WO2026011864A1 - 一种贝雷架用装配式钢栈桥板结构体系及其施工工艺 - Google Patents
一种贝雷架用装配式钢栈桥板结构体系及其施工工艺Info
- Publication number
- WO2026011864A1 WO2026011864A1 PCT/CN2025/087750 CN2025087750W WO2026011864A1 WO 2026011864 A1 WO2026011864 A1 WO 2026011864A1 CN 2025087750 W CN2025087750 W CN 2025087750W WO 2026011864 A1 WO2026011864 A1 WO 2026011864A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- trestle
- steel
- bailey
- steel pipe
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
- E01D19/125—Grating or flooring for bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D15/00—Movable or portable bridges; Floating bridges
- E01D15/12—Portable or sectional bridges
- E01D15/133—Portable or sectional bridges built-up from readily separable standardised sections or elements, e.g. Bailey bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/10—Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
- E01D19/103—Parapets, railings ; Guard barriers or road-bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/30—Metal
Definitions
- This invention relates to the field of steel trestle technology, and more specifically, to a prefabricated steel trestle structure system for Bailey bridges and its construction process.
- the existing steel trestle bridge is usually laid by using ordinary steel plates along the length of the bridge deck and fixing them with bolts on both sides. After the laying is completed, the steel plates of the trestle bridge are only constrained in the length direction, while the adjacent trestle plates are not properly constrained. Therefore, when subjected to the torque generated by large vehicles, especially when large vehicles turn, the steel plates are prone to deflection under stress, which can lead to large gaps between adjacent trestle plates and create certain safety hazards.
- the steel trestle bridge is connected to the Bailey bridge on both sides with bolts. Over time, the vibrations from construction vehicles can cause the bolts to loosen and fall off. Furthermore, the steel trestle bridge and the Bailey bridge require both to align their connection nodes to achieve a bolted connection. If the connection nodes between the steel trestle bridge's I-beams and the Bailey bridge are misaligned, effective fixation is not possible.
- the purpose of this invention is to overcome the shortcomings of existing technologies and provide a prefabricated steel trestle structure system for Bailey bridges and its construction process.
- the steel trestle of this invention is prefabricated and welded from multiple sets of patterned H-beams. Its strength, friction, and load-bearing capacity can meet and exceed the performance of existing steel trestles, realizing the integration of the trestle and beam, greatly simplifying the installation process. Furthermore, during the laying of the steel trestle, it only needs to be fixed with U-bolt clamps, eliminating the need for on-site welding. It is recyclable, reusable, and can be replaced locally, effectively saving costs and realizing resource recycling, thus possessing extremely high use value.
- the present invention discloses a prefabricated steel trestle structure system for Bailey bridges, comprising a trestle body, wherein mounting portions are provided at intervals on the side of the trestle body, and longitudinal connecting holes are provided on the side of the mounting portions. Longitudinal connecting bolts are installed in the longitudinal connecting holes. Two adjacent trestle bodies along the length of the steel trestle bridge deck are fixed together by the longitudinal connecting bolts passing through the longitudinal connecting holes.
- the trestle plate body is made by laying multiple sets of patterned H-beams flat and then welding them together.
- railing connection parts are provided at the four corners of the trestle board body.
- Railing connection holes are opened on the side of the railing connection parts.
- Railing fixing bolts are installed in the railing connection holes. The railings are placed on the side of the trestle board body and assembled with the railing connection holes of the trestle board body through the railing fixing bolts.
- the interior of the mounting part is configured as a cavity structure, and a lifting hole is provided at the top of the inner cavity of the mounting part.
- the upper and lower parts of the inner cavity of the mounting part are both fixedly welded with hoisting reinforcing ribs.
- a positioning plate is provided in the middle of the inner cavity of the mounting part, mounting holes are provided at intervals at the bottom of the inner cavity of the mounting part, and mounting holes are also provided on the surface of the positioning plate.
- a Bailey bridge frame is provided at the bottom of the trestle plate body, and a limiting device is provided at the connection between the trestle plate body and the Bailey bridge frame.
- the lower end of the limiting device passes through the Bailey bridge frame, and the upper end of the limiting device is sequentially installed with a mounting part and a positioning plate, and is fixed to the positioning plate by mounting bolts.
- a Bailey bridge frame is provided at the bottom of the trestle plate body, and an installation auxiliary component is provided at the connection between the trestle plate body and the Bailey bridge frame.
- the longitudinal section of the installation auxiliary component is U-shaped, the upper end of the installation auxiliary component is welded to the trestle plate body, and the lower end of the installation auxiliary component is fixed relative to the upper beam of the Bailey bridge frame.
- the installation auxiliary component can be a U-shaped hook or an L-shaped hook.
- a construction process for a prefabricated steel trestle structure system for Bailey bridges comprising the following steps:
- Step 1 Measurement and layout
- the coordinates of each steel pipe pile were calculated based on the construction layout plan. The calculation results were submitted to the chief engineer of the project for review. After confirmation, field surveying was carried out.
- the steel pipe piles were initially positioned using GPS and monitored throughout the process using a total station. During the pile driving process, two total stations were used at a 90-degree angle to monitor the deviation of the steel pipe piles to ensure the quality of the pile position.
- Step Two Steel Pipe Pile Construction
- the steel pipe piles of the steel platform are treated with anti-corrosion.
- the pipe piles are transported to the construction site by transport vehicle. Due to the long size, heavy weight and easy rolling of the steel pipe piles, steel pipe piles must be tied and reinforced with steel wire ropes to ensure transportation safety.
- steel pipe piles are transported to the site and pass the acceptance, they are spliced into a whole according to the design length. In order to ensure the welding quality, the welding quality meets the requirements of the second-level weld.
- control points of the traverse network are accurately laid out to locate the center point of the pile.
- a guide frame is installed, and a crane is used to lift the assembled steel pipe pile and place it into the guide frame.
- the system uses hydraulic clamps, which quickly clamp and release steel pipes by oil inlet and outlet of hydraulic cylinders.
- the clamps hold the steel pipe piles, while a crawler crane suspends the top of the steel pipe piles with a spare wire rope.
- the crawler crane directly lifts the steel pipe pile using a vibratory hammer and a spare wire rope. Guided by measurements, the steel pipe pile is adjusted to the marked position and then quickly lowered. Once the pile stabilizes in the soil under its own weight, the vibratory hammer is activated to further drive it down. The duration of each vibration must be precisely controlled; too long a duration will damage the hammer, while too short a duration will hinder sinking. Each pile should be driven down in one continuous motion, without interruption or prolonged gaps, to prevent soil regeneration around the pile and subsequent sinking difficulties. During the vibratory sinking process, measuring instruments continuously monitor the verticality.
- the hydraulic hammer is hoisted to clamp the pile, and vibration is continued to drive the steel pipe pile to the design elevation of the pile bottom;
- Step 3 Installation of the substructure of the steel trestle bridge
- the horizontal bracing and diagonal bracing are connected.
- the horizontal bracing and diagonal bracing are made of 20 channel steel shear bracing.
- the connection between the steel pipe piles and the horizontal bracing is made by welding.
- the steel platform load-bearing beam is constructed using H400 ⁇ 400 ⁇ 13 ⁇ 21.
- the beam is placed inside the grooves cut into the top of the steel pipe piles and stiffening plates welded at the pile openings.
- the double-section steel I-beams are processed in the back-end and installed on-site. First, the axis and position of the load-bearing beam are marked on the steel pipe piles. Then, grooves are cut into the top of the steel pipe piles and stiffening plates are welded inside the pile openings. The beams are then lifted, installed, and welded together.
- Step 4 Installation of the superstructure of the steel trestle bridge
- the Bailey bridge is assembled into a group in the back field according to the design span, transported to the front field and installed in place by crane.
- Each group of Bailey bridges is connected to the support frame welded with steel sections to form a whole.
- the group is connected by a fixed flower rack to ensure the overall stability.
- the Bailey bridge is connected to the load-bearing beam through a limiting device.
- the trestle panels are laid and fixed to the Bailey bridge frame using limiting devices; two adjacent trestle panels along the length of the steel trestle bridge deck are fixed together using longitudinal connecting bolts.
- the steel trestle of the present invention is prefabricated and welded by splicing multiple sets of patterned H-beams. Its strength, friction and bearing capacity can meet the requirements of the use of steel trestle. In addition, during the laying process of steel trestle, it only needs to be fixed by bolts. No on-site welding is required. It can be recycled, reused, and can be replaced locally. It effectively saves costs, realizes resource recycling, and has extremely high use value.
- the railing connection hole as a side opening, the railing can be installed on the side of the trestle board body, thus not occupying the upper part of the trestle board body, and reserving more bridge surface operation space for the trestle board body without losing safety protection.
- the installation part of the present invention can be used as a connection node between two adjacent bridge panels, as a hoisting node for the bridge panel body, and as a fixing node between the bridge panel body and the Bailey bridge frame, thereby achieving multi-functionality.
- the present invention can be assembled by laying multiple sets of bridge deck bodies to form a corresponding bridge deck structure system; the connection between the bridge deck body and the Bailey frame is provided with installation auxiliary parts or limiting devices, so as to achieve relative fixation between the bridge deck body and the Bailey frame, and avoid the bridge deck body from shaking.
- the installation auxiliary parts, together with the limiting devices and installation bolts, can effectively prevent the installation bolts from loosening or falling off, and improve safety and stability.
- Figure 1 is a front view of the trestle plate body of the present invention
- Figure 2 is a partial enlarged view of the mounting part of the present invention
- Figure 3 is a side view of the trestle plate body of the present invention.
- Figure 4 is a top view of the trestle plate body of the present invention.
- Figure 5 is a diagram showing the splicing effect of the trestle plate body of the present invention.
- Figure 6 is an enlarged view of the connection effect of the mounting part of the present invention.
- Figure 7 is a diagram showing the installation effect of the railing according to the present invention.
- Figure 8 is an enlarged view of the partial installation effect of the railing of the present invention.
- Figure 9 is a diagram showing the fixed state of the trestle plate body of the present invention.
- Figure 10 is a schematic diagram of the installation auxiliary component of the present invention.
- Figure 11 is a schematic diagram of the installation of the steel pipe pile of the present invention.
- Figure 12 is an installation diagram of the Bailey bridge frame of the present invention.
- Trestle board body 11. Mounting part; 111. Longitudinal connecting hole; 112. Longitudinal connecting bolt; 113. Lifting hole; 114. Lifting reinforcing rib; 115. Positioning plate; 116. Mounting hole; 12. Guardrail connecting part; 121. Guardrail connecting hole; 122. Guardrail fixing bolt; 2. Bailey bridge; 3. Limiting device; 31. Mounting bolt; 4. Installation auxiliary parts; 5. Guardrail.
- a prefabricated steel trestle for Bailey bridges in this embodiment includes a trestle body 1.
- the sides of the trestle body 1 are provided with mounting parts 11 at intervals.
- the sides of the mounting parts 11 are provided with longitudinal connecting holes 111.
- Longitudinal connecting bolts 112 are installed in the longitudinal connecting holes 111.
- Two adjacent trestle body 1s along the length of the steel trestle bridge deck are fixed together by the longitudinal connecting bolts 112 passing through the longitudinal connecting holes 111.
- the main body of the trestle deck 1 is made by laying multiple sets of patterned H-beams flat and then welding them together.
- the steel trestle of this invention is prefabricated and welded from multiple sets of patterned H-beams. Its strength, friction, and load-bearing capacity can all meet the requirements for use as a steel trestle. Furthermore, during the laying process, the steel trestle only needs to be fixed with bolts, eliminating the need for on-site welding. It is recyclable, reusable, and can be replaced locally, effectively saving costs and realizing resource recycling, thus possessing extremely high use value.
- the main body 1 of the trestle plate which is laid along the length of the steel trestle bridge, is fixed to the Bailey frame 2 by bolts or limiting components;
- the trestle plate body 1 is laid along the length of the steel trestle bridge. Two adjacent trestle plate bodies 1 are fixed by longitudinal connecting bolts 112, which can effectively prevent the trestle plate body 1 from deflecting due to torque, and can ensure that there are no gaps between the trestle plate bodies 1, effectively eliminating safety hazards.
- a prefabricated steel trestle for Bailey bridges has railing connection parts 12 at the four corners of the trestle body 1.
- the side of the railing connection part 12 has railing connection holes 121.
- Railing fixing bolts 122 are installed in the railing connection holes 121.
- the railing 5 is placed on the side of the trestle body 1 and assembled with the railing connection holes 121 of the trestle body 1 through the railing fixing bolts 122.
- the railing connection hole 121 as a side opening, the railing 5 can be installed on the side of the trestle body 1, thus not occupying the upper usable area of the trestle body 1, and reserving more bridge surface operation space for the trestle body 1 without losing safety protection.
- the width direction of the trestle plate body 1 is the same as the length direction of the steel trestle, and the length direction of the trestle plate body 1 is the same as the width direction of the steel trestle.
- the trestle plate body 1 is a prefabricated component. Usually, the length of one trestle plate body 1 is equal to the width of the steel trestle. When the length of one trestle plate body 1 cannot meet the width requirement of the steel trestle, the trestle plate bodies 1 can be laid sequentially along the width direction of the steel trestle. At this time, the railing connection hole 121 can be used as the connection hole of the trestle plate body 1.
- the interior of the mounting part 11 is a hollow structure, and a lifting hole 113 is provided at the top of the inner cavity of the mounting part 11.
- the upper and lower parts of the inner cavity of the mounting part 11 are fixedly welded with hoisting reinforcing ribs 114.
- a positioning plate 115 is provided in the middle of the inner cavity of the mounting part 11, and mounting holes 116 are provided at intervals at the bottom of the inner cavity of the mounting part 11. Mounting holes 116 are also provided on the surface of the positioning plate 115.
- the mounting section 11 can serve as a connection node between two adjacent bridge deck bodies 1, a hoisting node for the bridge deck body 1, and a fixing node between the bridge deck body 1 and the Bailey bridge 2, thus achieving multi-functionality.
- a prefabricated steel trestle bridge system for Bailey bridges is provided at the bottom of the trestle bridge body 1. By laying multiple sets of trestle bridge body 1, the corresponding bridge deck structure system can be assembled.
- a limiting device 3 is provided at the connection between the trestle plate body 1 and the Bailey bridge 2.
- the lower end of the limiting device 3 passes through the Bailey bridge 2, and the upper end of the limiting device 3 is sequentially mounted with the mounting part 11 and the positioning plate 115, and is fixed to the positioning plate 115 by mounting bolts 31.
- the bottom of the trestle plate body 1 is supported by the Bailey bridge 2.
- an installation auxiliary part 4 is provided at the connection between the trestle plate body 1 and the Bailey bridge 2.
- the longitudinal section of the installation auxiliary part 4 is U-shaped.
- the upper end of the installation auxiliary part 4 is welded to the trestle plate body 1, and the lower end of the installation auxiliary part 4 is fixed relative to the upper beam of the Bailey bridge 2.
- the installation auxiliary component 4 can be a U-shaped hook or an L-shaped hook, which can achieve relative fixation between the bridge plate body 1 and the Bailey frame 2, and prevent the bridge plate body 1 from shaking. At the same time, it can be used in conjunction with the limiting device 3 and the mounting bolts 31 to effectively prevent the mounting bolts 31 from loosening or falling off, thereby improving safety and stability.
- Step 1 Measurement and layout
- the coordinates of each steel pipe pile were calculated based on the construction layout plan. The calculation results were submitted to the chief engineer of the project for review. After confirmation, field surveying was carried out.
- the steel pipe piles were initially positioned using GPS and monitored throughout the process using a total station. During the pile driving process, two total stations were used at a 90-degree angle to monitor the deviation of the steel pipe piles to ensure the quality of the pile position.
- Step Two Steel Pipe Pile Construction
- the steel pipe piles of the steel platform are treated with anti-corrosion.
- the pipe piles are transported to the construction site by transport vehicle. Due to the long size, heavy weight and easy rolling of the steel pipe piles, steel pipe piles must be tied and reinforced with steel wire ropes to ensure transportation safety.
- steel pipe piles are transported to the site and pass the acceptance, they are spliced into a whole according to the design length. In order to ensure the welding quality, the welding quality meets the requirements of the second-level weld.
- control points of the traverse network are accurately laid out to locate the center point of the pile.
- a guide frame is installed, and a crane is used to lift the pre-assembled steel pipe pile and place it into the guide frame.
- the system uses hydraulic clamps, which quickly clamp and release steel pipes by oil inlet and outlet of hydraulic cylinders.
- the clamps hold the steel pipe piles, while a crawler crane suspends the top of the steel pipe piles with a spare wire rope.
- the crawler crane directly lifts the steel pipe pile using a vibratory hammer and a spare wire rope. Guided by measurements, the steel pipe pile is adjusted to the marked position and then quickly lowered. Once the pile stabilizes in the soil under its own weight, the vibratory hammer is activated to further drive it down. The duration of each vibration must be precisely controlled; too long a duration will damage the hammer, while too short a duration will hinder sinking. Each pile should be driven down in one continuous motion, without interruption or prolonged gaps, to prevent soil regeneration around the pile and subsequent sinking difficulties. During the vibratory sinking process, measuring instruments continuously monitor the verticality.
- the hydraulic hammer is hoisted to clamp the pile, and vibration is continued to drive the steel pipe pile to the design elevation of the pile bottom;
- Step 3 Installation of the substructure of the steel trestle bridge
- connection of horizontal bracing and diagonal bracing begins.
- 20 channel steel shear bracing is used for horizontal bracing and diagonal bracing.
- the connection between the steel pipe piles and the horizontal bracing is made by welding.
- the steel platform load-bearing beam is constructed using H400 ⁇ 400 ⁇ 13 ⁇ 21.
- the beam is placed inside the grooves cut into the top of the steel pipe piles and stiffening plates welded at the pile openings.
- the double-section steel I-beams are processed in the back-end and installed on-site. First, the axis and position of the load-bearing beam are marked on the steel pipe piles. Then, grooves are cut into the top of the steel pipe piles and stiffening plates are welded inside the pile openings. The beams are then lifted, installed, and welded together.
- Step 4 Installation of the superstructure of the steel trestle bridge
- Bailey Frame 2 After the load-bearing beam is installed, the position of Bailey Frame 2 is measured and laid out on the load-bearing beam.
- Bailey Frame 2 is assembled into a group in the back field according to the design span, transported to the front field and installed in place by crane.
- Each group of Bailey Frame 2 is connected to the support frame welded by steel profiles to form a whole.
- the group is connected by a fixed flower rack to ensure the overall stability.
- Bailey Frame 2 is connected to the load-bearing beam through a limiting device.
- the trestle plate body 1 is laid.
- the trestle plate body 1 and the Bailey bridge 2 are fixed together by the limiting device 3.
- Two adjacent trestle plate bodies 1 along the length of the steel trestle bridge deck are fixed together by longitudinal connecting bolts 112.
- the safety and stability of the installation of the trestle plate body 1 can also be improved by using the auxiliary component 4 in conjunction with the limiting device 3.
- this invention simplifies the construction process of the Bailey bridge superstructure.
- the prefabricated trestle panel body 1 is recyclable, realizing resource recycling and possessing extremely high use value.
- the trestle panel body 1 is a single-layer structure, replacing the traditional three-layer structure combining transverse distribution beams, longitudinal distribution beams, and bridge deck, significantly simplifying the construction process, shortening the construction cycle, and saving construction costs.
- the quality of the prefabricated trestle panel body 1 is controllable, eliminating the need for frequent welding work during on-site construction, effectively solving the construction quality problem from the root.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种贝雷架用装配式钢栈桥板结构体系及其施工工艺,属于钢栈桥技术领域。本发明包括栈桥板本体,所述的栈桥板本体的侧边间隔设置有安装部,安装部的侧边开设有纵向连接孔,纵向连接孔内安装有纵向连接螺栓,沿钢栈桥桥面长度方向相邻的两块栈桥板本体通过纵向连接螺栓穿过纵向连接孔实现共同固定。本发明的栈桥板本体采用多组花纹H型钢拼接预制焊接而成,实现了板梁一体化结构,其强度、摩擦力、承载力均能够满足并超过传统钢栈桥板的使用性能,并且钢栈桥板铺设过程中,只需要通过带螺栓的限位装置固定即可,无需现场焊接,可回收,可循环使用,可局部针对性更换,有效的节约成本,实现了资源循环利用,具有极高的使用价值。
Description
本发明涉及钢栈桥技术领域,更具体地说,涉及一种贝雷架用装配式钢栈桥板结构体系及其施工工艺。
在钢栈桥施工过程中,钢栈桥属于重要的临时工程,在整个施工过程中占重要地位。所有钢栈桥结构之间的连接是非常重要的。
现有的钢栈桥的铺设过程通常是采用普通钢板沿钢栈桥沿桥面的长度方向进行铺设,在钢栈桥的两侧辅以螺栓进行固定,铺设完成后,钢栈桥的板面钢板只受长度方向的约束,而相邻的两块栈桥板并没有进行合理的约束,因此,当承受大型车辆时,尤其是大型车辆转向时产生的扭矩时,板面钢板容易受力发生偏转;进而导致相邻的两块栈桥板之间产生较大的缝隙,从而产生一定的安全隐患。
在钢栈桥体系安装过程中,如中国专利CN202122253864.2-应用于深基坑施工的贝雷架钢栈桥所示,现有的施工方法具有以下弊端,首先在贝雷架的顶部固定焊接多个工字钢横梁,第二步在工字钢横梁的顶部固定焊接桥面钢板,该施工方法需要进行工字钢横梁、桥面钢板分步铺设,并且都是采用现场的焊接工艺,施工成本高,工时长,且现场施工的质量层次不齐,拆除时用火焰切割变形量大,材料损耗大;
其次,钢栈桥的两侧与贝雷梁采用螺栓进行连接,施工车辆行驶振动,时间久了,螺栓易松动、脱落,并且,钢栈桥与贝雷梁需要两者共同对齐连接节点,才能够实现螺栓连接,当钢栈桥工字钢与贝雷梁的连接节点错位时,则无法进行有效的固定。
本发明的目的在于克服现有技术的不足,提供了一种贝雷架用装配式钢栈桥板结构体系及其施工工艺,本发明的钢栈桥板,采用多组花纹H型钢拼接预制焊接而成,其强度、摩擦力、承载力均能够满足并超过现有钢栈桥板的性能,实现了板梁一体化,大幅度简化了安装板面的工序,并且钢栈桥板铺设过程中,只需要通过U型螺栓卡具固定即可,无需现场焊接,可回收,可循环使用,可局部进行针对性更换,有效的节约成本,实现了资源循环利用,具有极高的使用价值。
为达到上述目的,本发明提供的技术方案为:
本发明的一种贝雷架用装配式钢栈桥板结构体系,包括栈桥板本体,所述的栈桥板本体的侧边间隔设置有安装部,安装部的侧边开设有纵向连接孔,纵向连接孔内安装有纵向连接螺栓,沿钢栈桥桥面长度方向相邻的两块栈桥板本体通过纵向连接螺栓穿过纵向连接孔实现共同固定。
进一步地,所述的栈桥板本体采用多组花纹H型钢平铺后焊接制成。
进一步地,所述的栈桥板本体的四个角落设置有栏杆连接部,栏杆连接部的侧面开设有栏杆连接孔,栏杆连接孔内安装有栏杆固定螺栓,栏杆放置在栈桥板本体的侧边,并通过栏杆固定螺栓与栈桥板本体的栏杆连接孔装配。
进一步地,所述的安装部的内部设置为空腔结构,安装部的内腔顶部开设有吊装孔。
进一步地,所述的安装部的内腔上部和下部均固定焊接有吊装加强筋。
进一步地,所述的安装部的内腔中部设置有定位板,安装部的内腔底部间隔开设有安装孔,定位板的板面上也开设有安装孔。
进一步地,所述的栈桥板本体的底部设置有贝雷架,栈桥板本体与贝雷架的连接处设置有限位装置,限位装置的下端穿过贝雷架,限位装置的上端依次安装部、定位板,并通过安装螺栓与定位板固定。
进一步地,所述的栈桥板本体的底部设置有贝雷架,栈桥板本体与贝雷架的连接处设置有安装辅助件,安装辅助件的纵截面呈U型,安装辅助件的上端与栈桥板本体焊接,安装辅助件的下端与贝雷架的上梁相对固定。
进一步地,所述的安装辅助件可以为U型钩或L型钩。
一种贝雷架用装配式钢栈桥板结构体系的施工工艺,其步骤为:
步骤一:测量放样;
根据施工平面布置图计算出每根钢管桩的坐标位置,计算成果交项目总工复核,确认无误后开展外业测量工作,钢管桩定位利用GPS初测,全站仪进行全程监测的方法控制钢管桩位,在沉桩过程中,利用两台全站仪成90度角监测钢管桩偏位,保证桩位质量;
步骤二:钢管桩施工;
(2-1)钢管桩运输及接桩
钢平台钢管桩出厂前进行防腐处理,管桩在专业钢结构加工厂制作完成后采用运输车运至施工现场,由于钢管桩尺寸长、重量大、易滚动,为确保运输安全须对钢管桩采用钢丝绳进行绑扎加固,钢管桩运输到现场,验收合格后,根据设计长度拼接成整根,为保证焊接质量,焊接质量满足二级焊缝要求;
(2-2)导向架安装
用全站仪由导线控制网点精准放样,定位出桩中心点位置,安设导向架,用吊机吊起已拼接好的钢管桩,放入导向架内;
(2-3)对位插桩
系统采用液压夹具,通过液压油缸的进油和回油实现迅速夹紧钢管和放松钢管,利用夹具夹住钢管桩,同时用履带吊通过备用钢丝绳吊住钢管桩顶;
(2-4)振动下沉
履带吊通过振动锤及备用钢丝绳直接起吊钢管桩,在测量引导下调整钢管桩到测量标定的桩位后快速下钩,钢管桩靠自重入土稳定后,开启振动锤振动下沉钢管桩;振动时每次振动持续时间需控制无误,过长则振动锤易遭到破坏,太短则难以下沉;每根桩的下沉应一气呵成,不可中途停顿或较长时间的间隙,以免桩周土恢复造成继续下沉困难;振动下沉过程中测量用仪器随时监控垂直度;
(2-5)施振就位
接桩完成后,吊装液压锤夹桩,继续施振打使钢管桩至桩底设计标高;
步骤三:钢栈桥下部结构安装
(3-1)钢管的抄平
钢管桩沉桩结束后,按照设计标高进行测量放点和抄平;
(3-2)平联及斜撑施工
单排钢管桩施打就位后,开始平联及斜撑的连接,水平撑及斜撑采用20槽钢剪力撑,钢管桩与平联之间的连接通过焊接连接;
(3-3)承重梁施工
钢平台承重梁采用H400×400×13×21构成,通过在钢管桩顶部开槽,并在桩口处焊接加劲板,将横梁放置在其内,双拼型钢工字钢在后场加工、现场安装,首先在钢管桩上放出承重梁轴线及位置,在钢管桩顶部开槽、桩口内焊接加劲板,起吊安装横梁、焊接连接;
步骤四:钢栈桥上部结构安装
(4-1)贝雷架安装
承重梁安装完毕后,在承重梁上测量放样定出贝雷架位置,贝雷架按设计跨度在后场拼装成一组,运输到前场用吊车安装到位,各组贝雷架之间用型钢焊接的支撑架联结成整体,组内使用定型花架连接,确保整体稳定性,贝雷架与承重梁通过限位装置连接;
(4-2)桥面系安装
贝雷架安装完毕,铺设栈桥板本体,栈桥板本体与贝雷架通过限位装置进行固定;沿钢栈桥桥面长度方向相邻的两块栈桥板本体通过纵向连接螺栓共同固定;
(4-3)栏杆安装
将栏杆放置在栈桥板本体的侧边,通过栏杆固定螺栓与栈桥板本体装配。
采用本发明提供的技术方案,与现有技术相比,具有如下有益效果:
(1)本发明的钢栈桥板,采用多组花纹H型钢拼接预制焊接而成,其强度、摩擦力、承载力均能够满足钢栈桥板的使用要求,并且钢栈桥板铺设过程中,只需要通过螺栓固定即可,无需现场焊接,可回收,可循环使用,可局部进行针对性更换,有效的节约成本,实现了资源循环利用,具有极高的使用价值。
(2)本发明通过将栏杆连接孔设计为侧向开孔,栏杆可安装在栈桥板本体的侧边,从而不占用栈桥板本体上部的使用面积,在不失去安全防护的同时,为栈桥板本体预留更多的桥面操作空间;
(3)本发明的安装部既可以作为相邻两块栈桥板本体的连接节点,又能够作为栈桥板本体的吊装节点,还可以用作栈桥板本体与贝雷架的固定节点,从而实现多功能化。
(4)本发明通过多组栈桥板本体铺设,即可搭接相应的桥面结构体系;栈桥板本体与贝雷架的连接处设置有安装辅助件或限位装置,从而可以实现栈桥板本体与贝雷架的相对固定,避免栈桥板本体产生晃动,安装辅助件配合限位装置、安装螺栓共同使用,可有效避免安装螺栓松动、脱落等现象,提高安全性与稳定性。
图1为本发明的栈桥板本体主视图;
图2为本发明的安装部局部放大图;
图3为本发明的栈桥板本体侧视图;
图4为本发明的栈桥板本体俯视图;
图5为本发明的栈桥板本体拼接效果图;
图6为本发明的安装部连接效果放大图;
图7为本发明的栏杆安装效果图;
图8为本发明的栏杆局部安装效果放大图。
图9为本发明的栈桥板本体固定状态图;
图10为本发明的安装辅助件结构示意图;
图11为本发明的钢管桩安装示意图;
图12为本发明的贝雷架安装图。
图中:1、栈桥板本体;11、安装部;111、纵向连接孔;112、纵向连接螺栓;113、吊装孔;114、吊装加强筋;115、定位板;116、安装孔;12、栏杆连接部;121、栏杆连接孔;122、栏杆固定螺栓;2、贝雷架;3、限位装置;31、安装螺栓;4、安装辅助件;5、栏杆。
下面结合附图和实施例对本发明作进一步的描述:
从图1-6可以看出,本实施例的一种贝雷架用装配式钢栈桥板,包括栈桥板本体1,栈桥板本体1的侧边间隔设置有安装部11,安装部11的侧边开设有纵向连接孔111,纵向连接孔111内安装有纵向连接螺栓112,沿钢栈桥桥面长度方向相邻的两块栈桥板本体1通过纵向连接螺栓112穿过纵向连接孔111实现共同固定。
栈桥板本体1采用多组花纹H型钢平铺后焊接制成。
本发明的钢栈桥板,采用多组花纹H型钢拼接预制焊接而成,其强度、摩擦力、承载力均能够满足钢栈桥板的使用要求,并且钢栈桥板铺设过程中,只需要通过螺栓固定即可,无需现场焊接,可回收,可循环使用,可局部进行针对性更换,有效的节约成本,实现了资源循环利用,具有极高的使用价值。
沿钢栈桥长度方向铺设的栈桥板本体1通过螺栓或限位件与贝雷架2固定;
沿钢栈桥长度方向铺设的栈桥板本体1,相邻的两块栈桥板本体1通过纵向连接螺栓112进行固定,可以有效的防止栈桥板本体1受扭矩而产生偏转,可以确保栈桥板本体1相互之间无缝隙,有效杜绝安全隐患。
从图7-8可以看出,本实施例的一种贝雷架用装配式钢栈桥板,栈桥板本体1的四个角落设置有栏杆连接部12,栏杆连接部12的侧面开设有栏杆连接孔121,栏杆连接孔121内安装有栏杆固定螺栓122,栏杆5放置在栈桥板本体1的侧边,并通过栏杆固定螺栓122与栈桥板本体1的栏杆连接孔121装配。
本发明通过将栏杆连接孔121设计为侧向开孔,栏杆5可安装在栈桥板本体1的侧边,从而不占用栈桥板本体1上部的使用面积,在不失去安全防护的同时,为栈桥板本体1预留更多的桥面操作空间;
栈桥板本体1的宽度方向即为钢栈桥的长度方向,栈桥板本体1的长度方向即为钢栈桥的宽度方向,栈桥板本体1为预制件,通常一块栈桥板本体1的长度即等于钢栈桥的宽度,当一块栈桥板本体1长度无法满足钢栈桥的宽度需求时,可以沿钢栈桥的宽度方向依次铺设栈桥板本体1,此时,栏杆连接孔121可用作栈桥板本体1的连接孔;
安装部11的内部设置为空腔结构,安装部11的内腔顶部开设有吊装孔113。
安装部11的内腔上部和下部均固定焊接有吊装加强筋114。
安装部11的内腔中部设置有定位板115,安装部11的内腔底部间隔开设有安装孔116,定位板115的板面上也开设有安装孔116。
安装部11既可以作为相邻两块栈桥板本体1的连接节点,又能够作为栈桥板本体1的吊装节点,还可以用作栈桥板本体1与贝雷架2的固定节点,从而实现多功能化。
从图7-10可以看出,本实施例的一种贝雷架用装配式钢栈桥板的结构体系,栈桥板本体1的底部设置有贝雷架2,通过多组栈桥板本体1铺设,即可搭接相应的桥面结构体系;
从图7-8可以看出,当栈桥板本体1的安装部11与贝雷架2的上梁对应在同一水平线上时,栈桥板本体1与贝雷架2的连接处设置有限位装置3,限位装置3的下端穿过贝雷架2,限位装置3的上端依次安装部11、定位板115,并通过安装螺栓31与定位板115固定。
从图9-10可以看出,栈桥板本体1的底部通过贝雷架2进行支撑,当贝雷架2的上梁与栈桥板本体1的连接节点处,并没有设置相应的安装部11时,栈桥板本体1与贝雷架2的连接处设置有安装辅助件4,安装辅助件4的纵截面呈U型,安装辅助件4的上端与栈桥板本体1焊接,安装辅助件4的下端与贝雷架2的上梁相对固定。
安装辅助件4可以为U型钩或L型钩,从而可以实现栈桥板本体1与贝雷架2的相对固定,避免栈桥板本体1产生晃动,同时配合限位装置3、安装螺栓31共同使用,可有效避免安装螺栓31松动、脱落等现象,提高安全性与稳定性。
从图11-12可以看出,一种贝雷架用装配式钢栈桥板结构体系的施工工艺,其步骤为:
步骤一:测量放样;
根据施工平面布置图计算出每根钢管桩的坐标位置,计算成果交项目总工复核,确认无误后开展外业测量工作,钢管桩定位利用GPS初测,全站仪进行全程监测的方法控制钢管桩位,在沉桩过程中,利用两台全站仪成90度角监测钢管桩偏位,保证桩位质量;
步骤二:钢管桩施工;
(2-1)钢管桩运输及接桩
钢平台钢管桩出厂前进行防腐处理,管桩在专业钢结构加工厂制作完成后采用运输车运至施工现场,由于钢管桩尺寸长、重量大、易滚动,为确保运输安全须对钢管桩采用钢丝绳进行绑扎加固,钢管桩运输到现场,验收合格后,根据设计长度拼接成整根,为保证焊接质量,焊接质量满足二级焊缝要求;
(2-2)导向架安装
用全站仪由导线控制网点精准放样,定位出桩中心点位置,安设导向架,用吊机吊起已拼接好的钢管桩,放入导向架内;
(2-3)对位插桩
系统采用液压夹具,通过液压油缸的进油和回油实现迅速夹紧钢管和放松钢管,利用夹具夹住钢管桩,同时用履带吊通过备用钢丝绳吊住钢管桩顶;
(2-4)振动下沉
履带吊通过振动锤及备用钢丝绳直接起吊钢管桩,在测量引导下调整钢管桩到测量标定的桩位后快速下钩,钢管桩靠自重入土稳定后,开启振动锤振动下沉钢管桩;振动时每次振动持续时间需控制无误,过长则振动锤易遭到破坏,太短则难以下沉;每根桩的下沉应一气呵成,不可中途停顿或较长时间的间隙,以免桩周土恢复造成继续下沉困难;振动下沉过程中测量用仪器随时监控垂直度;
(2-5)施振就位
接桩完成后,吊装液压锤夹桩,继续施振打使钢管桩至桩底设计标高;
步骤三:钢栈桥下部结构安装
(3-1)钢管的抄平
钢管桩沉桩结束后,按照设计标高进行测量放点和抄平;
(3-2)平联及斜撑施工
单排钢管桩施打就位后,开始平联及斜撑的连接,水平撑及斜撑采用20槽钢剪力撑,钢管桩与平联之间的连接通过焊接连接;
(3-3)承重梁施工
钢平台承重梁采用H400×400×13×21构成,通过在钢管桩顶部开槽,并在桩口处焊接加劲板,将横梁放置在其内,双拼型钢工字钢在后场加工、现场安装,首先在钢管桩上放出承重梁轴线及位置,在钢管桩顶部开槽、桩口内焊接加劲板,起吊安装横梁、焊接连接;
步骤四:钢栈桥上部结构安装
(4-1)贝雷架2安装
承重梁安装完毕后,在承重梁上测量放样定出贝雷架2位置,贝雷架2按设计跨度在后场拼装成一组,运输到前场用吊车安装到位,各组贝雷架2之间用型钢焊接的支撑架联结成整体,组内使用定型花架连接,确保整体稳定性,贝雷架2与承重梁通过限位装置连接;
(4-2)桥面系安装
贝雷架2安装完毕,铺设栈桥板本体1,栈桥板本体1与贝雷架2通过限位装置3进行固定;沿钢栈桥桥面长度方向相邻的两块栈桥板本体1通过纵向连接螺栓112共同固定;
还可以通过安装辅助件4配合限位装置3共同使用,提高栈桥板本体1安装的安全性与稳定性。
(4-3)栏杆5安装
将栏杆5放置在栈桥板本体1的侧边,通过栏杆固定螺栓122与栈桥板本体1装配。
从上述施工工艺可以看出,本发明简化了贝雷梁上部结构的施工工艺,采用预制的栈桥板本体1,可循环使用,实现了资源循环利用,具有极高的使用价值;栈桥板本体1为单层结构,替代了传统横向分配梁、纵向分配梁、桥面板相结合的三层结构,显著的简化了施工工艺,缩短了施工周期,节约施工成本;同时,预制的栈桥板本体1质量可控,无需在现场施工过程进行频繁的焊接工作,有效的从根源上解决了施工质量问题。
以上示意性的对本发明及其实施方式进行了描述,该描述没有限制性,附图中所示的也只是本发明的实施方式之一,实际的结构并不局限于此。所以,如果本领域的普通技术人员受其启示,在不脱离本发明创造宗旨的情况下,不经创造性的设计出与该技术方案相似的结构方式及实施例,均应属于本发明的保护范围。
Claims (10)
- 一种贝雷架用装配式钢栈桥板结构体系,包括栈桥板本体(1),其特征在于:所述的栈桥板本体(1)的侧边间隔设置有安装部(11),安装部(11)的侧边开设有纵向连接孔(111),纵向连接孔(111)内安装有纵向连接螺栓(112),沿钢栈桥桥面长度方向相邻的两块栈桥板本体(1)通过纵向连接螺栓(112)穿过纵向连接孔(111)实现共同固定。
- 根据权利要求1所述的一种贝雷架用装配式钢栈桥板结构体系,其特征在于:所述的栈桥板本体(1)采用多组花纹H型钢平铺后焊接制成。
- 根据权利要求1所述的一种贝雷架用装配式钢栈桥板结构体系,其特征在于:所述的栈桥板本体(1)的四个角落设置有栏杆连接部(12),栏杆连接部(12)的侧面开设有栏杆连接孔(121),栏杆连接孔(121)内安装有栏杆固定螺栓(122),栏杆(5)放置在栈桥板本体(1)的侧边,并通过栏杆固定螺栓(122)与栈桥板本体(1)的栏杆连接孔(121)装配。
- 根据权利要求3所述的一种贝雷架用装配式钢栈桥板结构体系,其特征在于:所述的安装部(11)的内部设置为空腔结构,安装部(11)的内腔顶部开设有吊装孔(113)。
- 根据权利要求4所述的一种贝雷架用装配式钢栈桥板结构体系,其特征在于:所述的安装部(11)的内腔上部和下部均固定焊接有吊装加强筋(114)。
- 根据权利要求4所述的一种贝雷架用装配式钢栈桥板结构体系,其特征在于:所述的安装部(11)的内腔中部设置有定位板(115),安装部(11)的内腔底部间隔开设有安装孔(116),定位板(115)的板面上也开设有安装孔(116)。
- 根据权利要求6所述的一种贝雷架用装配式钢栈桥板结构体系,其特征在于:所述的栈桥板本体(1)的底部设置有贝雷架(2),栈桥板本体(1)与贝雷架(2)的连接处设置有限位装置(3),限位装置(3)的下端穿过贝雷架(2),限位装置(3)的上端依次安装部(11)、定位板(115),并通过安装螺栓(31)与定位板(115)固定。
- 根据权利要求1所述的一种贝雷架用装配式钢栈桥板结构体系,其特征在于:所述的栈桥板本体(1)的底部设置有贝雷架(2),栈桥板本体(1)与贝雷架(2)的连接处设置有安装辅助件(4),安装辅助件(4)的纵截面呈U型,安装辅助件(4)的上端与栈桥板本体(1)焊接,安装辅助件(4)的下端与贝雷架(2)的上梁相对固定。
- 根据权利要求8所述的一种贝雷架用装配式钢栈桥板结构体系,其特征在于:所述的安装辅助件(4)可以为U型钩或L型钩。
- 根据权利要求9所述的一种贝雷架用装配式钢栈桥板结构体系的施工工艺,其特征在于:其步骤为:步骤一:测量放样;根据施工平面布置图计算出每根钢管桩的坐标位置,计算成果交项目总工复核,确认无误后开展外业测量工作,钢管桩定位利用GPS初测,全站仪进行全程监测的方法控制钢管桩位,在沉桩过程中,利用两台全站仪成90度角监测钢管桩偏位,保证桩位质量;步骤二:钢管桩施工;(2-1)钢管桩运输及接桩钢平台钢管桩出厂前进行防腐处理,管桩在专业钢结构加工厂制作完成后采用运输车运至施工现场,由于钢管桩尺寸长、重量大、易滚动,为确保运输安全须对钢管桩采用钢丝绳进行绑扎加固,钢管桩运输到现场,验收合格后,根据设计长度拼接成整根,为保证焊接质量,焊接质量满足二级焊缝要求;(2-2)导向架安装用全站仪由导线控制网点精准放样,定位出桩中心点位置,安设导向架,用吊机吊起已拼接好的钢管桩,放入导向架内;(2-3)对位插桩系统采用液压夹具,通过液压油缸的进油和回油实现迅速夹紧钢管和放松钢管,利用夹具夹住钢管桩,同时用履带吊通过备用钢丝绳吊住钢管桩顶;(2-4)振动下沉履带吊通过振动锤及备用钢丝绳直接起吊钢管桩,在测量引导下调整钢管桩到测量标定的桩位后快速下钩,钢管桩靠自重入土稳定后,开启振动锤振动下沉钢管桩;振动时每次振动持续时间需控制无误,过长则振动锤易遭到破坏,太短则难以下沉;每根桩的下沉应一气呵成,不可中途停顿或较长时间的间隙,以免桩周土恢复造成继续下沉困难;振动下沉过程中测量用仪器随时监控垂直度;(2-5)施振就位接桩完成后,吊装液压锤夹桩,继续施振打使钢管桩至桩底设计标高;步骤三:钢栈桥下部结构安装(3-1)钢管的抄平钢管桩沉桩结束后,按照设计标高进行测量放点和抄平;(3-2)平联及斜撑施工单排钢管桩施打就位后,开始平联及斜撑的连接,水平撑及斜撑采用20槽钢剪力撑,钢管桩与平联之间的连接通过焊接连接;(3-3)承重梁施工钢平台承重梁采用H400×400×13×21构成,通过在钢管桩顶部开槽,并在桩口处焊接加劲板,将横梁放置在其内,双拼型钢工字钢在后场加工、现场安装,首先在钢管桩上放出承重梁轴线及位置,在钢管桩顶部开槽、桩口内焊接加劲板,起吊安装横梁、焊接连接;步骤四:钢栈桥上部结构安装(4-1)贝雷架(2)安装承重梁安装完毕后,在承重梁上测量放样定出贝雷架(2)位置,贝雷架(2)按设计跨度在后场拼装成一组,运输到前场用吊车安装到位,各组贝雷架(2)之间用型钢焊接的支撑架联结成整体,组内使用定型花架连接,确保整体稳定性,贝雷架(2)与承重梁通过限位装置连接;(4-2)桥面系安装贝雷架(2)安装完毕,铺设栈桥板本体(1),栈桥板本体(1)与贝雷架(2)通过限位装置(3)进行固定;沿钢栈桥桥面长度方向相邻的两块栈桥板本体(1)通过纵向连接螺栓(112)共同固定;(4-3)栏杆(5)安装将栏杆(5)放置在栈桥板本体(1)的侧边,通过栏杆固定螺栓(122)与栈桥板本体(1)装配。
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202410930874.0 | 2024-07-12 | ||
| CN202410930874.0A CN118639539A (zh) | 2024-07-12 | 2024-07-12 | 一种贝雷架用装配式钢栈桥板结构体系及其施工工艺 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2026011864A1 true WO2026011864A1 (zh) | 2026-01-15 |
Family
ID=92671356
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/CN2025/087750 Pending WO2026011864A1 (zh) | 2024-07-12 | 2025-04-08 | 一种贝雷架用装配式钢栈桥板结构体系及其施工工艺 |
Country Status (2)
| Country | Link |
|---|---|
| CN (1) | CN118639539A (zh) |
| WO (1) | WO2026011864A1 (zh) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118639539A (zh) * | 2024-07-12 | 2024-09-13 | 瑞马丸建(安徽)工程支护科技有限公司 | 一种贝雷架用装配式钢栈桥板结构体系及其施工工艺 |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20060117504A1 (en) * | 2004-12-06 | 2006-06-08 | Ronald Hugh D | Bridge construction system and method |
| US20090077758A1 (en) * | 2007-09-21 | 2009-03-26 | Groupe Canam Inc. | Bridge deck panel |
| JP4807809B1 (ja) * | 2010-11-25 | 2011-11-02 | 株式会社高知丸高 | 桟橋構築方法 |
| CN208151837U (zh) * | 2018-04-12 | 2018-11-27 | 马鞍山瑞马钢构材料有限公司 | 一种装配式h型钢栈桥板 |
| CN215518324U (zh) * | 2021-09-03 | 2022-01-14 | 中交基础设施养护集团有限公司 | 分配梁连接结构 |
| CN114934433A (zh) * | 2022-06-22 | 2022-08-23 | 中铁十九局集团有限公司 | 用于辅助桥梁施工的马镫桩基钢栈桥结构及其施工工艺 |
| CN217438686U (zh) * | 2022-05-24 | 2022-09-16 | 中交第二航务工程局有限公司 | 一种便携式栈桥面板连接结构 |
| CN115961567A (zh) * | 2023-01-13 | 2023-04-14 | 中冶南方城市建设工程技术有限公司 | 可调高的装配式uhpc桥面板轻型组合梁及桥面板调高方法 |
| CN118639539A (zh) * | 2024-07-12 | 2024-09-13 | 瑞马丸建(安徽)工程支护科技有限公司 | 一种贝雷架用装配式钢栈桥板结构体系及其施工工艺 |
-
2024
- 2024-07-12 CN CN202410930874.0A patent/CN118639539A/zh active Pending
-
2025
- 2025-04-08 WO PCT/CN2025/087750 patent/WO2026011864A1/zh active Pending
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20060117504A1 (en) * | 2004-12-06 | 2006-06-08 | Ronald Hugh D | Bridge construction system and method |
| US20090077758A1 (en) * | 2007-09-21 | 2009-03-26 | Groupe Canam Inc. | Bridge deck panel |
| JP4807809B1 (ja) * | 2010-11-25 | 2011-11-02 | 株式会社高知丸高 | 桟橋構築方法 |
| CN208151837U (zh) * | 2018-04-12 | 2018-11-27 | 马鞍山瑞马钢构材料有限公司 | 一种装配式h型钢栈桥板 |
| CN215518324U (zh) * | 2021-09-03 | 2022-01-14 | 中交基础设施养护集团有限公司 | 分配梁连接结构 |
| CN217438686U (zh) * | 2022-05-24 | 2022-09-16 | 中交第二航务工程局有限公司 | 一种便携式栈桥面板连接结构 |
| CN114934433A (zh) * | 2022-06-22 | 2022-08-23 | 中铁十九局集团有限公司 | 用于辅助桥梁施工的马镫桩基钢栈桥结构及其施工工艺 |
| CN115961567A (zh) * | 2023-01-13 | 2023-04-14 | 中冶南方城市建设工程技术有限公司 | 可调高的装配式uhpc桥面板轻型组合梁及桥面板调高方法 |
| CN118639539A (zh) * | 2024-07-12 | 2024-09-13 | 瑞马丸建(安徽)工程支护科技有限公司 | 一种贝雷架用装配式钢栈桥板结构体系及其施工工艺 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN118639539A (zh) | 2024-09-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107013038A (zh) | 一种大型建筑物屋顶采光中庭的钢结构滑移换柱施工方法 | |
| CN109958065A (zh) | 一种桥梁钢箱梁分段吊装高空合拢的施工方法 | |
| JP6763010B2 (ja) | 斜張橋、および斜張橋の架設方法 | |
| CN114934433A (zh) | 用于辅助桥梁施工的马镫桩基钢栈桥结构及其施工工艺 | |
| CN108423565A (zh) | U型双梁吊钩门式起重机的架设及拆除施工方法 | |
| CN103882808B (zh) | 匝道桥与主线桥交接跨架设预制梁支撑系统的施工方法 | |
| CN217325044U (zh) | 拆装式现浇横梁托架 | |
| CN109653101B (zh) | 一种用于桥梁施工的栈桥的搭设方法 | |
| CN118639539A (zh) | 一种贝雷架用装配式钢栈桥板结构体系及其施工工艺 | |
| CN115341701B (zh) | 高空悬挑钢筋桁架楼承板吊模施工方法 | |
| CN116892171B (zh) | 一种用于下承式提篮钢箱系杆拱桥桥面结构的施工方法 | |
| CN219342875U (zh) | 一种中小曲线现浇箱梁新型组合支架结构 | |
| CN117418465A (zh) | 一种装配式无支墩支架安装方法 | |
| CN116927092A (zh) | 一种钢箱桥梁建造用辅助栈桥搭设拆卸工艺 | |
| CN116289593A (zh) | 一种中小曲线现浇箱梁新型组合支架结构及施工方法 | |
| CN221822718U (zh) | 一种单体承重钢抱箍装置 | |
| CN223373576U (zh) | 桥岸边跨现浇梁结构 | |
| CN221822740U (zh) | 一种无支承悬吊式桥梁施工作业人员操作平台 | |
| CN119843886B (zh) | 一种钢桁架节段落梁方法以及钢桁架施工方法 | |
| CN221052585U (zh) | 全砂层地质超大直径复合桩钢管的安装系统 | |
| JP2002004226A (ja) | コンクリート床版の補強方法 | |
| CN117127744B (zh) | 一种用贝雷梁和型钢搭设的钢筋加工平台的施工方法 | |
| CN206844680U (zh) | 钢连廊地面拼装荷载转移装置 | |
| CN217419309U (zh) | 一种用于桥梁下方排水管道安装的施工平台 | |
| CN222251761U (zh) | 一种桥梁施工临时支承体系 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 25835771 Country of ref document: EP Kind code of ref document: A1 |