WO2025213539A1 - 一种空间立体悬吊廊道及其优化方法 - Google Patents
一种空间立体悬吊廊道及其优化方法Info
- Publication number
- WO2025213539A1 WO2025213539A1 PCT/CN2024/094887 CN2024094887W WO2025213539A1 WO 2025213539 A1 WO2025213539 A1 WO 2025213539A1 CN 2024094887 W CN2024094887 W CN 2024094887W WO 2025213539 A1 WO2025213539 A1 WO 2025213539A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- corridor
- suspended
- boom
- requirements
- formula
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D1/00—Bridges in general
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
- E01D19/125—Grating or flooring for bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/0046—Loggias
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/34—Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
- G06F30/23—Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B2001/0053—Buildings characterised by their shape or layout grid
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2119/00—Details relating to the type or aim of the analysis or the optimisation
- G06F2119/14—Force analysis or force optimisation, e.g. static or dynamic forces
Definitions
- the present invention relates to the technical field of steel structure buildings, and in particular to a spatial three-dimensional suspended corridor and an optimization method thereof.
- the applicant previously disclosed a patented technology for an indoor zigzag suspension bridge structure with the patent publication number CN103967131B.
- the zigzag suspension bridge deck (equivalent to the bridge deck section) is connected to the floor aisle through a first connecting component, and the first connecting component includes a fixing plate and bolts, that is, the connection between the bridge deck and the floor aisle adopts the combination of fixing plates and bolts, and no corresponding weakening parts are provided.
- the bridge deck is under stress, it will affect the stability between the bridge deck and the floor aisle.
- the suspension bridge system has no organic connection with the large venue system, and the overall seismic stability and comfort of the suspension bridge structure are difficult to guarantee.
- Patent Publication No. CN108875286A discloses a parametric optimization method for analyzing the overall structure of a suspension bridge. This method introduces side span and vector height as influencing factors, and by changing these two variables, the cable tension of the suspension bridge is adjusted to achieve the optimization purpose.
- Patent Announcement No. CN104899377B discloses a suspension bridge cable tension optimization method. This method forms an influence matrix of the suspension bridge structure based on the constant load stiffness, and then obtains the ideal cable tension of the suspension bridge through iterative analysis. Both of the above patents are based on optimizing the hanger cable tension.
- the technical problem to be solved by the present invention is: how to solve the problem of insufficient stability of the current spatial suspended corridor bridge deck section and the problem of corridor unloading instability.
- the present invention provides the following technical solutions:
- a three-dimensional suspended corridor comprising a suspended corridor connecting indoor floor corridors, characterized in that: the edges of the indoor floor corridors are all provided with oblique grid columns;
- the suspended corridor includes a plurality of fixed sections and a plurality of bridge deck sections from top to bottom, wherein at least one corner section is provided between two adjacent fixed sections, and the fixed sections or the corner sections are connected to the corresponding bridge deck sections via node connection components;
- corner sections are connected to the corresponding oblique grid columns through several oblique hangers, and each bridge deck section is connected to the top steel roof through several vertical hangers.
- the present invention sets fixed sections at reasonable positions in the aerial corridor system, and connects and fixes the fixed sections or corner sections to the bridge deck sections through node connection components, thereby maximizing the safety of the aerial corridor;
- the corner sections are freely cantilevered, avoiding obstruction of the structure by surrounding buildings, and making it convenient for pedestrians to view a wide range of surrounding landscapes;
- the present application sets the aerial corridor in the atrium of a large venue, which can serve as a passage to the corresponding floors, making full use of the atrium space, satisfying the functional requirements of venue visits and fully reflecting the beauty of the architecture.
- an angle ⁇ is formed between each bridge deck section and the horizontal plane, wherein the value range of ⁇ is: 0° ⁇ 60°.
- the node connection component includes a first T-shaped steel plate embedded in the corresponding bridge deck section, and a second T-shaped steel plate embedded in the corresponding fixed section or corner section.
- the left and right sides of the first T-shaped steel plate and the second T-shaped steel plate are detachably connected by energy dissipation and weakening parts, and the energy dissipation and weakening parts are detachably connected to the reinforcement connecting plate.
- the upper and lower sides of the middle position of the energy dissipation and weakening component are both concave structures, and a waist-shaped groove is opened in the horizontal direction of the middle position; the middle position of the reinforced connecting plate is opened in the horizontal direction of an arc groove, wherein the arc groove corresponds to the corresponding waist-shaped groove, and the two are fixed by bolts.
- the oblique grid columns are installed around the indoor venue, and the overall structure is "X"-shaped, "K”-shaped, or "Y"-shaped.
- the present invention also discloses a spatial three-dimensional suspended corridor optimization method, comprising the following steps:
- step S14 Based on the obtained axial force value of the hanger and the overall deformation information of the corridor, compare the results with the specifications to verify whether the results are reasonable. If not, return to step S12 to recalculate, adjust the correlation coefficient, and update the structural dimensions until the rationality and correctness of the simulation model are determined; otherwise, proceed to the next step;
- step S23 determining whether the optimization process has converged. If the optimization process has not converged, returning to step S21 to redetermine the material, quantity, and position of the boom; if the optimization process has converged, outputting the optimal parameters of the boom cross-sectional area;
- the analysis is performed using the modal analysis method or the transient analysis method, or the modal analysis method plus the transient analysis method, and then compared with the provisions of the dynamic response value limit in the known specifications to determine whether the comfort requirements are met. If the comfort requirements are not met, the boom optimization of step S2 is re-entered.
- step S22 the specific method for iterative calculation of the cross-sectional area in step S22 is:
- the tension force FT of the suspender rod can be simulated by changing the temperature difference of the rod element, that is, the axial force of the rod can be simulated, wherein the tension force FT is approximately equal to the design value of the axial force FN ;
- the linear expansion coefficient of the hanger material is defined as ⁇ T . Select the relevant value according to the type of material.
- the elastic modulus of the suspender material is E. As the material type is known, the elastic modulus is E. Sure;
- the method for calculating the mass and length of the boom in step S24 is:
- the formula is deduced from the formula, that is, the relationship between the mass m and the length l of the boom is obtained. Since the type of material is known, that is, the density ⁇ of the material is determined, and the volume V of the boom is determined, the density ⁇ and the cross-sectional area Ai are substituted into the formula to obtain the specific proportional relationship between the mass and length of the boom;
- F N is the design value of the axial force of the hanger, which has been determined; f 1 and f 2 are the first-order and second-order natural frequencies of the hanger; ⁇ is the partial coefficient of seismic action, and the specific values of the mass and length of the hanger are finally calculated.
- step S25 the specific operation method of step S25 is:
- the specific method of modal analysis in step S3 includes:
- the basic vibration characteristics of the corridor structure during free vibration are obtained, including parameters such as the natural mode, natural frequency, and mode shape of vibration.
- the corridor structure comfort is evaluated based on known vibration comfort evaluation indicators to see whether it meets the requirements, mainly natural frequency and acceleration;
- the comfort level meets the specification requirements, and there is no need to verify the acceleration; if the natural frequency meets the requirements, the comfort level meets the specification requirements, and there is no need to verify the acceleration; If the rate is not satisfied, it is necessary to judge the acceleration. If it reaches the limit, it meets the specification requirements, otherwise it does not meet the requirements.
- the present invention has the following beneficial effects:
- the present invention arranges fixed sections at reasonable locations in the skywalk system. Node connection components are used to connect and fix the bridge deck sections and the bridge deck sections to the skywalk, thereby maximizing the safety of the skywalk.
- the corner sections are freely cantilevered, avoiding obstruction of the structure by surrounding buildings and allowing pedestrians to conveniently view a wide range of surrounding landscapes.
- the present application arranges the skywalk in the atrium of a large venue, which can serve as a passage to the corresponding floors, making full use of the atrium space. This not only meets the functional requirements of venue visits and tours, but also fully demonstrates the beauty of the architecture.
- the present invention effectively ensures the horizontal stability of the skywalk by arranging oblique grid columns on both sides of the venue's atrium, connecting them to the oblique hangers and fixed sections of the skywalk.
- the oblique grid columns themselves also function as shear walls. Their continuous arrangement from bottom to top can improve the seismic resilience of the venue's overall structure while increasing the venue's floor height, while also providing a wide field of view, making them particularly suitable for visiting venues.
- the present invention provides energy dissipation weakening members and reinforcement connection plates between the bridge deck section and the fixed section or corner section, and between the fixed section and the main structure of the corridor.
- a weakening member a single connecting square steel plate
- the stress dispersion to the connecting section is smaller. Without a weakening member, the stress reaches 500 MPa, exceeding the ultimate strength of the component itself, resulting in serious damage. However, with a weakening member, the stress reaches 375 MPa but does not reach the ultimate strength, and the component is stable.
- the present invention optimizes the structure of the aerial corridor.
- the stress distribution of the suspended corridor channel in the optimized model is more uniform, the deformation is more coordinated, the hanger material is more fully utilized, and the phenomenon of compressive instability of the rod is avoided.
- the number of hangers in the optimized model is reduced, which is more conducive to construction.
- the hanger material of the optimized model is reduced, and it has better economic indicators.
- the simulation model of the present invention is only a tool for rationality verification of the parameters derived from the formula.
- the optimized model of the present invention is not only more reliable in terms of safety, but also meets the comfort requirements of the project, whether in modal analysis considering only deadweight or transient analysis considering pedestrian load. It avoids resonance between the corridor structure and pedestrian load, which can cause sympathetic nervous tension, accelerated heartbeat, and other mental stimulation, as well as damage to the suspended corridor, thus ensuring an excellent overall comfort level for the suspended corridor.
- the present invention proposes an aerial corridor structure, and then establishes a corridor simulation model based on a preliminary understanding of the stress performance of the corridor structure through some feasible experiments, and continuously optimizes the model parameters and repeatedly adjusts The test is then conducted, and a preliminary stress performance calculation is performed and compared with some of the test results previously performed. If the results are very similar to the experimental results, it is proved that the model is better, that is, the optimized model is obtained, and then this model is used to analyze other more complex performances of the corridor.
- the optimization purpose of this invention is to make the structure and stress of the aerial corridor safer, more reliable and more comfortable.
- FIG1 is a schematic diagram of the overall structure of a three-dimensional suspended corridor according to an embodiment of the present invention.
- FIG2 is a schematic diagram of the top structure of the suspended corridor according to an embodiment of the present invention.
- FIG3 is a schematic diagram of the front structure of the suspended corridor according to an embodiment of the present invention.
- FIG4 is a schematic structural diagram of a node connection component according to an embodiment of the present invention.
- FIG5 is a partial enlarged view of a node connection component according to an embodiment of the present invention.
- FIG6 is a schematic diagram of a partial structure of a node connection component according to an embodiment of the present invention.
- FIG7 is a schematic diagram of a partial structure of a vertical boom according to an embodiment of the present invention.
- FIG8 is a Mises stress cloud diagram when no weakening member is provided at the node connection position according to an embodiment of the present invention.
- FIG9 is a Mises stress cloud diagram when a weakening member is provided at a node connection position according to an embodiment of the present invention.
- FIG10 is a structural flow chart of model establishment and preliminary optimization according to an embodiment of the present invention.
- FIG11 is a structural flow chart of boom optimization according to an embodiment of the present invention.
- FIG12 is a structural flow chart of the overall comfort analysis according to an embodiment of the present invention.
- a three-dimensional suspended corridor includes a suspended corridor 1, a top steel roof 2, diagonal grid columns 3 and a main structural plate 4.
- the suspended corridor 1 is arranged in the atrium of an indoor venue, the top steel roof 2 is fixed to the top of the venue, and the diagonal grid columns 3 are arranged around the venue.
- the diagonal grid columns 3 are arranged from top to bottom to support the main structural plate 4 of the indoor floors.
- the suspended corridor 1 includes a plurality of fixed sections 101, a plurality of bridge deck sections 102, a plurality of corner sections 103, vertical hangers 112 and inclined hangers 113, wherein the specific number of bridge deck sections 102 is related to the indoor floor height, the bridge deck sections 102, the inclination angle of the horizontal plane and the floor height; each group of bridge deck sections 102 is arranged upwardly, and there is an angle ⁇ between each group of bridge deck sections 102 and the horizontal plane, wherein the value range of ⁇ is: 0° ⁇ 60°, and a staircase for walking upward is provided above each group of bridge deck sections 102.
- the bridge deck section 102 and the corner section 103 of the present application are connected via a node connection component, and the bridge deck section 102 and the fixed section 101 are also connected via a node connection component, and the connection principles of the two locations are the same.
- the node connection components specifically include a first T-shaped steel plate 114 and a second T-shaped steel plate 115.
- the first T-shaped steel plate 114 is a reserved section for the bridge deck section 102, and the first T-shaped steel plate 114 and the bridge deck section 102 are integrally cast with concrete.
- the second T-shaped steel plate 115 is a reserved section for the fixed section 101, and the second T-shaped steel plate 115 and the fixed section 101 are integrally cast with concrete.
- the first T-shaped steel plate 114 is fitted with the second T-shaped steel plate 115, and energy dissipation weakening parts 117 are installed on the front and rear sides of the connection between the two.
- the two arc holes on the left are connected to the second T-shaped steel plate 115 through fastening bolts 116, and the two arc holes on the right are connected to the first T-shaped steel plate 114 through fastening bolts 116 (the left and right directions here are referred to as Figure 5).
- the purpose of the arc holes here instead of round holes is that the bolts have a certain buffering effect during the force process, which has achieved energy unloading.
- the surface section 102 has a safe and stable effect; an arc-shaped concave structure is set in the middle and upper and lower sides of the energy dissipation weakening member 117.
- the design here can reduce energy transfer.
- This component is demonstrated by ABAQUS software; and a waist-shaped groove 119 is also opened horizontally in the middle position of the energy dissipation weakening member 117.
- a reinforcement connecting plate 118 is set outside the waist-shaped groove 119.
- An arc groove is also opened at the corresponding position on the reinforcement connecting plate 118.
- the arc groove corresponds to the waist-shaped groove 119.
- the two are reinforced by bolts.
- a cover can be installed on the top
- the plate covers the gap at the connection to facilitate subsequent mechanical maintenance; the design purpose of the waist-shaped groove and the arc groove here is also to ensure that the bolts have a certain buffering effect during the stress process, thereby achieving energy unloading and ensuring the safety and stability of the bridge deck section 102.
- ABAQUS is used below to demonstrate the effectiveness of the aforementioned node connection components, comparing the energy dissipation effect of the square plate with that of our designed weakening member 117.
- the Mises stress contours obtained from the ABAQUS analysis show that the weakening member of our design experiences less stress dispersion than the one without a weakening member (a single connecting square steel plate).
- the stress without the weakening member reaches 500 MPa, exceeding the ultimate strength of the component itself, resulting in severe damage.
- the stress with the weakening member reaches 375 MPa, which falls below the ultimate strength, resulting in a stable component. This is because the arc in the middle effectively releases the stress transmitted from the surrounding area, ensuring a stable load on the entire component.
- the top steel roof 2 is installed in a grid-like manner on the top of the venue, which is used to support the vertical hangers 112, wherein the top steel roof is constructed using a combined truss steel roof; considering the influence of factors such as site conditions, project characteristics and construction costs, it is difficult to adopt construction methods such as high-altitude bulk, overall hoisting, and overall sliding of the roof.
- the present application adopts BIM technology to establish an X-steel model of the steel roof, realize three-dimensional CNC processing, pre-assembly, simulated hoisting, etc., which not only ensures the hoisting accuracy but also reduces the difficulty of operation.
- the above design can ensure the accurate positioning of the steel structure space components and reasonably optimize special nodes; at the same time, considering that the steel roof is located inside the building and it is difficult for hoisting equipment to enter, the present application can adopt the method of reserving hoisting holes, setting reserved holes in the top plate and reserved channels on the outer wall in the basement, and the crane enters the basement atrium for direct hoisting, which speeds up the construction period, saves costs, and has significant technical benefits.
- hoisting the steel trusses in sections the hoisting weight of a single component is reduced, which is safe, reliable and easy to construct.
- the diagonal grid columns 3 of this application are installed in an "X" shape around the venue to support the venue floors.
- the installation of the diagonal grid rigid concrete columns of this application adopts the method of reserving hoisting holes and hoisting them in sections, rather than setting up scaffolding and assembling them as a whole.
- the use of tower cranes and giant truck cranes for hoisting has achieved significant technical innovations.
- the rigid concrete columns are cast in a self-compacting one-time process, which reduces construction steps, shortens construction time, and avoids the cost of secondary treatment at concrete joints.
- the installation of the diagonal grid rigid concrete columns fully utilizes BIM technology, which can optimize steel structures and complex nodes, not only saving steel but also reducing operational difficulty and shortening construction time.
- the oblique grid column 3 can also adopt a "Y"-shaped or "K"-shaped structure. This application does not limit the specific shape, and the staff will decide based on the on-site conditions.
- the aerial corridor structure consists of a bridge deck section 102, a corner section 103, a fixed section 101, vertical hangers 112, and inclined hangers. 113 and corresponding railings, the corner section 103 and the fixed section 101 divide the aerial corridor into several bridge deck sections 102; from top to bottom, the starting and ending positions are fixed sections 101, and at least one corner section 103 is set between two adjacent fixed sections 101.
- the corner sections 103 are freely cantilevered.
- the other fixed sections 101 are connected to the main structure plate 4 of the floor; the corner sections 103 are connected to the oblique grid columns 3 through multiple oblique hangers 113, and the bridge deck section 102 is connected to the top steel roof 2 through multiple vertical hangers 112.
- the upper end of the vertical suspension rod 112 is connected to the steel roof 2 by an ear plate and a pin, and the middle part of the vertical suspension rod 112 is connected to the first rod 1121 and the second rod 1123 by a limiting sleeve 1122 (refer to Figure 7), and the inner wall of the limiting sleeve 1122 is provided with an internal thread, one end of the first rod 1121 is provided with an external thread that matches the internal thread of the limiting sleeve, and one end of the second rod 1123 is provided with an external thread that matches the internal thread of the limiting sleeve.
- the middle part of the oblique suspension rod 113 is connected to the first rod member and the second rod member by a limiting sleeve, the inner wall of the limiting sleeve is provided with an internal thread, one end of the first rod member is provided with an external thread that cooperates with the internal thread of the connecting sleeve, and one end of the second rod member is provided with an external thread that cooperates with the internal thread of the connecting sleeve, but one end of the first rod member of the oblique suspension rod is hinged to the oblique grid column 3 structure, and the other end is connected to the limiting sleeve, and one end of the second rod member is connected to the limiting sleeve.
- the present invention also provides a method for parameter optimization of a spatial three-dimensional suspended corridor and evaluation of the overall comfort of the structure.
- the optimization process of the present invention is divided into three parts:
- the specification is compared to verify whether the result is reasonable. If it is unreasonable, return to step S12 to recalculate, adjust the correlation coefficient, and update the structural dimensions until the rationality and correctness of the simulation model are determined; otherwise, enter the next step. Secondary optimization stage.
- the tension force F T of the hanger rod that is, the axial force of the rod
- the tension force F T is approximately equal to the design value of the hanger rod axial force F N .
- the linear expansion coefficient ⁇ of the material is selected according to the material type, as shown in Table 1 below.
- the elastic modulus E of the material is determined by the material type.
- step S23 judging whether the optimization process has converged, that is, whether the result approaches 0. If the optimization process has not converged, returning to step S21 to re-determine the material, quantity and position of the boom; if the optimized boom cross-sectional area has converged, outputting the optimal parameter of the cross-sectional area Ai;
- Formula (4) is derived from formula (2) and formula (3), which is the relationship between the mass and length of the boom. Since the type of boom material is known, that is, the density ⁇ of the boom material is determined, and the volume V of the boom is determined, the density ⁇ is Substitute the cross-sectional area Ai obtained in step S23 into formula (4) to obtain the specific proportional relationship between the mass and length of the boom;
- F N is the design value of the axial force of the hanger, which has been determined; f 1 and f 2 are the first-order and second-order natural frequencies of the hanger; ⁇ is the partial coefficient of seismic action, which can be taken according to Table 2 according to specific needs, and finally the specific values of the mass and length of the hanger are calculated.
- F N is the design value of the axial force of the hanger
- FT is the tension force of the hanger
- f 1 and f 2 are the first and second order natural frequencies of the boom, respectively;
- ⁇ is the partial coefficient of earthquake action
- ⁇ T is the linear expansion coefficient of the material
- E is the elastic modulus of the material
- ⁇ T is the temperature load variable of the i-th boom unit
- Ai is the cross-sectional area of the i-th boom
- V, m, l, and ⁇ are the volume, mass, length, and density of the boom.
- an optimized finite element simulation model is established, and the overall structural safety calculation is performed. Considering the most unfavorable combined effects of "dead load + live load + temperature + shrinkage creep", the optimized suspension corridor/suspension bridge is structurally verified using finite element simulation software, the results are output, and the overall deformation information of the suspension corridor/suspension bridge is extracted.
- step S22 If all requirements are met, the process proceeds to the next step of overall optimization. If one of the requirements is not met, the process returns to step S22 and performs secondary parameter optimization again.
- the optimized mathematical model is used to evaluate the overall comfort of the suspended corridor structure.
- comfort evaluation There are two methods for comfort evaluation: one is modal analysis; the other is transient analysis.
- the structure is subjected to modal analysis (i.e., step S31) or transient analysis (step S32), or modal analysis + transient analysis, to avoid resonance or make the structure vibrate at a specific frequency.
- Modal analysis loading method Finite element software is used to perform modal analysis on the structure considering only the corridor's deadweight conditions.
- Transient Analysis Loading Method Determine the pedestrian load loading method, which is divided into two loading methods: one that considers the load of a single person walking, and the other that considers the load of a crowd. Different loading methods use different functional expressions. Choose the appropriate loading method based on project requirements, or verify both.
- Modal analysis first determines a reasonable modal analysis method; different finite element software has different built-in modal analysis methods.
- ANSYS finite element software provides seven modal analysis methods: 1 Block Lanzcos method, 2 Subspace method, 3 Unsymmetric method, 4 Reduced method, 5 Power Dynamics method, 6 QR damping method, 7 Damped method, etc. choose a reasonable modal analysis method.
- the analytical method not only considers the complete stiffness matrix of the structure, but also ensures the accuracy of the calculation and the speed of calculation is fast;
- Natural frequency and acceleration There are two main types of tests: natural frequency and acceleration. If the natural frequency meets the requirements, the comfort level meets the regulatory requirements, and there is no need to verify acceleration. If the natural frequency does not meet the requirements, acceleration needs to be evaluated. If it meets the limit, the regulatory requirements are met, otherwise it does not. Natural frequency and mode shape curves can also be used to analyze the mass, stiffness distribution, and the rationality of the stiffness of the structure.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Theoretical Computer Science (AREA)
- Geometry (AREA)
- Electromagnetism (AREA)
- Computer Hardware Design (AREA)
- General Physics & Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Bridges Or Land Bridges (AREA)
- Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)
Abstract
本发明公开了一种空间立体悬吊廊道,包括连接室内楼层过道之间的悬吊廊道,其中室内楼层过道的边部均设有斜交网格柱;悬吊廊道从下往上包括若干固定段和若干桥面段,固定段或转角段均通过节点连接部件连接相应的桥面段。本发明还通过部分能实施的试验在对廊道结构受力性能有初步了解的基础上,建立廊道仿真模型,不断优化模型参数进行反复调试,然后进行初步受力性能计算并与之前做的部分试验结果进行对比,如果跟实验结果很相似,则证明该模型比较优,即得到优化后的模型,再通过这个模型去分析廊道其他更复杂的性能;本发明优化目的是使空中廊道结构和受力更安全、可靠、舒适。
Description
本发明涉及钢结构建筑技术领域,具体涉及一种空间立体悬吊廊道及其优化方法。
随着国家经济的快速发展和人民对建筑美学的提升以及建筑功能需求的增多,各地各种大型场馆建造兴建,推动了社会各领域的发展,在满足人民对健康、知识、交流、娱乐及探索的需求的同时,游客的观光体验也尤为重要。现行大型场馆观光通道都比较狭小,游客视野受限,在参观的时不能有很好的视觉体验,典型的空间立体交通体系即桥梁体系,不仅视野开阔,而且便于游客观光,特别适合作为大型场馆观光通道。然而,直接将该体系用到大型场馆中,则存在空间受限,结构体系复杂多变等问题。
在新型通道体系发明方面,申请人早期公开了一种室内折线吊桥结构专利技术,专利公告号为CN103967131B,该技术中折线吊桥桥板(相当于桥面段)通过第一连接组件与楼层过道连接,而第一连接组件中包括固定板和螺栓,即桥板在与楼层过道之间的连接采用固定板和螺栓的配合,且并未设置相应的削弱件,当桥板在受力时则会影响桥板与楼层过道之间的稳定性,吊桥体系与大型场馆体系未形成有机联系,吊桥结构整体抗震稳定性和舒适性难以保证。
在新型通道结构体系优化方面,专利公开号CN108875286A公开一种悬索桥整体结构分析的参数化优化方法,该方法是引入边跨、矢量高作为影响因子,改变这两个变量,从而调整悬索桥的索力达到优化的目的;又如专利公告号CN104899377B公布的一种悬索桥索力优化方法,该方法在恒载刚度的基础上,形成了悬索桥结构的影响矩阵,之后通过迭代分析,得到悬索桥理想索力。以上两个专利均是以优化吊杆索力为出发点,而在实际现场施工中,吊杆索力的施加受工人影响较大,难以施加到理想状态;且上述公开的两个专利均单一考虑悬索桥吊杆索力优化,未考虑吊杆位置、材料、数量、尺寸等方面以及结构整体的舒适度,从而无法保证结构整体的安全性、耐久性及舒适性。
综上所述,为满足人们对建筑体系的多元化需求,同时确保结构体系的安全
性、舒适性及技术可实施性,亟需结合大型场馆观光需求,发明一种空间立体悬吊廊道及其优化方法。
发明内容
本发明所要解决的技术问题在于:如何解决目前空间悬吊廊道桥面段稳定性不足,以及廊道卸载失稳的问题。
为解决上述技术问题,本发明提供如下技术方案:
一种空间立体悬吊廊道,包括连接室内楼层过道之间的悬吊廊道,其特征在于:其中室内楼层过道的边部均设有斜交网格柱;
所述悬吊廊道从上往下包括若干固定段和若干桥面段,其中相邻两个固定段之间至少设置一个转角段,所述固定段或转角段均通过节点连接部件连接相应的桥面段;
其中转角段通过若干斜吊杆连接到相应斜交网格柱上,每个桥面段上均通过若干竖吊杆连接到顶部钢屋盖上。
本发明在空中廊道体系中合理位置设置固定段,在固定段或转角段与桥面段之间通过节点连接部件连接固定,最大程度的提高了空中廊道的安全性;转角段自由悬挑,避免了四周建筑对结构的遮挡,可以方便行人观看大范围周边景观;本申请将空中廊道设置在大型场馆中庭部位,可作为通往相应楼层的通道,充分利用了中庭空间,即满足了场馆参观游览的功能需求,又充分体现了建筑之美。
作为本发明进一步的方案:每处桥面段与水平面均存在夹角α,其中α的取值范围为:0°<α<60°。
作为本发明进一步的方案:所述节点连接部件包括有预埋在相应桥面段内的第一T型钢板,预埋在相应固定段或者转角段内的第二T型钢板,所述第一T型钢板与第二T型钢板的左右两侧均通过消能削弱件进行可拆卸连接,其中消能削弱件又可拆卸连接有加固连接板。
作为本发明进一步的方案:所述消能削弱件的中间位置上下侧均为内凹式结构,且在中间位置水平方向开设有腰形槽;所述加固连接板的中间位置水平方向开设弧形槽,其中弧形槽与相应的腰形槽对应,且二者通过螺栓固定。
作为本发明进一步的方案:所述斜交网格柱安装在室内场馆的四周,整体呈“X”型结构或者“K”型结构或者“Y”型结构布置。
本发明还公开了一种空间立体悬吊廊道优化方法,包括如下步骤:
S1、首先建立模型,初步优化;
S11、定位悬吊廊道位置和尺寸;
S12、初步拟定悬吊廊道结构的参数、荷载形式,建立悬吊廊道整体仿真模型;
S13、验算悬吊廊道在恒载条件对其进行静力运算;
S14、根据得到吊杆的轴力值及廊道整体变形信息,对比规范,验证结果是否合理,若不合理,则回到步骤S12重新计算,调整相关系数,更新结构尺寸,直到确定仿真模型的合理性及正确性;反之,则进入下一步;
S2、其次进行吊杆优化;
S21、确定吊杆的材料、数量,依据给定吊杆轴力的设计值;
S22、采用有限元软件对吊杆的截面面积迭代计算;
S23、判断优化过程是否收敛,若优化过程不收敛,则返回步骤S21重新确定吊杆的材料、数量及位置;若优化过程收敛则输出吊杆截面面积最优参数;
S24、根据吊杆材料密度和体积并利用公式计算吊杆质量和长度的具体值;
S25、建立优化仿真模型,并进行结构整体安全验算,提取悬吊廊道整体变形信息;
S26、判断吊杆受力及廊道结构整体变形情况是否合理,判断吊杆轴力是否满足规范的限值是否合理;若均满足要求则进入下一步,若不满足其中之一的要求,则返回步骤S22重新进行二次参数优化;
S3、最后进行舒适度的整体分析;
通过模态分析方法或瞬态分析方法,或模态分析方法+瞬态分析方法的方式进行分析,后对比已知规范中动力响应值限值的规定,判断是否满足舒适度要求,若不满足舒适度要求,则重新进入步骤S2的吊杆优化。
作为本发明进一步的方案:所述步骤S22中截面面积迭代计算的具体方法为:
S221、在有限元程序中,可以通过改变杆单元的温差来模拟吊杆的张拉力FT,即模拟杆件的轴力,其中张拉力FT近似等于轴力设计值FN;
S222、吊杆材料的线膨胀系数定义为αT,根据材料的类别,选取相关值;
S223、吊杆材料的弹性模量定位为E,由于材料的类别可知,即弹性模量E
确定;
S224、最后,通过改变吊杆的单元温差△T,进行迭代运算得到材料截面面积Ai;
其中迭代运算公式为:FT=αT·(ΔT)·E·Ai………公式(1)。
作为本发明进一步的方案:所述步骤S24中吊杆质量和长度的计算方法为:
利用公式~得到吊杆质量和长度的关系,具体方法为:
由公式和公式推理出公式,即得到吊杆质量m和长度l的关系,因材料的类别已知,即材料的密度ρ确定,吊杆的体积V确定,将密度ρ和截面面积Ai代入到公式,得到吊杆质量和长度的具体比例关系;
然后将公式得到的吊杆质量和长度的比例关系,代入到公式,得出吊杆质量和长度具体的值,具体方法为:
公式中,FN为吊杆轴力设计值,已确定;f1和f2为吊杆的第一阶和第二阶的固有频率给出;γ为地震作用分项系数,最终算出吊杆的质量和长度具体的值。
作为本发明进一步的方案:所述步骤S25的具体操作方法为:
首先根据得到吊杆具体的质量和长度,建立优化后有限元仿真模型,并进行结构整体安全验算;
其次考虑“恒载+活载+温度+收缩徐变”最不利组合效应,通过有限元模拟软件对优化后的悬吊廊道进行结构验算,输出结果,提取悬吊廊道整体变形信息。
作为本发明进一步的方案:所述步骤S3中模态分析的具体方法包括:
首先得到廊道结构发生自由振动时具有的基本振动特性,包括振动的固有模式、固有频率和振型等参数;
然后根据已知振动舒适度评价指标对廊道结构舒适度进行评价是否满足要求,主要有自振频率和加速度两种;
如果自振频率满足则舒适度满足规范要求,则无需验证加速度;如果自振频
率不满足,则需要对加速度进行判断,达到限值则满足规范要求,反之不满足。
与现有技术相比,本发明的有益效果是:
一、本发明在空中廊道体系中合理位置设置固定段,在桥面段与桥面段之间,桥面段和廊道之间通过节点连接部件连接固定,最大程度的提高了空中廊道的安全性;转角段自由悬挑,避免了四周建筑对结构的遮挡,可以方便行人观看大范围周边景观;本申请将空中廊道设置在大型场馆中庭部位,可作为通往相应楼层的通道,充分利用了中庭空间,即满足了场馆参观游览的功能需求,又充分体现了建筑之美;
二、本发明通过在场馆中庭两侧设置斜交网格柱与空中廊道斜吊杆和固定段相连,有效保证了空中廊道在水平方向上的稳定性,同时斜交网格柱本身兼具剪力墙功能,由下至上连续性设置可在增加场馆层高的条件下提高场馆整体结构抗震韧性,又提供开阔视野,尤其适合参观类场馆;
三、本发明通过在桥面段与固定段或者转角段之间,固定段与廊道主体结构之间均设置了消能削弱件和加固连接板,通过设置削弱件相较于无削弱件(单一的连接方形钢板)连接段所受到的应力分散更小,无削弱件应力达到500MPa以超过部件本身极限强度,破坏严重;而有削弱件应力达到375MPa而未达到极限强度,部件稳定,这是由于消能削弱件中部的弧形有效释放了周围传递的应力,使得桥面段与固定段或者转角段之间,固定段与廊道主体结构之间整体稳定受力;
四、本发明通过对空中廊道结构的优化,优化后模型的悬吊廊道通道受力分布更加均匀,变形更加协调,吊杆材料得到了更充分的利用,避免了杆件受压失稳现象;优化后模型吊杆数量减少,更有利于施工,而且优化模型的吊杆用材料减少,具有更优的经济指标,本发明的仿真模型仅是通过公式得出的参数进行合理性检验的工具;
五、本发明优化后的模型不仅在安全上更加可靠,且不管是在仅考虑自重条件下的模态分析还是在考虑行人荷载条件下瞬态分析均满足工程所需舒适度的要求,避免了廊道结构和行人荷载产生共振造成交感神经紧张、心跳加速等精神刺激以及对悬吊廊道的破坏,使悬吊廊道的整体舒适度非常良好;
六、本发明提出空中廊道结构,然后通过部分能实施的试验在对廊道结构受力性能有初步了解的基础上,建立廊道仿真模型,不断优化模型参数进行反复调
试,然后进行初步受力性能计算并与之前做的部分试验结果进行对比,如果跟实验结果很相似,则证明该模型比较优,即得到优化后的模型,再通过这个模型去分析廊道其他更复杂的性能;本发明优化目的是使空中廊道结构和受力更安全、可靠、舒适。
图1为本发明实施例一种空间立体悬吊廊道的整体结构示意图;
图2为本发明实施例悬吊廊道的俯面结构示意图;
图3为本发明实施例悬吊廊道的正面结构示意图;
图4为本发明实施例节点连接部件的结构示意图;
图5为本发明实施例节点连接部件的部分放大图;
图6为本发明实施例节点连接部件的部分结构示意图;
图7为本发明实施例竖吊杆的部分结构示意图;
图8为本发明实施例节点连接位置处未设置削弱件时的Mises应力云图;
图9为本发明实施例节点连接位置处设置削弱件时的Mises应力云图;
图10为本发明实施例建立模型、初步优化的结构流程图;
图11为本发明实施例吊杆优化的结构流程图;
图12为本发明实施例舒适度整体分析的结构流程图;
附图标记说明:
1、悬吊廊道;101、固定段;102、桥面段;103、转角段;112、竖吊杆;
1121、第一杆件;1122、限位套;1123、第二杆件;113、斜吊杆;114、第一T型钢板;115、第二T型钢板;116、紧固螺栓;117、消能削弱件;118、加固连接板;119、腰形槽;
2、顶部钢屋盖;
3、斜交网格柱;
4、主体结构板。
1、悬吊廊道;101、固定段;102、桥面段;103、转角段;112、竖吊杆;
1121、第一杆件;1122、限位套;1123、第二杆件;113、斜吊杆;114、第一T型钢板;115、第二T型钢板;116、紧固螺栓;117、消能削弱件;118、加固连接板;119、腰形槽;
2、顶部钢屋盖;
3、斜交网格柱;
4、主体结构板。
为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本
领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
参照图1,一种空间立体悬吊廊道,包括有悬吊廊道1、顶部钢屋盖2、斜交网格柱3和主体结构板4,其中悬吊廊道1布置在室内场馆中庭,顶部钢屋盖2固定在场馆顶部,而斜交网格柱3布置在场馆的四周,斜交网格柱3从上往下布置,用来支撑室内楼层的主体结构板4。
参照图1、图2和图3,悬吊廊道1包括有若干固定段101、若干桥面段102、若干转角段103、竖吊杆112和斜吊杆113,其中桥面段102具体设置多少根据室内楼层高度、桥面段102、水平面倾角以及楼层高度均有关系;每组桥面段102均为倾斜往上布置,每组桥面段102与水平面之间存在夹角α,其中α的取值范围为:0°<α<60°,且每组桥面段102的上方均设置往上行走的阶梯。
参照图4、图5和图6,本申请桥面段102与转角段103之间通过节点连接部件连接,桥面段102与固定段101也是通过节点连接部件连接,两处连接原理相同。
下面以桥面段102与固定段101之间的连接为例,介绍二者之间节点连接部件的连接关系:节点连接部件具体包括有第一T型钢板114、第二T型钢板115,其中第一T型钢板114为桥面段102的预留段,第一T型钢板114与桥面段102为混凝土一体式浇筑成型;而第二T型钢板115为固定段101的预留段,第二T型钢板115与固定段101为混凝土一体式浇筑成型;
第一T型钢板114与第二T型钢板115贴合,二者连接处的前后两侧均安装有消能削弱件117,前后两侧的消能削弱件117上开设有四个圆弧孔,左侧的两个圆弧孔均通过紧固螺栓116连接到第二T型钢板115,右侧的两个圆弧孔均通过紧固螺栓116连接到第一T型钢板114(此处的左右方向以图5为参照图),此处圆弧孔而非圆孔目的在于螺栓在受力过程中有一定的缓冲作用,已达到卸能,桥面段102安全稳定的效果;在消能削弱件117的中间且上下两侧均设置为弧形内凹式结构,此处的设计能够达到降低能量传递,此部件通过ABAQUS软件进行论证;而在消能削弱件117的中间位置处还横向开设有腰形槽119,腰形槽119外部设加固连接板118,在加固连接板118上相应位置处同样开设弧形槽,弧形槽与腰形槽119相对应,二者通过螺栓加固,最后安装完成后,可在顶部安装盖
板,将连接处的空隙盖住,便于后续机械检修;此处腰形槽和弧形槽的设计目的也是在于螺栓在受力过程中有一定的缓冲作用,已达到卸能,桥面段102安全稳定的效果。
下面利用ABAQUS对以上节点连接部件进行有效性论证,通过对比方形板与我们设计的消能削弱件117的消能效果以论证部件有效性。由ABAUQS分析得到的Mises应力云图结果可知(参照图8和图9),本设计的削弱件相较于无削弱件(单一的连接方形钢板)所受到的应力分散更小,无削弱件应力达到500MPa以超过部件本身极限强度,破坏严重;而有削弱件应力达到375MPa而未达到极限强度,部件稳定,这是由于中部的弧形有效释放了周围传递的应力,使得整体部件稳定受力。
参照图1,顶部钢屋盖2呈格栅式安装在场馆的顶部,其用来支撑竖吊杆112,其中顶部钢屋盖采用组合桁架钢屋盖施工;考到现场条件、工程特点和施工成本等因素的影响,难以采用高空散装、整体吊装、屋面整体滑移等施工方法,本申请采用BIM技术,建立钢屋盖X-steel模型,实现三维数控加工、预拼装、模拟吊装等,不但保证吊装精度,而且降低操作难度,采用上述设计可确保钢结构空间构件准确定位,合理优化特殊节点;同时考虑到钢屋盖位于楼栋内部,吊装设备难以进入,本申请可以采用预留吊装洞口的方法,在地下室设置顶板预留洞口及外墙留置通道,吊车进入地下室中庭直接进行吊装,加快工期、节约成本,技术创效显著,通过钢桁架分段吊装,减少单构件吊装重量,安全可靠,施工简便。
参照图1,本申请斜交网格柱3呈“X”型安装在场馆的四周,用来对场馆楼层间进行支撑,本申请斜交网格劲性砼柱的安装,采用预留吊装洞口的方法,分段整体吊装,而非搭设脚手架和整体拼装,使用塔吊和巨型汽车吊吊装,技术创效显著。劲性砼柱采用自密实一次浇筑成型,减少了施工工序,节约了工期,避免了混凝土接茬处的二次处理费用,且斜交网格劲性砼柱的安装充分利用BIM技术,能够对钢结构和复杂节点进行优化,不但能够节省了钢材,而且减少了操作难度,节约了工期。
斜交网格柱3也可以采用“Y”型或者“K”型结构,具体采用何种形状本申请不做限定,工作人员视现场情况而定。
空中廊道结构由桥面段102、转角段103、固定段101、竖吊杆112、斜吊杆
113及相应的栏杆组成,转角段103和固定段101将空中廊道分割为若干桥面段102;由上至下,起始及终点位置为固定段101,相邻两个固定段101之间至少设置一个转角段103,转角段103自由悬挑,除终点位置固定段101与地面连接,其余固定段101均与楼层主体结构板4连接;转角段103通过多根斜吊杆113与斜交网格柱3连接,桥面段102通过多根竖吊杆112与顶部钢屋盖2连接。
需要注意的是,竖吊杆112的上端用耳板和销与钢屋盖2连接,竖吊杆112的中部由限位套1122将第一杆件1121与第二杆件1123连接(参照图7),其限位套1122内壁设置有内螺纹,第一杆件1121的一端设置有与限位套内螺纹配合的外螺纹,第二杆件1123一端设置有与限位套内螺纹配合的外螺纹,第二杆件1123一端与限位套1122连接;与竖吊杆相同,斜吊杆113中部由限位套将第一杆件与第二杆件连接,其限位套内壁设置有内螺纹,第一杆件的一端设置有与连接套内螺纹配合的外螺纹,第二杆件一端设置有与连接套内螺纹配合的外螺纹,但斜吊杆第一杆件一端与斜交网格柱3结构进行铰接,另一端与限位套连接,第二杆件一端与限位套连接。
本发明还提供一种空间立体悬吊廊道参数化优化及结构整体舒适度评价方法,本发明优化过程分为三个部分:
S1、建立模型,初步优化;
S11、定位吊桥位置和尺寸:
利用三维扫描机器人对已完工的主体结构进行三维扫描,定位悬吊廊道、尺寸;
S12、初步建立仿真模型:
初步拟定悬吊廊道结构的几何参数、荷载形式等数据,利用ANASY有限元软件建立悬吊廊道整体仿真模型;
S13、吊桥静力运算:
验算悬吊廊道在恒载(自重)条件对其进行静力运算;
S14、判断悬吊廊道在恒载的受力和变形是否合理;
根据得到吊杆的轴力值及廊道(或称吊桥,下文与此一致)整体变形信息,对比规范,验证结果是否合理,若不合理,则回到步骤S12重新计算,调整相关系数,更新结构尺寸,直到确定仿真模型的合理性及正确性;反之,则进入下一
步二次优化阶段。
S2、吊杆优化;
S21、确定吊杆(包括竖吊杆和斜吊杆,下文与此一致)的材料、数量,依据给定吊杆轴力的设计值;
S22、利用公式(1),采用有限元软件对吊杆的截面面积迭代计算,具体方法为:
在相关有限元程序中,可以通过改变杆单元的温差来模拟吊杆的张拉力FT,即模拟杆件的轴力;其中,张拉力FT近似等于吊杆轴力设计值FN;材料的线膨胀系数α,根据材料的类别,选取相关值,如下表1;材料的弹性模量E,根据材料的类别可知,即弹性模量E确定;最后,通过改变吊杆的单元温差△T,进行相关迭代运算得到吊杆材料截面面积Ai;
FT=αT·(ΔT)·E·Ai………公式(1)
FT=αT·(ΔT)·E·Ai………公式(1)
表1常用材料的线膨胀系数α
S23、判断优化过程是否收敛,即看结果是否趋近与0,若优化过程不收敛,则返回步骤S21重新确定吊杆的材料、数量及位置;若优化的吊杆截面面积收敛,则输出截面面积Ai最优参数;
S24、利用公式(2)~(4)得到吊杆质量和长度的关系,具体方法为:
由公式(2)和公式(3)得出公式(4),即得到吊杆质量和长度的关系;因吊杆材料的类别已知,即吊杆材料的密度ρ确定,吊杆的体积V确定,将密度ρ
和步骤S23得到的截面面积Ai代入到公式(4),得到吊杆质量和长度的具体比例关系;
具体的,将公式(4)得到的吊杆质量和长度的比例关系,代入到公式(5),得出吊杆质量和长度具体的值,具体方法为:
公式(5)中,FN为吊杆轴力设计值,已确定;f1和f2为吊杆的第1阶和第2阶的固有频率给出;γ为地震作用分项系数,可根据具体需求按表2取值,最终算出吊杆的质量和长度具体的值。
表2地震作用分项系数
γh:为水平地震分项系数。
γv:为竖向地震分项系数。
全部公式为:
式中:FN为吊杆轴力设计值;FT为吊杆的张拉力;
f1和f2分别为吊杆的第1阶和第2阶的固有频率;
γ为地震作用分项系数;
αT为材料的线膨胀系数;E为材料的弹性模量;
△T为第i根吊杆单元温度荷载变量;
Ai为第i根吊杆的截面面积;
V、m、l、ρ分为吊杆的体积、质量、长度以及密度。
S25、建立优化仿真模型:
根据得到吊杆具体的质量和长度,建立优化后的有限元仿真模型,并进行结构整体安全验算;考虑“恒载+活载+温度+收缩徐变”等最不利组合效应,通过有限元模拟软件对优化后的悬吊廊道/悬索吊桥进行结构验算,输出结果,提取悬吊廊道/悬索吊桥整体变形信息;
S26、判断吊杆受力及结构整体变形情况是否合理,并比较优化后的方案工程造价是否减少?
判断吊杆轴力是否满足规范的限值,或过大不经济、过小使材料无法完全发挥其性能?
若均满足要求则进入下一步整体优化,若不满足其中之一的要求,则重新返回步骤S22重新进行二次参数优化。
S3、整体分析(舒适度评价);
利用优化后数学模型对悬吊廊道进行结构整体舒适度的评价;舒适度评价分方法为两种,一种是模态分析;另一种是瞬态分析;据工程需求对结构进行模态分析(即步骤S31)或瞬态分析(步骤S32),或模态分析+瞬态分析,避免共振或使结构以特定的频率进行振动;
确定加载方式:
模态分析加载方式:通过有限元软件对仅考虑廊道自重条件的结构进行模态分析。
瞬态分析加载方式:确定人行荷载加载方法,其分为两种加载方式;一种为考虑单人行走荷载的加载方式;另一种为考虑人群荷载的加载方式。不同的加载方式其运用的函数表达式不同,根据工程需求选择合适的加载方式,也可两者均验证。
S31、确定模态分析方法:
模态分析首先确定合理的模态分析方法;不同有限元软件内置模态分析方法不同,如ANSYS有限元软件提供了七种模态分析的方法:①Block Lanzcos法、②子空间(Subspace)法、③非对称(Unsymmetric)法、④缩减(Reduced)、⑤Power Dynamics法、⑥QR阻尼法、⑦阻尼(Damped)法等,选择合理的模态
分析方法不仅能对结构完整的刚度矩阵进行考虑,还能确保计算精确度并且计算速度也快;
进行模态分析,得到廊道结构发生自由振动时具有的基本振动特性,包括振动的固有模式、固有频率和振型等参数。根据工程需求对结构舒适度进行评价是否满足要求。不同国家的舒适度评价指标不一,如表3所示。
主要有自振频率和加速度两种,如果自振频率满足则舒适度满足规范要求,则无需验证加速度;如果自振频率不满足,则需要对加速度进行判断,达到限值则满足规范要求,反之不满足。也可根据固有频率和振型曲线分析结构的质量、刚度分布以及刚度大小的合理性。
对比国内外规范中动力响应值限值的规定,看是否满足舒适度要求。若不满足舒适度要求,则重新进入步骤S2的吊杆优化;
表3国内外振动舒适度评价指标
S32、确定瞬态分析的分析方法:
进行瞬态分析,通过有限元模拟软件分别计算得到廊道结构的振动频率与固有频率的比值、时程-加速度动力曲线、时程-位移曲线等数据;
S33、对比国内外规范中动力响应值限值的规定,看是否满足舒适度要求。若不满足舒适度要求,则重新进入步骤S2的吊杆优化。
以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以
对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的精神和范围。
Claims (10)
- 一种空间立体悬吊廊道,包括连接室内楼层过道之间的悬吊廊道(1),其特征在于:其中室内楼层过道的边部均设有斜交网格柱(3);所述悬吊廊道(1)从上往下包括若干固定段(102)和若干桥面段(102),其中相邻两个固定段(102)之间至少设置一个转角段(103),所述固定段(102)或转角段(103)均通过节点连接部件连接相应的桥面段(102);其中转角段通过若干斜吊杆(113)连接到相应斜交网格柱(3)上,每个桥面段(102)上均通过若干竖吊杆(112)连接到顶部钢屋盖(2)上。
- 根据权利要求1所述的一种空间立体悬吊廊道,其特征在于:每处桥面段与水平面均存在夹角α,其中α的取值范围为:0°<α<60°。
- 根据权利要求1所述的一种空间立体悬吊廊道,其特征在于:所述节点连接部件包括有预埋在相应桥面段(102)内的第一T型钢板(114),预埋在相应固定段(101)或者转角段(103)内的第二T型钢板(115),所述第一T型钢板(114)与第二T型钢板(115)的左右两侧均通过消能削弱件(117)进行可拆卸连接,其中消能削弱件(117)又可拆卸连接有加固连接板(118)。
- 根据权利要求3所述的一种空间立体悬吊廊道,其特征在于:所述消能削弱件(117)的中间位置上下侧均为内凹式结构,且在中间位置水平方向开设有腰形槽(119);所述加固连接板(118)的中间位置水平方向开设弧形槽,其中弧形槽与相应的腰形槽(119)对应,且二者通过螺栓固定。
- 根据权利要求1所述的一种空间立体悬吊廊道,其特征在于:所述斜交网格柱(3)安装在室内场馆的四周,整体呈“X”型结构或者“K”型结构或者“Y”型结构布置。
- 一种如上述权利要求1-5任意一项所述的空间立体悬吊廊道的优化方法,其特征在于,包括如下步骤:S1、首先建立模型,初步优化;S11、定位悬吊廊道位置和尺寸;S12、初步拟定悬吊廊道结构的参数、荷载形式,建立悬吊廊道整体仿真模型;S13、验算悬吊廊道在恒载条件对其进行静力运算;S14、根据得到吊杆的轴力值及廊道整体变形信息,对比规范,验证结果是否合理,若不合理,则回到步骤S12重新计算,调整相关系数,更新结构尺寸,直到确定仿真模型的合理性及正确性;反之,则进入下一步;S2、其次进行吊杆优化;S21、确定吊杆的材料、数量,依据给定吊杆轴力的设计值;S22、采用有限元软件对吊杆的截面面积迭代计算;S23、判断优化过程是否收敛,若优化过程不收敛,则返回步骤S21重新确定吊杆的材料、数量及位置;若优化过程收敛则输出吊杆截面面积最优参数;S24、根据吊杆材料密度和体积并利用公式计算吊杆质量和长度的具体值;S25、建立优化仿真模型,并进行结构整体安全验算,提取悬吊廊道整体变形信息;S26、判断吊杆受力及廊道结构整体变形情况是否合理,判断吊杆轴力是否满足规范的限值是否合理;若均满足要求则进入下一步,若不满足其中之一的要求,则返回步骤S22重新进行二次参数优化;S3、最后进行舒适度的整体分析;通过模态分析方法或瞬态分析方法,或模态分析方法+瞬态分析方法的方式进行分析,后对比已知规范中动力响应值限值的规定,判断是否满足舒适度要求,若不满足舒适度要求,则重新进入步骤S2的吊杆优化。
- 根据权利要求6所述的空间立体悬吊廊道的优化方法,其特征在于:所述步骤S22中截面面积迭代计算的具体方法为:S221、在有限元程序中,可以通过改变杆单元的温差来模拟吊杆的张拉力FT,即模拟杆件的轴力,其中张拉力FT近似等于轴力设计值FN;S222、吊杆材料的线膨胀系数定义为αT,根据材料的类别,选取相关值;S223、吊杆材料的弹性模量定位为E,由于材料的类别可知,即弹性模量E确定;S224、最后,通过改变吊杆的单元温差△T,进行迭代运算得到材料截面面积Ai;其中迭代运算公式为:FT=αT·(ΔT)·E·Ai………公式(1)。
- 根据权利要求7所述的空间立体悬吊廊道的优化方法,其特征在于:所述步骤S24中吊杆质量和长度的计算方法为:利用公式(2)~(4)得到吊杆质量和长度的关系,具体方法为:
由公式(2)和公式(3)推理出公式(4),即得到吊杆质量m和长度l的关系,因材料的类别已知,即材料的密度ρ确定,吊杆的体积V确定,将密度ρ和截面面积Ai代入到公式(4),得到吊杆质量和长度的具体比例关系;然后将公式(4)得到的吊杆质量和长度的比例关系,代入到公式(5),得出吊杆质量和长度具体的值,具体方法为:
公式(5)中,FN为吊杆轴力设计值,已确定;f1和f2为吊杆的第一阶和第二阶的固有频率给出;γ为地震作用分项系数,最终算出吊杆的质量和长度具体的值。 - 根据权利要求6所述的空间立体悬吊廊道的优化方法,其特征在于:所述步骤S25的具体操作方法为:首先根据得到吊杆具体的质量和长度,建立优化后有限元仿真模型,并进行结构整体安全验算;其次考虑“恒载+活载+温度+收缩徐变”最不利组合效应,通过有限元模拟软件对优化后的悬吊廊道进行结构验算,输出结果,提取悬吊廊道整体变形信息。
- 根据权利要求6所述的空间立体悬吊廊道的优化方法,其特征在于:所述步骤S3中模态分析的具体方法包括:首先得到廊道结构发生自由振动时具有的基本振动特性,包括振动的固有模式、固有频率和振型等参数;然后根据已知振动舒适度评价指标对廊道结构舒适度进行评价是否满足要求,主要有自振频率和加速度两种;如果自振频率满足则舒适度满足规范要求,则无需验证加速度;如果自振频 率不满足,则需要对加速度进行判断,达到限值则满足规范要求,反之不满足。
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2025527823A JP2026514553A (ja) | 2024-04-11 | 2024-05-23 | 空間立体吊り廊下及びその最適化方法 |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202410436545.0A CN118327230A (zh) | 2024-04-11 | 2024-04-11 | 一种空间立体悬吊廊道及其优化方法 |
| CN202410436545.0 | 2024-04-11 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2025213539A1 true WO2025213539A1 (zh) | 2025-10-16 |
Family
ID=91781373
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/CN2024/094887 Pending WO2025213539A1 (zh) | 2024-04-11 | 2024-05-23 | 一种空间立体悬吊廊道及其优化方法 |
Country Status (4)
| Country | Link |
|---|---|
| JP (1) | JP2026514553A (zh) |
| CN (2) | CN118327230A (zh) |
| WO (1) | WO2025213539A1 (zh) |
| ZA (1) | ZA202404766B (zh) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN121562279A (zh) * | 2025-11-21 | 2026-02-24 | 徐州城泽建筑科技有限公司 | 基于有限元分析的钢结构稳定性仿真评价方法及平台 |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6728987B1 (en) * | 2002-04-23 | 2004-05-04 | Ch2M Hill, Inc. | Method of adjusting the vertical profile of a cable supported bridge |
| CN103967131A (zh) * | 2014-05-21 | 2014-08-06 | 中建五局蚌埠建筑工程有限公司 | 室内折线吊桥结构 |
| CN104899377A (zh) * | 2015-06-08 | 2015-09-09 | 大连理工大学 | 一种悬索桥索力优化方法 |
| CN107476581A (zh) * | 2017-07-06 | 2017-12-15 | 中国十七冶集团有限公司 | 一种钢结构双层悬挑结构吊装安装方法 |
| CN108875286A (zh) * | 2018-08-22 | 2018-11-23 | 大连理工大学 | 一种悬索桥整体结构分析的参数化优化方法 |
| CN214784662U (zh) * | 2021-02-08 | 2021-11-19 | 中国建筑一局(集团)有限公司 | 一种钢结构外悬挑仿古廊道布置结构 |
| CN114703956A (zh) * | 2022-04-06 | 2022-07-05 | 浙江乔兴建设集团有限公司 | 一种双层大跨度钢结构连廊施工工艺方法 |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101086965B1 (ko) * | 2009-01-30 | 2011-11-29 | 고려대학교 산학협력단 | 초대형 대각 가새 조립체 |
-
2024
- 2024-04-11 CN CN202410436545.0A patent/CN118327230A/zh active Pending
- 2024-05-23 WO PCT/CN2024/094887 patent/WO2025213539A1/zh active Pending
- 2024-05-23 JP JP2025527823A patent/JP2026514553A/ja active Pending
- 2024-06-19 ZA ZA2024/04766A patent/ZA202404766B/en unknown
-
2025
- 2025-03-31 CN CN202510394997.1A patent/CN120350742A/zh active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6728987B1 (en) * | 2002-04-23 | 2004-05-04 | Ch2M Hill, Inc. | Method of adjusting the vertical profile of a cable supported bridge |
| CN103967131A (zh) * | 2014-05-21 | 2014-08-06 | 中建五局蚌埠建筑工程有限公司 | 室内折线吊桥结构 |
| CN104899377A (zh) * | 2015-06-08 | 2015-09-09 | 大连理工大学 | 一种悬索桥索力优化方法 |
| CN107476581A (zh) * | 2017-07-06 | 2017-12-15 | 中国十七冶集团有限公司 | 一种钢结构双层悬挑结构吊装安装方法 |
| CN108875286A (zh) * | 2018-08-22 | 2018-11-23 | 大连理工大学 | 一种悬索桥整体结构分析的参数化优化方法 |
| CN214784662U (zh) * | 2021-02-08 | 2021-11-19 | 中国建筑一局(集团)有限公司 | 一种钢结构外悬挑仿古廊道布置结构 |
| CN114703956A (zh) * | 2022-04-06 | 2022-07-05 | 浙江乔兴建设集团有限公司 | 一种双层大跨度钢结构连廊施工工艺方法 |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN121562279A (zh) * | 2025-11-21 | 2026-02-24 | 徐州城泽建筑科技有限公司 | 基于有限元分析的钢结构稳定性仿真评价方法及平台 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN120350742A (zh) | 2025-07-22 |
| ZA202404766B (en) | 2025-01-29 |
| CN118327230A (zh) | 2024-07-12 |
| JP2026514553A (ja) | 2026-05-12 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101200916B (zh) | 一种预应力悬挂式建筑结构的施工方法 | |
| Foraboschi | Versatility of steel in correcting construction deficiencies and in seismic retrofitting of RC buildings | |
| CN107476581B (zh) | 一种钢结构双层悬挑结构吊装安装方法 | |
| CN111395532B (zh) | 大跨度半开口椭圆球面网壳安装施工方法 | |
| CN114837483B (zh) | 一种高低跨门式钢架建筑结构及其施工工艺 | |
| CN109138452A (zh) | 大型建筑螺栓球钢管网架整体快速提升施工工艺 | |
| CN115012554B (zh) | 一种多层冷弯薄壁型钢结构体系及装配方法 | |
| CN116561852A (zh) | 带转换结构大跨后张有粘结预应力混凝土框架梁设计方法 | |
| Ma et al. | Vertical deformation analysis of a high‐rise building with high‐position connections | |
| CN120350742A (zh) | 一种空间立体悬吊廊道及其优化方法 | |
| CN112069586A (zh) | 悬挑结构上安装型钢悬挑脚手架设计与施工方法 | |
| CN111364642A (zh) | 一种装配式耗能剪力墙体系及其施工方法 | |
| CN106337590B (zh) | 一种提高建筑结构抗倒塌能力的抗震设计方法 | |
| Kiriparan et al. | Analysis and Design of Skybridges connecting Tall Buildings–A case study | |
| CN118498635A (zh) | 一种室内场馆螺旋式悬吊廊道及其优化方法 | |
| CN208137136U (zh) | 一种设置单向斜撑的转换梁 | |
| CN109518897B (zh) | 轻质装配式折板与悬挑梁组合楼梯 | |
| CN208009632U (zh) | 一种框架结构体系 | |
| CN119956929B (zh) | 一种空间立体悬吊廊道及其吊装、卸载方法 | |
| Yao et al. | Research on Design and Construction Technology of Width-Narrowing Multi-Layer Interval High-Level Connected Structure | |
| Yu et al. | Analysis of Engineering Structure Design and Management Mode of Lihuayi Group Media Center | |
| CN203821926U (zh) | 一种抗震房的轻钢龙骨结构体系 | |
| Güler et al. | An examination of damages of reinforced concrete consoled buildings in Turkey due to 17 August 1999 Kocaeli Earthquake | |
| CN203640308U (zh) | 高空架设式钢梁受力平台 | |
| Qin et al. | Seismic performance of reinforced concrete open-web sandwich slab-column structures for high-rise long-span buildings under rare earthquakes |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| ENP | Entry into the national phase |
Ref document number: 2025527823 Country of ref document: JP Kind code of ref document: A |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2025527823 Country of ref document: JP |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 24934614 Country of ref document: EP Kind code of ref document: A1 |