WO2025026311A1 - Arched tunnel structure and arched tunnel construction method - Google Patents
Arched tunnel structure and arched tunnel construction method Download PDFInfo
- Publication number
- WO2025026311A1 WO2025026311A1 PCT/CN2024/108503 CN2024108503W WO2025026311A1 WO 2025026311 A1 WO2025026311 A1 WO 2025026311A1 CN 2024108503 W CN2024108503 W CN 2024108503W WO 2025026311 A1 WO2025026311 A1 WO 2025026311A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- arched
- arc
- tunnel
- shaped
- ribs
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/102—Removable shuttering; Bearing or supporting devices therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/107—Reinforcing elements therefor; Holders for the reinforcing elements
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
Definitions
- the present application relates to the field of tunnel construction, and specifically to an arched tunnel structure and an arched tunnel construction method.
- the arched vault is formed by splicing a plurality of small-area square templates to form an arched surface and then pouring.
- the square template itself has no curvature, the shape of the final vault is not round enough.
- the multiple spliced arc templates may be deformed or even cracked, which further leads to a poor curvature of the final poured vault, a distorted arc and a rough surface, which ultimately leads to a poor forming effect of the vault.
- an arched tunnel structure comprising a plurality of support rods, a plurality of top supports, a plurality of arched beams, a plurality of lower ribs and a plurality of arcuate lower templates.
- the top supports are located at the ends of the support rods and supported by the support rods.
- a plurality of arched beams are arranged at intervals along the longitudinal direction of the tunnel, and each arched beam is supported by a plurality of top supports.
- Each lower rib extends longitudinally along the tunnel, and a plurality of lower ribs are arranged at intervals along the length track of the arched beam, and each lower rib is supported by at least two adjacent arched beams.
- a plurality of arcuate lower templates are supported by the lower ribs, and a plurality of arcuate lower templates are spliced into an arched lower casting surface, and the lower casting surface is located on the side of the arcuate lower template facing away from the lower ribs.
- the force of the lower casting surface is dispersed to the length track lines of the plurality of lower ribs, and then to the length track lines of the plurality of arched beams, and then to each top support, and the length track line of the lower ribs is perpendicular to the length track line of the arched beam, so that the lower casting surface maintains an arch shape during casting.
- the concrete is supported by the lower pouring surface.
- the force on the lower pouring surface is surface force.
- the force on the lower pouring surface can be dispersed to the length trajectory lines of multiple lower ribs, and the surface force is converted into longitudinal line force.
- the force of multiple lower ribs will be further dispersed to the length trajectory lines of multiple arched beams, and the longitudinal line force is converted into transverse line force.
- the force of multiple arched beams will be further dispersed to each top support, and the transverse line force is converted into point force.
- the force is more dispersed through three-level dispersed force, avoiding excessive stress concentration, and avoiding deformation or cracking of the arc-shaped lower formwork, so that the arch shape can be better maintained during the pouring of the lower pouring surface, and the surface of the arch top after pouring is smoother and the arc shape is more beautiful.
- the arched tunnel structure also includes multiple arc-shaped upper formworks and multiple upper ribs.
- the multiple arc-shaped upper formworks can be spliced into an arched upper casting surface.
- the upper casting surface is located above the lower casting surface.
- the space between the lower casting surface and the upper casting surface is used for pouring concrete.
- Each upper rib extends longitudinally along the tunnel.
- the multiple upper ribs are arranged at intervals along the width track of the upper casting surface.
- the upper ribs are located on the side of the arc-shaped upper formwork facing away from the arc-shaped lower formwork.
- the arc-shaped upper formwork is fixed to the upper ribs.
- the arched tunnel structure further includes a plurality of tension screws, each of which passes through the arc-shaped upper template and the arc-shaped lower template and limits the distance between the arc-shaped upper template and the arc-shaped lower template.
- the arc-shaped upper template located at the top of the upper casting surface of the arched tunnel structure is provided with a casting hole, and the casting hole connects the space between the arc-shaped upper template and the arc-shaped lower template to cast concrete.
- At least two tubes are placed side by side on the top of the jacking support, each of which extends longitudinally along the tunnel, and the jacking support contacts and supports the topmost portion of the lower surface of the arched beam through the tubes, and a wedge block is placed on the top of the tubes, and the jacking support contacts and supports the non-topmost portion of the lower surface of the arched beam through the inclined surface of the wedge block.
- some of the multiple support rods are vertically arranged, and the top supports are arranged at the top ends of the some of the vertically arranged support rods; some of the multiple support rods are horizontally arranged along the transverse direction of the tunnel, and the top supports are arranged at the opposite ends of the some of the horizontally arranged support rods; some of the multiple support rods are cross-arranged along the transverse direction of the tunnel, and the top supports are arranged at the top ends of the some of the cross-arranged support rods.
- the plurality of arched beams are arranged at intervals of a first distance, and the plurality of lower ribs are arranged at intervals of a second distance, wherein the second distance is smaller than the first distance.
- the arched tunnel structure also includes two side walls and multiple tripod supports.
- the two side walls extend longitudinally along the tunnel.
- the arched beam is located above the two side walls.
- Multiple tripod supports are provided on the facing sides of each side wall, and the tripod supports are used to support multiple support rods.
- the lower rib is made of pine wood with a rectangular cross-section, and the arc-shaped lower template is fixed to the lower rib.
- an arch tunnel construction method for building the arch tunnel structure in any of the above embodiments comprising: pouring a concrete cushion layer, laying a waterproof membrane on the concrete cushion layer, and pouring a waterproof layer on the waterproof membrane to form a working plane; pouring a bottom plate and short side walls on both sides of the bottom plate on the working plane; pouring side walls on the top of the two short side walls respectively; constructing a plurality of support rods; installing top supports at the ends of the plurality of support rods; supporting a plurality of arch beams on the plurality of top supports; splicing a plurality of arc-shaped lower templates to form a lower casting surface, during which the plurality of arc-shaped lower templates are fixed to the lower ribs so that the lower ribs and the arc-shaped lower templates become one body, and at the same time the integrated lower ribs and the arc-shaped lower templates are supported on the arch beams; pouring concrete on the lower casting surface to
- the above-mentioned arch tunnel construction method also enables the force of the lower casting surface to be dispersed to the length trajectory lines of multiple lower ribs, converting the surface force into longitudinal line force.
- the force of multiple lower ribs will be further dispersed to the length trajectory lines of multiple arch beams, converting the longitudinal line force into transverse line force.
- the force of multiple arch beams will be further dispersed to each top support, converting the transverse line force into point force. Therefore, the force is more dispersed through three-level force dispersion, avoiding excessive stress concentration, avoiding deformation or cracking of the arc-shaped lower formwork, and thus making the arch shape better maintained during the casting of the lower casting surface, making the surface of the arch top smoother and the arc shape more beautiful after casting.
- FIG1 is a flow chart of an arch tunnel construction method in one embodiment of the present application.
- FIG. 2 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S1 is completed.
- FIG. 3 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S2 is completed.
- FIG. 4 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S3 is completed.
- FIG. 5 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S9 is completed.
- FIG. 6 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S10 is completed.
- FIG. 7 is a partial cross-sectional view of an arched tunnel structure in one embodiment of the present application.
- FIG8 is a schematic diagram of the structure of the arched beam and the lower rib in one embodiment of the present application.
- FIG. 9 is a schematic structural diagram of an arched beam and a lower rib in another embodiment of the present application.
- a component when referred to as being "fixed to” another component, it may be directly on the other component or there may also be a component centered.
- a component When a component is considered to be “connected to” another component, it may be directly connected to the other component or there may also be a component centered.
- a component When a component is considered to be “set on” another component, it may be directly set on the other component or there may also be a component centered.
- the terms “vertical”, “horizontal”, “left”, “right” and similar expressions used herein are for illustrative purposes only.
- perpendicular is used to describe an ideal state between two components. In actual production or use, there may be a state that is approximately perpendicular between the two components.
- perpendicularity may refer to the angle between two straight lines being in the range of 90° ⁇ 10°
- perpendicularity may also refer to the dihedral angle between two planes being in the range of 90° ⁇ 10°
- perpendicularity may also refer to the angle between a straight line and a plane being in the range of 90° ⁇ 10°.
- the two components described as "perpendicular” may not be absolute straight lines or planes, but may be roughly straight lines or planes. From a macroscopic perspective, a component can be considered a "straight line” or a “plane” if the overall extension direction is a straight line or a plane.
- the vault of the arch is formed by splicing a plurality of small-area arc-shaped templates together to form an arched surface and then pouring.
- the plurality of spliced arc-shaped templates may be deformed or even cracked, resulting in a poor curvature of the finally poured vault, a distorted arc and a rough surface, which ultimately leads to a poor forming effect of the vault.
- the arched tunnel structure includes multiple support rods, multiple top supports, multiple arched beams, multiple lower ribs and multiple arc-shaped lower templates.
- the top supports are located at the ends of the support rods and supported by the support rods.
- Multiple arched beams are arranged at intervals along the longitudinal direction of the tunnel, and each arched beam is supported by multiple top supports.
- Each lower rib extends along the longitudinal direction of the tunnel, and multiple lower ribs are arranged at intervals along the length track of the arched beams, and each lower rib is supported by at least two adjacent arched beams.
- Multiple arc-shaped lower templates are supported by the lower ribs, and multiple arc-shaped lower templates are spliced into an arched lower casting surface, and the lower casting surface is located on the side of the arc-shaped lower template facing away from the lower ribs.
- the force of the lower pouring surface is dispersed to the length trajectory lines of multiple lower ribs, and then to the length trajectory lines of multiple arched beams, and then to each top support.
- the length trajectory line of the lower ribs is perpendicular to the length trajectory line of the arched beam, so that the lower pouring surface maintains an arch shape during pouring.
- the force on the lower pouring surface is surface force.
- the force on the lower pouring surface can be dispersed to the length trajectory lines of multiple lower ribs, and the surface force is converted into longitudinal line force.
- the force on multiple lower ribs will be further dispersed to the length trajectory lines of multiple arched beams, and the longitudinal line force will be converted into transverse line force.
- the force on multiple arched beams will be further dispersed to each top support, and the transverse line force will be further dispersed to each top support.
- Line force is transformed into point force, and the force is further dispersed through three-level dispersed force, avoiding excessive stress concentration and deformation or cracking of the arc-shaped lower formwork, so that the arch shape can be better maintained during the pouring of the lower pouring surface, making the surface of the arch after pouring smoother and the arc more beautiful.
- an arched tunnel structure 100 and an arched tunnel construction method 200 are provided in one embodiment of the present application.
- the arched tunnel construction method 200 is used to build the arched tunnel structure 100, and the arched tunnel structure 100 is used to cast the arch of the arched tunnel.
- the arched tunnel structure 100 includes a plurality of support rods 10, a plurality of top supports 20, a plurality of arched beams 30, a plurality of lower ribs 40 and a plurality of arc-shaped lower templates 50.
- a plurality of support rods 10 are staggeredly built in the foundation pit of the tunnel to form a support structure.
- Top supports 20 are installed at the ends of some support rods 10, and the top supports 20 are used to contact the arched beams 30 to realize the support of the support rods 10 to the arched beams 30.
- a plurality of arched beams 30 are arranged at intervals along the longitudinal direction of the tunnel, and the length of each arched beam 30 is extended along the cross section of the tunnel, and each arched beam 30 is supported by a plurality of top supports 20.
- Each lower rib 40 extends longitudinally along the tunnel, and the length trajectory of the lower rib 40 is perpendicular to the length trajectory of the arched beam 30. Multiple lower ribs 40 are arranged at intervals along the length trajectory of the arched beam 30.
- the lower ribs 40 are located above the arched beam 30, and each lower rib 40 is supported by at least two adjacent arched beams 30.
- Multiple arc-shaped lower templates 50 are located above the lower ribs 40 and supported by the lower ribs 40.
- the multiple arc-shaped lower templates 50 can be spliced into an arched lower casting surface, which is located on the side of the arc-shaped lower template 50 facing away from the lower rib 40, that is, it is arranged upward.
- the force on the lower casting surface is surface force.
- the force on the lower casting surface can be dispersed to the length trajectory lines of multiple lower ribs 40, and the surface force is converted into longitudinal line force.
- the force on multiple lower ribs 40 will be further dispersed to the length trajectory lines of multiple arched beams 30, and the longitudinal line force is converted into transverse line force.
- the force on multiple arched beams 30 will be further dispersed to each top support 20, and the transverse line force is converted into point force.
- the force is further dispersed through the three-level dispersed force, avoiding excessive stress concentration, and avoiding deformation or cracking of the arc-shaped lower formwork 50, so that the arch shape can be better maintained during the pouring of the lower casting surface, and the surface of the arch top after pouring is smoother and the arc shape is more beautiful.
- multiple arch beams 30 are arranged at intervals of a first distance, and multiple lower ribs 40 are arranged at intervals of a second distance, which is smaller than the first distance, so that more lower ribs 40 are distributed on each arch beam 30, so that the lower ribs 40 can distribute the force more evenly to the arch beam 30, so that the force distribution of the arch beam 30 is more even.
- the arc of the arc-shaped lower template 50 between two adjacent lower ribs 40 may be flattened under the pressure of concrete.
- the second distance is equal to one-fifth of the first distance, which makes the arch after pouring the most beautiful on the basis of saving building materials and manpower.
- multiple arch beams 30 are arranged at intervals of 75 cm, and multiple lower ribs 40 are arranged at intervals of 15 cm.
- the arched tunnel structure 100 further includes a plurality of arc-shaped upper templates 60 and a plurality of upper ribs 70.
- the plurality of arc-shaped upper templates 60 can be spliced together to form an arched upper casting.
- the upper casting surface is located above the lower casting surface, and the space between the lower casting surface and the upper casting surface is used for pouring concrete.
- Each upper rib 70 extends longitudinally along the tunnel, and multiple upper ribs 70 are arranged at intervals along the width track of the upper casting surface.
- the upper rib 70 is located on the side of the arc-shaped upper template 60 that is away from the arc-shaped lower template 50, that is, the upper rib 70 is located above the arc-shaped upper template 60, and the arc-shaped upper template 60 is fixed to the upper rib 70.
- the upper rib 70 is fixed in position by tying steel bars 71 on the back.
- the upper casting surface can transfer the surface force to the upper rib 70, so that the surface force is converted into line force, thereby dispersing the force, and because the upper casting surface is less stressed than the lower casting surface, the upper rib 70 can withstand the dispersed force after being tied with steel bars 71, without the need to disperse the force again, thereby avoiding unnecessary consumables and manpower.
- the lower ribs 40 and the upper ribs 70 are made of pine wood with a rectangular cross section, and the arc-shaped lower template 50 is nailed to the lower ribs 40, and multiple arc-shaped lower templates 50 are integrated with multiple lower ribs 40, so that the lower ribs 40 can be placed on the arched beam 30, and there is no need to fix the arc-shaped lower template 50 and the arched beam 30, thereby improving construction efficiency.
- the arc-shaped upper template 60 is nailed to the upper ribs 70, and multiple arc-shaped upper templates 60 are integrated with multiple upper ribs 70, and the upper ribs 70 are fixed in position by tying steel bars 71 on the back, thereby fixing the arc-shaped upper template 60, which can also improve construction efficiency.
- the arched tunnel structure 100 also includes a plurality of tension screws 80, each of which passes through the arched beam 30, the arc-shaped upper formwork 60 and the arc-shaped lower formwork 50, and is used to limit the distance between the arc-shaped upper formwork 60 and the arc-shaped lower formwork 50 to prevent the arc-shaped upper formwork 60 and the arc-shaped lower formwork 50 from expanding and cracking during pouring.
- the tensioning screw 80 since the tensioning screw 80 needs to contact the curved surface at the bottom of the arched beam 30, the arched tunnel structure 100 also includes a curved plate 82 and two circular tubes 81.
- the bottom end of the tensioning screw 80 is pressed against the curved surface by the curved plate 82 and the two circular tubes 81 (i.e., double-piece steel tubes).
- the circular tubes 81 extend longitudinally along the tunnel.
- the curved plate 82 presses the side walls of the two circular tubes 81 to the bottom of the arched beam 30.
- the side walls of the two circular tubes 81 are in line contact with the curved surface at the bottom of the arched beam 30, thereby playing a pulling role.
- the top of the tensioning screw 80 also needs to contact the top surface of the curved steel bar 71. Therefore, the side walls of the two circular tubes 81 are pressed to the top surface of the steel bar 71 by the curved plate 82.
- the side walls of the two circular tubes 81 are in line contact with the curved top surface of the steel bar 71, thereby achieving tightening tension.
- the arc-shaped upper formwork 60 at the top of the upper casting surface of the arched tunnel structure 100 is provided with a casting hole 61, which extends longitudinally along the tunnel.
- the casting hole 61 connects the space between the arc-shaped upper formwork 60 and the arc-shaped lower formwork 50 to realize the casting of concrete.
- At least two tubes 21 are placed side by side on the top of the jacking support 20, and each tube 21 extends longitudinally along the tunnel. If the jacking support 20 just radially supports the arched beam 30 along the arc surface at the bottom of the arched beam 30, the jacking support 20 only needs to contact and support the lower surface of the arched beam 30 through the tubes 21, for example, the vertical jacking support 20 supports the topmost part of the arched beam 30 through the tubes 21, or the inclined jacking support 20 supports the non-topmost part of the arched beam 30 through the tubes 21.
- top support 20 cannot fully contact the lower surface of the arched beam 30 directly through the tube body 21, for example, when the vertical top support 20 supports the non-topmost part of the arched beam 30, a wedge block 22 is placed on the top of the tube body 21, and the top support 20 contacts and supports the lower surface of the arched beam 30 through the inclined surface of the wedge block 22.
- wedge blocks 22 There are multiple types of wedge blocks 22, and the inclination of the inclined surface of each wedge block 22 is different.
- Each top support 20 selects the required wedge block 22 according to its own position, so that the inclined surface of the wedge block 22 can more fully contact the lower surface of the arched beam 30, thereby stably supporting the arched beam 30.
- the wedge block 22 has a curved surface instead of an inclined surface. The curved surface of the wedge block 22 is used to fully contact the lower surface of the arched beam 30 , so that the wedge block 22 can more fully disperse the force and further improve the stability of the arched beam 30 .
- the cross section of the tube body 21 is circular, forming a line contact with the arched beam 30, so that the tube body 21 stably contacts the arched beam 30.
- the cross section of the tube body 21 is square, so as to fully contact the flat bottom surface of the wedge block 22 and improve the stability of the wedge block 22.
- some of the multiple support rods 10 are arranged vertically, and the top supports 20 are arranged at the top ends of the vertically arranged support rods 10.
- Some of the multiple support rods 10 are arranged horizontally along the tunnel, and the top supports 20 are arranged at opposite ends of the horizontally arranged support rods 10, and the top supports 20 at both ends are used to support the arched beams 30.
- Some of the multiple support rods 10 are arranged crosswise along the tunnel to form a transverse scissors brace, and the top supports 20 are arranged at the top ends of the crosswise arranged support rods 10.
- the arc-shaped lower template 50 uses a customized curved surface 1.5 cm thick wooden template
- the arched beam 30 uses an I14 steel I-beam
- the lower rib 40 uses a 5 cm*10 cm square wood
- multiple lower ribs 40 are arranged at a spacing of 15 cm
- the arc-shaped upper template 60 also uses a customized curved surface 1.5 cm thick wooden template
- the upper rib 70 also uses a 5 cm*10 cm square wood
- multiple upper ribs 70 are also arranged at a spacing of 15 cm.
- the steel bars 71 use double ⁇ 32 steel bars to tie the upper ribs 70 tightly, and the steel bars 71 are arranged transversely along the tunnel and at a spacing of 75 cm.
- the arched tunnel structure 100 further includes two side walls 240 and a plurality of tripod supports 90 .
- the two side walls 240 extend longitudinally along the tunnel.
- the arched beam 30 is located above the two side walls 240 .
- a plurality of tripod supports 90 are provided on the facing sides of each side wall 240 .
- the tripod supports 90 are used to assist in supporting a plurality of support rods 10 to enhance the strength and stability of the support rods 10 .
- each lower rib 40 on a plurality of arched beams 30 always extends in the longitudinal direction of the tunnel, that is, each lower rib 40 spans over all arched beams 30 to facilitate construction design.
- each lower rib 40 does not always extend in the longitudinal direction of the tunnel, and the lower ribs 40 on opposite sides of some arched beams 30 are staggered so that when the lower rib 40 is insufficient in length and cannot continue to extend, the lower rib 40 on the other side can have enough area to contact the arched beam 30, so as to avoid the ends of the lower ribs 40 on both sides from crowding at the same place of the arched beam 30, thereby improving stability.
- an arch tunnel construction method 200 includes:
- S6 Supporting a plurality of arched beams 30 on a plurality of top supports 20, as shown in FIGS. 5 and 7;
- S7 Splice multiple arc-shaped lower templates 50 to form a lower casting surface.
- the lower rib 40 is fixed to the lower rib 40 so that the lower rib 40 and the arc-shaped lower template 50 are integrated, and the integrated lower rib 40 and the arc-shaped lower template 50 are supported on the arched beam 30, as shown in FIG. 5 and FIG. 7;
- the concrete cushion layer is a 5cm thick fine stone concrete cushion layer
- the waterproof layer is a 5cm thick fine stone waterproof protective layer, so that the working plane 210 connects the project foundation and the building without leakage, which is the first barrier to waterproofing the entire project and plays a role in resisting external rainwater and groundwater leakage.
- the bottom plate reinforcement is tied, and then the low side wall formwork is installed, and then the water stop steel plate is set, and finally the bottom plate 220 and the low side wall 230 are cast.
- the height of the low side wall 230 is preferably set to a height range of 200-300 mm from the bottom plate 220, and the concrete is C35P10 anti-seepage concrete.
- the side wall reinforcement is tied.
- a temporary work platform 270 is set up on both sides of the short side wall 230 to facilitate construction workers to build the template.
- the side wall template is reinforced by the main rib, which uses vertical 50*50*3mm square steel pipes with a spacing of 150mm; and two horizontal double-jointed 48mm*3mm straightening steel pipes are set up; M14 tensioning screws are used with a spacing of 450*450mm for tensioning; the bracket is set up with a steel pipe rack with a pitch of 600*600*900.
- the side wall concrete is poured to form the side wall 240.
- the side wall formwork is removed and the arch support system is erected.
- the support rod 10 uses a 600*600*900 steel pipe, and all vertical poles are erected with horizontal scissors braces, longitudinal scissors braces and transverse scissors braces to further ensure the stability of the frame.
- the pouring when pouring the vault concrete, the pouring is carried out in layers and symmetrically, with the pouring height of each layer not exceeding 40 cm. At the same time, an inserted vibrator is used to vibrate evenly to improve the pouring quality.
- the protective layer 260 is a 0.5 mm thick self-adhesive waterproof membrane and a brick membrane, which plays a protective role.
- a tunnel concrete structure for the experiment is usually cast in a laboratory, and a tunnel formed by using the arch tunnel structure 100 and the arch tunnel construction method 200 of the present application is used for indoor experiments.
- the overall size of the tunnel is not as large as the tunnel actually used.
- the arch tunnel structure 100 and the arch tunnel construction method 200 of the present application are suitable for tunnel structures constructed by open-cut method.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
本申请涉及隧道建造领域,具体为一种拱形隧道结构及拱形隧道施工方法。The present application relates to the field of tunnel construction, and specifically to an arched tunnel structure and an arched tunnel construction method.
目前在建造拱形隧道时,拱形的拱顶通过多个小面积的方形模板相拼接呈拱形面后再浇筑形成,但方形模板由于本身不具有弧度,导致最后成型的拱顶的形状不够圆,并且在浇筑时,由于液态混凝土的压力较大,会导致多个相拼接的弧形模板变形甚至开裂,进一步导致最后浇筑出的拱顶的弧度较差,拱顶的弧形扭曲且表面粗糙,最终导致拱顶的成型效果差。At present, when constructing an arched tunnel, the arched vault is formed by splicing a plurality of small-area square templates to form an arched surface and then pouring. However, since the square template itself has no curvature, the shape of the final vault is not round enough. During pouring, due to the high pressure of liquid concrete, the multiple spliced arc templates may be deformed or even cracked, which further leads to a poor curvature of the final poured vault, a distorted arc and a rough surface, which ultimately leads to a poor forming effect of the vault.
发明内容Summary of the invention
有鉴于此,有必要提供一种能够提升隧道拱顶的成型效果的拱形隧道结构及拱形隧道施工方法,能够使拱顶浇筑后的表面更光滑且弧形更优美。In view of this, it is necessary to provide an arched tunnel structure and an arched tunnel construction method that can improve the forming effect of the tunnel vault, so that the surface of the vault after casting is smoother and the arc is more beautiful.
本申请一实施例中提供一种拱形隧道结构,包括多个支撑杆、多个顶托、多个拱形梁、多个下楞及多个弧形下模板。顶托位于支撑杆的端部并受支撑杆支撑。多个拱形梁沿隧道纵向相间隔地排列,每个拱形梁受多个顶托支撑。每个下楞沿隧道纵向延伸,多个下楞沿拱形梁的长度轨迹相间隔地排列,每个下楞至少受相邻两个拱形梁支撑。多个弧形下模板受下楞支撑,多个弧形下模板相拼接成拱形的下浇筑面,下浇筑面位于弧形下模板背向下楞的一侧。浇筑时下浇筑面的受力分散至多个下楞的长度轨迹线,再分散至多个拱形梁的长度轨迹线,再分散至每个顶托,下楞的长度轨迹线与拱形梁的长度轨迹线相垂直,使下浇筑面浇筑时维持拱形。In one embodiment of the present application, an arched tunnel structure is provided, comprising a plurality of support rods, a plurality of top supports, a plurality of arched beams, a plurality of lower ribs and a plurality of arcuate lower templates. The top supports are located at the ends of the support rods and supported by the support rods. A plurality of arched beams are arranged at intervals along the longitudinal direction of the tunnel, and each arched beam is supported by a plurality of top supports. Each lower rib extends longitudinally along the tunnel, and a plurality of lower ribs are arranged at intervals along the length track of the arched beam, and each lower rib is supported by at least two adjacent arched beams. A plurality of arcuate lower templates are supported by the lower ribs, and a plurality of arcuate lower templates are spliced into an arched lower casting surface, and the lower casting surface is located on the side of the arcuate lower template facing away from the lower ribs. During casting, the force of the lower casting surface is dispersed to the length track lines of the plurality of lower ribs, and then to the length track lines of the plurality of arched beams, and then to each top support, and the length track line of the lower ribs is perpendicular to the length track line of the arched beam, so that the lower casting surface maintains an arch shape during casting.
上述拱形隧道结构在浇筑时,混凝土受下浇筑面支撑,下浇筑面的受力为面受力,下浇筑面的受力能够分散至多个下楞的长度轨迹线,将面受力变为纵向线受力,多个下楞的受力会再分散至多个拱形梁的长度轨迹线,将纵向线受力变为横向线受力,多个拱形梁的受力会再分散至每个顶托,将横向线受力变为点受力,从而通过三级分散受力使受力更加分散,避免应力过于集中,避免弧形下模板变形或开裂,进而使下浇筑面浇筑时始终更好地维持拱形,使拱顶浇筑后的表面更光滑且弧形更优美。When the above-mentioned arched tunnel structure is poured, the concrete is supported by the lower pouring surface. The force on the lower pouring surface is surface force. The force on the lower pouring surface can be dispersed to the length trajectory lines of multiple lower ribs, and the surface force is converted into longitudinal line force. The force of multiple lower ribs will be further dispersed to the length trajectory lines of multiple arched beams, and the longitudinal line force is converted into transverse line force. The force of multiple arched beams will be further dispersed to each top support, and the transverse line force is converted into point force. Thus, the force is more dispersed through three-level dispersed force, avoiding excessive stress concentration, and avoiding deformation or cracking of the arc-shaped lower formwork, so that the arch shape can be better maintained during the pouring of the lower pouring surface, and the surface of the arch top after pouring is smoother and the arc shape is more beautiful.
在一些实施例中,拱形隧道结构还包括多个弧形上模板及多个上楞,多个弧形上模板能相拼接成拱形的上浇筑面,上浇筑面位于下浇筑面的上方,下浇筑面与上浇筑面之间的空间用于浇筑混凝土,每个上楞沿隧道纵向延伸,多个上楞沿上浇筑面的宽度轨迹相间隔地排列,上楞位于弧形上模板背向弧形下模板的一侧,弧形上模板固定于上楞。 In some embodiments, the arched tunnel structure also includes multiple arc-shaped upper formworks and multiple upper ribs. The multiple arc-shaped upper formworks can be spliced into an arched upper casting surface. The upper casting surface is located above the lower casting surface. The space between the lower casting surface and the upper casting surface is used for pouring concrete. Each upper rib extends longitudinally along the tunnel. The multiple upper ribs are arranged at intervals along the width track of the upper casting surface. The upper ribs are located on the side of the arc-shaped upper formwork facing away from the arc-shaped lower formwork. The arc-shaped upper formwork is fixed to the upper ribs.
在一些实施例中,拱形隧道结构还包括多个对拉螺杆,每个对拉螺杆穿过弧形上模板及弧形下模板,并限制弧形上模板及弧形下模板之间的距离。In some embodiments, the arched tunnel structure further includes a plurality of tension screws, each of which passes through the arc-shaped upper template and the arc-shaped lower template and limits the distance between the arc-shaped upper template and the arc-shaped lower template.
在一些实施例中,拱形隧道结构位于上浇筑面最顶部的弧形上模板设有浇筑孔,浇筑孔连通弧形上模板及弧形下模板之间的空间,以浇筑混凝土。In some embodiments, the arc-shaped upper template located at the top of the upper casting surface of the arched tunnel structure is provided with a casting hole, and the casting hole connects the space between the arc-shaped upper template and the arc-shaped lower template to cast concrete.
在一些实施例中,顶托的顶部并列放置有至少两个管体,每个管体沿隧道纵向延伸,顶托通过管体接触并支撑拱形梁的下表面的最顶部,管体的顶部放置有楔形块,顶托通过楔形块的斜面接触并支撑拱形梁的下表面的非最顶部。In some embodiments, at least two tubes are placed side by side on the top of the jacking support, each of which extends longitudinally along the tunnel, and the jacking support contacts and supports the topmost portion of the lower surface of the arched beam through the tubes, and a wedge block is placed on the top of the tubes, and the jacking support contacts and supports the non-topmost portion of the lower surface of the arched beam through the inclined surface of the wedge block.
在一些实施例中,部分的多个支撑杆竖直设置,顶托设于部分的竖直设置的支撑杆的顶端,部分的多个支撑杆沿隧道横向水平设置,顶托设于部分的水平设置的支撑杆的相对两端,部分的多个支撑杆沿隧道横向交叉设置,顶托设于部分的交叉设置的支撑杆的顶端。In some embodiments, some of the multiple support rods are vertically arranged, and the top supports are arranged at the top ends of the some of the vertically arranged support rods; some of the multiple support rods are horizontally arranged along the transverse direction of the tunnel, and the top supports are arranged at the opposite ends of the some of the horizontally arranged support rods; some of the multiple support rods are cross-arranged along the transverse direction of the tunnel, and the top supports are arranged at the top ends of the some of the cross-arranged support rods.
在一些实施例中,多个拱形梁以第一距离为间隔排列,多个下楞以第二距离为间隔排列,第二距离小于第一距离。In some embodiments, the plurality of arched beams are arranged at intervals of a first distance, and the plurality of lower ribs are arranged at intervals of a second distance, wherein the second distance is smaller than the first distance.
在一些实施例中,拱形隧道结构还包括两个侧墙体及多个三角架托,两个侧墙体沿隧道纵向延伸,拱形梁位于两个侧墙体之间的上方,每个侧墙体的相向侧设有多个三角架托,三角架托用于支撑多个支撑杆。In some embodiments, the arched tunnel structure also includes two side walls and multiple tripod supports. The two side walls extend longitudinally along the tunnel. The arched beam is located above the two side walls. Multiple tripod supports are provided on the facing sides of each side wall, and the tripod supports are used to support multiple support rods.
在一些实施例中,下楞为截面呈矩形的松木,弧形下模板固定于下楞。In some embodiments, the lower rib is made of pine wood with a rectangular cross-section, and the arc-shaped lower template is fixed to the lower rib.
本申请一实施例中还提供一种拱形隧道施工方法,用于搭建上述任一实施例中的拱形隧道结构,拱形隧道施工方法包括:浇筑混凝土垫层,在混凝土垫层上铺设防水卷材,在防水卷材上浇筑防水层,以形成作业平面;在作业平面上浇筑底板及底板两侧的矮边墙;在两个矮边墙顶部分别浇筑侧墙;搭建多个支撑杆;在多个支撑杆的端部安装顶托;将多个拱形梁支撑在多个顶托上;拼接多个弧形下模板形成下浇筑面,拼接时多个弧形下模板与下楞固定,使下楞与弧形下模板成为一体,同时一体的下楞与弧形下模板支撑在拱形梁上;在下浇筑面上浇筑混凝土以形成拱顶,且拱顶的两侧分别与两个侧墙连接;在底板、侧墙及拱顶的外表面铺设保护层,并在保护层的外侧进行碎石回填。In one embodiment of the present application, there is also provided an arch tunnel construction method for building the arch tunnel structure in any of the above embodiments, the arch tunnel construction method comprising: pouring a concrete cushion layer, laying a waterproof membrane on the concrete cushion layer, and pouring a waterproof layer on the waterproof membrane to form a working plane; pouring a bottom plate and short side walls on both sides of the bottom plate on the working plane; pouring side walls on the top of the two short side walls respectively; constructing a plurality of support rods; installing top supports at the ends of the plurality of support rods; supporting a plurality of arch beams on the plurality of top supports; splicing a plurality of arc-shaped lower templates to form a lower casting surface, during which the plurality of arc-shaped lower templates are fixed to the lower ribs so that the lower ribs and the arc-shaped lower templates become one body, and at the same time the integrated lower ribs and the arc-shaped lower templates are supported on the arch beams; pouring concrete on the lower casting surface to form an arch, and the two sides of the arch are respectively connected to the two side walls; laying a protective layer on the outer surface of the bottom plate, the side walls and the arch, and backfilling gravel on the outer side of the protective layer.
上述拱形隧道施工方法同样使得下浇筑面的受力能够分散至多个下楞的长度轨迹线,将面受力变为纵向线受力,多个下楞的受力会再分散至多个拱形梁的长度轨迹线,将纵向线受力变为横向线受力,多个拱形梁的受力会再分散至每个顶托,将横向线受力变为点受力,从而通过三级分散受力使受力更加分散,避免应力过于集中,避免弧形下模板变形或开裂,进而使下浇筑面浇筑时始终更好地维持拱形,使拱顶浇筑后的表面更光滑且弧形更优美。The above-mentioned arch tunnel construction method also enables the force of the lower casting surface to be dispersed to the length trajectory lines of multiple lower ribs, converting the surface force into longitudinal line force. The force of multiple lower ribs will be further dispersed to the length trajectory lines of multiple arch beams, converting the longitudinal line force into transverse line force. The force of multiple arch beams will be further dispersed to each top support, converting the transverse line force into point force. Therefore, the force is more dispersed through three-level force dispersion, avoiding excessive stress concentration, avoiding deformation or cracking of the arc-shaped lower formwork, and thus making the arch shape better maintained during the casting of the lower casting surface, making the surface of the arch top smoother and the arc shape more beautiful after casting.
图1为本申请一实施例中拱形隧道施工方法的流程图。FIG1 is a flow chart of an arch tunnel construction method in one embodiment of the present application.
图2为图1中拱形隧道施工方法中S1完成后的剖视图。 FIG. 2 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S1 is completed.
图3为图1中拱形隧道施工方法中S2完成后的剖视图。FIG. 3 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S2 is completed.
图4为图1中拱形隧道施工方法中S3完成后的剖视图。FIG. 4 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S3 is completed.
图5为图1中拱形隧道施工方法中S9完成后的剖视图。FIG. 5 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S9 is completed.
图6为图1中拱形隧道施工方法中S10完成后的剖视图。FIG. 6 is a cross-sectional view of the arch tunnel construction method in FIG. 1 after S10 is completed.
图7为本申请一实施例中拱形隧道结构的部分剖视图。FIG. 7 is a partial cross-sectional view of an arched tunnel structure in one embodiment of the present application.
图8为本申请一实施例中拱形梁及下楞的结构示意图。FIG8 is a schematic diagram of the structure of the arched beam and the lower rib in one embodiment of the present application.
图9为本申请另一实施例中拱形梁及下楞的结构示意图。FIG. 9 is a schematic structural diagram of an arched beam and a lower rib in another embodiment of the present application.
主要元件符号说明Main component symbols
拱形隧道结构 100Arched tunnel structure 100
支撑杆 10Support rod 10
顶托 20Top support 20
管体 21Pipe body 21
楔形块 22Wedge Block 22
拱形梁 30Arched beam 30
下楞 40Lower edge 40
弧形下模板 50Curved lower template 50
弧形上模板 60Curved upper template 60
浇筑孔 61Casting hole 61
上楞 70Shang Leng 70
钢筋 71Steel bar 71
对拉螺杆 80Tie screw 80
圆管 81Round tube 81
弧形板 82Curved plate 82
三角架托 90Tripod bracket 90
拱形隧道施工方法 200Arch Tunnel Construction Methods 200
作业平面 210Working plane 210
底板 220Bottom plate 220
矮边墙 230Low side wall 230
侧墙 240Side wall 240
拱顶 250Vault 250
保护层 260Protective layer 260
临时作业平台 270Temporary working platform 270
下面将结合本申请实施方式中的附图,对本申请的技术方案进行描述,显然,所描述的实施方式仅仅是本申请一部分实施方式,而不是全部的实施方式。 The technical solution of the present application will be described below in conjunction with the drawings in the implementation modes of the present application. Obviously, the described implementation modes are only part of the implementation modes of the present application, rather than all the implementation modes.
需要说明的是,当组件被称为“固定于”另一个组件,它可以直接在另一个组件上或者也可以存在居中的组件。当一个组件被认为是“连接”另一个组件,它可以是直接连接到另一个组件或者可能同时存在居中组件。当一个组件被认为是“设置于”另一个组件,它可以是直接设置在另一个组件上或者可能同时存在居中组件。本文所使用的术语“垂直的”、“水平的”、“左”、“右”以及类似的表述只是为了说明的目的。It should be noted that when a component is referred to as being "fixed to" another component, it may be directly on the other component or there may also be a component centered. When a component is considered to be "connected to" another component, it may be directly connected to the other component or there may also be a component centered. When a component is considered to be "set on" another component, it may be directly set on the other component or there may also be a component centered. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.
此外,术语“第一”、“第二”、“第三”等仅用于描述目的,而不能理解为指示或暗示相对重要性。术语“垂直”用于描述两个部件之间的理想状态。实际生产或使用的状态中,两个部件之间可以存在近似于垂直的状态。举例来说,结合数值描述,垂直可以指代两直线之间夹角范围在90°±10°之间,垂直也可以指代两平面的二面角范围在90°±10°之间,垂直还可以指代直线与平面之间的夹角范围在90°±10°之间。被描述“垂直”的两个部件可以不是绝对的直线、平面,也可以大致呈直线或平面,从宏观来看整体延伸方向为直线或平面即可认为部件为“直线”或“平面”。In addition, the terms "first", "second", "third", etc. are used for descriptive purposes only and are not to be understood as indicating or implying relative importance. The term "perpendicular" is used to describe an ideal state between two components. In actual production or use, there may be a state that is approximately perpendicular between the two components. For example, in combination with numerical descriptions, perpendicularity may refer to the angle between two straight lines being in the range of 90°±10°, perpendicularity may also refer to the dihedral angle between two planes being in the range of 90°±10°, and perpendicularity may also refer to the angle between a straight line and a plane being in the range of 90°±10°. The two components described as "perpendicular" may not be absolute straight lines or planes, but may be roughly straight lines or planes. From a macroscopic perspective, a component can be considered a "straight line" or a "plane" if the overall extension direction is a straight line or a plane.
除非另有定义,本文所使用的所有的技术和科学术语与属于本申请的技术领域的技术人员通常理解的含义相同。本文中在本申请的说明书中所使用的术语只是为了描述具体的实施方式的目的,不是旨在于限制本申请。本文所使用的术语“或/及”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application. The term "or/and" used herein includes any and all combinations of one or more of the related listed items.
目前在建造拱形隧道时,拱形的拱顶通过多个小面积的弧形模板相拼接呈拱形面后再浇筑形成,但在浇筑时,由于液态混凝土的压力较大,会导致多个相拼接的弧形模板变形甚至开裂,致使最后浇筑出的拱顶的弧度较差,拱顶的弧形扭曲且表面粗糙,最终导致拱顶的成型效果差。At present, when constructing an arched tunnel, the vault of the arch is formed by splicing a plurality of small-area arc-shaped templates together to form an arched surface and then pouring. However, during pouring, due to the high pressure of liquid concrete, the plurality of spliced arc-shaped templates may be deformed or even cracked, resulting in a poor curvature of the finally poured vault, a distorted arc and a rough surface, which ultimately leads to a poor forming effect of the vault.
有鉴于此,有必要提供一种能够提升隧道拱顶的成型效果的拱形隧道结构及拱形隧道施工方法,能够使拱顶浇筑后的表面更光滑且弧形更优美。拱形隧道结构包括多个支撑杆、多个顶托、多个拱形梁、多个下楞及多个弧形下模板。顶托位于支撑杆的端部并受支撑杆支撑。多个拱形梁沿隧道纵向相间隔地排列,每个拱形梁受多个顶托支撑。每个下楞沿隧道纵向延伸,多个下楞沿拱形梁的长度轨迹相间隔地排列,每个下楞至少受相邻两个拱形梁支撑。多个弧形下模板受下楞支撑,多个弧形下模板相拼接成拱形的下浇筑面,下浇筑面位于弧形下模板背向下楞的一侧。浇筑时下浇筑面的受力分散至多个下楞的长度轨迹线,再分散至多个拱形梁的长度轨迹线,再分散至每个顶托,下楞的长度轨迹线与拱形梁的长度轨迹线相垂直,使下浇筑面浇筑时维持拱形。In view of this, it is necessary to provide an arched tunnel structure and an arched tunnel construction method that can improve the forming effect of the tunnel vault, so that the surface of the vault after casting is smoother and the arc is more beautiful. The arched tunnel structure includes multiple support rods, multiple top supports, multiple arched beams, multiple lower ribs and multiple arc-shaped lower templates. The top supports are located at the ends of the support rods and supported by the support rods. Multiple arched beams are arranged at intervals along the longitudinal direction of the tunnel, and each arched beam is supported by multiple top supports. Each lower rib extends along the longitudinal direction of the tunnel, and multiple lower ribs are arranged at intervals along the length track of the arched beams, and each lower rib is supported by at least two adjacent arched beams. Multiple arc-shaped lower templates are supported by the lower ribs, and multiple arc-shaped lower templates are spliced into an arched lower casting surface, and the lower casting surface is located on the side of the arc-shaped lower template facing away from the lower ribs. During pouring, the force of the lower pouring surface is dispersed to the length trajectory lines of multiple lower ribs, and then to the length trajectory lines of multiple arched beams, and then to each top support. The length trajectory line of the lower ribs is perpendicular to the length trajectory line of the arched beam, so that the lower pouring surface maintains an arch shape during pouring.
上述拱形隧道结构在浇筑时,混凝土受下浇筑面支撑,下浇筑面的受力为面受力,下浇筑面的受力能够分散至多个下楞的长度轨迹线,将面受力变为纵向线受力,多个下楞的受力会再分散至多个拱形梁的长度轨迹线,将纵向线受力变为横向线受力,多个拱形梁的受力会再分散至每个顶托,将横向 线受力变为点受力,从而通过三级分散受力使受力更加分散,避免应力过于集中,避免弧形下模板变形或开裂,进而使下浇筑面浇筑时始终更好地维持拱形,使拱顶浇筑后的表面更光滑且弧形更优美。When the arched tunnel structure is poured, the concrete is supported by the lower pouring surface. The force on the lower pouring surface is surface force. The force on the lower pouring surface can be dispersed to the length trajectory lines of multiple lower ribs, and the surface force is converted into longitudinal line force. The force on multiple lower ribs will be further dispersed to the length trajectory lines of multiple arched beams, and the longitudinal line force will be converted into transverse line force. The force on multiple arched beams will be further dispersed to each top support, and the transverse line force will be further dispersed to each top support. Line force is transformed into point force, and the force is further dispersed through three-level dispersed force, avoiding excessive stress concentration and deformation or cracking of the arc-shaped lower formwork, so that the arch shape can be better maintained during the pouring of the lower pouring surface, making the surface of the arch after pouring smoother and the arc more beautiful.
下面结合附图,对本申请的一些实施方式作详细说明。在不冲突的情况下,下述的实施方式及实施方式中的特征可以相互组合。Some embodiments of the present application are described in detail below in conjunction with the accompanying drawings. In the absence of conflict, the following embodiments and features in the embodiments can be combined with each other.
请参阅图1、图5、图7及图8,本申请一实施例中提供一种拱形隧道结构100及拱形隧道施工方法200,拱形隧道施工方法200用于搭建拱形隧道结构100,拱形隧道结构100用于浇筑成型拱形隧道的拱顶。拱形隧道结构100包括多个支撑杆10、多个顶托20、多个拱形梁30、多个下楞40及多个弧形下模板50。多个支撑杆10相交错地搭建于隧道的基坑内以形成一个支撑架构。部分支撑杆10的端部安装有顶托20,顶托20用于接触拱形梁30,以实现支撑杆10对拱形梁30的支撑。多个拱形梁30沿隧道纵向相间隔地排列,且每个拱形梁30的长度沿隧道横截面延伸设置,每个拱形梁30受多个顶托20支撑。每个下楞40沿隧道纵向延伸,下楞40的长度轨迹线与拱形梁30的长度轨迹线相垂直,多个下楞40沿拱形梁30的长度轨迹相间隔地排列,下楞40位于拱形梁30上方,且每个下楞40至少受相邻两个拱形梁30支撑。多个弧形下模板50位于下楞40上方并受下楞40支撑,多个弧形下模板50能够相拼接成一个拱形的下浇筑面,下浇筑面位于弧形下模板50背向下楞40的一侧,即朝上设置。Referring to Fig. 1, Fig. 5, Fig. 7 and Fig. 8, an arched tunnel structure 100 and an arched tunnel construction method 200 are provided in one embodiment of the present application. The arched tunnel construction method 200 is used to build the arched tunnel structure 100, and the arched tunnel structure 100 is used to cast the arch of the arched tunnel. The arched tunnel structure 100 includes a plurality of support rods 10, a plurality of top supports 20, a plurality of arched beams 30, a plurality of lower ribs 40 and a plurality of arc-shaped lower templates 50. A plurality of support rods 10 are staggeredly built in the foundation pit of the tunnel to form a support structure. Top supports 20 are installed at the ends of some support rods 10, and the top supports 20 are used to contact the arched beams 30 to realize the support of the support rods 10 to the arched beams 30. A plurality of arched beams 30 are arranged at intervals along the longitudinal direction of the tunnel, and the length of each arched beam 30 is extended along the cross section of the tunnel, and each arched beam 30 is supported by a plurality of top supports 20. Each lower rib 40 extends longitudinally along the tunnel, and the length trajectory of the lower rib 40 is perpendicular to the length trajectory of the arched beam 30. Multiple lower ribs 40 are arranged at intervals along the length trajectory of the arched beam 30. The lower ribs 40 are located above the arched beam 30, and each lower rib 40 is supported by at least two adjacent arched beams 30. Multiple arc-shaped lower templates 50 are located above the lower ribs 40 and supported by the lower ribs 40. The multiple arc-shaped lower templates 50 can be spliced into an arched lower casting surface, which is located on the side of the arc-shaped lower template 50 facing away from the lower rib 40, that is, it is arranged upward.
浇筑时,混凝土受下浇筑面支撑,下浇筑面的受力为面受力,下浇筑面的受力能够分散至多个下楞40的长度轨迹线,将面受力变为纵向线受力,多个下楞40的受力会再分散至多个拱形梁30的长度轨迹线,将纵向线受力变为横向线受力,多个拱形梁30的受力会再分散至每个顶托20,将横向线受力变为点受力,从而通过三级分散受力使受力更加分散,避免应力过于集中,避免弧形下模板50变形或开裂,进而使下浇筑面浇筑时始终更好地维持拱形,使拱顶浇筑后的表面更光滑且弧形更优美。During pouring, concrete is supported by the lower casting surface. The force on the lower casting surface is surface force. The force on the lower casting surface can be dispersed to the length trajectory lines of multiple lower ribs 40, and the surface force is converted into longitudinal line force. The force on multiple lower ribs 40 will be further dispersed to the length trajectory lines of multiple arched beams 30, and the longitudinal line force is converted into transverse line force. The force on multiple arched beams 30 will be further dispersed to each top support 20, and the transverse line force is converted into point force. Thus, the force is further dispersed through the three-level dispersed force, avoiding excessive stress concentration, and avoiding deformation or cracking of the arc-shaped lower formwork 50, so that the arch shape can be better maintained during the pouring of the lower casting surface, and the surface of the arch top after pouring is smoother and the arc shape is more beautiful.
为了更好地维持隧道顶部的拱形,多个拱形梁30以第一距离为间隔排列,多个下楞40以第二距离为间隔排列,第二距离小于第一距离,使得每个拱形梁30上分布有更多的下楞40,从而使下楞40将受力更均匀地分散至拱形梁30上,使拱形梁30得受力分布更均匀。另外在浇筑时,在混凝土的压力下相邻两个下楞40之间的弧形下模板50的弧形可能会被压平,所以根据微积分原理,即使弧形下模板50的弧形被压平,只有每相邻两个下楞40之间的距离越近,下浇筑面的拱形就越优美。根据大量的现场作业经验而言,第二距离等于第一距离五分之一,在节约建材及人力的基础上,使得浇筑后的拱形最为优美。作为示范性举例,多个拱形梁30以75厘米相隔设置,多个下楞40以15厘米相隔设置。In order to better maintain the arch of the tunnel top, multiple arch beams 30 are arranged at intervals of a first distance, and multiple lower ribs 40 are arranged at intervals of a second distance, which is smaller than the first distance, so that more lower ribs 40 are distributed on each arch beam 30, so that the lower ribs 40 can distribute the force more evenly to the arch beam 30, so that the force distribution of the arch beam 30 is more even. In addition, during pouring, the arc of the arc-shaped lower template 50 between two adjacent lower ribs 40 may be flattened under the pressure of concrete. Therefore, according to the principle of calculus, even if the arc of the arc-shaped lower template 50 is flattened, the closer the distance between each two adjacent lower ribs 40, the more beautiful the arch of the lower casting surface. According to a large amount of on-site operation experience, the second distance is equal to one-fifth of the first distance, which makes the arch after pouring the most beautiful on the basis of saving building materials and manpower. As an exemplary example, multiple arch beams 30 are arranged at intervals of 75 cm, and multiple lower ribs 40 are arranged at intervals of 15 cm.
请参阅图5及图7,在一些实施例中,拱形隧道结构100还包括多个弧形上模板60及多个上楞70,多个弧形上模板60能相拼接成拱形的上浇筑 面,上浇筑面位于下浇筑面的上方,下浇筑面与上浇筑面之间的空间用于浇筑混凝土。每个上楞70沿隧道纵向延伸,多个上楞70沿上浇筑面的宽度轨迹相间隔地排列,上楞70位于弧形上模板60背向弧形下模板50的一侧,即上楞70位于弧形上模板60的上方,弧形上模板60固定于上楞70,上楞70通过背面捆扎钢筋71来实现位置的固定。浇筑时,上浇筑面能够将面受力传递至上楞70,使面受力变为线受力,从而分散受力,并且由于上浇筑面相较于下浇筑面的受力较小,故上楞70通过钢筋71捆扎后即可承受分散的受力,无需再次分散受力,避免多余的耗材及人力。Please refer to FIG. 5 and FIG. 7. In some embodiments, the arched tunnel structure 100 further includes a plurality of arc-shaped upper templates 60 and a plurality of upper ribs 70. The plurality of arc-shaped upper templates 60 can be spliced together to form an arched upper casting. The upper casting surface is located above the lower casting surface, and the space between the lower casting surface and the upper casting surface is used for pouring concrete. Each upper rib 70 extends longitudinally along the tunnel, and multiple upper ribs 70 are arranged at intervals along the width track of the upper casting surface. The upper rib 70 is located on the side of the arc-shaped upper template 60 that is away from the arc-shaped lower template 50, that is, the upper rib 70 is located above the arc-shaped upper template 60, and the arc-shaped upper template 60 is fixed to the upper rib 70. The upper rib 70 is fixed in position by tying steel bars 71 on the back. During pouring, the upper casting surface can transfer the surface force to the upper rib 70, so that the surface force is converted into line force, thereby dispersing the force, and because the upper casting surface is less stressed than the lower casting surface, the upper rib 70 can withstand the dispersed force after being tied with steel bars 71, without the need to disperse the force again, thereby avoiding unnecessary consumables and manpower.
在一些实施例中,下楞40及上楞70为截面呈矩形的松木,弧形下模板50钉于下楞40上,多个弧形下模板50与多个下楞40形成一体,从而使下楞40可以搭在拱形梁30上,无需固定弧形下模板50与拱形梁30,提升施工效率。同理,弧形上模板60钉于上楞70,多个弧形上模板60与多个上楞70形成一体,上楞70通过背面捆扎钢筋71来实现位置的固定,从而固定弧形上模板60,也能够提升施工效率。In some embodiments, the lower ribs 40 and the upper ribs 70 are made of pine wood with a rectangular cross section, and the arc-shaped lower template 50 is nailed to the lower ribs 40, and multiple arc-shaped lower templates 50 are integrated with multiple lower ribs 40, so that the lower ribs 40 can be placed on the arched beam 30, and there is no need to fix the arc-shaped lower template 50 and the arched beam 30, thereby improving construction efficiency. Similarly, the arc-shaped upper template 60 is nailed to the upper ribs 70, and multiple arc-shaped upper templates 60 are integrated with multiple upper ribs 70, and the upper ribs 70 are fixed in position by tying steel bars 71 on the back, thereby fixing the arc-shaped upper template 60, which can also improve construction efficiency.
在一些实施例中,拱形隧道结构100还包括多个对拉螺杆80,每个对拉螺杆80穿过拱形梁30、弧形上模板60及弧形下模板50,并用于限制弧形上模板60及弧形下模板50之间的距离,避免浇筑时弧形上模板60及弧形下模板50膨胀开裂。其中,由于对拉螺杆80需要接触拱形梁30底部的弧面,拱形隧道结构100还包括弧形板82及两个圆管81,对拉螺杆80的底端通过弧形板82及两个圆管81(即双拼钢管)压紧弧面,圆管81沿隧道纵向延伸,弧形板82压紧两个圆管81的侧壁至拱形梁30底部,两个圆管81的侧壁与拱形梁30底部的弧面线接触,从而起到对拉的作用,同理,对拉螺杆80的顶部也需要接触弧形的钢筋71的顶面,所以,通过弧形板82压紧两个圆管81的侧壁至钢筋71的顶面,两个圆管81的侧壁与钢筋71的弧形顶面线接触,从而实现紧固的对拉。In some embodiments, the arched tunnel structure 100 also includes a plurality of tension screws 80, each of which passes through the arched beam 30, the arc-shaped upper formwork 60 and the arc-shaped lower formwork 50, and is used to limit the distance between the arc-shaped upper formwork 60 and the arc-shaped lower formwork 50 to prevent the arc-shaped upper formwork 60 and the arc-shaped lower formwork 50 from expanding and cracking during pouring. Among them, since the tensioning screw 80 needs to contact the curved surface at the bottom of the arched beam 30, the arched tunnel structure 100 also includes a curved plate 82 and two circular tubes 81. The bottom end of the tensioning screw 80 is pressed against the curved surface by the curved plate 82 and the two circular tubes 81 (i.e., double-piece steel tubes). The circular tubes 81 extend longitudinally along the tunnel. The curved plate 82 presses the side walls of the two circular tubes 81 to the bottom of the arched beam 30. The side walls of the two circular tubes 81 are in line contact with the curved surface at the bottom of the arched beam 30, thereby playing a pulling role. Similarly, the top of the tensioning screw 80 also needs to contact the top surface of the curved steel bar 71. Therefore, the side walls of the two circular tubes 81 are pressed to the top surface of the steel bar 71 by the curved plate 82. The side walls of the two circular tubes 81 are in line contact with the curved top surface of the steel bar 71, thereby achieving tightening tension.
在一些实施例中,拱形隧道结构100位于上浇筑面最顶部的弧形上模板60设有浇筑孔61,浇筑孔61沿隧道纵向延伸,浇筑孔61连通弧形上模板60及弧形下模板50之间的空间,以实现浇筑混凝土。In some embodiments, the arc-shaped upper formwork 60 at the top of the upper casting surface of the arched tunnel structure 100 is provided with a casting hole 61, which extends longitudinally along the tunnel. The casting hole 61 connects the space between the arc-shaped upper formwork 60 and the arc-shaped lower formwork 50 to realize the casting of concrete.
在一些实施例中,顶托20的顶部并列放置有至少两个管体21,每个管体21沿隧道纵向延伸。若顶托20恰好沿拱形梁30底部的弧面径向顶住拱形梁30,则顶托20只需要通过管体21接触并支撑拱形梁30的下表面,例如竖直的顶托20通过管体21支撑拱形梁30的最顶部,或倾斜的顶托20通过管体21支撑拱形梁30的非最顶部。若顶托20无法直接通过管体21充分接触拱形梁30的下表面,例如竖直的顶托20支撑拱形梁30的非最顶部时,管体21的顶部放置有楔形块22,顶托20通过楔形块22的斜面接触并支撑拱形梁30的下表面,楔形块22具有多种,每种楔形块22的斜面的倾斜度不同,每个顶托20根据自身位置选择所需的楔形块22,使得楔形块22的斜面能够更充分地接触拱形梁30的下表面,从而稳定地支撑拱形梁30。在其 他实施例中,楔形块22具有弧面,而非斜面,楔形块22的弧面用于充分接触拱形梁30的下表面,从而使楔形块22更充分地分散受力,进一步提升拱形梁30的稳定性。In some embodiments, at least two tubes 21 are placed side by side on the top of the jacking support 20, and each tube 21 extends longitudinally along the tunnel. If the jacking support 20 just radially supports the arched beam 30 along the arc surface at the bottom of the arched beam 30, the jacking support 20 only needs to contact and support the lower surface of the arched beam 30 through the tubes 21, for example, the vertical jacking support 20 supports the topmost part of the arched beam 30 through the tubes 21, or the inclined jacking support 20 supports the non-topmost part of the arched beam 30 through the tubes 21. If the top support 20 cannot fully contact the lower surface of the arched beam 30 directly through the tube body 21, for example, when the vertical top support 20 supports the non-topmost part of the arched beam 30, a wedge block 22 is placed on the top of the tube body 21, and the top support 20 contacts and supports the lower surface of the arched beam 30 through the inclined surface of the wedge block 22. There are multiple types of wedge blocks 22, and the inclination of the inclined surface of each wedge block 22 is different. Each top support 20 selects the required wedge block 22 according to its own position, so that the inclined surface of the wedge block 22 can more fully contact the lower surface of the arched beam 30, thereby stably supporting the arched beam 30. In other embodiments, the wedge block 22 has a curved surface instead of an inclined surface. The curved surface of the wedge block 22 is used to fully contact the lower surface of the arched beam 30 , so that the wedge block 22 can more fully disperse the force and further improve the stability of the arched beam 30 .
作为示范性举例,当顶托20直接通过管体21接触拱形梁30时,管体21的截面为圆形,与拱形梁30形成线接触,使管体21稳定接触拱形梁30。当顶托20通过楔形块22接触拱形梁30时,管体21的截面为方形,以充分接触楔形块22的平底面,提升楔形块22的稳定性。As an illustrative example, when the jacking support 20 directly contacts the arched beam 30 through the tube body 21, the cross section of the tube body 21 is circular, forming a line contact with the arched beam 30, so that the tube body 21 stably contacts the arched beam 30. When the jacking support 20 contacts the arched beam 30 through the wedge block 22, the cross section of the tube body 21 is square, so as to fully contact the flat bottom surface of the wedge block 22 and improve the stability of the wedge block 22.
在一些实施例中,部分的多个支撑杆10竖直设置,顶托20设于部分的竖直设置的支撑杆10的顶端。部分的多个支撑杆10沿隧道横向水平设置,顶托20设于部分的水平设置的支撑杆10的相对两端,两端的顶托20均用于支撑拱形梁30。部分的多个支撑杆10沿隧道横向交叉设置,形成横向剪刀撑,顶托20设于部分的交叉设置的支撑杆10的顶端。In some embodiments, some of the multiple support rods 10 are arranged vertically, and the top supports 20 are arranged at the top ends of the vertically arranged support rods 10. Some of the multiple support rods 10 are arranged horizontally along the tunnel, and the top supports 20 are arranged at opposite ends of the horizontally arranged support rods 10, and the top supports 20 at both ends are used to support the arched beams 30. Some of the multiple support rods 10 are arranged crosswise along the tunnel to form a transverse scissors brace, and the top supports 20 are arranged at the top ends of the crosswise arranged support rods 10.
在一些实施例中,弧形下模板50采用定制的曲面1.5cm厚度的木模板,拱形梁30采用I14钢工字梁,下楞40采用5cm*10cm方木,且多个下楞40之间以间距15cm设置。同样地,弧形上模板60也采用定制的曲面1.5cm厚度的木模板,上楞70也采用5cm*10cm方木,且多个上楞70之间也以间距15cm设置。钢筋71采用双拼φ32钢筋将上楞70捆紧,钢筋71沿隧道横向设置且以间距为75cm设置。In some embodiments, the arc-shaped lower template 50 uses a customized curved surface 1.5 cm thick wooden template, the arched beam 30 uses an I14 steel I-beam, the lower rib 40 uses a 5 cm*10 cm square wood, and multiple lower ribs 40 are arranged at a spacing of 15 cm. Similarly, the arc-shaped upper template 60 also uses a customized curved surface 1.5 cm thick wooden template, the upper rib 70 also uses a 5 cm*10 cm square wood, and multiple upper ribs 70 are also arranged at a spacing of 15 cm. The steel bars 71 use double φ32 steel bars to tie the upper ribs 70 tightly, and the steel bars 71 are arranged transversely along the tunnel and at a spacing of 75 cm.
在一些实施例中,拱形隧道结构100还包括两个侧墙240及多个三角架托90,两个侧墙240沿隧道纵向延伸,拱形梁30位于两个侧墙240之间的上方,每个侧墙240的相向侧设有多个三角架托90,三角架托90用于辅助支撑多个支撑杆10,以提升支撑杆10的强度及稳定性。In some embodiments, the arched tunnel structure 100 further includes two side walls 240 and a plurality of tripod supports 90 . The two side walls 240 extend longitudinally along the tunnel. The arched beam 30 is located above the two side walls 240 . A plurality of tripod supports 90 are provided on the facing sides of each side wall 240 . The tripod supports 90 are used to assist in supporting a plurality of support rods 10 to enhance the strength and stability of the support rods 10 .
请参阅图8及图9,在一些实施例中,多个拱形梁30上的每个下楞40始终沿隧道纵向延伸,即每个下楞40跨过所有的拱形梁30,以便于施工设计。在另一些实施例中,每个下楞40并非始终沿隧道纵向延伸,部分的拱形梁30的相对两侧的下楞40交错设置,以便由于下楞40长度不足而无法继续延伸时,另一侧的下楞40能有足够的面积接触拱形梁30,避免两侧的下楞40的端部拥挤在拱形梁30的同一处,从而提升稳定性。Please refer to FIG8 and FIG9 . In some embodiments, each lower rib 40 on a plurality of arched beams 30 always extends in the longitudinal direction of the tunnel, that is, each lower rib 40 spans over all arched beams 30 to facilitate construction design. In other embodiments, each lower rib 40 does not always extend in the longitudinal direction of the tunnel, and the lower ribs 40 on opposite sides of some arched beams 30 are staggered so that when the lower rib 40 is insufficient in length and cannot continue to extend, the lower rib 40 on the other side can have enough area to contact the arched beam 30, so as to avoid the ends of the lower ribs 40 on both sides from crowding at the same place of the arched beam 30, thereby improving stability.
请参阅图1至图6,在一些实施例中,拱形隧道施工方法200包括:Referring to FIGS. 1 to 6 , in some embodiments, an arch tunnel construction method 200 includes:
S1:在隧道基坑内浇筑混凝土垫层,在混凝土垫层上铺设防水卷材,在防水卷材上浇筑防水层,以形成作业平面210,如图2所示;S1: pouring a concrete cushion in the tunnel foundation pit, laying a waterproof membrane on the concrete cushion, and pouring a waterproof layer on the waterproof membrane to form a working plane 210, as shown in FIG2 ;
S2:在作业平面210上浇筑底板220及底板220两侧的矮边墙230,如图3所示;S2: Casting the bottom plate 220 and the short side walls 230 on both sides of the bottom plate 220 on the working plane 210, as shown in FIG. 3;
S3:在两个矮边墙230顶部分别浇筑侧墙240,如图4所示;S3: Casting side walls 240 on top of the two short side walls 230, as shown in FIG4 ;
S4:搭建多个支撑杆10,如图5所示;S4: Building a plurality of support rods 10, as shown in FIG5 ;
S5:在多个支撑杆10的端部安装顶托20,如图5所示;S5: Installing jacking supports 20 at the ends of the plurality of support rods 10, as shown in FIG5;
S6:将多个拱形梁30支撑在多个顶托20上,如图5及图7所示;S6: Supporting a plurality of arched beams 30 on a plurality of top supports 20, as shown in FIGS. 5 and 7;
S7:拼接多个弧形下模板50形成下浇筑面,拼接时多个弧形下模板50 与下楞40固定,使下楞40与弧形下模板50成为一体,同时一体的下楞40与弧形下模板50支撑在拱形梁30上,如图5及图7所示;S7: Splice multiple arc-shaped lower templates 50 to form a lower casting surface. The lower rib 40 is fixed to the lower rib 40 so that the lower rib 40 and the arc-shaped lower template 50 are integrated, and the integrated lower rib 40 and the arc-shaped lower template 50 are supported on the arched beam 30, as shown in FIG. 5 and FIG. 7;
S8:在下浇筑面上方拼接多个弧形上模板60形成上浇筑面,如图5及图7所示;S8: splicing a plurality of arc-shaped upper templates 60 above the lower casting surface to form an upper casting surface, as shown in FIG. 5 and FIG. 7 ;
S9:在下浇筑面与上浇筑面之间浇筑混凝土以形成拱顶250,且拱顶的两侧分别与两个侧墙240连接,如图5所示;S9: pouring concrete between the lower casting surface and the upper casting surface to form a vault 250, and the two sides of the vault are respectively connected to the two side walls 240, as shown in FIG5;
S10:在底板220、侧墙240及拱顶250的外表面铺设保护层260,并在保护层260的外侧进行碎石回填,如图6所示。S10: laying a protective layer 260 on the outer surfaces of the bottom plate 220 , the side wall 240 and the arch 250 , and backfilling the outer side of the protective layer 260 with crushed stones, as shown in FIG6 .
在一些实施例中,混凝土垫层为5CM厚的细石混凝土垫层,防水层为5cm厚的细石防水保护层,使作业平面210将工程基础与建筑物之间无渗漏连接,是整个工程防水的第一道屏障,起到抵御外界雨水、地下水渗漏的作用。In some embodiments, the concrete cushion layer is a 5cm thick fine stone concrete cushion layer, and the waterproof layer is a 5cm thick fine stone waterproof protective layer, so that the working plane 210 connects the project foundation and the building without leakage, which is the first barrier to waterproofing the entire project and plays a role in resisting external rainwater and groundwater leakage.
在一些实施例中,作业平面210完成后绑扎底板钢筋,再安装矮边墙模板,再设置止水钢板,最后浇筑形成底板220及矮边墙230。矮边墙230高度宜设置为距离底板220的高度范围在200-300mm内,混凝土采用C35P10抗渗砼。In some embodiments, after the work plane 210 is completed, the bottom plate reinforcement is tied, and then the low side wall formwork is installed, and then the water stop steel plate is set, and finally the bottom plate 220 and the low side wall 230 are cast. The height of the low side wall 230 is preferably set to a height range of 200-300 mm from the bottom plate 220, and the concrete is C35P10 anti-seepage concrete.
在一些实施例中,待矮边墙混凝土强度达到要求后,进行凿毛处理,再绑扎侧墙钢筋,并且绑扎侧墙钢筋之前在矮边墙230两侧搭设临时作业平台270,以便施工人员搭建模板。侧墙模板通过主楞加固,主楞采用竖向50*50*3mm方钢管,间距150mm;并设置两道横向双拼48mm*3mm校直钢管;采用M14对拉螺杆,间距450*450mm进行对拉;支架采用步距600*600*900钢管架搭设,加固完成后浇筑侧墙混凝土,形成侧墙240。In some embodiments, after the concrete strength of the short side wall reaches the required level, it is roughened and then the side wall reinforcement is tied. Before tying the side wall reinforcement, a temporary work platform 270 is set up on both sides of the short side wall 230 to facilitate construction workers to build the template. The side wall template is reinforced by the main rib, which uses vertical 50*50*3mm square steel pipes with a spacing of 150mm; and two horizontal double-jointed 48mm*3mm straightening steel pipes are set up; M14 tensioning screws are used with a spacing of 450*450mm for tensioning; the bracket is set up with a steel pipe rack with a pitch of 600*600*900. After the reinforcement is completed, the side wall concrete is poured to form the side wall 240.
在一些实施例中,侧墙240浇筑完毕后,拆除侧墙模板,再搭设拱顶支撑体系,支撑杆10采用600*600*900钢管,所有立杆搭设时辅以水平剪刀撑、纵向剪刀撑和横向剪刀撑,以进一步保证架体稳定性。In some embodiments, after the side wall 240 is poured, the side wall formwork is removed and the arch support system is erected. The support rod 10 uses a 600*600*900 steel pipe, and all vertical poles are erected with horizontal scissors braces, longitudinal scissors braces and transverse scissors braces to further ensure the stability of the frame.
在一些实施例中,浇筑拱顶混凝土时,进行分层对称浇筑,每层灌筑高度不超过40cm,同时使用插入式振捣器,均匀振捣,提升浇筑质量。In some embodiments, when pouring the vault concrete, the pouring is carried out in layers and symmetrically, with the pouring height of each layer not exceeding 40 cm. At the same time, an inserted vibrator is used to vibrate evenly to improve the pouring quality.
在一些实施例中,保护层260为0.5mm厚自粘防水卷材以及砖胎膜,起到保护作用。In some embodiments, the protective layer 260 is a 0.5 mm thick self-adhesive waterproof membrane and a brick membrane, which plays a protective role.
在一些实施例中,为了对隧道进行试验,通常在实验室内浇筑实验用的隧道混凝土结构,使用本申请的搭建拱形隧道结构100及拱形隧道施工方法200成型的隧道,用于室内的试验使用,其隧道整体尺寸不及实际使用的隧道大,并且,本申请的搭建拱形隧道结构100及拱形隧道施工方法200适用于明挖法搭建的隧道结构。In some embodiments, in order to test the tunnel, a tunnel concrete structure for the experiment is usually cast in a laboratory, and a tunnel formed by using the arch tunnel structure 100 and the arch tunnel construction method 200 of the present application is used for indoor experiments. The overall size of the tunnel is not as large as the tunnel actually used. In addition, the arch tunnel structure 100 and the arch tunnel construction method 200 of the present application are suitable for tunnel structures constructed by open-cut method.
另外,本技术领域的普通技术人员应当认识到,以上的实施方式仅是用来说明本申请,而并非用作为对本申请的限定,只要在本申请的实质精神范围之内,对以上实施例所作的适当改变和变化都落在本申请的公开范围之内。 In addition, those skilled in the art should recognize that the above embodiments are only used to illustrate the present application and are not intended to be limiting of the present application. As long as they are within the spirit and scope of the present application, appropriate changes and modifications to the above embodiments are within the scope of the present application.
Claims (10)
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310954255.0 | 2023-07-31 | ||
| CN202310954255.0A CN116971798B (en) | 2023-07-31 | 2023-07-31 | Arch tunnel structure and arch tunnel construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2025026311A1 true WO2025026311A1 (en) | 2025-02-06 |
Family
ID=88471002
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/CN2024/108503 Pending WO2025026311A1 (en) | 2023-07-31 | 2024-07-30 | Arched tunnel structure and arched tunnel construction method |
Country Status (3)
| Country | Link |
|---|---|
| CN (1) | CN116971798B (en) |
| LU (1) | LU600833B1 (en) |
| WO (1) | WO2025026311A1 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116971798B (en) * | 2023-07-31 | 2024-05-10 | 中铁隧道集团二处有限公司 | Arch tunnel structure and arch tunnel construction method |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0571295A (en) * | 1991-09-13 | 1993-03-23 | Okumura Corp | Movable form device for gradually changed sectional tunnel |
| JPH07139295A (en) * | 1993-11-17 | 1995-05-30 | Ishikawajima Constr Materials Co Ltd | Method for constructing arched tunnel |
| CN108951865A (en) * | 2018-09-19 | 2018-12-07 | 北京城建集团有限责任公司 | A kind of Large-Span Continuous domes, top plate supporting system and its construction method |
| CN211038666U (en) * | 2019-12-05 | 2020-07-17 | 中铁二十局集团第六工程有限公司 | Lining pouring construction structure based on assembled scaffolding |
| CN115749250A (en) * | 2022-11-30 | 2023-03-07 | 上海二十冶建设有限公司 | Straight wall circular arch cast-in-place structure template and installation method thereof |
| CN116971798A (en) * | 2023-07-31 | 2023-10-31 | 中铁隧道集团二处有限公司 | Arch tunnel structure and arch tunnel construction method |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2686507B1 (en) * | 2011-03-15 | 2017-05-03 | Lock-Block Ltd. | A formwork for use in the construction of arched structures and a method of constructing arched structures |
| CN112627418A (en) * | 2020-12-09 | 2021-04-09 | 深圳市鹏城建筑集团有限公司 | Construction method for pouring circular arch roof and template supporting structure |
-
2023
- 2023-07-31 CN CN202310954255.0A patent/CN116971798B/en active Active
-
2024
- 2024-07-30 LU LU600833A patent/LU600833B1/en active IP Right Grant
- 2024-07-30 WO PCT/CN2024/108503 patent/WO2025026311A1/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0571295A (en) * | 1991-09-13 | 1993-03-23 | Okumura Corp | Movable form device for gradually changed sectional tunnel |
| JPH07139295A (en) * | 1993-11-17 | 1995-05-30 | Ishikawajima Constr Materials Co Ltd | Method for constructing arched tunnel |
| CN108951865A (en) * | 2018-09-19 | 2018-12-07 | 北京城建集团有限责任公司 | A kind of Large-Span Continuous domes, top plate supporting system and its construction method |
| CN211038666U (en) * | 2019-12-05 | 2020-07-17 | 中铁二十局集团第六工程有限公司 | Lining pouring construction structure based on assembled scaffolding |
| CN115749250A (en) * | 2022-11-30 | 2023-03-07 | 上海二十冶建设有限公司 | Straight wall circular arch cast-in-place structure template and installation method thereof |
| CN116971798A (en) * | 2023-07-31 | 2023-10-31 | 中铁隧道集团二处有限公司 | Arch tunnel structure and arch tunnel construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116971798A (en) | 2023-10-31 |
| CN116971798B (en) | 2024-05-10 |
| LU600833B1 (en) | 2025-07-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112796511B (en) | Supporting structure of double-layer bare concrete arc-shaped roof template and construction method | |
| CN105507476B (en) | Construction method of multi-arch roof | |
| CN111058631B (en) | Concrete construction method for large-gradient inclined roof | |
| CN103741817A (en) | Enhancement method of X-shaped reinforcing bars for improving seismic resistance of special-shaped column nodes | |
| CN114575593A (en) | Overload small clear distance beam adjustable disk buckle formwork support frame and its construction method | |
| CN116122169B (en) | Steel plate composite beams and construction methods | |
| CN217734853U (en) | Overload small clear distance beam adjustable disc buckle formwork support frame | |
| WO2025026311A1 (en) | Arched tunnel structure and arched tunnel construction method | |
| CN108678193B (en) | Post-cast strip and construction method thereof | |
| CN110259114A (en) | The construction method of the mould bases of beam slab rod structure | |
| CN106285721B (en) | A kind of railway culvert method of construction based on sliding mode system | |
| CN115387233A (en) | Construction method for large-span and large-volume bent cap of transition pier of composite beam cable-stayed bridge | |
| CN107165280B (en) | A kind of large span open-spandrel sandwich board stay in place form support system and construction method | |
| CN117432239A (en) | Construction method of new ground ring beams in old buildings | |
| CN212388856U (en) | Cast-in-place clear water concrete batter post structure of prestressing force | |
| CN214530768U (en) | A cast-in-place integrated pipe gallery formwork support structure | |
| CN215254565U (en) | Supporting Structure of Double-layer Fair-faced Concrete Curved Roof Formwork | |
| CN212250056U (en) | Support arrangement for tunnel mould side form | |
| CN105507475B (en) | Continuous alternating semi-conical roof and construction method thereof | |
| CN115726565A (en) | Construction method of conical barrel clean water structure | |
| CN104405069B (en) | A kind of curved surface hollow top board and construction method thereof | |
| CN115538778A (en) | Vertical Structural Butt Joint Method of Reverse Construction Structure | |
| CN112746628A (en) | Cast-in-place comprehensive pipe gallery formwork supporting structure and cast-in-place comprehensive pipe gallery construction method | |
| CN116791885B (en) | A method for constructing a light well | |
| CN111550039A (en) | Formwork support system and application construction method and construction structure thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 24848266 Country of ref document: EP Kind code of ref document: A1 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: LU600833 Country of ref document: LU |
|
| WWG | Wipo information: grant in national office |
Ref document number: LU600833 Country of ref document: LU |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |