in real time with abnormal information.
(4) if testing result is inconsistent, then network management system is shown to the user in real time with the form that inconsistent information generates contrast.
Alternately the protection path is monitored by network management system and protection controller; the state of monitoring and protecting group middle controller veneer and service board in real time; the running status that guarantees the controller veneer is consistent with single board state; and can present the protection service condition in real time to the user; be convenient to the user and carry out subsequent treatment, better user experience.
Embodiment two
The operating path of (1) three protection group is through the same line road; this moment line interruption, the protection controller triggers to be switched and reports the incident of switching to give network management system, after network management system is received the incident of switching; judge the line interruption point, and calculate and to switch three protection groups this moment.
(2) if this moment three protection groups all report the incident of switching, think that then the protection group all normally switches, in real time the result is shown to the user.
(3) if this moment, three protection groups had one or more incidents of switching that do not report, network management system notice protection controller carries out secondary check and secondary switching operation to the protection group of not switching.
(4) if after secondary was switched, all protection groups were all successfully switched, and then in real time the result are shown to the user.
(5) if after secondary is switched, still have the protection group successfully not switch, then point out the user to carry out associative operation.
By twice verification of network management system with the protection controller, whether can judging current which protection group, should to switch and detect protection group switch status normal, reached the effect of automatic detection protection group switch status.Thereby can guarantee to protect the correct generation of switching, improve the success rate that the protection of protection group is switched, and can reduce O﹠M personnel's the upkeep operation time effectively.
The structured flowchart of the system that Fig. 5 switches for the protection according to the realization protection group of the embodiment of the invention.As shown in Figure 5, this system comprises with lower device: protection controller 50, network management system 52.
Protection controller 50 is used for after protection group execute protection is switched, and sends PSE Protection Switch Event to network management system, receives the protection group that the notice that comes from network management system switches successful execution protection not and repeats the protection switching operation;
Network management system 52 is used for whether whole successful execution protection is switched according to the PSE Protection Switch Event verification protection group that receives, if there are not whole successful execution, then sends notice to the protection controller.
Adopt the device of the embodiment of the invention, can effectively improve the success rate that the protection of protection group is switched, and can effectively reduce O﹠M personnel's the upkeep operation time.
Preferably, as shown in Figure 6, network management system 52 may further include: determine device 520, be used to determine the protection group number that needs execute protection to switch; Judgment means 524 is used to judge whether the PSE Protection Switch Event number that reports is consistent with protection group number.
In preferred implementation process, when certain veneer port of operating path broke down, what protection groups are network management system need calculate needed execute protection to switch.
By above-mentioned processing, determine that device 520 can current which protection group should switch, judgment means 524 can reach the effect of automatic detection protection group switch status.
Preferably, as shown in Figure 6, network management system 52 can also comprise: service path calculation element 526 is used to calculate each professional transmission path; The related calculation element 528 of service path is used for calculating the veneer port that transmission path is associated; Many protections group synchronous switching calculation element 530 is used for veneer port and protection group are mated, and determines the protection group that need switch when each veneer port breaks down; Event prompting device 532 is used for the result of calculation of the related calculation element 528 of real-time display business path calculation device 526, service path and many protections group synchronous switching calculation element 530.
Wherein, service path calculation element 526, the related calculation element 528 of service path, many protections group synchronous switching calculation element 530, event prompting device 532 and many protections group synchronous switching device 542 (be equivalent to protection and switch final controlling element 506) can be formed the related subsystem of service protection of network management system, and the related subsystem of this service protection specifically can be referring to Fig. 7.
By above-mentioned processing, can judge current which protection group and should switch, thereby can determine whether the protection group has all been carried out protection and switched, effectively improved the success rate that the protection of protection group is switched.
Preferably, as shown in Figure 6, network management system 52 can also comprise: dispensing device 534 is used for when all successful execution protection has been switched, directly check results being back to user side in definite protection group.
By above-mentioned processing, can the real-time prompting user protect the state of switching, thereby can improve user experience.
Preferably, as shown in Figure 6, protection controller 50 can comprise: receiving system 500, be used for when network management system is determined the protection group all the successful execution protection is not switched, and receive the protection group id that the not successful execution protection that comes from network management system is switched; Calibration equipment 502 is used for the protection group of protection group id correspondence is carried out verification; Feedback device 504 is used for the check results of calibration equipment is fed back to network management system to generate daily record; Final controlling element 506 is switched in protection, is used for the protection group execute protection switching operation to confirming that not successful execution protection is switched.
In preferred implementation process, if the protection group is all normally switched, then direct log of network management system and real-time display result are by the user; In said method; if existing, the protection group switches unusually; then network management system offers the protection controller with unusual protection group information; carry out secondary by the protection controller and switch verification; after the verification of protection controller is finished; report relevant information to give network management system, and generate the log record check results by network management system.Above-mentioned processing specifically can be referring to above-mentioned second kind of scheme.
By the interaction process (promptly by second kind scheme handle) of network management system with the protection controller, carry out twice verification, the accuracy of verification can be improved, thereby the operating efficiency that follow-up execute protection is switched can be improved.
Preferably, as shown in Figure 6, network management system 52 can also comprise: checkout gear 536 is used for the alarm status every predetermined amount of time verification protection path; Notifying device 538 is used for after each the detection, and notice protection controller detects the alarm status in protection path; Processing unit 540, be used for unifying the testing result of protecting controller when inconsistent at NMS, produce the inconsistent prompting incident of alarm status, when NMS is unified the testing result unanimity of protecting controller, the alarm status in record protection path, and determine the protection path of can execute protection switching according to testing result; Then protect controller 50, also be used for after the notice that receives the notifying device transmission, detecting the alarm status in protection path.
In preferred implementation process, checkout gear 536, notifying device 538, processing unit 540 can be formed the protection path detection subsystem of network management system, and the working method of this protection path detection subsystem can be referring to describing among Fig. 4.
By above-mentioned processing; network management system and the state of protecting controller real-time monitoring and protecting group middle controller veneer and service board; the running status that guarantees the controller veneer is consistent with single board state; determine the protection path of can execute protection switching further to improve protection by this scheme and to switch success rate.
The working method that each device mutually combines in the said system specifically can repeat no more referring to the description of Fig. 2 to Fig. 4 herein.
In sum, by the above embodiment of the present invention, the scheme that the realization protection group protection that provides is switched, the state of monitoring and protecting group middle controller veneer and service board can guarantee that the running status of controller veneer is consistent with single board state in real time; Simultaneously, switch when taking place when protection, whether can judging current which protection group, should to switch and detect protection group switch status normal, reached the effect of automatic detection protection group switch status.Thereby can guarantee to protect the correct generation of switching, improve the success rate that the protection of protection group is switched, and can effectively reduce O﹠M personnel's the upkeep operation time.
Obviously, those skilled in the art should be understood that, above-mentioned each module of the present invention or each step can realize with the general calculation device, they can concentrate on the single calculation element, perhaps be distributed on the network that a plurality of calculation element forms, alternatively, they can be realized with the executable program code of calculation element, thereby, they can be stored in the storage device and carry out by calculation element, perhaps they are made into each integrated circuit modules respectively, perhaps a plurality of modules in them or step are made into the single integrated circuit module and realize.Like this, the present invention is not restricted to any specific hardware and software combination.
The above is the preferred embodiments of the present invention only, is not limited to the present invention, and for a person skilled in the art, the present invention can have various changes and variation.Within the spirit and principles in the present invention all, any modification of being done, be equal to replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. a method that realizes that the protection of protection group is switched is characterized in that, comprising:
Network management system receive the protection controller the protection group is protected switch after the PSE Protection Switch Event of transmission;
According to the described protection group of described PSE Protection Switch Event verification whether all protection switch successfully;
If there are not whole successful execution, then notify the described protection controller protection group that protection is switched to successful execution not to repeat the protection switching operation.
2. method according to claim 1 is characterized in that, described network management system according to the described protection group of described PSE Protection Switch Event verification whether all the successful execution protection switch and comprise:
Described network management system is determined the protection group number that needs execute protection to switch;
Described network management system judges whether the described PSE Protection Switch Event number that reports is consistent with described protection group number;
If then described network management system determines that described protection organizes the protection of whole successful execution and switch;
Otherwise then described network management system determines that described protection group does not have whole successful execution protections to switch.
3. method according to claim 2 is characterized in that, before described network management system need to determine protection group number that execute protection switches, also comprises:
Calculate each professional transmission path;
Calculate the veneer port that is associated in the described transmission path;
Described veneer port and protection group are mated, determine the protection group that to switch when each described veneer port breaks down.
4. method according to claim 1 is characterized in that, the described protection controller protection group execute protection switching operation that protection is switched to successful execution not comprises:
The protection group id that the not successful execution protection that described protection controller reception comes from described network management system is switched;
Described protection controller carries out verification to the protection group of described protection group id correspondence, and check results is fed back to described network management system to generate daily record;
The protection group execute protection switching operation of described protection controller to confirming that not successful execution protection is switched.
5. according to claim 1 or 4 described methods, it is characterized in that, before described protection controller execute protection switching operation, also comprise:
Described network management system detects the alarm status in protection path every predetermined amount of time;
After each the detection, described network management system notifies described protection controller to detect the alarm status in described protection path;
The testing result of described protection controller is inconsistent if described NMS is unified, and then described network management system generates the inconsistent prompting incident of alarm status;
The testing result unanimity of described protection controller if described NMS is unified, then described network management system writes down the alarm status in described protection path;
Described network management system is determined the protection path of can execute protection switching according to described testing result.
6. a system that realizes that the protection of protection group is switched is characterized in that, comprising:
The protection controller is used for after protection group execute protection is switched, and sends PSE Protection Switch Event to described network management system, receives the protection group that the notice that comes from described network management system switches successful execution protection not and repeats the protection switching operation;
Network management system is used for whether whole successful execution protection is switched according to the described protection group of described PSE Protection Switch Event verification that receives, if there are not whole successful execution, then sends described notice to described protection controller.
7. system according to claim 6 is characterized in that, described network management system comprises:
Determine device, be used to determine the protection group number that needs execute protection to switch;
Judgment means is used to judge whether the described PSE Protection Switch Event number that reports is consistent with described protection group number.
8. system according to claim 7 is characterized in that, described network management system also comprises:
The service path calculation element is used to calculate each professional transmission path;
The related calculation element of service path is used for calculating the veneer port that described transmission path is associated;
Many protections group synchronous switching calculation element is used for described veneer port and protection group are mated, and determines the protection group that need switch when each described veneer port breaks down;
Event prompting device is used for showing in real time the result of calculation of described service path calculation element, the related calculation element of described service path and described many protections group synchronous switching calculation element.
9. system according to claim 6 is characterized in that, described protection controller comprises:
Receiving system is used for when described network management system is determined described protection group all the successful execution protection is not switched, and receives the protection group id that the not successful execution protection that comes from described network management system is switched;
Calibration equipment is used for the protection group of described protection group id correspondence is carried out verification;
Feedback device is used for the check results of described calibration equipment is fed back to described network management system to generate daily record;
Final controlling element is switched in protection, is used for the protection group execute protection switching operation to confirming that not successful execution protection is switched.
10. according to each described system in the claim 6 to 9, it is characterized in that,
Described network management system comprises:
Checkout gear is used for the alarm status every predetermined amount of time verification protection path;
Notifying device is used for notifying described protection controller to detect the alarm status in described protection path after each the detection;
Processing unit, be used for unifying the testing result of described protection controller when inconsistent at described NMS, produce the inconsistent prompting incident of alarm status, unify the testing result of described protection controller when consistent at described NMS, write down the alarm status in described protection path, and determine the protection path of can execute protection switching according to described testing result;
Described protection controller also is used for detecting the alarm status in described protection path after the notice that receives described notifying device transmission.
CN201010149574A 2010-03-17 2010-03-17 Method and system for realizing protection switching (PS) of protection groups Pending CN101820317A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201010149574A CN101820317A (en) 2010-03-17 2010-03-17 Method and system for realizing protection switching (PS) of protection groups
PCT/CN2010/077495 WO2011113272A1 (en) 2010-03-17 2010-09-29 Method and system for implementing protection switching of protection groups

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010149574A CN101820317A (en) 2010-03-17 2010-03-17 Method and system for realizing protection switching (PS) of protection groups

Publications (1)

Publication Number Publication Date
CN101820317A true CN101820317A (en) 2010-09-01

Family

ID=42655275

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010149574A Pending CN101820317A (en) 2010-03-17 2010-03-17 Method and system for realizing protection switching (PS) of protection groups

Country Status (2)

Country Link
CN (1) CN101820317A (en)
WO (1) WO2011113272A1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011113272A1 (en) * 2010-03-17 2011-09-22 中兴通讯股份有限公司 Method and system for implementing protection switching of protection groups
CN102820981A (en) * 2011-06-08 2012-12-12 中兴通讯股份有限公司 Single board switching method and protective single board
CN103973359A (en) * 2014-04-16 2014-08-06 烽火通信科技股份有限公司 OTN protection switching automation testing system, method and device
EP2892180A4 (en) * 2012-09-26 2015-12-09 Huawei Tech Co Ltd Service traffic protection method and apparatus

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115174363B (en) * 2022-07-05 2024-04-12 云合智网(上海)技术有限公司 Multi-protection group set fast switching method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5930232A (en) * 1996-03-01 1999-07-27 Alcatel Network Systems, Inc. Method and system for implementing a protection switching protocol
CN101102521A (en) * 2006-07-03 2008-01-09 华为技术有限公司 A method for service protection in automatically switching optical network
CN101309300A (en) * 2008-06-26 2008-11-19 华为技术有限公司 Path switching control method and system in multipath storage system
US20090154337A1 (en) * 2007-12-12 2009-06-18 Electronics And Telecommunications Research Institute Protection switching method based on change in link status in ethernet link aggregation sublayer

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101820317A (en) * 2010-03-17 2010-09-01 中兴通讯股份有限公司 Method and system for realizing protection switching (PS) of protection groups

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5930232A (en) * 1996-03-01 1999-07-27 Alcatel Network Systems, Inc. Method and system for implementing a protection switching protocol
CN101102521A (en) * 2006-07-03 2008-01-09 华为技术有限公司 A method for service protection in automatically switching optical network
US20090154337A1 (en) * 2007-12-12 2009-06-18 Electronics And Telecommunications Research Institute Protection switching method based on change in link status in ethernet link aggregation sublayer
CN101309300A (en) * 2008-06-26 2008-11-19 华为技术有限公司 Path switching control method and system in multipath storage system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011113272A1 (en) * 2010-03-17 2011-09-22 中兴通讯股份有限公司 Method and system for implementing protection switching of protection groups
CN102820981A (en) * 2011-06-08 2012-12-12 中兴通讯股份有限公司 Single board switching method and protective single board
EP2892180A4 (en) * 2012-09-26 2015-12-09 Huawei Tech Co Ltd Service traffic protection method and apparatus
CN103973359A (en) * 2014-04-16 2014-08-06 烽火通信科技股份有限公司 OTN protection switching automation testing system, method and device
CN103973359B (en) * 2014-04-16 2016-05-25 烽火通信科技股份有限公司 Automatization test system, method and device are switched in a kind of OTN protection

Also Published As

Publication number Publication date
WO2011113272A1 (en) 2011-09-22

Similar Documents

Publication Publication Date Title
CN101800675B (en) Failure monitoring method, monitoring equipment and communication system
US8112521B2 (en) Method and system for security maintenance in a network
CN104301136A (en) Method and equipment for reporting and processing fault information
CN102571457B (en) A kind of method, bypass equipment changing method and device triggering bypass equipment and switch
CN101820317A (en) Method and system for realizing protection switching (PS) of protection groups
CN104065526B (en) A kind of method and apparatus of server failure alarm
CN102571492B (en) Method and device for detecting failure of routing equipment
CN104678850B (en) A kind of method of vehicle mounted communication device intelligence self diagnosis
CN102025562A (en) Path detection method and device
CN101777951B (en) Method and system for data monitoring
CN109491304A (en) A kind of control system automatic failure detection circuit and fault self-detection method
CN105223949A (en) Electric equipment and communication failure diagnostic method thereof and device
CN103763127A (en) Device state alarm monitoring method and system
CN103139033A (en) Primary device redundancy switching method of single main communication control bus
CN103810076A (en) Monitoring method and device for data reproduction
CN101989933A (en) Method and system for failure detection
CN107688547B (en) Method and system for switching between main controller and standby controller
CN103188113A (en) Failure processing method of communication equipment
CN101924661A (en) Alarm processing method and device
CN109361672A (en) A kind of the data back transmission method and system of safety insulating device
CN111030871A (en) Configuration information synchronization method and device based on dual-computer hot standby system
CN103457755A (en) IEC 61850 system communication fault detection method and system
CN102340407B (en) Protection switching method and system
CN104348676A (en) Link detection method and device based on operation administration and maintenance
KR101639713B1 (en) Outage-management system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20100901