CN101742576A - Method and device for recovering reserved GBR load - Google Patents

Method and device for recovering reserved GBR load Download PDF

Info

Publication number
CN101742576A
CN101742576A CN200810225719A CN200810225719A CN101742576A CN 101742576 A CN101742576 A CN 101742576A CN 200810225719 A CN200810225719 A CN 200810225719A CN 200810225719 A CN200810225719 A CN 200810225719A CN 101742576 A CN101742576 A CN 101742576A
Authority
CN
China
Prior art keywords
reserved gbr
gbr load
message
bearing
quality
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200810225719A
Other languages
Chinese (zh)
Other versions
CN101742576B (en
Inventor
陆伟
胡伟华
周汉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei Technologies Co Ltd
Original Assignee
Huawei Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei Technologies Co Ltd filed Critical Huawei Technologies Co Ltd
Priority to CN 200810225719 priority Critical patent/CN101742576B/en
Publication of CN101742576A publication Critical patent/CN101742576A/en
Application granted granted Critical
Publication of CN101742576B publication Critical patent/CN101742576B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mobile Radio Communication Systems (AREA)

Abstract

The embodiment of the invention provides a method and a device for recovering a reserved GBR load. The method comprises that: an MME receives message related to a terminal; after determining to recover the reserved GBR load of the terminal, the MME sends first indication message which carries information for recovering the reserved GBR load to a PDN GW to indicate the PDN GW to recover a core network side load corresponding to the reserved GBR load; and the MME sends second indication message which carries service quality information to a base station to indicate the base station to recover an S1 interface load and a wireless side load corresponding to the reserved GBR load according to the service quality information. The embodiment of the invention can successfully recover the reserved GBR load, and meets the requirement of receiving the reserved GBR load.

Description

Recover the method and the device of reserved GBR load
Technical field
The present invention relates to the network communications technology field, be specifically related to recover method, mobile management network element, grouped data network gateway and the terminal equipment of reserved GBR load.
Background technology
In the UMTS Terrestrial radio access network (E-UTRAN) of UMTS Terrestrial radio access network (UTRAN) and evolution, can exist and be in the GBR carrying that keeps attitude, as in E-UTRAN, because user's inactivity (User inactivity) causes the S1 interface to discharge, make the GBR carrying be in the reservation attitude; For another example, in UTRAN,, the Iu interface make the conversation class and the GBR carrying of stream class be in the reservation attitude because discharging.
In present practical application, there is the demand of recovering to be in reserved GBR load, yet, how to make to be in the GBR carrying recovery that keeps attitude, do not have clear and definite regulation at present.
How recovering to be in the GBR carrying that keeps attitude is a technical problem that needs to be resolved hurrily.
Summary of the invention
Embodiment of the present invention provides method and the device that recovers reserved GBR load, can successfully recover to be in the GBR carrying that keeps attitude.
A kind of method of recovering reserved GBR load that embodiment of the present invention provides comprises:
Mobile management network element MME receives the message relevant with terminal;
After described MME determines and need recover the reserved GBR load of described terminal, send first Indication message that carries recovery reserved GBR load information to grouped data network gateway PDNGW, recover the core-network side carrying of this reserved GBR load correspondence with indication PDN GW, described MME sends second Indication message that carries quality of service information to the base station, recovers the S1 interface bearing and the wireless side carrying of this reserved GBR load correspondence according to described quality of service information with the indication base station.
Embodiment of the present invention also provides a kind of method of recovering reserved GBR load, comprising:
PDN GW receives the request bearing resource and revises message, and the described request bearing resource is revised message and revised message for the request bearing resource that transmits owing to terminal triggering bearing resource modification process;
After described PDN GW revises message and determines needs the reserved GBR load of described terminal is recovered according to the described request bearing resource, determine the quality of service information of described reserved GBR load, and trigger to revise the dedicated bearing modification process of service quality, with core-network side carrying and the S1 interface bearing and the wireless side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
Embodiment of the present invention also provides a kind of method of recovering reserved GBR load, comprising:
The downlink data packet of PDN GW receiving terminal;
After described PDN GW determines the reserved GBR load that is carried as described terminal of this downlink data packet correspondence, determine the quality of service information of described reserved GBR load, and trigger to revise the dedicated bearing modification process of service quality, with core-network side carrying and the S1 interface bearing and the wireless side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
The mobile management network element that embodiment of the present invention provides comprises:
First receiver module is used to receive the message relevant with terminal;
First recovers judge module, is used to judge whether and need the reserved GBR load of described terminal be recovered;
First recovers module, be used for first recover judge module determine need recover the reserved GBR load of described terminal after, send first Indication message that carries recovery reserved GBR load information to PDN GW, recover the core-network side carrying of this reserved GBR load correspondence with indication PDN GW, and send second Indication message carry quality of service information to the base station, recover the S1 interface bearing and the wireless side carrying of this reserved GBR load correspondence according to described quality of service information with the indication base station.
The another kind of grouped data network gateway that the embodiment of the invention provides comprises:
Second receiver module is used to receive bearing resource and revises message, and described bearing resource is revised the bearing resource modification message that message is transmitted for trigger the bearing resource modification process owing to terminal;
Second recovers judge module, is used for revising message according to described bearing resource and judges whether that needs recover the reserved GBR load of described terminal;
Second recovers module, be used for second recover judge module determine need recover the reserved GBR load of described terminal after, trigger to revise the dedicated bearing modification process of service quality, with core-network side carrying and the S1 interface bearing and the wireless side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
The another kind of grouped data network gateway that the embodiment of the invention provides comprises:
The 3rd receiver module is used for the downlink data packet of receiving terminal;
The 3rd recovers judge module, is used to judge whether the carrying of described downlink data packet correspondence is the reserved GBR load of described terminal;
The 3rd recovers module, be used for after described the 3rd recovery judge module is determined the reserved GBR load that is carried as described terminal of this downlink data packet correspondence, trigger to revise the dedicated bearing modification process of service quality, with core-network side carrying and the S1 interface bearing and the wireless side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
The another kind of grouped data network gateway that the embodiment of the invention provides comprises:
The 4th receiver module is used to receive first Indication message that carries recovery reserved GBR load information that MME sends;
The 4th recovers module, be used for after the 4th receiver module receives described first Indication message, determine the quality of service information of described reserved GBR load, and recover the maximum rate of the core-network side carrying of described reserved GBR load correspondence according to described definite quality of service information.
The terminal equipment that the embodiment of the invention provides comprises:
The message constructing module is used for carrying the information relevant with recovering reserved GBR load in message;
Sending module is used to send the described message that carries the information relevant with recovering reserved GBR load.
Description by technique scheme as can be known, the embodiment of the invention provides the technical scheme of multiple recovery reserved GBR load, has successfully recovered to be in the GBR carrying that keeps attitude.
Description of drawings
Fig. 1 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention one;
Fig. 2 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention two;
Fig. 3 a is the method flow diagram one of the recovery reserved GBR load of the embodiment of the invention three;
Fig. 3 b is the method flow diagram two of the recovery reserved GBR load of the embodiment of the invention three;
Fig. 4 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention four;
Fig. 5 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention five;
Fig. 6 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention six;
Fig. 7 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention seven;
Fig. 8 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention eight;
Fig. 9 a is the method flow diagram one of the recovery reserved GBR load of the embodiment of the invention nine;
Fig. 9 b is the method flow diagram two of the recovery reserved GBR load of the embodiment of the invention nine;
Figure 10 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention ten;
Figure 11 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention 11;
Figure 12 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention 12;
Figure 13 is the method flow diagram of the recovery reserved GBR load of the embodiment of the invention 13;
Figure 14 a is the mobile management network element structural representation one of the embodiment of the invention 14;
Figure 14 b is the mobile management network element structural representation two of the embodiment of the invention 14;
Figure 15 is the grouped data network gateway structural representation of the embodiment of the invention 15;
Figure 16 is the grouped data network gateway structural representation of the embodiment of the invention 16;
Figure 17 a is the grouped data network gateway structural representation one of the embodiment of the invention 17;
Figure 17 b is the grouped data network gateway structural representation two of the embodiment of the invention 18;
Figure 18 is the terminal equipment structural representation of the embodiment of the invention 19.
Embodiment
Below in conjunction with accompanying drawing the technical scheme that the embodiment of the invention provides is described.
Embodiment one, and the method for recovery reserved GBR load as shown in Figure 1.
Step 1, MME receive the message relevant with terminal.
The message relevant with terminal that MME receives can be the message that terminal sends, and for example, is in the service request information of the terminal transmission of connected state; Again for example, be in the service request information of the terminal transmission of Idle state; Also have the tracing section updating request message that terminal sends etc.The message that terminal sends can be sent to MME by intermediate equipment such as base station.
The message relevant with terminal that MME receives also can be the message that other network entity sends, for example, in the handoff procedure of terminal, acknowledge message is finished in the switching that switching request acknowledgement message that the target BS that target MME receives sends and source-end networks equipment send.
When the message relevant with terminal is the message of terminal transmission, can carry the information relevant in this message with recovering reserved GBR load.The reserved GBR load tabulation that information relevant with recovering reserved GBR load such as needs recover recovers the information of whole reserved GBR loads etc. for another example.
Step 2, MME determine and need the reserved GBR load of above-mentioned terminal be recovered.
The information that MME carries in can the message relevant with terminal according to its reception is determined needs the reserved GBR load of terminal is recovered; For example, the reserved GBR load tabulation that recovers according to the needs that carry in the message is determined needs the reserved GBR load of terminal is recovered; Again for example, determining needs according to the information of the whole reserved GBR loads of recovery that carry in the message recovers etc. the reserved GBR load of terminal.
MME also can determine and need the reserved GBR load of terminal be recovered when find that there is the GBR carrying that keeps attitude in this terminal; For example, do not carry in the message relevant that receives at MME and recover under the situation of the relevant information of reserved GBR load with terminal, MME finds this terminal and whether has the GBR carrying that keeps attitude, there is the carrying that keeps attitude GBR if find this terminal, then determines and need the reserved GBR load of this terminal be recovered.
Step 3, MME send to PDN GW and carry first Indication message that recovers reserved GBR load information, recover the core-network side carrying of this reserved GBR load correspondence with indication PDN GW; MME sends second Indication message that carries quality of service information to the base station, recovers the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence according to the quality of service information that carries in second Indication message with the indication base station.The wireless side carrying is an empty port load-supporting.
The recovery reserved GBR load information of carrying in above-mentioned first Indication message can be the reserved GBR load sign and the quality of service information that need to recover.When the reserved GBR load of needs recovery was many, the sign and the quality of service information of the reserved GBR load that MME can recover all needs only sent by one first Indication message, also can be by many first Indication messages transmissions.That is to say, article one, can carry an identification information and a quality of service information that needs the reserved GBR load of recovery in first Indication message, at least two reserved GBR loads that need to recover that also can carry in all reserved GBR loads that need recover identify and quality of service information, can also carry all reserved GBR loads that need recover sign and quality of service information.Need to prove, also can not carry quality of service information in above-mentioned first Indication message.
Carry at first Indication message under the situation of quality of service information, MME need obtain the quality of service information of the reserved GBR load that needs recovery earlier, and the mode that MME obtains quality of service information can comprise following two kinds:
Mode one, at E-UTRAN reduce to quality of service information before zero owing to store reserved GBR load speed among the MME, therefore, MME can obtain the quality of service information that needs the reserved GBR load correspondence recovered from its canned data.
Mode two, at UTRAN because MME can receive the PDP Context information that carries quality of service information, therefore, MME can obtain the quality of service information that needs the reserved GBR load correspondence recovered from the PDP Context information that it receives.
First Indication message that MME sends can transfer to PDN GW by the gateway of intermediate equipment such as terminal.Under there was more news in the gateway of terminal, MME can be sent to PDN GW with first Indication message by the gateway after upgrading; For example, the terminal initiating updating of tracking area, the tracing section updating request message that the MME receiving terminal sends by the base station, MME is not selecting under the situation of new gateway for terminal, and MME sends to PDN GW by the current gateway of terminal and carries first Indication message that recovers reserved GBR load information; MME is selecting for terminal under the situation of new gateway, and MME is by carrying first Indication message that recovers reserved GBR load information for the new gateway of selecting of terminal sends to PDN GW.
PDN GW determines the quality of service information of this reserved GBR load after receiving first Indication message, and the maximum rate of reserved GBR load is set according to the quality of service information of determining.It is multiple that PDN GW determines that the mode of the quality of service information of reserved GBR load has, as PDN GW by carrying out the quality of service requirement that information interaction obtains this reserved GBR load with PCRF, and the quality of service information of determining this reserved GBR load according to the quality of service requirement that obtains and current network resources situation; The PDN GW quality of service information requirement of obtaining this reserved GBR load for another example according to local collocation strategy, and require and the current network resources situation is determined the quality of service information of this reserved GBR load according to the quality of service information that obtains; Also have, PDN GW obtains the quality of service information that carries in first Indication message, and determines the quality of service information of this reserved GBR load according to the quality of service information that carries in first Indication message and current network resources situation.Need to prove that PDN GW also can adopt alternate manner to determine the quality of service information of reserved GBR load, the embodiment of the invention does not limit the specific implementation process that PDN GW determines the quality of service information of reserved GBR load.
PDN GW determines the process of quality of service information of reserved GBR load as under the situation about allowing in the real network resource according to the quality of service information that carries in first Indication message and current network resources situation, distribute the quality of service information that is not less than the quality of service information that carries in first Indication message for reserved GBR load; Under the situation that the real network resource allows, distribute the service quality of carrying in first Indication message for reserved GBR load for another example; Also have under the unallowed situation of real network resource, be lower than quality of service information of the quality of service information that carries in first Indication message or the like for reserved GBR load distributes.The embodiment of the invention does not limit PDN GW determines the quality of service information of reserved GBR load according to quality of service information that carries in first Indication message and current network resources situation specific implementation process.
The quality of service information of the reserved GBR load that above-mentioned PDN GW determines can only be maximum rate, certainly, also can comprise maximum rate and other parameter.
PDN GW is after determining the quality of service information of reserved GBR load, according to the core-network side carrying that this quality of service information of determining recovers above-mentioned reserved GBR load correspondence, promptly carry Resources allocation according to the core-network side that this quality of service information of determining is the reserved GBR load correspondence.The core-network side carrying of reserved GBR load correspondence for example, is set according to the maximum rate of determining.
PDN GW returns response message at first Indication message to MME after the core-network side carrying that has recovered the reserved GBR load correspondence.Can carry the quality of service information that PDN GW determines in this response message, the reserved GBR load sign that also can carry the quality of service information that PDNGW determines and successfully recover the core-network side carrying.Need to prove that it can be the quality of service information that MME obtains that above-mentioned MME is sent to the quality of service information that carries in second Indication message of base station from this response message.Certainly, the quality of service information that carries in second Indication message also can be the quality of service information that MME adopts alternate manner to obtain, and for example, target MME is from switching the quality of service information that former end obtains.
In addition, PDN GW is after receiving first Indication message and determining the quality of service information of reserved GBR load, can trigger the dedicated bearing modification process of existing modification service quality according to this quality of service information of determining, thereby utilize this bearing modification flow process to recover the core-network side carrying of above-mentioned reserved GBR load correspondence.No matter terminal is in Idle state, still is in connected state, utilizes the above-mentioned bearing modification flow process that is triggered all can realize the recovery of the core-network side carrying of reserved GBR load correspondence.Utilize the above-mentioned bearing modification flow process that is triggered can also the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence be recovered.The core-network side of utilizing the bearing modification flow process to recover the reserved GBR load correspondence is carried and the specific implementation process of S1 interface bearing and wireless side carrying can be not described in detail at this for existing implementation procedure.Need to prove, if PDN GW triggers the bearing modification flow process, then second Indication message of MME transmission can send to the message base station, that carry quality of service information for MME in the bearing modification flow process, is bearing modification request or the session management request that MME sends in the bearing modification flow process as second Indication message.The quality of service information that carries in second Indication message can only comprise maximum rate, certainly, also can comprise maximum rate and out of Memory.
The base station is behind second Indication message that receives the MME transmission, the reserved GBR load correspondence of exist to need recovering, maximum rate is under the situation of zero S1 interface bearing and wireless side carrying, the base station does not need to carry out the process of setting up of S1 interface bearing and wireless side carrying again, but the maximum rate of S1 interface bearing and wireless side carrying directly is set according to the quality of service information in second Indication message, be nonzero value by zero adjustment directly promptly with the maximum rate of S1 interface bearing and wireless side carrying; Do not exist the reserved GBR load correspondence, maximum rate is under the situation of zero S1 interface bearing and wireless side carrying, the S1 interface bearing of the reserved GBR load correspondence that needs recovery and the process of setting up of wireless side carrying need be carried out in the base station, the maximum rate of S1 interface bearing and wireless side carrying is set according to the quality of service information in second Indication message then, again.
If above-mentioned two kinds of situations all might exist at the place, base station, but only may there be a kind of situation at a concrete reserved GBR load, then the base station is after receiving second Indication message, need judge whether earlier that the reserved GBR load correspondence, successful foundation, the maximum rate that exist needs to recover are zero S1 interface bearing and wireless side carrying, then, carry out corresponding operation according to judged result again.If only there be a kind of in above-mentioned two kinds of situations at base station place, then the base station does not need to carry out above-mentioned deterministic process, but after receiving second Indication message, directly carries out above-mentioned corresponding operation.For example, the S1 interface bearing of the reserved GBR load correspondence of need recovering and wireless side carrying one fix on the base station and receive not carry out before second Indication message and set up operation, then the base station is after receiving second Indication message, directly set up the S1 interface bearing and the wireless side carrying of this reserved GBR load correspondence, and the maximum rate of S1 interface bearing and wireless side carrying is set according to the quality of service information that carries in second Indication message.
When the base station receives second Indication message, successfully set up, maximum rate is that zero S1 interface bearing and wireless side carrying can be: under terminal is in Idle state, MME is after the service request that receives the terminal transmission, and the maximum rate of the reserved GBR load correspondence that the indication base station is set up is zero S1 interface bearing and wireless side carrying.Under terminal was in Idle state, it was zero S1 interface bearing and the specific implementation process of wireless side carrying such as the description among the following embodiment that maximum rate is set up in MME indication base station.
Need to prove that in the description of the foregoing description one, MME can send first Indication message earlier, sends second Indication message again; MME also can send second Indication message earlier, sends first Indication message again.The different sending orders of first Indication message, second Indication message exemplify description in the following embodiments.
From the description of the foregoing description one as can be known, embodiment one triggers the core-network side carrying that PDN GW recovers the reserved GBR load correspondence by MME, and trigger S1 interface bearing and the wireless side carrying that recovers the reserved GBR load correspondence in the base station, thereby successfully recovered reserved GBR load by MME.
Embodiment one has multiple different specific implementation process, is elaborated below in conjunction with several specific implementation processes of accompanying drawing to embodiment one.
Embodiment two, terminal such as UE (subscriber equipment) are in Idle state, the service request procedure that UE initiates under the Idle state earlier makes the state of UE become connected state, then, UE initiates the service request procedure of connected state, recovers the reserved GBR load of UE in the service request procedure of the UE under being in connected state.
The specific implementation process of embodiment two as shown in Figure 2.
Among Fig. 2, step 1, the UE that is in connected state send service request information to MME.Carry cells such as S-TMSI in this service request information.Can also increase in the service request information that UE sends and carry the cell that is used to carry the information relevant with recovering reserved GBR load.The sign of the reserved GBR load that the cell loaded information of this increase can be recovered for needs also can be for recovering the indication information of whole reserved GBR loads.When the cell loaded information that increases during for the sign of the reserved GBR load that needs to recover, this sign can exist with the form of GBR bearing identification tabulation.The indication information that recovers whole reserved GBR loads can be 1 bit indicating bit etc.
Certainly, also can not carry the cell of above-mentioned increase in the service request information that UE sends, in the present embodiment, the cell that service request information is not carried above-mentioned increase can be expressed as the whole reserved GBR loads of requirement recovery in this service request procedure, also can be expressed as in this service request procedure and not require the whole reserved GBR loads of recovery.The implication of the concrete expression of service request information need clearly be stipulated in each network equipment.If in the service request procedure of the terminal that is in connected state, do not require the recovery reserved GBR load, then can in other process, recover reserved GBR load, for example, when UE need utilize the GBR carrying that keeps attitude to carry out business, UE can initiate the bearing resource modification process, to recover reserved GBR load in the bearing resource modification process.UE initiates the bearing resource modification process, and the specific implementation process of recovery reserved GBR load is on the books in other embodiments in this flow process.
Step 2, eNodeB receive the service request information that UE sends, and this service request information is transmitted to MME.
After step 2a, MME received service request information, determining needed to recover reserved GBR load, and then MME sends and upgrades bearing request message (i.e. first Indication message).
MME determines mode that need to recover reserved GBR load to be had multiplely, and when carrying the reserved GBR load tabulation in the service request information that receives at MME, MME determines needs to recover reserved GBR load; Carry the indication information that recovers whole reserved GBR loads and this indication information for another example when representing that needs recover reserved GBR load in the service request information that MME receives, MME determines needs the recovery reserved GBR load; Also have, not carrying the information representation relevant with recovering reserved GBR load in MME in the default service requests message recovers under the situation of whole reserved GBR loads, after MME receives the service request information of not carrying above-mentioned increase cell, search the reserved GBR load that whether has this UE, after finding the reserved GBR load that has this UE, determining needs to recover reserved GBR load.
Can carry the QoS of the GBR carrying tabulation of the reservation attitude that needs recovery and each the GBR carrying correspondence in the tabulation in the renewal bearing request message that MME sends, promptly MME utilizes one to upgrade the information that bearing request message sends all reserved GBR loads that need recover.When the reserved GBR load of needs recovery has many, MME also can upgrade the information that bearing request message sends the reserved GBR load that needs recovery by many, for example, one is upgraded bearing request message and only carries a sign that needs the reserved GBR load that recovers and QoS etc.
The QoS that upgrades the reserved GBR load that the needs that carry in the bearing request message recover can be the QoS of reserved GBR load when normally moving.In the E-UTRAN environment, for discharge the reserved GBR load that forms owing to the S1 interface, owing to preserve the QoS that maximum rate is reduced to the carrying before zero among the MME, therefore, the QoS when MME can obtain reserved GBR load and normally moves from its canned data.For the maximum rate that passes over from UTRAN is that zero carrying (is that UE is under the UTRAN environment, having maximum rate is zero carrying, afterwards, UE moves to the E-UTRAN environment from the UTRAN environment, because the QoS that consults when including reserved GBR load in the PDP Context of UE under former UTRAN environment that receive of MME and normally moving, therefore, MME can get access to the QoS of reserved GBR load when normally moving from the PDP Context information that received in the past.
Need to prove that the renewal bearing request message here only is a kind of explanation that exemplifies, the step 2a of present embodiment also can adopt other message, and present embodiment does not limit the message name of concrete employing.
Step 2b, Serving GW should upgrade bearing request message and be transmitted to PDN GW after receiving the renewal bearing request message of MME transmission.Still carry in the renewal bearing request message that Serving GW transmits and recover reserved GBR load information, as carry reserved GBR load tabulation and QoS, carry reserved GBR load sign and QoS for another example.
After step 2c, PDN GW receive the renewal bearing request message that Serving GW sends, obtain the recovery reserved GBR load information of carrying in the bearing request message of upgrading, and need to determine the QoS of the reserved GBR load that recovers.PDN GW is provided with the core-network side carrying of reserved GBR load correspondence according to the QoS of the reserved GBR load of determining.
The QoS of the reserved GBR load that determine to need recovers can for: PDN GW by carrying out information interaction or obtain qos requirement at reserved GBR load according to local collocation strategy with PCRF, then, determine the QoS of reserved GBR load again according to the qos requirement of the concrete condition of current network resources and above-mentioned acquisition.The object lesson of the QoS of another definite reserved GBR load that need recover is: reduce to zero reserved GBR load at the maximum rate of coming from the UTRAN band, PDN GW provides a new QoS who is not less than the QoS of former requirement according to the current network resources situation for reserved GBR load.The QoS of the former requirement here is meant the QoS of reserved GBR load when normal operation.Certainly, here be not less than also can be for being equal to or less than.For example, PDN GW can will upgrade the QoS that carries in the bearing request message QoS as reserved GBR load under the situation that the current network resources situation allows, promptly PDN GW carries according to upgrading the core-network side that the QoS that carries in the bearing request message is provided with the reserved GBR load correspondence under the situation that the current network resources situation allows.
Step 2d, PDN GW are after the core-network side carrying that is provided with the reserved GBR load correspondence, send and upgrade bearing response message, can carry the QoS of the reserved GBR load that successfully recovers and the tabulation that successfully recovers reserved GBR load in this renewal bearing response message.The successful recovery here is meant the successful recovery of core-network side carrying.No matter PDN GW has successfully recovered all reserved GBR loads, has still recovered the part reserved GBR load, all can carry the tabulation of the reserved GBR load that successfully recovers in this renewal bearing response message.A kind of simple variation is: when successfully recovering all reserved GBR loads, can not carry the tabulation of the reserved GBR load that successfully recovers, and when successful recovered part reserved GBR load, can carry the tabulation of the reserved GBR load that successfully recovers.Another kind of simple variation is: the reserved GBR load that recovers at needs only has one and when successfully having been recovered, the tabulation that can not carry the reserved GBR load that successfully recovers.Above-mentionedly also be applicable in the following respective embodiments no longer repeat specification in the following embodiments at upgrading the description of carrying the tabulation that successfully recovers reserved GBR load in the bearing response message.
The renewal bearing response message that step 2e, Serving GW will receive is transmitted to MME, still can carry the QoS of the reserved GBR load that successfully recovers and the carrying tabulation that success recovers in this renewal bearing response message.To step 4.
Fig. 2 acceptance of the bid is marked with step 3, and the subscription authentication of step 3 is applied to be in the service request procedure of UE of Idle state, and in the present embodiment, because UE is in connected state, therefore, this step does not need to carry out.
Step 4, MME send S1 bearer context request message (i.e. second Indication message) to eNodeB after receiving and upgrading bearing response message, are that the reserved GBR load that successfully recovers the core-network side carrying recovers the S1 carrying with indication eNodeB.Carry QoS in the S1 bearer context request message, this QoS is for upgrading the QoS that carries in the bearing response message.Can also carry the reserved GBR load identification information that successfully recovers the core-network side carrying in the S1 bearer context request message, this identification information is for upgrading the identification information that carries in the bearing response message.An object lesson that recovers the S1 interface bearing is: set up the S1 interface bearing according to the QoS in the S1 bearer context request message.
Step 5, eNodeB are that the reserved GBR load that successfully recovers the core-network side carrying recovers corresponding wireless side carrying.
An object lesson that recovers the wireless side carrying is: after successfully setting up the S1 carrying, eNodeB calculates the QoS of the wireless side carrying of reserved GBR load correspondence according to the QoS in the S1 bearer context request message, then, set up the wireless side carrying according to the QoS that calculates.Successfully recover the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence by step 4 and 5.
Step 6, UE can send upstream data according to the reserved GBR load that above-mentioned success recovers.
Step 7, eNodeB send the S1 bearer context to MME and finish message, with the restoration result of notice MME reserved GBR load.
Step 8, MME send to Serving GW and upgrade bearing request message.Can not successfully set up if there is core-network side to carry corresponding empty port load-supporting, MME will trigger the carrying dispose procedure so.
MME in the foregoing description two is after the service request that receives the UE transmission that is in connected state, by send the renewal bearing request message that carries reserved GBR load tabulation and QoS to PDN GW, make PDN GW upgrade the core-network side carrying that bearing request message is recovered the reserved GBR load correspondence according to this; PDN GW is by sending the QoS carry the reserved GBR load that successfully recovers the core-network side carrying and successfully recovering the renewal bearing response message of the reserved GBR load sign of core-network side carrying to MME, make MME upgrade bearing response message according to this and send to eNodeB and carry that the reserved GBR load that successfully recovers the core-network side carrying identifies and the S1 bearer context request message of QoS; ENodeB can recover the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence according to the S1 bearer context request message that receives.Thereby in being in the process of connected state, UE successfully recovers reserved GBR load.
Embodiment three, UE are in Idle state, and UE initiates earlier Idle state service request procedure down, in this service request procedure, set up the reserved GBR load correspondence, maximum rate is that zero S1 interface bearing and wireless side are carried.After this service request procedure was finished, UE was in connected state.The UE that is in connected state initiates the connected state service request procedure again, serves as the zero S1 interface bearing and the QoS of wireless side carrying with core-network side carrying that recovers the reserved GBR load correspondence and the maximum rate that is modified in Idle state foundation, improves maximum rate.The specific implementation process of embodiment three is shown in Fig. 3 a and Fig. 3 b.
Fig. 3 a shows the service request procedure under the UE initiation Idle state that is in Idle state.In the service request procedure shown in Fig. 3 a, set up the reserved GBR load correspondence, maximum rate is zero S1 interface bearing and wireless side carrying.
Among Fig. 3 a, step 1, the UE that is in Idle state send service request information to MME, carry cells such as S-TMSI in this service request information.
Step 2, eNodeB receive service request information, and this service request information is transmitted to MME.
The authentication process that step 3, MME initiate NAS message.
Step 4, after authentication success, MME sends S1 bearer context request message to eNodeB, to set up the S1 interface bearing.At MME after to find this network element internal memory be zero reserved GBR load at maximum rate, it is zero S1 interface bearing that MME can utilize S1 bearer context request message indication eNodeB to set up maximum rate for reserved GBR load, for example, MME is carried at reserved GBR load tabulation and QoS in the S1 bearer context request message, and sends to eNodeB.An object lesson that recovers the S1 interface bearing is: set up the S1 interface bearing according to the QoS in the S1 bearer context request message.
Step 5, eNodeB are that the UE that is in Idle state sets up the wireless side carrying that maximum rate is a non-zero.It is zero wireless side carrying that eNodeB also need set up maximum rate at reserved GBR load.
The maximum rate that step 6, UE can set up according to above-mentioned success is that the wireless side carrying of non-zero sends upstream data.
Step 7, eNodeB send the S1 bearer context request to MME and set up message (also claiming the S1 bearer context request to finish message).
Step 8, MME receive after the S1 bearer context request sets up message, send to Serving GW and upgrade bearing request message, can not successfully set up if there is core-network side to carry corresponding empty port load-supporting, and MME will trigger the carrying dispose procedure so.
If the access technology of step 9 UE changes, then Serving GW sends to PDN GW and upgrades bearing request message.
After step 10, PDN GW receive and upgrade bearing request message, otherwise according to disposed dynamic PCC, by determining the PCC rule of the access technology after the variation with the information interaction of PCRF, determine Qos according to the PCC rule of the access technology after changing again; PDN GW determines Qos according to local Qos strategy.
Step 11, PDN GW send and upgrade bearing response message.
The renewal bearing response message that step 12, Serving GWS-GW will receive is transmitted to MME.
Fig. 3 b shows the service request procedure under the UE initiation connected state that is in connected state.In the service request procedure shown in Fig. 3 b, recover the core-network side carrying of reserved GBR load correspondence, and for that set up, the reserved GBR load correspondence, maximum rate be that zero S1 interface bearing and wireless side carrying are provided with maximum rate.
Among Fig. 3 b, step 1, UE send service request information to MME.Carry cells such as S-TMSI in this service request information.Can also increase in the service request information that UE sends and carry the cell that is used to carry the information relevant with recovering reserved GBR load.The sign of the reserved GBR load that the cell loaded information of this increase can be recovered for needs also can be for recovering the indication information of whole reserved GBR loads.When the cell loaded information that increases during for the sign of the reserved GBR load that needs to recover, this sign can exist with the form of GBR bearing identification tabulation.The indication information that recovers whole reserved GBR loads can be 1 bit indicating bit etc.
Certainly, also can not carry the cell of above-mentioned increase in the service request information that UE sends, in the present embodiment, the cell that service request information is not carried above-mentioned increase can be expressed as the whole reserved GBR loads of requirement recovery in this service request procedure, also can be expressed as in this service request procedure and not require the whole reserved GBR loads of recovery.The implication of the concrete expression of service request information need clearly be stipulated in each network equipment.If in the service request procedure of the terminal that is in connected state, do not require the recovery reserved GBR load, then can in other process, recover reserved GBR load, for example, when UE need utilize the GBR carrying that keeps attitude to carry out business, UE can initiate the bearing resource modification process, to recover reserved GBR load in the bearing resource modification process.UE initiates the bearing resource modification process, and the specific implementation process of recovery reserved GBR load is on the books in other embodiments in this flow process.
Step 2, eNodeB receive the service request information that UE sends, and this service request information is transmitted to MME.
After step 2a, MME received service request information, determining needed to recover reserved GBR load, and then MME sends and upgrades bearing request message (i.e. first Indication message).
MME determines mode that need to recover reserved GBR load to be had multiplely, and when carrying the reserved GBR load tabulation in the service request information that receives at MME, MME determines needs to recover reserved GBR load; Carry the indication information that recovers whole reserved GBR loads and this indication information for another example when representing that needs recover reserved GBR load in the service request information that MME receives, MME determines needs the recovery reserved GBR load; Also have, not carrying the information representation relevant with recovering reserved GBR load in MME in the default service requests message recovers under the situation of whole reserved GBR loads, after MME receives the service request information of not carrying above-mentioned increase cell, search the reserved GBR load that whether has this UE, after finding the reserved GBR load that has this UE, determining needs to recover reserved GBR load.PDN GW determines the specific implementation process of Qos such as the description among the above-mentioned embodiment.
Can carry the QoS of the GBR carrying tabulation of the reservation attitude that needs recovery and each the GBR carrying correspondence in the tabulation in the renewal bearing request message that MME sends, promptly MME utilizes one to upgrade the information that bearing request message sends all reserved GBR loads that need recover.When the reserved GBR load of needs recovery has many, MME also can upgrade the information that bearing request message sends the reserved GBR load that needs recovery by many, for example, one is upgraded bearing request message and only carries a sign that needs the reserved GBR load that recovers and QoS etc.
The QoS that upgrades the reserved GBR load that the needs that carry in the bearing request message recover can be the QoS of reserved GBR load when normally moving.In the E-UTRAN environment, for discharge the reserved GBR load that forms owing to the S1 interface, owing to preserve the QoS that maximum rate is reduced to the carrying before zero among the MME, therefore, the QoS when MME can obtain reserved GBR load and normally moves from its canned data.For the maximum rate that passes over from UTRAN is zero carrying, because the QoS that consults when including reserved GBR load in the PDP Context that receives of MME and normally moving, therefore, MME can get access to the QoS of reserved GBR load when normally moving from the PDP Context information that receives.
Need to prove that the renewal bearing request message here only is a kind of explanation that exemplifies, the step 2a of present embodiment also can adopt other message, and present embodiment does not limit the message name of concrete employing.
Step 2b, Serving GW should upgrade bearing request message and be transmitted to PDN GW after receiving the renewal bearing request message of MME transmission.Still carry in the renewal bearing request message that Serving GW transmits and recover reserved GBR load information, as carry reserved GBR load tabulation and QoS, carry reserved GBR load sign and QoS for another example.
After step 2c, PDN GW receive the renewal bearing request message that Serving GW sends, obtain and upgrade the recovery reserved GBR load information of carrying in the bearing request message, and the QoS of definite reserved GBR load.PDN GW is provided with the core-network side carrying of reserved GBR load correspondence according to the QoS of the reserved GBR load of determining.
Determine reserved GBR load QoS can for: PDN GW by carrying out information interaction or obtain qos requirement at reserved GBR load according to local collocation strategy with PCRF, then, determine the QoS of reserved GBR load again according to the qos requirement of the concrete condition of current network resources and above-mentioned acquisition.The object lesson of the QoS of a definite reserved GBR load is: reduce to zero reserved GBR load at the maximum rate of coming from the UTRAN band, PDN GW provides a new QoS who is not less than the QoS of former requirement according to the current network resources situation for reserved GBR load.Certainly, here be not less than also can be for being equal to or less than.A concrete example is: PDN GW can will upgrade the QoS that carries in the bearing request message QoS as reserved GBR load, and promptly PDN GW is according to upgrading the core-network side carrying that the QoS that carries in the bearing request message is provided with the reserved GBR load correspondence.Concrete as the description among the above-mentioned embodiment.
Step 2d, PDN GW send and upgrade bearing response message after the core-network side carrying that is provided with the reserved GBR load correspondence, can carry the QoS of the reserved GBR load that successfully recovers in this renewal bearing response message.Upgrade the identification information that also can carry the reserved GBR load that successfully recovers in the bearing response message, tabulate as reserved GBR load.Concrete as the description among the above-mentioned embodiment.The successful recovery here is meant the successful recovery of core-network side carrying.
The renewal bearing response message that step 2e, Serving GW will receive is transmitted to MME, still can carry the QoS of the reserved GBR load that successfully recovers in this renewal bearing response message.To step 4.
Fig. 3 b acceptance of the bid is marked with step 3, and the subscription authentication of step 3 is applied to be in the service request procedure of UE of Idle state, and in the present embodiment, because UE is in connected state, therefore, this step does not need to carry out.
After step 4, MME receive and upgrade bearing response message, from upgrade bearing response message, obtain reserved GBR load tabulation and the QoS information successfully recovered, and to eNodeB transmission S1 bearer context request message (i.e. second Indication message), the maximum rate of revising the reserved GBR load correspondence with indication eNodeB is the QoS that zero S1 carries.Carry QoS in the above-mentioned S1 bearer context request message, this QoS can be for upgrading the QoS that carries in the bearing response message, in addition, can also carry the reserved GBR load tabulation that successfully recovers in this S1 bearer context request message, concrete as the description among the above-mentioned embodiment.
Step 5, eNodeB are wireless side carrying Resources allocation, the modification QoS that successfully recovers the reserved GBR load correspondence of core-network side carrying, to improve the speed of wireless side carrying.Successfully recover the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence by step 4 and step 5.
Step 6, UE can send upstream data according to the reserved GBR load that above-mentioned success recovers.
Step 7, eNodeB send the S1 bearer context to MME and finish message, with the restoration result of notice MME reserved GBR load.The S1 bearer context is finished message bearing bearing identification.This bearing identification such as S1 interface bearing sign etc.
Step 8, MME are receiving after the S1 bearer context finishes message, send to Serving GW and upgrade bearing request message, can not successfully set up if there is core-network side to carry corresponding empty port load-supporting, and MME will trigger the carrying dispose procedure so.
MME in the foregoing description three is after the service request that receives the UE transmission that is in Idle state, by send S1 bearer context request message to eNodeB, make eNodeB can be under the situation of the Idle state of UE be that to set up maximum rate be zero S1 interface bearing and wireless side carrying to reserved GBR load according to this message; MME is after the service request that receives the UE transmission that is in connected state, by send the renewal bearing request message that carries reserved GBR load tabulation and QoS to PDN GW, make PDN GW upgrade the core-network side carrying that bearing request message is recovered the reserved GBR load correspondence according to this; PDN GW is by sending the QoS carry the reserved GBR load that successfully recovers the core-network side carrying and successfully recovering the renewal bearing response message of the reserved GBR load sign of core-network side carrying to MME, make MME upgrade bearing response message according to this and send to eNodeB and carry that the reserved GBR load that successfully recovers the core-network side carrying identifies and the S1 bearer context request message of QoS; ENodeB can will revise the S1 interface bearing of above-mentioned foundation and the maximum rate of wireless side carrying according to the S1 bearer context request message that receives.Thereby in being in the process of Idle state and connected state, UE successfully recovers reserved GBR load.
Embodiment four, UE are in Idle state, and UE initiates the service request procedure under the Idle state, recover the reserved GBR load of UE in the service request procedure of the UE under being in Idle state.The specific implementation process of embodiment four as shown in Figure 4.
Among Fig. 4, step 1, UE send service request information to MME.Carry cells such as S-TMSI in this service request information.
Step 2, eNodeB receive the service request information that UE sends, and this service request information is transmitted to MME.
After step 2a, MME received service request information, MME searched the reserved GBR load that whether has this UE in the system, and behind the reserved GBR load of this UE of existence, MME sends and upgrades bearing request message (i.e. first Indication message) in the system of finding.
Can carry the QoS of the GBR carrying tabulation of the reservation attitude that needs recovery and each the GBR carrying correspondence in the tabulation in the renewal bearing request message that MME sends, promptly MME utilizes one to upgrade the information that bearing request message sends all reserved GBR loads that need recover.When the reserved GBR load of needs recovery has many, MME also can upgrade the information that bearing request message sends the reserved GBR load that needs recovery by many, for example, one is upgraded bearing request message and only carries a sign that needs the reserved GBR load that recovers and QoS etc.
The QoS of the reserved GBR load that the needs that carry in this renewal bearing request message recover can be the QoS of reserved GBR load when normally moving.In the E-UTRAN environment, for discharge the reserved GBR load that forms owing to the S1 interface, owing to preserve the QoS that maximum rate is reduced to the carrying before zero among the MME, therefore, the QoS when MME can obtain reserved GBR load and normally moves from its canned data.For the maximum rate that passes over from UTRAN is zero carrying, because the QoS that consults when including reserved GBR load in the PDP Context that receives of MME and normally moving, therefore, MME can get access to the QoS of reserved GBR load when normally moving from the PDP Context information that receives.
Need to prove that the renewal bearing request message here only is a kind of explanation that exemplifies, the step 2a of present embodiment also can adopt other message, and present embodiment does not limit the message name of concrete employing.
Step 2b, Serving GW should upgrade bearing request message and be transmitted to PDN GW after receiving the renewal bearing request message of MME transmission.Still carry in the renewal bearing request message that Serving GW transmits and recover reserved GBR load information, as carry reserved GBR load tabulation and QoS, carry reserved GBR load sign and QoS for another example.
After step 2c, PDN GW receive the renewal bearing request message that Serving GW sends, obtain and upgrade the recovery reserved GBR load information of carrying in the bearing request message, and the QoS of definite reserved GBR load.PDN GW is provided with the core-network side carrying of reserved GBR load correspondence according to the QoS of the reserved GBR load of determining.
Determine reserved GBR load QoS can for: PDN GW by carrying out information interaction or obtain qos requirement at reserved GBR load according to local collocation strategy with PCRF, then, determine the QoS of reserved GBR load again according to the qos requirement of the concrete condition of current network resources and above-mentioned acquisition.The object lesson of the QoS of a definite reserved GBR load is: reduce to zero reserved GBR load at the maximum rate of coming from the UTRAN band, PDN GW provides a new QoS who is not less than the QoS of former requirement according to the current network resources situation for reserved GBR load.Certainly, here be not less than also can be for being equal to or less than.A concrete example is: PDN GW also can will upgrade the QoS that carries in the bearing request message QoS as reserved GBR load, and promptly PDN GW is according to upgrading the core-network side carrying that the QoS that carries in the bearing request message is provided with the reserved GBR load correspondence.
Step 2d, PDN GW send and upgrade bearing response message after the core-network side carrying that has recovered the reserved GBR load correspondence, can carry the QoS of the reserved GBR load that successfully recovers in this renewal bearing response message.The successful recovery here is meant the successful recovery of core-network side carrying.Also can carry the identification information of the reserved GBR load that successfully recovers in the above-mentioned renewal bearing response message, tabulate as reserved GBR load.Concrete as the description among the above-mentioned embodiment.
The renewal bearing response message that step 2e, Serving GW will receive is transmitted to MME, still can carry the QoS of the reserved GBR load that successfully recovers in this renewal bearing response message.
Step 3 is carried out the subscription authentication process.
After step 4, MME receive and upgrade bearing response message, from upgrade bearing response message, obtain reserved GBR load tabulation and the QoS information successfully recovered, and, recover the S1 interface bearing of reserved GBR load correspondence with indication eNodeB to eNodeB transmission S1 bearer context request message (i.e. second Indication message).Carry QoS in the above-mentioned S1 bearer context request message, this QoS can be for upgrading the QoS that carries in the bearing response message, in addition, can also carry the reserved GBR load tabulation that successfully recovers in this S1 bearer context request message, concrete as the description among the above-mentioned embodiment.
Step 5, eNodeB are that the reserved GBR load that successfully recovers the core-network side carrying recovers corresponding wireless side carrying.An example that recovers the wireless side carrying is: after successfully setting up the S1 carrying, eNodeB calculates the QoS of the wireless side carrying of reserved GBR load correspondence according to the QoS in the S1 bearer context request message, then, sets up the wireless side carrying according to the QoS that calculates.
Step 6, UE can send upstream data according to the reserved GBR load that above-mentioned success recovers.
Step 7, eNodeB send the S1 bearer context to MME and finish message, with the restoration result of notice MME reserved GBR load.The S1 bearer context is finished message bearing bearing identification.This bearing identification such as S1 interface bearing sign etc.
Step 8, MME are receiving after the S1 bearer context finishes message, send to Serving GW and upgrade bearing request message, can not successfully set up if there is core-network side to carry corresponding empty port load-supporting, and MME will trigger the carrying dispose procedure so.
MME in the foregoing description four is after the service request that receives the UE transmission that is in Idle state, by send the renewal bearing request message that carries reserved GBR load tabulation and QoS to PDN GW, make PDN GW upgrade the core-network side carrying that bearing request message is recovered the reserved GBR load correspondence according to this; PDN GW is by sending the QoS carry the reserved GBR load that successfully recovers the core-network side carrying and successfully recovering the renewal bearing response message of the reserved GBR load sign of core-network side carrying to MME, make MME upgrade bearing response message according to this and send to eNodeB and carry that the reserved GBR load that successfully recovers the core-network side carrying identifies and the S1 bearer context request message of QoS; ENodeB can recover the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence according to the S1 bearer context request message that receives.Thereby in being in the process of Idle state, UE successfully recovers reserved GBR load.
Embodiment five, UE are in Idle state, UE initiates the service request under the Idle state, in the service request procedure of UE under being in Idle state, MME notice PDN GW recovers reserved GBR load, and PDN GW recovers the reserved GBR load of UE according to the notice of MME, by the dedicated bearer modification process that utilizes modification QoS.The specific implementation process of embodiment five as shown in Figure 5.
Among Fig. 5, step 1, UE send service request information to MME.Carry cells such as S-TMSI in this service request information.
Step 2, eNodeB receive the service request information that UE sends, and this service request information is transmitted to MME.
After step 2a, MME received service request information, MME searched the reserved GBR load that whether has this UE in the system, and behind the reserved GBR load of this UE of existence, MME sends and upgrades bearing request message (i.e. first Indication message) in the system of finding.
Can carry the QoS of the GBR carrying tabulation of the reservation attitude that needs recovery and each the GBR carrying correspondence in the tabulation in the renewal bearing request message that MME sends, promptly MME utilizes one to upgrade the information that bearing request message sends all reserved GBR loads that need recover.When the reserved GBR load of needs recovery has many, MME also can upgrade the information that bearing request message sends the reserved GBR load that needs recovery by many, for example, one is upgraded bearing request message and only carries a sign that needs the reserved GBR load that recovers and QoS etc.
The QoS of the reserved GBR load that the needs that carry in this renewal bearing request message recover can be the QoS of reserved GBR load when normally moving.In the E-UTRAN environment, for discharge the reserved GBR load that forms owing to the S1 interface, owing to preserve the QoS that maximum rate is reduced to the carrying before zero among the MME, therefore, the QoS when MME can obtain reserved GBR load and normally moves from its canned data.For the maximum rate that passes over from UTRAN is zero carrying, because the QoS that consults when including reserved GBR load in the PDP Context that receives of MME and normally moving, therefore, MME can get access to the QoS of reserved GBR load when normally moving from the PDP Context information that receives.
Need to prove that the renewal bearing request message here only is a kind of explanation that exemplifies, the step 2a of present embodiment also can adopt other message, and present embodiment does not limit the message name of concrete employing.
Step 2b, Serving GW should upgrade bearing request message and be transmitted to PDN GW after receiving the renewal bearing request message of MME transmission.Still carry in the renewal bearing request message that Serving GW transmits and recover reserved GBR load information, as carry reserved GBR load tabulation and QoS, carry reserved GBR load sign and QoS for another example.
After PDN GW receives the renewal bearing request message that Serving GW sends, determine the quality of service information of the reserved GBR load that needs recover according to the current network resources situation, then, dedicated bearer modification process according to the existing modification of this quality of service information of determining triggering QoS utilizes this bearing modification flow process to recover reserved GBR load.Need to prove, in this bearing modification flow process, if the S1 interface bearing of reserved GBR load correspondence and wireless side carrying are successfully set up, but maximum rate is zero, then need to revise the S1 interface bearing of reserved GBR load correspondence and the QoS of wireless side carrying; If the S1 interface bearing of reserved GBR load correspondence and wireless side carrying are not set up, then need to set up the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence according to QoS.In addition, the detailed process of the quality of service information of the definite reserved GBR load that need recover of PDN GW such as the description among other embodiment no longer describe in detail at this.
In the bearing modification flow process, the S1 interface bearing of the reserved GBR load correspondence that success is set up and wireless side carrying can be S1 interface bearing and the wireless side carryings that utilizes flow process shown in Figure 3 to set up.
Step 2d, PDN GW are sending the renewal bearing response message.
The renewal bearing response message that step 2e, Serving GW will receive is transmitted to MME.
Step 3 is carried out the subscription authentication process.
After step 4, MME receive the renewal bearing response message that Serving GW sends, send S1 bearer context request message to eNodeB, eNodeB recovers the S1 interface bearing with indication.The S1 interface bearing here is at the carrying except that reserved GBR load.
Step 5, eNodeB are that the wireless side carrying is set up in the carrying in the network.
Need to prove, in carrying out this step 5 processes, if the S1 interface bearing of reserved GBR load correspondence is not successfully set up, then eNodeB can set up S1 interface bearing and wireless side carrying for reserved GBR load in this step, like this, behind second Indication message of eNodeB in receiving the bearing modification flow process, eNodeB modification reserved GBR load is correspondence, successful foundation, maximum rate is zero S1 interface bearing and the maximum rate of wireless side carrying.
An example that recovers the wireless side carrying is: eNodeB is after successfully setting up the S1 interface bearing, calculate the QoS of the wireless side carrying of reserved GBR load correspondence according to the QoS in the S1 bearer context request message, then, set up the wireless side carrying according to the QoS that calculates.
Need to prove that in addition present embodiment can be carried out the different implementation procedure of difference generation of sequential according to step.For example, the S1 interface bearing and the wireless side carrying back of recovering the reserved GBR load correspondence are carried out, like this, eNodeB is when receiving S1 bearer context request message, can set up maximum rate earlier is zero S1 interface bearing and wireless side carrying, then, in the S1 interface bearing and wireless side load bearing process that recover the reserved GBR load correspondence, the maximum rate of revising above-mentioned foundation is the zero S1 interface bearing and the QoS of wireless side carrying.Again for example, eNodeB directly sets up the carrying of non-vanishing S1 interface bearing of maximum rate and wireless side after receiving S1 bearer context request message.
Step 6, UE can send upstream data according to the reserved GBR load that above-mentioned success recovers.
Step 7, eNodeB send the S1 bearer context to MME and finish message.This S1 bearer context is finished message bearing and has the EPS carrying tabulation of the EPS carrying tabulation of eNodeB address, acceptance, refusal and S1 TEID (s) (DL) etc.
Step 8, MME are receiving after the S1 bearer context finishes message, send to Serving GW and upgrade bearing request message, can not successfully set up if there is EPS to carry corresponding empty port load-supporting, and MME will trigger the carrying dispose procedure so.
MME in the foregoing description five is after the service request that receives the UE transmission that is in Idle state, by send the renewal bearing request message that carries reserved GBR load tabulation and QoS to PDN GW, make PDN GW upgrade bearing request message and trigger the bearing modification flow process according to this, thus the core-network side carrying, S1 interface bearing and the wireless side carrying that recover the reserved GBR load correspondence; In the bearing modification flow process of embodiment five, can directly set up S1 interface bearing and wireless side carrying according to QoS, also can be that zero S1 interface bearing and wireless side carrying improves the maximum rate processing to the maximum rate that has existed; Thereby in being in the process of Idle state, UE successfully recovers reserved GBR load.
Embodiment six, UE are in connected state, UE initiates the service request under the connected state, in the service request procedure of UE under being in connected state, MME notice PDN GW recovers reserved GBR load, and PDN GW recovers the reserved GBR load of UE according to the notice of MME, by the dedicated bearer modification process that utilizes modification QoS.The specific implementation process of embodiment six as shown in Figure 6.
Among Fig. 6, step 1, UE send service request information to MME.Carry cells such as S-TMSI in this service request information.Can also increase in the service request information that UE sends and carry the cell that is used to carry the information relevant with recovering reserved GBR load.The sign of the reserved GBR load that the cell loaded information of this increase can be recovered for needs also can be for recovering the indication information of whole reserved GBR loads.When the cell loaded information that increases during for the sign of the reserved GBR load that needs to recover, this sign can exist with the form of GBR bearing identification tabulation.The indication information that recovers whole reserved GBR loads can be 1 bit indicating bit etc.
Certainly, also can not carry the cell of above-mentioned increase in the service request information that UE sends, in the present embodiment, the cell that service request information is not carried above-mentioned increase can be expressed as the whole reserved GBR loads of requirement recovery in this service request procedure, also can be expressed as in this service request procedure and not require the whole reserved GBR loads of recovery.The implication of the concrete expression of service request information need clearly be stipulated in each network equipment.If in the service request procedure of the terminal that is in connected state, do not require the recovery reserved GBR load, then can in other process, recover reserved GBR load, for example, when UE need utilize the GBR carrying that keeps attitude to carry out business, UE can initiate the bearing resource modification process, to recover reserved GBR load in the bearing resource modification process.UE initiates the bearing resource modification process, and the specific implementation process of recovery reserved GBR load is on the books in other embodiments in this flow process.
Step 2, eNodeB receive the service request information that UE sends, and this service request information is transmitted to MME.
After step 2a, MME received service request information, MME searched the reserved GBR load that whether has this UE in the system, and behind the reserved GBR load of this UE of existence, MME sends and upgrades bearing request message (i.e. first Indication message) in the system of finding.
Can carry the QoS of the GBR carrying tabulation of the reservation attitude that needs recovery and each the GBR carrying correspondence in the tabulation in the renewal bearing request message that MME sends, promptly MME utilizes one to upgrade the information that bearing request message sends all reserved GBR loads that need recover.When the reserved GBR load of needs recovery has many, MME also can upgrade the information that bearing request message sends the reserved GBR load that needs recovery by many, for example, one is upgraded bearing request message and only carries a sign that needs the reserved GBR load that recovers and QoS etc.
The QoS of the reserved GBR load that the needs that carry in this renewal bearing request message recover can be the QoS of reserved GBR load when normally moving.In the E-UTRAN environment, for discharge the reserved GBR load that forms owing to the S1 interface, owing to preserve the QoS that maximum rate is reduced to the carrying before zero among the MME, therefore, the QoS when MME can obtain reserved GBR load and normally moves from its canned data.For the maximum rate that passes over from UTRAN is zero carrying, because the QoS that consults when including reserved GBR load in the PDP Context that receives of MME and normally moving, therefore, MME can get access to the QoS of reserved GBR load when normally moving from the PDP Context information that receives.
Need to prove that the renewal bearing request message here only is a kind of explanation that exemplifies, the step 2a of present embodiment also can adopt other message, and present embodiment does not limit the message name of concrete employing.
Step 2b, Serving GW should upgrade bearing request message and be transmitted to PDN GW after receiving the renewal bearing request message of MME transmission.Still carry in the renewal bearing request message that Serving GW transmits and recover reserved GBR load information, as carry reserved GBR load tabulation and QoS, carry reserved GBR load sign and QoS for another example.
After PDN GW receives the renewal bearing request message that Serving GW sends, determine the quality of service information of the reserved GBR load that needs recover according to the current network resources situation, then, dedicated bearer modification process according to the existing modification of this quality of service information of determining triggering QoS utilizes this bearing modification flow process to recover reserved GBR load.Need to prove, in this bearing modification flow process, if the S1 interface bearing of reserved GBR load correspondence and wireless side carrying are successfully set up, but maximum rate is zero, then need to revise the S1 interface bearing of reserved GBR load correspondence and the QoS of wireless side carrying; If the S1 interface bearing of reserved GBR load correspondence and wireless side carrying are not set up, then need to set up the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence according to QoS.In addition, the detailed process of the quality of service information of the definite reserved GBR load that need recover of PDN GW such as the description among other embodiment no longer describe in detail at this.
In the bearing modification flow process, the S1 interface bearing of the reserved GBR load correspondence that success is set up and wireless side carrying can be S1 interface bearing and the wireless side carryings that utilizes flow process shown in Figure 3 to set up.
Step 2d, PDN GW are sending the renewal bearing response message to Serving GW.
The renewal bearing response message that step 2e, Serving GW will receive is transmitted to MME, to step 4.
Fig. 6 acceptance of the bid is marked with step 3, and the subscription authentication of step 3 is applied to be in the service request procedure of UE of Idle state, and in the present embodiment, because UE is in connected state, therefore, this step does not need to carry out.
Step 4, after subscription authentication success, MME sends service request to UE and accepts message.
MME in the foregoing description six is after the service request that receives the UE transmission that is in connected state, by send the renewal bearing request message that carries reserved GBR load tabulation and QoS to PDN GW, make PDN GW upgrade bearing request message and trigger the bearing modification flow process according to this, thus the core-network side carrying, S1 interface bearing and the wireless side carrying that recover the reserved GBR load correspondence; In the bearing modification flow process of embodiment six, can directly set up S1 interface bearing and wireless side carrying according to QoS, also can be that zero S1 interface bearing and wireless side carrying improve maximum rate and handle to the maximum rate that has existed, the maximum rate here be that zero S1 interface bearing and wireless side carrying can be to set up in UE is in the process of Idle state; Thereby be in the process of connected state or in UE is in the process of connected state and Idle state, successfully recover reserved GBR load at UE.
Embodiment seven, UE initiating updating of tracking area, in the tracing section updating process that UE initiates, MME notice PDN GW recovers reserved GBR load, and PDN GW recovers the reserved GBR load of UE according to the notice of MME.The specific implementation process of embodiment seven as shown in Figure 7.
Among Fig. 7, step 1, under the situation that satisfies the tracing section updating condition, UE initiating updating of tracking area request message.UE is provided with in the tracing section updating request message under the situation of " Active Flag " sign, can also in the tracing section updating request message, increase cell, the cell of this increase is used to carry the information relevant with recovering reserved GBR load, needs the reserved GBR load that recovers with indication.
Step 2, UE send the tracing section updating request message to eNodeB, can comprise in this tracing section updating request message: oldGUTI, last visited TAI, active flag, cells such as EPS bearer status, P-TMSI Signature.
After step 3, eNodeB receive the tracing section updating request message, this tracing section updating request message is transmitted to MME.
Step 4, caused attached to MME and routing update originally under the situation of MME change at UE, target MME sends context request message to former MME.
After step 5, former MME received context request message, MME returned context response information to target, to step 8.
If UE caused moving under the situation of MME attached to SGSN and routing update originally, then above-mentioned steps 4 and step 5 can replace with following step 6 and step 7.
Step 6, target MME network element send context request message to former SGSN.
After step 7, former SGSN received context request message, MME returned context response information to target, to step 8.
Step 8, UE initiate authentication process.This step is an optional step, and promptly UE can not initiate authentication process.
Step 9, target MME send context acknowledgement message to former MME.
Under the situation of carrying out above-mentioned steps 6 and step 7, above-mentioned steps 9 can replace with following step 10.
Step 10, target MME send context acknowledgement message to former SGSN.
Step 11, do not reselect under the situation of new Serving GW at MME, MME sends to Serving GW network element and upgrades bearing request message.Selected at MME under the situation of new Serving GW, then MME can send to new Serving GW and create bearing request message.
Being provided with " active flag " mark and MME in the tracing section updating request message that MME receives finds under the situation that has reserved GBR load in the system, perhaps MME determines under the situation of the reservation attitude GBR that has the needs recovery according to the cell that increases in the above-mentioned steps 1, MME is to carry first Indication message that recovers reserved GBR load information by Serving GW to renewal bearing request message or the establishment bearing request message that PDN GW sends, and first Indication message is used to indicate PDN GW to recover reserved GBR load.
The renewal bearing request message that MME sends or create can carry the GBR carrying tabulation that needs the reservation attitude recovered and the corresponding QoS of each GBR carrying in the tabulation in the bearing request message, promptly MME utilizes one to upgrade bearing request message or one and create the information that bearing request message sends all reserved GBR loads that need recover.When the reserved GBR load of needs recovery has many, MME also can upgrade bearing request message or many by many and create the information that bearing request message sends needs the reserved GBR load that recovers, for example, one is upgraded bearing request message or one and creates bearing request message and only carry a sign that needs the reserved GBR load that recovers and QoS etc.
The QoS that upgrades bearing request message or create the reserved GBR load that the needs that carry in the bearing request message recover can be the QoS of reserved GBR load when normally moving.In the E-UTRAN environment, for discharge the reserved GBR load that forms owing to the S1 interface, owing to preserve the QoS that maximum rate is reduced to the carrying before zero among the MME, therefore, the QoS when MME can obtain reserved GBR load and normally moves from its canned data.For the maximum rate that passes over from UTRAN is zero carrying, because the QoS that consults when including reserved GBR load in the PDP Context that receives of MME and normally moving, therefore, MME can get access to the QoS of reserved GBR load when normally moving from the PDP Context information that receives.
Need to prove that renewal bearing request message here and establishment bearing request message only are a kind of explanations that exemplifies, the step 11 of present embodiment also can adopt other message, and present embodiment does not limit the message name of concrete employing.
Step 12, Serving GW should upgrade bearing request message and be transmitted to PDN GW after receiving and upgrading bearing request message.
Step 13, PDN GW receive the renewal bearing request message, parse upgrade carry in the bearing request message recover reserved GBR load information after, carry out and recover to keep attitude GBR operation.
The recovery reserved GBR load operation here can have two kinds of different modes:
Mode 1, the definite QoS that needs the reserved GBR load of recovery of PDN GW, for example, PDN GW is by mutual with PCRF or according to the quality of service information that carries in local collocation strategy or transmission comes according to MME the message and consider that mode such as present Internet resources situation determines QoS, recover the core-network side carrying of reserved GBR load correspondence according to this QoS, and QoS sent to MME, make MME indication eNodeB recover the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence.For example, utilize the process that step 2c among the embodiment two describes to step 5 or utilize the process that step 2c among the embodiment three describes to step 5 or utilize the process that step 2b describes to step 5 among the embodiment four to recover reserved GBR load.
Mode 2, PDN GW determine the QoS of the reserved GBR load that needs recover according to present Internet resources situation, and trigger the dedicated bearer modification process of revising QoS, recover reserved GBR load to utilize this bearing modification process.For example, utilize the process that step 2b describes among the embodiment five to recover reserved GBR load.
Step 14, PDN GW send to Serving GW and upgrade bearing response message.If PDN GW adopts mode 1, then PDN GW can increase cell in upgrading bearing response message, this cell is used to carry the reserved GBR load sign of recovery and the QoS of respective carrier, and the reserved GBR load sign can adopt the form of reserved GBR load tabulation.If PDN GW adopts mode 2, then the renewal bearing response message of PDN GW transmission is the message in the existing tracing section updating flow process.
Step 15, Serving GW will upgrade bearing response message and be transmitted to MME after receiving and upgrading bearing response message.If PDN GW adopts mode 1, then still carry the cell that increases newly of the QoS of the reserved GBR load sign that is used to carry recovery and respective carrier in the renewal bearing response message that Serving GW sends, above-mentioned reserved GBR load sign can adopt the form of reserved GBR load tabulation.If PDN GW adopts mode 2, then the renewal bearing response message of Serving GW transmission is the message in the existing tracing section updating flow process.
After step 16, target MME receive and upgrade bearing response message, send the renewal location request message to HSS.
Step 17, HSS send cancel location message to former MME after receiving and upgrading location request message.
Step 18, caused moving under the situation of MME attached to SGSN and routing update originally at UE, former SGSN network element sends Iu to RNC and connects release command.
Step 19, RNC discharge Iu and connect after receiving Iu connection release command, and send Iu connection Release complete to former SGSN.
After step 20, former MME receive cancel location message, return the canceling position acknowledge message to HSS.
Step 21, HSS send renewal position acknowledge message to target MME after receiving the canceling position acknowledge message.
After step 22, target MME receive and upgrade the position acknowledge message, send tracing section updating to UE and accept message.If be provided with " Active Flag " sign in the tracing section updating request message, then this moment S1 interface bearing and wireless side bearing activation.The wireless side carrying is the user plane bearer of wireless side.
Step 23, UE receive after tracing section updating accepts message, send tracing section updating to target MME and finish message.
Embodiment seven is on MME notice PDN GW recovers basis that reserved GBR load and MME change, the corresponding steps of above-mentioned corresponding embodiment is merged in the tracing section updating process, successfully recover reserved GBR load in the tracing section updating process thereby be at UE.
Embodiment eight, UE initiating updating of tracking area, in the tracing section updating process that UE initiates, MME and Serving GW network element all do not change, and MME notice PDN GW recovers reserved GBR load, and PDN GW recovers the reserved GBR load of UE according to the notice of MME.The specific implementation process of embodiment eight as shown in Figure 8.
Among Fig. 8, step 1, under the situation that satisfies the tracing section updating trigger condition, UE triggers the tracing section updating process, UE is provided with in the tracing section updating request message under the situation of " Active Flag " sign, can also in the tracing section updating request message, increase cell, the cell of this increase is used to carry the information relevant with recovering reserved GBR load, needs the reserved GBR load that recovers with indication.
Step 2, UE send the tracing section updating request message to eNodeB, can comprise in this tracing section updating request message: oldGUTI, last visited TAI, active flag, cells such as EPS bearer status, P-TMSI Signature.
After step 3, eNodeB receive the tracing section updating request message, this tracing section updating request message is transmitted to MME.
If step 4 UE is in Idle state, then can carry out authentication/security process.
Step 5, be provided with " Active Flag " sign and MME finds under the situation that has reserved GBR load in the system in the tracing section updating request message, MME send to upgrade bearing request message (i.e. first Indication message).
Can carry the QoS of the GBR carrying tabulation of the reservation attitude that needs recovery and each the GBR carrying correspondence in the tabulation in the renewal bearing request message that MME sends, promptly MME utilizes one to upgrade the information that bearing request message sends all reserved GBR loads that need recover.When the reserved GBR load of needs recovery has many, MME also can upgrade the information that bearing request message sends the reserved GBR load that needs recovery by many, for example, one is upgraded bearing request message and only carries a sign that needs the reserved GBR load that recovers and QoS etc.
The QoS that upgrades the reserved GBR load that the needs that carry in the bearing request message recover can be the QoS of reserved GBR load when normally moving.In the E-UTRAN environment, for discharge the reserved GBR load that forms owing to the S1 interface, owing to preserve the QoS that maximum rate is reduced to the carrying before zero among the MME, therefore, the QoS when MME can obtain reserved GBR load and normally moves from its canned data.For the maximum rate that passes over from UTRAN is zero carrying, because the QoS that consults when including reserved GBR load in the PDP Context that receives of MME and normally moving, therefore, MME can get access to the QoS of reserved GBR load when normally moving from the PDP Context information that receives.
Need to prove that the renewal bearing request message here only is a kind of explanation that exemplifies, the step 5 of present embodiment also can adopt other message, and present embodiment does not limit the message name of concrete employing.
Step 6, Serving GW should upgrade bearing request message and be transmitted to PDN GW after receiving and upgrading bearing request message.
Step 7 or step 7b, PDN GW network element receive and upgrade bearing request message, carry the reserved GBR load information of recovering in the bearing request message if upgrade, and then carry out and recover to keep attitude GBR operation.
The recovery reserved GBR load operation here can have two kinds of different modes, and is concrete as the description among the above-mentioned embodiment seven, in this no longer repeat specification.
Step 8, PDN GW send to Serving GW and upgrade bearing response message.If PDN GW adopts mode 1, then PDN GW can increase cell in upgrading bearing response message, this cell is used to carry the reserved GBR load sign of recovery and the QoS of respective carrier, and the reserved GBR load sign can adopt the form of reserved GBR load tabulation.If PDN GW adopts mode 2, then PDN GW sends and upgrades bearing response message, can not increase above-mentioned cell in this renewal bearing response message.
Step 9, Serving GW will upgrade bearing response message and be transmitted to MME after receiving and upgrading bearing response message.If PDN GW adopts mode 1, then still carry the cell that increases newly of the QoS of the reserved GBR load sign that is used to carry recovery and respective carrier in the renewal bearing response message that Serving GW sends, above-mentioned reserved GBR load sign can adopt the form of reserved GBR load tabulation.If PDN GW adopts mode 2, then can not carry the cell of above-mentioned increase in the renewal bearing response message that Serving GW sends.
After step 10, MME receive and upgrade bearing response message, send tracing section updating to UE and accept message.If be provided with " Active Flag " sign in the tracing section updating request message, then this moment, the carrying of S1 interface bearing and wireless side was activated.
Step 11, UE receive after tracing section updating accepts message, send tracing section updating to target MME and finish message.
Embodiment eight is on MME notice PDN GW recovers basis that reserved GBR load and MME do not change, the corresponding steps of above-mentioned corresponding embodiment is merged in the tracing section updating process, successfully recover reserved GBR load in the tracing section updating process thereby be at UE.
Embodiment nine, UE switch to the E-UTRAN from UTRAN, are that reserved GBR load is set up S1 interface bearing and wireless side carrying in handoff preparation phase, recover the core-network side carrying of reserved GBR load correspondence in handover execution stage.The specific implementation process of embodiment nine is shown in Fig. 9 a and 9b.
Fig. 9 a shows the flow chart of the handoff preparation phase of UE when UTRAN switches to EUTRAN.In handoff preparation phase, the up-downgoing data are normal transmission still.In addition, when not adopting direct pass-through mode to transmit the up-downgoing data, can adopt SGSN to transmit the mode of data.
Among Fig. 9 a, step 1, UE initiate handoff procedure.
Step 2, former RNC send RELOCATION REQUEST message to former SGSN.
Step 3, former SGSN transmit RELOCATION REQUEST message to target MME, and former SGSN transmits S1 bearer context information to target MME.
Step 4, target MME send to target Serving GW and create bearing request message.
Step 4a, target Serving GW send the establishment bearing response message to target MME after receiving the establishment bearing request message.
Step 5, target MME send handoff request message to target eNode B after receiving and creating bearing response message.If target MME is after receiving S1 bearer context information, find that to have maximum rate in the system be zero reserved GBR load, then target MME can carry announcement information in the handoff request message that target eNode B sends, and is that reserved GBR load is set up S1 interface bearing and wireless side carrying with notification target eNodeB.At this moment, the maximum rate of the S1 interface bearing of foundation and wireless side carrying is a non-zero.
Step 5a, target eNode B are after receiving handoff request message, and MME returns switching request acknowledgement message to target.
Step 6, target MME send the establishment bearing request message to target Serving GW after receiving switching request acknowledgement message.
Step 6a, target Serving GW return the establishment bearing response message to target MME after receiving the establishment bearing request message.
Step 7, target MME send relocation response message to former SGSN after receiving the establishment bearing response message.
Step 8, former SGSN send to former Serving GW network element and create bearing request message.
Step 9, former Serving GW return the establishment bearing response message to former SGSN after receiving the establishment bearing request message.
After handoff preparation phase is finished, continue follow-up handover execution stage.Fig. 9 b shows the flow chart of the handover execution stage of UE when UTRAN switches to EUTRAN.In the handover execution stage shown in Fig. 9 b, recover the core-network side carrying of reserved GBR load correspondence.
Among Fig. 9 b, after step 1, handoff preparation phase were finished, former SGSN sent the reorientation order to former RNC.
After step 2, former RNC receive the reorientation order, send from the UTRAN switching command to UE, UE switches to target eNode B with order.
Step 3, former RNC can send the SRNC contextual information to former SGSN.
Step 3a, former SGSN is transmitted to target MME with the SRNC contextual information that receives.
After step 3b, target MME receive the SRNC contextual information, return SRNC context confirmation to former SGSN.
After step 3c, former SGSN receive SRNC context confirmation, send the SRNS contextual information to target eNode B.
Step 4, UE move in the E-UTRAN environment, and carry out the operation that inserts eNodeB.
Step 5, after UE has entered the E-UTRAN environment, send from the UTRAN handoff completion message to target eNode B.
Step 6, target eNode B receive behind the UTRAN handoff completion message, send handoff notification message to target MME.
After step 7, target MME receive handoff notification message, send reorientation to former SGSN and finish message, finish to notify former SGSN to switch.
Step 7a, former SGSN receive after reorientation finishes message, return reorientation to target MME and finish acknowledge message.
Step 8, target MME send and upgrade bearing request message.Find under the situation that has reserved GBR load in the system at target MME, can carry the QoS of the GBR carrying tabulation of the reservation attitude that needs recovery and each the GBR carrying correspondence in the tabulation in the renewal bearing request message (i.e. first Indication message) that target MME sends, promptly target MME utilizes one to upgrade the information that bearing request message sends all reserved GBR loads that need recover.When the reserved GBR load of needs recovery has many, target MME also can upgrade the information that bearing request message sends the reserved GBR load that needs recovery by many, for example, one is upgraded bearing request message and only carries a sign that needs the reserved GBR load that recovers and QoS etc.
The QoS that upgrades the reserved GBR load that the needs that carry in the bearing request message recover can be the QoS of reserved GBR load when normally moving.Target MME can be when the bearer context information that former MME or former SGSN transmission comes be obtained reserved GBR load and is normally moved QoS.
Need to prove that the renewal bearing request message here only is a kind of explanation that exemplifies, the step 5 of present embodiment also can adopt other message, and present embodiment does not limit the message name of concrete employing.
Renewal bearing request message that step 9, target Serving GW will receive, that target MME sends is transmitted to PDN GW.After PDN GW finds to recover reserved GBR load information in upgrading bearing request message, carry out and recover the reserved GBR load operation.
The recovery reserved GBR load operation here can have two kinds of different modes, and is concrete as the description among the above-mentioned embodiment seven, in this no longer repeat specification.
PDN GW sends and upgrades bearing response message after having carried out recovery reservation attitude GBR operation.
The renewal bearing response message that step 10, target Serving GW will receive is transmitted to target MME.If PDN GW adopts mode 1, then still carry the cell that increases newly of the QoS of the reserved GBR load sign that is used to carry recovery and respective carrier in the renewal bearing response message that Serving GW sends, above-mentioned reserved GBR load sign can adopt the form of reserved GBR load tabulation.If PDN GW adopts mode 2, then the renewal bearing response message of Serving GW transmission is the message in the existing tracing section updating flow process.
Step 11, under the situation that satisfies the tracing section updating trigger condition, can trigger the tracing section updating process.Do not recover the reserved GBR load operation if in the step 9 of present embodiment, carry out, then can in this tracing section updating process, recover reserved GBR load.In the tracing section updating process, recover the process of reserved GBR load such as the description of above-mentioned embodiment eight.
Step 12, former SGSN network element send the deleting bearing request message to former Serving GW.
After step 12a, former Serving GW receive the deleting bearing request message, reply the deleting bearing response message to former SGSN.Former SGSN network element discharges original Iu and connects.
If in above-mentioned handoff preparation phase and handover execution stage, reserved GBR load is not recovered, then after switching is finished, still have reserved GBR load in the system.In this case, can utilize other embodiment to recover the GBR carrying, for example, after above-mentioned switching was finished, UE initiated the connected state service request procedure, and recovers reserved GBR load in this service request procedure.In service request procedure, recover the specific implementation process of reserved GBR load such as the description among the above-mentioned embodiment.
In the foregoing description nine, the target MME in the handoff preparation phase by sending handoff request message to target BS, makes target BS can recover the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence after receiving the S1 loading context information; Target MME in the handover execution stage receive switch finish acknowledge message after, upgrade bearing request message by sending to PDN GW, make the PDN GW can be according to the core-network side carrying of this message recovery reserved GBR load correspondence; When recovering the core-network side carrying, the corresponding steps of above-mentioned corresponding embodiment can be merged come in.Thereby be at UE and successfully recover reserved GBR load in the handoff procedure.
The method of embodiment ten, UE triggering PDN GW initiation recovery reserved GBR load as shown in Figure 10.
Among Figure 10, step 1, terminal trigger the bearing resource modification process, and terminal sends the request bearing resource to PDN GW and revises message, to step 2.
The request bearing resource that terminal sends is revised can carry reserved GBR load sign and the quality of service information that needs recovery in the message.Revise reserved GBR load sign and quality of service information that message can be carried needs recovery in order to make the request bearing resource, need revise message to existing request bearing resource expands, as increase new cell, carry reserved GBR load sign and quality of service information to utilize new cell.
The request bearing resource is revised message can transfer to PDN GW by intermediate equipment; For example, the request bearing resource is revised message and is transferred to PDN GW through MME and gateway.
Step 2, PDN GW can revise the information of carrying in the message according to the request bearing resource and judge whether that needs recover the reserved GBR load of terminal after receiving request bearing resource modification message; After determining the reserved GBR load that needs the recovery terminal, PDN GW determines the quality of service information of the reserved GBR load that needs recover according to the current network resources situation, and trigger the dedicated bearing modification process of revising service quality according to this quality of service information, recover core-network side carrying and the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence to utilize the bearing modification flow process.Utilize the bearing modification flow process to recover the specific implementation process of core-network side carrying and the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence, in following embodiment 13, describe.
The PDN GW of the foregoing description ten can successfully recover the core-network side carrying of reserved GBR load correspondence, S1 interface bearing and wireless side carrying by triggering the bearing modification flow process after the request bearing resource that receives the terminal transmission is revised message; Thereby in the bearing resource modification process process that terminal triggers, successfully recover reserved GBR load.
A specific implementation process of the method for embodiment 11, UE triggering PDN GW initiation recovery reserved GBR load as shown in Figure 11.
Among Figure 11, step 1, UE trigger the bearing resource modification process, and UE sends the request bearing resource and revises message, and this bearing resource is revised in the message and included cells such as LBI, PTI, QoS and TAD.
The request bearing resource that UE sends is revised in the message can also increase the cell that is used to carry the information relevant with recovering reserved GBR load.As increase Bearer Id cell and bearer QoS cell, and can carry the reserved GBR load that needs to recover in the Bearer Id cell and identify, bearer QoS cell can carry the quality of service information of the reserved GBR load correspondence that needs recovery.
Step 2, MME revise forwards with its request bearing resource that receives and give Serving GW, and the request bearing resource of this forwarding is revised in the message and included cells such as IMSI, LBI, PTI, QOS and TAD.Carry under the situation of Bearer Id and Bearer QoS cell in the request bearing resource modification message that MME receives, the request bearing resource that MME sends is revised in the message also needs to carry Bearer Id and Bearer QoS cell.
The request bearing resource that step 3, Serving GW will receive is revised forwards and is given PDN GW, and the request bearing resource of this forwarding is revised in the message and included cells such as IMSI, LBI, PTI, QOS and TAD.Carry under the situation of Bearer Id and Bearer QoS cell in the request bearing resource modification message that Serving GW receives, the request bearing resource that Serving GW sends is revised in the message also needs to carry Bearer Id and Bearer QoS cell.
Step 4, PDN GW receive the request bearing resource and revise message.PDN GW finds Bearer Id and Bearer QoS cell in request bearing resource modification message after, determine the quality of service information of the GBR carrying that needs recover according to the current network resources situation.Definite quality of service information of the GBR carrying of recovery that needs here can be as the description among the above-mentioned embodiment, in this no longer repeat specification.
Step 5, PDN GW trigger the dedicated bearer modification process of revising QoS according to the quality of service information of the GBR carrying that the needs of determining recover.
Step 6, indication provides the result of strategy in finishing the IP-CAN session modification process that PCEF initiates.
The PDN GW of the foregoing description 11 can successfully recover the core-network side carrying of reserved GBR load correspondence, S1 interface bearing and wireless side carrying by triggering the bearing modification flow process after the request bearing resource that receives the UE transmission is revised message; Thereby in the bearing resource modification process process that UE triggers, successfully recover reserved GBR load.
The method of embodiment 12, downlink data packet triggering PDN GW initiation recovery reserved GBR load as shown in Figure 12.
Among Figure 12, the downlink data packet of step 1, PDN GW receiving terminal.
After step 2, PDN GW determine the reserved GBR load that is carried as this terminal of this downlink data packet correspondence, trigger the dedicated bearing modification process of revising service quality, recover core-network side carrying and the S1 interface bearing and the wireless side carrying of this reserved GBR load correspondence to utilize this bearing modification flow process.The terminal here can be the terminal that is in Idle state, also can be the terminal that is in connected state.
PDN GW can determine the reserved GBR load that is carried as described terminal of this downlink data packet correspondence when judging the maximum rate that there is the carrying of bearer context and this downlink data packet correspondence in this downlink data packet and be zero.
The PDN GW of the foregoing description 12 can successfully recover the core-network side carrying of reserved GBR load correspondence, S1 interface bearing and wireless side carrying by triggering the bearing modification flow process after receiving the downlink data packet of terminal; Thereby in the downlink data packet transmission course, successfully recover reserved GBR load.
A specific implementation process of the method for embodiment 13, downlink data packet triggering PDN GW initiation recovery reserved GBR load as shown in Figure 13.
Among Figure 13, step 1, PDN GW receive the downlink data packet of UE.
Step 1a, PDN GW find that having the bearer context information of this downlink data packet correspondence and the maximum rate of the corresponding carrying of downlink data packet is zero, then PDN GW determines the quality of service information of the reserved GBR load that needs recover according to current network resources, and trigger the bearing modification flow process, to recover reserved GBR load.The specific implementation process of definite quality of service information here such as the description among the above-mentioned embodiment.
Need to prove, store the QOS of reserved GBR load when normal operation among the PDN GW.The QOS of the reserved GBR load of storing among the PDN GW when normal operation can obtain by following dual mode:
Mode one, for UE from the UTRAN environment moves to the EUTRAN environment maximum rate that time band comes is zero reserved GBR load, because being unifications, PDN GW and GGSN be provided with, QOS value when therefore, PDN GW can obtain and store reserved GBR load and normally moves.
Mode two, in the EUTRAN environment owing to the S1 interface discharges the reserved GBR load cause, the QOS when PDN GW can obtain and store reserved GBR load and normally moves.
Step 2, PDN GW send and upgrade bearing request message.
The renewal bearing request message that step 3, Serving GW will receive is transmitted to MME.Receive at MME upgrade bearing request message, UE is under the situation of ECM_IDLE attitude, the service request procedure that MME trigger network side is initiated, be that MME sends service request information, at this moment, following step 4 to step 7 can merge in the service request procedure that network side initiates, promptly with service request procedure in corresponding message combine.Certainly, step 4 to step 7 also can be carried out according to following order.
Step 4, MME send bearing modification request message or session management request message to eNodeB.
After step 5, eNodB receive bearing modification request message or session management request message, the QoS of EPS carrying is mapped as the QoS of wireless side carrying, and initiates the RRC reconfiguration course.ENodB sends RRC to UE and connects reconfiguration message.
Step 6, UE receive after RRC connects reconfiguration message, send RRC to eNodeB and connect to reshuffle and finish message, to confirm radio bearer modification.
Step 7, eNodeB receive RRC connect reshuffle finish message after, send the bearing modification response message to MME.
Step 8, UE send to eNodeB and directly transmit the session management response message, comprise EPS BearerIdentity cell in this response message.
Step 9, eNodeB send the session management response message to MME, include EPS BearerIdentity cell in this session management response message.
Step 10, MME send to Serving GW and upgrade bearing response message.
Step 11, Serving GW send to PDN GW and upgrade bearing response message.
Step 12, be because under the situation that PCC triggers at bearing modification, PDN GW need be bearing modification is finished after confirms that to PCRF modification finish.
The PDN GW of the foregoing description 13 can successfully recover the core-network side carrying of reserved GBR load correspondence, S1 interface bearing and wireless side carrying by triggering the bearing modification flow process after receiving the downlink data packet of UE; Thereby in the downlink data packet transmission course, successfully recover reserved GBR load.
Embodiment 14, mobile management network element MME.The structure of MME is shown in accompanying drawing 14a and Figure 14 b.
MME shown in Figure 14 a comprises that first receiver module 1410, first recovers judge module 1420 and first and recovers module 1430; MME can also comprise that memory module 1440, acquisition module 1450 and first set up indicating module 1460 alternatively.
First receiver module 1410 is used to receive the message relevant with terminal.The message relevant with terminal that first receiver module 1410 receives can be the message that terminal sends, and for example, is in the service request information of the terminal transmission of connected state; Again for example, be in the service request information of the terminal transmission of Idle state; Also have the tracing section updating request message that terminal sends etc.The message that terminal sends can send by intermediate equipment such as base station.The message relevant with terminal that first receiver module 1410 receives also can be the message that other network entity sends, for example, in the handoff procedure of terminal, the switching request acknowledgement message of acknowledge message and target BS transmission is finished in the switching that the source-end networks equipment that target MME receives sends.When the message relevant with terminal is the message of terminal transmission, can carry the information relevant in this message with recovering reserved GBR load.The reserved GBR load tabulation that information relevant with recovering reserved GBR load such as needs recover recovers the information of whole reserved GBR loads etc. for another example.
First recovers judge module 1420 is used to judge whether and need the reserved GBR load of terminal be recovered.
First structure of recovering judge module 1420 can be shown in Figure 14 b.Among Figure 14 b first recovers judge module 1420 and comprise: first judges the submodule 1421 and/or the second judgement submodule 1422.
First judges that submodule 1421 is used for determining needs according to the relevant information with recovering reserved GBR load that first receiver module, 1410 message relevant with terminal that receive are carried the reserved GBR load of terminal is recovered.For example, first judges that reserved GBR load tabulation that submodule 1421 recovers according to the needs that carry in the message determines needs the reserved GBR load of terminal is recovered; Again for example, first judges that submodule 1421 determines needs according to the information of the whole reserved GBR loads of recovery that carry in the message and the reserved GBR load of terminal is recovered etc.Concrete as the description in the various embodiments described above, no longer describe in detail at this.
Second judges that submodule 1422 is used to find that terminal exists the GBR carrying that keeps attitude then to determine and need the reserved GBR load of terminal be recovered.For example, in first receiver module, 1410 message relevant that receive, do not carry and recover under the situation of the relevant information of reserved GBR load with terminal, second judges that submodule 1422 finds this terminal and whether has the GBR carrying that keeps attitude, have the carrying that keeps attitude GBR if find this terminal, then the second judgement submodule 1422 is determined and need the reserved GBR load of this terminal be recovered.Concrete as the description in the various embodiments described above, no longer describe in detail at this.
First recover module 1430 be used for first recover judge module 1420 determine need recover the reserved GBR load of terminal after, send first Indication message that carries recovery reserved GBR load information to PDN GW, recover the core-network side carrying of this reserved GBR load correspondence with indication PDN GW, and send second Indication message carry quality of service information to the base station, recover the S1 interface bearing and the wireless side carrying of this reserved GBR load correspondence according to quality of service information with the indication base station.
The recovery reserved GBR load information of carrying in above-mentioned first Indication message can be the reserved GBR load sign and the quality of service information that need to recover.When the reserved GBR load of needs recovery is many, the sign and the quality of service information of the reserved GBR load that the first recovery module 1430 can be recovered all needs only send by one first Indication message, also can be by many first Indication messages transmissions.That is to say, article one, can carry an identification information and a quality of service information that needs the reserved GBR load of recovery in first Indication message, at least two reserved GBR loads that need to recover that also can carry in all reserved GBR loads that need recover identify and quality of service information, can also carry all reserved GBR loads that need recover sign and quality of service information.Need to prove, also can not carry quality of service information in first Indication message that the above-mentioned first recovery module 1430 sends.
Carry at first Indication message under the situation of quality of service information, first recovers the quality of service information that module 1430 need be obtained the reserved GBR load that needs recovery earlier, memory module 1440 can provide quality of service information for the first recovery module 1430, and acquisition module 1450 also can provide quality of service information for the first recovery module 1430.
At E-UTRAN, memory module 1440 stores reserved GBR load speed and reduces to zero quality of service information before.
At UTRAN, acquisition module 1450 obtains quality of service information from the PDP Context information that the MME at its place receives.
First first Indication message that recovers module 1430 transmissions can transfer to PDN GW by the gateway of intermediate equipment such as terminal.Under there was more news in the gateway of terminal, first recovers module 1430 can be sent to PDN GW with first Indication message by the gateway after upgrading; For example, the terminal initiating updating of tracking area, the tracing section updating request message that first receiver module, 1410 receiving terminals send by the base station, MME is selecting under the situation of new gateway for terminal, and first recovers module 1430 sends first Indication message that carries recovery reserved GBR load information by the current gateway of terminal to PDN GW; MME is selecting for terminal under the situation of new gateway, and first recovers module 1430 by carrying first Indication message that recovers reserved GBR load information for the new gateway of selecting of terminal sends to PDN GW.First recovers module 1430 can send first Indication message earlier, sends second Indication message again; First recovers module 1430 also can send second Indication message earlier, sends first Indication message again.The different sending orders of first Indication message, second Indication message exemplify description in the various embodiments described above, in this no longer repeat specification.
First sets up indicating module 1460 is used under terminal is in Idle state, first receiver module 1410 receive service request information and first recover judge module judge need recover the reserved GBR load of terminal after, the maximum rate that the reserved GBR load correspondence is set up in the indication base station is zero S1 interface bearing and wireless side carrying, so that the base station is that zero S1 interface bearing and wireless side carrying are provided with maximum rate to maximum rate after receiving second Indication message.
Each module among Figure 14 a and Figure 14 b can be accomplished in several ways the recovery of reserved GBR load, and for example, the operation that each module among Figure 14 a and Figure 14 b is carried out can be as the record among the above-mentioned embodiment two to embodiment nine.No longer describe in detail at this.
From the description of the foregoing description 14 as can be known, MME among the embodiment 14 is by triggering the core-network side carrying that PDN GW recovers the reserved GBR load correspondence, and trigger S1 interface bearing and the wireless side carrying that recovers the reserved GBR load correspondence in the base station, thereby can realize the recovery of reserved GBR load.
Embodiment 15, grouped data network gateway PDN GW.The structure of PDN GW as shown in Figure 15.
PDN GW shown in Figure 15 comprises: second receiver module 1510, second recovers judge module 1520 and second and recovers module 1530.
Second receiver module 1510 is used to receive bearing resource and revises message, and this bearing resource is revised the bearing resource modification message that message is transmitted for trigger the bearing resource modification process owing to terminal.That is to say that terminal triggers the bearing resource modification process, terminal sends the request bearing resource to PDN GW and revises message, and second receiver module 1510 receives this request bearing resource and revises message.This request bearing resource that second receiver module 1510 receives is revised can carry reserved GBR load sign and the quality of service information that needs recovery in the message.This request bearing resource is revised second receiver module 1510 that message can transfer to PDN GW by intermediate equipment; For example, the request bearing resource is revised message transfers to PDN GW through MME and gateway second receiver module 1510.
Second recovers judge module 1520 is used for judging whether that according to the information that the bearing resource modification message that second receiver module 1510 receives is carried needs recover the reserved GBR load of terminal.
Second recover module 1530 second recover judge module 1520 judge need recover the reserved GBR load of terminal after, determine the quality of service information of the reserved GBR load that needs recover according to current network resources, and trigger the dedicated bearing modification process of revising service quality, recover core-network side carrying and the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence to utilize the bearing modification flow process.Utilize the bearing modification flow process to recover the specific implementation process of core-network side carrying and the S1 interface bearing and the wireless side carrying of reserved GBR load correspondence, describe in the above-described embodiments, in this no longer repeat specification.
Second receiver module 1510, second recovers judge module 1520 and the 1530 concrete operations of carrying out of the second recovery module can be as the description among the above-mentioned embodiment 11.
From the description of the foregoing description 15 as can be known, PDN GW among the embodiment 15 is after terminal triggers the bearing resource modification process, core-network side carrying, S1 interface bearing and the wireless side carrying of reserved GBR load correspondence can be recovered by the dedicated bearing modification process that triggers modification service quality, thereby the recovery of reserved GBR load can be in the bearing resource modification process, realized.
Embodiment 16, grouped data network gateway PDN GW.The structure of PDN GW as shown in Figure 16.
PDN GW shown in Figure 16 comprises: the 3rd receiver module the 1610, the 3rd recovers judge module 1620 and the 3rd and recovers module 1630.
The downlink data packet of the 3rd receiver module 1610 receiving terminals.
The 3rd recovers judge module 1620 judges whether the carrying of high downlink data packet correspondence is the reserved GBR load of terminal.The 3rd recovers judge module 1620 can determine the reserved GBR load that is carried as terminal of this downlink data packet correspondence when judging the maximum rate that there is the carrying of bearer context and this downlink data packet correspondence in this downlink data packet and be zero.
The 3rd recovers module 1630 after the 3rd recovery judge module 1620 is determined the reserved GBR load that is carried as terminal of this downlink data packet correspondence, determine the quality of service information of the reserved GBR load that needs recover according to current network resources, and trigger the dedicated bearing modification process of revising service quality, recover core-network side carrying and the S1 interface bearing and the wireless side carrying of this reserved GBR load correspondence to utilize this bearing modification flow process.The terminal here can be the terminal that is in Idle state, also can be the terminal that is in connected state.
The 3rd receiver module the 1610, the 3rd recovers judge module 1620 and the 1630 concrete operations of carrying out of the 3rd recovery module can be as the description among the above-mentioned embodiment 13.
From the description of the foregoing description 16 as can be known, PDN GW among the embodiment 16 is after receiving the downlink data packet of terminal, core-network side carrying, S1 interface bearing and the wireless side carrying of reserved GBR load correspondence can be recovered by the dedicated bearing modification process that triggers modification service quality, thereby the recovery of reserved GBR load can be in the downlink data packet transmission course, realized.
Embodiment 17, grouped data network gateway PDN GW.The structure of PDN GW is shown in accompanying drawing 17a and Figure 17 b.
PDN GW shown in Figure 17 a comprises: the 4th receiver module 1710 and the 4th recovers module 1720.
The 4th receiver module 1710 receives first Indication message that carries recovery reserved GBR load information that MME sends.
The 4th recovers module 1720 behind the 4th receiver module 1710 to first Indication messages, determine the reserved GBR load that needs recover according to the recovery reserved GBR load information of carrying in this first Indication message, and determine the quality of service information of this reserved GBR load according to the current network resources situation, then, recover the maximum rate of the core-network side carrying of reserved GBR load correspondence according to this quality of service information of determining.The 4th mode of recovering the quality of service information of module 1720 definite reserved GBR loads that need recover has multiple, below in conjunction with accompanying drawing 17b the 4th structure of recovering module 1720 is exemplified explanation.
Among Figure 17 b the 4th recovers module 1720 can comprise that determination module 1721 and the 5th recovers module 1722.
Determination module 1721 is according to obtaining the quality of service information requirement that recovers reserved GBR load with the mutual of PCRF or according to local collocation strategy, requires and the current network resources state is determined the quality of service information of reserved GBR load according to the quality of service information that obtains.Determination module 1722 also can be determined the quality of service information of reserved GBR load according to the quality of service information that carries in first Indication message and current network resources state.The 5th recovers module 1722 recovers the maximum rate of the core-network side carrying of reserved GBR load correspondence according to determination module 1721 definite quality of service information.The 5th recovers module 1722 can return response message to MME after successfully recovering the core-network side carrying.The quality of service information of core-network side carrying be can carry in this response message, the quality of service information of core-network side carrying and the GBR bearing identification that success recovers also can be carried.
The 5th recovers module 1722 also can be the 6th recovery module 1723, after the 6th recovery module 1723 is determined the quality of service information of the reserved GBR load that needs recovery at determination module 1721, trigger to revise the dedicated bearing modification process of service quality, with the core-network side carrying of the reserved GBR load correspondence of the terminal of utilizing the bearing modification flow process to recover to be in Idle state or connected state.
The 4th receiver module the 1710, the 4th recovers module 1720, determination module the 1721, the 5th recovers judge module 1722 and the 6th recovery module 1723 can cooperate the relevant art content of finishing record among the embodiment two to embodiment nine with the MME among above-mentioned Figure 14, is not described in detail at this.
From the description of the foregoing description 17 as can be known, PDN GW among the embodiment 17 is after receiving first Indication message, can determine the quality of service information that needs the reserved GBR load that recovers by adopting with modes such as PCRF are mutual, thus the core-network side carrying that can recover the reserved GBR load correspondence.
Embodiment 18, terminal equipment are UE.The structure of terminal equipment as shown in Figure 18.
Terminal equipment shown in Figure 180 comprises: message constructing module 1810 and sending module 1820.
Message constructing module 1810 is carried the information relevant with recovering reserved GBR load in message.This message can be revised message etc. in the service request information of connected state, service request information, tracing section updating request message or the request bearing resource that terminal is in Idle state for end.
Sending module 1820 sends the message that carries the information relevant with recovering reserved GBR load.
Message constructing module 1810 among Figure 18 and sending module 1820 concrete operations of carrying out such as the record in above-mentioned embodiment one to three, six to seven and embodiment ten and 11 no longer describe in detail at this.
From the description of the foregoing description 18 as can be known, terminal equipment among the embodiment 18 is by carrying the information relevant with recovering reserved GBR load in the message of structure, make the reserved GBR load that MME or PDN GW can be known needs recovery, thereby can make MME or PDN GW continue the process of follow-up recovery reserved GBR load.
Through the above description of the embodiments, those skilled in the art can be well understood to the present invention and can realize by the mode that software adds essential hardware platform, can certainly all implement, but the former is better execution mode under a lot of situation by hardware.Based on such understanding, all or part of can the embodying that technical scheme of the present invention contributes to background technology with the form of software product, this computer software product can be stored in the storage medium, as ROM/RAM, magnetic disc, CD etc., comprise that some instructions are with so that a computer equipment (can be a personal computer, server, the perhaps network equipment etc.) carry out the described method of some part of each embodiment of the present invention or embodiment.
Though described the present invention by embodiment, those of ordinary skills know, the present invention has many distortion and variation and do not break away from spirit of the present invention, and the claim of application documents of the present invention comprises these distortion and variation.

Claims (27)

1. a method of recovering reserved GBR load is characterized in that, comprising:
Mobile management network element MME receives the message relevant with terminal;
After described MME determines and need recover the reserved GBR load of described terminal, send first Indication message that carries recovery reserved GBR load information to grouped data network gateway PDNGW, recover the core-network side carrying of this reserved GBR load correspondence with indication PDN GW, described MME sends second Indication message that carries quality of service information to the base station, recovers the S1 interface bearing and the wireless side carrying of this reserved GBR load correspondence according to described quality of service information with the indication base station.
2. the method for claim 1 is characterized in that, the described message relevant with terminal comprises:
Be in the service request information of the terminal transmission of connected state; Perhaps
Be in the service request information of the terminal transmission of Idle state; Perhaps
The tracing section updating request message that terminal sends; Perhaps
Finish acknowledge message at the network equipment before in S1 loading context information that target MME sends and hand-off execution process, switching in the switching set-up procedure of described terminal to the switching that target MME sends.
3. the method for claim 1 is characterized in that, described MME determines the step that need recover the reserved GBR load of described terminal and comprises following at least one step:
Described MME according to receive with the relevant message of terminal in the relevant information with recovering reserved GBR load of carrying determine needs the reserved GBR load of terminal recovered; Perhaps
Described MME finds that described terminal exists the GBR carrying that keeps attitude then to determine and need the reserved GBR load of terminal be recovered.
4. method as claimed in claim 3 is characterized in that, the described information relevant with recovering reserved GBR load comprises: the reserved GBR load that needs recover is tabulated or is recovered the information of whole reserved GBR loads.
5. the method for claim 1 is characterized in that, described recovery reserved GBR load information comprises: reserved GBR load sign and quality of service information that needs recover; And described MME sends described recovery reserved GBR load information by at least one the first Indication messages to PDNGW.
6. method as claimed in claim 5 is characterized in that, the quality of service information that carries in described first Indication message is:
At E-UTRAN, the reserved GBR load speed of described MME storage is reduced to the quality of service information before zero; Perhaps
At UTRAN, the quality of service information that described MME obtains from the PDP Context information that receives.
7. the method for claim 1 is characterized in that, described method also comprises:
After described PDN GW receives described first Indication message, determine the quality of service information of described reserved GBR load according to the current network resources state, and recover the maximum rate of the core-network side carrying of described reserved GBR load correspondence, and return response message to described MME according to described definite quality of service information.
8. method as claimed in claim 7 is characterized in that, describedly determines that according to the current network resources state quality of service information of described reserved GBR load comprises:
From first Indication message, obtain quality of service information, and determine the quality of service information of described reserved GBR load according to the described quality of service information that obtains and current network resources state; Perhaps
According to PCRF obtain quality of service requirement alternately, and determine the quality of service information of described reserved GBR load according to described quality of service requirement and current network resources situation; Perhaps
Obtain quality of service requirement according to local collocation strategy, and determine the quality of service information of described reserved GBR load according to described quality of service requirement and current network resources situation.
9. method as claimed in claim 7 is characterized in that:
Carry described definite quality of service information in the described response message, and MME comprises to second Indication message that carries quality of service information that the base station sends:
Described MME receives described response message, the quality of service information that carries in the described response message is carried in second Indication message, and sends described second Indication message to the base station;
Carries described definite quality of service information in the perhaps described response message and successfully recover the reserved GBR load sign of core-network side carrying, and MME comprises to second Indication message that the base station transmission carries quality of service information:
Described MME receives described response message, quality of service information that carries in the described response message and the reserved GBR load sign of successfully recovering the core-network side carrying is carried in second Indication message, and sends described second Indication message to the base station.
10. the method for claim 1 is characterized in that, described method also comprises:
Described base station receives described second Indication message, sets up the carrying of S1 interface bearing and wireless side, and the maximum rate of described S1 interface bearing and wireless side carrying is set according to the quality of service information that carries in described second Indication message; Perhaps
Described base station receives described second Indication message, search S1 interface bearing described reserved GBR load correspondence, success foundation and wireless side carrying, and the maximum rate of described S1 interface bearing and wireless side carrying is set according to the quality of service information that carries in described second Indication message.
11. method as claimed in claim 10 is characterized in that, S1 interface bearing described reserved GBR load correspondence, success foundation and wireless side carrying comprise:
Under terminal was in Idle state, MME was after the service request that receives described terminal transmission, and the maximum rate of the described reserved GBR load correspondence that the indication base station is set up is zero S1 interface bearing and wireless side carrying.
12. the method for claim 1 is characterized in that, described method also comprises:
Described PDN GW is after receiving described first Indication message, determine the quality of service information of described reserved GBR load according to the current network resources state, and trigger to revise the dedicated bearing modification process of service quality, with the core-network side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state;
And described second Indication message is: the message in the described bearing modification flow process.
13. a method of recovering reserved GBR load is characterized in that, described method comprises:
PDN GW receives the request bearing resource and revises message, and the described request bearing resource is revised message and revised message for the request bearing resource that transmits owing to terminal triggering bearing resource modification process;
After described PDN GW revises message and determines needs the reserved GBR load of described terminal is recovered according to the described request bearing resource, determine the quality of service information of described reserved GBR load, and trigger to revise the dedicated bearing modification process of service quality, with core-network side carrying and the S1 interface bearing and the wireless side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
14. method as claimed in claim 13 is characterized in that, the described request bearing resource is revised in the message and is comprised: the quality of service information of the reserved GBR load that the bearing identification of the reserved GBR load that needs recover and described needs recover.
15. a method of recovering reserved GBR load is characterized in that, described method comprises:
The downlink data packet of PDN GW receiving terminal;
After described PDN GW determines the reserved GBR load that is carried as described terminal of this downlink data packet correspondence, determine the quality of service information of described reserved GBR load, and trigger to revise the dedicated bearing modification process of service quality, with core-network side carrying and the S1 interface bearing and the wireless side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
16. method as claimed in claim 15 is characterized in that, described PDN GW determines that the reserved GBR load that is carried as described terminal of this downlink data packet correspondence comprises:
Described PDN GW determines the reserved GBR load that is carried as described terminal of this downlink data packet correspondence when judging maximum rate that described downlink data packet exists bearer context and this carrying and be zero.
17. a mobile management network element is characterized in that, comprising:
First receiver module is used to receive the message relevant with terminal;
First recovers judge module, is used to judge whether and need the reserved GBR load of described terminal be recovered;
First recovers module, be used for first recover judge module determine need recover the reserved GBR load of described terminal after, send first Indication message that carries recovery reserved GBR load information to PDN GW, recover the core-network side carrying of this reserved GBR load correspondence with indication PDN GW, and send second Indication message carry quality of service information to the base station, recover the S1 interface bearing and the wireless side carrying of this reserved GBR load correspondence according to described quality of service information with the indication base station.
18. mobile management network element as claimed in claim 17 is characterized in that, first recovers judge module comprises:
First judges submodule, and the relevant information with recovering reserved GBR load that the message relevant with terminal that is used for receiving according to described first receiver module is carried is determined needs the reserved GBR load of terminal is recovered; Perhaps
Second judges submodule, is used to find that described terminal exists the GBR carrying that keeps attitude then to determine and need the reserved GBR load of terminal be recovered.
19. mobile management network element as claimed in claim 17 is characterized in that, described mobile management network element also comprises:
Memory module is used at E-UTRAN, and storage reserved GBR load speed is reduced to the quality of service information before zero; And the quality of service information that the described first recovery module will be obtained from memory module is carried in first Indication message; And/or
Acquisition module is used at UTRAN, obtains quality of service information from the PDP Context information that MME receives; And the quality of service information that the described first recovery module gets access to described acquisition module is carried in first Indication message.
20. mobile management network element as claimed in claim 17 is characterized in that, described mobile management network element also comprises:
First sets up indicating module, be used under terminal is in Idle state, first receiver module receive service request and first that described terminal sends recover judge module determine need recover the reserved GBR load of described terminal after, the maximum rate that described reserved GBR load correspondence is set up in the indication base station is zero S1 interface bearing and wireless side carrying.
21. a grouped data network gateway is characterized in that, described grouped data network gateway comprises:
Second receiver module is used to receive bearing resource and revises message, and described bearing resource is revised the bearing resource modification message that message is transmitted for trigger the bearing resource modification process owing to terminal;
Second recovers judge module, is used for revising message according to described bearing resource and judges whether that needs recover the reserved GBR load of described terminal;
Second recovers module, be used for second recover judge module determine need recover the reserved GBR load of described terminal after, trigger to revise the dedicated bearing modification process of service quality, with core-network side carrying and the S1 interface bearing and the wireless side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
22. a grouped data network gateway is characterized in that, described grouped data network gateway comprises:
The 3rd receiver module is used for the downlink data packet of receiving terminal;
The 3rd recovers judge module, is used to judge whether the carrying of described downlink data packet correspondence is the reserved GBR load of described terminal;
The 3rd recovers module, be used for after described the 3rd recovery judge module is determined the reserved GBR load that is carried as described terminal of this downlink data packet correspondence, trigger to revise the dedicated bearing modification process of service quality, with core-network side carrying and the S1 interface bearing and the wireless side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
23. a grouped data network gateway is characterized in that, described grouped data network gateway comprises:
The 4th receiver module is used to receive first Indication message that carries recovery reserved GBR load information that MME sends;
The 4th recovers module, be used for after the 4th receiver module receives described first Indication message, determine the quality of service information of described reserved GBR load, and recover the maximum rate of the core-network side carrying of described reserved GBR load correspondence according to described definite quality of service information.
24. a kind of grouped data network gateway as claimed in claim 23 is characterized in that, the described the 4th recovers module comprises:
Determination module, be used for after the 4th receiver module receives described first Indication message, according to obtaining the quality of service requirement of described recovery reserved GBR load, determine the quality of service information of described reserved GBR load according to the described quality of service requirement that obtains and current network resources state with the mutual of PCRF or according to local collocation strategy; Perhaps determine the quality of service information of described reserved GBR load according to the quality of service information that carries in described first Indication message and current network resources state;
The 5th recovers module, is used for recovering according to the quality of service information that described determination module is determined the maximum rate of the core-network side carrying of described reserved GBR load correspondence.
25. a kind of grouped data network gateway as claimed in claim 24 is characterized in that, the described the 5th recovers module comprises:
The 6th recovers module, the quality of service information that is used for determining according to described determination module triggers the dedicated bearing modification process of revising service quality, with the core-network side carrying of the described reserved GBR load correspondence of the terminal of utilizing described bearing modification flow process to recover to be in Idle state or connected state.
26. a terminal equipment is characterized in that, described terminal equipment comprises:
The message constructing module is used for carrying the information relevant with recovering reserved GBR load in message;
Sending module is used to send the described message that carries the information relevant with recovering reserved GBR load.
27. terminal equipment as claimed in claim 26 is characterized in that, described message comprises: terminal is in the service request information of connected state, service request information, tracing section updating request message or the request bearing resource that terminal is in Idle state revised message.
CN 200810225719 2008-11-07 2008-11-07 Method and device for recovering reserved GBR load Active CN101742576B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200810225719 CN101742576B (en) 2008-11-07 2008-11-07 Method and device for recovering reserved GBR load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200810225719 CN101742576B (en) 2008-11-07 2008-11-07 Method and device for recovering reserved GBR load

Publications (2)

Publication Number Publication Date
CN101742576A true CN101742576A (en) 2010-06-16
CN101742576B CN101742576B (en) 2013-06-05

Family

ID=42465282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200810225719 Active CN101742576B (en) 2008-11-07 2008-11-07 Method and device for recovering reserved GBR load

Country Status (1)

Country Link
CN (1) CN101742576B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101883430A (en) * 2010-06-28 2010-11-10 新邮通信设备有限公司 Radio resource control (RRC) connection reestablishment method
WO2011110000A1 (en) * 2010-08-20 2011-09-15 华为技术有限公司 Method and apparatus for reporting radio bearer loss message
WO2012025031A1 (en) * 2010-08-23 2012-03-01 中兴通讯股份有限公司 Method and system for bearer setup based on local access
WO2012024989A1 (en) * 2010-08-23 2012-03-01 中兴通讯股份有限公司 Method and system for bearer release
WO2016150046A1 (en) * 2015-03-25 2016-09-29 中兴通讯股份有限公司 Method, device and system for reducing dropped-call rate
WO2017101117A1 (en) * 2015-12-18 2017-06-22 华为技术有限公司 Method and device for redirection
US9730263B2 (en) 2009-04-27 2017-08-08 Huawei Technologies Co., Ltd. Service recovery method, apparatus, and system for a wireless communication network
WO2017166927A1 (en) * 2016-03-30 2017-10-05 中兴通讯股份有限公司 Information notification method and apparatus
CN108476546A (en) * 2015-12-29 2018-08-31 Lg 电子株式会社 The method and apparatus for establishing the carrying of the transmission for user data
CN109392014A (en) * 2017-08-14 2019-02-26 电信科学技术研究院 A kind of acceptance controlling method and communication device of QoS flow
US10893404B2 (en) 2015-08-14 2021-01-12 Zte Corporation Gateway recovery processing method and device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1917706B (en) * 2006-08-18 2011-01-19 华为技术有限公司 Method for configuring resources of up-link channel, and corresponging terminal, base staion and system

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9730263B2 (en) 2009-04-27 2017-08-08 Huawei Technologies Co., Ltd. Service recovery method, apparatus, and system for a wireless communication network
US10098163B2 (en) 2009-04-27 2018-10-09 Huawei Technologies Co., Ltd. Service recovery method, apparatus, and system for a wireless communication network
CN101883430A (en) * 2010-06-28 2010-11-10 新邮通信设备有限公司 Radio resource control (RRC) connection reestablishment method
WO2011110000A1 (en) * 2010-08-20 2011-09-15 华为技术有限公司 Method and apparatus for reporting radio bearer loss message
CN102232301A (en) * 2010-08-20 2011-11-02 华为技术有限公司 Method and apparatus for reporting radio bearer loss message
US10075865B2 (en) 2010-08-20 2018-09-11 Huawei Technologies Co., Ltd. Method and apparatus for reporting radio bearer loss information
US9060305B2 (en) 2010-08-20 2015-06-16 Huawei Technologies Co., Ltd. Method and apparatus for reporting radio bearer loss information
US10812999B2 (en) 2010-08-20 2020-10-20 Huawei Technologies Co., Ltd. Method and apparatus for reporting radio bearer loss information
WO2012025031A1 (en) * 2010-08-23 2012-03-01 中兴通讯股份有限公司 Method and system for bearer setup based on local access
CN102378160B (en) * 2010-08-23 2015-11-25 中兴通讯股份有限公司 Based on carrying establishing method and the system of this locality access
CN102378160A (en) * 2010-08-23 2012-03-14 中兴通讯股份有限公司 Local access-based load bearing establishing method and system
WO2012024989A1 (en) * 2010-08-23 2012-03-01 中兴通讯股份有限公司 Method and system for bearer release
WO2016150046A1 (en) * 2015-03-25 2016-09-29 中兴通讯股份有限公司 Method, device and system for reducing dropped-call rate
US10893404B2 (en) 2015-08-14 2021-01-12 Zte Corporation Gateway recovery processing method and device
US10455380B2 (en) 2015-12-18 2019-10-22 Huawei Technologies Co., Ltd. Redirection method and apparatus
CN108370613A (en) * 2015-12-18 2018-08-03 华为技术有限公司 A kind of method and device of redirection
WO2017101117A1 (en) * 2015-12-18 2017-06-22 华为技术有限公司 Method and device for redirection
CN108476546A (en) * 2015-12-29 2018-08-31 Lg 电子株式会社 The method and apparatus for establishing the carrying of the transmission for user data
CN108476546B (en) * 2015-12-29 2021-11-09 Lg 电子株式会社 Method and apparatus for establishing bearer for transmission of user data
CN107295452A (en) * 2016-03-30 2017-10-24 中兴通讯股份有限公司 A kind of information notice method and device
WO2017166927A1 (en) * 2016-03-30 2017-10-05 中兴通讯股份有限公司 Information notification method and apparatus
CN107295452B (en) * 2016-03-30 2021-06-08 中兴通讯股份有限公司 Information notification method and device
CN109392014A (en) * 2017-08-14 2019-02-26 电信科学技术研究院 A kind of acceptance controlling method and communication device of QoS flow
CN109392014B (en) * 2017-08-14 2020-11-24 电信科学技术研究院 QoS flow admission control method and communication device

Also Published As

Publication number Publication date
CN101742576B (en) 2013-06-05

Similar Documents

Publication Publication Date Title
CN101742576B (en) Method and device for recovering reserved GBR load
CN101370001B (en) Information transfer method
CN101605353B (en) Data communication method, communication system and relevant device
CN101588325B (en) Disaster recovery method, device and system based on wireless packet gateways
JP5478737B2 (en) Method and device for group-based mobility optimization in machine type communication
CN101888617B (en) Processing method and system of access point name constraint information and network element device and gateway device
CN101552977B (en) Load creating method and mobility management entity
US20120327893A1 (en) Method, Device, and System for Reporting Radio Access Network Element Information
EP3490280B1 (en) Session management entity relocation
CN102076038A (en) Method and device for implementing oop initialization prearranged assignment (LIPA) connection switching preparation process
CN101128053A (en) Method, element and system for switching between core network control systems
CN103249096B (en) A kind of switching handling method, equipment and system
CN103338487A (en) Method and equipment for intersystem reselection or switching processing
CN101990174A (en) Message sending method and SGSNs (Serving GPRS (General Packet Radio Service) Supporting Node)
EP3986082B1 (en) User plane gateway updating methods, mobility management entity, computer-readable storage medium and communications system
CN101553011B (en) Method for confirming default bearing and mobile management entity
CN101742696A (en) Method and device for transferring information
CN102413562B (en) Management method and equipment of PDN (Packet Data Network) connection
CN101877841B (en) Method, system and network equipment for realizing urgent services
CN101594607B (en) Maintaining method, system and device of gateway information of packet data network
EP3737199B1 (en) Communication network component and method for handling a service request
CN101621783A (en) Method and system for avoiding redundant position update, user equipment and network
CN108307457B (en) Message routing method and device
CN101772096A (en) Information acquisition method, device and system
CN101594572A (en) Bearer resource processing method, system and device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant